Anandapu Tirupathi vs The State Of Telangana on 7 April, 2026

    0
    51
    ADVERTISEMENT

    Telangana High Court

    Anandapu Tirupathi vs The State Of Telangana on 7 April, 2026

    Author: Nagesh Bheemapaka

    Bench: Nagesh Bheemapaka

                                          1
                                                                         wp_34438_2024
                                                                                 NBK, J
    
    
    
    
        IN THE HIGH COURT FOR THE STATE OF TELANGANA
                        AT HYDERABAD
    
          THE HON'BLE SRI JUSTICE NAGESH BHEEMAPAKA
    
                      WRIT PETITION No. 34438 of 2024
    
                                  07th April, 2026
    
    Between:
    
    1. Anandapu Tirupathi S/o Bhoomaiah, and others
                                                                    ... Petitioners
                                        AND
    1. The State of Telangana, and others
                                                                  ... Respondents
    ORDER:

    The case of the petitioners, precisely as per the writ affidavit, is that
    in the first week of April 2021, they first became aware–purely by
    chance–of a Section 3A notification published in Gazette No. 10162(E)
    dated 02.03.2021, which had appeared in newspapers on 25.03.2021,
    proposing acquisition of lands in approximately 10 villages in Chityal,
    Mogullapally, and Tekumatla mandals, including portions of the
    petitioners’ lands. The notification, however, contained only survey
    number-wise extents and lacked landowner details, preventing them from
    filing meaningful objections. Nevertheless, they submitted preliminary
    objections within the stipulated time to the competent authority, expressing
    their unwillingness to part with their lands and proposing, as an alternative,
    the expansion of an existing highway rather than the construction of a new
    one. These objections were reiterated during a discussion held on
    31.05.2021, where they emphasized their dependence on the land for
    2
    wp_34438_2024
    NBK, J

    livelihood. The petitioners assert that no formal notice of hearing, nor any
    communication regarding the disposal of their objections, was ever
    provided thereafter.

    SPONSORED

    1.1 It is stated that in March 2023, they came to know of a public
    notice under Section 3G displayed at the Gram Panchayat office, calling
    upon affected landowners to submit documents for compensation claims. It
    is stated that this was the first instance where farmer-wise extents of land
    acquisition was disclosed, as they had not been previously informed of the
    Section 3D declaration. Acting on this notice, some petitioners submitted
    representations highlighting discrepancies in survey numbers and extents,
    and pointing out the omission of structures and trees from the acquisition.
    They also reiterated their earlier objection to the project alignment. It is
    stated that the authoritiesorally assured them that these discrepancies
    would be examined and rectified prior to passing the awards.

    1.2. It is stated that, contrary to these assurances, during April and
    May 2024 the petitioners were served individual award notices specifying
    acquisition extents and compensation amounts. These notices allegedly
    stated that there were no trees or structures on the lands. They assert that
    no proper award enquiry was conducted and that they were denied copies
    of the award proceedings at that stage. Although officials, including the
    Tahsildar, subsequently visited the lands and conducted some form of
    enquiry, no prior notices, reports, or revised findings were shared with the
    petitioners. It was only in October 2024, through applications made under
    the Right to Information Act, they obtained copies of the awards and
    related proceedings, including modification orders dated 05.09.2024,
    which altered both land extents and compensation amounts without issuing
    fresh notices.

    3

    wp_34438_2024
    NBK, J

    1.3. Upon reviewing these documents, the petitioners discovered
    that multiple Section 3A notifications dated 10.03.2021 and 21.04.2022
    had been issued for the same highway stretch, followed by corresponding
    Section 3D declarations dated 22.02.2022 and 07.10.2022. They assert that
    only one set of notifications was ever publicly displayed, and that the
    second set was neither locally published nor communicated to them. They
    further allege that only one public notice under Section 3G(3) dated
    08.03.2023 was issued, and that no notice was given for the second set of
    proceedings. According to the petitioners, the authorities failed to provide
    landowner-specific details, did not conduct Gram Sabha consultations, and
    issued notifications in newspapers with negligible circulation, thereby
    defeating the statutory purpose of publication. It is alleged that no personal
    hearing was conducted before issuance of the Section 3D notification dated
    22.02.2022, nor were any orders disposing of their objections
    communicated.

    1.4. The petitioners contend that the awards themselves are legally
    unsustainable, as they omit compensation for structures and trees and fail
    to include Rehabilitation and Resettlement (R&R) benefits, which they
    contend are mandatory under the 2013 Act as applied to acquisitions under
    the National Highways Act. They assert that the term “compensation”
    under Section 3G must be interpreted to include not only land value but
    also structures and R&R entitlements, in accordance with Sections 16 to
    18, 21 to 30, 23, and 31 of the 2013 Act and the Schedules thereto. It is
    contended that possession cannot be taken under Section 3H unless such
    comprehensive compensation is determined and paid.

    1.5. It is contended that the respondent authorities have proceeded
    on the basis that valid notifications and awards were issued and that
    4
    wp_34438_2024
    NBK, J

    compensation has been determined in accordance with law. However, the
    petitioners state that the respondents ignored the discrepancies, failed to
    conduct proper enquiries, and subsequently issued modification orders to
    correct errors without granting any opportunity of hearing to the affected
    landowners, and these actions themselves demonstrate that the original
    notifications and awards were erroneous and issued without due diligence.

    1.6. The petitioners therefore contend that the entire acquisition
    process is procedurally flawed due to lack of diligence–from the initial
    notifications in March 2021 and April 2022, through the declarations in
    February and October 2022, the public notice in March 2023, the awards in
    January and March 2024, and the modifications in September 2024–is
    procedurally flawed.The petitioners contend that they remain in possession
    of the lands, with standing crops, and that any attempt to dispossess them
    without lawful determination and payment of full compensation and R&R
    benefits would cause irreparable harm.

    2. A counter affidavit has been filed by respondents No. 6 and 7,
    essentially contending that the petitioners have failed to establish any
    illegality in the acquisition process and that all actions undertaken for
    acquisition of land for the NH-163G project–from Km. 63.779 to Km.
    88.418 in Jayashankar Bhupalapally District–have been carried out
    strictly in accordance with the National Highways Act, 1956 and the
    applicable provisions of the Right to Fair Compensation and Transparency
    in Land Acquisition, Rehabilitation and Resettlement Act, 2013
    .

