Gpt (Jv) & Ors vs The Union Of India & Ors on 10 March, 2026

    0
    53
    ADVERTISEMENT

    Calcutta High Court

    Rahee – Gpt (Jv) & Ors vs The Union Of India & Ors on 10 March, 2026

                     IN THE HIGH COURT AT CALCUTTA
                                 ORIGINAL SIDE
                            COMMERCIAL DIVISION
    
    
    
    
    Present:
    
    The Hon'ble Justice Krishna Rao
    
    
    
                           C.S. (COM) No. 56 of 2024
    
                           [Old No. C.S. 97 of 2014]
    
                                        With
    
                                GA No. 13 of 2022
    
    
    
                            Rahee - GPT (JV) & Ors.
    
                                     Versus
    
                           The Union of India & Ors.
    
    
    
               Mr. Nirmalya Dasgupta
               Mr. R.L. Mitra
               Ms. Priyanka Dhar
                                                    ... For the plaintiffs.
    
    
               Mr. Pramod Kumar Drolia
               Mr. Santosh Kumar Pandey
    
    
                                               ... For the defendant nos. 2 & 3.
    Hearing Concluded On : 12.12.2025
    
    Judgment on          : 10.03.2026
                                            2
    
    
    Krishna Rao, J.:
    

    1. The plaintiffs have initially prayed for declaration that the purported

    notices dated 3rd July, 2013; 30th January, 2014 and 19th /21st

    SPONSORED

    February, 2014, are illegal, wrongful, null and void and is of no effect or

    further effect and also not binding upon the parties along with the

    declaration that the purported invocation and/or attempt to invoke the

    performance bank guarantee bearing No. 01154101IPG000277 dated

    19th August, 2010, for a sum of Rs.61,53,350/- is illegal, wrongful,

    fraudulent, null and void and is of no effect and/or further effects and

    also not binding upon the plaintiffs and the perpetual injunction

    restraining the defendants and/or their men, agents, servants, officials,

    assigns from giving any effect or further effects to the purported notices

    dated 3rd July, 2013, 30th January, 2014 and 19th/21st February, 2014

    in any manner whatsoever and/or to invoke the subject performance

    bank guarantee being No. 01154101IPG000277 dated 19th August,

    2010.

    2. Subsequently, the plaintiffs have amended the plaint on three

    occasions that is in the year 2017, 2020 and 2022 and also

    incorporated prayers in the plaint in the year 2017 which reads as

    follows:

    “c1) Declaration that the subject contract had stood
    discharged by reason of supervening impossibility
    and that the plaintiffs had accordingly stood
    absolved from any further performance of their
    reciprocal promises under the contract.

    3

    c2) Declaration that the purported communication
    issued by the defendant No.4 dated January 9,
    2020 be adjudged and/or declared as null and
    void and invalid by this Hon’ble Court.

    c3) Declaration that the purported invocation of the
    said Performance Bank Guarantee being
    No.01154101IPG000277 dated August 19, 2010 be
    declared as null and void and invalid by this
    Hon’ble Court.

    e1) Decree in the sum of Rs.4,52,36,276.89 as
    pleaded in paragraph 55 (s) hereof to be paid by
    the defendant nos. 1 – 3 jointly and/or severally to
    the plaintiffs.

    e2) In the alternative, as enquiry be conducted by
    this Hon’ble Court so as to ascertain the loss and
    damage suffered by the plaintiffs and a decree be
    passed for such sum or sums as maybe found due
    and payable to the plaintiffs upon such enquiry.

    e3) Interest.”

    3. The present dispute revolves around the designing and construction of

    foundation, substructure, approaches including allied and

    miscellaneous works for Bridge No. 182 (9 x 45.7 Meters) between River

    IB and Brajraj Nagar stations in connection with 3rd Line between

    Chapma-Jharsuguda.

    PLAINTIFF’S CASE:

    (i) The plaintiff no.1 is a Joint Venture project formed by the

    plaintiff nos. 2 and 3.

    (ii) The plaintiff nos. 2 and 3 are flagship companies and renowned

    names in the field of construction and engineering.

    4

    (iii) The plaintiff no.2 is engaged in the business of construction

    engineering and the plaintiff no. 3 is also engaged in the similar

    business to that of the plaintiff no.2

    (iv) The plaintiff nos. 2 and 3 for the purpose of participating in the

    tender process, by virtue of Memorandum of Understanding on

    or around 20th February, 2010, formed the plaintiff no.1 as a

    Joint Venture Company.

    (v) The plaintiff nos. 2 and 3 pursuant to the Memorandum of

    Understanding dated 20th February, 2010, entered into and

    executed a joint venture agreement amongst the plaintiff nos.2

    and 3, on 29th November, 2010.

    (vi) The plaintiffs pursuant to the tender notice dated 23rd February,

    2010, issued by the defendant nos.1 and 2, submitted its offer

    letter on 20th February, 2010, to undertake the project for

    designing and construction of foundation, substructure,

    approaches including allied and miscellaneous works for bridge

    No. 182 (9 x 45.7 Meters) between IB and Brajraj Nagar station

    in connection with 3rd Line between Champa-Jharsuguda.

    (vii) The defendant no.2 by its letter of acceptance dated 28th July,

    2010, had duly accepted the offer of the plaintiff no.1 and thus,

    a contract was entered between the plaintiff no. 1 and the

    defendant nos. 2 and 3.

    5

    (viii) The plaintiffs thereafter deposited the earnest money of Rs.

    7,28,300/-. The total value of the said project was a for a sum of

    Rs.12,30,67,001/-. The plaintiff no.1 furnished Bank Guarantee

    for a total sum of Rs. 61,53,350/- issued by the defendant no.4,

    namely, Allahabad Bank now merged with Indian Bank, being

    the Bank Guarantee No. 01154101IPG000277 dated 19th

    August, 2010, which was valid upto 27th December, 2012.

    Subsequently, from time to time the validity of Bank Guarantee

    was extended and the same was lastly valid upto 29th

    September, 2014.

    (ix) The plaintiffs thereafter had duly honoured the contract by

    deploying their men, agents, and representatives at the work

    site.

    (x) The plaintiffs submit that a sum of Rs.54,25,050/- is lying with

    the Railway Authorities, on account of deduction of 10% of the

    bill value deducted from the eight bills dated between 15th

    September, 2011 and 13th July, 2012, payable to the plaintiff

    no. 1, on account of security deposit.

    (xi) The plaintiffs submit that even before such approval, the

    plaintiffs had acquired materials, equipment and machineries

    for commencement of necessary work.

    (xii) The plaintiffs submit that from the very initial day of the

    contract, the plaintiffs had suffered insurgency and hooliganism
    6

    at the site, therefore, on 6th January, 2011, the plaintiff no. 2

    had duly lodged complaint with the local police authority and an

    FIR had been registered on 7th January, 2011.

    (xiii) Subsequently by a letter dated 15th January, 2011, the

    plaintiffs had informed the defendant no.3 about such insurgent

    activities carried out at the local site along with a copy of the

    FIR dated 7th January, 2011.

    (xiv) The plaintiffs were thereafter handed over with a sub-soil

    investigation report and approved D.A.B, which was duly

    conducted by the Railway Authorities, within the scope and

    ambit of the contract.

    (xv) In compliance with the said Purchase Order dated 28th July,

    2010, issued by the defendant no.3, the plaintiffs had duly

    prepared drawings and designs to execute the said project and

    had submitted the same with the defendant no.2 for their

    approval and accordingly the Railway Authorities, by its letter

    dated 31st January, 2011, approved the same.

    (xvi) The plaintiffs submit that thereafter from time to time on 23rd

    November, 2011, 20th December, 2011 and 26th December,

    2011, there had been series of letters exchanged between the

    parties, with regard to the difficulties being faced by the

    plaintiffs at the work site.

    7

    (xvii) The plaintiffs submit that under the aforementioned

    circumstances by a letter dated 26th September, 2012, the

    plaintiffs for the first time had applied before the Railway

    Authorities for an extension of time for completion of the project

    work till 31st July, 2013.

    (xviii) The plaintiffs had further lodged a police complaint and FIR

    on 29th September, 2012 with regard to the insurgency and local

    hooliganism at the work site.

    (xix) The plaintiffs while undertaking the job of construction of

    substructure of the bridge over the river IB faced with scarcity of

    cement of the brand insisted upon by the defendant no.2 and

    the plaintiffs by a letter dated 29th September, 2012, requested

    the defendant no.3 to permit the plaintiffs to procure requisite

    quantity of cement from an alternative source.

    (xx) The plaintiffs by a letter dated 1st October, 2012, provided the

    defendant no.3 with a work progress report of the project and

    requested the defendant no.2 to extend the time for completion

    of the project.

    (xxi) The plaintiffs submit that in course of execution of the work,

    the plaintiffs found that the soil report provided by the

    defendant nos. 1 to 3 was not correct as there was rocks strata

    in the soil which was not suitable for Well Sinking and drilling

    was not possible for construction of the Well, thereby requested
    8

    the Railway Authorities to re-investigate the soil in as much as

    the rocky strata by a letter dated 9th October, 2012.

    (xxii) The plaintiffs by a letter dated 27th November, 2012, duly

    appraised the defendant no.2 regarding the stoppage of work

    due to insurgent activities and accordingly lodged a complaint

    with different authorities of the railways.

    (xxiii) The plaintiffs thereafter had tried to conclude the job but were

    suffering from not only local insurgency, insufficiency of supply

    of cement, flood, hooliganism and lastly the rocky strata which

    was not at all reflected in the geotechnical report whereas the

    said land had reflected as soft coal, which is wholly contrary to

    the actual scenario.

    (xxiv) The plaintiffs submit that the defendants had further

    extended the period for completion of the work by its letter dated

    9th April, 2013 till 31st March, 2014, as per the request of the

    plaintiffs.

    (xxv) The plaintiffs thereafter were served with a “7 Days’ Notice” on

    3rd July, 2013 by the defendant no.3, purported to be in terms

    of Clause 62 of the General Conditions of Contract threatening

    the plaintiffs to terminate the contract, to which the plaintiffs

    had replied by its letter dated 11th July, 2013, stating that there

    was no scope of issuance of a 7 days’ notice.

    9

    (xxvi) The defendants thereafter again on 30th January, 2014,

    issued a 7 days’ notice on the plaintiffs and accordingly the

    plaintiffs had sent their reply on 14th February, 2014, refuting

    all the allegations.

    (xxvii) The plaintiffs submit that the defendants had further issued

    a 48 hours’ notice dated 19th/ 21st February, 2014, with the

    threat to rescind the contract.

    (xxviii) The contract was subsequently terminated by the defendants

    on 5th March, 2014 and the present suit was filed by the

    plaintiffs on 4th March, 2014.

    (xxix) The plaintiffs on or around 28th April, 2014, invoked the

    arbitration clause before the internal Arbitral Tribunal of the

    Railways for a monetary claim on account of total eight claims

    for a total sum of Rs.3,88,06,700/-. Thereafter on 21st

    December, 2015, the Arbitration which was initially initiated by

    the plaintiffs was not entertained as the claim of the plaintiffs

    was in excess of 20% of the contract value and as a result, the

    arbitral proceeding was terminated.

