S & S Technocrat Pvt. Ltd vs Hindustan Letex Ltd on 23 July, 2026

    0
    6
    ADVERTISEMENT

    Delhi High Court

    S & S Technocrat Pvt. Ltd vs Hindustan Letex Ltd on 23 July, 2026

                      *      IN THE HIGH COURT OF DELHI AT NEW DELHI
                      %                                 Judgment reserved on: 06.07.2026
                                                     Judgment pronounced on: 23.07.2026
                      +      O.M.P. (COMM) 398/2018
                             S & S TECHNOCRAT PVT. LTD.                       .....Petitioner
                                                 Through:   Mr. Vivekanand &              Mr.
                                                            Abhishek Semwal, Advs.
                                                 versus
    
                             HINDUSTAN LETEX LTD.                            .....Respondent
                                                 Through:   Mr. Nikhilesh Krishnan, Mr.
                                                            Siddharth Singh, Mr. Karna
                                                            Mehra & Ms. Ritika Priya,
                                                            Advs.
    
                             CORAM:
                             HON'BLE MR. JUSTICE AVNEESH JHINGAN
                                                 JUDGMENT
    

    1. This petition is filed under Section 34 of the Arbitration and
    Conciliation Act, 1996 (for short „the Act‟) seeking setting aside of
    arbitral award dated 05.05.2018.

    Brief Facts

    SPONSORED

    2. The brief facts are that on 10.02.2006, the respondent,
    Hindustan Letex Ltd (for short, „HLL‟) invited a tender for
    construction of an Office Complex. The petitioner, M/s S&S
    Technocrats Pvt. Ltd. (for short, „SSTPL‟) was the successful bidder
    and Letter of Acceptance (LOA) dated 17.03.2006 was issued for a
    total value of Rs.3,48,85,500/-. The parties to the lis entered into a

    Signature Not Verified
    Signed By:CHANCHAL
    Signing Date:23.07.2026
    O.M.P. (COMM) 398/2018 Page 1 of 23
    18:21:46
    contract dated 31.05.2006 and the work was to be completed within
    fifteen months from the date of commencement i.e., 27.03.2006.
    2.1 The scope of contract was enhanced by including an additional
    floor and the period for completion was extended till 26.08.2007. The
    work could not be completed within the stipulated period and time
    was extended till 16.05.2009.

    2.2 Dispute arose between the parties and on 20.05.2009 the
    petitioner invoked arbitration under clause 31 of the General
    Conditions of Contract (for short „GCC‟). The work was not
    completed within the extended period and the respondent terminated
    the contract on 15.02.2010.

    2.3 The decision on claims and counter-claims in the award are
    tabulated below:

                                           CLAIM                                 DECISION
                      CLAIM NO. 1                                              Partly Allowed
    

    Claim towards release of payment due under the (Gross final bill to be paid and
    Final Bill after deducting the payments received to be calculated as per
    against the running bills Annexure „F‟ after contractual
    deductions. 12% p.a. interest
    granted on awarded amount
    subject to adjustments of HLL
    awarded dues).

    CLAIM NO. 2 Rejected
    Claim towards payment of increase in rates other
    than the deviated/ extra items executed beyond
    the permissible deviation limit i.e., 10% of the
    contract amount
    CLAIM NO. 3 Rejected
    Claim towards escalation on electrical works
    CLAIM NO. 4 Allowed Conditionally
    Claim towards release of security deposit (Security Deposit to be
    computed on gross amount of
    final bill and released after

    Signature Not Verified
    Signed By:CHANCHAL
    Signing Date:23.07.2026
    O.M.P. (COMM) 398/2018 Page 2 of 23
    18:21:46
    adjustment of awarded dues of
    respondent. Interest @12%
    p.a. awarded after expiry of
    one year defect liability period
    from 15.02.2010).

                      CLAIM NO. 5                                                Allowed
                      Claim towards release of Performance Bank       (Performance Bank Guarantee
                      Guarantee                                       released subject to recovery of
                                                                      awarded      dues      of    the
                                                                      respondent).
                      CLAIM NO. 6                                                Rejected
    

    Claim towards losses suffered for engaging
    additional staff and machinery during the
    extended period

    CLAIM NO. 7 Rejected
    Claim towards reimbursement of Bank
    Guarantee commission paid after the completion
    date
    CLAIM NO. 8 Partly Allowed
    Claim towards pre-suit and pendente lite interest (Pre-suit and pendente lite
    at 18% per annum on Claims Nos. 1, 2, 3 and 4 interest @ 12% p.a. awarded
    on claim nos. 1 & 4).