    2.1. Tit is stated that National Highways Authority of India
    (NHAI), constituted under the 1956 Act, initiated the greenfield highway
    project to reduce travel distance, lower vehicle operating costs, and
    5
    wp_34438_2024
    NBK, J

    promote economic development. The Revenue Divisional Officer,
    Bhupalpally, was duly appointed as the Competent Authority for Land
    Acquisition (CALA), and a requisition was made for acquisition of lands
    across 14 villages, including those of the petitioners. The process began
    with the issuance of a Section 3A notification vide S.O. No. 1016(E) dated
    02.03.2021, the substance of which was published in the newspapers
    “Mana Telangana” (Telugu) and “The Hindu” (English) on 25.03.2021,
    granting 21 days for objections. The respondents state that objections were
    indeed received from certain landowners, primarily seeking alignment
    changes and market-value compensation. In response, the CALA issued
    notices under Section 3C(2), calling all interested persons to appear for a
    personal hearing on 31.05.2021 at 11:00 AM. After considering these
    objections, the CALA rejected them through office proceedings No.
    J/69/2021/NH dated 05.08.2021, and communicated replies to the
    objectors. This culminated in the issuance of a Section 3D declaration vide
    S.O. No. 814(E) dated 22.02.2022.

    2.2. It is contended that an additional Section 3A notification vide
    S.O. No. 1869(E) dated 19.04.2022 was issued to cover certain missing
    extents, and its substance was published in the same newspapers on
    08.05.2022, again granting 21 days for objections. No objections were
    received in response to this second notification, leading to a subsequent
    Section 3D declaration vide S.O. No. 4780(E) dated 07.10.2022. It is
    contended that upon publication of the Section 3D notifications, the land
    vested absolutely in the Central Government free from encumbrances. It is
    stated that environmental clearance for the project was granted on
    05.07.2023 by the Ministry of Environment, Forest and Climate Change.

    6

    wp_34438_2024
    NBK, J

    2.3. It is stated that a public notice under Section 3G(3) was issued
    on 28.02.2023 in “Mana Telangana” and “The Hindu”, requiring interested
    persons to appear before the Competent Authority on 18.03.2023 during
    office hours to submit claims with documentary proof. Thereafter, awards
    were passed by Respondent No. 3/CALA on 16.01.2024 and 09.03.2024
    under proceedings No. J/69/2021-NH-163G/Nawabpet, following what
    they describe as a due and lawful enquiry process. These awards
    determined compensation in accordance with the NH Act, 1956 read with
    Sections 26 to 30 of the 2013 Act, and the awarded amounts were duly
    deposited with the competent authority. The respondents acknowledge that
    in some cases, landowners did not attend the enjoyment survey or award
    enquiry, or failed to produce title documents, leading the CALA to pass
    awards based on available records. Subsequently, when certain land losers
    submitted claims and documents or pointed out discrepancies in survey
    numbers and extents, a field survey was conducted and a modification
    award dated 05.09.2024 was issued to rectify such variations and correctly
    demarcate ownership and extents in revised statements.

    2.4. It is stated that objections were considered, and a personal
    hearing was conducted on 31.05.2021 and the objections were rejected
    vide orders issued on 05.08.2021. It is contended that notifications were
    duly published in widely circulated newspapers in Telugu and English
    languages, and that statutory requirements under Section 3A(3) were fully
    complied with. It is stated that additional notifications were issued Section
    3A
    notification dated 19.04.2022 only to include additional or missing
    extents, and there is no duplication or overlap of extents of land. It is also
    stated that opportunity under Section 3G, vide public notice dated
    28.02.2023 was afforded and the hearing was scheduled on 18.03.2023.

    7

    wp_34438_2024
    NBK, J

    2.5. It is contended that compensation was determined after due
    enquiry and in accordance with law, and that any subsequent corrections
    were legitimately addressed through the modification award dated
    05.09.2024. It is contended that this modification was a corrective measure
    undertaken after some landowners belatedly produced documents or raised
    discrepancies, and that the inconsistencies arose due to the petitioners’
    own failure to participate fully in the enquiry process or submit necessary
    documentation in time.

    2.6. It is contended that while compensation is to be determined
    under Sections 26 to 30 of the Act with effect from 01.01.2015, the
    provisions relating to Rehabilitation and Resettlement (R&R) under the
    Second and Third Schedules apply only in cases of actual displacement or
    dislocation, and the petitioners do not qualify as “displaced families” under
    Section 3(k), as only small extents of land have been acquired, thereby
    relocation or resettling the petitioners does not arise. They further contend
    that no documentary evidence has been produced by the petitioners to
    establish loss of livelihood or displacement, and that such factual
    determinations cannot be adjudicated in writ jurisdiction.

    2.7. It is contended that if the petitioners are aggrieved by the
    compensation awards, they have an alternative statutory remedy under
    Section 3G(5) of the NH Act, 1956 to approach the designated arbitrator,
    and therefore the writ petition is not maintainable.

    3. A counter affidavit has been filed by respondent No.3-Revenue
    Divisional Officer, acting as Competent Authority for Land Acquisition
    (CALA) and representing Respondent Nos. 1, 2, and 4. It is contended that
    there has been full compliance with statutory procedure at every stage of
    8
    wp_34438_2024
    NBK, J

    acquisition proceedings, right from issuance of Section 3A notification,
    and adequate opportunities were provided to landowners.

    3.1. It is contended that the acquisition relates to the greenfield
    highway alignment from Km. 63.779 to Km. 88.418 in Jayashankar
    Bhupalpally District, for which the Revenue Divisional Officer,
    Bhupalpally, was designated as CALA through Gazette Notification
    No.3099 dated 27.08.2019. The acquisition process formally commenced
    with the publication of a Section 3A notification in newspapers on
    25.03.2021, triggering a statutory 21-day period for objections, which
    expired on 14.04.2021. The respondent asserts that while some objections
    were received from certain interested persons, no objections were filed by
    the present petitioners within this stipulated period. Consequently, the
    process moved forward, and a Section 3D declaration was issued and
    published on 22.02.2022.

