Union Of India Through The Ministry Of … vs Tata Sons Private Limited Formerly Tata … on 30 April, 2026

    0
    61
    ADVERTISEMENT

    Bombay High Court

    Union Of India Through The Ministry Of … vs Tata Sons Private Limited Formerly Tata … on 30 April, 2026

    Author: G. S. Kulkarni

    Bench: G. S. Kulkarni

                                                                                   1-WP4914-22RESERVED.DOC
    2026:BHC-OS:11242-DB
    
                                IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                                   ORDINARY ORIGINAL CIVIL JURISDICTION
    
                                       WRIT PETITION NO. 4914 OF 2022
                                                    WITH
                                   INTERIM APPLICATION (L) NO. 17868 OF 2023
    
                 Tata Sons Private Ltd.                                      )...Petitioner
                       vs
                 1. Union of India, through the Ministry of Finance          )
                 2. Central Board of Indirect Taxes & Customs                )
                 3. Additional Director, Directorate General of              )
                    GST Intelligence
                 4. Joint Director,                                          )
                    Directorate General of GST Intelligence                  )
                 5. Joint/Additional Commissioner,                    )
                   Mumbai South Commissionerate.                      )...Respondents
                                                   __________
                 Mr. Arvind Datar, Sr. Adv. (through V. C.) a/w Mr. Rohit Jain, Chirag Shetty and
                 Ms. Ayushi Agrawal i/b Economic Laws Practice for the petitioner.
                  Mr. Anil C. Singh, ASG a/w Jitendra Mishra, Aditya Thackker, Sangeeta Yadav,
                 Ashutosh Mishra, Rupesh Dubey, Adarsh Vyas for Respondents.
                                                   __________
    
                                                        CORAM:
                                                            G. S. KULKARNI &
                                                            AARTI SATHE, JJ.
                                               RESERVED ON: 27 JANUARY 2026.
                                            PRONOUNCED ON: 30 APRIL 2026
    
    
                 JUDGMENT:

    (Per G. S. Kulkarni, J.)

    1. Rule, returnable forthwith. Respondents waive service. Heard finally by

    SPONSORED

    consent of the parties.

    2. This Petition under Article 226 of the Constitution of India challenges the

    legality and validity of (i) the intimation under Form DRC-01A bearing F. No.

    DGGSTI/MZU/I&IS ‘A’/12(4)12/2017/3900 dated 28 September 2022

    (Impugned Intimation) and (ii) the show cause notice dated 26 July 2023

    Page 1 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    (Impugned Show cause Notice) issued by the Joint Director of the Directorate

    General of GST Intelligence, Mumbai Zonal Unit whereby a demand of Rs.1524

    crores (Rs.15,24,35,20,405/-) towards payment of Integrated Goods and Service

    Tax (IGST) is sought to be levied on the petitioner.

    3. Briefly stated, the petitioner’s case is : The petitioner-Tata Sons Private

    Limited (for short “Tata”) is inter alia the principal investment holding company

    of the Tata Group, as also the promoter of its operating companies, and the

    owner of the Tata brand and trademarks. It is principally engaged in the business

    of making and holding investments.

    4. NTT Docomo Inc. (“Docomo”), a Japanese company, had invested in the

    shares of Tata Teleservices Limited (for short “TTSL”) along with Tata, such

    relationship between the parties was governed by a Shareholders agreement.

    TTSL and Docomo entered into a Shareholders Agreement (hereinafter referred

    to as “SHA”) on 25 March 2009 inter alia for providing telecommunication

    services to their customers. The SHA sets out the terms and conditions of the

    share transfer between the parties and certain performance indicators to be

    achieved by TTSL within the time specified therein. The ‘First Key Performance

    Indicators’ were set out in Schedule 7 of the SHA and the ‘Second Key

    Performance Indicators’ were specified in Schedule 8 of the SHA.

    5. Pursuant to the SHA, Docomo acquired 26% of TTSL’s equity capital.

    Under Clauses 5.6.3 and 5.7.2 of the SHA, it was provided that in the event

    TTSL failed to satisfy the ‘Second Key Performance Indicators’, Tata was

    Page 2 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    obligated to find a buyer for Docomo’s share at a ‘Sale Price’. Upon non-

    fulfillment of the said indicators, a ‘Trigger Notice’ would be deemed to have

    been issued under Clause 5.7.1. A ‘Sale Notice’ dated 7 July 2014 was issued by

    Docomo calling upon Tata to find a buyer in terms of Clause 5.7.2. As Tata was

    unable to comply with the same, disputes had arisen between Tata and Docomo.

    Such disputes were ultimately referred for adjudication in arbitral proceedings by

    Docomo, submitting its request for arbitration on 3 January, 2015 to the London

    Court of International Arbitration (“LCIA”). The arbitral proceedings

    culminated in an unanimous arbitral award dated 22 June 2016 (hereinafter

    referred to as the “Award”) rendered by the Arbitral Tribunal, whereunder the

    following amounts were held to be payable by Tata to Docomo:

    (i) Damages amounting to USD 1,172,137,717;

    (ii) Interest amounting to USD 65,276,963;

    (iii) Arbitration costs amounting to GBP 119,012.59; and

    (iv) Legal costs amounting to JPY 1,067,670,175.

    6. For enforcement of the aforesaid Award, Docomo initiated proceedings in

    the Courts of United Kingdom and United States of America. In India,

    proceedings for enforcement of the arbitral award were filed before the Delhi

    High Court. In such proceedings, Tata and Docomo filed Consent Terms,

    pursuant to which the Delhi High Court, by its order dated 28 April 2017,

    declared the Award to be enforceable in India. It was held that the arbitral award

    would operate as a deemed decree passed by the High Court. In terms of the said

    order passed by the Delhi High Court, Tata deposited an amount of Rs. 8,450

    Page 3 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    Crores with the Registry of the Delhi High Court.

    7. Prior to the remittance of the said amounts to Docomo, Tata received a

    letter dated 25 September 2017 from the Directorate General of GST

    Intelligence (“DGGI”) bearing F No. DGGSTI/MZU/I&S’A’/ 12(1)36/ 2017/

    4870 stating that an enquiry was proposed to ascertain facts relating to levy of

    Service Tax on such amounts being paid by Tata to Docomo. Tata was called

    upon to submit documents including the SHA with Docomo, details of damages

    paid/payable, copies of any invoice/debit note raised and service tax paid on the

    damages. Tata was also directed to depute an authorized representative to appear

    and tender evidence on 10 October 2017 in relation to the said matter.

    8. In compliance thereto, Mr. Eruch N. Kapadia, the Chief Financial Officer

    of Tata appeared before the authorities on 10 October 2017 and submitted the

    documents as called upon. It was informed to the officials that the amount of

    damages had been deposited with the Registry of the Delhi High Court on 29

    July 2016.

    9. Meanwhile, in terms of the order dated 28 April, 2017 passed by the

    Delhi High Court, and upon receipt of approval from the Competition

    Commission of India and the relevant tax certificates, the amounts awarded by

    the Arbitral Tribunal were remitted to Docomo on 30 October 2017 and 7

    November 2017.

    10. On 3 November 2017, Tata informed the department that the Service Tax

    Department did not have jurisdiction to initiate an investigation, as the payment

    Page 4 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    made to Docomo was not in lieu of any service, much less a taxable service.

    However, by its letter dated 15 November 2017, DGGI addressed to Tata, it was

    recorded that Tata’s contention was not acceptable, in view of clause (e) of

    Section 66E of the Finance Act, 1994. Tata was again called upon to depute an

    authorized representative and furnish the requisite documents.

    11. Thereafter, Tata by letter dated 27 November 2017, reiterated that no

    service tax was payable on the damages paid to Docomo, although it submitted

    the documents as requested. Subsequently, by letter dated 26 December 2017,

    DGGI called upon Tata to submit copies of the inter se agreement between the

    parties dated 25 March 2009, copies of which were duly furnished on 3 January

    2018. Tata reiterated its stand that no service tax was payable on the damages

    paid to Docomo under the arbitral award.

    12. After over six months from the last communication, DGGI issued another

    letter bearing F. No. DGGSTI/MZU/I&IS’A’/12(1)36/2017/4139 dated 25 July

    2018 seeking from Tata, a copy of the tax deduction certificate, if received. Tata

    by its letter dated 3 August 2018 submitted the tax deduction certificates in

    respect of payments made to Docomo. Thereafter, by letter dated 4 September

    2018, DGGI sought further details as to whether the payments as made by Tata

    to Docomo were reflected in the ST-3 returns. Tata by its letter dated 5 October

    2018 replied that the award payments were not in lieu of any taxable service and

    hence not liable to be declared in ST-3 returns.

    13. Things remained quite stagnant, till after almost eleven months, by

    Page 5 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    communication dated 19 August 2019, DGGI again sought further information

    and the exact dates of payment made by Tata to Docomo, along with bank details

    and documentary evidence. Tata’s authorized representative was called upon to

    appear before the concerned official on 30 August 2019. Tata submitted the

    requisite details on 30 August 2019 and 18 September 2019. Thereafter, on 27

    December 2019, Tata filed a representation with Respondent No. 2 (CBIT)

    seeking clarification on applicability of GST, on payments made by Tata to

    Docomo pursuant to the orders of the Delhi High Court. By further letters dated

    16 January 2020 and 9 February 2021, Tata requested that the investigation be

    kept in abeyance pending consideration of the representation. However, Tata has

    not received any response from the office of the Respondent No. 2 on such

    representation till date.

    14. It is Tata’s case that to its surprise, by letter dated 15 February 2022,

    respondent No. 3 informed Tata that the payments made to Docomo on 30

    October 2017 and 7 November 2017 under the arbitral award, namely, the

    damages, interest, legal costs and arbitration costs attracted GST under the Goods

    and Services Tax Act, 2017. Tata was directed to depute its representative to

    appear before respondent no. 3 on 23 February 2022. Accordingly, Tata’s

    authorized representative appeared before respondent no. 3 on 23 February 2022

    and 22 March 2022.

    15. Thereafter, vide letter dated 4 April 2022, Tata informed respondent No.

    3 that all the information pertaining to the transaction was provided by Tata to

    the respondents. Tata inter alia requested respondent no. 3 to provide any

    Page 6 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    communication received by Respondent No. 3 from the office of Respondent

    No. 2 on the representation filed by Tata dated 27 December 2019.

    16. On the aforesaid conspectus, on 28 September 2022, an intimation of tax

    ascertained as payable under Form DRC-01A bearing F. No.

    DGGSTI/MZU/I&IS ‘A’/12(4)12/2017/3900 was issued, advising Tata to pay

    Integrated Goods and Services Tax (“IGST”) of Rs.1524,35,20,405/- along with

    interest and penalty under Section 74(5) of the Central Goods and Services Tax

    Act, 2017 (“CGST Act“). Such intimation inter alia refers to the Office

    Memorandum F. No. 349/168/2017-GST-Pt. 1/314 dated 21 February 2018

    issued by Central Board of Excise & Customs (now Central Board of Indirect

    Taxes and Customs), Policy wing, Government of India recording the grounds on

    the basis of which IGST was proposed to be demanded from Tata in respect of

    the payment made to Docomo. Such intimation alleged that Docomo by its act of

    tolerating the contractual defaults by Tata and by refraining from initiating any

    further proceedings against Tata in relation to the SHA and/or the Award had

    rendered “supply of service” of the nature of agreeing to refrain from an act or

    tolerating an act, falling within the ambit of Entry 5(e) of Schedule II under

    Section 7 of the CGST Act. It was stated that Tata was liable to discharge IGST

    on reverse charge basis as the said service was considered to be an import of

    service. Tata sought time to examine the said intimation and requested for a copy

    of the Office Memorandum issued by the CBIC-GST Policy Wing, relied upon

    in the said intimation. Despite reminder letter dated 2 November 2022, the said

    document was not furnished and/or was refused is Tata’s conclusion. Aggrieved

    Page 7 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    thereby, the petitioner-Tata has preferred the present Writ Petition inter alia

    challenging the intimation under Form DRC-01A.

    17. When this petition was listed for hearing on 30 March 2023, a co-

    ordinate Bench of this Court deferred the hearing to enable Tata to appear before

    the concerned authority without prejudice to its rights and contentions including

    that of submitting to the jurisdiction of the authority of the designated officer. It

    was also ordered that the documents referred to in the intimation, if sought for by

    Tata shall be supplied to it. Also, liberty was granted to Tata to place on record

    the order which would be issued by the concerned authority on the outcome of

    the said proceedings, if the same were adverse to Tata by necessary amendments.

    18. Accordingly, Tata addressed a letter dated 6 April 2023 to respondent no.

    3 seeking copy of the Office Memorandum dated 21 February 2018, which was

    furnished by Respondent No. 3 vide letter dated 21 April 2023. Thereafter, Tata

    by its letter dated 16 May 2023 addressed to respondent no. 3, sought

    confirmation as to whether any further correspondence existed on the issue

    subsequent to the said Office Memorandum between CBIC and the office of

    Respondent No. 3, and requested copies thereof, if any. In the absence of any

    response from the office of Respondent No. 3 to the said letter dated 16 May

    2023, Tata submitted its detailed reply to the intimation under Form DRC-01A

    under its letter dated 31 May 2023, as per the directions of this Court including

    on jurisdiction. However, after Tata filed its reply dated 31 May, 2023, on 3 June

    2023, Tata received a communication dated 30 May 2023 from Respondent No.

    3, which was in response to Tata’s letter dated 16 May 2023, inter alia stating that

    Page 8 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    there was no other correspondence in relation to the Office Memorandum dated

    21 February 2018 and further directed Tata to file its reply

    19. Thereafter, the present writ petition came to be listed for hearing before a

    co-ordinate Bench of this Court on 6 June 2023, to which one of us (G.S.

    Kulkarni, J.) was a member. On the even date, this Court passed an order

    directing Respondent No. 3 to grant Tata a personal hearing and take an

    appropriate decision within three weeks from 6 June 2023, while adjourning the

    proceedings to 4 July, 2023.

    20. Tata by letter dated 7 June 2023, informed Respondent No. 3 that its

    reply to the intimation under Form DRC-01A had already been filed on 31 May

    2023 and requested for copies of any further correspondence apart from the

    Office Memorandum dated 21 February 2018.

    21. Pursuant to the order dated 6 June, 2023 passed by this Court, the

    authorized officer of Tata was granted a personal hearing, who addressed

    submissions on the lines of Tata’s reply dated 31 May 2023.

    22. When this writ petition was listed before the Court on 7 July 2023,

    respondent No. 3 moved an Interim Application seeking extension of time to

    take a decision in the matter on which hearing had stood concluded. By an order

    of even date, this Court directed Respondent No. 3 to expeditiously dispose of

    the pending proceedings within a period of three weeks from 7 July 2023.

    23. On such backdrop, Tata was issued a Show Cause Notice dated 26 July

    Page 9 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    2023 under Section 74(1) of the CGST Act by the Joint Director, DGGI, Zonal

    Unit, Mumbai (Respondent No. 4), calling upon Tata to show cause within 30

    days of receipt of the notice as to why IGST amounting to Rs. 1,524,35,20,405/-

    along with applicable interest and penalty under Section 74(5) of the CGST Act

    should not be demanded from it. In paragraph 11 of the said Show Cause Notice,

    the Respondents in detail referred to the circulars dated 3 August 2022 and 28

    February 2023 issued by CBIC, which were relied upon by Tata inter alia stating

    that the same were not applicable to the facts of the present case.

    24. On the aforesaid backdrop, Tata contends that the respondents have acted

    arbitrarily and without jurisdiction in demanding GST, by issuance of the

    impugned intimation and the consequent impugned Show Cause Notice, which

    is contended to be in violation of the principles of judicial discipline, as well as

    the principles of natural justice.

    25. On the aforesaid conspectus, the prayers as made in the petition

    (including the amended prayers*) are required to be noted which read thus:

    “(a) that this Hon’ble Court be pleased to issue a Writ of Certiorari or a writ in
    the nature of Certiorari or any other writ, order or direction under Article 226 of
    the Constitution of India calling for the records pertaining to the petitioner-Tatas
    case and after going into the validity and legality thereof be pleased to quash and
    set aside the intimation under Form DRC-01A bearing F. No.
    DGGSTI/MZU/I&IS ‘A’/12(4)12/2017 /3900 dated 28.09.2022 (Exhibit – T)
    issued by the Respondent No. 3;

    (b) that this Hon’ble Court be pleased to issue a writ of mandamus or a writ in
    the nature of mandamus or any other appropriate writ or order or direction
    under Article 226 of the Constitution of India ordering and directing the
    Respondents themselves, their officers and subordinates to forthwith withdraw
    the intimation under Form DRC-01A bearing F. No. DGGSTI/MZUI&IS
    ‘A’/12(4)12/2017 3900 dated 28.09.2022 (Exhibit T) issued by the Respondent
    No. 3;

    * Amended prayers are in italics

    Page 10 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    (c) that this Hon’ble Court be pleased to issue a writ of prohibition restraining
    the Respondents from giving effect to and/or proceeding with the intimation
    under Form DRC-01A bearing F. No. DGGSTI/MZU/I&IS
    *A’/12(4)12/2017/3900 dated 28.09.2022 (Exhibit – T) issued by the
    Respondent No. 3;

    (ca) that this Hon’ble Court be pleased to issue a Writ of Certiorari/or a writ in
    the nature of Certiorari or any other writ, order or direction under Article 226 of
    the Constitution of India calling for the records pertaining to the petitioner-Tatas
    case and after going into the validity and legality thereof be pleased to quash and
    set aside the Show Cause Notice bearing F No. DGGSTI/MZU/I&IS
    A/12(4)12/2017/7319 dated 26.07.2023 (Exhibit-II) issued by the Respondent
    No. 4;

    (cb) that this Hon’ble Court be pleased to issue a writ of mandamus or a writ in
    the nature of mandamus or any other appropriate writ or order or direction
    under Article 226 of the Constitution of India ordering and directing the
    Respondents themselves, their officers and subordinates to forthwith withdraw
    the Show Cause Notice bearing F No. DGGSTI/MZU/I&IS
    A’/12(4)12/2017/7319 dated 26.07.2023 (Exhibit-II) issued by the Respondent
    No. 4;

    (cc) that this Hon’ble Court be pleased to issue a writ of prohibition restraining
    the Respondents from giving effect to and/or proceeding with the Show Cause
    Notice bearing F No. DGGSTI/MZU/I&IS *A’/12(4)12/2017/7319 dated
    26.07.2023 (Exhibit-II) issued by the Respondent No. 4;
    (cd) that pending the hearing and final disposal of this Petition, the Respondents
    by themselves, their officers, subordinates, servants and agents be restrained
    from in any manner enforcing or acting upon the Show Cause Notice bearing F
    No. DGGSTI/MZU/I&IS ‘A’/12(4)12/2017/7319 dated 26.07.2023 (Exhibit-
    II) issued by the Respondent No. 4.

    d. In the alternative, declare that Section 7 read with entry 5(e) to Schedule II of
    the CGST Act
    of the GST is illegal, ultra vires and unconstitutional;”

    Case of the DGGI in the Reply Affidavit

    26. The Directorate General of Goods and Services Tax Intelligence (DGGI)

    has filed a reply affidavit dated 11 January 2023 of Mr. Rahul Raichur, Deputy

    Director of DGGI prior to issuance of the impugned show cause notice dated 26

    July, 2023.

    27. At the outset, considering the prayers as made in the writ petition, an

    objection is raised to its maintainability and/or that no ground to maintain such

    prayers being made out by Tata. It is also contended that the writ petition is

    Page 11 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    premature.