                      CLAIM NO. 9
                      Claim towards declaration that termination of the            Rejected
                      contract is illegal
                      CLAIM NO. 10                                                 Rejected
                      Litigation / Arbitration Costs
                      ADDITIONAL CLAIM                                             Rejected
                      Claim towards reimbursement of renewal
    

    charges of Contractors All Risk and Workmen
    Compensation Policy (for short „CAR Policy‟)

    COUNTER-CLAIM NO. 1(a)
    Claim towards recovery of liquidated damages Liquidated damages @ 7.5%
    @ 7.5% on the gross work done on gross value of XVIth &
    final bill awarded with 12%
    p.a. interest.

    COUNTER-CLAIM NO. 2 Rejected

    Signature Not Verified
    Signed By:CHANCHAL
    Signing Date:23.07.2026
    O.M.P. (COMM) 398/2018 Page 3 of 23
    18:21:46
    Claim towards reimbursement of office rent for
    the extended period
    COUNTER-CLAIM NO. 3 Rejected
    Claim towards payment of minimum electricity
    charges for new office building
    COUNTER-CLAIM NO. 4 Partly Allowed
    Claim towards reimbursement of insurance paid (Rs.3,85,516/- towards CAR
    and the interest on premium amount policy premium awarded with
    12% p.a. interest subject to a
    maximum of Rs.40,479/-).

    COUNTER-CLAIM NO. 5 Rejected
    Claim towards extra expenditure incurred for
    engaging professionals during the extended
    period beyond 10.01.2009
    COUNTER-CLAIM NO. 6 Rejected
    Claim towards additional amount claimed by
    Architects due to prolongation of contract
    (claims after10.01.2009 only included).

                      COUNTER-CLAIM NO. 7                                     Partly Allowed
                      Claim towards expenditure incurred for making (Claim       of     Rs.2,93,980/-
                      the building habitable                         allowed to the extent of
                                                                     Rs.1,04,977/- with 12% p.a.
                                                                     interest).
    
                      COUNTER-CLAIM NO. 8                                       Rejected
    

    Claim towards expenditure likely to be incurred
    on rectification of defects
    COUNTER-CLAIM NO. 9 Partly Allowed
    Claim towards inadequate deployment of (Claim of Rs. 31,40,000/-
    qualified engineers allowed to the extent of
    Rs.6,90,000/-).

                      COUNTER-CLAIM NO. 10                                        Rejected
                      Litigation Costs
                      COUNTER-CLAIM NO. 11                                        Rejected
    

    Claim towards loss of interest on Counter Claims
    Nos. 1-8

    The challenge to the impugned award by petitioner while arguing the
    matter was confined to claim nos. 1,2,3,6 & 9 and counter-claim no.
    1(a).

    Signature Not Verified
    Signed By:CHANCHAL
    Signing Date:23.07.2026
    O.M.P. (COMM) 398/2018 Page 4 of 23
    18:21:46

    Submissions of the Parties

    3. Learned counsel for the petitioner submits that claim no. 1 was
    partly allowed without considering that the procedure prescribed
    under clause 15(d) of the Special Conditions of Contract (for short
    ‘SCC’) was not followed. The submission is that the rates proposed by
    the internal committee and approved by the respondent were not
    binding on the petitioner. Reliance is on the Minutes of Meeting (for
    short „MoM‟) dated 19.01.2007 wherein the consultant agreed to
    recommend the rates for approval but instead the rates were
    subsequently determined by a committee constituted by the
    respondent. The contention is that the arbitrator failed to adjudicate
    the issue by not deciding the prevailing market rates in accordance
    with clause 15(d).

    3.1 The contention is that the arbitrator erred in relying on clause
    19 of the SCC in rejecting claim no.2 for payment of increased rates
    for deviated and extra items beyond variable limit under clause 15(a)
    of the SCC. The argument is that the claim was not on account of
    prolongation of the contract but for revised rates of deviated and extra
    items for additional works beyond the permissible deviation provided
    under clause 15(a) of the SCC. It is contended that the rates were to be
    determined in terms of clause 15(d) of the SCC and clause 19 of the
    SCC was not applicable.

    3.2 The rejection of claim nos. 3 & 6 relating to payment of
    escalation in electrical work and loss suffered on account of

    Signature Not Verified
    Signed By:CHANCHAL
    Signing Date:23.07.2026
    O.M.P. (COMM) 398/2018 Page 5 of 23
    18:21:46
    maintaining additional staff and machinery during the extended period
    of execution of the contract is challenged on the ground that Sections
    55
    and 73 of the Indian Contract Act, 1872 (for short, ‘Contract Act‘)
    were not considered.

    3.3 The grievance is that no reasons were assigned while deciding
    the claims and the award is in violation of Section 31(3) of the Act.