    3.2. It is contended that during the preparation of subdivision
    records following the first Section 3D notification, certain extents of land
    were found to have been inadvertently omitted from the initial Section 3A
    notification. To address this, additional Section 3A notifications were
    issued twice, strictly limited to the missing extents and without any
    overlap, followed by corresponding Section 3D and Section 3G
    proceedings after disposal of objections in accordance with Section 3C of
    the Act. The respondent emphasizes that all such notifications were
    published in compliance with statutory requirements, namely in two local
    newspapers–“Mana Telangana” (Telugu) and “The Hindu” (English)–as
    mandated, and that subsequent publications were made in the same
    newspapers to maintain procedural consistency.

    9

    wp_34438_2024
    NBK, J

    3.3. It is stated that environmental clearance for the project was
    granted by the Ministry of Environment, Forest and Climate Change on
    05.05.2023, and that this clearance was publicly notified in “Mana
    Telangana” on 25.08.2023. The respondent also refers to final declarations
    under Section 3D published in the Gazette of India on 28.02.2023 and
    23.08.2023 for additional extents, emphasizing that under Section 3D(2),
    the land vests absolutely in the Central Government upon such publication
    and cannot be challenged thereafter.

    3.4. It is stated that awards were passed under proceedings dated
    20.01.2024 and 14.03.2024, after conducting due enquiry under Section
    3G
    . These awardsdetermined compensation in accordance with Sections
    26
    to 30 of the RFCTLARR Act, 2013, including 100% solatium, 12%
    additional market value calculated from the date of the Section 3A
    notification to the date of the award, and a multiplication factor of 1.5
    applicable to rural lands. Following the awards, notices under Section 3E
    were issued to the petitioners to receive compensation, but the respondent
    alleges that they failed to come forward to collect the amounts. The
    respondent also details that where discrepancies in names or title were
    identified, corrections were made at the award stage through speaking
    orders based on original documents.

    3.5. It is contended that certain landowners, including petitioner
    No. 9, later submitted petitions highlighting discrepancies in survey
    alignments and extents, prompting a re-survey. This re-survey revealed
    variations, leading to the issuance of modified awards, supported by
    revised enjoyment statements, and the publication of re-survey reports in
    the village by Respondent No. 4. It is contended that these modifications
    were not procedural lapses but were legitimate corrections. Further, in
    10
    wp_34438_2024
    NBK, J

    relation to structures and trees, the initial resistance by some farmers
    prevented enumeration during the survey stage, resulting in awards being
    passed based on land value alone. However, after subsequent cooperation,
    enumeration reports were received, and the respondent has undertaken that
    supplementary award for structures and trees would be passed within one
    week.

    3.6. It is contended that both first and second notices were issued
    on 08.03.2023 and placed in the Gram Panchayat office, with individual
    notices served on the petitioners or their family members, including
    service on the parents of petitioner No. 10. It is contended that no houses
    have been displaced and that the petitioners do not fall within the
    definition of “displaced family.” It is contended that since no relocation or
    resettlement has occurred, the provisions of the Second and Third
    Schedules of the RFCTLARR Act, 2013
    are not attracted. The respondent
    reiterates that only compensation-related provisions under Sections 26 to
    30 apply, and that the compensation awarded already includes all statutory
    benefits such as solatium and additional market value.

    3.7. It is contended that out of 615 land losers affected by the
    project, only the present petitioners have approached the Court. It is stated
    some petitioners were parties to W.P. No. 13384 of 2023, which was
    disposed of on 06.03.2024 with directions not to interfere with possession
    without due process and compensation, and the directions of the Court
    have been fully complied with through lawful acquisition proceedings and
    payment of compensation, and therefore the writ petition is liable to be
    dismissed.

    11

    wp_34438_2024
    NBK, J

    4. A reply affidavit is filed by the petitioners, in response to the
    counter affidavit of the respondent No.3, essentially contending that the
    respondents have failed to demonstrate compliance with mandatory
    procedural safeguards under the National Highways Act, 1956 and the
    RFCTLARR Act, 2013, and that the acquisition process remains
    fundamentally vitiated by lack of due process, absence of proper notice
    and hearing, and failure to determine full statutory entitlements. They
    therefore maintain that the writ petition deserves to be allowed.

    4.1. It is stated that the petitioners had submitted objections and
    representations within time, however, the respondent has failed to produce
    anyrecord of consideration of those objections. They assert that no
    personal hearing under Section 3C was ever conducted and no order
    disposing of objections was communicated to them at any stage.

    4.2. It is contended that, by the respondent’s own admission, the
    environmental clearance for the project was obtained only on 05.07.2023,
    whereas the Section 3D declarations had already been issued earlier in
    2022 and 2023. On this basis, they contend that the declarations
    themselves are legally invalid, as they were made without prior
    environmental approval, and the clearance granted in July 2023 amounts to
    an impermissible post facto clearance.

    4.3. The petitioners contend that the repeated issuance of
    notifications–purportedly to cover “missing extents”–demonstrates a
    lack of due diligence in finalizing the alignment and preparing land
    records. This failure resulted in incomplete and vague initial notifications
    that did not contain subdivision-wise or pattadar-wise details, thereby
    depriving them of a meaningful opportunity to understand the extent of
    acquisition and to file effective objections. They further state that the
    12
    wp_34438_2024
    NBK, J

    issuance of a subsequent Section 3A notification on 19.04.2022 after a
    Section 3D declaration dated 22.02.2022 is procedurally impermissible.
    More critically, they allege that yet another Section 3A notification dated
    09.12.2024 was issued for the same lands even after passing of awards and
    after filing of the writ petition.

    4.4. It is contended that proper individual notices under Section
    3G(3)
    were not served, and merely placing notices in the Gram Panchayat
    does not satisfy the requirement of issuing individual notices to affected
    landowners. They further state that the alleged second Section 3G notice
    was never made available and that they could access such documents only
    later through RTI applications and newspaper publications. It is contended
    that no proper survey or marking exercise was conducted by the
    authorities, which is evident from the repeated issuance of notifications. It
    is contended that if authorities could measure land extents, there was no
    justification for failing to enumerate trees and structures, and therefore the
    awards passed without including such components are incomplete and
    invalid.

    4.5. It is contended that Rehabilitation and Resettlement benefits
    under the Second Schedule, by virtue of the Removal of Difficulties Order,
    2015, apply to acquisitions under the National Highways Act; and that no
    Rehabilitation and Resettlement awards have been passed till date, and
    therefore possession cannot be taken until full statutory entitlements are
    determined and paid.

