West Bengal Mineral Development And … vs Trans Damodar Coal Mining Pvt. Ltd on 7 May, 2026

    0
    29
    ADVERTISEMENT

    Calcutta High Court

    West Bengal Mineral Development And … vs Trans Damodar Coal Mining Pvt. Ltd on 7 May, 2026

    Author: Shampa Sarkar

    Bench: Shampa Sarkar

                          IN THE HIGH COURT AT CALCUTTA
                               ORIGINAL CIVIL JURISDICTION
                                     ORIGINAL SIDE
                                 COMMERCIAL DIVISION
    
    
    
    BEFORE :-
    THE HON'BLE JUSTICE SHAMPA SARKAR
    
                                    AP-COM/171/2024
                                  [OLD NO. AP/618/2019]
        WEST BENGAL MINERAL DEVELOPMENT AND TRADING CORPORATION LTD.
                                            VS
                        TRANS DAMODAR COAL MINING PVT. LTD.
                                            AND
                                    AP-COM/172/2024
                                  [OLD NO. AP/673/2019]
                        TRANS DAMODAR COAL MINING PVT. LTD.
                                            VS
        WEST BENGAL MINERAL DEVELOPMENT AND TRADING CORPORATION LTD.
    
    
      For the West Bengal Mineral                 :Mr. Kishore Datta, Ld. AG
      Development and                             Mr. Sanjay Saha, Adv.
      Trading Corporation Ltd.                     Mr. Chayan Gupta, Adv.
                                                  Mr. Aviroop Mitra, Adv.
    
      For the Respondent in                        :Mr. Jaydip Kar, Sr.Adv
      AP-COM 171 of 2024                           Ms. Manju Bhuteria, Sr. Adv
       for the petitioner in                       Mr. Kumar Gupta, Adv.
      AP-COM 172 of 2024                .          Ms. Meenakshi Manot, Adv.
                                                    Ms. Arundhuti Barman Roy, Adv.
                                                    Mr. Piyush Jain, Adv.
    
      Judgment Reserved on                         : 12.03.2026
      Judgment Delivered on                       : 06.05.2026
      Judgment Uploaded on                        : 06.05.2026
                                           2
    
    
         Shampa Sarkar, J.
    

    1. AP-COM 171 of 2024 and AP-COM No. 172 of 2024 arise out of an

    award dated June 13, 2019 made by a learned retired judge of this Court,

    SPONSORED

    who acted as the Arbitrator, for settlement of the dispute between the

    parties. AP-COM 171 of 2024 was filed by West Bengal Mineral Development

    and Trading Corporation Limited, the respondent in the arbitral proceeding.

    AP-COM 172 of 2024 was filed by the Trans Damodar Coal Mining Private

    Limited, the claimant before the learned arbitrator.

    2. Mr. Kishore Dutta, the then learned Advocate General appeared on

    behalf of the West Bengal Mineral Development and Trading Corporation

    (hereinafter referred to as the Corporation). He submitted that the award

    should be set aside for being patently illegal and contrary to public policy.

    The learned arbitrator, after having come to the conclusion that the contract

    between the parties was illegal and void ab initio, could not have taken

    recourse to the Coal Mines (Special Provisions) Act 2015, (hereinafter

    referred to as the 2015 Act) and allowed claims a,b,c,d,e,g,h,m,n.

    3. It was urged that the 2015 Act was promulgated to give full effect to

    the judgment of the Supreme Court in Manohar Lal Sharma vs. Principal

    Secretary and Ors., reported in (2014) 9 SCC 516. Referring to the

    Statements of Objects And Reasons of the 2015 Act, learned Advocate

    General submitted that, the 2015 Act was necessary in public interest as

    immediate action had to be taken to allocate coal mines to successful

    bidders and allottees, keeping in view the energy security of the country. The

    Act did not provide any security or protection to the contractors of the prior
    3

    allottee. By judgment dated August 25, 2014, the Hon’ble Supreme Court

    had held that allocation of coal blocks through the screening committee and

    the Government Dispensation route, was arbitrary and illegal. The Supreme

    Court cancelled the allocation of 204 coal blocks out of 218 since 1993. The

    Supreme Court further directed that additional levy of Rs. 295 per

    metric ton should be paid by the 42 coal blocks for the coal extracted since

    the commencement of production till 31st March, 2015. In light of the

    judgment of the Supreme Court, it was considered necessary in public

    interest that the Central Government should take immediate action so as

    to ensure energy security of the country.

    4. Learned Advocate General submitted that, the need for promulgation

    of the ordinance was to overcome the acute shortage of coal in core sectors

    such as steel, cement and power utilities, which were vital for the

    development of the country. Further, to mitigate the hardship of the

    household consumers, medium and small scale enterprises, cottage

    industries, a law was required to be put in place. As the Parliament was not

    in session and immediate action was required to be taken by the Central

    Government to implement the judgment and order of the Supreme Court

    and to address the objectives, an ordinance, namely Coal Mine (Special

    Provisions) Ordinance 2014 was promulgated by the President on 21st

    October, 2014 under Article 123 of the Constitution. After considering all

    such issues, it had been decided to include certain additional provisions in

    the Coal Mines (Special Provisions) Bill, 2015. The Bill provided for

    allocation of coal mines and vesting of right, title and interest in and over
    4

    the land and mine infrastructure together with mining leases to successful

    bidders and allottees, through a transparent bidding process with a view to

    ensure continuity in coal mining operations and production of coal and for

    promoting optimum utilization of the coal resources consistent with the

    country’s national interest. Further, having regard to the coordinated and

    scientific development and utilization of coal resources, consistent with the

    growing requirement of the country, the Bill prescribed certain conditions to

    rationalize the coal sector for mining operations, consumption and sale.

