Saltee Infrastructure Limited vs M/S. Shivam Industrial Parks And … on 1 April, 2026

    0
    39
    ADVERTISEMENT

    Calcutta High Court

    Saltee Infrastructure Limited vs M/S. Shivam Industrial Parks And … on 1 April, 2026

                         IN THE HIGH COURT AT CALCUTTA
                              COMMERCIAL DIVISION                                  2026:CHC-OS:107
    
                                  ORIGINAL SIDE
    
                             RESERVED ON: 04.02.2026
                             DELIVERED ON: 01.04.2026
    
                                       PRESENT:
    
                    THE HON'BLE MR. JUSTICE GAURANG KANTH
    
                                  APOT 259 OF 2025
                                  GA-COM 2 OF 2025
    
                       SALTEE INFRASTRUCTURE LIMITED
                                     VS
               M/S. SHIVAM INDUSTRIAL PARKS AND ESTATES LTD.
    
    Appearance: -
    
    Mr. Sakya Sen, Sr. Adv.
    Mr. Amritam Mandal, Adv.
    Ms. Swati Agarwal, Adv.
                                                      .............. for the appellant
    Mr. Jishnu Chowdhury, Sr. Adv.
    Ms. Ujjaini Chatterjee, Adv.
    Ms. Rekha Dey, Adv.
                                                      .............. for the respondent
    
                                      JUDGMENT
    

    Gaurang Kanth, J. :-

    1. The Appellant has preferred the present Arbitration Petition under Section

    37(2)(b) of the Arbitration and Conciliation Act, 1996, challenging the

    interim award dated 16.05.2025 passed by the learned Sole Arbitrator in

    the arbitral proceedings arising between the parties.

    2. The facts relevant for adjudication of the present petition are briefly noted

    below.

    3. The Respondent is the owner of land measuring 91.5 decimals (55 cottahs)

    situated at Municipal Holding No. 148, Block-A, Gopalpur, Jagardanga

    Main Road, Rajarhat Six Lane Expressway, Kolkata. By a Development

    Agreement dated 07.04.2014, the Appellant was appointed as the
    2
    2026:CHC-OS:107
    developer in respect of the said property, while the Respondent remained

    the landowner. In furtherance thereof, a registered Power of Attorney was

    executed by the Respondent in favour of two representatives of the

    Appellant to facilitate implementation of the development project.

    4. Under the terms of the Development Agreement, the Respondent’s

    obligation was limited to contributing the land, whereas the Appellant was

    responsible for undertaking and financing the development of the project,

    including construction and marketing.

    5. On 20.03.2018, the Appellant obtained building sanction for construction

    of two blocks, namely: (i) Basement + Ground + 7 floors, and (ii) Ground +

    5 floors. The first block (B+G+7), forming part of the project known as

    “Saltee Splendora”, was completed in 2019, following which construction

    of the second phase commenced.

    6. In terms of the agreed sharing arrangement, the Appellant handed over

    four flats with car parking spaces and four shops to the Respondent,

    which were duly accepted. The Appellant also offered seven additional flats

    to the Respondent; however, the Respondent declined to accept the same

    and disputes arose between the parties in relation to deductions towards

    marketing charges, incidental expenses and 10% additional proceeds in

    respect of the increased saleable area.

    7. On 21.12.2022, the Respondent issued a notice terminating the

    Development Agreement on the ground of delay in completion of the

    project. Disputes having arisen between the parties in relation to the

    project and their respective rights and obligations under the Development

    Agreement, the Respondent invoked the arbitration clause contained

    therein and the disputes were referred to arbitration.
    3

    2026:CHC-OS:107

    8. Prior to commencement of the arbitral proceedings, the Respondent filed

    Misc. Case No. 32 of 2023 under Section 9 of the Arbitration and

    Conciliation Act, 1996 before the Commercial Court at Rajarhat. By an

    order passed therein, it was directed that any prospective sale of flats or

    shops in the project would be executed with the Respondent as a

    confirming party, and that the Respondent would be entitled to 40% of the

    sale proceeds, pending disposal of the application. Upon constitution of

    the Arbitral Tribunal, the said arrangement was continued by the

    Tribunal.