    4.6. The petitioners reject the respondent’s suggestion that they
    should pursue arbitration under Section 3G(5), by contending that their
    challenge is to the legality of the acquisition process itself. It is contended
    that despite interim orders of the Court, the respondent authorities entered
    13
    wp_34438_2024
    NBK, J

    the lands of petitioner Nos. 1 and 9 on 14.06.2025 and damaged standing
    crops, and that no remedial action was taken despite representations and
    indicate their intention to initiate contempt proceedings.

    5. Heard Mr. Ch. Ravi Kumar, learned counsel for the petitioners;
    learned Standing Counsel for NHAI, learned Standing Counsel for
    CALA,and Mr. B. Narasimha Sarma, learned Additional Solicitor General
    of India. Perused the record.

    6. Learned counsel for the petitioners would essentially contend that
    the entire land acquisition process undertaken for the NH-163G project
    from Km. 63.779 to Km. 88.418 is vitiated by procedural illegality,
    arbitrariness, and violation of principles of natural justice, warranting
    interference under Article 226. It is contended that the Section 3A
    notifications dated 02.03.2021 and 19.04.2022, and the subsequent Section
    3D
    declarations dated 22.02.2022 and 07.10.2022, suffer from lack of
    proper publication, absence of landowners details, and failure to provide
    meaningful opportunity to file objections, as the petitioners came to know
    of the acquisition only in April 2021 through newspapers with no local
    circulation. It is contended that although objections were filed and
    reiterated on 31.05.2021, no personal hearing under Section 3C was
    conducted and no order with regard to disposal of their objections was ever
    communicated. It is further contended that the authorities issued multiple
    and inconsistent notifications for the same lands without finalizing
    alignment, thereby depriving the petitioners of their statutory rights. The
    public notice under Section 3G(3) dated 08.03.2023 was the first instance
    where actual extents were disclosed, and even thereafter, discrepancies in
    survey numbers, omission of structures and trees, and lack of clarity
    14
    wp_34438_2024
    NBK, J

    persisted. The awards dated 16.01.2024 and 09.03.2024 are assailed as
    incomplete and arbitrary, as they exclude compensation for structures and
    trees and omit mandatory Rehabilitation and Resettlement benefits under
    the RFCTLARR Act, 2013 read with the Removal of Difficulties Order
    dated 28.08.2015. It is contended that the subsequent modification orders
    dated 05.09.2024, altering extents and compensation without notice,
    themselves demonstrate lack of due diligence and illegality in the original
    awards. The counsel argues that possession cannot be taken under Section
    3H
    unless full compensation, including R&R entitlements, is determined
    and paid. It is also submitted that there was no proper survey, no Gram
    Sabha consultation, and no transparency in the process. It is stated that out
    of 11 petitioners, only petitioner Nos. 1, 3, 8, 9 and 10 are challenging the
    acquisition proceedings in this writ petition, and the other petitioners
    received the compensation and have withdrawn from the writ petition.
    Learned counsel therefore seek to set aside the impugned notifications,
    awards, and proceedings insofar as the petitioners No. 1, 3, 8, 9 and 10 are
    concerned, and that fresh acquisition proceedings be initiated, at least from
    the Section 3G(3) stage if not from Section 3A, with proper notice,
    accurate land details, and lawful determination of compensation including
    all statutory benefits.

    6.1. Learned counsel for the petitionersrelies on:

    1) Akkala Chandrakala v. The State of Telangana 1;

    2) Kolkata Municipal Corporation v. Bimal Kumar Shah 2;

    3) B.K. Ravichandra v. Union of India 3;

    4) Hindustan Petroleum Corpn. Ltd. v. Darius Shapur Chenai 4;

    1

    W.P. No. 11486 of 2024 (Telangana High Court)
    2
    (2024) 10 SCC 533
    3
    (2021) 14 SCC 703
    4
    (2005) 7 SCC 627
    15
    wp_34438_2024
    NBK, J

    5) K. Ramachandram v. State of Telangana 5;

    6) Madi Satyavati v. State of Telangana 6;

    7) Manorama Devi v. National Highways Authority of India 7;

    8) Nagpur Improvement Trust v. Vithal Rao 8;

    9) National Highways Authority of India v. P. Nagaraju alias Cheluvaiah 9;

    10)Ranivr Singh v. National Highways Authority of India 10;

    11) Union of India v. Shiv Raj 11;

    12) State of Uttar Pradesh v. Singhara Singh 12

    6.2. In Akkala Chandrakala (supra), this Courtconsidered a
    dispute over land acquisition for the development of National Highway
    765DG. The petitioners, whose homes were being acquired, sought
    Rehabilitation and Resettlement (R&R) benefits under the Right to Fair
    Compensation and Transparency in Land Acquisition, Rehabilitation and
    Resettlement Act, 2013
    , while government authorities argued that such
    benefits were not applicable to the road-widening project under the
    National Highways Act, 1956. This Court, by interim order dated
    12.11.2024, rejected the authorities’ prayer to vacate an earlier stay order
    and indicated that highway acquisitions remain subject to modern R&R
    protections, and granted status quo until final hearing, while allowing
    authorities to begin the formal process of determining and awarding R&R
    compensation.

    5

    W.P. No. 23939 of 2013 (Telangana High Court)
    6
    W.A. No. 676 of 2023 (Telangana High Court)
    7
    Neutral Citation No. 2023:AHC:240588 – DB (Allahabad High Court)
    8
    (1973) 1 SCC 500
    9
    (2022) 15 SCC 1
    10
    2023 SCC OnLine All 5276
    11
    (2014) 6 SCC 564
    12
    1963 SCC OnLine SC 23
    16
    wp_34438_2024
    NBK, J

    6.3. In Bimal Kumar Shah (supra), the Hon’ble Supreme Court
    broadened the understanding of the constitutional right to property under
    Article 300-A of the Constitution of India by stating that lawful land
    acquisition requires more than just public purpose and compensation. The
    Hon’ble Supreme Court identified seven essential procedural sub-rights–
    including the right to notice, the right to be heard, and the right to a
    reasoned decision–along with requirements for an efficient process and
    fair rehabilitation. Ruling against the Kolkata Municipal Corporation, the
    Supreme Court held that any State action that ignores these safeguards is
    invalid.