    Thereafter, the 2015 Act was promulgated. Special emphasis was laid on the

    Statement of Objects and Reasons by the learned Advocate General in order

    to support his contention that the said Act would be applicable only with

    regard to the dispute between the successful bidder and the prior allottee.

    The said Act protected the successful bidder. The Act would not be

    applicable to the claims of the contractor, arising out of the contract which

    had been entered into between the prior allottee and the contractor for the

    purpose of raising large quantity of coal from the Trans Damodar Coal

    Block. The allocation of the Trans Damodar sector of Raniganj Coal Field

    in favour of the West Bengal Mineral Development & Trading Corporation

    Limited by the Ministry of Coal, Government of India, had been cancelled by

    the Supreme Court.

    5. Learned Advocate General further submitted that the Preamble to the

    Act would indicate that the same was promulgated for allocation of coal

    mines and vesting of the right, title and interest in and over the land and

    mine infrastructure together with continuity in coal mining operation and
    5

    production of coal and for promoting optimum utilization of coal resources

    consistent with the requirement of the country in national interest, and

    matters connected therewith or incidental thereto. It was expedient in public

    interest for the Central Government to take immediate action to allocate coal

    mines to successful bidders and allottees, keeping in view the energy

    security of the country and to minimise the impact in the core sectors

    namely, steel, cement and power utility.

    6. The Parliament was competent to legislate under Entry 54 of List I of

    the Seventh Schedule of the Constitution for regulation of mines and for

    mineral development. The 2015 Act was not promulgated for settlement of

    disputes between the prior allottee and the contractor. The difficulties faced

    by the contractors after the decision of the Hon’ble Supreme Court in

    Manohar Lal Sharma (supra) cancelling the allocation of the coal block in

    respect of the Corporation, were not covered by the said Act. The Act only

    protected the subsequent successful bidders. Their rights and obligations

    vis-à-vis the prior allottee was the main purpose behind the promulgation of

    the said statute.

    7. It was next submitted that, in paragraphs 25 and 28 of the award, the

    learned arbitrator had clearly held that one party to the contract could not

    compel the other party to perform obligations arising out of a contract which

    was void under Section 23 of the Indian Contract Act. It was urged that the

    contentions of the learned Senior Advocate for the claimant made before the

    learned arbitrator, were not accepted by the learned Arbitrator, yet the

    claims were allowed.

    6

    8. The learned arbitrator held that a validly executed contract between

    the claimant and the respondent (Corporation) was inconsequential. The

    moment the Supreme Court declared the allotment in favour of the

    Corporation by the Central Government as illegal, the claimant could not

    pray for enforcement of any of the terms of the contract as the said contract

    for illegal mining was void.

    9. The learned arbitrator also held that the claimant was a third party

    who had entered into the contract with a prior allottee in respect of coal

    mining operations. The Corporation was a prior allottee within the meaning

    of the 2015 Act. Trans Damodar Coal Mine was a mine which figured in

    both Schedule 1 and Schedule 2 of the 2015 Act. The arbitrator had already

    relied upon various Supreme Court decisions, and held that the parties to a

    void contract, entered into in violation of Section 23 of the Contract Act,

    were remediless for the purpose of realization of money spent on such

    contracts or for enforcing the terms of such void contracts. The prior allottee

    and the third party with whom the contract had been made by the prior

    allottee were equally remediless. Having recognized the above position of

    law and upon holding that the prior allottee as also the third party

    were remediless and the enforcement of a void contract could not be

    permissible, the learned arbitrator arrogated to himself the power to award

    compensation and allow some of the claims. Such wrongful exercise

    of jurisdiction by invoking the provisions of the 2015 Act was legally

    untenable, and as such, the award suffered from patent illegality. The award

    was not only contrary to law, but also suffered from perversity as the
    7

    learned Arbitrator exceeded his jurisdiction and wrongly applied the

    provisions of the 2015 Act, with the intention to grant some relief to the

    claimant, although there was a legal bar. Thus, the award was also contrary

    to the public policy of India.

    10. The award should be set aside on the ground that the learned

    Arbitrator made out a third case on behalf the claimant. Learned Advocate

    General emphasized that the claimant had not made out a case for

    application of the provisions of the 2015 Act qua the dispute between the

    parties. The statement of claim and the averments therein,

    would indicate that the disputes between the parties were purely

    contractual. Both parties proceeded on the basis that the contract was valid.