    9. During the arbitral proceedings, both parties filed applications under

    Section 17 of the Arbitration and Conciliation Act, 1996. By an order dated

    16.08.2023, the learned Arbitrator modified the earlier interim order and

    restrained the Appellant from entering into fresh agreements for sale or

    creating third party rights in respect of the remaining unsold flats.

    10. Thereafter, upon further applications filed by the Respondent, the Arbitral

    Tribunal, by an order dated 26.02.2024, directed the parties to maintain

    status quo, restrained the Appellant from creating any encumbrance in

    respect of the title deeds, and further directed the Appellant to deposit the

    admitted amount of Rs. 11,54,09,382/- in a nationalised bank, subject to

    the final outcome of the arbitral proceedings.

    11. The Appellant challenged the said order dated 26.02.2024 by filing Misc.

    Appeal (Commercial) No. 3 of 2024 under Section 37 of the Arbitration and

    SPONSORED

    Conciliation Act, 1996 before the Commercial Court at Rajarhat. By an

    order dated 08.07.2024, the said appeal was dismissed.

    12. On 02.03.2024, the Respondent filed a further application under Section

    17 alleging non compliance with the order dated 26.02.2024. By an order
    4
    2026:CHC-OS:107
    dated 24.04.2024, the Arbitral Tribunal appointed Shri Sarbananda

    Sanyal, Advocate, as Receiver with directions to take possession of the

    unsold flats and parking spaces, sell the same and distribute the proceeds

    in accordance with the terms of the Development Agreement. The Receiver

    was also authorised to execute supplementary agreements in the event of

    failure on the part of the Appellant to do so.

    13. By further directions issued on 24.04.2024, the Tribunal directed the

    Appellant to hand over the original title deeds to the Receiver and

    authorised the Receiver to take possession of 42 car parking spaces.

    14. It appears from the record that, pursuant to the supplementary agreement

    executed by the Receiver, the Respondent was authorised to sell four flats

    together with four car parking spaces and four shops, the aggregate value

    of which has been admitted to be Rs. 6,61,01,000/-.

    15. The Arbitral Tribunal thereafter recommended initiation of contempt

    proceedings against the Appellant for alleged non compliance with the

    direction to deposit the amount of Rs. 11,54,09,382/-. On the basis of the

    said recommendation, the Respondent initiated contempt proceedings

    before the Commercial Court at Rajarhat. In view of the Judgment dated

    08.12.2025 passed by this Court, the Respondent withdrew the said

    contempt petition from the Commercial Court at Rajarhat and filed the

    same before this Court, where the matter is presently pending.

    16. In the meantime, the Appellant filed an application before the Arbitral

    Tribunal seeking modification of the order dated 26.02.2024, particularly

    the direction requiring deposit of Rs. 11,54,09,382/-, in view of the

    subsequent developments including the realisation of Rs. 6,61,01,000/-

    and the Receiver having taken possession of the remaining unsold units.
    5

    2026:CHC-OS:107
    By the impugned order dated 16.05.2025, the Tribunal rejected the said

    application.

    17. Aggrieved by the said order dated 16.05.2025, the Appellant has preferred

    the present petition under Section 37(2) of the Arbitration and Conciliation

    Act, 1996.

    18. At the outset, the Respondent raised an objection as to the maintainability

    of the present petition on the ground of territorial jurisdiction. By a

    Judgment dated 08.12.2025, this Court held that it is the Court within the

    meaning of Section 2(1)(e) of the Arbitration and Conciliation Act, 1996 for

    the purpose of the present matter.

    Submission on behalf of the Appellant

    19. Mr. Sakya Sen, learned senior Counsel appearing on behalf of the

    Appellant, submits that the Arbitral Tribunal passed the order dated

    16.05.2025 without taking into consideration the subsequent

    developments and changed circumstances. It is submitted that pursuant

    to the supplementary agreement executed by the Receiver, the Respondent

    was authorised to sell four flats together with four car parking spaces and

    four shops, the aggregate value whereof has been admitted to be Rs.

