(In The Matters Of Appeals Under Section … vs Kuntala Behera on 15 May, 2026

    0
    33
    ADVERTISEMENT

    Orissa High Court

    (In The Matters Of Appeals Under Section … vs Kuntala Behera on 15 May, 2026

    Author: Sanjeeb K Panigrahi

    Bench: Sanjeeb K Panigrahi

                                                             Signature Not Verified
                                                             Digitally Signed
                                                             Signed by: BHABAGRAHI JHANKAR
                                                             Reason: Authentication
                                                             Location: ORISSA HIGH COURT, CUTTACK
                                                             Date: 21-May-2026 17:57:39
    
    
    
    
                      IN THE HIGH COURT OF ORISSA AT CUTTACK
    
                                  ARBA No.13 of 2021
                                        And
                                  ARBA No.14 of 2021
    
         (In the matters of Appeals under Section 37 of the Arbitration and
         Conciliation Act, 1996)
           The Competent Authority & Special ...                              Appellant (s)
           Land Acquisition Officer, Sambalpur
                                        -versus-
           Kuntala Behera                        ...                     Respondent (s)
          (In ARBA No.13 of 2021)                .
          Sarojini Pradhan
          (In ARBA No.14 of 2021)
         Advocates appeared in the case through Hybrid Mode:
           For Appellant (s)           :              Mr. Ajit Patnaik, Advocate.
    
    
           For Respondent (s)          :                  Mr. R.N. Debata, Adv.
                                                          Mr. S.K. Mishra, Adv.
    
                     CORAM:
                     DR. JUSTICE SANJEEB K PANIGRAHI
    
                         DATE OF HEARING:-07.03.2026
                        DATE OF JUDGMENT:-15.05.2026
    
         Dr. Sanjeeb K Panigrahi, J.
    

    1. The present Appeals have been preferred seeking setting aside of

    judgments and orders dated 26.8.2021, passed by the Ld. District Judge,

    SPONSORED

    Sambalpur in ARBP No.1 of 2018 and ARBP No.2 of 2018. As both

    matters arise out of the same land acquisition proceedings relating to

    Village Naxapali, are founded upon identical notifications issued under

    the National Highways Act, 1956, and involve common and

    Page 1
    Signature Not Verified
    Digitally Signed
    Signed by: BHABAGRAHI JHANKAR
    Reason: Authentication
    Location: ORISSA HIGH COURT, CUTTACK
    Date: 21-May-2026 17:57:39

    overlapping questions of law, particularly concerning the applicability

    of the RFCTLARR Act, 2013, they are being taken up together and dealt

    with vide this common judgment.

    I. FACTUAL MATRIX OF THE CASE:

    2. The lands involved in these connected appeals are situated at Village

    Naxapali under Maneswar Tahasil in the district of Sambalpur and

    were acquired for the purpose of widening and development of

    National Highway No. 42/55 under the provisions of the National

    Highways Act, 1956.

    3. The acquisition process commenced with the publication of a

    preliminary notification under Section 3A of the Act on 29.10.2012.

    After completion of the statutory formalities and consideration of

    objections, a declaration under Section 3D was published on 21.5.2013,

    upon which the acquired lands vested absolutely in the Union of India,

    free from all encumbrances. Thereafter, the Competent Authority-cum-

    Special Land Acquisition Officer, Sambalpur undertook the process of

    determination of compensation under Section 3G of the Act in respect

    of the acquired lands.

    4. The estimate and determination of compensation were completed and

    the award was finalized on 18.10.2014. On the same date, the

    Competent Authority issued a formal requisition to the National

    Highways Authority of India seeking sanction and release of the

    requisite funds for disbursement of the awarded compensation.

    5. The award was duly entered in the Award Register, reflecting the land

    value, solatium, and other statutory components. In so far as the lands

    Page 2
    Signature Not Verified
    Digitally Signed
    Signed by: BHABAGRAHI JHANKAR
    Reason: Authentication
    Location: ORISSA HIGH COURT, CUTTACK
    Date: 21-May-2026 17:57:39

    at Village Naxapali are concerned, the award was recorded in the

    names of the recorded tenants or vendors, which was Iswar Pandey

    and Krushna Pandey in the subject land in ARBA No. 13 of 2021 as the

    revenue records had not been mutated in favour of the respondents at

    the relevant point of time and the present Respondent herself in the

    subject land in ARBA No. 14 of 2021.

    6. Pursuant to the requisition dated 18.10.2014, the National Highways

    Authority of India released the compensation funds, and for Village

    Naxapali, such funds were released on 8.12.2014.

    7. Consequently, it is the Appellant’s case that the entire awarded amount

    stood sanctioned, released, and available with the Competent

    Authority for disbursement well before 31.12.2014.

    8. The date 1.1.2015 is of significance, as certain provisions of the Right to

    Fair Compensation and Transparency in Land Acquisition,

    Rehabilitation and Resettlement Act, 2013 were extended to

    acquisitions under the National Highways Act with effect from that

    date by virtue of Section 105(3).

    9. The respondent in ARBA No. 13 of 2021 claims to have purchased the

    acquired lands during the years 1984-1985. However, at the time of

    acquisition and passing of the award, the lands continued to stand

    recorded in the names of her vendors, no mutation had been effected in

    favour of the respondent, and the lands were found to be vacant and

    barren on field verification. No objections were filed by the respondent

    pursuant to the notifications under Sections 3A or 3D of the National

    Highways Act. Immediately after the award dated 18.10.2014, the

    Page 3
    Signature Not Verified
    Digitally Signed
    Signed by: BHABAGRAHI JHANKAR
    Reason: Authentication
    Location: ORISSA HIGH COURT, CUTTACK
    Date: 21-May-2026 17:57:39

    respondent raised oral objections before the Competent Authority,

    objecting to payment of compensation in favour of her vendors and

    claiming entitlement in her own right, whereupon she was advised to

    submit formal written objections with supporting documents.

    10. The first written representation was submitted by the respondent in

    ARBA No. 13 of 2021 on 4.2.2015, after the cut-off date of 1.1.2015,

    seeking release of compensation in her favour. In the said

    representation, the respondent acknowledged knowledge of the award

    and furnished detailed break-ups of the compensation awarded,

    indicating access to award-related information soon after 18.10.2014. As

    all original and authenticated documents were not initially furnished,

    verification and apportionment could not be immediately completed.

    In ARBA No. 13 of 2021, an amount of Rs. 3,13,051/- was ultimately

    credited through NEFT on 8.9.2015 to the present Respondent as she

    managed to bring forward all relevant documents to showcase that she

    was in fact the owner of the subject land.

    11. In contrast, in ARBA No. 14 of 2021, the respondent Sarojini Pradhan

    was already the recorded owner and the Record of Rights stood in her

    name. The compensation determined under the award was credited

    directly to her bank account on 17.4.2015 in the sum of Rs.32,34,923/-.

    12. Dissatisfied with the quantum and manner of determination of

    compensation, the respondents in both cases invoked the remedy under

    Section 3G(5) of the National Highways Act. The Collector-cum-

    Arbitrator rejected their claims by arbitral awards dated 16.2.2018.

    These awards were set aside by the Ld. District Judge, Sambalpur by

    Page 4
    Signature Not Verified
    Digitally Signed
    Signed by: BHABAGRAHI JHANKAR
    Reason: Authentication
    Location: ORISSA HIGH COURT, CUTTACK
    Date: 21-May-2026 17:57:39

    judgments dated 26.8.2021, leading to the present appeals filed in the

    year 2021 and heard analogously.

    13. This Court shall now endeavour to summarise the contentions of the

    Parties and the broad grounds that have been raised.