    3.4 It is submitted that claim no. 9 challenging the termination of
    the contract was wrongly rejected without considering that the Virtual
    Completion Certificate (for short „VCC‟) was issued certifying that
    the building was fit for occupation. The arbitrator ignored that the
    incomplete works enumerated by the respondent were recorded on
    23.11.2009 whereas the contract was terminated on 15.02.2010 and
    work done in between was not considered. The building was taken
    over by the respondent, inaugurated and put to use yet the contract
    was terminated. It is canvassed that extension was granted up to
    16.05.2009 and no further period for completion was fixed thereby
    rendering the time for completion of the work open-ended. Reliance is
    placed upon the decision of the Supreme Court in Hind
    Constructions v. State of Maharashtra
    (1979) 2 SCC 70 to fortify
    the contention that the contract could be terminated only after fixing a
    final time for completion and making time the essence of the contract.

    3.5 Lastly, the grievance is that counter-claim no. 1(a) was allowed
    awarding liquidated damages (for short „LD‟) for the delay in
    completion of the work not attributable to the petitioner and in the

    Signature Not Verified
    Signed By:CHANCHAL
    Signing Date:23.07.2026
    O.M.P. (COMM) 398/2018 Page 6 of 23
    18:21:46
    absence of evidence of actual loss suffered or a genuine pre-estimate
    of loss. The contention is that an adverse inference should be drawn
    against the respondent for failure to produce the hindrance register.
    Further that the arbitrator failed to consider the material evidence
    while concluding that the delay was attributable to the petitioner. The
    argument is that the respondent granted extension up to 16.05.2009
    without levy of damages indicating that the delay was not attributable
    to the petitioner. It is emphasized that the loss suffered was neither
    quantified nor proved yet the maximum amount provided under clause
    19 of the GCC was awarded as LD.

    4. Per contra, the arbitrator passed a detailed award. The scope of
    interference under Section 34 of the Act is limited and the Court
    cannot sit in appeal over the award. The view taken by the arbitrator is
    a plausible one and cannot be interfered with, for another possible
    view. Reliance is placed upon Dyna Technologies Pvt. Ltd. v.
    Crompton Greaves Ltd.
    , 2009 SCC OnLine SC 1656 and
    Hindustan Construction Company Ltd. v. Union of India
    2019
    SCC OnLine SC 1520.

    4.1 The rejection of claim no. 1 is defended and the submission is
    that clause 15(d) nowhere provides that the rates recommended by the
    consultant shall be binding on the respondent. It is submitted that an
    internal committee was constituted to determine the prevailing market
    rates and the rates approved by the respondent were binding on the
    petitioner.

    Signature Not Verified
    Signed By:CHANCHAL
    Signing Date:23.07.2026
    O.M.P. (COMM) 398/2018 Page 7 of 23
    18:21:46

    4.2 The rejection of claim no. 2 is defended by stating that the
    permissible variation limits are provided under clause 15(a) whereas
    the mechanism for fixation of rates is given under clause 15(d) and
    clause 15 is to be read as a whole. It is argued that reliance upon the
    MoM dated 19.01.2007 is misplaced.

    4.3 Claim nos. 3 and 6 are asserted to have been rightly rejected in
    view of clauses 17 & 19. Clause 17 of the SCC provides that time was
    the essence of the contract and the work was to be completed within
    the stipulated period. Clause 19 of the SCC debars claim of
    compensation by the petitioner for loss suffered on account of delay in
    commencement or execution of the work irrespective of the cause of
    delay. Further that the work was not completed within the extended
    period and the petitioner was not entitled to claim compensation
    contrary to the contractual provisions. Reliance is placed upon the
    decision of the Supreme Court in Nabha Power Ltd. v. Punjab State
    Power Corporation Ltd. & Anr.
    (2018) 11 SCC 508.

    4.4 It is argued that the respondent could terminate the contract
    under clause 29(i) of the GCC for failure of the petitioner to maintain
    the progress and to execute the work within prescribed period. The
    emphasis is that despite extension of time and issuance of notices the
    work was not completed in time. The issue raised is that issuance of
    the VCC and taking over of the building was not the proof of
    completion of work as per the contract. The respondent got the
    balance work executed at the risk and cost of the petitioner.

    Signature Not Verified
    Signed By:CHANCHAL
    Signing Date:23.07.2026
    O.M.P. (COMM) 398/2018 Page 8 of 23
    18:21:46

    4.5 It is contended that the LD was worked out at the time of
    preparation of the final bill after assessing the total cost and recording
    the balance measurements. The LD determined is a factual finding and
    calls for no interference under Section 34 of the Act. The emphasis is
    that a number of letters were written to the petitioner stating that the
    respondent was incurring huge expenditure in running the offices
    which were to be shifted upon completion of the project and the LD
    was awarded considering the loss suffered and is not liable to be
    tinkered with.