    Specific pleadings in paragraph 25, 27, 35 and 38 of the statement of claim

    would indicate that the claimant had admitted that the dispute arose solely

    out of the contract. The claimant did not seek redressal under the 2015

    Act. Reference was made to question numbers 72 to 89 of the cross-

    examination in support of the contention that the witness of the Corporation

    was not put any suggestion in the cross-examination with regard to the

    applicability of the 2015 Act. The specific case of the Corporation was that,

    the additional levy paid by the Corporation to the Government of India was

    appropriated from the claimants payment’, on the basis of clarification and

    modification to the contract agreement dated March 31, 2010. RW1, in his

    cross-examination had specifically emphasized such fact and he

    also stated that the recovery of dues from the contractor was guided by the

    terms of the agreement executed between the parties. No contrary
    8

    suggestion was put to RW1 by the claimant on the applicability of the

    provisions of the 2015 Act qua the dispute between the parties. Thus, the

    learned arbitrator erred in holding that the 2015 Act also applied in cases of

    contractors of prior allottees and that their rights vis-a-vis such contracts

    which were otherwise void, were protected to some extent under the 2015

    Act. In the absence of any foundation in the pleadings with regard to the

    applicability of the 2015 Act in respect of disputes between the parties, and

    in the absence of any evidence being led and no suggestions having been

    put to the witnesses of the Corporation with regard to the applicability of the

    2015 Act, the learned arbitrator committed jurisdictional error in holding

    that the 2015 Act would come to the aid of the claimant, and some of the

    claims against the Corporation, for the breaches committed by the

    Corporation in respect of the contract, could be permitted under the 2015

    Act.

    11. Once the contract was found to be void, the arbitrator did not have

    any jurisdiction to pass the award. The arbitrator assumed jurisdiction from

    the contract. He exceeded his jurisdiction by deciding the dispute on the

    anvil of the 2015 Act. The dispute between the prior allottee and the

    contractors was never the subject matter of either of the judgments in

    Manohar Lal Judgments reported in (2014) 11 SCC 516 and (2014) 11

    SCC 614 (hereinafter referred to as Manohar Lal Sharma 1 and 2

    respectively). The other feature of the 2015 Act was to protect the successful

    bidder from claims which other entities may have against the prior

    allottee. The interpretation of the learned Arbitrator with regard to the
    9

    various sections of the 2015 Act, were all misconceived and de hors the

    object of the 2015 Act. Even if it was assumed that, the 2015 Act could be

    made applicable, in that event Section 27 of the said Act provided for a

    tribunal for redressal of all grievances. Section 29 of the 2015 Act had the

    effect of overriding all instruments, including the subject contract. The

    finding in the award that Section 11 of the 2015 Act treated contracts which

    were otherwise void as valid, was contrary to the provisions of the 2015 Act.

    Likewise, the finding that by applying Section 11(2) of the 2015 Act, the

    third party contractor had remedies against the prior allottee, was also

    contrary to law.

    12. The law was misinterpreted and the learned Arbitrator misdirected

    himself by holding that the cancellation would take effect on 31st March

    2015. The Supreme Court did not keep the contract between prior allottee

    and the contractor valid till 31st March 2015. The contract between the

    parties became impossible to perform in view of the judgment of the

    Supreme Court. The said contract could not be revived by any statute, more

    so by a statutory interpretation, especially in the absence of any specific

    provision thereunder. The operation of coalmines was allowed till 31st

    March 2015, to facilitate holding of a fresh allocation process of coal blocks,

    and in order to protect the industries by ensuring adequate supply of energy

    to the core sectors.

    13. The judgments of the Supreme Court could not be interpreted to mean

    that the Supreme Court had accorded any sanctity to the contract between

    the third party and the corporation. The judgments were restricted to the
    10

    validity in the allotment of the coal blocks. Even the public sector

    undertakings were not protected. The consequence of such reallocation

    and/or cancellation of allocation was the subject matter of the decision in

    Manohar Lal Sharma (2). The right of the contractor vis-a-vis the prior

    allottee were not a relevant issue before the Hon’ble Supreme Court and the

    2015 Act. Both the judgments dealt with the issues with regard to recovery

    and imposition of additional levy from the prior allottee.

    14. Learned Advocate General relied on various paragraphs

    of both judgments to emphasize that neither the judgments of the Supreme

    Court nor the enactment of 2015 Act, were concerned with the right of the

    contractor of the prior allottee and the obligation arising out of those

    contracts vis-à-vis the parties. The claimant proceeded on the basis that the

    contracts between the parties were valid and the Corporation had committed

    breach of those contractual terms. The allegations of the claimant against

    the Corporation, were restricted to non-performance of the contractual

    obligation and nothing beyond. Thus, it was prayed that the award should

    be set aside.

    15. Mr. Jaydip Kar learned Senior Advocate for the claimant submitted

    that the learned Arbitrator allowed claims a, b, c, d, e g, h, m and n with

    elaborate reasons and by following the principle of restitution.

    16. According to Mr. Kar, the primary grounds for challenge by the

    Corporation were patent illegality, perversity, jurisdictional error and

    violation of the public policy of India. The grounds on which an award could

    be set aside were specified under Section 34(2)(a) and 34(2)(b) as also
    11

    Section 34(2A) of the Arbitration and Conciliation Act, 1996 (hereinafter

    referred to as the A & C Act). None of the grounds for setting aside the

    award could be established. Section 34(2)(b) provided that, when the award

    was in contravention to the fundamental policy of Indian law or was in

    conflict with the most basic notions of morality and justice, the award could

    be set aside. The award, read as a whole, would clearly indicate that the

    aforementioned grounds would not be attracted. Section 34(2)(a) provided

    that an arbitral award arising out of a domestic arbitration, could be set

    aside by the court, if the court found that the award was vitiated by patent

    illegality, apparent on the face of the award. The case of patent illegality

    could not be established in the course of arguments by the learned Advocate

    General.