    II. APPELLANT’S SUBMISSIONS:

    14. The Appellant submits that the Ld. District Judge committed a manifest

    error in setting aside the arbitral awards dated 16.2.2018 by erroneously

    invoking Section 24 of the RFCTLARR Act, 2013, despite the acquisition

    having been undertaken under the National Highways Act, 1956, a

    special statute. It is urged that the entire foundation of the impugned

    judgment rests on a misapplication of law, inasmuch as Section 24 of

    the Act of 2013 applies only to acquisitions initiated under the Land

    Acquisition Act, 1894, and not to acquisitions under enactments listed

    in the Fourth Schedule, including the National Highways Act, 1956

    15. It is further contended that Section 105 of the RFCTLARR Act, 2013

    clearly excludes the application of the provisions of the said Act to

    acquisitions under the National Highways Act, save and except to the

    limited extent expressly provided under Section 105(3). By virtue of the

    amendments and ordinances issued thereunder, only the First, Second

    and Third Schedules of the Act of 2013 were made applicable to

    acquisitions under the National Highways Act with effect from

    1.1.2015. According to the Appellant, Section 24 does not form part of

    these schedules and was never extended to acquisitions under the

    National Highways Act 1956, rendering the reasoning adopted by the

    Ld. District Judge legally unsustainable.

    Page 5
    Signature Not Verified
    Digitally Signed
    Signed by: BHABAGRAHI JHANKAR
    Reason: Authentication
    Location: ORISSA HIGH COURT, CUTTACK
    Date: 21-May-2026 17:57:39

    16. The Appellant places strong reliance on the admitted factual position

    that the award determining compensation was passed on 18.10.2014

    and that the requisite funds were requisitioned on the same date and

    released by the National Highways Authority of India on 8.12.2014,

    well before the cut-off date of 31.12.2014. It is submitted that the

    compensation amount was thus fully sanctioned and available for

    disbursement prior to 1.1.2015, which is the date from which the

    limited application of the RFCTLARR Act, 2013 to National Highways

    acquisitions commenced. The Ld. District Judge, it is urged, failed to

    consider these admitted dates, despite the same being borne out from

    the record and the Additional Affidavit filed before this Court.

    17. The Appellant further submits that the arbitral awards dated 16.2.2018

    were passed strictly in accordance with Section 3G of the National

    Highways Act, 1956 and after considering the materials placed by the

    claimants. It is argued that the Ld. Arbitrator neither ignored any

    mandatory statutory provision nor acted in conflict with public policy.

    The finding of the Ld. District Judge that the arbitral awards were

    contrary to public policy under Section 34(2)(b) of the Arbitration and

    Conciliation Act, 1996 is assailed as wholly unfounded, being premised

    solely on an incorrect assumption regarding the applicability of the Act

    of 2013.

    18. Lastly, the Appellant submits that the reliance placed by the Ld.

    District Judge on the decision of the Hon’ble Supreme Court in Indore

    Development Authority v. Manoharlal1 is wholly misconceived. It is

    1
    (2020) 8 SCC 129
    Page 6
    Signature Not Verified
    Digitally Signed
    Signed by: BHABAGRAHI JHANKAR
    Reason: Authentication
    Location: ORISSA HIGH COURT, CUTTACK
    Date: 21-May-2026 17:57:39

    argued that the said decision deals exclusively with the scope and

    interpretation of Section 24 of the RFCTLARR Act, 2013 in the context

    of acquisitions under the Land Acquisition Act, 1894, and does not

    address, far less extend, the applicability of Section 24 to acquisitions

    under the National Highways Act, 1956. On these grounds, the

    Appellant seeks setting aside of the impugned judgment dated

    26.8.2021 and restoration of the arbitral awards dated 16.2.2018.

    III. RESPONDENT’S SUBMISSIONS

    19. Per contra, the Respondents submit that the Ld. District Judge

    committed no error in setting aside the arbitral awards dated 16.2.2018,

    as the determination of compensation by the Competent Authority and

    the Arbitrator was contrary to the mandate of the RFCTLARR Act,

    2013, which embodies the current public policy governing land

    acquisition and compensation. It is contended that the arbitral awards

    failed to take into account the beneficial and welfare-oriented

    provisions of the Act of 2013, thereby resulting in manifest injustice to

    the landowners. According to the Respondents, the approach adopted

    by the Arbitrator was mechanical and rooted in the repealed

    framework of compensation, warranting judicial interference under

    Section 34 of the Arbitration and Conciliation Act, 1996

    20. The Respondents argue that Section 24 of the RFCTLARR Act, 2013 was

    rightly applied by the Ld. District Judge, as the acquisition proceedings,

    though initiated earlier, had not culminated in lawful payment of

    compensation prior to the cut-off date. It is urged that mere preparation

    of an award or release of funds to the acquiring authority does not

    Page 7
    Signature Not Verified
    Digitally Signed
    Signed by: BHABAGRAHI JHANKAR
    Reason: Authentication
    Location: ORISSA HIGH COURT, CUTTACK
    Date: 21-May-2026 17:57:39

    amount to “payment” of compensation to the landowner. In the present

    cases, the compensation was either paid after 1.1.2015 or paid in a

    manner disputed by the Respondents, thereby attracting the beneficial

    provisions of the Act of 2013. The Ld. District Judge, it is submitted,

    correctly appreciated this distinction.

    21. It is further contended that the Respondents were not given effective

    notice or opportunity at the stage of determination of compensation,

    and that the awards were passed without proper consideration of their

    rights, title, possession, and the nature of the land and structures. In

    ARBA No. 13 of 2021, the Respondent asserts that compensation was

    initially awarded in favour of her vendor despite her prior purchase,

    while in ARBA No. 14 of 2021, though compensation was credited, the

    same was not calculated in accordance with the First Schedule of the

    Act of 2013. These deficiencies, according to the Respondents, vitiate

    the arbitral awards on the ground of patent illegality.

    22. The Respondents also submit that the applicability of the RFCTLARR

    Act, 2013 to acquisitions under the National Highways Act, 1956 cannot

    be viewed in a narrow or technical manner. It is argued that Section

    105(3) of the Act of 2013 reflects legislative intent to extend the benefit

    of enhanced and fair compensation to landowners affected by

    acquisitions under special enactments, including the National

    Highways Act, 1956. The Ld. District Judge, it is urged, rightly

    harmonised Section 105(3) with Section 24 to ensure that landowners

    are not deprived of just compensation merely due to the timing of

    administrative actions.

    Page 8
    Signature Not Verified
    Digitally Signed
    Signed by: BHABAGRAHI JHANKAR
    Reason: Authentication
    Location: ORISSA HIGH COURT, CUTTACK
    Date: 21-May-2026 17:57:39

    23. Lastly, the Respondents contend that the arbitral awards were rightly

    held to be in conflict with public policy, as they denied the

    Respondents compensation in accordance with the law in force and the

    constitutional mandate of fairness and equality. The Ld. District Judge,

    it is submitted, correctly relied on the principles laid down by the

    Hon’ble Supreme Court while interpreting Section 24 of the Act of 2013

    and applied them to the facts of the present cases. The Respondents

    therefore pray for dismissal of the appeals and affirmance of the

    judgment dated 26.8.2021.

    IV. ISSUE FOR CONSIDERATION

    24. Having heard the parties and perused the materials available on record,

    this court here has identified the following issue to be determined:

    A. Whether Section 24 of the Right to Fair Compensation and

    Transparency in Land Acquisition, Rehabilitation and

    Resettlement Act, 2013 is applicable to land acquisitions

    undertaken under the National Highways Act, 1956, and,

    consequentially, whether the learned District Judge was

    justified in setting aside the arbitral awards dated 16.2.2018

    passed under Section 3G(5) of the National Highways Act by

    applying the provisions of the Act of 2013?