    (xxx) Subsequent to the termination of arbitration proceeding filed

    by the plaintiffs, the application filed by the defendants under

    Section 8, was dismissed for non-prosecution by an order dated

    28th January, 2016.

    10

    (xxxi) Thereafter, the plaintiffs have issued notice under Section

    80(2) of the Code of Civil Procedure as to the defendants on 19th

    November, 2016, which was duly replied by the Railways on 10th

    January, 2017.

    (xxxii) After termination of Arbitration proceeding, the plaintiffs had

    filed an amendment application before this Court for the

    purpose of including the claims in the present suit, being G.A.

    No. 4 of 2017 (Old G.A. No. 649 of 2017).

    (xxxiii) The amendment application filed by the plaintiffs, was

    allowed by this Court by an order dated 4th May, 2017. The

    order of amendment allowed by this Court was challenged

    before the Hon’ble Division Bench by the defendants but the

    same was dismissed by an order dated 13th June, 2017.

    (xxxiv) The plaintiffs have filed an application for interim order. By

    an order dated 10th November, 2017, this Court granted interim

    order.

    (xxxv) The Railway authorities had challenged the said interim order

    dated 10th November, 2017, and the Hon’ble Division Bench had

    allowed the same by a judgment dated 30th September, 2019.

    (xxxvi) Being aggrieved and dissatisfied by the order dated 30th

    September, 2019, a Special Leave Petition was preferred before

    the Hon’ble Apex Court which was dismissed on 13th December,
    11

    2019. However, the suit was directed to be decided expeditiously

    within a period of six months from the date of such order.

    (xxxvii) The plaintiffs had further amended the plaint on 12th

    March, 2020, and incorporated the Bank Guarantee amount.

    Being aggrieved and dissatisfied by the order dated 12th March,

    2020, an appeal was preferred by the defendants before the

    Hon’ble Division Bench of this Court which was subsequently

    dismissed on 6th January, 2021.

    DEFENDANT’S CASE:

    (i) The defendant no.1 herein is the Union of India, the defendant

    no.2 is the South East Central Railway, Bilaspur, the defendant

    no.3 is the Deputy Chief Engineer (CON) working for gain at

    South East Central Railway and the defendant no. 4 is the

    Allahabad Bank now merged with Indian Bank.

    (ii) The South East Central Railway at Bilaspur, intended to

    construct a bridge between IB and Brajrajnagar Stations for a

    third line in between Chapma-Jharsuguda and accordingly the

    Chief Administrative Officer (Con/Bilaspur), South East Central

    Railway in the State of Chhattisgarh initiated Tender Notice in

    the year 2010 for an estimated cost of Rs. 11,56,53,000/-.

    (iii) The plaintiff no.1 had participated in the said tender process

    and the tender offer of the plaintiff no.1 was accepted by the
    12

    defendant no.2 vide a Letter of Acceptance dated 28th July,

    2010.

    (iv) The defendants as per requirement of the Railway Board had

    assigned the work of Soil Investigation to Vision Labs,

    Hyderabad.

    (v) The defendants submit that the defendant no.3 had handed over

    the Sub-Soil Exploration Report dated 25th March, 2010 to the

    representative of the plaintiff no.1 on 27th August, 2010.

    (vi) The defendants submit that in terms of the Letter of Acceptance

    dated 28th July, 2010, the construction of the bridge was to be

    completed within 27 months from the date of the Letter of

    Acceptance.

    (vii) The defendants submit that the plaintiff no.1 had submitted its

    drawings and designs to execute the said work and the same

    was approved by the defendant no.2 by its letter dated 31st

    January, 2011.

    (viii) The defendants state that the plaintiff no.1 had alleged that

    after receiving the approval letter dated 31st January, 2011, it

    had commenced its works and, in the process, have incurred

    substantial expenses. It is further alleged by the plaintiff no.1 in

    the process of construction, submitted necessary bar chart to
    13

    the defendant no.3 showing the progress of the construction

    works.

    (ix) The defendants further submit that the plaintiff no.1 by its letter

    dated 1st October, 2012, that is just 27 days prior to expiry of

    the completion period of the project, had applied for extension of

    time for a further period of eight months i.e. upto 30th June,

    2013 for completion of the said bridge without raising any

    grievance about the sub-soil investigation report of the Vision

    Labs, Hyderabad.

    (x) The defendant no.3 in reply to the request of the plaintiff no.1

    duly extended the time of contract upto 31st March, 2013 but in

    spite of such extension of time for completion of the project work

    on various pretexts had failed to complete the said work.

    (xi) The defendant no.3 as per request of the plaintiffs, further

    extended the time from 28th October, 2012 to 31st August, 2013

    under Clause 17A (with PVC) and the remaining period upto 31st

    March, 2014 under Clause 17B (without PVC) of the General

    Conditions of Contract, 2001.

    (xii) The defendants submit that since there was lack of progress

    towards completion of the bridge, the defendant no.3 by a letter

    dated 3rd July, 2013, addressed to the plaintiff no.1, issued a

    seven days’ notice under Clause 62 of the General Terms and

    Conditions of Contract, 2001 for completion of the project work,
    14

    failing which the defendants will take necessary actions to

    terminate the contract.

    (xiii) The defendants state that despite service of seven days’ notice

    dated 3rd July, 2013, the plaintiff no.1 failed and neglected to

    make sufficient progress towards the completion of the project

    work.

    (xiv) The defendants submit that the plaintiff no.1 did not show any

    progress to complete the project by 31st March, 2014, and as

    such the defendant no.3 was compelled to issue a seven days’

    notice dated 30th January, 2014, under Clause 62 of General

    Conditions of Contract, 2001, and thereafter the defendant no.2

    had issue 48 hours’ notice on 19th/21st February, 2014, stating

    that on expiry of the said period of the instant contract for

    construction of bridge will stand rescinded.

    (xv) The defendant no.3 did not receive any reply to the 48 hours’

    notice dated 19th/ 21st February, 2014, and as such the

    defendant no.2 by its letter dated 5th March, 2014 in absence of

    any action from the plaintiff no.1, rescinded the contract in

    terms of Clause 62 of the General Conditions of Contract, 2001.

    (xvi) The defendants submit that the plaintiff no.1 after receiving the

    48 hours’ notice and prior to termination notice dated 5th

    March, 2014, on or around 4th March, 2014, instituted the Civil

    Suit being C.S. No. 97 of 2014 before this Court, praying for
    15

    perpetual injunction restraining the defendants from giving any

    effect to the notices dated 3rd July, 2013; 30th January, 2014

    and 19th/21st February, 2014. Further restraining the

    defendants to invoke the performance Bank Guarantee dated

    19th August, 2010, as extended from time to time.

    (xvii) The defendants submit that the plaintiffs have filed an

    arbitration proceeding but the same was terminated and

    thereafter, the plaintiffs have made several amendments in the

    plaint and also amended the prayers in the suit.

    (xviii) It is the case of the defendants that as the plaintiffs failed to

    perform the contract of construction of bridge was entrusted to

    another contractor as a request of which there was considerable

    delay in construction of the bridge. The trains’ movement both

    passengers as well as goods, trains are delayed due to non-

    construction of bridge in the time by which the Railway had

    suffered severe financial loss.

    (xix) The defendants say that after termination of the contract of the

    plaintiffs, the defendants have invited fresh tender for the same

    bridge and miscellaneous job. The total job value of the said

    tender was Rs. 22,29,22,866.93 though the contract value of the

    plaintiffs in the year 2010 was Rs. 12,30,67,001/-, thus the

    defendants have suffered financial loss of Rs. 9,98,55,865.93.
    16

    (xx) The defendants have filed written statement along with counter

    claims for an amount of Rs. 15,30,09,215.53 against the

    plaintiffs.

    4. On the basis of the pleadings of the parties by an order dated 18th

    January, 2022, this Court had framed the following issues:

    ISSUES:-

    “1. Is the suit maintainable, as framed?

    2. Whether the plaintiffs failed to perform any part of the
    contract despite the same being achievable under the
    contract conditions?

    3. Whether the designs; drawings and work
    methodology approved by the Defendant no.2 on the
    basis of the Sub-Soil Exploration Report and GAD made
    over by the defendant no.2 ultimately frustrate the
    contract and render it impossible of performance?

    4. If the answer to the previous issue be in the negative,
    whether supervening and intervening circumstances,
    including the work methodology approved by the
    Defendant no.2, render the contract unworkable and
    unfeasible in terms of the contract conditions?

    5. Whether it was the plaintiffs who were alone
    responsible for the delay in the performance of their
    reciprocal promises under the contract or whether such
    delay was attributable to reasons beyond the control of
    the plaintiffs, including force majeure conditions?

    6. Whether the issuance of the notices dated 3rd July,
    2013; 30th January, 2014; 19th/21st February 2014 and
    17

    the issuance of the notice of termination dated 5th
    March, 2014 were justified, reasonable and warranted
    in the facts and circumstances of the instant case?

    7. Whether the subject contract stood discharged in the
    facts of the case and the plaintiffs accordingly stood
    absolved from any further performance of their
    reciprocal promises under the subject contract?

    8. Whether the invocation and encashment by the
    defendant no.2 of the Bank Guarantee furnished by the
    plaintiffs, being BG No.01154101IPG000277 dated 19th
    August, 2010, for Rs. 61,53,350.00/- as extended from
    time to time, was valid, proper, justified and warranted
    in the facts and circumstances of the instant case?

    9. In the event, the answer to the previous issue be in
    the negative, to what sum or sums are the plaintiffs
    entitled, towards and as compensation for the loss and
    damage suffered by the plaintiffs as a result of the
    invocation and encashment of the aforesaid bank
    guarantee?

    10. Whether the plaintiffs have become entitled to
    compensation for the loss sustained by the plaintiffs in
    the facts and circumstances of the instant case?

    11. What sums, if any, are the plaintiffs entitled to in
    the facts and circumstances of the instant case?

    12. Whether the defendant no.2 is entitled to its
    counterclaim and if so, to what extent?

    18

    13. To what other or further reliefs are the parties
    entitled, in the facts and circumstances of the instant
    case?

    14. Whether the suit is barred by the principles of
    waiver, estoppel, and acquiescence?

    15. Whether the suit is barred by limitation?

    16. Whether the suit suffers from want of cause of
    action?

    17. Whether the plaintiffs are liable to pay costs and
    compensation to the defendants for committing breach of
    contract?”

    5. The plaintiffs in order to prove its case has examined 3 witnesses,

    namely:

    (a) P.W.-1 – Pradip Khaitan, the Managing Director
    of the plaintiff no.2.

    (b) P.W.-2 – Pradip Kumar Mukherjee, consultant
    and advisor in engineering technicalities for
    construction works.

    (c) P.W.-3 – Anil Kumar Singh, Joint General
    Manager of the plaintiff no. 2.