    6.4. In B.K. Ravichandra (supra), the Hon’ble Supreme Court
    clarified the limits of Government power over private property. The
    Supreme Court held that although the right to property is no longer a
    fundamental right, it remains a constitutional safeguard under Article 300-
    A
    of the Constitution of India, protecting both physical land and intangible
    assets, and the government cannot occupy private land indefinitely without
    proper legal authority, as prolonged possession amounts to unlawful
    deprivation of property. Emphasizing the rule of law, the Court rejected
    any notion that the State can act with “royal prerogative” and insisted that
    all State actions must be backed by clear statutory authority. As a result,
    the Court ordered the return of land that had been held by the government
    for over thirty years and directed that fair compensation be paid to the
    rightful owners.

    6.5. In Darius Shapur Chenai (supra), the Hon’ble Supreme
    Court examined the procedural safeguards required under the Land
    Acquisition Act, 1894
    during the acquisition of private property. The
    Supreme Court focused on whether the State had genuinely considered the
    17
    wp_34438_2024
    NBK, J

    landowner’s objections as required under Section 5-A of the Land
    Acquisition Act, 1894. It held that the right to object and be heard under
    Section 5-A is a significant safeguard–comparable in importance to a
    fundamental right–and must involve a real and careful consideration by
    the government rather than a mere formality. The Court further ruled that
    when such decisions are challenged, the government must produce its
    records to demonstrate that a fair decision-making process was followed.
    Since the State failed to provide adequate evidence or a proper counter-
    affidavit, the Court upheld the quashing of the acquisition, reinforcing that
    laws allowing the taking of private property must be strictly interpreted to
    prevent arbitrary state action.

    6.6. In K. Ramachandram(supra), this Courtexamined whether
    the government had followed the required statutory procedures while
    attempting to acquire the petitioner’s land; and held that although the
    preliminary notification remained valid because it had been properly
    extended, the later declaration was unlawful due to the authorities’ failure
    to prepare and publish mandatory rehabilitation and resettlement schemes
    under the Right to Fair Compensation and Transparency in Land
    Acquisition, Rehabilitation and Resettlement Act, 2013
    . Finding that these
    procedural safeguards are essential to protect the landowner’s rights, the
    declaration was quashed with a direction to the government to strictly
    comply with the Act if it wishes to proceed with the acquisition, while also
    encouraging both parties to pursue an amicable settlement through land
    exchange or fair monetary compensation.

    18

    wp_34438_2024
    NBK, J

    6.7. In Madi Satyavati v. State of Telangana 13, the Division
    Bench of this Court dealt with a matter pertaining to land acquisition for a
    railway project; and held that not only the mother, but also her three
    daughters, qualify as an affected family under Right to Fair Compensation
    and Transparency in Land Acquisition, Rehabilitation and Resettlement
    Act, 2013
    ; and modified a prior order to ensure that rehabilitation benefits
    are determined for the daughters in addition to the mother’s solatium and
    allowed the appellants to seek a formal reference if they are dissatisfied
    with the final monetary compensation, reinforcing that the rights of all
    affected family members must be recognized in land acquisition cases.

    6.8. In Manorama Devi (supra), the Allahabad High Court
    adjudicated a petition filed by Manorma Devi against the National
    Highway Authority of India. The Allahabad High Court addressed her
    claim for rehabilitation and resettlement benefits, which she had not
    received despite being compensated for her land. The Court observed that
    her grievance aligned with previous cases under the Right to Fair
    Compensation and Transparency in Land Acquisition, Rehabilitation and
    Resettlement Act, 2013
    , where affected landowners were entitled to
    additional support. It directed the authorities to prepare a formal proposal
    within six months to provide the petitioner with entitlements for housing,
    employment, and relocation as outlined in the Second Schedule of the Act,
    and granted legal relief consistent with earlier, similar judgments.

    6.9. In Nagpur Improvement Trust (supra), the Hon’ble
    Supreme Court examined whether the Nagpur Improvement Trust Act
    violated Article 14 of the Constitution of India by allowing the State to
    acquire property at lower compensation rates than standard national laws.

    13

    W.A. No. 676 of 2023 (Telangana High Court)
    19
    wp_34438_2024
    NBK, J

    The Supreme Court held that the Government cannot justify paying
    different amounts for similar lands based solely on which authority
    conducts the acquisition or the stated public purpose. Emphasizing the
    principle of equal protection, the judgment affirmed that landowners are
    entitled to consistent, market-value compensation regardless of the
    acquiring body, and dismissed the appeal, ruling that discriminatory
    treatment in compensation or statutory bonuses is unconstitutional.

    6.10. In P. Nagaraju alias Cheluvaiah (supra), the Hon’ble
    Supreme Court addressed the determination of fair compensation and
    clarified the role of Courts in reviewing arbitral awards under Section 34
    of the Arbitration and Conciliation Act, 1996. The Supreme Court held
    that an arbitrator’s failure to provide adequate and intelligible reasoning
    for compensation constitutes a ground of “patent illegality,” justifying
    judicial intervention. Emphasizing equitable treatment for landowners,
    including solatium and interest, the ruling aligned compensation practices
    with constitutional protections and remanded the matter for recalculation
    of the property’s market value using proper evidence and updated
    guideline rates.

    6.11. In Ranivr Singh (supra), the Allahabad High Court
    addressed petitions by displaced families who claimed that the National
    Highway Authority of India had failed to provide mandatory rehabilitation
    and resettlement benefits under the Right to Fair Compensation and
    Transparency in Land Acquisition, Rehabilitation and Resettlement Act,
    2013
    . The Court held that the status of affected families must be properly
    assessed, rejecting the authorities’ contention that linear road projects
    cause minimal disruption. It directed the competent authority to conduct a
    thorough inquiry and submit a resettlement proposal to the District
    20
    wp_34438_2024
    NBK, J

    Collector, ensuring that eligible landowners receive entitlements such as
    housing units, employment opportunities, or relocation allowances as part
    of their compensation.

    6.12. In Shiv Raj (supra), the Hon’ble Supreme Courtconsidered
    the validity of land acquisition proceedings under the Land Acquisition
    Act, 1894
    . The Supreme Court highlighted procedural lapses, including
    violations of natural justice where objections were heard by one official
    but the final report was issued by another without a fresh hearing. It also
    examined the impact of the Right to Fair Compensation and Transparency
    in Land Acquisition, Rehabilitation and Resettlement Act, 2013
    on older
    cases where the government delayed possession or failed to provide
    compensation for over five years.