    28. As regards the challenge to the constitutional validity of Section 7 read

    with Entry 5(e) of Schedule II of the CGST Act, 2017, the Respondents

    submitted that the same is wholly academic and does not arise for consideration

    in the absence of any factual foundation.

    Affidavit-in-Rejoinder

    29. Tata has filed a para-wise Affidavit-in-Rejoinder dated 25 January 2023 to

    the Affidavit-in-Reply filed on behalf of the Respondents dated 11 January 2023

    (supra), reiterating its case in the Writ Petition in relation to the impugned action

    of levying tax on the settlement of the arbitral award. Tata has also justified its

    challenge to the validity of the provisions of the GST Act, as assailed in the

    petition. It is further contended that the entire action of the respondents in

    initiating recovery proceedings in respect of the subject matter is wholly without

    jurisdiction. Tata has denied the contention that the petition is premature or not

    maintainable. Tata has also reiterated its contention regarding the Circular,

    namely, Circular No. 178/10/2022-GST dated 3 August, 2022 (supra) and its

    binding nature.

    Submissions on behalf of the petitioner-Tata

    30. Mr. Datar, learned Senior Advocate appearing for the petitioner-Tata has

    made the following submissions:

    (i) It is submitted that it is clear from the facts that a contractual dispute

    Page 12 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    between the petitioner-Tata and NTT Docomo Inc. (Docomo) subject matter

    of arbitral proceedings, resulted in an award of damages to the extent of Rs.

    8,450 crores passed by an arbitral tribunal in London dated 22 June, 2016.

    The award, which is an international commercial award, was governed by Part

    II of the Arbitration and Conciliation Act, 1996 (“A & C Act”). The award

    was being enforced by Docomo in terms of sections 48 and 49 of the A &

    Act. In the said proceedings initiated by Docomo before the Delhi High

    Court, it was held by the Delhi High Court that the award was enforceable as

    a decree of the Court. The petitioner – Tata in such proceedings deposited

    the award amount with the Registrar of the Delhi High Court, after

    compliance with other statutory formalities (for which, six months was

    provided). The amounts were thereafter withdrawn/remitted to Docomo.

    (ii) It is submitted that in addition to the proceedings before the Delhi High

    Court, Docomo has also filed execution proceedings in the Courts of United

    Kingdom (UK) and the United State of America (USA) for attachment of

    assets of the petitioner-Tata in Jaguar Land Rover and other Tata companies.

    It is submitted that since the award was fully satisfied with Tata making

    payment of damages of Rs.8,450 crores as awarded by the arbitral tribunal

    under the orders passed by the Delhi High Court. Docomo withdrew the

    execution proceedings, which were instituted before the Foreign Courts (UK

    and USA). To this effect, Docomo and Tata filed consent terms before the

    Delhi High Court agreeing that as the award had stood satisfied, Docomo

    agreed that the execution proceedings filed before the UK and USA Courts

    Page 13 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    would be withdrawn. It is Mr. Datar’s submission that no consideration was

    independently paid to Docomo for withdrawal of execution proceedings and

    that the withdrawal of the execution proceedings was an obvious outcome of

    discharge by Tata of the decretal amount in full and final, on which no tax

    could be levied.

    Submission on Show Cause Notice dated 26.07.2023

    (iii) Mr. Datar would submit that on the aforesaid premise, the show

    cause notice dated 26 July, 2023 in Form DRC-01A was issued against the

    petitioner-Tata seeking to levy Integrated Goods and Services Tax Act (IGST)

    on the damages of Rs.8450 crores on the ground that by withdrawing the

    execution proceedings, Docomo had “tolerated this act”, i.e., the breach,

    which has attracted a levy of GST under Entry No. 5(e) read with Schedule II

    of the CGST, 2017, which provides for “agreeing to the obligation to refrain

    from an act, or to tolerate an act or a situation, or to do an act”. It is

    submitted that ex-facie this was misconceived/ wrong, as Docomo had not

    tolerated the breach and finally was awarded damages of Rs. 8450 crores,

    which was enforced by the Delhi High Court as a decree of the Court.

    (iv) Mr. Datar has next submitted that a Writ Petition was filed for the

    reason that Circular No.178/10/2022-GST dated 3 August, 2022 had

    declared that the damages are not taxable, as despite bringing this to the

    notice of the GST authorities, as directed by this Court, the department

    proceeded to issue the impugned show cause notice dated 26 July, 2023 once

    Page 14 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    again seeking to levy IGST on the amount of damages. It is submitted that

    accordingly, the writ petition was amended to quash the show cause notice.

    Show cause notice liable to be quashed contrary to Board Circulars

    (v) Mr. Datar would submit that the show cause notice would be liable to

    be quashed, firstly on the ground that it is contrary to the Board Circulars

    referring to para 7.1.4 of Circular no. 178/10/2022 which expressly provides

    that liquidated damages are paid as compensation for an injury/breach of

    contract, and are not liable to tax. The circular also holds that Entry No. 5(e)

    of Schedule II of the CGST Act, 2017 will apply only when there is a

    “separate agreement” to tolerate an act and there is a separate consideration

    for the same. In such context, Mr. Datar has also referred to paragraphs 7.1.5

    and 7.1.6 of the Circular. It is submitted that the said circular, which refers to

    liquidated damages under section 74, necessarily would apply in the present

    case, which concerns award of damages.

    (vi) Mr. Datar would next submit that Circular no. 214/1/2023-Service

    Tax dated 28 February, 2023 has once again reiterated the earlier position as

    set out in Circular No.178/10/2022 and directed withdrawal of appeals in the

    Supreme Court against CESTAT rulings which had held that damages,

    penalty, etc. were not liable to service tax. The Circular also directed that no

    further appeals should be filed in other cases, as clearly seen from paragraph 5

    of the circular.

    (vii) Mr. Datar would submit that these circulars are binding on the

    department, hence a writ of Prohibition would certainly lie against the

    Page 15 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    Department, as a demand for IGST on damages cannot be made for such

    reason. It is submitted that the impugned show cause notice is hence liable to

    be quashed and set aside considering the circulars being binding on the

    Department. In supporting such submission, reliance is placed on the

    decision of the Supreme Court in Paper Products Limited v. CCE1

    (viii) Mr. Datar would next submit that apart from the Board Circulars, it

    is settled position in law that damages are the fait of the court. They do not

    represent consideration for any agreement/contract. In supporting such

    submission, reliance is placed on the decision of the Supreme in Union of

    India v. Raman Iron Foundry2, which affirms the view of Chagla CJ in the

    decision of this Court in Iron & Hardware (India) Co. vs. Shamlal &

    Brothers3. Mr. Datar would next submit that the levy of CGST or IGST is on

    supply of goods or services and on the consideration or transaction value of

    such supply, for such reason, it would be absurd to treat damages as

    consideration or the transaction value of supply. This, particularly, when a

    decree for damages is a consequence of a breach of contract, hence, it cannot

    be treated as “consideration” or transaction value for supply of services.

    (ix) Mr. Datar would submit that apart from the binding nature of the

    circulars and the settled principles of law in that regard as laid down in several

    decisions of the Supreme Court and of this Court, it is submitted that having

    due regard to the statutory provisions, IGST can be levied only if there is a

    1 1999(112) ENT 765 (SC)
    2 1974 SCC (2) 231
    3 1954 SCC OnLine Bom. 5

    Page 16 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    supply under sections 7 and 7(1A) of the CGST Act, 2017, and it can only be

    on the value of the taxable supply. It is submitted that under section 15 of the

    CGST Act, the value is the price actually paid or payable for the supply of

    goods or services. Damages awarded by an Arbitral Tribunal and affirmed by

    the High Court become a “decretal amount”, which can never be the

    transaction value or the price paid for supply of services of “tolerating an act”

    under Entry No. 5(e) of Schedule II of the CGST Act.

    (x) It is submitted that once Docomo has received the entire amount of

    damages post the award in proceedings before the UK/US Courts and further

    proceedings before the Delhi High Court, there is no question of the

    Japanese company/DOCOMO “tolerating any breach.” It is submitted that

    the withdrawal of the UK/US proceedings became consequential and there

    was no act of toleration by Docomo. It is submitted that thus, the demand is

    contrary to Entry No. 5(e) of Schedule II, as this entry will not apply in

    respect of such court proceedings.

    Submissions on Alternate remedy:

    (xi) It is submitted that the plea of alternative remedy needs to be

    rejected, as the show cause notice is wholly without jurisdiction. Also, in a

    writ of prohibition, the writ is a matter of right when there is no jurisdiction.

    (xii) It is submitted that a show cause notice as issued is – (i) in an open

    defiance of two Board Circulars; (ii) It is contrary to judgments of the

    Supreme Court and this Court on the nature of damages; and (iii) It is in

    Page 17 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    violation of Sections 7, 7(1A) and 15 read with Entry No. 5(e) of Schedule II

    of the CGST Act, 2017 and hence the same deserves to be quashed with

    exemplary costs. In supporting the submission on the plea of alternate

    remedy to be rejected, reliance is placed on the decision of the Supreme

    Court on Whirlpool Corporation v/s Registrar of Trade Marks 4.

    (xiii) It is submitted that the impugned show cause notice is inherently

    without jurisdiction inasmuch as the arbitral award being compromised in

    terms of the consent terms as entered before the Delhi High Court between

    the petitioner-Tata and Docomo cannot be categorized as supply of any

    service considering the clear provisions of the CGST Act and more

    particularly Section 7 read with Section 9 and Schedule II Entry 5(e) thereof.

    In the absence of such jurisdictional authority, the impugned show cause

    notice needs to fall to the ground.

    (xiv) The Arbitral Award necessarily awards damages against the

    petitioner-Tata, being a result of adjudication of the disputes in the arbitral

    proceedings. The award of damages necessarily stands recognized in terms of

    what Section 73 of the Indian Contract Act, 1872, would provide. The legal

    character of such amounts being leviable to be paid by Tata to Docomo is by

    way of damages, the nature and character of such amounts to be damages

    whether under Section 73 or Section 74 (liquidated damages) would not

    change. The award of damages is to compensate the party to an agreement for

    the losses it had suffered on account of breach of the contract, and in this

    4 (1998) 8 SCC 1

    Page 18 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    view of the matter, once there is adjudication of the damages and the liability

    to pay such damages is under an arbitral award, which is akin to a decree of

    the Court, there is no question of the award per se amounting to any supply

    of service.

    (xv) It is next submitted that even if the award is compromised under

    certain conditions, which would be to do away with the enforcement and

    recovery proceedings in the other jurisdiction, it would not alter the legal

    character of the award i.e. the damages being granted in the arbitral

    proceedings.

    (xvi) It is next submitted that the recovery proceedings under the award

    which are permissible to be instituted in different jurisdictions whenever

    enforcement and recovery are possible, are a consequence or incidental to the

    award and are not independent proceedings, much less, categorized as a

    supply of service in the event of any covenant to dispose of such incidental

    proceedings. This is an error which the jurisdictional officer has committed in

    issuing the impugned show cause notice.

    (xvii) It is next submitted that in any event the situation akin to the

    present situation has already been subject matter of consideration of the

    Central Board of Indirect Taxes and Customs (CBIC) when the Circular

    dated 3 August 2022 and 28 February 2023 were issued although in terms of

    liquidated damages (sic 73 of the Contract Act) categorically holding that in

    respect of an arbitration award for decree of damages, there cannot be any

    Page 19 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    levy under the GST Laws. The impugned action of issuing show cause notice,

    hence, is in the teeth of the circulars. The petitioner has hence become

    entitled for the reliefs as prayed for.

    Submissions on behalf of the respondent

    31. On behalf of the respondent, Mr. Anil Singh, learned Additional Solicitor

    General has made the following submissions:

    The present Writ Petition was initially filed by the petitioner-Tata inter

    alia challenging the notice dated 28 September, 2022 issued in Form DRC-01A,

    which was a pre-show cause consultation notice. Pending this petition, this Court

    passed an order dated 6 June 2023 directing the petitioner-Tata to appear before

    the GST authority under the said notice and make submissions, without

    prejudice to the rights and contentions, including submitting to the jurisdiction

    of the said authority. The petitioner-Tata accordingly appeared before the

    designated authority by filing its reply and written submissions. After considering

    the reply and submissions, the respondent issued the impugned show cause

    notice dated 26 July, 2023 under Section 74 (1) of the CGST Act, which is

    challenged in this petition by amending the petition. It is submitted that on such

    premise, the case of the petitioner-Tata is that the Court should consider and

    arrive at a finding that the payment made by the petitioner-Tata to Docomo is

    not a “supply of service” as per section 7 of the CGST Act read with entry 5(e) to

    Schedule II of CGST Act, as also the show cause notice is contrary to Circulars

    dated 3 August, 2022 and 28 February, 2023 issued by CBIC.

    Page 20 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    32. It cannot be that the DGGI has no jurisdiction and/or authority to issue

    the impugned show cause notice. It is submitted that there is no inherent lack of

    jurisdiction and therefore, the petition is not maintainable. Also, the applicability

    of the Circulars in the facts and circumstances of the case requires adjudication

    and the adjudicating authority is competent to determine the issue of taxability as

    well as jurisdiction, which ought to be raised by the petitioner-Tata. It is

    submitted that on this count alone, the petition is not maintainable and is liable

    to be dismissed. In supporting such submissions, reliance is placed on (i) State of

    Orrisa vs. Mesco Steel Ltd.5, (ii) Union of India vs. Bajaj Tempo Ltd. & Ors.6;

    (iii) Special Director vs. Mohd. Ghulam Ghouse7; (iv) Union of India vs.

    Kunisetty Satyanarayana8; (v) Om Drishian International Ltd vs. Additional

    Director, Directorate of Revenue Intelligence and Anr.9; (vi) Union of India vs.

    Coastal Containers Transporters Association10; (vii) State of Madhya Pradesh &

    Ors. vs. Commercial Engineers and Body Building Co.11; (viii) Oberoi

    Construction Ltd. vs. Union of India & Ors.12; (ix) United Bank of India vs.

    Satyavati Tondon & Ors.13.

    33. It is next submitted that Docomo and the petitioner-Tata had entered into

    the shareholders agreement dated 25 March 2009 (Exhibit A, page 54), under

    which disputes and differences had arisen in relation to performance of clause
    5 (2013) 4 SCC 340
    6 (1998) 9 SCC 281
    7 (2004) 3 SCC 440
    8 (2006) 12 SCC 28
    9 2021 SCC OnLine Bom 8036
    10 2019 (22) G.S.T.L. 481 (SC)
    11 2022 SCC OnLine 1425
    12 2024 SCC OnLine Bom 3508
    13 2010 (8) SCC 110

    Page 21 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    5.7.2 being a clause whereby the petitioner-Tata was to find a buyer for the shares

    held by Docomo at a fair price or to buy the shares itself. It is submitted that the

    arbitral tribunal has made the following observations in the context of the said

    clause:- “Docomo contends that its object was to ensure that Docomo could

    dispose of its shares if TTSL failed to perform and Docomo’s losses would never

    be greater than half of its initial investment & TATA accepts that the clause was

    intended to assure Docomo a minimum exit price or a guaranteed exit price. The

    Tribunal considers it fair to characterize this as stop loss protection “. It is

    submitted that in such context, the Delhi High Court in the proceedings qua

    enforcement of the award as initiated by Docomo has observed that the Docomo

    and the petitioner-Tata have arrived at Consent Terms inter alia to the effect that

    petitioner-Tata will comply with and make payment as per the Award. A period

    of six months was agreed between the parties, as a suspension period during

    which the Docomo will not precipitate further proceedings and that within such

    six months the petitioner-Tata has to obtain certain certificates from the tax

    perspective and make payment of the award amounts, whereupon the

    proceedings would stand withdrawn by Docomo and if payment is not made

    then proceedings would continue.

    34. In the aforesaid context, it is submitted that the show cause notice raised

    several grounds. It is submitted that the petitioner-Tata had failed to show cause

    and address certain portions of the impugned show cause notice which would

    indicate that ex facie, in terms of the 2022 and 2023 circulars, there is a supply

    which covers an independent contract for an act of forbearance or toleration. In

    Page 22 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    other words, it is submitted that it is noticed from the operative part of the Award

    that the monies awarded were due and payable within a period of 21 days from

    the award.

    35. It is next submitted that the petitioner-Tata has not simply agreed to pay as

    per the award resulting in withdrawal of the enforcement proceedings by

    Docomo, instead, Consent Terms have been entered into between the parties. It

    is submitted that even at the time of hearing at the pre show cause notice stage,

    the complete consent terms were not available, and the petitioner-Tata had

    referred to the orders passed by the Delhi High Court dated 28 April 2017.

    36. Mr. Singh would submit that it is the case of the department that the

    following contents of the consent terms imply a new and independent agreement

    and the obligations thereunder go beyond the award inasmuch as :-

    “3. The obligations of the Respondent hereunder shall further be subject to
    receipt of approval of the Competition Commission of India and (it) receipt of
    the Withholding Tax Certificate (as defined hereinafter) The petitioner will apply
    to the Indian Income Tax authorities to obtain the withholding tax certificate
    (“Withholding Tax Certificate!) in relation to payments under the Award based
    on which Respondent will remit the Funds, after deduction of taxes, if any, to
    Designated Bank Account. The petitioner agrees that the amount of Rs.
    $450,00,00,000 (Rupees Eight Thousand Four Hundred and Fifty Crore Only)
    along with accrued interest which amounts to a total of Rs. 8,730,59.83:623
    (Rupees Eight Thousand Seven Hundred Thirty Crore Fifty Nine Lakh Eighty
    Three Thousand Six Hundred and Twenty Three Only) as on 30 January 2017
    (along with any further interest which may accrue thereon) (“Deposit”) deposited
    in this Hon’ble Court shall be released in accordance with the procedure
    prescribed in detail in paragraph 4 below. It is clarified that in case there is any
    difference between the Deposit and the Funds as per the Award, then any
    shortfall would be made up by the Respondent to the extent of the shortfall, and
    in case there is any excess amount then the same will get remitted back to
    Respondent, by way of withdrawal or deposit from/into the Interim Account by
    the Respondent, and the deduction of tax, if any, shall be computed and withheld
    on such adjusted amount.

    4. Subject to the ruling and directions of this Honourable Court as provided in
    paragraph 3 above, the payment of the funds, after deduction of taxes, if any, to

    Page 23 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    the Designated Bank Account and other related actions shall be made in the
    following manner:

    4.1 The Deposit is to be retained by the Registrar of this Hon’ble Court till
    requisite clearance from Competition Commission and the Withholding Tax
    Certificate as mentioned in these consent terms have been obtained. Once the
    requisite clearances/certificate have been obtained the Deposit will be transferred
    to an account in the name of the Respondent (“Interim Account”)

    4.2 The petitioner will then nominate an Authorised Dealer (“AD”) for
    remittance of Funds after deduction of taxes, if any, to the Designated Bank
    Account ARE

    4.3 The petitioner undertakes that it shall, simultaneously with the receipt of the
    Funds, after deduction of taxes, if any, in the Designated Bank Account,
    complete the process of debiting its dematerialised accounts of all shares of Tata
    Teleservices Limited (“Shares) held by the petitioner and have the Shares
    credited to the dematerialised accounts of the Respondent and/or its nominees
    and the Respondent shall co-operate with the petitioner for having the “Shares”

    credited to the dematerialised accounts of the Respondent and/or its nominees
    and in completing and executing Form FCTRS for this purpose.

    4.4 Both Parties will take all actions and provide all documents and information
    as requested by the AD to permit remittance of the Funds, after deduction of
    taxes, if any, to the Designated Bank Account and the credit of the Shares to
    dematerialised accounts of the Respondent and/or its nominees.