    6. During the evidence of the plaintiff’s witnesses, altogether “74”

    documents, were marked and exhibited as “Exhibit – A to Exhibit –

    VVV”.

    19

    Exhibit – A: Certified copy of the Resolution
    passed by the Board of Directors, dated 13th
    February, 2020.

    Exhibit – B: Certified and true copy of the
    resolution dated 6th February, 2020, passed by the
    Executive Committee of the Board of Directors of
    GPT Infraprojects Ltd.

    Exhibit – C: Copy of the Minutes of the Meeting
    dated 13th February, 2020 of Rahee-GPT (JV).

    Exhibit – D: Copy of the original agreement dated
    7th September, 2011.

    Exhibit – E: Copy of the Notice Inviting Tender No.
    CES/BSP/0910/69, issued by the office of the
    Chief Administrative Officer (Construction),
    Bilaspur.

    Exhibit – F: Copy of the offer letter dated 20th
    February, 2010.

    Exhibit – G: Copy of the letter dated 7th March,
    2022.

    Exhibit – H: Copy of the Letter of Acceptance
    dated 28th July, 2010, issued by the defendants in
    favour of the plaintiffs.

    Exhibit – I: Copy of the Tender Notice dated 23rd
    June, 2014.

    Exhibit – J: Copy of the Completion Certificate
    dated 14th July, 2015, issued by the Deputy Chief
    Engineer (Construction), South Eastern Railway,
    Jharsuguda.

    Exhibit – K: Copy of the Bank Guarantee for a
    sum of Rs.61,53,350/- dated 19th August, 2010,
    furnished by the plaintiffs.

    Exhibit – L: Copy of the extended Bank Guarantee
    being the No.0115410IPG000277, for a sum of
    Rs.61,53,350/-, dated 23rd March, 2013.

    20

    Exhibit – M: Copy of the supplementary agreement
    dated 9th April, 2013.

    Exhibit – N: Copy of a 7 days’ notice dated 3rd
    July, 2013 issued to the plaintiffs by the
    defendants.

    Exhibit – O: Copy of the letter dated 11th July,
    2013 issued by the plaintiffs to the defendants that
    there was no scope of issuance of a 7 days’ notice.

    Exhibit – P: Copy of a 7 days’ notice dated 30th
    January, 2014 issued by the defendants to the
    plaintiffs.

    Exhibit – Q: Copy of a 48 hours’ notice dated 19th
    / 21st February, 2014 issued by the defendants to
    the plaintiffs.

    Exhibit – R: Copy of the notice dated 5th March,
    2014, issued by the defendants, addressing the
    plaintiffs, for termination of the contract.

    Exhibit – S: Copy of the notice dated 6th March,
    2014, issued by the South East Central Railway,
    addressing to the plaintiffs, terminating the work
    contract.

    Exhibit – T: Copy of the letter dated 10th January,
    2017, issued by the South East Central Railway, in
    reply to the letter dated 19th November, 2016,
    issued by the plaintiffs.

    Exhibit – U: Copies of several relevant bills issued
    for the purpose of the work contract.

    Exhibit – V: Copy of a Geo Technical Report/ Sub-
    Soil Investigation Report, approved by D.A.B.,
    conducted by the Railway, which was handed over
    to the plaintiffs.

    Exhibit – W: Copy of the letter dated 30th August,
    2010, issued by Rahee-GPT (JV), addressing the
    Chief Engineer of the South East Central Railway,
    regarding the soil exploration report and GAD on
    27th August, 2010.

    21

    Exhibit – X: Copy of notice dated 19th November,
    2016, along with the original postal receipts.

    Exhibit – Y: Copy of the Memorandum of
    Understanding dated 20th February, 2010.

    Exhibit – Z, Z/1, Z/2 and Z/3: Copy of the Joint
    Venture Agreement dated 26th November, 2010
    between M/s. Rahee Infratech Ltd. and M/s. GPT
    Infraprojects Ltd.

    Exhibit – AA: Copy of the letter dated 9th
    December, 2010.

    Exhibit – BB & BB/1: Copy of the letter dated 6th
    January, 2011, issued by Rahee Infratech Ltd.
    addressing to the Inspector-in-Charge, GRP, South
    East Central Railway, Jharsuguda.

    Exhibit – CC: Copy of the FIR dated 7th January,
    2011, recording the loss of the files which had the
    original documents.

    Exhibit – DD and DD/1: Copy of the letter dated
    15th January, 2011 along with the copy of FIR
    lodged by the plaintiffs.

    Exhibit – EE and EE/1: Copy of the letter dated
    17th February, 2011.

    Exhibit – FF and FF/1: Copy of the letter dated
    23rd November, 2011.

    Exhibit – GG and GG/1: Copy of a letter dated
    20th December, 2011.

    Exhibit – HH and HH/1: Copy of a letter dated
    26th December, 2011.

    Exhibit – II and II/1: Copy of the complaint letter
    dated 29th September, 2012.

    Exhibit – JJ, JJ/1, JJ/2 and JJ/3: Copy of the
    FIR dated 29th September, 2012, Lodged by the
    plaintiffs.

    Exhibit – KK and KK/1: Copy of the letter dated
    9th October, 2012.

    22

    Exhibit – LL: Copy of the letter dated 29th
    September, 2012.

    Exhibit – MM and MM/1: Copy of the letter dated
    27th November, 2012.

    Exhibit – NN and NN/1: Copy of the letter dated
    14th February, 2014.

    Exhibit – OO and OO/1: Copy of the letter dated
    5th April, 2014.

    Exhibit – PP: Copy of the General Conditions of
    the Contract.

    Exhibit – QQ and QQ/1: Certified true copy of the
    Resolution passed at the meeting held on 12th
    October, 2022.

    Exhibit – RR and RR/1: Resolution dated 17th
    July, 2023 of Rahee Infratech Limited.

    Exhibit – SS (Collectively), SS/1, SS/2 and
    SS/3: Copies of the original Invoices raised by
    Prahlad Biswas in favour of the defendant no.2 for
    Reinforcement & Shuttering work amounting to
    Rs.96,159 and TDS Certificates.

    Exhibit – TT (Collectively) and TT/1 to TT/4:

    Copies of the Invoices raised by one Prahlad
    Biswas.

    Exhibit – UU (Collectively), UU/1, UU/2, UU/3
    and UU/4 : Copies of the original Invoices raised
    by Prahlad Biswas.

    Exhibit – VV (Collectively) and VV/1: Copies of
    the original Invoices raised by Prahlad Biswas in
    favour of the defendant no.2 for Reinforcement &
    Shuttering work amounting to Rs.96,159 and TDS
    Certificates along with signatures appearing at the
    documents.

    Exhibit – WW: Copies of several TDS Certificates.

    Exhibit – XX (Collectively) : Copies of original
    bills issued by Rahee Infratech Limited.

    23

    Exhibit – YY (Collectively) : Copies of original
    bills issued by Rahee Infratech Limited.

    Exhibit – ZZ (Collectively) : Copies of original
    bills issued by Rahee Infratech Limited.

    Exhibit – AAA (Collectively) : Copies of original
    bills issued by Rahee Infratech Limited.

    Exhibit – BBB (Collectively) : Copies of original
    bills issued by Rahee Infratech Limited.

    Exhibit – CCC (Collectively) : Copies of original
    bills issued by Rahee Infratech Limited.

    Exhibit – DDD (Collectively) : Copies of original
    bills issued by Rahee Infratech Limited.

    Exhibit – EEE (Collectively) : Copies of original
    bills issued by Rahee Infratech Limited.

    Exhibit – FFF (Collectively) : Copies of original
    bills issued by Rahee Infratech Limited.

    Exhibit – GGG (Collectively) : Copies of original
    bills issued by Rahee Infratech Limited.

    Exhibit – HHH (Collectively) : Copies of original
    bills issued by Rahee Infratech Limited.

    Exhibit – III (Collectively) : Copies of original
    bills issued by Rahee Infratech Limited.

    Exhibit – JJJ and JJJ/1 to JJJ/33
    (Collectively): Copies of Depositors Copies of
    Employees State Insurance Corporation along with
    signatures of Mr. Ravi Khaitan.

    Exhibit – KKK: Copy of the Final Bill dated 25th
    April, 2013, issued by Emak Consulting
    Engineering Pvt. Ltd. in favour of the Plaintiffs,
    amounting to Rs.1,100,00/-.

    Exhibit – LLL: Copy of an invoice dated 26th April,
    2013, issued by Jadavpur University for Mix of
    M25 Grade Concrete, amounting to Rs.11,236/-

    24

    Exhibit – MMM (Collectively): Copies of the
    original bills raised by M/s. Konark Filling Station,
    in favour of the plaintiffs.

    Exhibit – NNN (Collectively) : Copies of the
    original bills raise by M/s. Santoshi Maa Security
    Services, in favour of the plaintiffs.

    Exhibit – OOO (Collectively) : Copies of challans
    issued by the South East Central Railway, on
    account of Contract Certificate.

    X (Marked for identification): Copies of
    Statement of Accounts of M/s. Rahee Infratech
    Limited of ICICI Bank.

    X1 (Marked for identification): Copies of
    Statement of Accounts of M/s. Rahee Infratech
    Limited of Allahabad Bank.

    Exhibit – PPP (Collectively) : Copies of Paysheet
    for Staff (Brijarajnagar) of the Plaintiffs.

    Exhibit – QQQ (Collectively) : Copy of a
    Debit/Credit Certificate dated 9th January, 2020
    and a letter dated 20th January, 2020, issued by
    the Allahabad Bank regarding the Bank
    Guarantee.

    Exhibit – RRR (Collectively): Copies of TDS
    Certificate of Rahee Infratech Limited.

    Exhibit – SSS (Collectively): Copies of TDS
    Certificate of Rahee Infratech Limited.

    Exhibit – TTT (Collectively): Copies of TDS
    Certificate of Rahee Infratech Limited.

    Exhibit – UUU (Collectively): Copies of TDS
    Certificate of Rahee Infratech Limited.

    Exhibit – VVV (Collectively): Copies of TDS
    Certificate of Rahee Infratech Limited.

    7. The defendants in order to prove their case, have examined two (2)

    witnesses, namely:

    25

    (a) Mr. Arpit Khunteta, Executive Engineer,
    Construction Division, South East Central
    Railway,

    (b) Mr. Teophil Ekka, authorized by the Deputy
    Chief Engineer Construction – II, Bilaspur to
    depose on behalf of the defendants.

    8. To prove the case, the defendants have exhibited “22” documents and

    are marked as “Exhibit – 1 to Exhibit – 22”:

    Exhibit – 1: Copy of the letter 30th August, 2010,
    sent by the plaintiffs to defendant no.3.

    Exhibit – 2: Designs and detailed structured
    drawings prepared by the plaintiffs on the basis of
    the sub-soil exploration report.

    Exhibit – 3: Copy of the letter dated 31st January,
    2011, issued by the plaintiffs to the Chief Engineer
    (Construction) – I.

    X3 (Marked for identification): Copy of the letter
    dated 8th February, 2011, issued by the Deputy
    Chief Engineer Construction, Raigarh, the
    defendant no.3 herein.