    5. Heard learned counsel for the parties at length. Though written
    submissions and factual notes were filed by the parties but during the
    course of arguments only the contentions and issues mentioned above
    were raised and pressed.

    6. Before proceeding further it would be relevant to reproduce the
    relevant clauses of the GCC and SCC:

    “Clause 15 of SCC
    Variations, Extra/ Substituted items
    15(a) Existing BOQ rates shall apply if the variation is ±
    25% in quantity of individual items and ± 10% of the total
    contract price. For items existing in the bill of quantities but
    where quantities have increased beyond the variation limits,
    the rate payable for quantity in excess of the quantity in the
    Bill of Quantity plus the permissible variation should be
    market rates of materials and labour.

    (b) Within 7 days of date of instruction for executing varied
    work, extra work or substituted works and before the
    commencement of such work, notice shall be given either (i)
    by the Contractor to the Employer/Consultant of his

    Signature Not Verified
    Signed By:CHANCHAL
    Signing Date:23.07.2026
    O.M.P. (COMM) 398/2018 Page 9 of 23
    18:21:46
    intention to claim extra payment or a varied rate or price or

    (ii) by the Employer/Consultant to the Contractor of his
    intention to vary a rate or price”.

    (d) In the case of extra items, whether additional, altered or
    substituted for which rates cannot be derived either from
    similar items of work in the contract or from CPWD-
    schedule, the Contractor shall submit to the Employer the
    rates which he proposes to claim supported by rate analysis
    of the item based on the prevailing rates of material and
    labour and allowing contractor‟s profit of 10%. The rates of
    such items shall be recommended by the Consultant and
    approved by the Employer and shall be binding to the
    Contractor.

    Clause 17 of SCC
    Time shall be considered as the essence of the Contract. The
    entire work must be completed in 15 Calendar months. It is
    intended that the general works should be so completed as
    to leave the last two months for installations and finishing
    items. The attention of the tenderer is drawn to Clause 19 of
    the general conditions contract referring to damages for
    non-completion. The tenderer shall before commencing
    work prepare a detailed work programme which shall be
    approved by the Employer/Consultant.

    Clause 19 of SCC
    The contractor shall not be entitled to any compensation of
    any loss suffered by him on account of delays in
    commencing or executing the work whatever the cause of
    delays may be including delays arising out of modification
    to the work entrusted to him or any sub contracts (refer
    clause 10) connected there with or delays in awarding
    contracts for other trades of the project or in commencement
    or completion of such works or in procuring government
    controlled or other building materials or obtaining water and
    power connection for construction purposes or for any other
    reason whatsoever and the Employer shall not be liable for
    claim in respect thereof. The Employer does not accept

    Signature Not Verified
    Signed By:CHANCHAL
    Signing Date:23.07.2026
    O.M.P. (COMM) 398/2018 Page 10 of 23
    18:21:46
    liability for any sum besides the tender amount subject only
    to such variations as may be provided for herein.
    Clause 19 of GCC
    Damages for non-completion
    If the contractor fails to complete the work and clear the site
    on or before the dates fixed for completion, he shall without
    prejudice be liable to pay liquidation damage (LD) ie. 0.5%
    the contract value for every week that the whole or the part
    of work remains Incomplete. The contract value shall be the
    total value of quantities of items in the contract at the
    contract rate plus algebraic sum of the subsequent work
    ordered. However the total amount of LD to be paid under
    this condition shall not exceed 7.5% of the contract value.
    Such amounts may be deducted by the employer from any
    money due or that may become due to the contractor.

    Clause 23(i) of GCC
    When the contractor successfully completes the works as
    per the contract, he shall be eligible to apply for provisional
    completion certificate in respect of the works. The
    Employer shall issue to the Contractor the provisional
    completion certificate after verifying from the completion
    documents submitted by the Consultant and satisfying
    himself that the work has been completed in accordance
    with the construction drawings and the contract documents.
    The contractor, after obtaining the provisional completion
    certificate, is eligible to present the final bill for the wok
    executed by him under the terms of the contract.
    Clause 29(i) of GCC
    Default of Contractor
    If the contractor fails to maintain progress and quality of
    work proportionate to time period allotted for the work in
    spite of notices or complete the work within the stipulated
    time period or extended time period, then the
    consultant/owner shall have the right:-

    Signature Not Verified
    Signed By:CHANCHAL
    Signing Date:23.07.2026
    O.M.P. (COMM) 398/2018 Page 11 of 23
    18:21:46

    (i)To determine the contract: In this event, the contract
    shall be terminated by giving written notice to the contractor
    and the unfinished works shall be got completed by labours
    engaged by the owner or through other agency at the cost of
    the contractor.”