    
    
    V.    ISSUE A: WHETHER SECTION 24 OF THE RIGHT TO FAIR
          COMPENSATION       AND   TRANSPARENCY    IN   LAND
    

    ACQUISITION, REHABILITATION AND RESETTLEMENT ACT,
    2013 IS APPLICABLE TO LAND ACQUISITIONS UNDERTAKEN
    UNDER THE NATIONAL HIGHWAYS ACT, 1956, AND,
    CONSEQUENTIALLY, WHETHER THE LEARNED DISTRICT

    Page 9
    Signature Not Verified
    Digitally Signed
    Signed by: BHABAGRAHI JHANKAR
    Reason: Authentication
    Location: ORISSA HIGH COURT, CUTTACK
    Date: 21-May-2026 17:57:39

    JUDGE WAS JUSTIFIED IN SETTING ASIDE THE ARBITRAL
    AWARDS DATED 16.2.2018 PASSED UNDER SECTION 3G(5) OF
    THE NATIONAL HIGHWAYS ACT BY APPLYING THE
    PROVISIONS OF THE ACT OF 2013?

    25. Before going into the merits of the contentions, it is necessary to outline

    the ambit and scope of Section 37(2)(b) of the 1996 Act. The said section

    is extracted below:

    “37. Appealable orders.–(1)[Notwithstanding anything
    contained in any other law for the time being in force, an
    appeal] shall lie from the following orders (and from no
    others) to the court authorised by law to hear appeals
    from original decrees of the court passing the order,
    namely:

    ∗∗∗
    (2) Appeal shall also lie to a court from an order of the
    Arbitral Tribunal–

    (a) accepting the plea referred to in sub-section (2) or
    sub-section (3) of Section 16; or

    (b) granting or refusing to grant an interim measure
    under Section 17.”

    26. The Supreme Court and this Court in catena of judgments have held

    that the powers of appellate court while exercising jurisdiction under

    Section 37(2)(b) of the 1996 Act against orders passed by the Arbitral

    Tribunal is very restricted and narrow and the same should be

    exercised when the orders seems to be perverse, arbitrary and contrary

    to law. The judgment of Wander Ltd. v. Antox India (P) Ltd.2 passed by

    the Apex Court, elaborates the ambit and scope of the appeals.

    Although the aforesaid judgment is not dealing with the arbitration

    proceedings but the same deals with the power of appellate court in

    2
    1990 Supp SCC 727

    Page 10
    Signature Not Verified
    Digitally Signed
    Signed by: BHABAGRAHI JHANKAR
    Reason: Authentication
    Location: ORISSA HIGH COURT, CUTTACK
    Date: 21-May-2026 17:57:39

    the Civil Procedure Code, 1908 (CPC). Operative paragraphs of the

    aforesaid judgment are extracted below:

    “13. On a consideration of the matter, we are afraid, the
    Appellate Bench fell into error on two important
    propositions. The first is a misdirection in regard to the
    very scope and nature of the appeals before it and the
    limitations on the powers of the appellate court to
    substitute its own discretion in an appeal preferred
    against a discretionary order. The second pertains to the
    infirmities in the ratiocination as to the quality of antox’s
    alleged user of the trade mark on which the passing-off
    action is founded. We shall deal with these two
    separately.

    14. The appeals before the Division Bench were against
    the exercise of discretion by the Single Judge. In such
    appeals, the appellate court will not interfere with the
    exercise of discretion of the court of first instance and
    substitute its own discretion except where the discretion
    has been shown to have been exercised arbitrarily, or
    capriciously or perversely or where the court had ignored
    the settled principles of law regulating grant or refusal of
    interlocutory injunctions. An appeal against exercise of
    discretion is said to be an appeal on principle. Appellate
    court will not reassess the material and seek to reach a
    conclusion different from the one reached by the court
    below if the one reached by that court was reasonably
    possible on the material. The appellate court would
    normally not be justified in interfering with the exercise
    of discretion under appeal solely on the ground that if it
    had considered the matter at the trial stage it would have
    come to a contrary conclusion. If the discretion has been
    exercised by the trial court reasonably and in a judicial
    manner the fact that the appellate court would have taken
    a different view may not justify interference with the
    trial court’s exercise of discretion. After referring to these
    principles Gajendragadkar, J. in Printers (Mysore) (P)
    Ltd. v. Pothan Joseph
    (SCC OnLine SC para 9)

    Page 11
    Signature Not Verified
    Digitally Signed
    Signed by: BHABAGRAHI JHANKAR
    Reason: Authentication
    Location: ORISSA HIGH COURT, CUTTACK
    Date: 21-May-2026 17:57:39

    ‘9. …These principles are well established, but as
    has been observed by Viscount Simon in Charles
    Osenton & Co. v. Johnston “the law as to the
    reversal by a court of appeal of an order made by a
    Judge below in the exercise of his discretion is well
    established and any difficulty that arises is due
    only to the application of well-settled principles in
    an individual case.”‘
    The appellate judgment does not seem to defer to this
    principle.”

    27. The said judgment is consistently followed in adjudicating petitions

    pertaining to the A&C Act by Courts across the Country in Green Infra

    Wind Energy Ltd. v. Regen Powertech (P) Ltd.3; Sona Corpn. India (P)

    Ltd. v. Ingram Micro India (P) Ltd.4; Manish Aggarwal v. RCI

    Industries & Technologies Ltd.5; Tahal Consulting Engineers India (P)

    Ltd. v. Promax Power Ltd.6 and Handicraft & Handlooms Exports Co.

    of India v. SMC Comtrade Ltd.7.

    28. In Reliance Infrastructure Ltd. v. State of Goa8, the Apex Court

    noticing its previous decision in MMTC Ltd. v. Vedanta Ltd.9 has noted

    the limited scope of interference under Section 34 and further narrower

    scope of appeal under Section 37 of the Act particularly when dealing

    with the concurrent findings of the arbitrator and that of the Court.

    Relevant paragraph ’14’ of MMTC Ltd.(supra) as noted in paragraph

    3
    2018 SCC OnLine Del 8273
    4
    2020 SCC OnLine Del 300
    5
    (2022) 3 HCC (Del) 289
    6
    2023 SCC OnLine Del 2069
    7
    2023 SCC OnLine Del 3981
    8
    (2024) 1 SCC 479
    9
    (2019) 4 SCC 163

    Page 12
    Signature Not Verified
    Digitally Signed
    Signed by: BHABAGRAHI JHANKAR
    Reason: Authentication
    Location: ORISSA HIGH COURT, CUTTACK
    Date: 21-May-2026 17:57:39

    ’26’ in Reliance Infrastructure Ltd.(supra) is to be extracted

    hereinunder:–

    “14. As far as interference with an order made
    under Section 34, as per Section 37, is concerned, it
    cannot be disputed that such interference
    under Section 37 cannot travel beyond the restrictions
    laid down under Section 34. In other words, the court
    cannot undertake an independent assessment of the
    merits of the award, and must only ascertain that the
    exercise of power by the court under Section34 has not
    exceeded the scope of the provision. Thus, it is evident
    that in case an arbitral award has been confirmed by the
    court under Section 34 and by the court in an appeal
    under Section 37, this Court must be extremely
    cautious and slow to disturb such concurrent findings.”