    X4 (Marked for identification): Copy of a letter
    dated 16th June, 2011, issued by the defendant
    no.3, addressing the plaintiffs.

    X5 (Marked for identification): Copy of the letter
    dated 24th August, 2011, issued by the defendant
    no.3, addressing the plaintiffs, conveying the lack
    of laboratory near worksite.

    X6 (Marked for identification): Copy of the letter
    dated 30th August, 2011, addressed to plaintiffs
    issued by the defendant no.2, Chief Engineer.

    26

    X7 (Marked for identification): Copy of the letter
    dated 11th October, 2011, issued by the defendant
    no.3 to the plaintiff no.1.

    X8 (Marked for identification): Copy of the letter
    dated 21st October, 2011, which is a continuation
    of the letter dated 11th October, 2011, issued by the
    defendant no.3 to the plaintiffs.

    X9 (Marked for identification): Copy of the letter
    dated 30th November, 2011, issued by the
    defendant no.3 to the plaintiff no.1, highlighting
    that the work programme is unsatisfactory.

    Exhibit – 4: Copy of the letter dated 20th
    December, 2011, addressed to the Deputy Chief
    Engineer from the plaintiffs in response to the
    defendant no.3’s letter dated 30th November, 2011.

    X10 (Marked for identification): Copy of the
    letter dated 10th March, 2012, issued from the
    defendant no.3 to the plaintiff no.1, highlighting
    about the slow progress in work.

    Exhibit – 5: Copy of the letter dated 4th May,
    2012, issued by the plaintiffs to the Deputy Chief
    Engineer (Construction) II.

    X11 (Marked for identification): Copy of the
    letter dated 5th May, 2012, from the Deputy Chief
    Engineer to the plaintiff no.1.

    Exhibit – 6: Copy of an application filed by the
    plaintiffs to the Deputy Chief Engineer
    (Construction) for extension of completion period for
    the extend agreement.

    Exhibit – 7 and 7/1: Copy of the letter dated 27th
    May, 2013, issued by the Deputy Chief Engineer
    (Construction) to the plaintiffs.

    Exhibit – 8: Copy of the notice dated 3rd July,
    2013, issued by the Deputy Chief Engineer
    (Construction) to the plaintiffs due to unsatisfactory
    progress in work.

    27

    Exhibit – 9: Copy of the letter dated 11th July,
    2013, issued by the plaintiffs.

    X12 (Marked for identification): Copy of the
    letter dated 19th September, 2013, issued by the
    South East Central Railway to the plaintiffs.

    Exhibit – 10 and 10/1: Copy of the letter dated
    29th October, 2013 issued by the Deputy Chief
    Engineer (Construction) to the plaintiffs.

    X13 (Marked for identification): Copy of the
    letter dated 25th November, 2013, issued by the
    South East Central Railway to the plaintiffs.

    Exhibit – 11 and 11/1: Copy of the notice dated
    30th January, 2014, issued by the Deputy Chief
    Engineer (Construction) to the plaintiffs.

    X14 (Marked for identification): Copy the
    Railway’s 48 hours’ notice dated 19th / 21st
    February, 2014, issued by the Deputy Chief
    Engineer (Construction) to the plaintiffs.

    X15 (Marked for identification): Copy of the
    termination notice dated 5th March, 2014, issued
    by the defendants to the plaintiffs.

    Exhibit – 12: Copy of the Tender Notice No.
    CEC/BSP/15-16/71 dated 16th September, 2015.

    Exhibit- 13 : Copy of the letter of authorization,
    issued by the Deputy Chief Engineer (Construction)

    – II, Bilaspur, authorizing Mr. Teophil Ekka.

    Exhibit – 14: Copy of the letter dated 16th June,
    2011, issued by the Deputy Chief Engineer
    Construction – II, Bilaspur, to the plaintiffs.

    Exhibit – 15 (with objection) : Copy of the letter
    dated 24th August, 2011, issued by the Deputy
    Chief Engineer Construction- II, Bilaspur to the
    plaintiffs.

    Exhibit – 16 (with objection): Copy of the letter
    dated 30th August, 2011, signed and issued by the
    28

    Deputy Chief Engineer Construction-I, Bilaspur, Mr.
    A.K. Singh, to the plaintiffs.

    Exhibit – 17: Copy of the letter dated 11th October,
    2011, signed and issued by the Deputy Chief
    Engineer (Construction) – II, Raigarh, Shri M.B.
    Satyanarayan, to the plaintiffs.

    Exhibit – 18: Copy of the letter dated 21st October,
    2011, signed and issued by the Deputy Chief
    Engineer (Construction) – II, Raigarh, Shri M.B.
    Satyanarayan, to the plaintiffs.

    Exhibit – 19: Copy of the letter dated 30th
    November, 2011, signed and issued by the Deputy
    Chief Engineer Construction) – II, Raigarh, Shri M.B.
    Satyanarayan, to the plaintiffs.

    Exhibit – 20: Copy of the letter dated 5th May,
    2012, signed and issued by the Deputy Chief
    Engineer Construction) – II, Raigarh, Shri M.B.
    Satyanarayan, to the plaintiffs.

    Exhibit – 21: Copy of the letter dated 19th
    September, 2013, signed and issued by the Deputy
    Chief Engineer Construction) – II, Raigarh, Shri
    Ashok Kumar Suryavanshi, to the plaintiffs.

    Exhibit – 22: Copy of the letter dated 25th
    November, 2013, signed and issued by the Deputy
    Chief Engineer (Construction) – II, Raigarh, Shri
    Ashok Kumar Suryavanshi, to the plaintiffs.

    9. DECISIONS WITH REASONS:

    Issue Nos. 1, 15 and 16 are taken up together:

    a. The defendants have raised two questions in the Issue No. 1 i.e.

    (i) No cause of action arose for filing of the suit within the
    29

    jurisdiction of this Court and (ii) The defendant Railway is not

    having any office within the jurisdiction of this Court.

    b. Mr. Pramod Kumar Drolia, Learned Advocate representing the

    defendant nos. 2 and 3, relied upon the judgement in the case of

    Rekhab Chand Jain Vs. Paras Das Bhartiya reported in AIR

    1970 Cal 394 and submits that it is settled law that for the

    purposes of invoking jurisdiction of the Court the expression

    “Case of Action” has a distinct connotation. Merely saying that

    something has happened within the jurisdiction of this Court

    would not be effective in conferring jurisdiction on the Court or

    to ask for leave under Clause 12 of the Letters Patent. It must

    first be a cause of action in the suit, secondly, such cause of

    action must arise within the jurisdiction of this Court and

    thirdly, that part cause of action on which jurisdiction is sought

    for, must affect the defendants against whom relief is asked for.

    c. Mr. Drolia relied upon the judgment in the case of Karam

    Chand Thapar and Bros. (Coal Sales) Vs. Inder Mohan

    Kapoor reported in AIR 1972 Cal 82 and submits that to

    succeed in an application for revocation of leave on the ground

    of balance of convenience, a strong case has to be made out. In

    other words, a mere balance of convenience would not be

    enough but it must be such that it would be overwhelmingly in

    favour of the suit being heard by the Court other than the

    Court granting the leave. The paramount consideration for the
    30

    Court in such a case would be to consider whether in acquiring

    jurisdiction it would cause serious prejudice resulting in

    injustice to the defendant if the suit would be permitted to be

    proceeded within the Court where it has been instituted with

    such leave.

    d. Mr. Drolia further relied upon the judgment in the case of

    Ultra Engineering Industries Pvt. Ltd. Vs. Spintex

    Industries Pvt. Ltd. reported in AIR 1980 Cal 159 and

    submits that admittedly the defendant has no office at Kolkata

    and the transaction has been entered between the parties

    outside Kolkata.

    e. Mr. Nirmalya Dasgupta, Learned Advocate representing the

    plaintiffs, has relied upon the judgment in the case of Om

    Prakash Srivastava Vs. Union of India and Another

    reported in (2006) 6 SCC 207 and submits that cause of

    action consists of a bundle of facts, which give cause to enforce

    the legal inquiry for redress in a Court of law.

    f. Mr. Dasgupta submits that in the present case the plaintiffs

    have submitted its offer from Kolkata and the after acceptance

    of the offer of the plaintiffs, the defendants have communicated

    the same to the plaintiffs. He submits that earnest money and

    performance guarantee have been submitted at Allahabad Bank

    now merged with Indian Bank at Kolkata, Park Street Branch,
    31

    all correspondences have been made between the plaintiffs and

    defendants at the registered address of the plaintiffs at Kolkata

    and the defendants have invoked the performance guarantee of

    the plaintiffs from the Allahabad Bank now Indian Bank which

    is within the Jurisdiction of this Court.

    g. Pursuant to the notice issued by the defendant nos.1 and 2,

    the plaintiff no.1 has submitted its offer from its office at

    Kolkata to undertake the project for designing and construction

    of foundation, substructure, approaches including allied and

    miscellaneous works for Bridge No.182 (9 x 45.7 mtrs.) between

    IB and Brajraj Nagar stations in connection with 3rd Line

    between Champa-Jharsuguda.

    By a letter dated 28th July, 2010, the defendant no. 3

    informed the plaintiffs that the competent authority accepted

    the offer of the plaintiffs for the abovementioned work. The

    defendant no.3 addressed the said letter to the plaintiffs at

    Kolkata address and the plaintiffs have accepted the same at

    Kolkata. The offer of acceptance is marked as Exhibit -H.

    h. The plaintiffs while submitting its offer letter to the defendants,

    the plaintiffs have also deposited earnest money of Rs.

    7,28,300/- in the form of fixed deposit Account No.

    50026690741 issued by the Allahabad Bank now merged with

    Indian Bank, Park Street Branch, Kolkata and after acceptance
    32

    of the offer of the plaintiffs, the earnest money deposit

    converted to initial security deposit.

    i. The total values of the work was Rs. 12,30,67,001/-. The

    plaintiffs were required to furnish bank guarantee for a total

    sum of Rs. 61,53,350/- by way of performance guarantee in the

    format as prescribed in the contract. The plaintiffs furnished

    bank guarantee for a sum of Rs. 61,53,350/- issued by the

    Allahabad Bank now Indian Bank, Park Street Branch which is

    within the jurisdiction of this Court being Bank Guarantee No.