    Analysis

    7. Claim no.1 is against the deductions made from the final bill.
    The dispute comprised of three parts: (a) dispute regarding rates of
    items; (b) admissibility of extra items; and (c) short measurement of
    items. During the arbitral proceedings, disputes under (b) & (c) were
    resolved between the parties and only the dispute regarding rates of
    items survived and was adjudicated.

    8. As per clause 15(a) of the SCC, in case of variation of ±25% in
    individual items and ±10% in the contract price, payment for the
    excess quantity is to be made at the prevailing market rates of material
    and labour. Under clause 15(b) variation beyond the prescribed limits
    under clause 15(a) could be brought to the notice of the other party by
    either party. Clause 15(d) provides the mechanism for determining the
    rates of extra, additional, altered or substituted items where the rates
    cannot be derived from similar items in the contract or the CPWD
    Schedule. For such items the contractor had to submit a rate analysis
    based on the prevailing market rates, whereafter the consultant was to
    recommend the rates and on approval by the employer, these would be
    binding on the contractor. The grievance is that the rates were not
    recommended by the consultant but were recommended by an internal
    committee for which there was no clause under the contract. The issue

    Signature Not Verified
    Signed By:CHANCHAL
    Signing Date:23.07.2026
    O.M.P. (COMM) 398/2018 Page 12 of 23
    18:21:46
    whether the rates determined contrary to the procedure under clause
    15(d) would be binding on the petitioner was not considered by the
    arbitrator. The submissions of the parties were recorded in the award
    but there is no discussion or reasoning as to why the procedure
    adopted by the respondent for determination of rates can be accepted.
    The arbitrator decided the claims as per Annexure „F‟ which contains
    calculations of quantities and rates but there are no reasons as to how
    the conclusion was arrived at.

    9. Under Section 31(3) of the Act, the arbitrator is obligated to
    pass a reasoned award. The award is bereft of reasons and after
    reading the award as a whole along with the annexures no reasons are
    forthcoming. The award falls within the teeth of Section 31(3) of the
    Act. Reference in this regard be made to the following decision of the
    apex court:-

    10. The Supreme Court in Dyna Technologies Pvt. Ltd. (supra)
    has held as under:

    “34. The mandate under Section 31(3) of the Arbitration Act
    is to have reasoning which is intelligible and adequate and,
    which can in appropriate cases be even implied by the
    courts from a fair reading of the award and documents
    referred to thereunder, if the need be. The aforesaid
    provision does not require an elaborate judgment to be
    passed by the arbitrators having regard to the speedy
    resolution of dispute.”

    11. The petitioner in claim no. 2 sought for increase in the rates of
    deviated/extra items utilised beyond the prescribed limit under clause

    Signature Not Verified
    Signed By:CHANCHAL
    Signing Date:23.07.2026
    O.M.P. (COMM) 398/2018 Page 13 of 23
    18:21:46
    15(a) of the SCC. The arbitrator relying upon clause 19 of the SCC
    proceeded on the basis that the petitioner was claiming revised rates
    on account of prolongation of the contract. The claim was for fixation
    of rates in terms of clause 15(d) and not on account of contract
    continuing beyond the agreed period. Clause 19 of the SCC deals with
    compensation for loss suffered on account of delay whereas clause 15
    provides the mechanism for determining the rates of extra items. The
    claim could not have been rejected by relying upon clause 19, without
    considering the applicability of clause 15. The arbitrator proceeded on
    a wrong foundation, the relevant clauses of the contract were not
    considered and the award suffers from patent illegality.

    12. The judgement in Nabha Power Ltd. (supra) pressed into
    service to buttress the argument that the contractual terms are to be
    given effect to, is of no help. Present is a case of non-consideration of
    the relevant clauses and their applicability to the claims raised thereby
    rendering the award liable to be set aside being patently illegal.

    13. The Supreme Court in Delhi Metro Rail Corporation Ltd. V.
    Delhi Airport Metro Express Pvt. Ltd.
    2024 INSC 292 and Bharat
    Coking Coal Ltd. v. Annapurna Construction
    (2003) 8 SCC 154
    held that non-consideration of a relevant clause of the contract is a
    patent illegality and renders the award liable to be set aside. The
    relevant paras are:

    13.1 In Delhi Metro Rail Corporation Ltd. (supra) held as under:

    “38. In Associate Builders vs. Delhi Development
    Authority22
    , a two-judge Bench of this Court held that

    Signature Not Verified
    Signed By:CHANCHAL
    Signing Date:23.07.2026
    O.M.P. (COMM) 398/2018 Page 14 of 23
    18:21:46
    although the interpretation of a contract is exclusively
    within the domain of the arbitrator, construction of a
    contract in a manner that no fair-minded or reasonable
    person would take, is impermissible. A patent illegality
    arises where the arbitrator adopts a view which is not a
    possible view. A view can be regarded as not even a
    possible view where no reasonable body of persons could
    possibly have taken it. This Court held with reference to
    Sections 28(1)(a) and 28(3), that the arbitrator must take
    into account the terms of the contract and the usages of trade
    applicable to the transaction. The decision or award should
    not be perverse or irrational. An award is rendered perverse
    or irrational where the findings are (i) based on no evidence;