    6,61,01,000/-. Learned Counsel further submits that the Receiver was

    appointed by order dated 24.04.2024 and has since taken possession of 13

    unsold flats. According to the Appellant, the value of the said flats,

    calculated on the basis of the base rate of the last sold unit, works out to

    Rs. 15,64,61,500/-, out of which the Appellant’s share would be Rs.

    10,35,05,300/-. It is further submitted that, as per the Statement of

    Claim, the total claim of the Respondent is Rs. 14,73,58,358/-. In view of

    the aforesaid developments, learned Counsel contends that the
    6
    2026:CHC-OS:107
    Respondent’s claim already stands sufficiently secured. It is therefore

    submitted that directing the Appellant to furnish an additional security of

    Rs. 11,54,09,382/- would result in the Respondent’s claim being secured

    far in excess of the amount claimed.

    20. Learned Senior Counsel for the Appellant further submits that the

    Respondent’s claim already stands secured in several ways. First, the

    Respondent has been authorised to sell four flats together with four car

    parking spaces and four shops, valued at Rs. 6,61,01,000/-. Secondly, a

    sum of Rs. 1,50,00,000/- is stated to be lying with the Respondent as

    security. Thirdly, the Appellant’s share in the 13 unsold flats presently in

    the custody of the Receiver is valued at Rs. 10,35,05,300/-.

    21. Learned Senior Counsel appearing for the Appellant submits that, as per

    the Statement of Claim, the total value of the Respondent’s claim is Rs.

    14,73,58,358/-. However, the learned Sole Arbitrator, while passing the

    impugned order, erroneously proceeded on the basis that the claim

    amount was Rs. 20,39,25,591/-.

    22. It is further submitted that, while adjudicating the application under

    Section 17 of the Arbitration and Conciliation Act, 1996, the learned

    Arbitrator ought not to have been influenced by the alleged past conduct of

    the Appellant, including the alleged non compliance with earlier directions

    of the Arbitral Tribunal. According to learned Senior Counsel, the relevant

    consideration under Section 17 is confined to ensuring that the claim

    amount in the arbitral proceedings is adequately secured, and not to

    penalise a party for past instances of non compliance. Accordingly, it is

    contended that the direction requiring the Appellant to furnish security

    ought to have been determined solely with reference to the extent
    7
    2026:CHC-OS:107
    necessary to secure the claim amount. In order to substantiate this point,

    the learned counsel for the Appellant relies upon the Judgment of Delhi

    High Court in World Window Infrastructure Pvt Ltd Vs Central

    Warehousing Corporation reported as 2021(3) High court Cases (Del)

    731, and Judgment of the Calcutta High Court in Shivananda Pandey Vs

    Bhagwandas Harlalka reported as 1999 SCC Online Cal 246,

    23. It is contended that the object of granting interim protection under Section

    17 of the Arbitration and Conciliation Act, 1996 is only to secure the claim

    amount during the pendency of the arbitral proceedings. According to the

    Appellant, there is no requirement in law to secure an amount in excess of

    the claim made in the Statement of Claim. In the present case, since the

    Respondent’s claim of Rs. 14,73,58,358/- already stands adequately

    secured, the learned Arbitral Tribunal ought to have modified the earlier

    direction requiring the Appellant to deposit Rs. 11,54,09,382/-,

    particularly in view of the subsequent developments.

    Submission on behalf of the Respondent

    24. Mr. Jishnu Chowdhury, learned Senior Counsel appearing on behalf of the

    Respondent, at the outset submits that it is not correct to contend that the

    Respondent’s claim before the Arbitral Tribunal is confined to Rs.

    14,73,58,358/-. According to him, the said amount represented only a

    partial quantification of the claim at the relevant point of time. Learned

    Senior Counsel submits that from the very beginning the Appellant has

    failed to disclose the actual sale consideration received from the

    prospective purchasers of the units, with the result that the Respondent

    was kept in the dark regarding the true sale value of the units sold by the

    Appellant.

