Jammu vs 3. Comptroller on 3 August, 2026

    0
    8
    ADVERTISEMENT

    Jammu & Kashmir High Court

    Jammu vs 3. Comptroller on 3 August, 2026

                                                                                 2026:JKLHC-JMU:2377
                                                                        Serial No. 180
    
      HIGH COURT OF JAMMU & KASHMIR AND LADAKH
                      AT JAMMU
    WP (C) No. 168/2023
    
                                              Reserved on: 21.07.2026.
                                              Pronounced o: 03.08.2026.
                                              Uploaded on: 03 .08.2026.
    M/S Construction Engineer,
    54- Industrial Estate Barzulla, Srinagar.
    Through its Attorney Holder,
    Mohd Hussain Malik, S/o Ghulam Mohd
    R/o Matto Colony Trikuta Nagar Extension
    Jammu.
                                                         .... Appellant(s)/Petitioner(s)
                               Through: Mr. D.C. Raina, Sr. Advocate with
                                        Mr. Anuj Dewan Raina, Advocate.
                                        Mr. Mohd Junid, Advocate.
    
                         V/s
    
    
    01.    Sher-e-Kashmir University of
           Agricultural Sciences & Technology, Jammu.
           SKUAST-J.
           Through its Registrar.
    
    02.    Estate Officer
           Agricultural Sciences & Technology, Jammu.
           SKUAST-J.
    
    03.    Comptroller,                                                ..... Respondent(s)
           Agricultural Sciences & Technology, Jammu.
           SKUAST-J.
           Main Campus Chatha, Jammu.
    
    
                               Through: Mr. Anil Khajuria, Advocate.
    
    CORAM: HON'BLE MR. JUSTICE SANJAY PARIHAR, JUDGE
    
                                        JUDGMENT
    

    01. The petitioner was earlier awarded the work, namely, “Construction

    of Boys Hostel Building (G+1) along with associated sanitary and

    SPONSORED

    WP(C) No. 168/2023 Page 1 of 15
    2026:JKLHC-JMU:2377

    internal electrification work of FOA, Main Campus, District

    Jammu.” According to the petitioner, despite having executed the

    work in terms of the contract, the respondents failed to release the

    payments due to him. Aggrieved by the non-payment and claiming

    interest on the delayed release of dues, the petitioner was constrained

    to invoke the jurisdiction of this Court under Section 11(6) of the

    Jammu and Kashmir Arbitration and Conciliation Act, 1997. The said

    petition was allowed by this Court vide order dated 20.12.2013,

    pursuant whereof an Arbitrator was appointed. The learned Arbitrator

    rendered an award dated 31.10.2016, whereby price escalation and

    interest were awarded in favour of the petitioner. The respondents

    challenged the said arbitral award by filing an application for setting

    aside the award before the learned Principal District Judge, Jammu;

    however, the said application came to be dismissed.

    02. It is further submitted that thereafter the petitioner served a legal

    notice dated 01.09.2020 upon the respondents calling upon them to

    release the earnest money amounting to Rs. 11,00,000/-, the

    performance security of Rs. 18,00,000/-, and the bill deposit

    pertaining to the aforesaid work. Since the year 2021, the petitioner

    has been repeatedly pursuing the respondents for the release of the

    aforesaid amounts, which continue to be unjustifiably withheld.

    Finding no response from the respondents, the petitioner has been

    constrained to seek writ of mandamus against respondents.

    03. The respondents, on the other hand, have resisted the writ petition by

    contending that the aforesaid amounts have been withheld on account

    WP(C) No. 168/2023 Page 2 of 15
    2026:JKLHC-JMU:2377

    of disputes that had arisen between the parties, which formed the

    subject matter of the arbitral proceedings. According to the

    respondents, although the petitioner succeeded before the learned

    Arbitrator as well as before the learned Principal District Judge,

    Jammu, the arbitral award has been challenged before this Court and

    the matter is presently sub judice. It is, therefore, contended that the

    release of the earnest money, performance security and bill deposit at

    this stage would be premature.

    04. The respondents have further objected to the maintainability of the

    writ petition on the ground that while raising his claims before the

    learned Arbitrator, the petitioner had also sought refund of the security

    deposit. It is further submitted that the Arbitration and Conciliation

    Act provides a complete and comprehensive mechanism for

    adjudication of disputes and enforcement of arbitral awards, and,

    therefore, the present writ petition amounts to an attempt to bypass the

    statutory remedy available under the said Act. The respondents further

    contend that, having admitted before the learned Arbitrator that the

    claim included refund of the earnest money and bill deposit, the

    petitioner is precluded from re-agitating the same issue by way of the

    present writ proceedings.