    29. The same view has been expressed in UHL Power Company

    Ltd. v. State of Himachal Pradesh10 in paragraph ’16’ while noticing

    paragraph ’11’ in MMTC Ltd.(supra):–

    “16. As it is, the jurisdiction conferred on courts
    under Section 34 of the Arbitration Act is fairly narrow,
    when it comes to the scope of an appeal
    under Section 37 of the Arbitration Act, the jurisdiction
    of an appellate court in examining an order, setting aside
    or refusing to set aside an award, is all the more
    circumscribed. In MMTC Ltd. v. Vedanta Ltd. [MMTC
    Ltd.
    v. Vedanta Ltd., (2019) 4 SCC 163 : (2019) 2 SCC
    (Civ) 293], the reasons for vesting such a limited
    jurisdiction on the High Court in exercise of powers
    under Section 34 of the ArbitrationAct have been
    explained in the following words : (SCC pp. 166-67, para

    11)
    “11. As far as Section 34 is concerned, the position
    is well-settled by now that the Court does not sit

    10
    (2022) 4 SCC 116

    Page 13
    Signature Not Verified
    Digitally Signed
    Signed by: BHABAGRAHI JHANKAR
    Reason: Authentication
    Location: ORISSA HIGH COURT, CUTTACK
    Date: 21-May-2026 17:57:39

    in appeal over the arbitral award and may interfere
    on merits on the limited ground provided
    under Section 34(2)(b)(ii) i.e. if the award is
    against the public policy of India. As per the legal
    position clarified through decisions of this Court
    prior to the amendments to the 1996 Act in 2015,
    a violation of Indian public policy, in turn,
    includes a violation of the fundamental policy of
    Indian law, a violation of the interest of India,
    conflict with justice or morality, and the existence
    of patent illegality in the arbitral award.

    Additionally, the concept of the “fundamental
    policy of Indian law” would cover compliance with
    statutes and judicial precedents, adopting a
    judicial approach, compliance with the principles
    of natural justice, and Wednesbury [Associated
    Provincial Picture Houses Ltd. v. Wednesbury
    Corpn., [1948] 1 K.B. 223(CA)] reasonableness.
    Furthermore, “patent illegality” itself has been
    held to mean contravention of the substantive law
    of India, contravention of
    the 1996 Act, and contravention of the terms of the
    contract.”

    30. In Haryana Tourism Ltd. v. Kandhari Beverages Ltd.11 as noted in

    paragraph ’30’ in Reliance Infrastructure Ltd.(supra), it was held on the

    scope of interference under Sections 34 and 37 of the Act’ 1996 as

    under:–

    “30. In Haryana Tourism [Haryana Tourism
    Ltd. v. Kandhari Beverages Ltd.
    , (2022) 3 SCC
    237 : (2022) 2 SCC (Civ) 87], this Court yet again
    pointed out the limited scope of interference
    under Sections 34 and37 of the Act; and disapproved
    interference by the High Court under Section 37 of

    11
    2022) 3 SCC 237

    Page 14
    Signature Not Verified
    Digitally Signed
    Signed by: BHABAGRAHI JHANKAR
    Reason: Authentication
    Location: ORISSA HIGH COURT, CUTTACK
    Date: 21-May-2026 17:57:39

    the Act while entering into merits of the claim in the
    following words : (SCC p. 240, paras 8-9)
    “8. So far as the impugned
    judgment and order [Kandhari Beverages
    Ltd. v. Haryana Tourism Ltd., 2018 SCC OnLine
    P&H 3233] passed by the High Court
    quashing and setting aside the
    award and the order passed by the Additional
    District Judge under Section 34 of
    the Arbitration Act are concerned, it is required to
    be noted that in an appeal under Section 37 of
    the Arbitration Act, the High Court has entered
    into the merits of the claim, which is not
    permissible in exercise of powers
    under Section 37 of the Arbitration Act.

    9. As per settled position of law laid down by this
    Court in a catena of decisions, an award can be set
    aside only if the award is against the public policy
    of India. The award can be set aside
    under Sections 34/37 of the Arbitration Act, if the
    award is found to be contrary to : (a) fundamental
    policy of Indian Law; or (b) the interest of India; or

    (c) justice or morality; or (d) if it is patently
    illegal. None of the aforesaid exceptions shall be
    applicable to the facts of the case on hand. The
    High Court has entered into the merits of the
    claim and has decided the appeal
    under Section 37 of the Arbitration Act as if the
    High Court was deciding the appeal against the
    judgment and decree passed by the learned trial
    court. Thus, the High Court has exercised the
    jurisdiction not vested in it under Section 37 of
    the Arbitration Act. The impugned
    judgment andorder [Kandhari Beverages
    Ltd. v. Haryana Tourism Ltd., 2018 SCC OnLine
    P&H 3233] passed by the High Court is hence not
    sustainable.”

    Page 15
    Signature Not Verified
    Digitally Signed
    Signed by: BHABAGRAHI JHANKAR
    Reason: Authentication
    Location: ORISSA HIGH COURT, CUTTACK
    Date: 21-May-2026 17:57:39

    31. It was, thus, observed in paragraph ’33’ of Reliance Infrastructure

    Ltd.(supra) as under:–

    “33. Keeping in view the aforementioned principles
    enunciated by this Court with regard to the limited scope
    of interference in an arbitral award by a Court in the
    exercise of its jurisdiction under Section34 of the Act,
    which is all the more circumscribed in an appeal
    under Section 37, we may examine the rival submissions
    of the parties in relation to the matters dealt with by the
    High Court.”

    32. It is observed in Punjab State Civil Supplies Corpn. Ltd. v. Sanman

    Rice Mills12 that:

    “9. The object of the Act is to provide for a speedy and
    inexpensive alternative mode of settlement of dispute
    with the minimum of intervention of the courts. Section
    5
    of the Act is implicit in this regard and prohibits
    interference by the judicial authority with the arbitration
    proceedings except where so provided in Part-I of the
    Act
    . The judicial interference, if any, is provided inter-
    alia only by means of Sections 34 and 37 of the Act
    respectively.

    10. Section 34 of the Act provides for getting an arbitral
    award set aside by moving an application in accordance
    with sub-Section (2) andsub-Section (3) of Section 34 of
    the Act which inter-alia provide for the grounds on which
    an arbitral award is liable to be set aside. One of the main
    grounds for interference or setting aside an award is
    where the arbitral award is in conflict with the public
    policy of India i.e. if the award is induced or affected by
    fraud or corruption or is in contravention with the
    fundamental policy of Indian law or it is in conflict with
    most basic notions of morality and justice. A plain
    reading of Section 34 reveals that the scope of

    12
    2024 SCC OnLine SC 2632

    Page 16
    Signature Not Verified
    Digitally Signed
    Signed by: BHABAGRAHI JHANKAR
    Reason: Authentication
    Location: ORISSA HIGH COURT, CUTTACK
    Date: 21-May-2026 17:57:39

    interference by the court with the arbitral award under
    Section 34 is very limited and the court is not supposed
    to travel beyond the aforesaid scope to find out if the
    award is good or bad.

    11. Section 37 of the Act provides for a forum of appeal
    inter-alia against the order setting aside or refusing to set
    aside an arbitral award under Section 34 of the Act. The
    scope of appeal is naturally akin to andlimited to the
    grounds enumerated under Section 34 of the Act.