    17. Mr. Kar relied on the decisions of the Hon’ble Apex Court in MMTC

    Limited vs Vedanta Ltd. reported in (2019) 4 SCC 163, and Ssangyong

    Engineering & Construction Company Limited vs National Highways

    Authority of India (NHAI) reported in (2019) 15 SCC 131. In the above

    decisions, the Hon’ble Apex Court had laid down the scope of an application

    under Section 34 of the A & C Act. The Hon’ble Apex Court observed that,

    patent illegality on the face of the award would mean such illegality which

    would go to the root of the matter. Erroneous application of law would not

    qualify as patent illegality. Moreover, what was not subsumed within the

    fundamental policy of Indian law, i.e, contravention of a statute not linked to

    public policy or public interest, could not be brought in by the back door

    when it came to setting aside an award on the ground of patent illegality.
    12

    18. Reliance was also placed on Patel Engg. Ltd. vs North Eastern

    Electric Power Corporation Ltd. reported in (2020) 7 SCC 167 and

    Reliance Infrastructure Ltd. vs State of Goa reported in (2024) 1 SCC

    479. According to Mr. Kar, the ratio which could be carved out from the

    above cited decisions was that, mere illegality would not call for interference

    with the award but “patent illegality” must be apparent on the face of the

    award. Patent illegality could not be culled out by way of a long-drawn

    analysis of the pleadings and evidence.

    19. Further Reliance was placed on Hindustan Construction Co. Ltd vs

    NHAI reported in (2024) 2 SCC 613. According to Mr. Kar, the view of the

    learned Arbitrator was a possible view and this Court should accept such

    view. Courts were debarred from reviewing the conclusion arrived at by the

    learned Arbitrator, only on the ground that an alternative or a better view

    could be possible. The jurisdiction of the Court under Section 34 of the said

    Act was not to correct the opinion and/or the findings of the learned

    Arbitrator.

    20. Mr. Kar submitted that the scope for interference by this Court was

    limited, and strictly guided by the ratio laid down by the Hon’ble Apex

    Court. The award did not demonstrate that it suffered from either perversity

    or patent illegality. The learned Arbitrator had considered all aspects of the

    matter, the provisions of the law, the provisions of the contract, the effect of

    the judgment of the Supreme Court in Manohar Lal Sharma 1 and 2

    (supra) and had given his view, upon interpretation of the statutory

    provisions of the 2015 Act, the Contract Act and the covenants in the
    13

    contract. This Court cannot re-appreciate the evidence led by the parties.

    The arguments put forward by the Corporation did not indicate that the

    Corporation had alleged that substantive provisions of law had either been

    violated or ignored or transgressed or disregarded by the learned Arbitrator.

    21. In the light of the restricted jurisdiction of this court, Mr. Kar

    submitted that the arbitrator’s autonomy to decide the dispute should be

    respected and this court should adopt a hands-off approach. The award was

    a speaking one. It elaborately dealt with the contentions of the parties. The

    evidence was weighed and some of the claims were allowed by the learned

    Arbitrator, being supported by reasons. The learned Arbitrator opined that

    the Parliament had consciously conferred some remedies to third parties by

    treating the contract to be valid and keeping the contract alive for adoption

    and/or for enforcement. Otherwise, the third party who had entered into the

    contract for extraction of coal with the prior allottees would be rendered

    remediless for no fault of their own. Referring to the various paragraphs of

    the award, Mr. Kar submitted that the claimant was undoubtedly a third

    party who had entered into the contract with the prior allottees in respect of

    coal mining operations.

    22. Trans Damodar Coal Mines was one of such coal mines which figured

    both in Schedule 1 and Schedule 2 of the Act. The Parliament had enacted

    the 2015 Act for the purpose of implementing a void contract by use of non-

    obstante clauses in some of the sections of the 2015 Act. Special emphasis

    was laid on the non-obstante clause at the beginning of Section 11 of the

    2015 Act. The learned Arbitrator rightly held that although the contract may
    14

    be void, but the claimant was protected under Section 11(2) and other

    provisions of the 2015 Act would be attracted in respect of the rights of the

    third party/contractor. The claims allowed by the learned Arbitrator were

    based on the principle of restitution. Reference was made to Section 65 and

    70 of the Indian Contract Act. The contract had come to an end, and as

    such, the claimant had been deprived of the benefits arising out of the

    contract as also of the money receivable under the contract. The learned

    Arbitrator correctly held that the dispute would not be covered by Section 27

    of the 2015 Act.

    23. Under such situation, the Arbitrator allowed refund of only the

    amounts which were unjustly deducted by the Corporation, upon holding

    that the Corporation was not entitled to deduct the same contractually.

    Reference was made to the decision of Allahabad Bank and Ors. vs

    Bengal Paper Mills Co. reported in (2004) 8 SCC 236. It was further urged

    that the learned Arbitrator disallowed the claim for damages suffered by the

    claimant by holding that, the facts and circumstances leading to the

    cancellation of the contract would not amount to breach on the part of the

    Corporation.

    24. Mr. Kar explained the reasons behind allowing each of the claims.

    With regard to claim (a), the learned Arbitrator held that that additional levy

    has been wrongly appropriated by the Corporation, as such levy would not

    fall under the category of statutory levy. The deduction of the additional levy

    from the dues of the claimant was contrary to the contractual terms. The

    legislation had fixed the liability to pay compensation for illegal coal mining
    15

    described as additional levy, only upon the prior allottee under the 2015

    Act. The legislature was aware that there were existing contracts of the prior

    allottee with third parties and others, in respect of such mining activities,

    yet the legislature consciously did not make any provision under the 2015

    Act by which, the liability of additional levy would be proportionately borne

    by the prior allottee and the third party contractor. Moreover, the concept of

    additional levy which was brought in by the statute was never contemplated

    under the contract.