    05. Learned counsel for the petitioner argued that the contract amount had

    already been paid to the petitioner during the financial year 2011-

    2012 and that the only amount remaining payable was the interest on

    the delayed payment, which constituted the sole dispute requiring

    adjudication before the learned Arbitrator. It was submitted that the

    WP(C) No. 168/2023 Page 3 of 15
    2026:JKLHC-JMU:2377

    respondents themselves had contended before the Arbitrator that,

    since the principal amount had been paid in full, the petitioner’s claim

    for interest was not maintainable. Thus, according to the petitioner,

    the only issue that fell for consideration before the Arbitrator was

    whether the petitioner was legally entitled to interest on the delayed

    payment of the principal amount. The learned Arbitrator answered the

    issue in favour of the petitioner by holding that the petitioner was

    entitled to interest on the delayed payment and passed the award

    accordingly.

    06. It was further submitted that the arbitral proceedings were confined

    exclusively to the petitioner’s claim for interest and that, under the

    award, the petitioner had been granted interest, including interest upon

    interest, calculated up to 31.10.2016. Learned counsel contended that

    the earnest money deposit of ₹11 lakh, the performance security of

    ₹18 lakh, and the bill deposit were never the subject matter of the

    arbitration proceedings. Had those amounts been in dispute, the

    respondents would have specifically contested those claims before the

    learned Arbitrator as well.

    07. Responding to the objections raised by the respondents under Order II

    Rule II of the Code of Civil Procedure, learned counsel for the

    petitioner submitted that the said provision had no application to the

    facts and circumstances of the present case.

    08. Inviting the attention of the Court to the stand taken by the

    respondents before the High Court in the earlier proceedings, learned

    counsel argued that the respondents had never disputed the petitioner’s

    WP(C) No. 168/2023 Page 4 of 15
    2026:JKLHC-JMU:2377

    entitlement to payment for the work executed. On the contrary, their

    stand was that no arbitrable dispute existed between the parties

    warranting the appointment of an Arbitrator, as the dispute projected

    by the petitioner was allegedly not covered by the arbitration

    agreement. It was further pointed out that the University itself had

    taken up the matter with the Government for early submission of the

    requisite report and release of the outstanding payment.

    09. In support of the petition, learned counsel placed reliance upon the

    judgment of the Supreme Court in Union of India & Ors. v. Bali Ram,

    reported as 2026 INS 689. It was argued that the petitioner was legally

    entitled to the amounts in question, which had been unjustifiably

    withheld by the respondents despite there being no counterclaim

    alleging defective or incomplete execution of the work. According to

    the petitioner, the respondents were seeking to deny the release of the

    admitted amounts by raising purely technical objections. It was,

    therefore, submitted that this Court, in exercise of its writ jurisdiction,

    ought to render substantial justice by directing the release of the

    amounts wrongfully withheld, particularly when there was no material

    on record to suggest that the petitioner had committed any procedural

    breach disentitling it to such relief.

    10. Per contra, learned counsel appearing for the respondents contended

    that, once the petitioner had invoked the arbitration clause and

    pursued its claims before the learned Arbitrator, it was incumbent

    upon the petitioner to claim all reliefs to which it considered itself

    entitled, including the refund of the performance security and earnest

    WP(C) No. 168/2023 Page 5 of 15
    2026:JKLHC-JMU:2377

    money. Having consciously omitted to seek such reliefs in the arbitral

    proceedings, the petitioner was now estopped from raising those

    claims by invoking the writ jurisdiction of this Court. It was further

    submitted that the present claim was barred by the principles of res

    judicata and was also hit by the provisions of Order II Rule II of the

    Code of Civil Procedure.

    11. Heard counsels for the parties and have gone through record.

    12. A contract entered into between the parties is required to be performed

    in accordance with its terms, and the reciprocal contractual obligations

    are to be discharged in the manner contemplated by law. Once the

    contractual obligations stand duly performed, the corresponding

    liability to make payment arises. Where the contract amount is not

    paid within the stipulated time, the delay in payment gives rise to a

    claim for interest. In the present case, the dispute that was referred to

    arbitration pertained solely to the petitioner’s claim for interest on

    account of delayed payment. The pleadings reveal that the petitioner

    had been awarded the contract for the construction of the “Boys

    Hostel Building (G+1) along with associated sanitary and internal

    electrification works at FOA, Main Campus, District Jammu.” Upon

    completion of the work, allegations surfaced that the then Vice-

    Chancellor had committed certain irregularities by creating liabilities

    to the tune of ₹28.44 crores and by executing a majority of the works

    during his tenure without obtaining the requisite technical sanction,

    allegedly amounting to an abuse of power. Consequently, the

    Government constituted a Committee to inquire into the matter, and

    WP(C) No. 168/2023 Page 6 of 15
    2026:JKLHC-JMU:2377

    the respondent-University took the stand that it would furnish all

    necessary information to the said Committee.