    (ii) based on irrelevant material; or (iii) ignores vital
    evidence. Patent illegality may also arise where the award is
    in breach of the provisions of the arbitration statute, as when
    for instance the award contains no reasons at all, so as to be
    described as unreasoned. A fundamental breach of the
    principles of natural justice will result in a patent illegality,
    where for instance the arbitrator has let in evidence behind
    the back of a party. In the above decision, this Court
    observed:

    “31. The third juristic principle is that a
    decision which is perverse or so irrational
    that no reasonable person would have arrived
    at the same is important and requires some
    degree of explanation. It is settled law that
    where:

    (i) a finding is based on no evidence, or

    (ii) an Arbitral Tribunal takes into account
    something irrelevant to the decision which it
    arrives at; or

    (iii) ignores vital evidence in arriving at its
    decision,
    such decision would necessarily be perverse.

    42.2. (b) A contravention of the Arbitration
    Act
    itself would be regarded as a patent

    Signature Not Verified
    Signed By:CHANCHAL
    Signing Date:23.07.2026
    O.M.P. (COMM) 398/2018 Page 15 of 23
    18:21:46
    illegality — for example if an arbitrator
    gives no reasons for an award in
    contravention of Section 31(3) of the Act,
    such award will be liable to be set aside.”

    40. In essence, the ground of patent illegality is
    available for setting aside a domestic award, if the decision
    of the arbitrator is found to be perverse, or so irrational that
    no reasonable person would have arrived at it; or the
    construction of the contract is such that no fair or reasonable
    person would take; or, that the view of the arbitrator is not
    even a possible view.24 A „finding‟ based on no evidence at
    all or an award which ignores vital evidence in arriving at its
    decision would be perverse and liable to be set aside under
    the head of „patent illegality‟. An award without reasons
    would suffer from patent illegality. The arbitrator commits a
    patent illegality by deciding a matter not within his
    jurisdiction or violating a fundamental principle of natural
    justice.”

    13.2 In Bharat Coking Coal Ltd. v. Annapurna Construction,
    (2003) 8 SCC 154 held as under:

    “22. There lies a clear distinction between an error within
    the jurisdiction and error in excess of jurisdiction. Thus, the
    role of the arbitrator is to arbitrate within the terms of the
    contract. He has no power apart from what the parties have
    given him under the contract. If he has travelled beyond the
    contract, he would be acting without jurisdiction, whereas if
    he has remained inside the parameters of the contract, his
    award cannot be questioned on the ground that it contains an
    error apparent on the face of the record.”

    (emphasis supplied)

    14. Claim nos. 3 & 6 relates to escalation in the rates of electrical
    items and expenses incurred on maintaining staff and machinery
    during the extended period of execution of the contract. The claims

    Signature Not Verified
    Signed By:CHANCHAL
    Signing Date:23.07.2026
    O.M.P. (COMM) 398/2018 Page 16 of 23
    18:21:46
    were rejected by relying upon clause 19 of the SCC. The petitioner
    made claims under Sections 55 and 73 of the Contract Act and
    contended that the delay was attributable to the respondent. The
    arbitrator rejected the claims in the light of clause 19 of the SCC
    without dealing with the applicability of the provisions of the Contract
    Act
    . No reasons are recorded for concluding that the provisions of the
    Contract Act were not required to be considered in view of clause 19
    of the SCC. The award is non-speaking and is in violation of Section
    31(3)
    of the Act.

    15. There is no quarrel with the proposition propounded by learned
    counsel for the respondent that a plausible view taken by the arbitrator
    should not be interfered with under Section 34 of the Act and the court
    cannot re-appreciate the evidence. The judgment in Dyna
    Technologies Pvt. Ltd
    (supra) relied upon by the learned counsel for
    the respondent to contend that the award has to be read as a whole
    does not advance the case of the respondent. It was held that the
    reasons for arriving at a conclusion should be discernible from the
    award. In the present case, the conclusions recorded by the arbitrator
    are unsupported by reasons and the material contractual clauses
    governing claims were not considered.