    12. It is pertinent to note that an arbitral award is not
    liable to be interfered with only on the ground that the
    award is illegal or is erroneous in law that too upon
    reappraisal of the evidence adduced before the arbitral
    trial. Even an award which may not be reasonable or is
    non-speaking to some extent cannot ordinarily be
    interfered with by the courts. It is also well settled that
    even if two views are possible there is no scope for the
    court to reappraise the evidence and to take the different
    view other than that has been taken by the arbitrator. The
    view taken by the arbitrator is normally acceptable and
    ought to be allowed to prevail.

    xxxxxx

    14. It is equally settled law that the appellate power
    under Section 37of the Act is not akin to the normal
    appellate jurisdiction vested in the civil courts for the
    reason that the scope of interference of the courts with
    arbitral proceedings or award is very limited, confined to
    the ambit of Section 34 of the Act only and even that
    power cannot be exercised in a casual and a cavalier
    manner.

    xxxxxx

    16. It is seen that the scope of interference in an appeal
    under Section37 of the Act is restricted and subject to the
    same grounds on which an award can be challenged
    under Section 34 of the Act. In other words, the powers
    under Section 37 vested in the court of appeal are not

    Page 17
    Signature Not Verified
    Digitally Signed
    Signed by: BHABAGRAHI JHANKAR
    Reason: Authentication
    Location: ORISSA HIGH COURT, CUTTACK
    Date: 21-May-2026 17:57:39

    beyond the scope of interference provided
    under Section 34 of the Act.”

    Here, the Hon’ble Supreme Court has once again reiterated that even

    an award which may not be reasonable or is nonspeaking to some

    extent cannot ordinarily be interfered with by the courts. It is also well

    settled that even if two views are possible there is no scope for the court

    to reappraise the evidence and to take the different view other than that

    has been taken by the arbitrator. The view taken by the arbitrator is

    normally acceptable and ought to be allowed to prevail.

    33. In Konkan Railway Corpn. Ltd. v. Chenab Bridge Project13 referring

    to MMTC Limited (supra) it has been held that:

    “19….The scope of jurisdiction
    under Section 34 and Section 37 of the Act is not akin to
    normal appellate jurisdiction. It is well-settled that
    courts ought not to interfere with the arbitral award in a
    casual and cavalier manner. The mere possibility of an
    alternative view on facts or interpretation of the contract
    does not entitle courts to reverse the findings of the
    arbitral tribunal…”

    34. In Dyna Technology Private Limited v. Crompton Greaves Limited14,

    the Apex Court observed as under:

    “24. There is no dispute that Section 34 of the
    Arbitration Act limits a challenge to an award only on
    the grounds provided therein or as interpreted by various
    courts. We need to be cognizant of the fact that arbitral
    awards should not be interfered with in a casual and
    cavalier manner, unless the court comes to a conclusion
    that the perversity of the award goes to the root of the

    13
    (2023) 9 SCC 85
    14
    (2019) 20 SCC 1
    Page 18
    Signature Not Verified
    Digitally Signed
    Signed by: BHABAGRAHI JHANKAR
    Reason: Authentication
    Location: ORISSA HIGH COURT, CUTTACK
    Date: 21-May-2026 17:57:39

    matter without there being a possibility of alternative
    interpretation which may sustain the arbitral award.

    Section 34 is different in its approach and cannot be
    equated with a normal appellate jurisdiction. The
    mandate under Section 34 is to respect the finality of the
    arbitral award and the party autonomy to get their
    dispute adjudicated by an alternative forum as provided
    under the law. If the courts were to interfere with the
    arbitral award in the usual course on factual aspects,
    then the commercial wisdom behind opting for alternate
    dispute resolution would stand frustrated.

    25. Moreover, umpteen number of judgments of this
    Court have categorically held that the courts should not
    interfere with an award merely because an alternative
    view on facts and interpretation of contract exists. The
    courts need to be cautious and should defer to the view
    taken by the Arbitral Tribunal even if the reasoning
    provided in the award is implied unless such award
    portrays perversity unpardonable under Section 34 of the
    Arbitration Act.”

    35. Judicial scrutiny of arbitral awards is stringently limited under Indian

    law. Section 34 of the Arbitration and Conciliation Act, 1996, provides

    the exclusive grounds upon which an arbitral award can be challenged.

    Courts, therefore, are not empowered to interfere merely because

    another interpretation or outcome may seem more reasonable. The

    jurisdiction under Section 34 is confined to procedural and legal

    infirmities such as lack of jurisdiction, violation of natural justice, or

    patent illegality. Consequently, appellate jurisdiction under Section 37

    is even narrower in its scope. Its purpose is to evaluate whether the

    court adjudicating under Section 34 has remained within the

    permissible statutory boundaries. The appeal court cannot re-evaluate

    Page 19
    Signature Not Verified
    Digitally Signed
    Signed by: BHABAGRAHI JHANKAR
    Reason: Authentication
    Location: ORISSA HIGH COURT, CUTTACK
    Date: 21-May-2026 17:57:39

    evidence or reconsider the factual matrix afresh. The statutory

    framework thus reflects an overarching legislative intent to insulate

    arbitral decisions from excessive judicial intervention. The entire

    architecture of Sections 34 and 37 reinforces the finality and autonomy

    of arbitral proceedings. Arbitration is designed to offer an efficient,

    expert-led, and expedited alternative to litigation. Courts must

    therefore resist the temptation to intervene unless the decision by the

    court under Section 34 itself amounts to a significant transgression of

    legal boundaries.

    36. Now this Court shall endeavour to answer the main question framed

    herein. The question of applicability of Section 24 of the RFCTLARR

    Act, 2013 to acquisitions under the National Highways Act, 1956 must

    be examined first through the lens of legislative design. The National

    Highways Act is not a general acquisition statute but a special

    enactment intended to facilitate time-bound development of national

    infrastructure.

    37. Parliament, recognising the unique requirements of highway projects,

    deliberately carved out a separate acquisition mechanism under

    Sections 3A to 3J. This framework governs notification, vesting,

    determination of compensation, and payment, independent of the

    general land acquisition law. The insertion of Section 3J in 1997 is of

    decisive importance, as it unequivocally declares that nothing in the

    Land Acquisition Act, 1894 shall apply to acquisitions under the

    National Highways Act, 1956 thereby severing any statutory linkage

    between the two regimes.

    Page 20
    Signature Not Verified
    Digitally Signed
    Signed by: BHABAGRAHI JHANKAR
    Reason: Authentication
    Location: ORISSA HIGH COURT, CUTTACK
    Date: 21-May-2026 17:57:39

    38. This legislative separation was consciously preserved even when

    Parliament enacted the RFCTLARR Act, 2013. Section 105 of the 2013

    Act embodies a clear policy choice to exclude certain enactments from

    its general application. The Fourth Schedule appended to the Act lists

    thirteen such enactments, including the National Highways Act, 1956.

    Section 105(1) categorically exempts these enactments from the

    operation of the 2013 Act, while Section 105(3) empowers the Central

    Government to selectively apply beneficial provisions relating to

    compensation, rehabilitation, and resettlement. The structure of Section

    105 thus makes it clear that inclusion in the Fourth Schedule is not

    accidental but reflects Parliament’s intent to preserve special

    acquisition regimes while permitting limited, controlled harmonisation

    in matters of compensation.

    39. The RFCTLARR Act came into force on 1.1.2014. However, the

    applicability of even its limited provisions to acquisitions under the

    National Highways Act, 1956 was deferred and phased. Through

    Amendment Ordinance No. 9 of 2014 and subsequent ordinances, the

    Parliament provided that only specific provisions would apply with

    effect from 1.1.2015. This culminated in the notification dated 28.8.2015

    issued under Sections 105 and 113 of the Act. That notification is of

    central relevance, as it precisely enumerates the provisions extended to

    National Highways Act acquisitions. These are confined to

    determination of compensation in accordance with the First Schedule,

    rehabilitation and resettlement under the Second Schedule, and

    Page 21
    Signature Not Verified
    Digitally Signed
    Signed by: BHABAGRAHI JHANKAR
    Reason: Authentication
    Location: ORISSA HIGH COURT, CUTTACK
    Date: 21-May-2026 17:57:39

    infrastructure amenities under the Third Schedule. Section 24 does not

    find mention in this notification.