    8

    2026:CHC-OS:107

    25. It is submitted that the Respondent had initially quantified its claim at Rs.

    14,73,58,358/- on the basis of the disclosures made by the Appellant at

    that stage. However, during the course of the arbitral proceedings, the

    Respondent obtained copies of several registered sale deeds, from which

    the actual consideration received by the Appellant came to light. On the

    basis of the said materials, the Respondent contends that the value of its

    claim stands enhanced. Learned Senior Counsel submits that the

    Respondent is entitled to 40% of the sale consideration in terms of the

    Development Agreement and that the final quantification of the claim

    would ultimately be determined by the Arbitral Tribunal at the time of the

    final award. At present, based on the documents available on record, the

    Respondent estimates its claim to be approximately Rs. 20,39,25,591/-,

    which, according to him, ought to be secured.

    26. Learned Senior Counsel for the Respondent further submits that the

    conduct of the Appellant throughout the proceedings demonstrates a lack

    of bona fides. According to him, the Appellant has repeatedly failed to

    comply with the directions passed by the Arbitral Tribunal. In such

    circumstances, it is submitted that the conduct of the Appellant does not

    inspire confidence and that, in the event an award is ultimately passed in

    favour of the Respondent, there is a serious apprehension that the

    Respondent may not be able to realise the awarded amount, thereby

    rendering the award a mere paper award.

    27. Learned Senior Counsel for the Respondent, however, fairly submits that

    certain amounts have already been received by the Respondent. According

    to him, the Respondent has received Rs. 3,73,48,976/- from the Appellant,

    Rs. 6,61,13,820/- towards eight units, and Rs. 1,50,00,000/- towards a
    9
    2026:CHC-OS:107
    security deposit. It is submitted that the security deposit of Rs.

    1,50,00,000/- has already been refunded and therefore cannot be adjusted

    towards the Respondent’s claim.

    28. Learned Senior Counsel submits that, even if the aforesaid amounts are

    taken into account, the total amount presently secured would be Rs.

    11,84,62,976/-, whereas the Respondent’s claim, based on the presently

    available materials, is approximately Rs. 20,39,25,591/-, leaving a balance

    of about Rs. 8,54,62,795/- unsecured. It is further submitted that the

    amount of Rs. 6,61,13,820/- calculated towards eight units cannot be

    treated as entirely belonging to the Respondent, since under the

    Development Agreement only 40% thereof represents the Respondent’s

    share, while 60% belongs to the Appellant. Consequently, the said amount

    cannot be taken into account in a manner so as to suggest that the

    Respondent’s claim is fully secured.

    29. Learned Counsel further submits that the order under challenge is a

    discretionary order passed by the learned Arbitrator in exercise of powers

    under Section 17 of the Arbitration and Conciliation Act, 1996. The scope

    of interference by this Court with such an order is extremely limited and

    would arise only in cases of patent illegality or manifest arbitrariness.

    Reliance is placed on the judgments of the Hon’ble Supreme Court in C &

    C Constructions Ltd. v. Ircon International Ltd. reported as 2025 (4)

    SCC 234 and Somdutt Builders NCC-NEC (JV) v. National Highways

    Authority of India reported as 2025 (6) SCC 757.

    30. In the aforesaid circumstances, learned Senior Counsel for the Respondent

    contends that the Arbitral Tribunal rightly rejected the Appellant’s

    application seeking modification of the earlier order and directed the
    10
    2026:CHC-OS:107
    Appellant to deposit a sum of Rs. 11,54,09,382/-, the same being

    necessary to adequately secure the Respondent’s claim during the

    pendency of the arbitral proceedings. In support of the said submissions,

    reliance is placed upon the judgments of the Delhi High Court in Lava

    International Ltd. v. Mintellectuals LLP, reported as 2024 SCC OnLine

    Del 6908, and Shamlalji Expressway Pvt. Ltd. v. NHAI, reported as

    2024 SCC OnLine Del 7131.

    Legal Analysis

    31. This Court has considered the rival submissions advanced on behalf of the

    parties and has perused the materials placed on record.