    25. Thus, the direction for refund was rightly given by the learned

    Arbitrator. The deduction of the additional levy which was deposited with

    the Union of India, from the dues of the claimant was found to be contrary

    to the terms of the contract. The additional levy provided for in the statute

    under Section 22 of the 2015 Act, was not equivalent to royalty, cess, excise

    duty and any other statutory levy that was contemplated under Annexure C-

    1 of the contract.

    26. Claim (b) was allowed on the ground that the penalty was wrongfully

    imposed for the shortfall in the production for the financial year 2013-14.

    The refund was directed on the principle of restitution. The learned

    Arbitrator rightly held that the claimant could not be faulted on account of

    the shortfall, as the Corporation had itself asked the claimant to stop coal

    production.

    27. Claim (c) was based on the refund of the amount wrongfully deducted

    as penalty for alleged loss of coal, during transportation of coal from the

    mines to Durgapur Freight Terminal and then to the Railway Siding. The
    16

    learned Arbitrator held that, from the evidence on record and the admission

    of the witness of the Corporation in his cross-examination, it would appear

    that the procedure of measurement of the loss in transit as stated in the

    tripartite agreement, had not been followed and consequently the claimant

    should have got the benefit of 0.5 % loss, as per the agreement. The

    imposition of penalty was found to be illegal.

    28. Claims (d) and (e) were allowed towards dues on account of mining

    charges. The claims were allowed on the ground that the Corporation did

    not adduce any evidence disputing the calculation of the claimant. The case

    of the claimant was that, in violation of the marketing agreement the

    Corporation sold several consignments of coal to DPL and WBPDCL on

    credit, without receiving the full advance from them. The Corporation had

    also acted beyond the terms of the contract by opening a separate bank

    account and by not depositing the proceeds in the escrow agreement.

    29. Claim (g) was for refund on account of land advance. The claimant

    had advanced a sum of Rs.43,68,22,071/- for acquiring land for mining

    purpose, which was to be adjusted or be repaid over 30 years of commercial

    production. The commercial production commenced from the financial year

    2012-13, but due to the order of the Hon’ble Supreme Court, mining

    activities were required to be stopped from the midnight of 31st March,

    2015. The Corporation stopped mining activities by a letter dated February

    26, 2015. Till March 31, 2015 a sum of Rs.1,10,55,072 was refunded by way

    of adjustment. A sum of Rs.42,57,66,999 remained outstanding. A further

    sum of Rs.2,15,85,016 was paid to the claimant upon receiving the sum as
    17

    compensation from the Ministry of Coal. By a letter dated March 22, 2017,

    the Corporation informed the claimant that after all adjustments and

    payments, a sum of Rs.35,25,48,835 remained refundable. A further

    payment of Rs.1,69,33,157 was also made. Hence the claim.

    30. The claim was allowed on the admission of parties as to the payment

    and adjustment. The Corporation failed to produce any document to show

    that they had paid any amount over and above the amount of

    Rs.3,85,18,173. Thus the admitted case between the parties was that the

    land advance of Rs.43,68,22,071 was refundable to the claimant.

    31. Claim (m) was in respect of the claimant’s share of the escrow

    account. The claim was allowed on admission. Claim (n) was in respect of

    the claimant’s share in the fixed deposit lying with the State Bank of India.

    The learned Arbitrator allowed the claim on the ground that the claimant

    could not have any liability for the expenditure of any legal proceedings

    incurred by the respondent as the claimant was not a party to the

    proceeding. The Corporation had initially admitted the claim in the escrow

    account and there was no reason why the claimant would be deprived of the

    interest accrued thereon. There was no specific clause in the agreement

    which debarred payment of interest. Absence of such clause indicated the

    right to the interest as a matter of course. Thus, Mr. Kar submitted that the

    learned Arbitrator rightly directed the bank to liquidate the fixed deposits in

    respect of the escrow account in the ratio of 76.43% and 23.57%. The claim

    was allowed on the basis of the admitted case between the parties and
    18

    interpretation of the contract. The Arbitrator also allowed the pre-award and

    post-award interest, apart from cost.

    32. Thus, Mr. Kar submitted that, upon considering the award and its

    reasoning and rationality as well as the law laid down by the Hon’ble

    Supreme Court in various decisions, the award was not liable to be set aside

    in exercise of power conferred under Section 34 of the A & C Act.

    33. Before deciding the issues involved, in the application, a brief

    narration of the background is necessary. The claimant is a company

    incorporated under the Companies Act 1956, inter alia, engaged in the

    business of mining and agglomeration of coal. The Corporation is also a

    company fully controlled by the Government of West Bengal and was, inter

    alia, established to explore and extract various minerals from the mines in

    West Bengal.

    34. Allocation of the Trans Damodar Sector coal block of the Raniganj

    Coalfields, was made in favour of the Corporation by the Ministry of Coal,

    Government of India by a letter dated January 14, 2005, subject to

    conditions stated therein. One of such condition was that the Corporation

    would carry out coal mining in accordance with the provisions of the Coal

    Mines (Nationalization) Act, 1973.