    40. At this juncture, it becomes necessary to examine the statutory text of

    Section 24 of the RFCTLARR Act, 2013 itself, as the controversy

    essentially turns on its scope and field of operation. Section 24(2),

    which provides for deemed lapse, expressly opens with the words “in

    case of land acquisition proceedings initiated under the Land

    Acquisition Act, 1894“. The provision, set out verbatim, leaves little

    room for interpretive expansion beyond acquisitions traceable to Act

    No. 1 of 1894. Its language, structure, and placement all indicate that it

    is statute-specific and not intended to operate across disparate

    acquisition regimes.

    41. The deliberate omission of Section 24 from the notification is legally

    significant. Section 24 deals not with the quantum of compensation but

    with deemed lapse of acquisition proceedings based on non-payment

    or non-possession under the Land Acquisition Act, 1894. The absence of

    Section 24 from the notification underscores that Parliament and the

    Central Government did not intend to import lapse provisions into the

    National Highways Act regime, which has its own timelines, vesting

    provisions, and consequences under Sections 3D and 3G.

    42. The Hon’ble Supreme Court has repeatedly affirmed this

    understanding. In Union of India v. Tarsem Singh15, while examining

    the constitutional validity of Section 3J of the National Highways Act,

    the Hon’ble Apex Court acknowledged that the RFCTLARR Act was

    15
    (2019) 9 SCC 304

    Page 22
    Signature Not Verified
    Digitally Signed
    Signed by: BHABAGRAHI JHANKAR
    Reason: Authentication
    Location: ORISSA HIGH COURT, CUTTACK
    Date: 21-May-2026 17:57:39

    not made fully applicable to national highway acquisitions. Although

    Section 3J was read down to the extent it denied solatium and interest,

    the Court did not hold that the entire 2013 Act stood incorporated into

    the National Highways Act. On the contrary, the judgment recognises

    that the extension of RFCTLARR provisions is limited and controlled

    by statutory notifications, and that the Fourth Schedule exemption

    continues to operate.

    43. This limited incorporation was further clarified in National Highways

    Authority of India v. P. Nagaraju @ Cheluvaiah16. The Hon’ble

    Supreme Court, interpreting the 28.8.2015 notification, held that the

    applicability of the RFCTLARR Act to National Highways Act, 1956

    acquisitions is confined strictly to the provisions specified therein. The

    Hon’ble Apex Court emphasised that the National Highways Act, 1956

    remains in the Fourth Schedule and that the general provisions of the

    2013 Act do not apply unless expressly extended. Section 24, not being

    among the provisions notified, was held to have no application to

    acquisitions under the National Highways Act, 1956.

    44. The doctrinal foundation of this position was strengthened in Bharat

    Petroleum Corporation Ltd. v. Nisar Ahmed Ganai17, where the

    Hon’ble Supreme Court undertook a textual and purposive

    interpretation of Section 24 itself. The Court observed that the language

    of Section 24(1)(a) is “very clear and unambiguous” and refers

    exclusively to land acquisition proceedings under the Land Acquisition

    Act, 1894. The Court categorically rejected the argument that Section 24

    16
    Civil Appeal No.4671 of 2022 (SC)
    17
    2022 INSC 1072

    Page 23
    Signature Not Verified
    Digitally Signed
    Signed by: BHABAGRAHI JHANKAR
    Reason: Authentication
    Location: ORISSA HIGH COURT, CUTTACK
    Date: 21-May-2026 17:57:39

    could apply to acquisitions under other statutes merely because those

    statutes contain pari materia provisions. It was held that the RFCTLARR

    Act repeals only the 1894 Act and does not override or subsume other

    acquisition enactments.

    45. The reasoning in Bharat Petroleum (supra) is particularly instructive

    because it addresses the precise interpretive error often committed by

    courts, namely, extending Section 24 by analogy or equity. The Hon’ble

    Supreme Court made it clear that Section 24 is not a general equitable

    provision but a statute-specific transitional clause. Its operation is

    confined to proceedings initiated under the repealed 1894 Act and

    cannot be expanded through judicial interpretation to cover

    acquisitions under special statutes like the National Highways Act,

    1956.

    46. A similar constitutional perspective emerges from C.S. Gopalakrishnan

    v. State of Tamil Nadu18, where the Hon’ble Supreme Court upheld the

    continued operation of state highway acquisition laws even after the

    enactment of the RFCTLARR Act. The Court recognised that special

    enactments, particularly those protected under Article 254(2) of the

    Constitution, retain their independent force unless expressly

    overridden. The judgment reinforces the principle that lapse provisions

    and timelines under Section 24 are not automatically imported into

    special acquisition statutes, whether Central or State.

    47. High Court jurisprudence has also been consistent with this settled

    position. The Hon’ble Gujarat High Court, while examining the

    18
    2023 INSC 510

    Page 24
    Signature Not Verified
    Digitally Signed
    Signed by: BHABAGRAHI JHANKAR
    Reason: Authentication
    Location: ORISSA HIGH COURT, CUTTACK
    Date: 21-May-2026 17:57:39

    applicability of RFCTLARR provisions to National Highways Act, 1956

    acquisitions, held that the extension of compensation-related provisions

    does not imply wholesale application of the 2013 Act. The Hon’ble

    Karnataka High Court has similarly emphasised that Section 24 cannot

    be read into the National Highways Act regime in view of Section 3J,

    Section 105, and the Fourth Schedule. These decisions reinforce that the

    statutory text, rather than perceived hardship, must govern the

    applicability of Section 24.

    48. Another important aspect is the conceptual incompatibility between

    Section 24 and the National Highways Act, 1956. Under Section 3D of

    the National Highways Act, vesting of land is absolute and occurs upon

    publication of the declaration. Possession and vesting are not

    contingent upon payment of compensation. Compensation is

    determined separately under Section 3G, and disputes are resolved

    through arbitration. Importing Section 24, which predicates lapse on

    non-payment or non-possession under a different statutory scheme,

    would disrupt the internal coherence of the National Highways Act

    and undermine its purpose.

    49. It is also relevant that the Central Government, while extending

    Sections 26 and 28 of the RFCTLARR Act for market value

    determination, consciously limited the extension to substantive

    compensation principles. Procedural provisions dealing with lapse,

    reopening of proceedings, or annulment of acquisitions were not

    extended. This distinction reflects a calibrated legislative approach: to

    Page 25
    Signature Not Verified
    Digitally Signed
    Signed by: BHABAGRAHI JHANKAR
    Reason: Authentication
    Location: ORISSA HIGH COURT, CUTTACK
    Date: 21-May-2026 17:57:39

    ensure fair compensation without destabilising infrastructure projects

    through retrospective lapses.

    50. The consistent thread running through statutory provisions,

    notifications, and judicial precedents is that Section 24 is neither

    incidental nor ancillary to compensation determination. It is a drastic

    transitional provision tied exclusively to the repeal of the Land

    Acquisition Act, 1894. To apply it to National Highways Act, 1956

    acquisitions would amount to rewriting both statutes and disregarding

    the Fourth Schedule exemption.

    51. In sum, the legal position is clear. Section 24 of the RFCTLARR Act,

    2013 applies only to acquisitions initiated under the Land Acquisition

    Act, 1894. The National Highways Act, 1956 constitutes a distinct

    acquisition code, expressly exempted from the general application of

    the 2013 Act. Only specified provisions relating to compensation,

    rehabilitation, and amenities have been extended through the

    notification dated 28.8.2015, and Section 24 is not among them. Any

    application of Section 24 to National Highway acquisitions under the

    1956 Act would be contrary to the express statutory language,

    legislative intent, and binding authority of the Hon’ble Supreme Court.