    32. The present appeal has been filed under Section 37(2) of the Arbitration

    and Conciliation Act, 1996, challenging the order dated 16.05.2025 passed

    by the learned Arbitral Tribunal whereby the Appellant’s application

    seeking modification of the earlier order directing deposit of Rs.

    11,54,09,382/- came to be rejected.

    33. At the outset, it is necessary to note that the scope of interference under

    Section 37 of the Act is limited. An appellate court exercising jurisdiction

    under Section 37 does not sit in appeal over the merits of the interim order

    as a court of first instance. Interference is warranted only where the order

    impugned is shown to be arbitrary, perverse, or contrary to the settled

    principles governing the grant of interim measures.

    34. The impugned order arises from the exercise of powers by the Arbitral

    Tribunal under Section 17 of the Arbitration and Conciliation Act, 1996,

    which empowers the Tribunal to grant interim measures during the

    pendency of the arbitral proceedings, including directions for securing the

    amount in dispute in the arbitration. The purpose of such an order is
    11
    2026:CHC-OS:107
    essentially protective, namely to ensure that the successful party is not left

    with an arbitral award which cannot be effectively enforced. At the same

    time, the power under Section 17 is not intended to operate as a penal

    measure, nor to direct security beyond what is reasonably necessary to

    safeguard the claim pending adjudication. The limited scope of judicial

    interference with such discretionary orders of the Arbitral Tribunal has

    been recognised by the Hon’ble Supreme Court and most recently in C & C

    Constructions Ltd. (supra) and Somdutt Builders NCC-NEC (JV) (supra).

    35. The principal contention of the Appellant is that the Respondent’s claim, as

    reflected in the Statement of Claim, was Rs. 14,73,58,358/-, and that

    subsequent developments have already secured the said claim. It is

    submitted that the Receiver appointed by the Arbitral Tribunal has taken

    possession of 13 unsold flats, the value of which, based on the base rate of

    the last sold unit, is stated to be Rs. 15,64,61,500/-, out of which the

    Appellant’s share would be approximately Rs. 10,35,05,300/-. The

    Appellant also relies upon the admitted claim towards the sale of four flats

    together with four car parking spaces and four shops, amounting to Rs.

    6,61,01,000/-, as well as other amounts received by the Respondent, to

    contend that the Respondent’s claim already stands adequately secured. It

    is therefore argued that directing deposit of an additional amount of Rs.

    11,54,09,382/- results in the claim being secured more than once over.

    36. The Respondent disputes the aforesaid contention. According to the

    Respondent, the amount of Rs. 14,73,58,358/- mentioned in the

    Statement of Claim was only a provisional quantification based on the

    disclosures made by the Appellant at the relevant time. It is contended

    that the Appellant had failed to disclose the actual consideration received
    12
    2026:CHC-OS:107
    from the purchasers of the units, and that during the arbitral proceedings

    the Respondent obtained copies of several registered sale deeds, which

    indicated that the sale consideration received was higher than what had

    been disclosed earlier. On the basis of the materials presently available,

    the Respondent asserts that its claim stands at approximately Rs.

    20,39,25,591/-, subject to final determination by the Arbitral Tribunal.

    The Respondent has also emphasised the alleged non compliance by the

    Appellant with earlier directions of the Arbitral Tribunal, contending that

    the impugned order was necessary to ensure that the Respondent’s claim

    does not remain unsecured.

    37. Having considered the rival submissions, it is evident that the controversy

    essentially concerns the extent to which the Respondent’s claim presently

    stands secured, and whether the direction requiring the Appellant to

    deposit Rs. 11,54,09,382/- is disproportionate in light of the subsequent

    developments relied upon by the Appellant.

    38. The materials on record indicate that the Receiver appointed by the Arbitral

    Tribunal has taken possession of certain unsold units. However, the

    precise valuation of the said units and the ultimate entitlement of the

    Respondent are matters that necessarily fall for final adjudication before

    the Arbitral Tribunal upon appreciation of the evidence. At this

    interlocutory stage, the Court is not required to undertake a detailed

    examination of the competing valuations or to finally determine the extent

    of the parties’ respective entitlements.