    35. The Corporation published an expression of interest in respect of the

    coal mining activities and eventually a consortium was formed consisting of

    Godavari Commodities Limited, Banwarilal Agarwalla Private Limited and

    Calcutta Industrial Supply Corporation. The consortium was recommended

    by the committee constituted by the Government of West Bengal. The
    19

    Corporation entered into a contract on May 31, 2006 with the members of

    the consortium, by appointing them as contractors for coal mining and for

    the discharge of all other obligations to give effect to the coal mining in the

    Trans Damodar Zone. The Corporation also entered into a Marketing, Selling

    and Delivery of Coal Agreements with the consortium and the Corporation

    agreed to appoint a contractor. The contractor agreed to accept such

    appointments to perform and fulfil the agreements as indicated therein. The

    Corporation executed an agenda/clarification/modification to the contract

    agreement dated March 31, 2010 to make certain additions, alterations and

    modification and inserted certain clarifications in the contract agreement for

    smooth operation of excavation of coal and to fulfill the terms and conditions

    and covenants contained therein. The Corporation and the claimant entered

    and executed addendum/ clarification/ modification to the Marketing,

    Selling and Delivery of Coal Agreement dated May 31, 2006. On August 3,

    2011, the Corporation and the Claimant entered into an Escrow Agreement

    recording the terms and conditions under which the State Bank of India

    agreed to be an Escrow agent. The Corporation, the claimants and Palogix

    Infrastructure Pvt. Limited, (Freight Terminal Operator (FTD)), entered into a

    tripartite agreement wherein the FTO agreed to give in hire/rent the

    Durgapur Freight Terminal, inter alia, to provide security, supervision,

    stocking operation and Coordination services in terms of the agreement. On

    August 25, 2014 (Manohar Lal Sharma 1) and September 24, 2014

    (Manohar Lal Sharma 2) were delivered by the Hon’ble Supreme Court,

    cancelling the allotments of coal blocks including Trans Damodar Section.
    20

    However, the Hon’ble Supreme Court held that the allotments should be

    kept alive till March 31, 2016 to avoid public inconvenience. The relevant

    portions of Manoharlal Sharma (1) are quoted below :-

    “163. To sum up, the entire allocation of coal block as per
    recommendations made by the Screening Committee from 14-7-
    1993 in 36 meetings and the allocation through the Government
    Dispensation Route suffers from the vice of arbitrariness and legal
    flaws. The Screening Committee has never been consistent; it has
    not been transparent; there is no proper application of mind; it
    has acted on no material in many cases; relevant factors have
    seldom been its guiding factors; there was no transparency and
    guidelines have seldom guided it. On many occasions, guidelines
    have been honoured more in their breach. There was no objective
    criteria, nay, no criteria for evaluation of comparative merits. The
    approach had been ad hoc and casual. There was no fair and
    transparent procedure, all resulting in unfair distribution of the
    national wealth. Common good and public interest have, thus,
    suffered heavily. Hence, the allocation of coal blocks based on the
    recommendations made in all the 36 meetings of the Screening
    Committee is illegal.

    164. The allocation of coal blocks through Government
    Dispensation Route, however laudable the object may be, also is
    illegal since it is impermissible as per the scheme of the CMN Act.
    No State Government or public sector undertakings of the State
    Governments are eligible for mining coal for commercial use.
    Since allocation of coal is permissible only to those categories
    under Sections 3(3) and (4), the joint venture arrangement with
    ineligible firms is also impermissible. Equally, there is also no
    question of any consortium/leader/association in allocation. Only
    an undertaking satisfying the eligibility criteria referred to in
    Section 3(3) of the CMN Act viz. which has a unit engaged in the
    production of iron and steel and generation of power, washing of
    coal obtained from mine or production of cement, is entitled to the
    allocation in addition to the Central Government, a Central
    Government company or a Central Government corporation.

    165. In this context, it is worthwhile to note that the 1957 Act
    has been amended introducing Section 11-A w.e.f. 13-2-2012. As
    per the said amendment, the grant of reconnaissance permit or
    prospecting licence or mining lease in respect of an area
    containing coal or lignite can be made only through selection
    through auction by competitive bidding even among the eligible
    entities under Section 3(3)(a)(iii), referred to above. However, the
    government companies, government corporations or companies or
    corporations, which have been awarded power projects on the
    basis of competitive bids for tariff (including Ultra Mega Power
    21

    Projects) have been exempted of allocation in favour of them is not
    meant to be through the competitive bidding process.

    166. As we have already found that the allocations made, both
    under the Screening Committee Route and the Government
    Dispensation Route, are arbitrary and illegal, what should be the
    consequences, is the issue which remains to be tackled. We are of
    the view that, to this limited extent, the matter requires further
    hearing.

    167. By way of footnote, it may be clarified and we do, that no
    challenge was laid before us in respect of blocks where
    competitive bidding was held for the lowest tariff for power for
    Ultra Mega Power Projects (UMPPs). As a matter of fact, Mr
    Prashant Bhushan, learned counsel for Common Cause
    submitted that since allocation for UMPPs is in accord with the
    opinion given in Natural Resources Allocation, In re [Natural
    Resources Allocation, In re, Special Reference No. 1 of 2012, (2012)
    10 SCC 1] and the benefit of the coal block is passed on to the
    public, the said allocations may not be cancelled. However, he
    submitted that in some cases the Government has allowed
    diversion of coal from UMPP to other end uses i.e. for commercial
    exploitation. Having regard to this, it is directed that the coal
    blocks allocated for UMPP would only be used for UMPP and no
    diversion of coal for commercial exploitation would be permitted.”