    01154101IPG000277 dated 19th August, 2010. The Bank

    Guarantee furnished by the plaintiffs was extended from time

    to time till 29th September, 2014.

    j. On 3rd July, 2013 and 30th January, 2014, the defendants

    issued notices upon the plaintiffs at Kolkata address directing

    the plaintiffs to expedite the work failing which action will be

    taken to terminate the contract The said communications were

    marked as Exhibits-N and P. On 19th /21st February, 2014, the

    defendants have again issued 48 hours’ notice to the plaintiffs

    at Kolkata being Exhibit-Q informing the plaintiffs that on

    expiry of the period, the contract of the plaintiffs will be

    terminated and the security deposit and performance guarantee

    shall be encashed. In prayer “c3” of the plaint, the plaintiffs

    have prayed for declaration that the purported invocation of the

    said performance bank guarantee as null and void and invalid.
    33

    k. In the case of A.B.C. Laminart (P) Ltd. Vs. A.P. Agencies,

    Salem, reported in (1989) 2 SCC 163, the Hon’ble Supreme

    Court held that:

    “12. A cause of action means every fact,
    which if traversed, it would be necessary for the
    plaintiff to prove in order to support his right to a
    judgment of the court. In other words, it is a bundle
    of facts which taken with the law applicable to
    them gives the plaintiff a right to relief against the
    defendant. It must include some act done by the
    defendant since in the absence of such an act no
    cause of action can possibly accrue. It is not limited
    to the actual infringement of the right sued on but
    includes all the material facts on which it is
    founded. It does not comprise evidence necessary
    to prove such facts, but every fact necessary for the
    plaintiff to prove to enable him to obtain a decree.
    Everything which if not proved would give the
    defendant a right to immediate judgment must be
    part of the cause of action. But it has no relation
    whatever to the defence which may be set up by
    the defendant nor does it depend upon the
    character of the relief prayed for by the plaintiff.”

    l. This Court finds that though the office of the defendants is

    situated at Bilaspur outside the jurisdiction of this Court but

    all the correspondences were made by the defendants with the

    plaintiffs at Kolkata address and the plaintiffs have deposited

    earnest money at Allahabad Bank, Park Street Branch,

    Kolkata, now Indian Bank which subsequently converted as

    security deposit and the plaintiffs have deposited performance

    guarantee with the Allahabad Bank, Park Street Branch,

    Kolkata now Indian Bank and the defendants have accepted
    34

    the same and also invoked the said bank guarantee which the

    plaintiffs have challenged in the present suit.

    m. This Court finds that part cause of action for filing the suit

    arose within the jurisdiction of this Court, no part of the claim

    is barred by limitation and the suit filed by the plaintiffs, is in

    proper form. Thus the suit filed by the plaintiffs, is

    maintainable. Issue nos. 15 and 16 are decided in favour of the

    plaintiffs and against the defendants.

    10. Issue Nos. 2 to 14 and 17 are taken up together for consideration as

    all the issues are interconnected.

    a. Tender of the plaintiffs was accepted by the defendants on 28th

    July, 2010, which is marked as Exhibit-H. As per the

    acceptance letter, construction of bridge was to be completed

    within 27 months from the date of acceptance. After issuance of

    letter of acceptance, a contract was entered between the

    plaintiffs and the defendants, which is marked as Exhibit-D.

    b. The defendants have relied upon Clauses 5.1 and 7.1 of

    Chapter XII, Special Conditions of Contract and submit that for

    use of explosive in process of sinking of wells, it is clearly

    mentioned that no claim due to any obstruction met with

    during sinking or due to any other difficulties experience in the

    process shall be entertained. As per the case of the defendants,
    35

    on 4th May, 2012 being Exhibit-5, the plaintiffs have requested

    for permission to use explosive for the purpose of sinking the

    wells in hard strata and in response to the request of the

    plaintiffs, the defendants by a letter dated 5th May, 2012, being

    Exhibit-20 permitted the plaintiffs to use necessary controlled

    blasting for sinking of wells as per the relevant guidelines and

    IS Code.

    Clauses 5.1 and 7.1 of the Special Conditions of Contracts:

    “5.1 The curbs shall be places and cast truly
    in position. The steining shall be constructed in
    stages and the well sunk vertical within
    permissible limit (as detailed in clause 6.1) to reach
    the final founding levels as required. Suitable
    method of sinking other than pneumatic sinking
    may include open dredging with contractors
    construction plant, employment drivers, and use of
    explosive required in the process of normal sinking,
    however no claim due to any obstructions such as
    isolated boulders, log of trees, sunken boats etc.
    met with during sinking or due to any other
    difficulties experienced in this process shall be
    entertained. No claim in respect of difficulties due
    to sand blowing met with during sinking of wells,
    on account of heavy Kent ledge required. Either for
    sinking of wells or for any other reasons shall be
    entertained by the railways.

    7.1 Explosives shall generally not be used as
    an aided for well sinking. However, in cases where
    explosives are to be used prior approval of the
    Engineer shall be obtained. All prevalent laws
    concerning handling, storing and using of
    explosives shall be strictly followed. If blasting has
    been used for setting the well after it has reached
    the designed foundation level, normally 24 hours
    shall be allowed to lapses before the bottom plug is
    laid. All safety precautions shall be taken as per
    IS:4081 “safety Code for Blasting and related
    Drilling Operations”, to the extent applicable
    whoever blasting is restored to.”

    36

    c. After issuance of letter of acceptance on 27th August, 2010, the

    defendant no. 3 handed over Sub-Soil Exploration Report to the

    plaintiffs with the instruction not to carry out any its own

    independent soil investigation. The Sub-Soil Exploration Report

    did not indicate the existence of any hard rock and only

    mentioned soft coal/ stand stone in the geotechnical investigation

    report. The Schedule of Quantities and Rates forming the part of

    the contract provided for sinking of 8.0 mtr. to 10.0 mtr. dia

    circular type wells. The plaintiffs had not anticipated or

    apprehend the existence of any hard rock strata on an average of

    10 mtrs below the ground level. The plaintiffs had agreed to the

    price schedule and rates in the contract on the believe that the

    work of construction would be over soft subsoil and not over hard

    subsoil including coal and accordingly quoted the rates. During

    execution of the work, the plaintiffs find that the rock strata does

    not match with the soil report provided by the defendants. The

    wells had reached the hard rock strata after sinking the wells

    through the soil bed and to sink the wells further into the thick

    hard rock blasting of the rock was adopted as it was become

    necessary and emergent.

    d. For carrying out blasting activity with the help of explosives

    necessary licence was required and the same had to be done

    through a licenced agency having the requisite licence for carrying
    37

    out blasting activities. The Bill of Quantities did not provide for

    the rates to undertake well foundation under rocky strata.

    Different rates for undertaking well foundation under the rocky

    strata were not agreed by the defendants. There is no mention of

    any hard rock in description of Item No. 2 in Schedule-C of the

    tender document, which reads as follows:

    SCHEDULE-C (Well Sinking Works)

    Sl Item Unit Rate in Rate Qty Amount
    No. Figures in
    Words (Rs.)

    2. Sinking of 8.0m RM 96000/- Rupees 100 96,00,000/-

           to 10.0 m dia                         Ninety
           circular type                         six
           well through all                      thousa
           kinds of soils                        nd only
           including
           diverting flow of
           water, clearing
           all obstructions
           like boulder,
           timbers etc.,
           dewatering if
           required with
           contractor's
           pump and fuel,
           benching soft
           rock if any and
           dredging with
           use of divers
           where
           necessary
           (complete
           dredging plants
           with derricks or
           cranes grabs
           pumping sets
           air compressor
           consumable
           stores including
           explosives for
           controlled
           basting to
           facilitate placing
           removing
                         38
    
    
    kentleges and
    seating the
    wells and
    specialized staff
    such as divers
    and other
    labour with
    necessary
    equipment to be
    supplied and
    worked by the
    contractor at his
    own cost) in all
    types of strata
    till the cutting
    edge reaches
    the required
    level as
    approved by the
    Engineer-in-
    Charge. and
    including
    loading,
    unloading of
    kent-ledger,
    sand bags etc.
    on well,
    rectification of
    tilts and shifts,
    erection and
    removal of all
    derrick
    platform,
    painting of
    gauges on outer
    surface of well
    steining and
    disposal of the
    dredged muck
    from within the
    well as directed
    by the engineer
    or his
    representative
    with all lifts,
    descents and
    leads and
    including all
    labour and
    materials etc.
    complete.
    
    Note The depts.
    of sinking will
                                    39
    
    
              be measured
              from the level at
              which cutting
              edges placed
              initially.
    
    
    
    
    

    e. As per request of the plaintiffs, the defendants have allowed the

    plaintiffs to use necessary controlled blasting for sinking of wells

    as per the relevant guidelines and IS Code. The plaintiffs could

    not continue with the blasting for sinking of wells as the

    defendants have not provided different rates for undertaking well

    foundation under rocky strata. Immediately after the termination

    of contract, the defendants have published a tender for the

    balance work in which higher rates was offered to complete the

    work and in the said tender BoQ items was introduced for

    undertaking the well foundation under rocky strata. Item no.2 of

    Schedule-C of the tender in which the plaintiffs have participated

    and work order was issued, in the said tender document, there is

    no mentioning of any hard soil, hard rock or coal and an amount

    for per running metre was Rs. 96,000/- but for the same balance

    work, in the new tender, the defendants have fixed the rate of Rs.

    2,50,000/- per running meter for hard soil, coal and hard rock

    which is marked as Exhibit-I. This act of the defendants proves

    that instead of considering the request of the plaintiffs for

    enhancement of rate for hard soil, hard rock and coal from Rs.

    96,000/-, the defendants have forced the plaintiffs to terminate

    the tender and thereafter the defendants have published a
    40

    separate tender and have provided rate of Rs. 2,50,000/-. In the

    second tender, the defendants have further fixed the rate of other

    kind of soil except in hard soil and coal of Rs. 1,20,500/- though

    in the tender of the plaintiffs for the same work, the amount was

    fixed at Rs. 96,000/-.

    f. The design, drawing and work methodology (GAD) based on Sub-

    Soil Exploration Report was handed over to the plaintiffs which is

    marked as Exhibit-2. In the said report, a bar chart has been

    appended wherein hard rock has been clearly shown. The

    plaintiffs by a letter dated 4th May, 2012, being Exhibit-5 sought

    for permission for use of explosive for blasting in sinking of wells

    in hard strata. The plaintiffs prepared the design and drawing

    based on the Sub-Soil Exploration Report. The defendants by a

    letter dated 31st January, 2011, being Exhibt-3 provided two

    instructions to the plaintiffs for execution of the project namely:

    (i) All necessary arrangement to penetrate the wells in hard
    rock should be made prior to fabrication of well curb.

    (ii) Initially only one well should be lowered completely in the
    ground so after the success of the sinking of one well
    completely, the task of sinking of other wells will be
    easier.

    During the argument, the defendants have taken stand

    that by a letter dated 31st January, 2011, the defendants have

    provided two instructions to the plaintiffs for execution of the
    41

    project but the plaintiffs did not followed the said instructions

    due to which the defendants have suffered severe loss. The said

    stand is contrary to further correspondences made between the

    parties. After the letter dated 31st January, 2011, the

    defendants have issued several letters to the plaintiffs to

    expedite the work. In none of the correspondences, the

    defendants have restrained the plaintiffs not to proceed with

    sinking of other wells till one well is completed. In the other

    hand, the defendants requested the plaintiffs to complete the

    work.

    g. At the time of examination of the plaintiffs, witness no.2,

    namely, Pradip Kumar Mukherjee, who is having degree from

    Kharagpur IIT in the year 1978 in cell mechanics and

    foundation engineering has deposed that whenever a rocky

    strata is encountering the option to sink the well has to be

    based on the other devices other than the normal sinking

    process through a grab and which one has to take recourse to

    control blasting and even if that does not work then it has to be

    pneumatic sinking. He has further stated that narrative of soil

    report is completely different from what has been actually

    encountered during sinking. It is also stated that the narrative

    was available in the Bills of Quantities (BoQ) items. There was

    no other reference of any other specification in the contract.