    39. Learned Senior Counsel for the Respondent relied upon the judgments of

    the Delhi High Court in Lava International Ltd. (supra) and Shamlalji

    Expressway Pvt. Ltd. (supra) to contend that the Arbitral Tribunal, while
    13
    2026:CHC-OS:107
    exercising powers under Section 17 of the Arbitration and Conciliation Act,

    1996, is empowered to direct furnishing of security so as to ensure that

    the successful party is not ultimately left with a mere paper award. On the

    other hand, learned Senior Counsel for the Appellant relied upon World

    Window Infrastructure Pvt. Ltd. (supra) and Shivananda Pandey

    (supra) to contend that an order directing furnishing of security ought not

    to result in securing an amount in excess of the claim as reflected in the

    Statement of Claim.

    40. The legal principles enunciated in the aforesaid decisions are not in

    dispute, and this Court respectfully concurs with the propositions laid

    down therein. However, as also emphasized in the said judgments, the

    exercise of the power to grant interim protection must necessarily depend

    upon the facts and circumstances of each case, and any direction for

    securing the claim must bear a reasonable nexus with the claim sought to

    be protected. In the present case, the Respondent has contended that the

    amount reflected in the Statement of Claim represented only a provisional

    quantification based on the disclosures made by the Appellant at the

    relevant time, and that subsequent materials obtained during the course

    of the arbitral proceedings indicate that the claim amount may be higher.

    The final determination of the Respondent’s entitlement and the precise

    quantification of the claim are matters that fall within the domain of the

    Arbitral Tribunal and would be adjudicated at the stage of the final award.

    In such circumstances, the applicability of the aforesaid decisions must

    necessarily be assessed in the context of the factual matrix of the present

    case.

    14

    2026:CHC-OS:107

    41. Upon considering the factual matrix in detail, the Arbitral Tribunal arrived

    at the conclusion that a sum of Rs. 11,54,09,382/- was required to be

    secured in order to protect the claims raised by the Respondent. The

    determination of the quantum of security to be furnished, in the context of

    an application under Section 17 of the Arbitration and Conciliation Act,

    1996, squarely falls within the domain and discretion of the Arbitral

    Tribunal. It is also pertinent to note that the said amount has been

    directed to be deposited in a nationalised bank and would remain intact

    pending the final adjudication of the disputes between the parties. Upon

    the final determination of the claims, the amount would be released to the

    party found entitled thereto. In these circumstances, it cannot be said that

    the Arbitral Tribunal has exercised its discretion arbitrarily or

    unreasonably. This Court does not find any perversity or arbitrariness in

    the impugned order warranting interference in exercise of appellate

    jurisdiction under Section 37 of the Act.

    42. In view of the foregoing discussion, this Court is of the considered view that

    the impugned order dated 16.05.2025 passed by the learned Arbitral

    Tribunal does not warrant interference in exercise of appellate jurisdiction

    under Section 37 of the Arbitration and Conciliation Act, 1996. The order

    impugned is essentially an interim protective measure passed in exercise

    of powers under Section 17 of the Act with the object of securing the

    Respondent’s claim pending adjudication of the arbitral proceedings.

    43. The discretion exercised by the Arbitral Tribunal does not suffer from any

    arbitrariness, perversity, or violation of settled principles governing interim

    measures, so as to justify interference by this Court in appeal.
    15

    2026:CHC-OS:107

    44. The exact quantification of the Respondent’s claim and the respective

    entitlements of the parties are matters which fall within the domain of the

    Arbitral Tribunal and shall be determined on the basis of the evidence

    adduced before it at the stage of the final award. Any observations made in

    the present order are confined to the adjudication of the present appeal

    and shall not influence the Arbitral Tribunal while deciding the disputes

    on merits.

    45. The present appeal under Section 37(2) of the Arbitration and Conciliation

    Act, 1996 is accordingly dismissed. All pending applications, if any, also

    stand dismissed.

    (Gaurang Kanth, J.)
    SAKIL AMED (P.A)



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here