    16. It is trite law that this court while exercising jurisdiction under
    Section 34 of the Act does not sit in appeal. A possible view taken by
    the arbitrator on appreciation of evidence or interpretation of the terms
    of the contract in the normal course does not warrant interference.
    Reliance placed by the respondent on Hindustan Construction

    Signature Not Verified
    Signed By:CHANCHAL
    Signing Date:23.07.2026
    O.M.P. (COMM) 398/2018 Page 17 of 23
    18:21:46
    Company Ltd.
    (supra) on the proposition that the scope of
    interference under Section 34 is limited is of no avail. It is settled law
    that interference can be made on the grounds mentioned under Section
    34
    of the Act including patent illegality. In Ramesh Kumar Jain v.
    Bharat Aluminium Company Limited (BALCO
    ) 2025 INSC 1457
    held:-

    “28. The bare perusal of section 34 mandates a narrow
    lens of supervisory jurisdiction to set aside the arbitral
    award strictly on the grounds and parameters enumerated in
    sub-section (2) & (3) thereof. The interference is permitted
    where the award is found to be in contravention to public
    policy of India; is contrary to the fundamental policy of
    Indian Law; or offends the most basic notions of morality or
    justice. Hence, a plain and purposive reading of the section
    34
    makes it abundantly clear that the scope of interference
    by a judicial body is extremely narrow. It is a settled
    proposition of law as has been constantly observed by this
    court and we reiterate, the courts exercising jurisdiction
    under section 34 do not sit in appeal over the arbitral award
    hence they are not expected to examine the legality,
    reasonableness or correctness of findings on facts or law
    unless they come under any of grounds mandated in the said
    provision. In ONGC Limited. v. Saw Pipes Limited14, this
    court held that an award can be set aside under Section 34
    on the following grounds: “(a) contravention of fundamental
    policy of Indian law; or (b) the interest of India; or (c)
    justice or morality, or (d) in addition, if it is patently
    illegal.”

    16.1 In Parsa Kente Collieries Limited. v. Rajasthan Rajya
    Vidyut Utpadan Nigam Limited (2019) 7 SCC 236 held as under:-

    “9.1. In Associate Builders [Associate Builders v. DDA,
    (2015) 3 SCC 49 : (2015) 2 SCC (Civ) 204] , this Court had

    Signature Not Verified
    Signed By:CHANCHAL
    Signing Date:23.07.2026
    O.M.P. (COMM) 398/2018 Page 18 of 23
    18:21:46
    an occasion to consider in detail the jurisdiction of the Court
    to interfere with the award passed by the Arbitrator in
    exercise of powers under Section 34 of the Arbitration Act.

    In the aforesaid decision, this Court has considered the
    limits of power of the Court to interfere with the arbitral
    award. It is observed and held that only when the award is in
    conflict with the public policy in India, the Court would be
    justified in interfering with the arbitral award. In the
    aforesaid decision, this Court considered different heads of
    “public policy in India” which, inter alia, includes patent
    illegality………”

    (emphasis supplied)

    17. The claim no. 9 pertains to termination of the contract. Under
    clause 29(i) of the GCC the respondent could terminate the contract
    for failure of the petitioner to complete the work within the stipulated
    or extended period. A written notice to the petitioner was a pre-
    requisite for termination. The work remained incomplete despite
    extension of time and issuance of notices. The petitioner responded to
    the notices and thereafter the contract was terminated. The arbitrator
    analysed the definition of „Virtual completion‟ and clause 23(i) of the
    GCC regarding the completion certificate and held that the Provision
    Completion certificate (for brevity „PCC‟) is the relevant document
    and not the VCC. Under clause 23(i), upon completion of the work
    the contractor was eligible to apply for the PCC and the petitioner
    never applied for the PCC, this was factored in to conclude that the
    work was not completed. The arbitrator also took into consideration
    the fact that the unfinished works subsequently were executed by the
    respondent at the risk and cost of the petitioner. The eight letters

    Signature Not Verified
    Signed By:CHANCHAL
    Signing Date:23.07.2026
    O.M.P. (COMM) 398/2018 Page 19 of 23
    18:21:46
    written by the respondent that the work was not complete and the
    letter of petitioner dated 04.02.2010 stating that five items under the
    head „Extinguisher‟ were pending, demonstrated that the work was
    incomplete till 04.02.2010. The petitioner despite the specific query of
    the arbitrator with regard to the work done between 25.11.2009 and
    15.02.2010 produced no details. The reliance of the petitioner on
    applications made to statutory authorities for issuance of the
    completion certificate and NOC was held to be of no avail as the work
    to be completed under the contract and the requirement under the
    statute were different.