    5. In light of the withdrawal of the objections of the Respondent, this
    Honourable Court may be pleased to declare that the Award is enforceable in
    India and shall operate as a deemed decree and this Honourable Court shall
    proceed to execute the same, subject to the ruling on the objections of RBI as
    raised in RBI’s Application for Intervention in these proceedings (and for that
    purpose the Parties agree not to object to the intervention of RBI).

    6. The petitioner agrees and undertakes that the enforcement of the Award in
    India, and this deemed decree, against the Indian assets of Tata will be limited to
    the monies deposited (along with interest accrued thereon) in this Hon’ble Court
    by the Respondent only so long as Respondent complies with its obligation to
    make up for any difference between the Deposit and the Finds in terms of
    paragraph 3 of these consent terms.

    7. The petitioner undertakes to this Honourable Court that shall suspend
    proceedings initiated against the Respondent which are currently pending in
    United Kingdom [Claim No CL-2016-000428 in the High Court of Justice,
    Queen’s Bench Division of the Commercial Court) and in the United States of
    America [Civil Action No. 1:16-cv-7809, in the United States District Court,
    Southern District of New York for a period 6 months from the date hereof
    (“Suspension “Period”). Upon receipt of the Funds, after deduction of taxes, if
    any, by the petitioner in the Designated Bank Account any time within the
    unconditionally withdraw all proceedings initiated against the Suspension Period
    as per paragraph. 4 above, the petitioner shall Respondent in relation to the SIIA
    and/or the Award, including aforementioned proceedings in the United
    Kingdom and aforementioned proceedings in the United States of America
    within one week thereof. In the event of the petitioner not receiving payment of
    the Funds, after deduction of taxes, if any, in the Designated Bank Account of

    Page 24 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    the petitioner within the Suspension Period, the petitioner shall be free to pursue
    the UK and US enforcement actions.

    8. The petitioner undertakes to this Honourable Court that it shall not initiate
    any further proceedings in relation to the SHA and/or the Award during the
    Suspension Period, or thereafter, if the Suspension Period, if the Funds, after
    deduction of taxes, if any, are received during the Suspension Period.

    9. The Parties agree that upon receipt of the Funds, after deduction of taxes, if
    any, in the Designated Bank Account by the petitioner, and the credit of the
    Shares to dematerialised accounts of the Respondent and/or its nominees, as per
    paragraphs 3 and 4 above, the Award shall stand fully and finally satisfied and
    discharged and that the Parties shall have no outstanding claims against each
    other.

    10. The Parties agree that the Consent Terms as set out hereinabove care
    exhaustive and conclusive, as between the Parties hereto, with respect to the
    issues dealt hereinabove.

    11. The Parties shall co-operate with each other and provide all necessary
    assistance in completing and filing all forms and completing all other formalities
    necessary for completing the payment of the Funds, after deduction of taxes, if
    any, and the credit of the Shares to dematerialised accounts of the Respondent
    and/or its nominees as set out in this order.

    12. The parties shall bear their respective costs in connection with these
    proceedings.”

    37. Relying on the aforesaid paragraphs of the consent terms, it is submitted

    by Mr. Singh that the consent terms introduced further contractual bargains

    between the parties which are not limited to merely complying with the award as

    contended by the petitioner-Tata. It is submitted that apart from the detailed

    modalities of payment being agreed, one of the most important facets of the

    consent terms, is to the effect that, despite the award being enforceable, Docomo

    had agreed to forbear and/or refrain from and/or tolerate the non payment of

    monies for a period of six months, that is the suspension period. It is submitted

    that such suspension period is beyond the award and the same is nothing but a

    new contract between these parties whereby one party has agreed to refrain or

    tolerate non-payment for a period of six months without precipitating further

    Page 25 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    action. It is this agreement between the parties which, according to Mr. Singh,

    squarely falls within Clause 7.1.6 of the 2022 Circular. It is thus submitted that

    the consent terms go beyond the award and if it was simply the award which was

    to be complied, then there was no need for consent terms.

    38. It is next submitted that the show cause notice specifically refers to the

    consent terms and the fact that these consent terms make out a new bargain

    and/or constitute supply and make out a case in paragraph 6(c), 7.5, 7.12, 11.3,

    11.4 of the show cause notice. It is hence, submitted that ex facie there is a supply

    and the clear existence of a jurisdictional fact for the show cause notice to be

    issued, for which an inquiry needs to be conducted by the authorities under the

    GST Act. For such reason, it is not a case of lack of inherent jurisdiction.

    39. In regard to the contention as urged on behalf of the petitioner-Tata that

    the show cause notice violates the circulars, it is submitted that the said position

    can be taken before the adjudicating officer and such issue need not be gone into

    before this Court. On the aforesaid contention it is submitted that the petition

    deserves to be dismissed.

    Analysis & Conclusion

    40. Having heard learned counsel for the parties and having perused the

    record, in the facts and circumstances of the case, the question which would arise

    for determination is “Whether the settlement between the parties in the

    proceedings filed by Docomo under Sections 47 and 48 of the Arbitration and

    Conciliation Act, 1996 (ACA), under which the arbitral award for damages stood

    Page 26 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    settled between the parties, would amount to “supply” within the definition of

    Section 7(1) of the CGST Act?”

    41. As the facts of the case unfold, it is clear that disputes and differences had

    arisen between Tata and Docomo, which were subject matter of an international

    commercial arbitration, which culminated into an award of damages against Tata

    for an amount of US$ 1,172,137,717. The award liability was not discharged by

    Tata, consequent thereto, Docomo initiated recovery proceedings, which were in

    the nature of execution of the arbitral award by filing proceedings before UK and

    US Courts. Also, Docomo filed proceedings before the Delhi High Court

    invoking the provisions of Sections 44, 46, 47 and 49 of the ACA read with the

    provisions of Order 21 of the Code of Civil Procedure, 1908 for enforcement and

    execution of the said arbitral award dated 22 June, 2016. Admittedly, in such

    proceedings, Tata expressed its readiness and willingness to deposit the award

    amount with the Delhi High Court. In such proceedings, Tata and Docomo on

    25 February, 2017 sought to place on record the consent terms as arrived

    between the parties, and accordingly prayed for disposal of the

    enforcement/execution petition filed by Docomo in terms of the said settlement.

    The consent terms as entered between the parties were to the following effect:

    “26. The consent terms arrived at between the parties read as under:

    In the interest of putting an end to a dispute that had arisen between
    the Parties and in the public interest of preserving a fair investment
    environment in India, the Parties to the above Petition (“Parties”) submit that
    this Honourable Court be pleased to pass an order in terms of these Consent
    Terms so as to put an end to the issues and differences between the Parties
    relating to the arbitration award dated June 22, 2016 passed by the Arbitral
    Tribunal in London, United Kingdom in LCIA Case No. 152896 (“Award”):

    Page 27 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    1. The Respondent has always been, and remains committed to
    performing its contractual obligations under the Shareholders’ Agreement
    dated March 25, 2009 (“SHA”).

    2. In these circumstances although the Respondent believes it had
    grounds to resist enforcement of the Award as stated in its affidavit dated
    September 01 2016 “filed before this Hon’ble Court, as a gesture of good
    faith and in accordance with the Respondent’s record of adherence to
    contractual commitments that the Respondent has always enjoyed both in
    India and abroad, the Respondent withdraws its objections to the
    enforcement of the Award in India.

    3. The Respondent agrees to the disposition of the amount awarded in
    paragraph 202 of the Award (being the sums of (i) US $ 1,172,137,717, ( ii)
    US $ 65,276,963, (iii) GBP 119,012.59 and JPY 1,067,670,175, and (iv)
    interest at 3.5% per annum compounded with quarterly rests on the amounts
    specified in the foregoing items (1),(ii) and (iii) from 21 days of the date of
    the Award until payment of the said amounts) (“Funds”) in the manner set
    out in paragraph 4 below, and as per the directions of this Hon’ble Court, for
    payment to the petitioner-Tata in satisfaction of the Award in United States
    Dollars to a bank account designated by the petitioner-Tata (“Designated
    Bank Account”), subject to ruling on the objections raised by the Reserve
    Bank of India (“RBI”) in its Application for Intervention in these
    proceedings after hearing RBI. The obligations of the Respondent hereunder
    shall further be subject to (i) receipt of approval of the Competition
    Commission of India and (ii) receipt of the Withholding Tax Certificate (as
    defined hereinafter). The petitioner-Tata will apply to the Indian Income Tax
    authorities to obtain the withholding tax certificate (“Withholding Tax
    Certificate”) in relation to payments under the Award based on which
    Respondent will remit the Funds, after deduction of taxes, if any, to
    Designated Bank Account.

    The petitioner agrees that the amount of Rs. 8450,00,00,000 (Rupees Eight
    Thousand Four Hundred and Fifty Crore Only) along with accrued interest
    which amounts to a total of Rs. 8,730,59,83,623.. (Rupees Eight Thousand.
    Seven Hundred Thirty Crore Fifty Nine Lakh Eighty Three Thousand Six
    Hundred and Twenty Three Only) as on 30 January 2017 (along with any
    further interest which may accrue thereon) (“Deposit”) deposited in this
    Hon’ble Court shall be released in accordance with the procedure prescribed
    in detail in paragraph 4 below. It is clarified that in case there is any
    difference between the Deposit and the Funds as per the Award, then any
    shortfall would be made up by the Respondent to the extent of the shortfall,
    and in case there is any excess amount then the same will get remitted back to
    Respondent, by way of withdrawal or deposit from/into the Interim Account
    by the Respondent, and the deduction of tax, if any, shall be computed and
    withheld on such adjusted amount.

    4. Subject to the ruling and directions of this Honourable Court, as
    provided in paragraph 3 above, the payment of the Funds, after deduction of
    taxes, if any, to the Designated Bank Account and other related actions shall
    be made in the following manner:

    4.1 The Deposit is to be retained by the Registrar of this Hon’ble Court
    till requisite clearance from Competition Commission and the Withholding
    Tax Certificate as mentioned in these consent terms have been obtained.

    Page 28 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    Once the requisite clearances/ certificate have been obtained the Deposit will
    be transferred to an account in the name of the Respondent (“Interim
    Account”).

    4.2 Petitioner will then nominate an Authorised Dealer (“AD”) for
    remittance of Funds after deduction of taxes, if any, to the Designated Bank
    Account.

    4.3 The petitioner undertakes that it shall, simultaneously with the receipt
    of the Funds, after deduction of taxes, if any, in the Designated Bank
    Account, complete the process of debiting its dematerialised accounts of all
    shares of Tata Teleservices Limited (“Shares”) held by the petitioner-Tata and
    have the Shares credited to the. dematerialised accounts of the Respondent
    and/or its nominees and the Respondent shall co-operate with the petitioner-
    Tata for having the Shares credited to the dematerialised accounts of the
    Respondent and/or its nominees and in completing and executing Form
    FCTRS for this purpose.

    4.4 Both Parties will take all actions and provide all documents and
    information as requested by the AD to permit remittance of the Funds, after
    deduction of taxes, if any, to the Designated Bank Account and the credit of
    the Shares to dematerialised accounts of the Respondent and/or its
    nominees.’

    5. In light of the withdrawal of the objections of the Respondent, this
    Honourable Court may be pleased to declare that the Award is enforceable in
    India and shall operate as a deemed decree and this Honourable Court shall
    proceed to execute the same, subject to the ruling on the objections of RBI as
    raised in RBI’s Application for Intervention in these proceedings (and for
    that purpose the Parties agree not to object to the intervention of RBI).

    6. The petitioner* agrees and undertakes that the enforcement of the
    Award in India, and this deemed decree, against the Indian assets of Tata will
    be limited to the monies deposited (along with interest accrued thereon) in
    this Hon’ble Court by the Respondent only so long as Respondent complies
    with its obligation to make up for any difference between the Deposit and
    the Funds in terms of paragraph 3 of these consent terms.

    7. The petitioner undertakes to this Honourable Court that it shall
    suspend proceedings initiated against the Respondent which are currently
    pending in United Kingdom [Claim No.CL-2016-000428 in the High Court
    of Justice, Queen’s Bench Division of the Commercial Court] and in the
    United States of America [Civil Action No. 1:16-cv-7809, in the United
    States District Court, Southern District of New York] for a period 6 months.
    from the date hereof (“Suspension Period”). Upon receipt of the Funds, after
    deduction of taxes, if any, by the petitioner-Tata in the Designated Bank
    Account any time within the Suspension Period as per paragraph 4 above,
    the petitioner-Tata shall unconditionally withdraw all proceedings initiated
    against the Respondent in relation to the SHA and/or the Award, including
    aforementioned proceedings in the United Kingdom and aforementioned
    proceedings in the United States of America within one week thereof. In the
    event of the petitioner-Tata not receiving payment of the Funds, after

    * Petitioner is Docomo
    Tata is respondent

    Page 29 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    deduction of taxes, if any, in the Designated Bank Account of the petitioner-
    Tata within
    the Suspension Period, the petitioner shall be free to pursue the UK and US
    enforcement actions.

    8. The petitioner undertakes to this Honourable Court that it shall not
    initiate any further proceedings in relation to the SHA and/or the Award
    during the Suspension Period, or thereafter, if the Funds, after deduction of
    taxes, if any, are received duringthe Suspension Period.

    9. The Parties agree that upon receipt of the Funds, after deduction of
    taxes, if any, in the Designated Bank Account by the petitioner, and the credit
    of the Shares to dematerialised accounts of the Respondent and/or its
    nominees, as per paragraphs 3 and 4 above, the Award shall stand fully and
    finally satisfied and discharged and that the Parties shall have no outstanding
    claims against each other.

    10. The Parties agree that the Consent Terms as set out hereinabove are
    exhaustive and conclusive, as between the Parties hereto, with respect to the
    issues dealt hereinabove.

    11. The Parties shall co-operate with each other and provide all necessary
    assistance in completing and filing all forms and completing all other
    formalities necessary for completing the payment of the Funds, after
    deduction of taxes, if any, and the credit of the Shares to dematerialised
    accounts of the Respondent and/or its nominees as set out in this order.

    12. The parties shall bear their respective costs in connection with these
    proceedings.”

    (emphasis supplied)

    42. The learned Single Judge of the Delhi High Court passed a final order

    dated 28 April, 2017 on the said enforcement proceedings, whereby the Delhi

    High Court rejected even the intervention as made by the Reserve Bank of India

    (RBI) in the enforcement proceedings of the said arbitral award, when RBI had

    contended that its prior permission would be required for discharge of such

    liability under the award by Tata in favour of Docomo. It was also held that in

    the proceedings for enforcement of the arbitral award, RBI would not have any

    role to play. The Delhi High Court clearly observed that under the arbitral

    award, Docomo was entitled to the sum awarded, which was in the nature of

    damages and not the sale price of the shares and for such reason, special

    Page 30 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    permission to be taken from RBI as asserted, also did not arise. It was held that

    Docomo being awarded damages and not the price of shares, was the clear

    position on record of the arbitral proceedings. It is in these circumstances,

    considering the settled position in law that the parties to a suit, or as the case may

    be, an arbitration, may agree to the method of settlement and accordingly enter

    into a settlement, at the stage of execution of the decree/award, that the Court

    accepted the consent terms, which were held to be not in any manner contrary to

    the Indian law much less opposed to the public policy or void or voidable under

    the Indian Contract Act, 1872. The relevant observations as made by the Delhi

    High Court are imperative to be noted, which read thus:

    “43. The very stand that RBI is now taking in this Court that without its
    special permission there cannot be a transfer of monies by Tata to Docomo,
    was taken by Tata before the AT and was expressly negatived by the AT by a
    unanimous Award. The AT decided that since the sum awarded to Docomo
    was in the nature of damages and not the Sale Price of the shares the question
    of having to seek the special permission of RBI did not arise If, enforcement
    of the Award, and the Court finds no impediment to its enforcement, then the
    Award which takes a view on the requirement of RBI’s permission will be
    enforceable as such. RBI will be bound by such determination and cannot
    refuse permission.

    44. To repeat, the AT has come to a definite conclusion that what has been
    awarded to Docomo is damages. It has given effect to the alternative
    mechanism envisaged by the parties under Clause 5.7.2 of the SHA. It is not
    even RBI’s stand that any general or special permission of RBI would be
    required if what is being paid by Tata to Docomo is in the nature of
    damages. ……

    50. The Award is very clear on this issue. What was awarded to Docomo were
    damages and not the price of the shares. The order that that the share script
    must be returned to Tata was only incidental and, in fact, Docomo itself was
    not interested in retaining the share scrips. It could be seen as an
    acknowledgment of Docomo volunteering to return the share scrips as they
    were of no particular use to it. It is not open to RBI to re-characterise the
    nature of the payment in terms of the Award to which there is no longer any
    opposition from Tata, the only party which could possibly oppose its
    enforcement. RBI has not placed before the Court any requirement for any
    permission of RBI having to be obtained for Docomo to receive the money as
    damages in terms of the Award.

    …..

    Page 31 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    61. The Court next proposes to examine if the compromise/consent
    terms arrived at between the parties are lawful or whether they are void or
    voidable under the ICA. The Consent Terms were entered into between
    Docomo and Tata on 20/23 February 2017. They begin by noting that it is
    with a view to putting an end to their disputes and “in the public interest of
    preserving a fair investment environment in India” that the parties have
    decided to enter into the said consent terms. Further, it is noted that “as a
    gesture of good faith and in accordance with the Respondent’s record of
    adherence to contractual commitments that the Respondent has always
    enjoyed both in India and abroad, the Respondent withdraws its objections to
    the enforcement of the Award in India.”

    62. A perusal of paras 3 to 6 of the consent terms shows that the parties
    have undertaken to abide by the directions of this Court and obtain all the
    requisite statutory permissions and clearances. Another important aspect is
    that Docomo has in para 7 of the consent terms undertaken that for a period
    of six months pending compliance with the consent terms, all other
    enforcement actions instituted in Courts abroad shall stand suspended and
    after compliance shall stand withdrawn.

    63. The Court is unable to find anything in the Consent Terms which
    can be said to be contrary to any provision of Indian law much less opposed to
    public policy or void or voidable under the ICA. The issue of an Indian entity
    honouring its commitment under a contract with a foreign entity which was
    not entered into under any duress or coercion will have a bearing on its
    goodwill and reputation in the international arena. It will indubitably have an
    impact on the foreign direct investment inflows and the strategic relationship
    between the countries where the parties to a contract are located. These too
    are factors that have to be kept in view when examining whether the
    enforcement of the Award would be consistent with the public
    policy of India.

    64. It appears to be a well settled legal position that parties to a suit, or as
    in this case, an Award, may enter into a settlement even at the stage of
    execution of the decree or Award. In The Oudh Commercial Bank Ltd. v.
    Thakurain Bind Bist Kuer (1939) 41 Bom LR 708, the Privy Council held
    that independent of Order XXIII Rule 3 CPC, the provisions of Order XXI
    Rule 2 and Section 47 CPC would enable the executing Court to record and
    enforce a compromise. This was reiterated by the Supreme Court of India in
    Moti Lal Banker v. Mahraj Kumar Mahmood Hasan Khan AIR 1968 SC
    1087.
    In N.K. Rajgarhia v. Mahavir Plantation Ltd. & Ors. (2006) I SCC 502,
    it was observed that “the court’s freedom to act to further the ends ofjustice
    would surely not stand curtailed.” The Court came to the conclusion that the
    compromise entered into between the parties during the execution
    proceedings was valid in law.

    Conclusion

    65. The result is that:

    (i) IA No. 14897/2016 filed by RBI is dismissed.

