Ramanand Mahto vs Ashwath Quippo Infra Projects Pvt. Ltd on 25 April, 2026

    0
    39
    ADVERTISEMENT

    Delhi High Court – Orders

    Ramanand Mahto vs Ashwath Quippo Infra Projects Pvt. Ltd on 25 April, 2026

                                   $~7
                                   *        IN THE HIGH COURT OF DELHI AT NEW DELHI
                                   +        ARB.P. 251/2026 & I.A. 3409/2026
                                            RAMANAND MAHTO                                                       .....Petitioner
                                                       Through:                            Mr. Sanjay Bansal, Adv. (Through
                                                                                           VC)
                                                                                           M: 9810959432
                                                                                           Email:
                                                                                           [email protected]
                                                                         versus
    
                                            ASHWATH QUIPPO INFRA PROJECTS PVT.
                                            LTD.                                                                           .....Respondent
                                                        Through: None
    
                                            CORAM:
                                            HON'BLE MS. JUSTICE MINI PUSHKARNA
                                                                         ORDER
    

    % 25.04.2026

    1. The present petition has been filed under Section 11(6) of the
    Arbitration and Conciliation Act, 1996 (“Arbitration Act“), seeking
    appointment of a Sole Arbitrator, for adjudication of disputes between the
    parties, arising out of the Work Order dated 10th January, 2019, executed
    between the parties.

    SPONSORED

    2. Office Noting shows that the respondent has been served by the
    Registry, through E-mail as well as the ordinary mode.

    3. None appears for the respondent, despite service, when the matter is
    called out.

    4. Accordingly, this Court proceeds with the matter.

    5. Learned counsel for the petitioner submits that the aforesaid Work
    Order had been executed between the parties for “Pushing of MS pipe

    Page 1 of 4

    This is a digitally signed order.

    The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above.
    The Order is downloaded from the DHC Server on 25/04/2026 at 20:37:02
    through trenchless pipe jacking & pushing of RCC NP4 pipe through Micro
    Tunneling Method at Delhi Jal Board R1A Ashok Vihar Delhi”, whereunder,
    the petitioner undertook to complete the construction work in question for
    the respondent, in lieu of compensation.

    6. He submits that the petitioner completed the construction work, and
    consequently, raised a bill amounting to Rs. 10,78,992/- (Rupees Ten Lacs
    Seventy-Eight Thousand Nine Hundred Ninety-Two Only) on the
    respondent. During verification of the bill in question, the respondent
    reduced the amount to Rs. 10,24,128/- (Rupees Ten Lacs Twenty-Four
    Thousand One Hundred Twenty-Eight Only) vide bill dated 05th September,
    2020.

    7. He further submits that although the work in question was completed,
    the respondent is yet the pay the balance payment amounting to Rs.
    10,24,128/- (Rupees Ten Lacs Twenty-Four Thousand One Hundred
    Twenty-Eight Only), along with interest on delayed payment. Thus, disputes
    have arisen between the parties.

    8. He draws the attention of this Court to Clause 19 of the Work Order,
    to submit that there exists an Arbitration Clause between the parties, i.e.,
    Clause 19 of the Work Order.

    9. He further draws the attention of this Court to a notice dated 05th
    December, 2024, which was issued to the respondent, thereby, invoking the
    aforesaid Arbitration Clause, in terms of Section 21 of the Arbitration Act,
    along with Speed Post receipt for sending the same.

    10. Learned counsel for the petitioner submits that despite the same, the
    respondent failed to reply to the notice dated 05th December, 2024.

    11. The aforesaid Clause 19 of the Work Order dated 10th January, 2019,

    Page 2 of 4

    This is a digitally signed order.

    The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above.
    The Order is downloaded from the DHC Server on 25/04/2026 at 20:37:02
    is reproduced as under:

    “xxx xxx xxx

    xxx xxx xxx”

    12. Further, a reference may also be made to Clause 21 of the Work Order
    dated 10th January, 2019, which is reproduced as under:

    “xxx xxx xxx

    xxx xxx xxx”

    13. Perusal of the aforesaid Clauses, i.e., Clauses 19 and 21, clearly
    shows that there exists a valid arbitration agreement between the parties, and
    that the arbitration shall be held at Delhi/New Delhi. Further, the Courts at
    New Delhi have exclusive jurisdiction.

    14. At this stage, the Court records the statement of the learned counsel
    appearing for the petitioner that the petitioner has a claim of approximately
    Rs. 15,00,000/- (Rupees Fifteen Lacs Only).

    15. Thus, this Court is satisfied that there are disputes between the parties
    and there is a valid Arbitration Clause, and accordingly, the disputes are to
    be adjudicated by way of referring the parties to arbitral proceedings.

    16. Thus, this Court finds no impediment in appointing a sole Arbitrator

    Page 3 of 4

    This is a digitally signed order.

    The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above.
    The Order is downloaded from the DHC Server on 25/04/2026 at 20:37:02
    for adjudication of the disputes between the parties, and the following
    directions are issued in this regard:

    i. Ms. Parul Khosla, Advocate (Mob: +91- 9899013803) is appointed as
    the sole Arbitrator to adjudicate the disputes between the parties.
    ii. The remuneration of the Arbitrator shall be in terms of Schedule IV of
    the Arbitration Act
    .

    iii. The learned Arbitrator is requested to furnish a declaration in terms of
    Section 12 of the Arbitration Act prior to entering into the reference. In the
    event of any impediment to the Arbitrator’s appointment on that count, the
    parties are given liberty to file an appropriate application before this Court.
    iv. It shall be open to the respondent to raise counter-claims, if any, in the
    arbitration proceedings.

    v. It is made clear that all the rights and contentions of the parties,
    including, as to the arbitrability of any of the claim, any other preliminary
    objection, as well as claims/counter-claims on merits of the dispute of either
    of the parties, are left open for adjudication by the learned Arbitrator.
    vi. The parties shall approach the learned Arbitrator within two (02)
    weeks from today.

    17. Accordingly, the present petition, along with pending application, if
    any, is disposed of in the aforesaid terms.

    18. The Registry is directed to send a copy of this order to the learned
    Arbitrator, for information and compliance.

    MINI PUSHKARNA, J
    APRIL 25, 2026/KR

    Page 4 of 4

    This is a digitally signed order.

    The authenticity of the order can be re-verified from Delhi High Court Order Portal by scanning the QR code shown above.
    The Order is downloaded from the DHC Server on 25/04/2026 at 20:37:02



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here