    52. Ld. counsel for the Appellant has also repeatedly contended that where

    awards have been passed and compensation deposited prior to

    1.1.2015, the authorities become functus officio and lack jurisdiction to

    reopen or redetermine compensation by invoking the RFCTLARR Act.

    Reliance has been placed on judicial precedents, including Gopa Ram

    Page 26
    Signature Not Verified
    Digitally Signed
    Signed by: BHABAGRAHI JHANKAR
    Reason: Authentication
    Location: ORISSA HIGH COURT, CUTTACK
    Date: 21-May-2026 17:57:39

    v. Union of India and Lanka Prabhakar v. Union of India19, which

    categorically hold that Section 24 of the 2013 Act does not apply to

    acquisitions under the National Highways Act, particularly where

    awards were passed and compensation deposited before the cut-off

    date.

    53. The argument that administrative authorities under the National

    Highways Act become functus officio after passing the award is

    grounded in statutory design. Section 3G entrusts the competent

    authority with the task of determining compensation, and Section 3G(5)

    provides for arbitration if the amount is not acceptable. Once these

    statutory functions are discharged, neither the competent authority nor

    the arbitrator retains any residual power to reopen concluded awards

    in the absence of express statutory authorization. Any direction for

    redetermination dehors the statute would therefore be without

    jurisdiction.

    54. The plea based on principles of equality and uniformity, though

    appealing at first blush, cannot override the statutory mandate. Courts

    have consistently held that equity cannot supplant law, particularly in

    matters governed by clear legislative command. As observed in judicial

    reasoning addressing similar contentions, the discomfort or perceived

    unfairness experienced by landowners cannot justify judicial extension

    of a statutory provision beyond its text. The rule of law requires that

    statutory authorities act strictly within the four corners of the statute

    conferring power.

    19

    S.B. Civil Writ Petition No.12746 of 2017 (Rajastan High Court)

    Page 27
    Signature Not Verified
    Digitally Signed
    Signed by: BHABAGRAHI JHANKAR
    Reason: Authentication
    Location: ORISSA HIGH COURT, CUTTACK
    Date: 21-May-2026 17:57:39

    55. This legal position is also reinforced by the express opinion of the Ld.

    Attorney General of India, rendered upon consultation by the Ministry

    of Road Transport and Highways. The Ld. Attorney General

    unequivocally opined that Section 24 of the RFCTLARR Act, 2013

    applies only to acquisitions undertaken under the Land Acquisition

    Act, 1894, and that Section 105(1) of the 2013 Act excludes the

    application of all provisions of the Act to Fourth Schedule enactments,

    save to the limited extent permitted under Section 105(3). The opinion

    further clarifies that only the First, Second, and Third Schedules have

    been made applicable to the National Highways Act.

    56. This interpretation has also found reflection in the comprehensive

    guidelines issued by the Government of India, Ministry of Road

    Transport and Highways, dated 28.12.2017. The guidelines trace the

    legislative and administrative evolution of the applicability of the

    RFCTLARR Act to National Highways acquisitions and conclusively

    state that Section 24 is not applicable to acquisitions under the National

    Highways Act, 1956. The guidelines specifically clarify that where the

    acquisition process stood completed on or before 31.12.2014–meaning

    the award was announced, funds deposited, and compensation paid to

    the majority of landowners, the process is deemed settled and cannot

    be reopened.

    57. The circular records that although the RFCTLARR Act came into force

    on 1.1.2014, the applicability of its provisions to enactments listed in the

    Fourth Schedule, including the National Highways Act, was governed

    exclusively by Section 105 of the Act and subsequent amendment

    Page 28
    Signature Not Verified
    Digitally Signed
    Signed by: BHABAGRAHI JHANKAR
    Reason: Authentication
    Location: ORISSA HIGH COURT, CUTTACK
    Date: 21-May-2026 17:57:39

    ordinances and notifications. It reiterates that, with effect from 1.1.2015,

    only select provisions of the RFCTLARR Act were extended to

    acquisitions under the National Highways Act.

    58. The guidelines specifically state that “it remains an unambiguous and

    accepted position that the provisions of the Right to Fair Compensation and

    Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013,

    relating to the determination of compensation in accordance with the First

    Schedule, rehabilitation and resettlement in accordance with the Second

    Schedule and infrastructure amenities in accordance with the Third Schedule

    have been made applicable to all cases of land acquisition under the NH Act,

    1956… with effect from 01.01.2015.” By expressly enumerating the

    provisions extended, the circular makes it clear that no other provisions

    of the RFCTLARR Act stand incorporated into the National Highways

    Act acquisition regime.

    59. A separate and dedicated portion of the guidelines addresses the

    question of applicability of Section 24 of the RFCTLARR Act, 2013 to

    acquisitions under the National Highways Act. The circular records

    that although an earlier Office Memorandum dated 13.1.2016 had

    suggested applicability of Section 24, the issue was revisited in

    consultation with the Ld. Attorney General. Upon such reconsideration,

    the Attorney General opined that “a reading of Section 24 makes it

    abundantly clear that the provision is applicable only to acquisitions that have

    been undertaken under the Land Acquisition Act, 1894, inasmuch as the

    legislative intent can be ascertained from the specific mention of the ‘Land

    Acquisition Act, 1894‘.” The opinion further notes that Section 105(1) of

    Page 29
    Signature Not Verified
    Digitally Signed
    Signed by: BHABAGRAHI JHANKAR
    Reason: Authentication
    Location: ORISSA HIGH COURT, CUTTACK
    Date: 21-May-2026 17:57:39

    the RFCTLARR Act expressly excludes application of the Act to Fourth

    Schedule enactments, and that “the only exception to Section 105(1) is

    Section 105(3), which makes only the First, Second and Third Schedule

    applicable to the Fourth Schedule Acts”.

    60. Accepting this opinion, the Ministry categorically concludes in the

    guidelines that “as such, it is now clear that Section 24 of the RFCTLARR

    Act, 2013 is not applicable to the acquisitions under the NH Act, 1956.” This

    clarification represents the final and considered executive position of

    the Union of India on the issue and expressly withdraws any contrary

    administrative understanding that may have prevailed earlier. The

    guidelines thus align executive interpretation with the statutory text of

    Section 24 and Section 105 of the RFCTLARR Act.

    61. The circular further clarifies the legal position regarding completed

    acquisitions by stating that in cases where “the process of acquisition of

    land stood completed (i.e. Award under Section 3G announced by CALA,

    amount deposited by the acquiring agency with the CALA, and compensation

    paid to the landowners in respect of majority of the land under acquisition) as

    on or before 31.12.2014, the process would be deemed to have been completed

    and settled. Such cases would not be re-opened.” This declaration directly

    negates any attempt to invoke Section 24-based lapse or

    redetermination in respect of acquisitions completed prior to the cut-off

    date.

    62. Viewed as a whole, the 28.12.2017 MoRTH guidelines conclusively

    affirm that acquisitions under the National Highways Act, 1956

    constitute a distinct statutory regime, insulated by the Fourth Schedule

    Page 30
    Signature Not Verified
    Digitally Signed
    Signed by: BHABAGRAHI JHANKAR
    Reason: Authentication
    Location: ORISSA HIGH COURT, CUTTACK
    Date: 21-May-2026 17:57:39

    to the RFCTLARR Act. Only limited provisions of the RFCTLARR Act

    relating to compensation, rehabilitation, and infrastructure amenities

    have been consciously extended, while Section 24 stands expressly

    excluded. These guidelines, grounded in statutory interpretation and

    the Ld. Attorney General’s opinion, lend authoritative support to the

    conclusion that Section 24 of the RFCTLARR Act, 2013 has no

    application whatsoever to land acquisitions undertaken under the

    National Highways Act, 1956.