    (ii) IA No. 2585 of 2017 is allowed and the Consent Terms enclosed
    therewith are taken on record.

    Page 32 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    (iii)The Award dated 22″ June 2016 passed by the AT in London in Case No.
    152896 under the LCIA Rules is declared as enforceable in India and shall
    operate as a deemed decree of this Court .

    (iii) The parties are bound by the Consent Terms and will proceed to take
    steps in terms thereof.

    (iv) The monies deposited in this Court by Tata by way of the FDRs referred
    to in para 22 of this order together with the interest accrued thereon (‘the
    Deposit’) shall be retained by the Registrar of this Court till requisite
    clearance from the Competition Commission of India and the Withholding
    Tax Certificate as mentioned in the Consent Terms have been obtained.

    (v) Once the requisite clearances/certificate has been obtained, the Deposit
    will be transferred to an account in the name of Tata (‘Interim Account’). For
    this purpose, the parties are at liberty to mention the matter before the
    Registrar General of this Court who will from that point onwards either
    himself deal with the matter or designate a Registrar of this Court for the
    purpose of the completion of the further steps in terms of this judgment.

    (vi) Docomo will nominate an Authorised Dealer (‘AD’) for remittance of
    Funds after deduction of taxes, if any, to the Designated Bank Account as
    stated in the Consent Terms.

    (vii) As undertaken by it in the Consent Terms, Tata shall, simultaneously
    with the receipt of the Funds, after deduction of taxes, if any, in the
    Designated Bank Account, complete the process of debiting its dematerialised
    accounts of all shares of TTSL held by Docomo and have the Shares credited
    to the dematerialised accounts of Tata and/or its nominees and Tata shall co-
    operate with Docomo for having the Shares credited to the dematerialised
    accounts of Tata and/or its nominees and in completing and executing Form
    FCTRS for this purpose.

    (viii) Both, Tata and Docomo will take all actions and provide all documents
    and information as requested by the AD to permit remittance of the Funds,
    after deduction of taxes, if any, to the Designated Bank Account and the credit
    of the Shares to dematerialised accounts of Tata and/or its nominees.

    (ix) Docomo is bound by its undertaking as recorded in para 7 of the Consent
    Terms regarding keeping the other enforcement proceedings instituted by it
    against Tata elsewhere under suspension and to ultimately withdraw them
    subject to compliance by Tata with its obligations under the Consent Terms.
    Docomo is also bound by its undertaking that it shall not initiate any further
    proceedings in relation to the SHA and/or the Award during the Suspension
    Period, or thereafter, if the Funds, after deduction of taxes, if any, are received
    during the Suspension Period.

    (x) Upon receipt of the Funds, after deduction of taxes, if any, in the
    Designated Bank Account by Docomo, and the credit of the Shares to
    dematerialised accounts of Tata and/or its nominees, as per paragraphs 3 and
    4 of the Consent Terms, the Award shall stand fully and finally satisfied and
    discharged and that the Parties shall have no outstanding claims against each
    other.

    Page 33 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    66. Liberty is granted to both Tata and Docomo to apply to the Court in the
    event of any difficulty in complying with any of the directions.

    67. The petition is disposed of in the above terms.”

    (emphasis supplied)

    43. On the aforesaid backdrop, we now proceed to examine the question

    posed for consideration.

    44. As noted hereinabove, on 28 September, 2022, respondent no. 3-

    Additional Director, DGGI issued an intimation of tax ascertained and alleged to

    be payable by Tata under section 73(5)/74(5) of the CGST Act, 2017 read with

    Rule 142(1A) of CGST Rules, 2017. Being the foundation for the subsequent

    actions as impugned, it is necessary to note the premise/ground on the basis of

    which intimation of tax ascertained was issued to Tata, which is as follows:

    (i) At the outset, it is stated that the amount of tax/ interest/penalty

    payable by Tata under section 74(5) of the CGST Act was ascertained in

    terms of the available information, as under:

                                   Act                      Period                   Tax
    
                        IGST Act                           2017-18            15,24,35,20,405
                        Total                                                 15,24,35,20,405
    
    
                The grounds and qualification are attached              to such demand, which
    
    

    recorded that “M/s. Tata Sons Private Limited had not paid GST on

    damages amount of $117,21,37,717 paid to Docomo under the

    Arbitration Award of the London Court of International Arbitration

    (LCIA) dated 22 June, 2016 and upheld by the Delhi High Court on 28

    April, 2017”.

    Page 34 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    (ii) A detailed reference to the dispute in the arbitral proceedings has

    been set out leading to the Arbitral Tribunal (LCIA) awarding the

    damages of US$117,21,37,717 and Docomo approaching the Delhi High

    Court and Tata informing the Delhi High Court of its readiness and

    willingness to deposit an amount of Rs.8450 crores with the Registrar

    General of the Delhi High Court and ultimately the parties filing consent

    terms (supra). It is recorded that in such context, all the parties arrived at

    a settlement of the arbitral award, and thereafter the department recorded

    the statements of Mr. Eruch N. Kapadia, CFO of Tata and Mr. Sanjeev

    Mehra, GM-Corporate Taxation of TTSL, purportedly stated to be

    statements in the course of investigation. The following conclusions were

    accordingly derived:

    “3.9 On the basis of the investigation conducted as per the directives
    contained in the Office Memorandum dated 21.02.2018 issued by
    CBEC, GST Policy wing, Government of India vide F.No.
    349/168/2017-GST-Pt.I/314 dated 21.02.2018 it is revealed as under:

    1. It appears that DoCoMo had tolerated the act of breach
    of the conditions laid down in the Agreement by and between
    TSL, DoCoMo & TTSL against which DoCoMo received
    consideration in the form of damages from TSL.

    2. The location of the supplier, ie. DoCoMo, shall be its
    usual place of residence, under Section 2(15) of the IGST Act,
    2017. Since the company is incorporated in Japan, the location of
    the supplier will therefore be outside India. The location of the
    recipient of the supply, i.e. TSL is in India. Therefore, to determine
    the place of supply of this service, Section 13 of the IGST Act,
    2017 will have to be referred. Sub-section (2) of Section 13 ibid
    states that the place of supply of services, except the services
    specified in sub-sections (3) to (13) of the said section, shall be the
    location of the recipient of the service. Since the supply of service
    viz. “agreeing to the obligation to refrain from an act, or to tolerate
    an act or a situation, or to do an act”, as specified in Schedule II of
    the CGST Act, 2017
    , is not covered under sub-sections (3) to (13)
    of Section 13 of the IGST Act, the place of supply in respect to
    such service shall be the location of the recipient of the service, i.e.
    TSL and since the location of the supplier of service is outside

    Page 35 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    India and location of the recipient of the service is in India and the
    place of supply of service is in India, the said service shall be
    considered to be an import of service under sub-section (11) of
    Section 2 of the IGST Act, 2017.

    3. As per sub-section (4) of Section 7 of the IGST Act,
    2017, supply of services imported into the territory of India shall
    be treated to be a supply of service in the course of inter-state trade
    or commerce. Accordingly, as per sub-section (1) of Section 5 of
    the IGST Act, 2017, IGST is liable on such a supply. Vide
    Notification 10/2017-Integrated Tax (Rate) dated 28.06.2017, the
    Central Government, in exercise of powers conferred by sub-

    section (3) of section 5 of the IGST Act, 2017, has notified that on
    any service supplied by any person who is located in a non-taxable
    territory to any person other than non-taxable online recipient, the
    whole of integrated tax, leviable under section 5 of IGST Act shall
    be paid on reverse charge basis by the recipient.

    4. The name of the M/s. Tata Sons Limited changed to M/s.
    Tata Sons Private Limited with effect from 06-08-2018.

    3.10. In view of the above, as per the Arbitration Award of London
    Court of International Arbitration dated 22-06-2016 and upheld by the
    Delhi High Court on 28-04-2017 M/s. Tata Sons Private Limited have
    made total payment of Rs.84,68,62,24,473/- to M/s. NTT DoCoMo as
    damage amount.

    Details of the payments made:

                       Sr.       Particulars         Payment on      Payment on       Grant Total
                       No.                           30.10.2017      07.11.2017         (INR)
                        1    Damages               75,91,99,04,381   16,63,46,811 76,08,62,51,192
                        2    Interest               7,95,62,82,019                    7,95,62,82,019
                        3    Legal Costs               2,87,20,509   60,48,98,147      63,36,18,656
                        4    Arbitration Costs                        1,00,72,606       1,00,72,606
                                                   83,90,49,06,909   78,13,17,564 84,68,62,24,473
    
    

    Accordingly, rendering M/s. Tata Sons Private Limited liable to pay
    IGST amounting to Rs.15,24,35,20,405/- (Rupees One Thousand
    Five Hundred Twenty-Four Crore Thirty-Five Lakh Twenty
    Thousand Four Hundred Five).”

    (emphasis supplied)

    45. The aforesaid conclusion was stated to be the implication which was

    brought about by the provisions of Section 7(1)(c) read with sub-section (1A)

    and Schedule II to Entry 5(e) of the CGST Act, which defines “supply” to include

    the activity specified in Schedule I, made or agreed to be made without

    Page 36 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    consideration and that under sub-section (1A) ” where certain activities or

    transactions constitute a supply in accordance with the provisions of sub-section

    (1), they shall be treated either as supply of goods or supply of services as referred

    to in Schedule II”, as Schedule II in Entry 5(e) treats supply of services to a party

    “agreeing to the obligation to refrain from an act, or to tolerate an act or a

    situation, or to do an act.”

    46. Based on these provisions, the impugned intimation in paragraph 4.1 (b)

    to (e) inter alia recorded that it clearly appeared that the settlement of the arbitral

    award constituted supply in accordance with the provisions of sub-section (1) of

    Section 7 as referred to in Entry 5(e) of Schedule II. It was further recorded that

    Docomo, as part of the joint consent application filed before the Delhi High

    Court, had agreed to suspend and later withdraw its enforcement proceedings

    which it had initiated in the Courts in the UK and the US, threatening to attach

    properties of Tata’s global companies like Jaguar, Land Rover and Tata Steel

    Europe and agreeing not to initiate any further proceedings in relation to the

    Shareholder Agreement (SHA) and/or under the award in question. This is stated

    to be appearing to be an activity in the nature of agreeing to an obligation of

    refraining from an act; the act being of continuing with the proceedings initiated

    against Tata, in relation to the execution proceedings which were pending in UK

    and US Courts. It was further recorded that the act of Docomo also appeared to

    be one of tolerance with respect to the breach of the SHA by Tata. Such

    statements, as recorded in asserting the charge against Tata as set out in the said

    ‘Intimation of Tax Ascertained’, being payable and issued under 73(5)/74(5)

    Page 37 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    need to be noted, which read thus:

    “4.1 Provision of Supply:

    …..

    (b) From the above, it can be seen that sub-section (1A) of Section 7 of
    the CGST Act, 2017 which stated where certain activities or transactions
    constitute a supply in accordance with the provisions of sub-section (1), they
    shall be treated either as supply of goods or supply of services as referred to in
    Schedule II. However, clause 5(e) of Schedule II, specifies that ‘agreeing to the
    obligation to refrain from an act, or to tolerate an act or a situation, or to do an
    act,’ as supply of service. Section 7(1) states that for the purposes of this Act,
    the expression “supply” includes-(a) all forms of supply of goods or services or
    both such as sale, transfer, barter, exchange, license, rental, lease or disposal
    made or agreed to be made for a consideration by a person in the course or
    furtherance of business; (b) import of services for a consideration whether or
    not in the course or furtherance of business. However, Section 7(1A) states
    that where certain activities or transactions constitute a supply in accordance
    with the provisions of sub-section (1), they shall be treated either as supply of
    goods or supply of services as referred to in Schedule II.

    (c) In the instant case, DoCoMo, as part of its joint consent application
    filled in the Hon’ble High Court of Delhi, has agreed to suspend and later
    withdraw its enforcement proceedings which it had initiated the courts in the
    UK and the US, threatening to attach properties of Tata’s global companies
    like Jaguar Land Rover and Tata Steel Europe. It has also agreed not to initiate
    any further proceedings in relation to the SHA and/or the Award. This appears
    to be an activity in the nature of agreeing to an obligation of refraining from an
    act; the act here being that of continuing with the proceedings initiated against
    Tata which are currently pending in UK and in the US. DoCoMo has also
    agreed in the consent application to refrain from initiating any further
    proceedings against Tata in relation to the SHA and/or the Award.

    (d) Further, the act of DoCoMo also appears to be one of tolerance with
    respect to the breach of the SHA by Tata. The Arbitral Tribunal’s ruling,
    which has now been enforced by the Delhi High Court, is categorical in stating
    that Tata has committed breach of contract and is liable to pay damages to
    DoCoMo. These damages appear to be in the nature of consideration for
    supply of service, from DoCoMo to TTSL, of tolerating the said breach.

    (e) It appears from the discussion in para (c) and (d) above that DoCoMo
    is making a supply of Tata Teleservices (TTSL), as per the definition of supply
    in Section 7 of CGST Act, 2017.”

    (emphasis supplied)

    47. Referring to the provisions of Section 13 of the IGST Act, 2017 which

    defines “Place of supply of services where location of supplier or location of

    recipient is outside India” as also, referring to the provisions of Section 2(11) of

    IGST Act defining “import of services” and Section 7(4) of IGST Act defining

    Page 38 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    “Supply of services imported into the territory of India, shall be treated to be a

    supply of services in the course of inter-State trade or commerce “, it was sought

    to be concluded that, in the facts of the case, since the location of the supplier of

    service (Docomo) was outside India and the location of the recipient of the

    service was in India and the place of supply of service was also in India, such

    service shall be considered to be an import of service under Section 2(11) of the

    IGST Act, 2017. Further a reference to Notification 10/2017 issued by the

    Central Government was incorporated to record that in exercise of powers

    conferred by sub-section (3) of Section 5 of the IGST Act, the Central

    Government had notified that on any service supplied by any person who is

    located in a non-taxable territory to any person other than non-taxable online

    recipient, the whole of integrated tax, leviable under section 5 of IGST Act shall

    be paid on reverse charge basis by the recipient. It is hence concluded that the

    Tata is required to discharge the IGST liability on such alleged supply. The

    relevant contents of the Intimation in that regard also need to be noted, which

    read thus:

    “4.2 Nature of the Supply and Taxation:

    …..

    b) The location of the supplier, ie. DoCoMo, shall be its usual place of
    residence, under Section 2(15) of the IGST Act, 2017. Since the company is
    incorporated in Japan, the location of the supplier will therefore be outside
    India. The location of the recipient of the supply, i.e. TTSL is in India.

    Therefore, to determine the place of supply of this service, Section 13 of the
    IGST Act, 2017 will have to be referred. Sub-section (2) of the said section
    states that the place of supply of services, except the services specified in sub-
    sections (3) to (13) of the said section, shall be the location of the recipient of
    the service. Since the service of agreeing to the obligation to refrain from an
    act, or to tolerate an act or a situation, or to do an act, as specified in Schedule
    II of the CGST Act, 2017
    , is not covered under sub-sections (3) to (13) of
    Section 13 of the IGST Act, the place of supply in respect to such service shall

    Page 39 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    be the location of the recipient of the service, Le. TTSL, further, since the
    location of the supplier of service is outside India, the location of the recipient
    of the service is in India and the place of supply of service is in India, the said
    service shall be considered to be an import of service under sub-section (11) of
    Section 2 of the IGST Act, 2017.

    (c) As per sub-section (4) of Section 7 of the IGST Act, 2017, supply of
    services imported into the territory of India shall be treated to be a supply of
    service in the course of inter-state trade or commerce. Accordingly, as per sub-
    section (1) of Section 5 of the IGST Act, 2017, IGST is liable on such a supply.

    4.3. Vide Notification 10/2017-Integrated Tax (Rate) dated 28.06.2017, the
    Central Government, in exercise of powers conferred by sub-section (3) of
    section 5 of the IGST Act, 2017, has notified that on any service supplied by
    any person who is located in a non-taxable territory to any person other than
    non-taxable online recipient, the whole of integrated tax, leviable under
    section 5 of IGST Act shall be paid on reverse charge basis by the recipient.
    Therefore, it appears that TSPL is required to discharge the IGST liability on
    the above mentioned supply.”

    (emphasis supplied)

    48. The Intimation further records that the time of supply of the alleged

    services would be as provided for in Section 13(3) of the CGST Act, 2017. The

    relevant contents in that regard are required to be noted, which read thus:

    ” 4.4. The time of supply

    (a) As per sub-section (3) of Section 13 of the CGST Act, 2017: Time of
    supply of services

    “(3) In case of supplies in respect of which tax is paid or liable to be paid on
    reverse charge basis, the time of supply shall be the earlier of the following
    dates, namely:

    (a) the date of payment as entered in the books of account of the
    recipient or the date on which the payment is debited in his bank
    account, whichever is earlier, or

    (b) the date immediately following sixty days from the date of issue of
    invoice or other document, by whatever name called, in lieu thereof by
    the supplier: any

    Provided that where it is not possible to determine the time of supply
    under clause (a) or clause (b), the time of supply shall be the date of entry
    in the books of account of the recipient of supply:

    Provided further that in case of supply by associated enterprises, where
    the supplier of service is located outside India, the time of supply shall be
    the date of entry in the books of account of the recipient of supply or the

    Page 40 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    date of payment, whichever is earlier.”

    (b) As regarding the time of supply, since the tax is liable to be paid on
    reverse charge basis, the time of supply shall be determined in accordance with
    sub-section (3) of Section 13 of the CGST Act, 2017. The said sub-section
    states that in case of supplies in respect of which tax is paid or liable to be paid
    on reverse charge basis, the time of supply shall be the earlier of the date of
    payment and the date immediately following sixty days from the date of issue
    of invoice. The date of payment has been defined as the date of payment, as
    entered in the books of accounts of the recipient or the date, on which the
    payment is debited in his bank account, whichever is earlier. In the instant
    case, since the concept of issuance of an invoice is not applicable, the date of
    payment shall be the time of supply of the service.

    (c) As per para 4 of the terms of consent, jointly submitted by the
    petitioner-Tata and the respondent, the deposit (in the form of fixed deposit
    receipts) is to be retained by the Registrar of Delhi High Court till requisite
    clearance from Competition Commission and Withholding Tax Certificates
    from Income Tax Authorities are obtained. Once the requisite
    clearance/certificate has been obtained, the deposit will be transferred to an
    account in the name of the Respondent (ie. DoCoMo). Therefore, it appears
    that the date on which the amount, as specified in para 3 of the terms of
    consent, is debited from the bank account(s) of TTSL. shall be the time of
    supply of the service.

    (emphasis supplied)

    49. On the aforesaid basis, it was asserted that Tata was liable to pay IGST

    amounting to Rs.15,24,35,20,405/- on the payments made by Tata to Docomo

    amounting to Rs.84,68,62,24,473/- and the same is recoverable from Tata in

    terms of Section 74(1) of the CGST Act. Accordingly, Tata was called upon to

    pay the amount of tax as ascertained along with the amount of applicable interest

    and penalty under Section 74(5) of the CGST Act by 6 October, 2022, failing

    which, a show cause notice shall be issued under Section 74(1) of the CGST Act.