    The narrative of the BoQ is to be taken as actual soil report.
    42

    The basic difference is that in the narrative BoQ item, it was

    expressly specified that the well has to be sunk through all

    kinds of soil. Generally all kinds of soil is considered as clay,

    sand or silt. When actually went on to sink the wells and

    encountered rock which was not under the category of all kinds

    of soil. Sinking through soil and sinking through rock are

    completely different and the methodology is also different.

    Exhibit-1 is the Bill of Quantities which includes the item

    for sinking of the well under Schedule-C. Item-2 of Schedule-C

    of BoQ proposed sinking is mainly through winch and gravy

    method. It is a common condition for sinking through such soil.

    The moment it is to be sunk through rock which means that the

    well cutting edge has to penetrate rock and the method of

    sinking completely changes, the sinking then becomes very slow

    process and an expensive one and it has to be accomplished

    through blasting, chiselling and removal of debris in very small

    quantities.

    As per the evidence of P.W.2 sink through all types of soil as

    mentioned in the BoQ, the sinking can be one feet to three feet

    per day and one has to penetrate rock through blasting,

    chiselling, the total sinking cannot exceed beyond four inches

    and the expenditure becomes much more, at least three fold of

    the given rate.

    43

    Exhibit-1 is the First Tender document and Exhibit-D is the

    Second Tender document. The First Tender document had only

    one item under item no.2 in Schedule -C for sinking of the wells.

    In the Second Tender document, another item under item no.

    2(a) was added with a separate rate stating that the well is to

    sink through hard rock having greater value. This itself proved

    that the rock did exist under the riverbed and the rock does not

    fall under the category of all kinds of soil. The defendants have

    proposed additional rate for the portion which has to be

    penetrate rock.

    During the cross-examination of P.W.2, the learned counsel

    for the defendants had put the specific question that “Did you

    find any fault in the report?” and the P.W.2 has given a specific

    answer to the said question that “Fault as such is that the

    narrative of the soil mentioned there does not really match with

    the existing soil”.

    Another question was put to P.W.2 “that according to you,

    the report is not perfect?” and the answer was “I agree”.

    From the trend of the cross-examination by the defendants

    to the P.W.2, it is admitted by the defendants that the report is

    faulty and is not perfect.

    Section 56 of the Indian Contract Act, 1872, reads as follows:
    44

    “56. Agreement to do impossible
    act.–An agreement to do an act impossible in
    itself is void.

    Contract to do an act afterwards
    becoming impossible or unlawful.–A
    contract to do an act which, after the contract
    is made, becomes impossible, or, by reason of
    some event which the promisor could not
    prevent, unlawful, becomes void when the act
    becomes impossible or unlawful.

    Compensation for loss through non-

    performance of act known to be
    impossible or unlawful.– Where one person
    has promised to do something which he knew,
    or, with reasonable diligence, might have
    known, and which the promisee did not know,
    to be impossible or unlawful, such promisor
    must make compensation to such promisee for
    any loss which such promisee sustains
    through the nonperformance of the promise.”

    In the present case, the defendants in the first tender

    document had only one item under item no.2 in Schedule -C for

    sinking of the wells. In the second tender another item under

    item no. 2(a) was added with a separate rate stating that the well

    is to sink through hard rock having greater value. This itself

    proved that the rock did exist under the riverbed and the rock

    does not fall under the category of all kinds of soil. The

    defendants have proposed additional rate for the portion which

    has to be penetrate rock. The defendants have not denied with

    regard to availability of rock while sinking the well. The

    defendants have also allowed the plaintiffs for use of blasting. It

    is also admitted that the procedure for sinking by blasting is

    costlier than the normal sinking. There is no provision in the
    45

    tender document for Bill of Quantities. The defendants were not

    ready to enhance the rate other than the rate quoted by the

    plaintiffs in spite of having knowledge and admission about the

    presence of hard rock. In the second tender for the balance

    work, the defendants have proposed addition rate which has to

    be penetrate rock. Thus it was not possible for the plaintiffs to

    complete the awarded work.

    h. The defendants have issued notices dated 3rd July, 2013

    (Exhibit-8), 30th January, 2014 (Exhibit-P), 19th/21st February,

    2014 (Exhibit-Q) and 5th March, 2014 (Exhibit -R) wherein the

    defendants have issued 7 days and 48 hours’ notices to the

    plaintiffs and lastly terminated the contract of the plaintiffs.

    On 27th August, 2010, the defendants have handed over sub-

    soil exploration report to the plaintiffs. The work methodology

    detailed in the tender document was well foundation and the

    sub-soil exploration report also confirmed the same

    methodology. The plaintiffs initiated the work in terms of the

    said methodology. The plaintiffs could not complete the project

    on the basis of the methodology provided by the defendants.

    While executing the work beyond certain depth, the plaintiffs

    encountered hard rock which was impossible to penetrate given

    the diameter of the well and the requirement of the depth as

    per the instructions of the defendants. The report did not

    envisage and provide for the work methodology to penetrate
    46

    into hard rock. Schedule-C, item no.2, suggests soft coal and

    not hard rock. The plaintiffs have brought to the notice of the

    defendants that it is not possible for the plaintiffs to penetrate

    the rocky strata adopting foundation methodology and to allow

    plugging of well at a lower depth. The defendants instructed the

    plaintiffs to undertake the well foundation in one of the piers

    but it was not possible for the plaintiff to undertake plie

    foundation at the same location. It became impossible for the

    plaintiffs to continue with the work as BoQ did not provide for

    the rates to undertake well foundation under rocky strata. The

    request of the plaintiffs to the defendants for providing different

    rates for undertaking well foundation under the rocky strata

    was not agreed by the defendants.

    i. By a letter dated 6th January, 2011, the plaintiffs have made a

    written report to the Inspector-In-charge, Government Railway

    Police, SECR Railway, Brajrajnagar, Jharssuguda informing

    that on 4th January, 2011 at 11 pm. in the night around 12 to

    14 persons wearing monkey cap riding motorcycle came to the

    construction site and have misbehaved with the watchman of

    the plaintiffs and demanding phone number of the in-charge of

    the said work and on denial they open the padlock of the

    godown and other rooms and burnt the materials of the site.

    The said complaint is marked as Exhibit-BB. On the basis of

    the said complaint, the police registered an FIR on 7th January,
    47

    2011 and the same is marked as Exhibit-CC. The said incident

    was also informed by the plaintiffs to the defendants by a letter

    dated 15th January, 2011 which is marked as Exhibit-DD.

    j. On 17th February, 2011, the plaintiffs have sent a letter to the

    defendants informing the defendants that the plaintiffs are

    facing severe law and order problem even though the plaintiffs

    have taken steps for procurement of required steel for

    fabrication of cutting edge and well curb for one well,

    accordingly a part of its has already reached to fabrication

    workshop near bridge side. It was also informed to the

    defendants that the plaintiffs have set up a testing laboratory in

    their fabrication workshop across the River IB, near NH on

    Janshugura site and they intend to use the same for requires

    field lab test. The said letter is marked as Exhibit-EE.

    k. The plaintiff by a letter dated 23rd November, 2011, informed the

    defendants that there is shortage of Ultratech cement in the

    market but the concrete design mix had been finalized using

    the said cement and requested the defendants to allow the

    plaintiffs to use Konark Cement to avoid delay in execution of

    work. The said letter is marked as Exhibit-FF. On 20th

    December, 2011 and 26th December, 2011, the plaintiffs have

    informed the defendants about the work condition and

    impediments in execution of the work. The said documents are

    marked as Exhibit-GG and HH.

    48

    l. On 26th September, 2012, the plaintiffs have submitted a written

    complaint to the Inspector-in-charge, Brajranagar Police

    Station, Jharsuguda about the forceful entry of antisocial

    elements in the work site and camp and caused damaged to the

    property at the work site. On the basis of the said complaint,

    the police registered a FIR on 29th September, 2012 and the

    same are marked as Exhibit-II and JJ. By a letter dated 9th

    October, 2012, the plaintiffs submitted a request to the

    defendants informing the difficulties faced by the plaintiffs in

    bringing down the well foundation and requeted to Re-Soil

    Investigation. In the said letter, it was informed by the plaintiffs

    that while sinking the well found rocky strata instead of soil

    which was provided in the soil investigation report. In the said

    letter, it was also informed that after a lapse of two years, the

    plaintiffs are facing consistent obstacles in executing the well

    foundation and the plaintiffs were of the opinion to undertake

    an independent soil investigation and requested the defendants

    to allow the plaintiffs to carry out investigation. The soil

    condition faced by the plaintiffs during well foundation

    indicated rocky strata and the tender terms and conditions and

    BoQ did not provide any scope of payment for undertaking the

    work under rocky strata and accordingly the plaintiffs

    requested for separate rate or alternate foundation method to

    complete the work. The said request is marked as Exhibit-KK.
    49

    m. On 1st October, 2012, the plaintiffs have made a detailed

    request to the defendants for extension of time to complete the

    work wherein it is also mentioned that the work was hampered

    due to heavy rain and increase of water level in the river. The

    said letter is marked as Exhibit -6.

    n. On 20th November, 2012 to 22nd November, 2012, the violent

    mob threatened the site worker of the plaintiffs and forced to

    stop the work and the said incident was duly informed to the

    defendants by a letter dated 27th November, 2012 and the same

    is marked as Exhibit-MM. By a letter dated 14th February,

    2014, the plaintiffs informed the defendants that the plaintiffs

    have not able to complete the work due to law and order

    problem at the work site. The plaintiffs submitted detailed

    design with note that in case hard rock is encountered then the

    well should be allowed to be plugged at higher level while

    ensuring adequate socket depth in the rock. The same was not

    deleted by the Railways while approving the design and

    railways stipulated a minimum grip length of 6 meters below

    the rock. It was also informed that even after several

    representations and consistent work undertaken by the

    plaintiffs, spending huge amount of money and efforts, the

    plaintiffs could not achieve the penetration in rock of the wells.