    13. As the petitioner had completed the contractual work but was not paid

    the amounts due within time, he was constrained to invoke the

    jurisdiction of this Court by filing an application under Section 11(6)

    of the Arbitration and Conciliation Act, seeking the appointment of an

    Arbitrator. The application was allowed, and an Arbitrator was

    appointed to adjudicate the disputes between the parties.

    14. Before the learned Arbitrator, the petitioner claimed interest on the

    payments received on different dates in respect of Item Nos. I, II, III

    and V of the contract. The respondent-University, on the other hand,

    raised a counterclaim alleging that the petitioner had abandoned the

    construction of the boys’ hostel along with its allied works despite

    having received the mobilisation advance, thereby causing substantial

    financial loss to the University.

    15. During the arbitral proceedings, the respondent-University asserted

    that the principal contractual amount had already been paid and placed

    on record the details of the payments made to the petitioner. In view

    of the admitted payment of the principal amount, the learned

    Arbitrator confined the adjudication to the issue of interest and held

    that the petitioner was entitled to interest on the delayed payments,

    consequently passing an award directing payment of interest on the

    admitted liability. The respondents challenged the arbitral award

    before the District Court under Section 34 of the Arbitration and

    Conciliation Act; however, the challenge was dismissed. Aggrieved

    WP(C) No. 168/2023 Page 7 of 15
    2026:JKLHC-JMU:2377

    thereof, the respondents have preferred separate proceedings before

    this Court, which are presently pending adjudication. Through the

    present writ petition, the petitioner seeks the release of the earnest

    money deposit of ₹11 lakh and the performance security of ₹18 lakh,

    contending that the said amounts have been unlawfully withheld by

    the respondents despite repeated requests and the issuance of a legal

    notice. According to the petitioner, since the contractual work stands

    completed and the respondents have admitted their liability under the

    contract, the only dispute between the parties pertains to the quantum

    of interest awarded on account of delayed payment. The respondents,

    however, object to the maintainability of the writ petition on the

    ground that the contractual disputes are already the subject matter of

    arbitral proceedings and the pending challenge before this Court.

    16. The aforesaid objection, prima facie, does not appear to have any legal

    merit. Once a party has duly performed its contractual obligations and

    the employer has acknowledged such performance without raising any

    subsisting claim regarding breach or defective execution, it cannot

    subsequently contend that the performance security or earnest money

    may continue to be withheld or forfeited to secure any possible future

    liability. An employer who has accepted satisfactory completion of the

    contract is under a legal obligation to refund the security deposit in

    accordance with the terms of the contract and cannot indefinitely

    retain the same in the absence of any enforceable claim. This principle

    is well settled and finds support from a consistent line of judicial

    precedents rendered by the constitutional courts.

    WP(C) No. 168/2023 Page 8 of 15

    2026:JKLHC-JMU:2377

    17. In Maula Bux v. Union of India, reported as AIR 1970 SC 1955, the

    Supreme Court explained the nature of earnest money, holding that it

    is a deposit made by the purchaser to be adjusted towards the sale

    consideration upon completion of the contract and, until then, serves

    as evidence of the purchaser’s intention to perform the contract. It was

    held that the forfeiture of a reasonable amount of earnest money under

    a contract for sale of property does not ordinarily attract the provisions

    of Section 74 of the Indian Contract Act. The Court further observed

    that the expression “whether or not actual damage or loss is proved to

    have been caused thereby” occurring in Section 74 is intended to

    cover different classes of contracts. In certain cases, the loss

    occasioned by breach may be incapable of precise assessment,

    whereas in others it may be readily ascertainable. In the facts of that

    case, the contract empowered the Government to recover from the

    contractor any additional expenditure incurred in procuring the

    supplies or services agreed to be furnished under the contract.