    Also, it was recorded that in case Tata wishes to file any submissions against the

    above ascertained, the same be furnished by 6 October, 2022. The relevant

    extract in such context are required to be noted, which read thus:

    “5. Accordingly, M/s Tata Sons Private Ltd. is liable to pay IGST amounting to
    Rs.15,24,35,20,405/- (Rupees One Thousand Five Hundred Twenty-Four
    Crore Thirty-Five Lakh Twenty Thousand Four Hundred Five only) on the

    Page 41 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    payments made by M/s. Tata Sons Private Limited to M/s. NTT DoCoMo
    amounting to Rs.84,68,62,24,473/- (Rupees Eight Thousand Four Hundred
    Sixty-Eight Crore Sixty-Two Lakhs Twenty-Four Thousand Four Hundred
    only) and the same is recoverable from them in terms of Section 74(1) of the
    Central Goods and Services Tax Act, 2017 read with Section 20 of the
    Integrated Goods and Services Tax Act, 2017, by invoking the extended
    period of limitation, along with interest, as applicable, under Section 50 of the
    said Act and penalty as per Section 74 of the CGST Act, 2017.”

    You are hereby advised to pay the amount of tax as ascertained above along
    with the amount of applicable interest and penalty under Section 74(5) of the
    CGST Act, 2017 by 06/10/2022, failing which Show Cause Notice will be
    issued under Section 74(1) of the CGST Act, 2017.

    In case you wish to file any submissions against the above ascertained, the
    same may be furnished by 06/10/2022 In Part B of this form .”

    50. Such intimation was responded by Tata by its letter dated 6 October, 2022

    addressed to respondent no. 3-Additional Director, DGGI inter alia recording

    that the same was received on a weekend/festive holiday and an additional time

    of 30 days would be required to make an appropriate response. By further letter

    dated 12 October, 2022, Office Memorandum dated 21 February, 2018 as

    referred to in paragraph 3.9 of the copy of intimation was requested while

    denying the contents of the intimation. Further, it was stated that Tata’s request

    as made by letter dated 12 October, 2022 not being responded which was stated

    to have been again reiterated and recorded in its further letter dated 2 November,

    2022.

    51. On such backdrop, Tata approached this Court by filing the present

    petition in assailing the intimation. On the present proceedings on 30 March,

    2023 an order came to be passed, wherein this Court recorded a statement on

    behalf of the revenue that if the petitioner-Tata, appears before the proper officer,

    pursuant to the intimation for a pre-show cause consultation, and places before

    Page 42 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    the concerned authority its stand, based on the Circulars and other grounds taken

    in the petition, the concerned authority will look into the same as per Section 74

    of the CGST Act and inform the petitioner-Tata the outcome by communication

    in writing.

    52. Tata, in its reply dated 31 May 2023 to the impugned intimation dated 28

    September 2022, contended that –

    (i) The demand of GST on damages paid to Docomo under the arbitral

    award whose validity and enforceability was confirmed by the Delhi High

    Court, was illegal and contrary to CBIC Circular No. 178/10/2022-GST

    dated 3 August 2022, which clarified that damages for breach of contract

    do not fall within Schedule II Entry 5(e) of the CGST Act and are not

    consideration for supply; this position was reiterated in Circular No.

    214/1/2023 dated 28 February 2023 clarifying that even under the pre-

    GST regime no service tax was leviable on such damages; Tata further

    recorded that CBIC had relied on CESTAT decisions holding no such tax

    was leviable, chose not to appeal adverse decisions, and withdrew pending

    Supreme Court appeals, treating proceedings as closed; hence, such

    circulars being binding on the Additional Director, the intimation was

    liable to be withdrawn.

    (ii) Tata contended that once a decision is taken in favour of an assessee, it

    must be extended to all similarly placed assessees. In such context,

    reliance was placed on the decision in India Cements Ltd. v CCE14 and

    14 (1989) 2 SCC 676

    Page 43 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    Simplex Castings v. CCE15, wherein it was held that no appeal can be filed

    contrary to CBIC circulars; hence, if an appeal cannot be filed, even a

    show cause notice cannot be issued, and the department cannot selectively

    demand duty from one assessee while dropping it for others. It was further

    contended that the department cannot take a stand contrary to its own

    circulars, while placing reliance on the decision in CCE vs. Tikatar

    Industries16, which held that once orders have attained finality, the

    Revenue cannot accept such decisions in one case and challenge them in

    another. Further, in such context, reliance was also placed on the decision

    in CCE v Amar Bitumen and Allied Products Private Ltd.17.

    (iii) Without prejudice to the aforesaid, Tata submitted that the

    impugned intimation was liable to be withdrawn not only in view of the

    circulars but also as it lacked legal and jurisdictional basis, being founded

    on a perverse appreciation of facts also relying on CBIC Office

    Memorandum dated 21 February 2018 to contend that a pre-determined

    view was seen when the intimation recorded that IGST is payable, thereby

    rendering adjudication by DGGI (a subordinate authority bound by

    CBIC) a futile and premeditated exercise. It was further contended that

    whether the payment of damages constitutes “service” under Entry 5(e) of

    Schedule II and consequently “supply” under Section 7 of the CGST Act

    was the foundational jurisdictional fact. They placed reliance on the

    15 (2003) 5 SCC 528
    16 (2010) 13 SCC 73
    17 (2010) 13 SCC 76

    Page 44 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    decision of the Supreme Court in Arun Kumar & Ors vs. UOI18 and Raza

    Textiles Ltd. vs. Income tax Officer, Rampur 19, which according to Tata

    would support its contention that unless such determination is made,

    jurisdiction to levy GST on damages awarded under the arbitral award for

    breach of the Shareholders Agreement dated 25 March 2009 cannot be

    assumed.

    (iv) The Circular dated 3 August 2022 (paras 6 and 7.1.5) conclusively

    clarified that taxability under Entry 5(e) requires two essential elements:

    (i) an independent contract to refrain from or tolerate an act, and (ii)

    consideration for such act. It was contended that in the present case no

    independent contract existed whereby Docomo agreed to withdraw

    proceedings for consideration, making the allegation of “supply”

    erroneous; the circular clarified that toleration must arise from an

    independent agreement for consideration, whereas breach of contract

    merely gives rise to compensation for loss; the damages awarded by the

    arbitral tribunal and upheld by the Delhi High Court were compensation

    for breach and not consideration for any independent activity, and were

    paid because Docomo did not tolerate the breach. It was contended that

    the decisions of the CESTAT under Section 66E(e) of the Finance Act,

    1994 in M/s South Eastern Coal Fields Ltd v. Commissioner of Central

    Excise And Service Tax, Raipur20; Western Coalfields Ltd vs.

    18 (2007) 1 SCC 732
    19 (1973) 1 SCC 633
    20 2020(12) TMI 912

    Page 45 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    Commissioner of CGST & Central Excise 21 and Dy. GM (Finance),

    Bharat Heavy Electricals Ltd. vs. Commissioner of Customs& Central

    Excise, Bhopal22 had held that no service tax is leviable on such damages,

    which position has been accepted by CBIC and applies equally under

    GST.

    (v) Tata contended that the impugned demand was unsustainable as the

    primary condition for levy of GST, namely that the activity must qualify as

    “supply” under Section 7 of the CGST Act, was absent, since for an act to

    constitute supply of service it must be made or agreed to be made for

    consideration with a sufficient nexus between the activity and the

    consideration, as reflected in Schedule II, which was not satisfied in the

    case of payment pursuant to an arbitral award. Referring to Entry 5(e) of

    Schedule II, it was contended that there must be a positive agreement

    whereby one party agrees to refrain from an act or to tolerate an act in

    return for consideration, implying voluntary relinquishment of a

    contractual or statutory right or consensual toleration by a person who

    otherwise has the right to resist such act, whereas a party with such rights

    may instead enforce them and seek specific performance or damages. It

    was contended that the department’s case that Docomo, under consent

    terms before the Delhi High Court, agreed to withdraw enforcement

    proceedings in the UK and US and not initiate further proceedings,

    thereby tolerating breach, was wholly unfounded, as Docomo initiated

    21 2022 (9) TMI 741
    22 2022(9) TMI 1005

    Page 46 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    enforcement proceedings only to realise the damages awarded by the

    arbitral tribunal, and once payment was agreed and made by Tata, there

    was no reason or locus for Docomo to continue or initiate proceedings in

    India, UK, or US. Thus, Docomo’s agreement not to pursue further

    proceedings was merely to bring finality to the dispute with no separate

    ascribable value to it.

    (vi) That Docomo’s agreement to withdraw proceedings did not constitute

    a separate supply of service but was only a condition for complete

    settlement upon payment of compensation. The conclusion that damages

    were paid in consideration of withdrawal of proceedings was

    fundamentally erroneous, as withdrawal was merely consequential. The

    payment of damages had no nexus with withdrawal and did not fall within

    Entry 5(e). Further, Docomo did not tolerate breach but enforced its

    rights fully, obtained an arbitral award, pursued enforcement, and only

    after satisfaction of the decree upon payment by Tata, did the proceedings

    come to an end, which cannot be construed as toleration of an act.

    (vii) Referring to Section 73 of the Indian Contract Act, Tata contended

    that compensation for loss or damages caused by breach of contract is a

    statutory entitlement of the aggrieved party, and in cases of failure to

    discharge obligations resembling those created by contract, the injured

    party is entitled to receive the same compensation from the party in

    default as if such party had contracted to discharge it and had broken the

    contract. It was hence contended that payment of compensation to the

    Page 47 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    aggrieved party does not imply any positive act of toleration of breach, and

    acceptance of damages cannot be construed as tolerating an act.

    Accordingly, the payment of damages by Tata to Docomo does not fall

    within the scope of Entry 5(e) of Schedule II of the CGST Act, and the

    impugned intimation suffered from a fundamental error in invoking GST

    provisions when the alleged activity does not qualify as “service” or

    “supply”; hence, the demand is contrary to the CGST Act and violative of

    Article 14 of the Constitution. On such proposition, Tata placed reliance

    on the decision of this Court in Bai Mamubai Trust vs. Suchitra23.

    (viii) Tata next contended that Section 74 of the CGST Act, which applies

    to cases involving fraud, willful misstatement, or suppression of facts, was

    inapplicable in the present case, as none of these elements were attracted,

    since the payments made were pursuant to judicial orders and proceedings

    before the Delhi High Court and the department was fully aware of all

    material facts even prior to remittance being made by Tata to Docomo. It

    was thus contended that the allegations of fraud, suppression, or willful

    misstatement were unfounded and unsustainable in law, particularly as the

    department itself had conducted an inquiry for levy of service tax from

    2017 and only in 2022 changed its view to contend that GST, and not

    service tax, was leviable on the said payment, thereby negating any basis

    for such allegations.

    53. On the aforesaid backdrop, a personal hearing was held on 16 June 2023.

    23 2019 (31) GSTL 193

    Page 48 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    However, the department did not accept Tata’s case and consequentially the

    impugned show cause notice was issued by respondent No.4-Joint Director,

    Directorate General of GST Intelligence, Zonal Unit Mumbai, calling upon the

    petitioner-Tata to show cause as to why IGST amounting to

    Rs.15,24,35,20,405/- (Rupees One Thousand Five Hundred Twenty-Four Crore

    Thirty-Five Lakh Twenty Services Tax Act, 2017) should not be demanded from

    Tata under Section 74(1) of the CGST Act read with Section 20 of the IGST Act,

    along with interest and penalty, which is impugned in the present petition.

    54. On perusal of the impugned show cause notice, it appears that the basis on

    which the impugned demand has been made in the show cause notice, is not on

    the grounds different from what was set out in the impugned intimation dated 8

    September 2022 (supra) which is clear from the following contents of the show

    cause notice:-

    “(b) From the above, it can be seen that sub-section (1A) of Section 7 of the
    CGST Act, 2017 which stated where certain activities or transactions constitute
    a supply in accordance with the provisions of sub-section (1), they shall be
    treated either as supply of goods or supply of services as referred to in Schedule
    II. However, clause S(e) of Schedule IL, specifies that ‘agreeing to the
    obligation to refrain from an act, or to tolerate an act or a situation, or to do an
    act, as supply of service. Section 7(1) states that for the purposes of this Act, the
    expression “supply” Includes-(a) all forms of supply of goods or services or
    both such as sale, transfer, barter, exchange, license, rental, lease or disposal
    made or agreed to be made for a consideration by a person in the course or
    furtherance of business; (b) import of services for a consideration whether or
    not in the course or furtherance of business. Section 7(1A) states that where
    certain activities or transactions constitute a supply in accordance with the
    provisions of sub-section (1), they shall be treated either as supply of goods or
    supply of services as referred to in Schedule II.

    (c) In the Instant case, DOCOMO, as part of its joint consent application
    filed in the Hon’ble High Court of Delhi, agreed to suspend and later withdraw
    its enforcement proceedings which it had initiated in the courts in the UK and
    the US, threatening to attach properties of Tata’s global companies like Jaguar
    Land Rover and Tata Steel Europe. The act here being that of not continuing
    with the proceedings initiated against Tata which were currently pending In

    Page 49 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    UK and in the US. The act of DOCOMO also appears to be one of tolerance
    with respect to the breach of the SHA by TSPL & others. Thus, from the above
    it appears to be an activity agreeing to an obligation of refraining from an act,
    the act here being that of not continuing with the proceedings initiated against
    Tata which were pending in UK and in the US. The activity is thus, not in the
    nature of only tolerating the breach of contract as referred by TSPL.

    Supply of service (As per Section 7 of the CGST Act, 2017)

    DOCOMO has also agreed in the consent application to refrain from
    Initiating any further proceedings against Tata in relation to the SHA and/or
    the Award. Further, the act of DOCOMO also appears to be one agreeing to
    obligation to refrain from initiating any proceedings i.r.o. SHA and other
    proceedings. The Arbitral Tribunal’s ruling, which has now been enforced by
    the Delhi High Court, is categorical in stating that Tata has committed breach
    of contract and is liable to pay damages to DOCOMO. These damages are in
    the nature of consideration for supply of service, from DOCOMO to TSPL, of
    tolerating the said breach.

    Hence, from the discussion above, it can be seen that DOCOMO is making a
    supply to Tata Sons Pvt. Ltd. (TSPL), as per the definition of supply in Section
    7
    of CGST Act, 2017.

    In view of the above facts, it appears that DOCOMO has rendered the
    supply vide their act of Tolerance of the contractual Defaults by TSPL along
    with agreeing to obligation to refrain from initiating any proceedings and the
    same appears to squarely fall within the ambit of definition of ‘supply’ as
    envisaged under section 7(1A) of the CGST Act, 2017 and the damages
    referred to herein above is the ‘consideration’ paid by TSPL to DOCOMO in
    the course and furtherance of their business. Thus, the sald ‘supply by
    DOCOMO to TSPL would fall within in the ambit of entry no. [e] of Sr. no. 5
    of the Schedule – II to section 7 ibid as “supply of services viz. agreeing to the
    obligation to refrain from an act, or to tolerate an act or a situation, or to do an
    act”.

    (d) Further, the act of DOCOMO also appears to be one of tolerance with
    respect to the breach of the SHA by Tata and agreeing to obligation to refrain
    from initiating any proceedings i.r.o SHA. The Arbitral Tribunal’s ruling,
    which has now been enforced by the Delhi High Court, is categorical in stating
    that Tata has committed breach of contract and is liable to pay damages to
    DOCOMO. These damages appear to be in the nature of consideration for
    supply of service, from DOCOMO to TTSL, of tolerating the said breach.

    “7.5 ……

    It is clear from the consent terms that the petitioner is agreeing to refrain from
    act,ie, DOCOMO will not initiate any further proceedings in relation to the
    SHA and/or the Award during the Suspension Period and agreeing to
    unconditionally withdraw all the proceedings initiated against the Respondent.

    Schedule 11.1

    Page 50 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    11.3.). i] During the course of investigation, it appears that DOCOMO had
    tolerated the act of breach of the conditions laid down in the Agreement by and
    between TSPL, DOCOMO & TTSL against which DOCOMO received
    consideration in the form of damages from TSPL.

    ii). DOCOMO, as part of its joint consent application filed in the Hon’ble
    High Court of Delhi, agreed to suspend and later withdraw its enforcement
    proceedings which it had initiated in the courts in the UK and the US,
    threatening to attach properties of Tata’s global companies like Jaguar Land
    Rover and Tata Steel Europe. The act here being that of not continuing with
    the proceedings initiated against Tata which were pending in UK and in the
    US. The act of DOCOMO also appears to be agreeing to obligations to refrain
    from act of legal proceedings with respect to the breach of the SHA by TSPL &
    others.

    11.4. Thus, from the above it appears to be an activity of agreeing to an
    obligation of refraining from an act; the act here being that of not continuing
    with the proceedings initiated against Tata which were pending in UK and in
    the US. The activity is not only in the nature of tolerating the breach of
    contract as represented by TSPL but it is also the act of DOCOMO which
    appears to be agreeing to obligations to refrain from act of legal proceedings
    with respect to the breach of the SHA by TSPL & others.

    As regards TSPL contention that, the impugned payments constitute
    consideration for another independent contract envisaging tolerating an act or
    situation or refraining from doing an act or situation or simply doing an act is
    considered as “Supply”. In the instant case both the parties agreed and pursuant
    to this DOCOMO, as part of its Joint consent application filed before the
    Hon’ble High Court of Delhi, agreed to suspend and later withdrew its
    enforcement proceedings which it had initiated in the courts in the UK and the
    US, threatening to attach properties of Tata’s global companies like Jaguar Land
    Rover and Tata Steel Europe, thus tolerating/ refraining from doing an act for
    which it received consideration from TSPL and DOCOMO too withdrew its
    objections to the enforcement of Award in India. Thus, it appears to be a case
    of agreeing to the obligation to refrain from an act, or to tolerate an act or a
    situation, or to do an act and the amount paid by TSPL is consideration for
    service.

    In the Instant case, DOCOMO has also agreed in the consent application to
    refrain from initiating any further proceedings against Tata in relation to the
    SHA and/or the Award. Further, the act of DOCOMO also appears to be one
    of tolerance with respect to the breach of the SHA by TSPL & others. The
    Arbitral Tribunal’s ruling, which has now been enforced by the Delhi High
    Court, is categorical in stating that Tata has committed breach of contract and
    is liable to pay damages to DOCOMO. These damages are in the nature of
    consideration for supply of service, from DOCOMO to TSPI, of tolerating the
    said breach.

    From the above facts, it appears that DOCOMO has rendered the supply vide
    their act of toleration and agreeing to obligations to refrain from act of legal
    proceedings to TSPL and the same squarely falls within the ambit of definition
    of ‘supply’ as envisaged under sub-section [1] of section 7 of the CGST Act,
    2017 and the damages referred to herein above is the ‘consideration’ paid by

    Page 51 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    TSPL to DOCOMO in the course and furtherance of their business. Thus, it
    appears that the said ‘supply’ by DOCOMO would fall within in the ambit of
    entry no. [e] of Sr. no. 5 of the Schedule – II to section 7 ibid as “supply of
    services viz. agreeing to the obligation to refrain from an act, or to tolerate an
    act or a situation, or to do an act”.

    As per para 7.1.1 of the said circular “It is common for the parties entering into
    a contract, to specify in the contract itself, the compensation that would be
    payable in the event of the breach of the contract. Such compensation specified
    in a written contract for breach of non-performance of the contract or parties of
    the contract is referred to as liquidated damages. Black’s Law Dictionary
    defines “Liquidated Damages’ as cash compensation agreed to be a signed,
    written contract for breach of contract, payable to the aggrieved party.”

    From the above, it appears that the compensation paid by TSPL cannot be
    considered as liquidated damages as the said consideration was paid to
    DOCOMO after they had agreed to refrain from initiating any further
    proceeding against Tata in relation to SHA and/or the reward and withdrawal
    of Court proceedings in UK and US. Thus, this act of DOCOMO appears to
    be one of tolerance with respect to the breach of the contract.