    Without considering the request of the plaintiffs, the defendant

    by a letter dated 19th/ 21st February, 2014, issued 48 hours’
    50

    notice to rescind the contract and further action against the

    plaintiffs.

    o. The defendants have issued several notices to the plaintiffs

    directing the plaintiff to expedite the work. On 5th March, 2014,

    the defendants have issued notice to the plaintiffs intimating

    that since period of 48 hours has expired, the contract stand

    rescinded in terms of Clause 62 of the General Conditions of

    Contract and the balance work under the contract will be

    carried out independently, without the participation of the

    plaintiffs. The defendants have debarred the plaintiffs and its

    partner for participation in the tender for executing the balance

    work. It was also informed to the plaintiffs that the security

    deposit shall be forfeited and performance guarantee shall be

    encashed.

    p. The work methodology detailed in the tender document was well

    foundation and the soil exploration report also confirmed the

    same methodology. The plaintiffs initiated the work in terms of

    the said methodology. The plaintiffs could not complete the

    project on the basis of the methodology provided by the

    defendants. While executing the work beyond certain depth, the

    plaintiffs encountered hard rock which was impossible to

    penetrate given the diameter of the well and the requirement of

    the depth as per the instructions of the defendants. The report

    did not envisage and provide for the work methodology to
    51

    penetrate into hard rock. Schedule-C item no. 2 suggests soft

    coal and not hard rock. The plaintiffs have brought to the notice

    of the defendants that it is not possible for the plaintiffs to

    penetrate the rocky strata adopting foundation methodology and

    to allow plugging of well at a lower depth. The defendants

    instructed the plaintiffs to undertake the well foundation in one

    of the piers but it was not possible for the plaintiffs to undertake

    pile foundation at the same location. It became impossible for

    the plaintiffs to continue with the work as BoQ did not provide

    for the rates to undertake well foundation under rocky strata.

    The request of the plaintiffs to the defendants for providing

    different rates for undertaking well foundation under the rocky

    strata was not agreed by the defendants.

    q. It is established from the evidence of the plaintiffs which has not

    been challenged by the defendants during cross examination of

    the plaintiffs witness that whenever a rocky strata is

    encountering the option to sink the well has to be based on the

    other devices other than the normal sinking process through

    grab and which one has to take recourse to control blasting and

    even if that does not work then it has to be pneumatic sinking.

    He has further stated that narrative of soil report is completely

    different from what has been actually encountered during

    sinking. It is also stated that the narrative was available in the

    Bills of Quantities (BoQ) items. There was no other reference
    52

    specification in the contract. The narrative of the BoQ is to be

    taken as actual soil report.

    The basic difference is that in the narrative BoQ item, it was

    expressly specified that the well has to be sunk through all kind

    of soil. Generally all kinds of soil are considered as clay, sand or

    silt. When actually went on to sink the wells and encountered

    rock which was not under the category of all kind of soil. Sinking

    through the soil and sinking through rock are completely

    different and the methodology is also different.

    As per the evidence on record, sink through all types of soil

    as mentioned in the BoQ, the sinking can be one feet to three

    feet per day and one has to penetrate rock through blasting,

    chiselling, the total sinking cannot exceed beyond four inches

    and the expenditure becomes much more, at least three fold of

    the given rate.

    During cross-examination of the plaintiffs’ witness a specific

    question was put to the P.W.1 by the defendants:

    “Can you specify that which part of the agreement of the

    railway did not abide by the terms and conditions as specified in

    the agreement?

    “253. Can you specify that which part of
    the agreement the railway did not abide by the
    terms and conditions as specified in the
    agreement?

    53

    Ans. To start with the railways failed to
    inform us about the hostile law and order
    situation which prevailed at the bridge side
    which was a territory under the jurisdiction of
    the railways. Further the tender document and
    the agreement obliged us to make soil
    investigation before we submit our design for the
    foundations and other structures. The agreement
    document also specified the foundation to be
    undertaken by well foundation methodology.
    Subsequent to our signing of the agreement and
    before we could mobilize independent agency,
    the railways handed over soil investigation
    report from their chosen agency and instructed
    us to follow the same and prepare our design
    based on the said soil investigation report. The
    railways who had framed the tender document
    and had specified the execution methodology for
    the foundations were aware that the well
    foundation may not be the correct method of
    making the foundation. Immediately after
    signing of the agreement the railways handed
    over soil investigation report done by their own
    agency and denied us the opportunity to prepare
    the design or to bring forward to the railways the
    incorrect and erroneous choice of stipulating well
    foundations. The railways being fully aware that
    the strata at the river bed is rocky had denied us
    the opportunity to make our own investigation
    and in a fraudulent manner also deleted the
    BOQ item under which we were to carry out our
    independent soil investigation and ascertain the
    strata of the river bed. During the execution
    stage at various occasions we had brought to the
    attention of the railways that we are unable to
    progress due to the rocky strata as the well is
    not sinking but the railways completely
    overlooked our submissions. After repeated
    difficulty and observing the impossibility the
    railways themselves suggested that we
    undertake one foundation so that the progress
    can be reviewed. However, just to push us
    further into impossible work situation the
    railway instructed us to carry out other well
    foundation also. After almost working for 3 years
    the impossibility of the work became known to
    both the parties. All our request and submissions
    to railway authorities to find a solution were
    ignored. Finally, the railways terminated the
    54

    contract and called for another tender in which
    the method of work was changed from well
    foundation to pile foundation. The value of the
    new tender was almost double to the value of
    our contract agreement. The change of work
    methodology proves that the railway were well
    aware that the methodology as provided in our
    contract was not correct and in a fraudulent
    manner knowing well of the technical
    impossibilities the railways forced us to pursue
    on a faulty methodology causing financial loss to
    us.”

    Exhibit-1 is the First Tender document and Exhibit-D is

    the Second Tender document. The first tender document had

    only one item under item no.2 in Schedule-C for sinking of the

    wells. In the second tender another item under item no. 2(a) was

    added with a separate rate stating that the well is to sink

    through hard rock having greater value. This itself proved that

    the rock did exist under the riverbed and the rock does not fall

    under the category of all kinds of soil. The defendants have

    proposed additional rate for the portion which has to be

    penetrate rock but the defendants failed to provide extra rate to

    the plaintiffs even having the knowledge that sinking through

    the soil and sinking through rock are completely different and

    the methodology is also different. Thus there is no doubt that

    the termination of contract is illegal.

    r. After termination of contract of the plaintiffs, the defendants by

    invoking Clause 1.57 of Chapter VI of the Special Conditions of

    Contract had encashed the performance guarantee of Rs.
    55

    61,53,350/-. Clause 1.57 provides that “Whenever the contract is

    rescinded the Security Deposit shall be forfeited and the

    performance guarantee shall be enchased and balance work shall

    do independently without risk and cost of failed contractor”.

    Initially when the plaintiffs have filed the suit, the plaintiffs have

    also filed an application for grant of interim order with respect to

    the encashment of security deposit and performance guarantee.

    This Court has passed an interim order directing the defendants

    to maintain status quo with regard to the transfer of funds and

    the same was extended from time to time and by an order dated

    10th November, 2017, this Court passed an order restraining the

    defendants to encash the bank guarantee and shall continue

    subject to renewal of the performance guarantee by the plaintiffs

    till disposal of the suit. The plaintiff was directed to keep the

    bank guarantee renewed from time to time at least 15 days prior

    to the date of expiry failing which the defendants shall have the

    liberty to invoke the same.

    The said order was challenged by the defendants in an

    appeal and the appellate Court by an order dated 30th

    September, 2019, set aside the interim order dated 10th

    November, 2017. Subsequent to the order of the Hon’ble

    Appellate Court, the plaintiffs have filed an application in the

    present suit for amendment of the plaint for bringing certain

    subsequent events on record. This Court by an order dated 12th
    56

    March, 2020, allowed the amendment as sought for by the

    plaintiffs by passing the following order:

    “This Court is of the view that the
    amendments sought for are necessary since the
    orders culminating in the order of the Supreme
    Court on 13th December, 2019 were passed in the
    interlocutory proceedings where the plaintiffs had
    sought for an injunction on the invocation of the
    bank guarantee. Since the bank guarantee has
    been finally invoked in January, 2020, this is a
    case where this subsequent event has a real nexus
    to the original cause of action as pleaded in the un-
    amended plaint. If the plaintiff is forced to go to
    trial on the basis of the un-amended plaint, the suit
    will be decided on an incomplete cause of action
    and one where the Court will not have an
    opportunity to try and determine the real questions
    in controversy, including whether the invocation
    and encashment of the bank guarantee was illegal
    and should be declared as such.

    This is a fit case where the amendments
    sought for should be allowed.”

    The defendants have challenged the said order in an appeal

    but the appellate Court by an order dated 6th January, 2021,

    dismissed the appeal filed by the defendants.

    s. The defendants have forfeited security deposit and revoked the

    performance guarantee of the plaintiffs on the pretext that the

    plaintiffs have not executed the work inspite of several notices

    served upon the plaintiffs. The specific case of the plaintiffs that

    the plaintiffs tried to conclude the contract work in accordance

    with the General Conditions of Contract but due to local

    insurgency, insufficiency of supply of cement, flood, hooliganism

    and rocky strata which was not reflected in the geotechnical
    57

    report and the said land had reflected soft coal which was wholly

    contrary to the actual site position. The plaintiffs have made

    written complaint to the Inspector-in-charge GRP, South East

    Central Railway and the said document is marked Exhibit-BB

    and on the basis of the complaint made by the plaintiffs, an FIR

    is also registered which is marked as Exhibit-CC. There are

    several correspondences made by the plaintiffs with the

    defendants with respect to the work informing about the

    difficulties faced by the plaintiffs during the execution of the

    work and the said correspondences including the FIR are

    marked as Exhibits-DD to MM.

    u. The plaintiffs have examined witness no.3, Shri Anil Kumar

    Singh who was working as Joint General Manager (Contract)

    with the plaintiffs. In his evidence, he has stated that the

    plaintiffs used to raise bills month by month against the

    executed work. During his evidence, the plaintiffs have exhibited

    documents being Exhibits-SS to VVV, the said documents were

    marked as exhibits without any objection. From the Exhibits- SS

    to VVV, it is proved that the plaintiffs have submitted bills along

    with all documents. It was also the evidence that till the

    termination of contract, the plaintiffs have submitted their bills

    whichever the works executed by the plaintiffs. The defendants

    during their cross-examination with respect to the said

    documents, it is suggested that the said documents are inflated
    58

    and not genuine. It is not the case of the defendants that

    without executing work bill is submitted. The defendants even

    receipt of the said bill neither returned the same to the plaintiffs

    nor have made any communication that the said bill is not

    connected with the work executed by the plaintiffs. From the

    trend of cross-examination, this Court finds that the defence of

    the defendants was that the plaintiffs have not completed the

    project, thus the plaintiffs are not entitled to get payment.

    v. The defendants have also set up counterclaim along with written

    statement for recovery of an amount of Rs. 15,30,09,215.93. Out

    of the said amount, the defendants have claimed an amount of

    Rs. 9,98,55,865.93 as the defendants have made more

    expenditure due to increased 2nd contract value. An amount of

    Rs. 20,00,000/- is claimed being proportionate share of Railway

    personnel expenditure for organizing and other works for 2nd

    tender. An amount of Rs. 3,50,00,000/- is claimed being the

    loss of revenue due to slow train movement both goods and

    passenger. Further an amount of Rs. 1,00,00,000/- is claimed

    due to loss of image.

    w. The defendants have examined two witnesses none of the said

    two witnesses were connected with the said work. The

    defendants have neither exhibited the 2nd contract in which the

    defendants have made expenditure of Rs. 9,98,55,865.93. The

    defendants have not exhibited any documents to show that for
    59

    the same work the defendants have invested the above amount.