    36. The Hon’ble Supreme Court, upon realizing that the consequence of

    cancellation of the coal block allocations was of superior importance, kept

    the matter pending for further hearing, on this limited issue. Upon further

    hearing, the Supreme Court by its decision Manohar Lal Sharma (2) dated

    September 24, 2014, held that the consequence was intended to correct the

    wrong done by the Union of India. The proceedings were held with the

    intention to compensate the exchequer for the wrongs done by the Union of

    India, in the manner suggested by the Learned Attorney General. The

    Supreme Court proposed to publish the said suggestions. The Supreme

    Court noted that there were two categories of coal block allotments. The first

    category being allotments other than those mentioned in Annexure 1 and 2.

    The second category being allotments mentioned in Annexure 1 and 2 that
    22

    could possibly be based on cancellation on the terms and conditions as

    submitted by the Learned Attorney General. The Supreme Court held that

    follows: –

    “33. The learned Attorney General identified 46 coal blocks that
    could be “saved” from the guillotine, since all of them have
    commenced production or are on the verge of commencing
    production. As these allocations are also illegal and arbitrary they
    are also liable to be cancelled. However, the allotment of three
    coal blocks in Annexure 1 is not disturbed and they are Moher
    and Moher Amroli Extension allocated to Sasan Power Ltd.
    (UMPP) and Tasra [allotted to Steel Authority of India Ltd. (SAIL),
    a Central Government public sector undertaking not having any
    joint venture].

    34. As far as the 6 coal blocks mentioned in Annexure 2 are
    concerned, the allottees have not yet commenced production.

    They do not stand on a different or better footing as far the
    consequences are concerned. These allotments are also liable to
    be cancelled. The allocation of Pakri Barwadih coal block [allotted
    to National Thermal Power Corporation (NTPC), being a Central
    Government public sector undertaking not having any joint
    venture] is not liable to be cancelled.

    35. Except the above two allocations made to the UMPP and the
    two allocations made to the Central Government public sector
    undertaking not having any joint venture mentioned above, all
    other allocations mentioned in Annexure 1 and Annexure 2 are
    cancelled.

    36. It was submitted by the learned Attorney General that on the
    cancellation of the coal block allotments, CIL would require some
    breathing time to manage its affairs. The Central Government is
    keen to move ahead but some time would be required to manage
    the emerging situation. Similarly, breathing time is also required
    to be given to the allottees to manage their affairs on the
    cancellation of the coal blocks.

    37. In view of the submissions made, although we have quashed
    the allotment of 42 out of these 46 coal blocks, we make it clear
    that the cancellation will take effect only after six months from
    today, which is with effect from 31-3-2015. This period of six
    months is being given since the learned Attorney General
    submitted that the Central Government and CIL would need
    some time to adjust to the changed situation and move forward.
    This period will also give adequate time to the coal block allottees
    to adjust and manage their affairs. That CIL is inefficient and
    incapable of accepting the challenge, as submitted by the learned
    23

    counsel, is not an issue at all. The Central Government is
    confident, as submitted by the learned Attorney General, that CIL
    can fill the void and take things forward.

    38. In addition to the request for deferment of cancellation, we
    also accept the submission of the learned Attorney General that
    the allottees of the coal blocks other than those covered by the
    judgment and the four coal blocks covered by this order must pay
    an amount of Rs 295 per metric tonne of coal extracted as an
    additional levy. This compensatory amount is based on the
    assessment made by CAG. It may well be that the cost of
    extraction of coal from an underground mine has not been taken
    into consideration by CAG, but in matters of this nature it is
    difficult to arrive at any mathematically acceptable figure
    quantifying the loss sustained. The estimated loss of Rs 295 per
    metric tonne of coal is, therefore, accepted for the purposes of
    these cases. The compensatory payment on this basis should be
    made within a period of three months and in any case on or
    before 31-12-2014. The coal extracted hereafter till 31-3-2015
    will also attract the additional levy of Rs 295 per metric tonne.

    39. In view submissions made, although we have quashed the
    allotment of 42 out of these 46 coal blocks, we make it clear that
    the cancellation will take effect only after six months from today,
    which is with effect from 31st March, 2015. This period of six
    months is being given since the learned Attorney General
    submitted that the Central Government and CIL would need some
    time to adjust to the changed situation and move forward. This
    period will also give adequate time to the coal block allottees to
    adjust and manage their affairs. That the CIL is inefficient and
    incapable of accepting the challenge, as submitted by learned
    counsel, is not an issue at all. The Central government is confident,
    as submitted by the learned Attorney General, that the CIL can fill
    the void and take things forward.

    40. In addition to the request for deferment of cancellation, we
    also accept the submission of the learned Attorney General that
    the allottees of the coal blocks other than those covered by the
    judgement and the four coal blocks covered by this order must pay
    an amount of Rs. 295/- per metric ton of coal extracted as an
    additional levy. This compensatory amount is based on the
    assessment made by the CAG. It may well be that the cost of
    extraction of coal from an underground mine has not been taken
    into consideration by the CAG, but in matters of this nature it is
    difficult to arrive at any mathematically acceptable figure
    quantifying the loss sustained. The estimated loss of Rs. 295/- per
    metric ton of coal is, therefore, accepted for the purposes of these
    cases. The compensatory payment on this basis should be made
    within a period of three months and in any case on or before 31 st
    24

    December, 2014. The coal extracted hereafter till 31st March, 2015
    will also attract the additional levy of Rs. 295/- per metric ton.