    11.5. Para 7.1.4 of the CBIC circular which deals with the taxability states as
    under “taxability of liquidated damages is that where the amount paid as
    liquidated damages’ is an amount paid only to compensate for injury, loss or
    damage suffered by the aggrieved party due to breach of the contract and there
    is no agreement, express or implied, by the aggrieved party receiving the
    liquidated damages, to refrain from or tolerate an act or to do anything for the
    party paying the liquidated damages, in such cases liquidated damages are mere
    a flow of money from the party who causes breach of the contract to the party
    who suffers loss or damage due to such breach. Such payments do not
    constitute consideration for a supply and are not taxable”

    From the paras above, it appears from the consent terms (Joint consent
    application filed in the Hon’ble High Court of Delhi) that DOCOMO is
    agreeing to refrain from act the DOCOMO will not initiate any further
    proceedings in relation to the SHA and/or the Award during the Suspension
    Period and agreeing to unconditionally withdraw all the proceedings initiated
    against TSPL. Accordingly, it appears that damages are paid to the DOCOMO
    and there is an agreement to refrain from an act and accordingly, the same
    appears to be taxable and not merely flow of money.

    11.8. Circular No. 214/1/2023-Service Tax dated 28.02.2023 was issued for
    leviability of Service Tax on declared services “Agreeing to the obligations to
    refrain from an act or to tolerate an act or a situation, or to do an act” under
    Clause (e) of Section 66E of the Finance Act, 1994. This circular also referred
    the earlier circular dated 03.08.2022. However, Circular No. 214/1/2023-
    Service Tax dated 28.02.2023 and the case laws mentioned in the circular
    pertains to the Service Tax matters and does not interfere with the present issue
    in hand as the taxability in the present case arises at the time of payments made
    ie. GST period.

    11.9. Further, it appears that it is a case of suppression of facts. Had the officers
    of DGGI, Mumbai Zonal Unit (MZU) not observed the activity in hand, the

    Page 52 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    said facts would not have come to light. Further, the case is very clear and
    known to the noticee that he has paid the damage amount to DOCOMO. “The
    activity is considered as supply’ by DOCOMO and the same would fall within
    in the ambit of entry no. [e] of Sr. no. 5 of the Schedule – II to section 7 ibid as
    “supply of services viz. agreeing to the obligation to refrain from an act, or to
    tolerate an act or a situation, or to do an act”.” Accordingly, TSPL was required
    to declare the value of service in GSTR-3B returns declaring the correct nature
    and correct value of the services received. Accordingly, as per explanation 2 to
    the Section 74 of the CGST Act, 2017, any failure to declare information
    required to be declared in statutory returns leading to non-payment of
    appropriate GST thereon, has to be taken as GST not paid by reason of
    suppression of facts. The said irregularities would not have come to light bot
    for the Investigations conducted by the department officers.

    11.10. In view of the above facts, it appears that DOCOMO has rendered the
    supply vide their act of tolerance of the contractual Defaults by TSPL and
    refrained from Initiating any further proceedings against TSPL in UK and USA
    and in relation to the Shareholding Agreement (SHA) and/or the Award, the
    same appears to squarely fall within the ambit of definition of ‘supply’ as
    envisaged under sub-section [1] of section 7 of the CGST Act, 2017 and the
    damages referred to herein above is the ‘consideration’ paid by TSPL to
    DOCOMO in the course and furtherance of their business.

    12. Contraventions of Provisions:

    It appears that M/s Tata Sons Private Ltd. had contravened the following
    provisions of the Central Goods and Services Tax Act, 2017, the Integrated
    Goods and Services Tax Act, 2017
    and the rules made thereunder:

    i. Section 5 of the Integrated Goods and Services Tax Act, 2017 read with
    Section 7 of the CGST Act, 2017 inasmuch, they failed to pay Integrated
    Goods and Services Tax in the manner and at the rate provided under the said
    provisions.

    ii. Section 7 of the CGST Act, 2017 read with Section 20 of the IGST Act,
    2017 inasmuch, as they failed to account for the taxable supply received by
    them.

    iii. Notification No. 10/2017-Integrated Tax (Rate) dated 28.06.2017 notified
    under subsection (3) of Section 5 of the IGST Act, 2017 Inasmuch, they failed
    to pay Integrated Goods and Services Tax under Reverse Charge Mechanism
    and at the rate provided under the said provisions.

    iv. Section 15 of the Central Goods and Services Tax Act, 2017 read with Rule
    30 of the CGST Rules, 2017 and further read with Section 20 of the Integrated
    Goods and Services Tax Act, 2017 Inasmuch, they failed to correctly determine
    the correct value of taxable services.

    v. Section 38, 39 & 44 of the CGST Act, 2017 read with Rules 59, 60, 61 & 80
    of the CGST Rules, 2017 as made applicable in the case of IGST vide Section
    20
    of the IGST Act, 2016 and Rule 2 of IGST Rules, 2017 inasmuch as they
    have failed to furnish proper outward, inward and monthly returns mentioning

    Page 53 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    the particulars of services, the correct value of taxable services determinable
    under the category of taxable services and other particulars in the manner as
    provided therein and incorporating such information in such returns.”

    (emphasis supplied)

    55. Having noted the basis for demand being made in the impugned show

    cause notice, it is clear that respondent Nos.3 and 4 have proceeded to consider

    such payment as made by Tata to Docomo as supply of services under Section 7

    read with Schedule II Entry 5(e).

    56. Thus, the fundamental question which has arisen for determination is

    whether the parties settling the arbitral award in question in enforcement

    proceedings filed before the Delhi High Court under Sections 47 and 48 of

    theACA when incorporated Clause 7 (supra) in the consent terms in regard to

    the proceedings before the UK and US Courts, would at all attract Section 7 of

    the CGST Act. In our opinion, the answer would certainly be in the negative, as

    would be clear from the following discussion which would lead us to the said

    conclusion.

    57. Section 7 of the CGST Act falls under Chapter III – ‘Levy and Collection

    of Tax’. Section 7 pertains to ‘Scope of supply’ which is required to be noted

    which reads thus:

    “Chapter III : Levy and Collection of Tax

    Section 7 : Scope of supply
    (1) For the purposes of this Act, the expression “supply” includes—

    (a) all forms of supply of goods or services or both such as sale,
    transfer, barter, exchange, licence, rental, lease or disposal made or
    agreed to be made for a consideration by a person in the course or
    furtherance of business;

    Page 54 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    (aa) the activities or transactions, by a person, other than an individual,
    to its members or constituents or vice-versa, for cash, deferred
    payment or other valuable consideration.

    Explanation.—For the purposes of this clause, it is hereby clarified
    that, notwithstanding anything contained in any other law for the time
    being in force or any judgment, decree or order of any Court, tribunal
    or authority, the person and its members or constituents shall be
    deemed to be two separate persons and the supply of activities or
    transactions inter se shall be deemed to take place from one such
    person to another;

    (b) import of services for a consideration whether or not in the course
    or furtherance of business;2[and]

    (c) the activities specified in Schedule I, made or agreed to be made
    without a consideration;

    [(1A) Where certain activities or transactions constitute a supply in
    accordance with the provisions of sub-section (1), they shall be treated either
    as supply of goods or supply of services as referred to in Schedule II.]

    (2) Notwithstanding anything contained in sub-section (1),—

    (a) activities or transactions specified in Schedule III; or

    (b) such activities or transactions undertaken by the Central
    Government, a State Government or any local authority in which they
    are engaged as public authorities, as may be notified by the
    Government on the recommendations of the Council, shall be treated
    neither as a supply of goods nor a supply of services.

    (3) Subject to the provisions of sub-sections (1), (1A) and (2), the
    Government may, on the recommendations of the Council, specify, by
    notification, the transactions that are to be treated as—

    (a) a supply of goods and not as a supply of services; or

    (b) a supply of services and not as a supply of goods.”

    (emphasis supplied)

    58. A reference is made by the aforesaid provision to Schedule I and Schedule

    II which read thus:

    SCHEDULE I [See section 7]
    ACTIVITIES TO BE TREATED AS SUPPLY EVEN IF MADE WITHOUT
    CONSIDERATION

    1. Permanent transfer or disposal of business assets where input tax credit has
    been availed on such assets.

    2. Supply of goods or services or both between related persons or between
    distinct persons as specified in section 25, when made in the course or
    furtherance of business: Provided that gifts not exceeding fifty thousand rupees
    in value in a financial year by an employer to an employee shall not be treated
    as supply of goods or services or both.

    3. Supply of goods–

    (a) by a principal to his agent where the agent undertakes to supply such goods
    on behalf of the principal; or

    (b) by an agent to his principal where the agent undertakes to receive such

    Page 55 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    goods on behalf of the principal.

    4. Import of services by a 1 [person] from a related person or from any of his
    other establishments outside India, in the course or furtherance of business

    SCHEDULE II [See section 7]

    ACTIVITIES 1 [OR TRANSACTIONS] TO BE TREATED AS SUPPLY OF
    GOODS OR SUPPLY OF SERVICES
    …..

    5. Supply of services
    …..

    (2) the expression “construction” includes additions, alterations, replacements
    or remodelling of any existing civil structure;

    …..

    (e) agreeing to the obligation to refrain from an act, or to tolerate an act or a
    situation, or to do an act; and
    (emphasis supplied)

    59. Having noted the provisions of the CGST Act, the relevant provisions of

    the IGST are also required to be noted:

    Section 2. Definitions.–In this Act, unless the context otherwise requires,–

    (1) …..

    (11) ”import of services” means the supply of any service, where–

    (i) the supplier of service is located outside India;

    (ii) the recipient of service is located in India; and

    (iii) the place of supply of service is in India;

    (15) “location of the supplier of services” means,–

    (a) where a supply is made from a place of business for which the
    registration has been obtained, the location of such place of business;

    (b) where a supply is made from a place other than the place of
    business for which registration has been obtained (a fixed
    establishment elsewhere), the location of such fixed establishment;

    (c) where a supply is made from more than one establishment,
    whether the place of business or fixed establishment, the location of
    the establishment most directly concerned with the provision of the
    supply; and

    (d) in absence of such places, the location of the usual place of
    residence of the supplier;

    Section 5. Levy and collection.–(1) Subject to the provisions of sub-section

    Page 56 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    (2), there shall be levied a tax called the integrated goods and services tax on
    all inter-State supplies of goods or services or both, except on the supply of
    alcoholic liquor for human consumption and un-denatured extra neutral
    alcohol or rectified spirit used for manufacture of alcoholic liquor, for human
    consumption, on the value determined under section 15 of the Central
    Goods and Services Tax Act and at such rates, not exceeding forty per cent.,
    as may be notified by the Government on the recommendations of the
    Council and collected in such manner as may be prescribed and shall be paid
    by the taxable person:

    Provided that the integrated tax on goods other than the goods as may
    be notified by the Government on the recommendations of the Council
    imported into India shall be levied and collected in accordance with the
    provisions of section 3 of the Customs Tariff Act, 1975 (51 of 1975) on the
    value as determined under the said Act at the point when duties of customs
    are levied on the said goods under section 12 of the Customs Act, 1962 (52
    of 1962).

    Section 7. Inter-State supply.

    (1) …..

    (4) Supply of services imported into the territory of India shall be treated
    to be a supply of services in the course of inter-State trade or commerce.

    Section 13. Place of supply of services where location of supplier or location
    of recipient is outside India.–(1) The provisions of this section shall apply to
    determine the place of supply of services where the location of the supplier of
    services or the location of the recipient of services is outside India.

    (2) The place of supply of services except the services specified in sub-
    sections (3) to (13) shall be the location of the recipient of services:

    Provided that where the location of the recipient of services is not
    available in the ordinary course of business, the place of supply shall be the
    location of the supplier of services.”

    60. It is clear that the revenue has considered Clause 7 of the consent terms /

    settlement as brought about before the Delhi High Court between Tata and

    Docomo as supply of services, to the foreign recipient and hence attracting the

    provisions of the IGST Act as noted by us hereinabove. Considering the

    provisions of Section 20 of the IGST Act, which provide for ‘Application of

    provisions of CGST Act‘ to the provisions of the IGST Act, inter alia the scope

    of supply and other aspects as set out in clauses (i) to (xxv) are concerned and

    Page 57 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    from a plain reading of the provisions of Section 7 of the CGST Act, we are at a

    loss to understand as to how a settlement of an arbitral award in the manner as

    accepted by the Delhi High Court, which is a matter purely inter se between the

    parties and that too in the Court proceedings, which pertain to the enforcement

    of a foreign arbitral award qua the incorporation of condition 7 in the consent

    terms amount to supply and / or import of services, that too without involving

    any independent consideration, when per se there is no question of any

    consideration, once there was a monetary award under which damages were

    awarded against Tata, payable to Docomo.

    61. Under Entry 5(e) of Schedule II to the CGST Act ‘supply of services’

    includes ‘agreeing to the obligation to refrain from an act, or to tolerate an act or a

    situation, or to do an act;”. Thus, the words “agreeing to the obligation … … .. ”

    are a pointer that necessarily there needs to exist an independent agreement,

    where the parties in the normal course of business bind themselves to refrain

    from an act, or to tolerate an act or a situation, or to do an act involving

    consideration, which would amount to supply of services of such nature. As to

    whether such ingredients would at all fit into, what the parties have agreed under

    the award, as being found relevant by the department to be the charging element,

    i.e., Docomo agreeing that having received the award amounts, it would not

    pursue the recovery proceedings initiated before the U.S., U.K. and Indian Court.

    62. On a plain purport of the relevant provisions, it would not require any

    deep diving/elaboration to observe that the recovery of the amounts under a

    decree of the Court and for that matter an arbitral award, which is for damages by

    Page 58 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    any stretch of imagination ought not to amount to ‘supply of services’. The

    reason being multiple in the facts of the present case. We may observe that as a

    general principle, under the scheme of recovering amounts for breach of contract

    by seeking damages, either in a civil suit or in arbitral proceedings, is a part of the

    requirement of law or the rule of law, even when it comes to compliance of an

    arbitral award of a foreign arbitral tribunal. Any award of damages being

    recognized, in the context of its enforcement applying the Indian law, namely, the

    ACA and recognition of the principles for award of damages under the Indian

    Contract Act form part of a legal scheme integral to the arbitral process.

    Conversely, if it were not so, even assuming that such award of damages was not

    in the arbitral proceedings but under a decree of a Civil Court in a civil suit, on

    the defendant not discharging its obligation under the decree, necessarily the

    decree would be subjected to execution under the provisions of Order XXI of the

    Code of Civil Procedure, 1908. Any settlement brought about thereunder

    necessarily becomes “integral to” and or “intricately connected”, to the decree

    itself. The reciprocal obligation even in settlement of a decree necessarily

    emanates from a decree, which cannot be construed to be an independent

    agreement de hors the decree and/or alien to the decree itself.

    63. Similarly, the proceedings which are incidental, integral to the execution

    of the decree and falling under the decree (here an arbitral award) also cannot be

    considered to be alien to the decree, as such proceedings certainly partake the

    character of the original/principal proceedings, namely, execution of a decree. For

    illustration, in the process of execution of a decree, the properties

    Page 59 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    (immovable/movable) of the defendant being attached, which are situated at

    different places, certainly would be the proceedings under the umbrella of the

    decree, and not outside the decree. Hence, if the money decree itself is being

    satisfied by the defendants by making a full and final payment to the satisfaction

    of the decree holder, as a natural consequence, of such satisfaction of such decree,

    the plaintiff agreeing to withdraw the collateral proceedings, which are in the aid

    of the execution and for realization of the decretal dues, it certainly cannot be

    said that the plaintiff is discharging an obligation alien to the decree in

    withdrawing of such proceedings. Moreover, such collateral proceedings which

    are incidental to the execution of the decree cannot be regarded as independent

    proceedings, having legs different from the principal proceedings i.e. the

    proceedings for execution of a decree.

    64. Similar would be the position insofar as the arbitral award is concerned

    when in the present case a foreign award was subjected to enforcement before the

    Indian Court, that is, the Delhi High Court and realization of the award amount

    was also resorted in the proceedings initiated before the US and UK Courts. Such

    proceedings for recovery of the award amount certainly draw their colour from

    the arbitral award. The proceedings were in relation to or under the arbitral

    award only, hence any satisfaction of the award amounts in the manner as agreed

    in Clause 7 of the consent terms, in law would result in such collateral

    proceedings necessarily coming to an end, as a natural corollary, on the principle

    that once the decree itself stands satisfied and accepted, the collateral proceedings

    to recover the very decretal amounts would not survive, as they need to

    Page 60 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    necessarily yield to the decree being satisfied and would accordingly stand

    extinguished.

    65. In the facts of the present case, the parties merely recording in the terms,

    the conditions towards satisfaction of the decree of the nature as agreed in Clause

    7 (supra) of the consent terms that the collateral proceedings would not be

    pursued for the full and final satisfaction of the award being worked out, this

    being considered to be supply of services, itself is untenable considering the

    purport of the provisions of Section 7 read with Entry 5(e) of Schedule II.

    66. The reason being Section 7 which defines ‘Scope of supply’ categorically

    provides that “supply” would inter alia include all forms of supply of goods or

    services or both of the nature such as sale, transfer, barter, exchange, licence,

    rental, lease or disposal made or agreed to be made for “a consideration” by a

    person in the course or furtherance of business. Coupled with this, in the present

    case what is being applied is the provision of Schedule II Entry 5(e) to the effect

    of which is “a party agreeing to the obligation to refrain from an act, or to tolerate

    an act or a situation, or to do an act” . These provisions are being applied to the

    consent terms as entered between Docomo and Tata. In our view, considering as

    to what is provided by Entry 5(e), the same cannot be read beyond the purview

    and/or the context of principal provision, namely, Section 7, as noted by us

    hereinabove. Reading Entry 5(e) de hors the provision would amount to an

    erroneous reading of this provision, which are sought to be applied by the

    revenue. In the facts of the case, neither there is any independent agreement

    involving any consideration nor Clause 7 of the consent terms can be implied to

    Page 61 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    be any independent agreement, for which any separate consideration has been

    promised by Tata to be paid to Docomo so as to even remotely attract the

    provision of Section 7 read with Entry no. 5(e). Thus, in our view, Clause 7 of

    the consent terms cannot be construed to mean, that it is bringing about an

    independent contract between Docomo and Tata and on a consideration, so as to

    attract the applicability of Section 7 of the CGST Act. When Section 7 itself is

    not attracted, there is no question of the provisions of Entry 5(e) of Schedule II

    of the CGST Act and the corresponding provisions of IGST Act being made

    applicable. We are thus also afraid as to how the corresponding provisions of

    IGST as invoked and noted by us hereinabove, can at all be applied on the basis

    that Docomo is receiving supply of services by virtue of Clause 7 of the consent

    terms and/or on the arrangement between the parties, which is purely in the

    context of realization of the arbitral dues in the proceedings before the Delhi

    High Court. It also cannot be overlooked that in the facts of the present case, the

    situation is not that, Docomo and Tata has agreed for something different, that is,

    to some independent obligation/ arrangement for a consideration falling beyond

    the purview of the arbitral award, so as to categorize such obligation to be an

    independent obligation, amounting to supply of service within the purview of

    Section 7 read with entry 5(e) of Schedule II.

    67. It is thus difficult to comprehend as to how Docomo having received the

    principal amount under the award, having agreed not to proceed in the

    enforcement proceedings in U.S., U.K. or India, which was a logical consequence

    of the arbitral award itself being satisfied, could be said to create any independent

    Page 62 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    obligation, that too under Section 7 of the CGST Act. Thus, the approach of the

    department on the premise of Docomo merely agreeing not to pursue the UK/US

    proceedings in the course of realization of the decretal amounts would create any

    obligation on Docomo to refrain from an act or to tolerate an act or a situation or

    to do an act, as contemplated by Entry 5(e) of Schedule II, appears to be quite

    absurd.