    6.13. InSinghara Singh (supra), the Hon’ble Supreme Court
    addressed the admissibility of oral testimony regarding a defendant’s
    confession, arising from a Second-Class Magistrate’s failure to follow
    procedures under Section 164 of the Code of Criminal Procedure, 1973.

    7. Learned Standing Counsel for the respondent-NHAI would contend
    that the writ petition is wholly misconceived, devoid of merit, and liable to
    be dismissed in limine, as the entire land acquisition process for the NH-
    163G project from Km. 63.779 to Km. 88.418 has been strictly conducted
    in accordance with the National Highways Act, 1956 and the applicable
    provisions of the Act of 2013. It is submitted that the acquisition
    commenced with a Section 3A notification dated 02.03.2021, duly
    published on 25.03.2021 in “Mana Telangana” and “The Hindu”, granting
    21 days for objections, followed by a personal hearing conducted on
    31.05.2021 at 11:00 AM, and disposal of objections through proceedings
    21
    wp_34438_2024
    NBK, J

    dated 05.08.2021, culminating in the Section 3D declaration dated
    22.02.2022. It is further contended that an additional Section 3A
    notification dated 19.04.2022 was issued only to cover missing extents,
    with no objections received, leading to a subsequent Section 3D
    declaration dated 07.10.2022, upon which the land vested absolutely in the
    Central Government. It is contended that environmental clearance was
    granted on 05.07.2023, and thereafter a Section 3G(3) public notice dated
    28.02.2023 required landowners to attend enquiry on 18.03.2023 and
    submit claims. It is contended that awards dated 16.01.2024 and
    09.03.2024 were passed after due enquiry, compensation determined under
    Sections 26 to 30 of the 2013 Act, and amounts duly deposited, while a
    modification award dated 05.09.2024 was issued only to rectify
    discrepancies upon subsequent claims and surveys. It is further contended
    that discrepancies, if any, were due to non-participation or failure of
    certain petitioners to produce documents during enquiry, and were later
    corrected lawfully. Learned counsel contends that Rehabilitation and
    Resettlement benefitsapply only in cases of actual displacement, and the
    petitioners do not qualify as “displaced families” under Section 3(k), as
    only small extents were acquired. It is also submitted that the petitioners
    have not produced any proof of loss of livelihood, and the petitioners have
    an alternative remedy under Section 3G(5) by way of arbitration, and the
    writ petition not maintainable. It is contended that the directions in W.P.
    No. 13384 of 2023 have been misinterpreted by the petitioners; and that
    the present project is a vital public infrastructure initiative involving
    limited right-of-way of about 45 to 70 meters, causing minimal
    displacement, and any delays would lead to escalation of costs and loss to
    the public exchequer, and therefore the writ petition is liable to be
    dismissed.

    22

    wp_34438_2024
    NBK, J

    8. Learned counsel for the Competent Authority for Land Acquisition
    (CALA) would contend that the entire acquisition process for the NH-
    163G greenfield highway from Km. 63.779 to Km. 88.418 has been
    conducted strictly in accordance with the National Highways Act, 1956
    and the provisions of the RFCTLARR Act, 2013. It is submitted that the
    3rd respondent was duly appointed as CALA vide Gazette Notification No.
    3099 dated 27.08.2019, and the acquisition commenced with publication of
    Section 3A notification on 25.03.2021, granting 21 days up to 14.04.2021
    for filing objections, during which the present petitioners failed to submit
    any objections. It is contended that thereafter Section 3D declaration was
    validly issued on 22.02.2022, and additional Section 3A notifications were
    subsequently issued only to cover omitted extents, followed by
    corresponding 3D and 3G proceedings after due disposal of objections, all
    duly published in “Mana Telangana” and “The Hindu” as mandated.
    Learned counsel contends that environmental clearance was obtained on
    05.07.2023 and published on 25.08.2023, and final declarations under
    Section 3D were also published on 28.02.2023 and 23.08.2023, upon
    which the land vested absolutely in the Central Government. It is further
    contended that awards were passed on 20.01.2024 and 14.03.2024 after
    due enquiry under Section 3G, determining compensation in terms of
    Sections 26 to 30 of the 2013 Act, including 100% solatium, 12%
    additional market value, and multiplication factor of 1.5, and that notices
    under Section 3E were issued, but the petitioners failed to come forward to
    receive compensation. Learned counsel submits that any discrepancies in
    names, extents or survey details were corrected through re-survey
    conducted upon representations of landowners, leading to modified
    awards, which are lawful corrective measures and not procedural lapses. It
    23
    wp_34438_2024
    NBK, J

    is contended that omission of structures and trees in initial awards was due
    to resistance by some farmers during survey, and supplementary awards
    are being processed based on subsequent enumeration. Learned counsel
    contends that the petitioners failed to file objections within time, and all
    notifications were properly published as per statute. It is further submitted
    that Section 3G(3) notices dated 08.03.2023 were issued and displayed in
    Gram Panchayat offices and served individually, and therefore adequate
    opportunity was provided. Learned counsel contends that no houses were
    displaced and the petitioners do not fall within the definition of “displaced
    family,” thereby the Second and Third Schedules are not applicable.

    9. Learned Additional Solicitor General relies on several judgments in
    support of his contention that a writ remedy is not maintainable in the
    instant case; particularly on Ramniklal N. Bhutta v. State of
    Maharashtra14
    and contends that the Courts have to weigh the public
    interest vis-à-vis the private interest while exercising the power and there
    are many ways of affording appropriate relief and redressing a wrong, and
    that quashing of acquisition proceedings is not the only mode of redress.

    9.1. He also relies on Nerajala Nageswara Rao v. Union of
    India
    15, to contend that alternative remedy harsh one should not be
    resorted in public purpose projects and larger public purpose prevails over
    individual interest.
    He also relies on N.G. Projects Ltd. v. Vinod Kumar
    Jain16
    , to contend that construction of road is an infrastructure project and
    keeping in view the intent of the legislature that infrastructure projects
    should not be stayed, the High Court would have been well advised to hold
    its hand to stay the construction of the infrastructure project.