    18. The contention that after 16.05.2009 there was no extension of
    time and the contract was open-ended is ill-founded. The petitioner
    failed to complete the work within the extended time. By writing eight
    letters the petitioner was put to notice of inordinate delay in
    completion of the work and was reminded that the work had to be
    completed in a timely manner. Reliance on Hind Constructions
    (supra) does not advance the case of the petitioner. It was held that
    where time is not the essence of the contract, termination of the
    contract for failure to complete the work within the stipulated period
    cannot be sustained. Whereas in the present case, clause 17 expressly
    provides that time was the essence of the contract and clause 29(i)
    permitted termination of the contract for failure to maintain progress
    or to complete the work within the extended period. Moreover, the
    petitioner was put to notice to complete the work within the extended
    time and after receiving response to the notices, the contract was

    Signature Not Verified
    Signed By:CHANCHAL
    Signing Date:23.07.2026
    O.M.P. (COMM) 398/2018 Page 20 of 23
    18:21:46
    terminated as per clause 29(i) of the GCC. The upholding of
    termination of the contract is a plausible view and suffers from no
    factual or legal error much less perversity.

    19. Before proceeding further, it would be relevant to quote the
    following decisions of the Supreme Court dealing with the principles
    governing award of LD or penalty:-

    19.1 The Supreme Court in Kailash Nath Associates v. DDA (2015)
    4 SCC 136 held:

    “43.1. Where a sum is named in a contract as a liquidated
    amount payable by way of damages, the party complaining
    of a breach can receive as reasonable compensation such
    liquidated amount only if it is a genuine pre-estimate of
    damages fixed by both parties and found to be such by the
    court. In other cases, where a sum is named in a contract as
    a liquidated amount payable by way of damages, only
    reasonable compensation can be awarded not exceeding the
    amount so stated. Similarly, in cases where the amount fixed
    is in the nature of penalty, only reasonable compensation
    can be awarded not exceeding the penalty so stated. In both
    cases, the liquidated amount or penalty is the upper limit
    beyond which the court cannot grant reasonable
    compensation.

    43.2. Reasonable compensation will be fixed on well-known
    principles that are applicable to the law of contract, which
    are to be found inter alia in Section 73 of the Contract Act.
    43.3. Since Section 74 awards reasonable compensation for
    damage or loss caused by a breach of contract, damage or
    loss caused is a sine qua non for the applicability of the
    section.

    43.4. The section applies whether a person is a plaintiff or a
    defendant in a suit.

    Signature Not Verified
    Signed By:CHANCHAL
    Signing Date:23.07.2026
    O.M.P. (COMM) 398/2018 Page 21 of 23
    18:21:46

    43.5. The sum spoken of may already be paid or be payable
    in future.

    43.6. The expression “whether or not actual damage or loss
    is proved to have been caused thereby” means that where it
    is possible to prove actual damage or loss, such proof is not
    dispensed with. It is only in cases where damage or loss is
    difficult or impossible to prove that the liquidated amount
    named in the contract, if a genuine pre-estimate of damage
    or loss, can be awarded.”

    19.2 The Supreme Court in State of Rajasthan v. Ferro Concrete
    Construction (P) Ltd.
    , (2009) 12 SCC 1 held:

    “55.While the quantum of evidence required to accept a
    claim may be a matter within the exclusive jurisdiction of
    the arbitrator to decide, if there was no evidence at all and if
    the arbitrator makes an award of the amount claimed in the
    claim statement, merely on the basis of the claim statement
    without anything more, it has to be held that the award on
    that account would be invalid. Suffice it to say that the
    entire award under this head is wholly illegal and beyond
    the jurisdiction of the arbitrator, and wholly unsustainable.”

    20. The position of law that emerges is that for claiming LD the
    actual loss suffered is to be proved, except in cases where it is difficult
    or impossible to prove the actual loss. The arbitrator awarded LD in
    the absence of evidence adduced of actual loss suffered by the
    respondent or concluding that it was impossible or difficult to prove
    actual loss. The only material relied upon were the letters written by
    the respondent to the petitioner stating that huge expenditure was
    being incurred due to delay in shifting the offices to the building in
    question and continuing the offices in rented accommodation. The
    claim for LD in the statement of claim was not substantiated. It is not

    Signature Not Verified
    Signed By:CHANCHAL
    Signing Date:23.07.2026
    O.M.P. (COMM) 398/2018 Page 22 of 23
    18:21:46
    the case set that there were genuine pre-estimated damages fixed by
    the parties. The 7.5% of the gross value fixed in the contract was the
    upper limit for awarding damages and not a pre-estimate of damages.
    There was no material on record to quantify the loss suffered yet
    contrary to the settled position of law the maximum amount
    prescribed under clause 19 of the GCC was awarded as LD.

    21. In view of the above discussion the petition is allowed and the
    impugned award is set aside.

    AVNEESH JHINGAN, J.

    JULY 23, 2026
    ‘ha’
    Reportable:- Yes

    Signature Not Verified
    Signed By:CHANCHAL
    Signing Date:23.07.2026
    O.M.P. (COMM) 398/2018 Page 23 of 23
    18:21:46



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here