    After termination of contract of the plaintiffs, the defendants

    have published another tender for completion of remaining work

    but even after publication of the fresh tender for completion of

    the remaining work, none of the contractors have come forward

    to participate in the said tender.

    y. As regard to the proportionate share of the Railway personnel

    expenditure including the expenditure for organizing and other

    works for 2nd tender, the plaintiffs have not examined any

    witness or produced any evidence to show that for the purpose

    of 2nd render how the defendants have made expenditure of Rs.

    20,00,000/-. With regard to loss of revenue as the movement of

    goods and passenger trains were slow for which the Railway

    sustained revenue loss of Rs. 3,50,00.000/-, the defendants

    have not bring any document which good trains and which

    passenger trains were moved slow. No documents of any official

    of railway authorities come forward to say that due to non-

    completion of work trains were moved slow and the railways

    have sustained financial loss.

    z. The defendants have claimed Rs. 1,00,00,000/- being the loss of

    image but no one has come forward that due to non-completion

    of work, the image of the railway has lowered down due to which

    the defendants have sustained loss of image. D.W.1, Mr. Arpit

    Khunteta who is the Executive Engineer, Construction Division,
    60

    South East Central Railway. He has deposed in the instant case

    as authorised representative of the defendants. As per his

    evidence, he has completed his graduation in the year 2015 and

    joined Railways on 30th July, 2018. Admittedly, when the tender

    was awarded and the tender was terminated, he was not in

    service of Railway, has admitted that he has no personal

    knowledge of the work but after consulting his Headquarter and

    file, he has come to this Court for giving evidence being the

    representative of the defendants. He further admitted that he

    was posted at Jharsugada in the month of October 2023 i.e.

    much after the termination of contract of the plaintiffs. He has

    also admitted that no bidder has come forward for the balance

    work. In his cross-examination, he has also admitted that the

    Railway has published another tender with respect to all works

    and all official expenditures in relation to the new tender were

    incurred. He also admitted that in Exhibit-KK in the last

    paragraph, it is mentioned that re-soil investigation for the

    extend contract will be redone.

    aa. Maximum documents of the defendants have not proved as the

    same were marked as Exhibits X3 to X15. Neither the author of

    the documents nor any of the officials who were conversant with

    the said documents were examined. Neither the Chief Engineer

    nor the Deputy Chief Engineers who were posted or connected

    with the said work were examined as witness in the case. A
    61

    specific question was put to the witness by this Court whether

    the two officials, namely, Ashok Kumar Suryavanshi and Mr.

    M.B. Satyanarayan are still in service and in answer, the D.W.2

    stated that still they are in service. Both the said two officials are

    the Deputy Chief Engineers but failed to come to adduce

    evidence in the present case.

    bb. Written statement along with counter claim is filed and verified

    by Mahesh Kumar Agarwal, Deputy Chief Engineer

    (Construction), the defendant no. 3. The D.W.1 has deposed as

    representative of the defendants, that is the Railway Authorities.

    Admittedly, the D.W.1 was not in service of the railway authority

    when the cause of action for filing of the suit arose. He has no

    personal knowledge of the case. Only on the consultation with

    the Headquarter and file, the D.W.1 has deposed in the said

    case. D.W.2 also not the witness of the work he has only

    identified some of the signatures of the officials but the fact

    remains that the officials are in service but shy to appear before

    this Court to prove the case of the Railway. In the case of

    Manisha Mahendra Gala and Ors. Vs. Shalini Bhagwan

    Avatramani and Ors. reported in (2024) 6 SCC 130 wherein

    the Hon’ble Supreme Court held that:

    “28. The law as understood earlier was that a
    general power-of-attorney holder though can
    appear, plead and act on behalf of a party he
    represents but he cannot become a witness on
    behalf of the party represented by him as no one
    can delegate his power to appear in the witness
    62

    box to another party. However, subsequently
    in Janki Vashdeo Bhojwani v. Indusind Bank Ltd.,
    this Court held that the power-of-attorney holder
    can maintain a plaint on behalf of the person he
    represents provided he has personal knowledge of
    the transaction in question. It was opined that the
    power-of-attorney holder or the legal representative
    should have knowledge about the transaction in
    question so as to bring on record the truth in
    relation to the grievance or the offence. However, to
    resolve the controversy with regard to the powers
    of the general power-of-attorney holder to depose
    on behalf of the person he represents, this Court
    upon consideration of all previous relevant
    decisions on the aspect including that of Janki
    Vashdeo Bhojwani in A.C. Narayanan v. State of
    Maharashtra
    concluded by upholding the principle
    of law laid down in Janki Vashdeo Bhojwani and
    clarified that power-of-attorney holder can depose
    and verify on oath before the court but he must
    have witnessed the transaction as an agent and
    must have due knowledge about it. The power-of-
    attorney holder who has no knowledge regarding
    the transaction cannot be examined as a witness.
    The functions of the general power-of-attorney
    holder cannot be delegated to any other person
    without there being a specific clause permitting
    such delegation in the power of attorney; meaning
    thereby ordinarily there cannot be any sub-
    delegation.

    29. It is, therefore, settled in law that power-
    of-attorney holder can only depose about the facts
    within his personal knowledge and not about those
    facts which are not within his knowledge or are
    within the personal knowledge of the person who
    he represents or about the facts that may have
    transpired much before he entered the scene. The
    aforesaid power-of-attorney holder PW 1 had
    clearly deposed that he is giving evidence on behalf
    of Plaintiffs 2 to 4 i.e. the Galas. He was not having
    any authority to act as the power of attorney of the
    Galas at the time his statement was recorded. He
    was granted power of attorney subsequently as
    submitted and accepted by the parties. Therefore,
    his evidence is completely meaningless to establish
    that Galas have acquired or perfected any
    easementary right over the disputed rasta in 1994
    when the suit was instituted.

    63

    30. The only proper and valuable evidence in
    this regard could have been that of Joki Woler
    Ruzer who had instituted the suit but he failed to
    depose before the court. His pleadings are also
    vague and do not specifically state that he had
    been in use of the rasta in dispute for over 20 years
    or that he had acquired and perfected easementary
    right over the said rasta by prescription or
    necessity.”

    cc. In the case of Chowdamma (Dead) By Lrs. and Another Vs.

    Venkatappa (Dead) By Lrs. and Another reported in AIR

    OnLine 2025 SC 792 wherein the Hon’ble Supreme Court held

    that:

    “50. The failure of the defendants to
    substantiate their claims through documentary
    evidence is eclipsed by a more consequential
    omission. In a case where the principal controversy
    turns on matters lying within her exclusive
    personal knowledge, the silence of defendant No. 1,
    her absence from the witness box, is not a
    procedural lapse but a calculated withdrawal from
    scrutiny.

    51. The conspicuous silence of defendant no.
    1 strikes not merely as omission but as deliberate
    evasion. Defendant No. 1, who lies at the heart of
    the controversy, chose not to step into the witness
    box and depose regarding the relationship between
    the plaintiffs’ mother and her husband. Her
    testimony bore direct relevance not only to the
    status of plaintiffs’ mother but also her own
    position. The only justification advanced was that
    defendant No. 1, being an octogenarian and
    suffering from arthritis, was unable to attend the
    Court proceedings.

    52. However, this defence is conclusively
    dismantled by the record itself. The deposition of
    D.W.1 (Balachandrappa) clearly indicates that
    64

    defendant No. 1 was physically present in the
    Court during the examination of D.W.2 (G.V.
    Venkatappa), D.W.3 (Thimmappa) and D.W.4 (V.
    Thimmappa). It further emerges that defendant No.
    1 was also present in the Court when the evidence
    of P.W.1 (Venkatappa) was being recorded. If
    defendant No. 1 was capable of attending the
    Court on multiple occasions, no explanation
    remains for her failure to offer her own testimony,
    except for calculated restraint.

    53. This inference is inescapable. This is not a
    case of medical inability but of deliberate silence.
    In civil proceedings, particularly where the facts lie
    exclusively within the personal knowledge of the
    party, the refusal to enter the witness box carries
    grave evidentiary consequences.

    54. This principle is neither novel nor
    uncertain. This Court
    in Vidhyadhar v. Manikrao held thus:

    “17. Where a party to the suit does not
    appear in the witness-box and states his own
    case on oath and does not offer himself to be
    cross-examined by the other side, a
    presumption would arise that the case set up
    by him is not correct ….”

    55. The present case is a compelling
    invocation of the above principle. Defendant No. 1,
    though physically present in the Court during the
    trial, abstained from stepping into the witness box
    to rebut the plaintiffs’ assertions — assertions that
    strike at the very core of the dispute. In the
    absence of cogent medical evidence to support her
    alleged incapacity, her abstention from the witness
    box constitutes deliberate circumvention of the
    evidentiary burden resting upon her.

    56. In the present factual matrix, the adverse
    presumption under Section 114(g) of the Evidence
    Act is inevitable.

    57. This Court cannot overlook that defendant
    No. 1, while central to the controversy, chose not
    65

    only to abstain from entering the witness box but
    also wilfully bypassed the statutory remedy
    available to those pleading physical incapacity.”

    In the present case also all the documents issued by the

    officials who were the author of the documents and were the

    part of the work awarded to the plaintiffs are in service and

    connected with the said work but failed to appear before this

    Court and to depose the case of the defendants. The defendants

    failed to prove their case made out either in the written

    statement or in the Counter Claim.

    dd. Considering the facts and circumstances above, Issue Nos. 2 to

    9, 11 to 14 are decided in favour of the plaintiffs and against

    the defendants. Issue No. 10 and part of Issue No. 17 as regard

    to the compensation are against the plaintiffs and in favour of

    the defendants.

    11. Conclusion:

    a. The plaintiff is entitled to get an amount of Rs. 7,28,300/- being

    the earnest money adjusted through the security deposit. An

    amount of Rs. 54,25,050/- being the security deposit deducted

    from the running accounts bill of the plaintiffs. An amount of Rs.

    61,53,350/- being the amount of Bank Guarantee and an

    amount of Rs. 70,66,950/- being the bills raised by the plaintiffs

    and are pending before the defendants on different heads. The

    plaintiffs are also entitled to get interest at the rate of 9% per
    66

    annum from the date of termination of contract i.e. 5th March,

    2014 till the realisation of the total decretal amount. The

    defendants are also liable to pay cost of the suit assessed at Rs.

    1,00,000/-.

    b. The defendants are directed to pay the amount of Rs.

    1,93,73,650/- along with interest at the rate of 9% per annum

    from 5th March, 2014, till the realisation of the total amount to

    the plaintiff within a period of 60 days from date. The defendants

    are also directed to pay Rs. 1,00,000/- being the cost of the suit.

    c. The suit filed by the plaintiffs being C.S. (Com) No. 56 of 2024

    (Old No. CS 97 of 2014) is decreed. Counterclaim filed by the

    defendants is dismissed. GA No. 13 of 2022 is dismissed.

    Decree be drawn accordingly.

    (Krishna Rao, J.)



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here