    14

    1997 (1) SCC 134
    15
    2017 SCC Online Hyd 250
    16
    2022 (6) SCC 127
    24
    wp_34438_2024
    NBK, J

    9.2. He also relies on Bluepark Seafoods (P) Ltd v. District
    Collector17 and contends that in case of acquisition for benefit of general
    public, the landowner can stake claim for reasonable compensation and
    nothing beyond that. Relying on NHAI v. Sayedabad Tea Company
    Ltd 18, it is contended that National Highways Act is a special enactment
    and a comprehensive code which provides an inbuilt mechanism for
    initiating acquisition until culmination of the proceedings in determining
    the compensation and its adjudication by arbitrator under Section 3-G(5) of
    the NH Act.

    9.3. He also relies on the judgment of the High Court of
    Karnataka, at Bengaluru, in W.P.No.10103 of 2020 (LA-RES) and
    batch, dated 19.07.2022, and contends that in the said case, the High
    Court of Karnataka has set aside the awards passed by the CALA and
    directed the authority to redetermine the compensation afresh, and if the
    parties are aggrieved by the fresh awards passed by the CALA, the parties
    can approach the arbitrator.

    9.4. He also relies on the judgment of Hon’ble Supreme Court in
    M/s Tirupati Developers v. The Union Territory of Dadra and Nagar
    Haveli19
    , and contends that the Hon’ble Supreme Court directed the
    Collector to give one opportunity to the appellant therein to submit its
    objections, followed by personal hearing and thereafter pass appropriate
    award after holding inquiry under Section 23 of the RTCTLARR Act, and
    therefore similar dispensation may be shown in the present writ petition as
    well in view of similarity of facts.

    17

    2011 SCC OnLine AP 267
    18
    (2020) 15 SCC 161
    19
    Civil Appeal No.4952 of 2023, dated August 7, 2023
    25
    wp_34438_2024
    NBK, J

    10. Having considered the respective contentions and perused the
    record, it may be noted that the grievance of the petitioners essentially is
    that multiple notifications under Sections 3A and 3D of the National
    Highways Act were issued with incomplete information, inadequate
    publication, and without providing proper landowner-wise details, maps,
    or an effective opportunity to file objections with regard to the acquisition
    of their agricultural lands for the proposed four-lane National Highway-
    163G, and that their objections were not properly considered. It is also
    contended that the authorities proceeded with the declaration and award
    process even before obtaining environmental clearance, issued additional
    notifications without informing the affected landowners, and passed
    incomplete compensation awards without determining compensation for
    structures and trees, and without granting rehabilitation and resettlement
    benefits as required under the RFCTLARR Act, 2013 and the Removal of
    Difficulties Order, 2015. They also allegedenial of statutory entitlements,
    and attempts by the authorities to forcibly take possession of their lands
    without paying lawful compensation, thereby threatening their livelihood
    as small and marginal farmers. It is also their grievance that the
    compensation cannot be confined only to the land on the mere ground that
    the land is an agricultural extent, and that compensation should also be
    granted for the structures existing on the land, and rehabilitation and
    resettlement benefits should be extended to the petitioners.

    10.1. On the contrary, the essential contention of the respondents
    (NHAI and CALA authorities) is that the acquisition of the petitioners’
    land for the construction of the four-lane National Highway-163G
    (Mancherial-Warangal Greenfield Corridor) has been carried out strictly in
    accordance with the procedure prescribed under the National Highways
    26
    wp_34438_2024
    NBK, J

    Act, 1956 and the applicable provisions of the RFCTLARR Act, 2013, and
    that all statutory steps–issuance of notifications under Sections 3A and
    3D, consideration of objections under Section 3C, conduct of enquiry, and
    passing of compensation awards under Section 3G–were duly followed.
    According to them, adequate opportunity was given to the landowners, and
    compensation has been determined and deposited as per law.It is also their
    contention that the entire village or villages have not been acquired,
    requiring the villagers, along with their houses, cattle, and livelihood, to be
    shifted/relocated to an alternative location, or re-establish the village at
    some other place entirely; but only such extent of land(s) that is under
    alignment would go into the highway project, and only such limited
    extents of land(s) were acquired, and therefore there cannot be any
    contentions of displacement of persons requiring rehabilitation and
    resettlement under the RFCTLARR Act because they are not “displaced
    families”. It is contended that any grievance regarding compensation must
    be pursued through the statutory remedy of arbitration under Section 3G(5)
    of the National Highways Act rather than through a writ petition, and the
    petitioners’ allegations are unfounded. They further contend that the
    interim order restraining the project may be vacated since it delays a
    project of national importance and public interest.

    11. At this juncture, it is to be noted that the project concerns the laying
    of a four-lane National Highway (Mancherial-Warangal Greenfield
    Corridor), and that land acquisition has been undertaken for the said
    highway. In land acquisition for a National Highway of this nature,
    connecting highways across States, the acquisition process or the laying of
    the highway per se cannot be stalled indefinitely by taking recourse to the
    extraordinary jurisdiction of this Court. Ultimately, the sole grievance that
    27
    wp_34438_2024
    NBK, J

    can be agitated by the aggrieved persons is confined to the compensatory
    benefits in lieu of the lands acquired, which is pecuniary in nature.

    11.1 Further, the petitioners’ grievance with regard to entitlement
    to compensation for structures, trees, standing crops, or even alternative
    rehabilitation/resettlement benefits is also justiciable, provided such
    structures are legally permitted, and the CALA has certified that the
    structures/crops, etc., have been affected in the land acquisition process, in
    a way that resettlement and rehabilitation is necessary.

    11.2 Be that as it may, in land acquisition for a public purpose,
    unless there are proven malafides, neither is the acquisition liable to be set
    aside, nor can the opinion of experts–either with regard to the alignment
    of the highway or with regard to the determination of factual aspects such
    as the extent of land acquired and the monetary compensation payable–be
    substituted by exercising extraordinary jurisdiction under Article 226.

    12. At this juncture, it would be relevant to refer to the judgment of the
    Hon’ble Supreme Court in Union of India v. Kushala Shetty 20, wherein it
    was held as follows:

    “24. Here, it will be apposite to mention that NHAI is a
    professionally managed statutory body having expertise in the
    field of development and maintenance of National Highways. The
    projects involving construction of new highways and widening
    and development of the existing highways, which are vital for
    development of infrastructure in the country, are entrusted to
    experts in the field of highways. It comprises of persons having
    vast knowledge and expertise in the field of highway development

    20
    (2011) 12 SCC 69
    28
    wp_34438_2024
    NBK, J

    and maintenance. NHAI prepares and implements projects relating
    to development and maintenance of National Highways after
    thorough study by experts in different fields. Detailed project
    reports are prepared keeping in view the relevant factors including
    intensity of heavy vehicular traffic and larger public interest. The
    Courts are not at all equipped to decide upon the viability and
    feasibility of the particular project and whether the particular
    alignment would subserve the larger public interest. In such
    matters, the scope of judicial review is very limited. The Court can
    nullify the acquisition of land and, in rarest of rare cases, the
    particular project, if it is found to be ex facie contrary to the
    mandate of law or tainted due to mala fides.”