    However, the Trial Court found that the Government of India had

    failed to adduce any evidence to establish that it had suffered any loss

    on account of the plaintiff’s alleged default and, consequently, held

    that the security deposit was not liable to be forfeited. Although the

    High Court observed that the contractual terms permitted forfeiture of

    the security deposit upon the contractor’s failure to perform his

    obligations, it was also noticed that, despite having ample opportunity,

    the Government had failed to prove either the alleged breach or the

    loss suffered by it. The Supreme Court declined the Government’s

    WP(C) No. 168/2023 Page 9 of 15
    2026:JKLHC-JMU:2377

    request for a further opportunity to lead evidence regarding the alleged

    loss and, while modifying the High Court’s direction relating to

    interest, upheld the contractor’s entitlement to the refund of the

    performance security, directing the Union of India to release the same.

    18. In Union of India v. Rampur Distillery and Chemical Co., reported as

    AIR 1973 SC 1098, the Supreme Court considered the issue of

    forfeiture of a security deposit furnished to ensure due performance of

    a contract. The Court observed that the security deposit had been

    furnished solely as a guarantee for the proper performance of the

    contractual obligations and that, in the event of a default, the contract

    contemplated forfeiture of the deposit. However, as the appellants had

    failed to establish that they had suffered any loss or damage on

    account of the alleged breach committed by the respondents, the

    Supreme Court held that the security deposit could not be treated as

    earnest money so as to justify its forfeiture. Following the principles

    laid down in Maula Bux v. Union of India, the Court rejected the

    appellants’ claim to forfeit the security deposit in the absence of proof

    of any loss suffered by them.

    19. Similarly, in Bharat Sanchar Nigam Limited v. Teracom Limited

    [O.M.P. (COMM) 431/2019 & I.A. No. 14326/2019], the Delhi High

    Court, while dealing with a similar issue, held that there was no

    justification for BSNL to forfeit or retain any amount recovered

    against the performance bank guarantee in the absence of any claim

    alleging failure on the part of the contractor to perform its contractual

    obligations. The Court observed that, once BSNL had acknowledged

    WP(C) No. 168/2023 Page 10 of 15
    2026:JKLHC-JMU:2377

    due performance of the contract and had not asserted any subsisting

    claim for breach or damages, there existed no legal principle that

    would entitle it to continue retaining the performance security.

    Accordingly, it was held that the employer was under an obligation to

    release the performance security after accepting satisfactory

    completion of the contractual work.

    20. In the present case, the respondents, in their objections, have

    unequivocally admitted that at no point of time did they dispute the

    satisfactory execution of the contract by the petitioner. In fact, the

    stand now advanced by the learned counsel for the respondents is

    contrary to the consistent position adopted by the University

    throughout the arbitral proceedings and the earlier litigation. During

    the course of hearing, learned counsel for the petitioner invited the

    attention of the Court to the objections filed by the University in the

    proceedings instituted by the petitioner under Section 11(6) of the

    Arbitration and Conciliation Act, wherein it was specifically pleaded

    that the Works Committee of the University, in its meeting held on

    11.02.2010, had resolved to release 60% of the work-done liabilities,

    subject to fulfilment of the requisite codal formalities. The University

    had, in fact, maintained that no dispute existed between the parties

    warranting reference to arbitration and had opposed the appointment

    of an Arbitrator on the ground that the existence of an arbitrable

    dispute is a condition precedent for invoking Section 11 of the Act.

    The respondents had further pleaded, particularly in paragraph 12 of

    their objections, that no dispute subsisted between the parties and that

    WP(C) No. 168/2023 Page 11 of 15
    2026:JKLHC-JMU:2377

    the University had already approached the Government for the early

    submission of the report of the Committee constituted to examine the

    liabilities incurred during the tenure of the then Vice-Chancellor.

    According to the University, in the absence of the said report, it was

    unable to release the remaining payments and, therefore, the request

    for appointment of an Arbitrator was premature.

    21. The aforesaid stand of the University clearly demonstrates that,

    insofar as the contractual dues were concerned, the respondents never

    disputed their liability and intended to discharge the contractual

    obligations upon completion of the requisite formalities. The only

    issue that ultimately came to be referred to arbitration related to the

    petitioner’s claim for interest on account of delayed payment, and the

    award rendered thereon is admittedly the subject matter of separate

    proceedings pending before this Court. The question, therefore, that

    falls for consideration in the present petition is whether the petitioner

    can be deprived of the refund of the earnest money and performance

    security, which continue to remain with the respondents despite there

    being no allegation of breach of contract or unsatisfactory execution

    of work on the part of the petitioner.