    68. As rightly contended on behalf of Tata, the clear intention of Docomo in

    initiating enforcement proceedings before the Delhi High Court and before

    different Courts namely U.S., U.K., was to realize the award amount. Attributing

    any other purpose remains to be an ingenuity without any basis the law could

    recognize, as nothing is brought on record much less any independent agreement

    de hors from what was inter se brought out between the parties i.e. Tata and

    Docomo in the enforcement proceedings. Hence, in the absence of any such

    independent contract creating rights and obligations which can stand

    independent of the award/decree, to label the proceedings before the Delhi High

    Court and the parties agreeing to settle the claim under the award being

    characterized as “supply” within the meaning of Section 7 of the CGST Act read

    with Entry 5(e) of Schedule II, in our opinion, is a fundamental flaw. Such

    approach on the part of respondent No.3-Joint Director, Directorate General of

    GST Intelligence, is wholly without jurisdiction and patently perverse.

    69. In our opinion, if such logic as adopted by the Revenue in the present case

    if is accepted, in that event, the settlement of every money decree where parties

    are before the Court and agree to a course of action purely under the decree

    Page 63 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    without creating any independent obligation, would be required to be regarded as

    ‘supply of service’ as sought to be alleged on behalf of the revenue. This would

    amount to creating a situation wholly not recognized by law, in the context of the

    relevant provisions of the CGST Act, when it comes to execution of a decree

    and / or settlement of a decree, as the parties may mutually decide and which

    would receive the imprimatur of the Court as in the present case, when such

    arrangements between the parties in the course of execution/enforcement

    proceedings stand recognized by the Court. This is precisely what has happened

    in the present case, as the subject matter of the intimation as also the impugned

    show cause notice emanates from the proceedings relating to the enforcement of

    the foreign award in question, which stands confirmed by the Delhi High Court.

    It appears to us that as merely the award amounts are large amounts, the

    impugned action without application of mind to the law and the facts, has been

    resorted. Such action has no basis whatsoever in law, looked from any angle. This,

    more particularly, when the revenue at all material times was aware about the

    legal position in terms of what is clearly notified in Circular No.178/10/2022

    dated 3 August 2022, in paragraph 7.1.4 and 7.1.5 which read thus:

    “7.1.4 In this background a reasonable view that can be taken with regard to
    taxability of liquidated damages is that where the amount paid as ‘liquidated
    damages’ is an amount paid only to compensate for injury, loss or damage
    suffered by the aggrieved party due to breach of the contract and there is no
    agreement, express or implied, by the aggrieved party receiving the liquidated
    damages, to refrain from or tolerate an act or to do anything for the party
    paying the liquidated damages, in such cases liquidated damages are mere a
    flow of money from the party who causes breach of the contract to the party
    who suffers loss or damage due to such breach. Such payments do not
    constitute consideration for a supply and are not taxable.
    7.1.5 Examples of such cases are damages resulting from damage to property,
    negligence, piracy, unauthorized use of trade name, copyright, etc. Other
    examples that may be covered here are the penalty stipulated in a contract for
    delayed construction of houses. It is a penalty paid by the builder to the buyers

    Page 64 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    to compensate them for the loss that they suffer due to such delayed
    construction and not for getting anything in return from the buyers. Similarly,
    forfeiture of earnest money by a seller in case of breach of ‘an agreement to sell’
    an immovable property by the buyer or by Government or local authority in
    the event of a successful bidder failing to act after winning the bid, for
    allotment of natural resources, is a mere flow of money, as the buyer or the
    successful bidder does not get anything in return for such forfeiture of earnest
    money. Forfeiture of Earnest money is stipulated in such cases not as a
    consideration for tolerating the breach of contract but as a compensation for
    the losses suffered and as a penalty for discouraging the non-serious buyers or
    bidders. Such payments being merely flow of money are not a consideration for
    any supply and are not taxable. The key in such cases is to consider whether the
    impugned payments constitute consideration for another independent contract
    envisaging tolerating an act or situation or refraining from doing any act or
    situation or simply doing an act. If the answer is yes, then it constitutes a
    ‘supply’ within the meaning of the Act, otherwise it is not a “supply”.

    (emphasis supplied)

    70. The position is not different in the second circular dated 28 February

    2023, being Circular No. 214/1/2023-Service Tax, wherein again the following

    has been reiterated.

    “5. The issue also came up in the CESTAT in Appeal No. ST/50080 of
    2019 in the case of M/s Dy. GM (Finance) Bharat Heavy Electricals Ltd in
    which the Hon’ble Tribunal relied on the judgment of divisional bench in case
    of M/s South Eastern Coal Fields Ltd Vs. CCE Raipur {2021(55) G.S.T.L
    549(Tri-Del)}. Board has decided not to file appeal against the CESTAT order
    ST/A/50879/2022-CU[DB] dated 20.09.2022 in this case and also against
    Order A/85713/2022 dated 12.8.2022 in case of M/s Western Coalfields.
    Ltd.
    Further, Board has decided not to pursue the Civil Appeals filed before the
    Apex Court in M/s South Eastern Coalfields Ltd. supra (CA No. 2372/2021).
    M/s Paradip Port Trust (Dy. No. 24419/2022 dated 08-08-2022), and M/s
    Neyveli Lignite Corporation Ltd (CA No. 0051-0053/2022) on this ground.

    6. In view of above, it is clarified that the activities contemplated under
    section 66E(e), i.e. when one party agrees to refrain from an act, or to tolerate
    an act or a situation, or to do an act, are the activities where the agreement
    specifically refers to such an activity and there is a flow of consideration for this
    activity. Field formations are advised that while taxability in each case shall
    depend on facts of the case, the guidelines discussed above and jurisprudence
    that has evolved over time, may be followed in determining whether service tax
    on an activity or transaction needs to be levied treating it as service by way of
    agreeing to the obligation to refrain from an act, or to tolerate an act or a
    situation, or to do an act. Contents of Circular No. 178/10/2022-GST dated
    3rd August. 2022, may also be referred to in this regard.”

    (emphasis supplied)

    Page 65 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    71. The position the revenue has accepted in regard to the liquidated damages

    would necessarily apply in respect of unliquidated damages. This would be clear

    when one considers the award of damages under Section 73, as the damages

    awarded by the Court and the damages (penalty) agreed between the parties, the

    legal character of the payment is nothing but flow of money from the party who

    causes a breach of the contract to the party who suffers loss or damage due to

    such breach so as to be the damages as awarded by the Court in its decree. Thus,

    the parameters in recovery of such damages either in the decree of the Court or in

    the arbitral award, would not be different.

    72. In such context, it would be necessary to note the provisions of Sections

    73 and 74 of the Contract Act providing for ” Compensation for loss or damage

    caused by breach of contract.” and “Compensation for breach of contract where

    penalty stipulated for” respectively, which read thus:

    Section 73 of Contract Act – Compensation for loss or damage caused by
    breach of contract.–When a contract has been broken, the party who suffers
    by such breach is entitled to receive, from the party who has broken the
    contract, compensation for any loss or damage caused to him thereby, which
    naturally arose in the usual course of things from such breach, or which the
    parties knew, when they made the contract, to be likely to result from the
    breach of it. Such compensation is not to be given for any remote and indirect
    loss or damage sustained by reason of the breach. Compensation for failure to
    discharge obligation resembling those created by contract.–When an
    obligation resembling those created by contract has been incurred and has not
    been discharged, any person injured by the failure to discharge it is entitled to
    receive the same compensation from the party in default, as if such person had
    contracted to discharge it and had broken his contract. Explanation.–In
    estimating the loss or damage arising from a breach of contract, the means
    which existed of remedying the inconvenience caused by the non-
    performance of the contract must be taken into account.

    Section 74 of Contract Act – Compensation for breach of contract where
    penalty stipulated for.–When a contract has been broken, if a sum is named
    in the contract as the amount to be paid in case of such breach, or if the
    contract contains any other stipulation by way of penalty, the party
    complaining of the breach is entitled, whether or not actual damage or loss is

    Page 66 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    proved to have been caused thereby, to receive from the party who has broken
    the contract reasonable compensation not exceeding the amount so named or,
    as the case may be, the penalty stipulated for. Explanation.–A stipulation for
    increased interest from the date of default may be a stipulation by way of
    penalty.] Exception.–When any person enters into any bail-bond,
    recognizance or other instrument of the same nature, or, under the provisions
    of any law, or under the orders of the 2 [Central Government] or of any 3
    [State Government], gives any bond for the performance of any public duty or
    act in which the public are interested, he shall be liable, upon breach of the
    condition of any such instrument, to pay the whole sum mentioned therein.
    Explanation.–A person who enters into a contract with Government does
    not necessarily thereby undertake any public duty, or promise to do an act in
    which the public are interested.

    73. As seen in the facts of the present case, disputes inter se between Docomo

    and Tata, had arisen between the said parties, on Docomo’s case of the breach of

    the terms and conditions of the shareholders’ agreement, which was the subject

    matter of the international commercial arbitration. The arbitral proceedings

    resulted in the arbitral tribunal pronouncing the arbitral award in question,

    whereby the damages were awarded in favour of Docomo by the arbitral tribunal,

    i.e., the London Court of International Arbitration. Thus, the legal character of

    the amounts which were entitled to Docomo are the amounts as granted under

    the Arbitral award, being the damages payable by Tata to Docomo. The award of

    such damages in the context of the Indian law would stand recognized under

    Section 73 of the Contract Act (supra) being a provision which ordains

    compensation for loss or damage caused by breach of contract. It is recovery of

    such award amount which was the subject matter of the proceedings before the

    Delhi High Court. In such context, we examine the applicability of the circulars

    as issued by the CBIC, considering the petitioner/Tata’s contention that it is a

    settled principle of law that the department would be bound by the provisions of

    the circulars, this apart from the fact that respondents are certainly bound by law

    Page 67 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    74. It is clear from the contents of the aforesaid circular that, in cases where

    the amount of liquidated damages are paid, the same is regarded by the

    Department being amount paid, only to compensate, for injury, loss or damage

    suffered by the aggrieved party, due to breach of the contract and such amounts

    are regarded not to be any independent agreement, express or implied, in the

    hands of the aggrieved party receiving the liquidated damages, so as to infer that

    the aggrieved party would refrain from or tolerate an act or to do anything for the

    party paying the liquidated damages. Such receipt of amount is regarded as a

    mere flow of money from the party, who causes breach of the contract to the

    party, who suffers loss or damage due to such breach. For such reason, such

    payments do not constitute consideration for a supply and are not taxable, is the

    purport of the circular. The circular also has given clear examples in paragraph

    7.1.5 (supra) being cases of damages which also include the penalty stipulated in a

    contract, forfeiture of earnest money, etc. Most significantly, the Circular

    provides that it is necessary to consider whether the payments constitute

    consideration for “another independent contract” in envisaging tolerating an act

    or situation or refraining from doing any act or situation or simply doing an act.

    The circular states that if the answer is yes, then it constitutes a ‘supply’ within

    the meaning of the CGST Act, otherwise it is not a “supply”.

    75. Insofar as the second Circular, being Circular no. 214/1/2023-Service Tax

    dated 28 February, 2023 is concerned, the applicability of the same was

    considered by the CESTAT in the case of M/s. Dy. GM (Finance), Bharat Heavy

    Electricals Ltd. (supra), wherein CESTAT relied on the judgment of the Division

    Page 68 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    Bench of the High Court of Chattisgarh in South Eastern Coalfields Ltd. vs.

    Commissioner of Central Excise and Service Tax, Raipur 24. In such case as

    informed to the Court, the Board had decided not to file an appeal against the

    order passed by CESTAT. A similar view was taken in the case of M/s. Western

    Coalfields Ltd., M/s. Paradip Port Trust and M/s. Neyveli Lignite Corporation

    Ltd. It is in the context of paragraph 6 of the said Circular, a clarification was

    issued that when one party agrees to refrain from an act, or tolerate an act or a

    situation, or to do an act, are activities where the agreement specifically refers to

    such an activity and in such situation, if there is a flow of consideration for this

    activity, the departmental officers were advised that, while taxability in each such

    case, shall depend on the “facts of the case”, the guidelines which are set out and

    the principles that have evolved over the time, were required to be followed in

    determining whether service tax on an activity or transaction needs to be levied

    treating it as a service by a party agreeing to the obligation to refrain from an act,

    or to tolerate an act or a situation, or to do an act. Thus, the basis and focus is on

    a specific agreement in regard to such activity, to attract the provisions of Section

    7 of the CGST Act.

    76. Having discussed the Circulars, we are of the opinion that the circulars in

    fact appropriately consider the legal position that in the normal circumstances,

    once liquidated damages are an amount being received by a party on account of

    breach of contract, receipt of such amount would not constitute consideration for

    a supply and accordingly, such amounts would not be taxable. There would be

    24 2020 (12) TMI 912

    Page 69 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    hardly any distinction between a party receiving such amount being categorized

    as liquidated damages and a party receiving such amount as damages awarded by

    the Civil Court or by an arbitral tribunal, for the reason that the legal character

    and nature of such payment is nothing but receipt of compensation for a breach

    of contract. In these circumstances, also in the present case, once the award

    amount was received by Docomo as paid by Tata, was an amount payable towards

    damages under the arbitral award in question, considering the surrounding facts,

    there is no question of such amounts to be regarded as constituting consideration

    for a supply and accordingly being taxable, in the absence of any independent

    agreement of the nature as the law would envisage, creating distinct rights and

    liabilities, independent of the arbitral proceedings or totally alien to the arbitral

    award.

    77. The above discussion would lead us to conclude that the action on the

    part of the respondents in raising the impugned demand on the ground that

    Docomo agreed not to pursue the execution proceedings instituted before the

    Courts of different jurisdictions (UK and USA etc.) would by any stretch of

    imagination amount to an independent agreement between Docomo and Tata,

    under which Docomo tolerated an act or a situation, in our opinion, is totally

    untenable. In adopting such approach, the Designated Officer has completely

    overlooked the following:

    i) The amounts received by Docomo from Tata under the arbitral

    award was an indisputed position.

    (ii) In the event, a party succeeding in a Civil Suit or the arbitral

    Page 70 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    proceedings and who is the beneficiary of the monetary decree/award of

    damages on a default of honouring the decree/award by the award

    debtors, the only procedure known to law for the award creditor is to

    institute execution proceedings for recovery of the award amounts, within

    the jurisdiction of the appropriate Courts where the Judgment

    debtor/award debtor, would have properties/ resources. For such recovery,

    necessarily proceedings/ applications before the appropriate jurisdictional

    Courts* would be required to be instituted is the arbitration

    jurisprudence. Such proceedings necessarily owe their pursuit only to the

    arbitral award/decree

    (iii) In the event, in any such proceedings, the judgment debtor/award

    debtor takes a position to satisfy the decree/award, the necessary

    consequence, is to the effect that the decree-holder/award creditor would

    not be entitled in law to pursue the execution proceedings wherever

    instituted to recover the decretal/award dues for the satisfaction of the

    decree/award. As a natural corollary, such proceedings would come to an

    end and would stand concluded. In these circumstances, the decree-

    holder/award creditor in any scheme of settlement of the award/decree

    making a statement before the Court in such legal proceedings, that for

    receiving the amounts in full and final settlement of the decree, the

    decreeholder/award creditor would not pursue the proceedings as

    initiated before the different courts for recovery of such amounts, would

    * Sch. II Ent. 5(e) of the CGST Act

    Page 71 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    in fact become a mandatory legal requirement, recognizing the legal

    incapacity of the decree holder/award creditor to pursue such

    proceedings, in view of the decree/award being satisfied. Thus, looked

    from any angle, in these circumstances, such position taken before any

    Court by the decree holders/award creditor cannot bring about any

    independent agreement outside the scope and purview of the execution

    proceedings, as such position being taken by the decree holder/award

    creditor, would be incidental or integral to the satisfaction of the

    decree/award.

    78. Such legal consequences have been overlooked by the designated officer in

    attributing an independent agreement between Docomo and Tata, when in the

    course of enforcement of the arbitral award in question, the award

    creditor/Docomo took a position that in receiving the award amount in full and

    final, from Tata, it would not pursue the execution/recovery proceedings for

    recovery of the award amount. Thus, such statement by Docomo, that too, made

    before the Delhi High Court, in our clear opinion, does not create any

    independent agreement, so as to constitute a supply of services within the

    meaning of Section 7(1)(c) read with Entry 5(e) of Schedule II of the CGST Act.

    79. We may also observe that in the facts and circumstances of the case, it

    would be difficult to accept a proposition that the decision taken by Docomo

    before the Delhi High Court which was exercising powers under Sections 47 and

    48 of the ACA in regard to enforcement of the arbitral award in question, does

    not bring about any independent agreement between the parties, and of the

    Page 72 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    nature as contemplated by the provisions of Section 7 read with Section 9 and

    Schedule II Entry 5(e) of the CGST Act. The reason being that the orders passed

    by the Delhi High Court recorded the stand as taken by Docomo agreeing not to

    pursue the execution proceedings instituted before the UK and US Courts in

    view of Tata depositing and permitting Docomo to withdraw the entire award

    amount. The designated officer, therefore, could not have construed any

    different intention between Docomo and Tata arriving at an independent

    contract of the nature amounting to supply of service so as to attract levy of

    IGST. In fact, the designated officer assuming some intention between the

    parties on the basis of the consent terms, in our opinion, is quite an absurdity.

    Such impression as formed by the designated officer militates not only against the

    orders passed by the Delhi High Court but also the intention of the parties,

    inasmuch as, any proceedings to execute the arbitral award in the facts of the

    present case were incidental and inextricably connected to the principal

    proceedings, namely, the proceedings adopted by Docomo before the Delhi High

    Court to enforce the award for recovery of the amounts within the territory of

    India.

    80. Also, what has not been appreciated by the Designated Officer is that

    insofar as the foreign lender/Docomo was concerned, the recognition of the

    award for enforcement was upheld by the Delhi High Court. Thus, once the

    award amount was received by Docomo, as a direct consequence thereof, the

    execution proceedings before the UK and US Courts being ancillary and in aid of

    the claim of Docomo to receive the award amount, which was discharged by Tata,

    Page 73 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    the incidental proceedings before the US and UK Courts, necessarily could not

    have been pursued and/or were to become inconsequential on the award debt

    being discharged by Tata.

    81. In the context of levy of tax on the amount of damages received from the

    suppliers, on account of material breach of the terms and conditions of the

    contract, such issue had fell for consideration of the Tribunal in the case of South

    Eastern Coal Fields Ltd. vs. Commissioner of Central Excise and Service Tax,

    Raipur (supra). The revenue had fastened upon South Eastern Coal Fields Ltd. –

    the appellant, a liability under Section 65B read with Section 66E(e) of the

    Finance Act for the period from July 2012 till March 2016 on the ground that by

    collecting the said amount, the appellant had agreed to the obligation to refrain

    from an act or to tolerate the non-performance of terms of contract by the other

    party. Referring to the decision of the Supreme Court in Commissioner of

    Service Tax vs. M/s. Bhayana Builders (P.) Ltd.25 wherein it was held that any

    amount charged which has no nexus with the taxable service and which is not a

    consideration for the services provided, does not form part of the value which is

    taxable under Section 67 of the Finance Act. The Tribunal also considering the

    decision of the Supreme Court in Fateh Chand vs. Balkishan Das26 on damages,

    held that it was not possible to sustain the view taken by the Commissioner that

    the penalty amount, forfeiture of earnest money deposit and liquidated damages

    were received by the appellant towards ‘consideration’ for ‘tolerating an act’

    leviable to service tax under Section 66E(e) of the Finance Act and accordingly

    25 2018(2) TMI 1325 SC
    26 AIR 1963 SC 1405

    Page 74 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    decided the appeal in favour of the appellant. Also considering the decision of the

    Constitution Bench of the Supreme Court in Fatehchand (supra), it was held that

    the contention of the department that compensation received was synonymous to

    ‘tolerating an act’ was held to not the correct position. The view taken by the

    Commissioner that the penalty amount, forfeiture of earnest money and

    liquidated damages were received by the appellant towards consideration for

    tolerating an act, was held to be not the correct approach. Accordingly the orders

    passed by the Commissioner levying tax were set aside.