    13. Further, it would be relevant to refer to the judgment of the Hon’ble
    Division Bench of this Court in Writ Appeal No.774 of 2024, dated
    07.08.2024, which is an appeal filed challenging a Notification for laying a
    national highway. The Hon’ble Division Bench, by referring to various
    precedent judgments of the Hon’ble Supreme Court, more particularly
    Kushala Shetty (supra), held as follows:

    “12. In view of aforesaid enunciation of law, it is evident that the
    projects involving construction of new highways and widening
    and development of existing highways are vital for development of
    infrastructure of the country. The projects have been entrusted to
    the experts in the field of highways and it comprises of persons
    having vast knowledge and expertise in the field of highway
    development and maintenance. The NHAI is implementing the
    project relating to development and maintenance after thorough
    study by experts.

    13. It is pertinent to note that in pursuance of the notification
    issued under the Act, award has already been passed on
    10.05.2022 and petitioners No.8 and 11 in W.P.No.24150 of 2021
    29
    wp_34438_2024
    NBK, J

    have even received the compensation. The project is virtually
    complete except for a small stretch.”

    14. In this connection, it is to be noted that under Section 3G of the
    National Highways Act, determination of compensation is entrusted to the
    Competent Authority for Land Acquisition (CALA). Significantly, Section
    3G(5) expressly provides that where the amount determined by the
    Competent Authority is not acceptable to either of the parties, the matter
    shall, on application, be referred to the Arbitrator appointed by the Central
    Government–ordinarily the District Collector. Thus, the statute itself
    creates a complete adjudicatory mechanism for redressal of disputes
    relating to compensation.

    15. Further, once the Arbitrator renders an award under Section 3G(5)
    of the National Highways Act, 1956, such award is governed by the
    provisions of the Arbitration and Conciliation Act, 1996; and the persons
    aggrieved by the arbitral award has a further statutory remedy under
    Section 34 of the Arbitration and Conciliation Act before the competent
    Civil Court.

    16. Though the existence of an alternative remedy is not a bar to
    invoking the writ jurisdiction of this Court under Article 226, its
    invocation comes with the rider that there should be exceptional
    circumstances, warranting invocation under Article 226 bypassing the
    statutory remedy. In this context, it is relevant to refer to the judgment of
    30
    wp_34438_2024
    NBK, J

    the Hon’ble Supreme Court in Whirlpool Corporation v. Registrar of
    Trademarks 21, wherein the Supreme Court held as follows:

    “15. Under Article 226 of the Constitution, the High Court, having
    regard to the facts of the case, has a discretion to entertain or not
    to entertain a writ petition. But the High Court has imposed upon
    itself certain restrictions one of which is that if an effective and
    efficacious remedy is available, the High Court would not normally
    exercise its jurisdiction. But the alternative remedy has been
    consistently held by this Court not to operate as a bar in at least
    three contingencies, namely, where the writ petition has been filed
    for the enforcement of any of the Fundamental Rights or where
    there has been a violation of the principle of natural justice or
    where the order or proceedings are wholly without jurisdiction or
    the vires of an Act is challenged.”

    17. In the instant writ petition, this Court does not find any violation of
    fundamental rights per se, or any violation of the principles of natural
    justice, or any jurisdictional error on the part of the respondent authorities;
    nor does the writ petition challenge the vires of the Act passed by the
    competent authority. Further, it is the specific unrebutted contention of the
    respondents, borne out by the record, that out of 615 affected persons, only
    the present petitioners are challenging the acquisition with the claim of
    compensation for structures, trees, etc., and also rehabilitation and
    resettlement benefits. Further, some of the writ petitioners in this writ
    petition have accepted the compensation, and withdrawn from the writ
    petition. Furthermore, despite there being certain delay in obtaining
    environmental clearance, the very acquisition notifications cannot be set
    aside, as the issuance of notifications and their publication in Mana

    21
    1998 (8) SCC 1
    31
    wp_34438_2024
    NBK, J

    Telangana (Telugu) and The Hindu (English) newspapers, and considering
    of objections are prima facienot in dispute. The contention of the
    petitioners that the newspapers have little circulation and the petitioners
    were not aware cannot be countenanced, as primarily they submitted their
    objections.

    18. Though the petitioners contend that they are entitled to certain
    rehabilitation and resettlement benefits, it cannot be disputed that the
    competent authority should have certified that the affected landowner has
    been displaced. Furthermore, the petitioners have a two-step statutory
    remedy, one under the National Highways Act, 1956 and, if still aggrieved,
    the second under the Arbitration and Conciliation Act, 1996, and therefore
    the petitioners are not remediless.

    19. In light of the judgment of Hon’ble Supreme Court in Kushala
    Shetty
    (supra), and Whirlpool Corporation (supra), and also the
    judgment of the Hon’ble Division Bench in W.A. No.774 of 2024, dated
    07.08.2024, this Court does not find any exceptional circumstances to
    entertain the writ petitionbypassing the statutory mechanism provided
    under the National Highways Act, 1956 and the Arbitration and
    Conciliation Act, 1996
    .

    20. Accordingly, the writ petition is disposed of, relegating the
    petitioners to avail the statutory remedy under Section 3G(5) of the
    National Highways Act, 1956 and thereafter, if necessary, under Section
    34
    of the Arbitration and Conciliation Act, 1996. No costs. Interim order
    dated 06.12.2024 stands vacated. Miscellaneous petitions pending, if any,
    shall stand closed.

    32

    wp_34438_2024
    NBK, J

    ________________________________
    JUSTICE NAGESH BHEEMAPAKA
    07thApril, 2026

    ksm
    33
    wp_34438_2024
    NBK, J

    THE HON’BLE SRI JUSTICE NAGESH BHEEMAPAKA

    WRIT PETITION No. 34438 of 2024

    07thApril, 2026

    ksm



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here