    22. Mr. Anil Khajuria, learned counsel appearing for the respondents,

    argued that the counterclaim raised by the University in the arbitral

    proceedings is still pending adjudication in the challenge proceedings

    and that any liability which may ultimately be fastened upon the

    petitioner could be satisfied out of the earnest money and performance

    security lying with the University. It was, therefore, contended that the

    WP(C) No. 168/2023 Page 12 of 15
    2026:JKLHC-JMU:2377

    respondents possess a lien over the said amounts and are justified in

    withholding their release. The said contention was refuted by the

    learned counsel for the petitioner, who submitted that once the

    contractual work stands completed and the respondents themselves

    have admitted the contractual liability, there exists no legal

    justification for retaining the earnest money or performance security.

    It was further submitted that, even assuming the respondents’

    contention to be correct, the petitioner is willing to furnish an

    undertaking that any liability which may hereafter be determined

    against him shall be duly discharged in accordance with law.

    23. The respondents further contended that the relief sought in the present

    writ petition is barred by the provisions of Order II Rule II of the Code

    of Civil Procedure, inasmuch as the petitioner, while pursuing the

    arbitral proceedings, did not seek refund of the earnest money and

    performance security. Although the submission appears attractive at

    first blush, it cannot withstand judicial scrutiny in the factual matrix of

    the present case. Once the contract had been fully performed and the

    respondents had accepted the completion of the work without alleging

    any breach or deficiency, the petitioner’s reference to arbitration was

    confined solely to his claim for interest on delayed payment of the

    admitted contractual dues. The petitioner had no occasion to seek

    refund of the earnest money and performance security before the

    Arbitrator, particularly when the respondents themselves had

    consistently maintained that no dispute existed which was capable of

    being referred to arbitration. Having adopted such a stand, the

    WP(C) No. 168/2023 Page 13 of 15
    2026:JKLHC-JMU:2377

    respondents cannot now be permitted to contend that the petitioner

    ought to have included the relief of refund of the security deposits in

    the arbitral proceedings. A party which admits due performance of the

    contract and raises no claim for breach cannot assert any lien over the

    contractor’s security deposit merely on the speculative ground that

    some liability may arise in future. Such retention is contrary to the

    contractual relationship between the parties and cannot be sustained in

    law. Even otherwise, the petitioner has invoked the extraordinary

    jurisdiction of this Court seeking a writ of mandamus for enforcement

    of an undisputed legal right, namely, the refund of amounts which the

    respondents are under a legal obligation to release. The bar contained

    in Order II Rule II CPC, therefore, has no application to the facts of

    the present case.

    24. The reliance placed by the respondents on the judgment of the

    Supreme Court in Devilal Modi v. Sales Tax Officer, Ratlam & Ors.,

    AIR 1965 SC 1150, is wholly misconceived. Learned counsel for the

    respondents has been unable to demonstrate how the principles laid

    down in the said decision are attracted to the facts of the present case.

    The reliance is, therefore, misplaced and does not advance the case of

    the respondents.

    25. The respondents cannot be permitted to take refuge behind procedural

    or technical objections in order to evade their legal obligation to

    refund the earnest money and performance security. In the absence of

    any order of forfeiture founded upon breach of contract or proof of

    loss, the continued retention of the petitioner’s money is wholly

    WP(C) No. 168/2023 Page 14 of 15
    2026:JKLHC-JMU:2377

    arbitrary and contrary to the settled principles governing contractual

    obligations. As noticed hereinabove, such forfeiture cannot be

    sustained in law.

    26. For all the foregoing reasons, the objections raised by the respondents

    are devoid of merit and deserve to be rejected. This Court is

    persuaded, particularly in the light of the principles enunciated by the

    apex court in Union of India & Ors. v. Bali Ram, (supra) to exercise

    its writ jurisdiction and compel the respondents to perform their

    contractual obligation by refunding the earnest money and

    performance security to the petitioner.

    27. Accordingly, the writ petition is allowed. A writ of mandamus is

    issued directing the respondents-University to forthwith release the

    earnest money amounting to ₹11,00,000/- and the performance

    security amounting to ₹18,00,000/- in favour of the petitioner.

    However, having regard to the facts and circumstances of the case, the

    aforesaid amounts shall not carry any further interest.

    28. The writ petition is, accordingly, disposed of, along with all connected

    application(s).

    (Sanjay Parihar)
    Judge

    Jammu
    03.08.2026
    Renu

    Whether the judgment is speaking: Yes

    Whether the judgment is reportable: Yes

    WP(C) No. 168/2023 Page 15 of 15



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here