    82. Mr. Datar’s reliance in support of the propositions on damages being

    awarded to Docomo, and payable by Tata in the arbitral proceedings, is premised

    as to what would be the legal character of the amount of damages being received,

    and as considered by the Supreme Court in Union of India vs. Raman Iron

    Foundry27, which, according to him, would aptly apply to the present facts. In

    Raman Foundry, tender was accepted by the Government of India, which was

    subject to the General Conditions of Contract, contained in the Standard Form of

    Contract. The performance of the contract ran into difficulties. Dispute had

    arisen between the parties which gave rise to claims by both parties. The

    Government of India intimated to Raman Iron Foundry, that in case of failure to

    pay the damages within the stipulated time, the amount would be recovered from

    its pending bills in respect of other contracts. Consequent thereto, Raman Iron

    Foundry filed an application under Section 20 of the Arbitration Act, 1940 for

    filing the arbitration agreement. Such application was allowed and accordingly

    27 (1974) 2 SCC 231

    Page 75 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    arbitration proceedings were initiated. During the pendency of the arbitration,

    apprehending that the amounts due and payable by the Government of India are

    likely to be appropriated towards the recovery of the amount of damages, Raman

    Iron Foundry made an interim application before the High Court under Section

    41 read with the Second Schedule of the Arbitration Act, praying that the status

    quo be maintained and the appellant should be restrained from recovering its

    claim for damages from the pending bills of Raman Iron Foundry. The High

    Court issued an interim injunction. It is such order, which was the subject matter

    of consideration. In such context, the issue which fell for consideration of the

    Court, was to the purport of Clause 18, which intended to provide a right to

    recovery of claim for payment of a sum of money arising out of or under the

    contract. It is in such context, in examining as to whether there was any

    qualitative difference in the nature of a claim whether it be for liquidated

    damages or for unliquidated damages, it was held that, it makes no difference of

    the claim being for liquidated damages, as such claim stood on the same footing,

    as a claim for unliquidated damages. Referring to the decision of Chagla, CJ in

    Iron and Hardware (India) Co. vs. Firm Shamlal and Bros., the Supreme Court

    observed that the statement of law as made in the said judgment of this Court,

    represented the correct legal position and would have full concurrence of the

    Supreme Court. The relevant observations as made by the Supreme Court are

    required to be noted, which read thus:

    11. Having discussed the proper interpretation of Clause 18, we may now
    turn to consider what is the real nature of the claim for recovery of which the
    appellant is seeking to appropriate the sums due to the respondent under other
    contracts: The claim is admittedly one for damages for breach of the contract
    between the parties. Now, it is true that the damages which are claimed are

    Page 76 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    liquidated damages under cl. 14, but so far as the law in India is concerned,
    there is no qualitative difference in the nature of the claim whether it be for
    liquidated damages or for unliquidated damages. Sec. 74 of the Indian
    Contract Act eliminates the somewhat elaborate refinements made under the
    English common law in distinguishing between stipulations providing for
    payment of liquidated damages and stipulations in the nature of penalty.

    Under the common law a genuine pre-estimate of damages by mutual
    agreement is regarded as a stipulation naming liquidated damages and binding
    between the parties: a stipulation in a contract in terrors is a penalty and the
    Court refuses to enforce it, awarding to aggrieved party only reasonable
    compensation. The Indian Legislature has sought to cut across the web of rules
    and presumptions under the English common law, by enacting a uniform
    principle applicable to all stipulations naming amounts to be paid in case of
    breach, and stipulations by way of penalty, and according to this principle,
    even if there is a stipulation by way of liquidated damages, a party complaining
    of breach of contract can recover only reasonable compensation for the injury
    sustained by him, the stipulated amount being merely the outside limit. It,
    therefore makes no difference in the present case that the claim of the
    appellant is for liquidated damages. It stands on the same footing as a claim for
    unliquidated damages. Now the law is well settled that a claim for
    unliquidated damages does not give rise to a debt until the liability is
    adjudicated and damages assessed by a decree or order of a Court or other
    adjudicatory authority. When there is a breach of contract, the party who
    commits the breach does not eo instanti incur any pecuniary obligation, nor
    does the party complaining of the breach becomes entitled to a debt due from
    the other party. The only right which the party aggrieved by the breach of the
    contract has is the right to sue for damages. That is not in actionable claim and
    this position is made amply clear by the amendment in s. 6(e) of the Transfer
    of Property Act, which provides that a mere right to sue for damages cannot be
    transferred. This has always been the law in England and as far back as 1858
    we, find it stated by Wightman, J., in Jones v. Thompson, “Exparte Charles
    and several other cases decide that the amount of a verdict in an action for
    unliquidated damages is not a debt till judgment has. been signed”.. It was
    held in this case that a claim for damages dots not become a debt even after the
    jury has returned a verdict in favour of the plaintiff till the judgment is
    actually delivered. So also in O’ Driscoll v. Manchester Insurance Committee,
    (2) Swinfen Eady, L. J., said in reference to cases where the claim was for
    unliquidated damages : “…….. in such cases there is no debt at all until the
    verdict of the jury is pronounced assessing the damages and judgment is given.
    The same view has also been taken consistently by different High Courts in
    India. We may mention only a few of the decisions, namely, Jabed Sheikh v.
    Taher Mallik
    , S. Milkha Singh v. M/s N. K. Gopala Krishna Mudaliar and Iron
    & Hardware (India) Co. v. Firm Shamlal & Bros
    . Chagla, C. J. in the last
    mentioned case, stated the law in these terms:

    ” In my opinion it would not be true to say that a person who commits a breach of
    the contract incurs any pecuniary liability, nor would it be true to say that the
    other party to the contract who complains of the breach has any amount due to
    him from the other party.

    As already stated, the only right which he has is the right to go to a Court of law
    and recover damages. Now, damages are the compensation which a Court of law
    gives to a party for the injury which he has sustained. But, and this is most
    important to note, he does not get damages or compensation by reason of any
    existing obligation on the part of the person who has committed the breach. He
    gets compensation as a result of the fiat of the Court. Therefore, no pecuniary
    liability arises till the Court has determined that the party complaining of the

    Page 77 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    breach is entitled to damages. Therefore, when damages are assessed, it would not
    be true to say that what the Court is doing is ascertaining a pecuniary liability
    which already existed. The Court in the first place must decide that the defendant
    is liable and then it proceeds to assess what that liability is. But till that
    determination there is no liability at all upon the defendant. ”

    This statement in our view represents the correct legal position and has our
    full concurrence. A claim for damages for breach of contract is, therefore, not a
    claim for a sum presently due and payable and the purchaser is not entitled, in
    exercise of the right conferred upon it under cl. 18, to recover the amount of
    such claim by appropriating other sums due to the contractor. On this view, it
    is not necessary for us to consider the other contention raised on behalf of the
    respondent, namely, that on a proper construction of cl. 18, the purchaser is
    entitled to exercise the right conferred under that clause only where the claim
    for payment of a sum of money is either admitted by the contractor, or in case
    of dispute, adjudicated upon by a court or other adjudicatory authority. We
    must, therefore, hold that the appellant had no right or authority under cl. 18
    to appropriate the amounts of other pending bills of the respondent in or
    towards satisfaction of its claim for damages against the respondent and the
    learned Judge was justified in issuing an interim Injunction restraining the
    appellant from doing so.”

    (emphasis supplied)

    83. In the aforesaid circumstances, the position in law is clear that when

    damages were awarded by the arbitral tribunal in favour of Docomo, being

    compensation for the injury which it had suffered on account of breach of

    contract by petitioner-Tata. Such compensation was not being granted by reason

    of any different obligation on the part of petitioner-Tata, as Docomo became

    entitled to such compensation, only on being determined and awarded by the

    arbitral tribunal. Thus, as held in Iron and Hardware (India) Co. (supra), no

    pecuniary liability had arisen till the arbitral tribunal had determined, that

    Docomo complaining of the breach was entitled to damages, and for such reason

    when damages were assessed, the arbitral tribunal was not ascertaining the

    pecuniary liability otherwise than the claim for damages. Hence, till such

    determination by the arbitral tribunal, there was no liability on Tata to pay any

    such amount as damages. Such was the legal character of the determination in

    Page 78 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    the arbitral proceedings, i.e., the arbitral award bringing about a consequence that

    the claim for damages for breach of contract was not a claim for a sum which was

    ipso facto due and payable on the date of alleged breach and it was only after the

    determination by the Tribunal, on the proof of such breach, the damages being

    quantified and the entitlement of Docomo as recognized by the award was

    brought into existence. Thus, for such reason in the context of applicability of

    provisions of Section 7(1)(c) read with Entry 5(e) of Schedule II of CGST Act,

    there was no scope for the Designated Officer to read any independent contract

    between the parties whereby reciprocal obligations, dehors the arbitral

    proceedings and the satisfaction of the award by payments made by Tata to

    Docomo could at all be inferred or created.

    84. In the above circumstances, we proceed to answer the question framed by

    us to hold that the settlement as brought about between Docomo and Tata before

    the Delhi High Court settling the arbitral award would not amount to supply

    within the meaning of Section 7(1) of CGST Act, 2017. The consent terms

    entered between the parties on the basis of which the Delhi High Court passeD

    the final orders on the proceedings filed by Docomo under Sections 47 and 48 of

    the ACA, cannot be construed to create any independent agreement between the

    parties, de hors the arbitral award and/or bring about any legal consequence other

    than recognizing Docomo’s entitlement for the award amounts. Thus, these facts

    and circumstances did not attract the provisions of CGST and IGST Act so as to

    create tax liability on Tata. The award of damages in the proceedings before the

    arbitral tribunal is a judicial exercise (See: Raman Foundry). The sequitur being

    Page 79 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    that satisfaction of the arbitral award as recorded by the Delhi High Court in

    terms of any such judicial or arbitral determination, would not attract liability for

    payment of IGST under the provisions of Section 7 of the CGST Act, as neither

    the payment made by Tata to Docomo, nor Docomo agreeing not to pursue the

    execution/enforcement proceedings, can be regarded to be any ‘supply of

    services’.

    85. In the light of the above discussion, we are inclined to accept the case as

    urged on behalf of the petitioner-Tata for grant of reliefs as prayed for, while

    rejecting the case as urged on behalf of the respondents that the respondents were

    justified in proposing to levy GST on the settlement of arbitral award in the

    proceedings adopted by Docomo under Sections 47 and 48 of ACA.

    86. Now coming to the objections as raised on behalf of the respondents, we

    are also not inclined to accept the case as urged on behalf of the respondents that

    the Writ Petition ought not to be entertained in view of an alternate remedy

    being available to the petitioner-Tata, relying on the decisions which we have

    referred hereinabove. In such context, we may observe that the principles of law

    in regard to the parties being relegated to alternate remedy are well-settled. It is

    purely the discretion of the Court whether its writ jurisdiction needs to be

    exercised or not. Such discretion is required to be judicially exercised. In this

    context, we may refer to the recent decision of the Supreme Court in Godrej Sara

    Lee Limited vs. Excise and Taxation Officer 28 wherein on the Writ Petition to be

    entertained and maintainable, the Supreme Court held thus:-

    28 [(2023) SCC OnLine SC 95]

    Page 80 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    4. …. … … … … The power to issue prerogative writs under Article 226 is
    plenary in nature. Any limitation on the exercise of such power must be
    traceable in the Constitution itself. Profitable reference in this regard may be
    made to Article 329 and ordainments of other similarly worded articles in the
    Constitution. Article 226 does not, in terms, impose any limitation or
    restraint on the exercise of power to issue writs. While it is true that exercise
    of writ powers despite availability of a remedy under the very statute which
    has been invoked and has given rise to the action impugned in the writ
    petition ought not to be made in a routine manner, yet, the mere fact that the
    petitioner before the high court, in a given case, has not pursued the
    alternative remedy available to him/it cannot mechanically be construed as a
    ground for its dismissal. It is axiomatic that the high courts (bearing in mind
    the facts of each particular case) have a discretion whether to entertain a writ
    petition or not. One of the self-imposed restrictions on the exercise of power
    under Article 226 that has evolved through judicial precedents is that the
    high courts should normally not entertain a writ petition, where an effective
    and efficacious alternative remedy is available. At the same time, it must be
    remembered that mere availability of an alternative remedy of appeal or
    revision, which the party invoking the jurisdiction of the high court under
    Article 226 has not pursued, would not oust the jurisdiction of the high court
    and render a writ petition “not maintainable”. In a long line of decisions, this
    Court has made it clear that availability of an alternative remedy does not
    operate as an absolute bar to the “maintainability” of a writ petition and that
    the rule, which requires a party to pursue the alternative remedy provided by
    a statute, is a rule of policy, convenience and discretion rather than a rule of
    law. Though elementary, it needs to be restated that “entertainability” and
    “maintainability” of a writ petition are distinct concepts. The fine but real
    distinction between the two ought not to be lost sight of. The objection as to
    “maintainability” goes to the root of the matter and if such objection were
    found to be of substance, the courts would be rendered incapable of even
    receiving the lis for adjudication. On the other hand, the question of
    “entertainability” is entirely within the realm of discretion of the high courts,
    writ remedy being discretionary. A writ petition despite being maintainable
    may not be entertained by a high court for very many reasons or relief could
    even be refused to the petitioner, despite setting up a sound legal point, if
    grant of the claimed relief would not further public interest. Hence, dismissal
    of a writ petition by a high court on the ground that the petitioner has not
    availed the alternative remedy without, however, examining whether an
    exceptional case has been made out for such entertainment would not be
    proper.

    5. A little after the dawn of the Constitution, a Constitution Bench of
    this Court in its decision reported in 1958 SCR 595 (State of Uttar Pradesh
    vs. Mohd. Nooh
    ) had the occasion to observe as follows:

    10. In the next place it must be borne in mind that there is no
    rule, with regard to certiorari as there is with mandamus, that it
    will lie only where there is no other equally effective remedy. It is
    well established that, provided the requisite grounds exist,
    certiorari will lie although a right of appeal has been conferred by
    statute, (Halsbury’s Laws of England, 3rd Edn., Vol. 11, p. 130
    and the cases cited there). The fact that the aggrieved party has
    another and adequate remedy may be taken into consideration
    by the superior court in arriving at a conclusion as to whether it
    should, in exercise of its discretion, issue a writ of certiorari to

    Page 81 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    quash the proceedings and decisions of inferior courts
    subordinate to it and ordinarily the superior court will decline to
    interfere until the aggrieved party has exhausted his other
    statutory remedies, if any. But this rule requiring the exhaustion
    of statutory remedies before the writ will be granted is a rule of
    policy, convenience and discretion rather than a rule of law and
    instances are numerous where a writ of certiorari has been issued
    in spite of the fact that the aggrieved party had other adequate
    legal remedies. ***”

    6. At the end of the last century, this Court in paragraph 15 of the its
    decision reported in (1998) 8 SCC 1 (Whirlpool Corporation vs. Registrar of
    Trade Marks, Mumbai and Others
    ) carved out the exceptions on the
    existence whereof a Writ Court would be justified in entertaining a writ
    petition despite the party approaching it not having availed the alternative
    remedy provided by the statute. The same read as under:

    (i) where the writ petition seeks enforcement of any of the fundamental
    rights;

    (ii) where there is violation of principles of natural justice;

    (iii) where the order or the proceedings are wholly without jurisdiction; or

    (iv) where the vires of an Act is challenged.

    7. Not too long ago, this Court in its decision reported in 2021 SCC
    OnLine SC 884 (Assistant Commissioner of State Tax vs. M/s. Commercial
    Steel Limited) has reiterated the same principles in paragraph 11.

    8. That apart, we may also usefully refer to the decisions of this Court
    reported in (1977) 2 SCC 724 (State of Uttar Pradesh & ors. vs. Indian
    Hume Pipe Co. Ltd.) and (2000) 10 SCC 482 (Union of India vs. State of
    Haryana
    ). What appears on a plain reading of the former decision is that
    whether a certain item falls within an entry in a sales tax statute, raises a pure
    question of law and if investigation into facts is unnecessary, the high court
    could entertain a writ petition in its discretion even though the alternative
    remedy was not availed of; and, unless exercise of discretion is shown to be
    unreasonable or perverse, this Court would not interfere. In the latter
    decision, this Court found the issue raised by the appellant to be pristinely
    legal requiring determination by the high court without putting the appellant
    through the mill of statutory appeals in the hierarchy. What follows from the
    said decisions is that where the controversy is a purely legal one and it does
    not involve disputed questions of fact but only questions of law, then it
    should be decided by the high court instead of dismissing the writ petition on
    the ground of an alternative remedy being available.”

    (emphasis supplied)

    87. Adverting to the aforesaid settled principles of law, we may observe that

    no doubt the principles of law as laid down by the Supreme Court in the

    decisions as relied on behalf of the respondents in the facts pertaining to the said

    Page 82 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    decisions, are well settled, however, considering the facts of the present case, we

    are not inclined to accept the respondent’s contention that this petition ought not

    to be entertained and the petitioner-Tata needs to be relegated to the remedy of

    appeal. The reason being, that when have we come to a considered conclusion,

    that the designated officer had no jurisdiction to issue a show cause notice, so as

    to bring such demand within the purview of Section 7(1)(c) read with Schedule

    II Entry 5(e), on the basis of what had emanated between the parties, forming

    part of the consent order passed by the Delhi High Court in the proceedings filed

    by Docomo under Sections 47 and 48 of ACA. Thus, when the jurisdictional

    authority itself was absent for the designated officer, to exercise jurisdiction to tax

    a settlement between the parties as arrived in the proceedings for enforcement of

    a foreign arbitral award, in our opinion, there is no gainsaying that the petitioner-

    Tata nonetheless needs to be relegated to an alternate remedy. We have

    accordingly entertained the petition.

    88. While parting, we may also observe that we have discussed only the

    relevant decisions so as not to burden the judgment, considering that such

    decisions, on the issue they decide, lay down the settled principles of law.

    89. Considering the nature of reliefs which we intend to grant to the

    petitioner-Tata, we are not inclined to examine the petitioner-Tata’s alternate

    prayer, namely, challenge as mounted to Section 7 read with Entry 5(e) to

    Schedule II of the CGST Act being illegal and ultra vires.

    90. In the light of the above discussion, we are certain that the petition needs

    Page 83 of 84

    Rane/Amin
    1-WP4914-22RESERVED.DOC

    to be partly allowed. It is accordingly allowed in terms of prayer clauses (a) and

    (ca).

    91. Rule is made absolute in the aforesaid terms.

    92. No costs.

    93. In view of disposal of Writ Petition, Interim Application does not survive

    and the same is accordingly disposed of.

                               (AARTI SATHE, J.)                               (G. S. KULKARNI, J.)
    
    
    
    
    Signed by: Vidya S. Amin                                   Page 84 of 84
    Designation: PS To Honourable Judge
    Date: 30/04/2026 19:06:27 Rane/Amin
     



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here