    63. Viewed holistically, the statutory text of Section 24, the structure of the

    National Highways Act, 1956, the Fourth Schedule exemption under

    Section 105, the Ld. Attorney General’s opinion, executive guidelines,

    and consistent judicial precedent converge on a single conclusion.

    Section 24 of the RFCTLARR Act, 2013 is confined exclusively to

    acquisitions initiated under the Land Acquisition Act, 1894. It does not

    apply, either directly or by implication, to acquisitions under the

    National Highways Act, 1956, particularly where awards were passed

    and compensation deposited prior to 1.1.2015. Any contrary approach

    would amount to judicial legislation and would undermine the

    carefully calibrated statutory framework governing national highway

    acquisitions.

    64. Applying the aforesaid statutory scheme, executive guidelines, and

    binding judicial precedents to the facts as found and the dates already

    culled out by this Court, the conclusion is inescapable that the

    applications under Section 34 of the Arbitration and Conciliation Act,

    1996 were erroneously allowed by the Ld. District Judge. The

    Page 31
    Signature Not Verified
    Digitally Signed
    Signed by: BHABAGRAHI JHANKAR
    Reason: Authentication
    Location: ORISSA HIGH COURT, CUTTACK
    Date: 21-May-2026 17:57:39

    acquisition in the present cases was admittedly undertaken under the

    National Highways Act, 1956. The notifications under Sections 3A and

    3D were issued on 29.10.2012 and 21.5.2013 respectively, and the

    awards determining compensation under Section 3G were passed on

    18.10.2014. These dates are not in dispute. Thus, the acquisition

    proceedings had not only been initiated but had culminated in the

    passing of awards well before the cut-off date of 1.1.2015.

    65. The record further establishes that on the very date of passing of the

    awards, i.e. 18.10.2014, the Competent Authority requisitioned funds

    from the National Highways Authority of India, and the requisite

    compensation amounts were released on 8.12.2014. Consequently, as on

    or before 31.12.2014, the compensation stood fully sanctioned, released,

    and made available with the Competent Authority for disbursement. In

    terms of the comprehensive guidelines dated 28.12.2017 issued by the

    Ministry of Road Transport and Highways, such cases are expressly

    treated as having attained finality, it being clarified that where the

    award has been announced, funds deposited, and compensation paid

    to the majority of landowners on or before 31.12.2014, “the process would

    be deemed to have been completed and settled” and “such cases would not be

    re-opened”.

    66. Even assuming, arguendo, that disbursement to certain claimants

    occurred after 1.1.2015 owing to disputes regarding title or

    apportionment, such circumstance would not alter the legal position.

    The Hon’ble Supreme Court in Indore Development Authority v.

    Manohar Lal (supra) has made it clear that non-payment attributable to

    Page 32
    Signature Not Verified
    Digitally Signed
    Signed by: BHABAGRAHI JHANKAR
    Reason: Authentication
    Location: ORISSA HIGH COURT, CUTTACK
    Date: 21-May-2026 17:57:39

    reasons other than inaction of the acquiring authority does not result in

    lapse, and that tender or availability of compensation satisfies the

    statutory obligation. More importantly, Section 24 itself is confined to

    proceedings initiated under the Land Acquisition Act, 1894, and does

    not apply to acquisitions under special enactments.

    67. In the present cases, the Ld. District Judge proceeded on the

    assumption that Section 24 of the RFCTLARR Act, 2013 was applicable

    to acquisitions under the National Highways Act, 1956, and on that

    basis concluded that the arbitral awards dated 16.02.2018 were in

    conflict with public policy. This approach overlooks the express

    language of Section 24, the exemption carved out by Section 105 read

    with the Fourth Schedule, and the notification dated 28.08.2015, which

    extends only the First, Second and Third Schedules of the RFCTLARR

    Act to National Highways Act acquisitions. Section 24 is conspicuously

    absent from the provisions so extended.

    68. The executive position of the Union of India, as crystallised in the

    MoRTH guidelines dated 28.12.2017 and founded on the opinion of the

    Ld. Attorney General for India, further clarifies that “Section 24 of the

    RFCTLARR Act, 2013 is not applicable to the acquisitions under the NH Act,

    1956“. This clarification was issued after reconsideration of earlier

    instructions and leaves no scope for administrative or judicial doubt.

    The Ld. District Judge, however, failed to notice or give effect to this

    authoritative clarification and instead relied upon an erroneous

    extension of Section 24.

    Page 33
    Signature Not Verified
    Digitally Signed
    Signed by: BHABAGRAHI JHANKAR
    Reason: Authentication
    Location: ORISSA HIGH COURT, CUTTACK
    Date: 21-May-2026 17:57:39

    69. Once it is held that Section 24 of the RFCTLARR Act, 2013 does not

    apply to acquisitions under the National Highways Act, 1956, the very

    foundation of the impugned judgment collapses. The arbitral awards

    dated 16.2.2018 were passed strictly in exercise of powers under Section

    3G(5) of the National Highways Act, 1956, after the Competent

    Authority had already discharged its statutory function under Section

    3G(1). The Ld. Arbitrator, upon adjudication, upheld the determination

    of compensation. No ground falling within the limited contours of

    Section 34 of the Arbitration and Conciliation Act, 1996 was made out

    for interference.

    70. In view of the admitted dates, the completion of the acquisition process

    prior to 31.12.2014, the non-applicability of Section 24 of the

    RFCTLARR Act, 2013 to acquisitions under the National Highways Act,

    1956, and the settled legal position declared by the Hon’ble Supreme

    Court and clarified by the Union of India, this Court has no hesitation

    in holding that the ARBP applications ought not to have been allowed.

    The impugned judgment proceeds on a clear error of law apparent on

    the face of the record and cannot be sustained.

    VI. CONCLUSION:

    71. For the reasons recorded hereinabove, this Court is satisfied that the

    Ld. District Judge proceeded on an erroneous assumption of law in

    applying Section 24 of the RFCTLARR Act, 2013 to acquisitions made

    under the National Highways Act, 1956. The acquisition proceedings in

    the present cases had culminated in the passing of awards on

    18.10.2014, with funds duly released on 8.12.2014, well prior to the cut-

    Page 34
    Signature Not Verified
    Digitally Signed
    Signed by: BHABAGRAHI JHANKAR
    Reason: Authentication
    Location: ORISSA HIGH COURT, CUTTACK
    Date: 21-May-2026 17:57:39

    off date of 1.1.2015. In any event, Section 24 of the Act of 2013 has no

    application to acquisitions under the National Highways Act. The

    arbitral awards dated 16.2.2018 were thus validly passed within the

    statutory framework, and no ground existed for their interference

    under Section 34 of the Arbitration and Conciliation Act, 1996. The

    impugned judgment, being founded on an incorrect application of law

    and an excess of jurisdiction, cannot be sustained.

    72. Accordingly, ARBA No.13 of 2021 and ARBA No.14 of 2021 are

    allowed. The judgment dated 26.8.2021 passed by the Ld. District

    Judge, Sambalpur in ARBP No.02 of 2018 and ARBP No. 01 of 2018 is

    hereby set aside. The arbitral awards dated 16.2.2018 passed by the

    Collector-cum-Arbitrator, Sambalpur are restored and shall stand

    affirmed.

    73. There shall be no order as to costs.

    (Dr. Sanjeeb K Panigrahi)
    Judge

    Orissa High Court, Cuttack,
    Dated the 15th May, 2026/-

    Page 35

    [ad_1]

    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here