    41. It is made clear that the scrutiny by the CBI in respect of the
    allotment of 12 coal blocks out of 46 identified by the learned
    Attorney General (and for that matter against any other allottee)
    will continue and be taken to its logical conclusion. Needless to
    say, the observations and findings in this order shall no bearing
    on the pending investigations.”

    37. After the decision of the Supreme Court, the Parliament enacted the

    2015 Act on March 30, 2015. The Preamble of the Act is quoted below: –

    An Act to provide for allocation of coal mines and vesting of the right,
    title and interest in and over the land and mine infrastructure
    together with mining leases to successful bidders and allottees with a
    view to ensure continuity in coal mining operations and production of
    coal, and for promoting optimum utilisation of coal resources
    consistent with the requirement of the country in national interest
    and for matters connected therewith or incidental thereto.

    Whereas the Supreme Court vide judgment dated 25th August, 2014
    read with its order dated 24th September, 2014 has cancelled the
    allocation of coal blocks and issued directions with regard to such
    coal blocks and the Central Government in pursuance of the said
    directions has to take immediate action to implement the said order;

    And whereas it is expedient in public interest for the Central
    Government to take immediate action to allocate coal mines to
    successful bidders and allottees keeping in view the energy security of
    the country and to minimise any impact on core sectors such as steel,
    cement and power utilities, which are vital for the development of the
    nation;

    And whereas Parliament is competent to legislate under Entry 54 of
    List I of the Seventh Schedule to the Constitution for regulation of
    mines and mineral development to the extent to which such
    regulation and development under the control of Union is declared by
    Parliament by law to be expedient in the public interest.

    Be it enacted by Parliament in the Sixty-sixth Year of the Republic of
    India as follows.”

    38. On cessation of the mining activities pursuant to the above decision of

    the Supreme Court and consequent to passing of 2015 Act, various disputes

    arose between the parties resulting in the present arbitral proceeding. The
    25

    claimant filed its statement of claim (SOC). The Corporation denied the

    claims by filing a statement of defence (SOD).

    39. Particulars of the claim are quoted below :-

            Sl. No.           Particulars of Claim            Amounts in Rs.
    
             a.       Refund of the amounts wrongly           54,91,79,927.00
                      appropriated     on     account    of
                      Additional Levy as pleaded in
                      paragraph 40 of the SOC.
             b.       Refund of the amounts wrongly           9,39,06.983.00
                      imposed as penalty for the alleged
                      shortfall in production in FY 2013-
                      14, as pleaded in paragraph 66 of
                      the SOC.
             c.       Refund of penalty wrongly deducted      1,67,92,183.00
                      on account of alleged loss of
                      transportation of coal from mines to
                      the railway siding, as pleaded in
                      paragraph 74 of the SOC.
             d.       Dues on account of Mining Charges       7,51,48,652.00
                      and commission on the direct sales
                      by respondent to West Bengal Power
                      Development Corporation Ltd., as
                      pleaded in paragraph 89 of the SOC.
             e.       Dues on account of Mining Charges       4,73,45,333.00
                      and commission on the direct sales
                      by respondent to Durgapur Projects
                      Ltd., as pleaded in paragraph 89 of
                      the SOC.
             f.       Interest @ 13.50% p.a. on the total     29,97,88,215.00
                      outstanding      dues       of    Rs.
                      78,23,73,080.00 (a + b +c +d +e
                      above)     from     01.04.2015     to
                      31.01.2018)
             g.       Refund on account of land advance,      38,72,48,826.00
                      as pleaded in paragraph 83 of the
                      SOC.
             h.       Interest @ 13.50% p.a. on the refund    14,83,85,262.00
                      of land advance amount for the
                      period 01.04.2015 to 31.01.2018
             i.       Claim on account of loss in mine        15,11,59,609.00
                      development      as     pleaded    in
                      paragraph 103 of the SOC.
             j.       Claim on account of loss in             19,02,63,274.00
                      investments in Fixed assets, as
                      pleaded in paragraph 109 of the
                      SOC.
                                              26
    
    
              k.        Interest   @    13.50%   on   mine     13,08,25,765.00
                        development and investment in
                        Fixed    assets   for  the   period
                        01.04.2015 to 31.01.2018
              l.        Claim on account of claimant's             8,16,784
                        share of credit balance in Escrow
                        account with State Bank of India as
                        on 12.03.2017, as pleaded in
                        paragraph 91 of the SOC.
              m.        Claim on account of claimant's          6,00,00,000.00
                        share in Fixed Deposit with State
                        Bank of India, as pleaded in
                        paragraph 95 of the SOC.
              o.        Total                                 3,47,59,52,376.00
    
    
    
    
    

    40. The specific contention of the learned Advocate General, apart from

    the factual denial of the case was that, in view of the decisions of the

    Supreme Court on August 25, 2014 and September 24, 2014, thereby

    cancelling the allocation of coal mines including the Trans Damodar Coal

    Mine, the claims were not tenable in law. Claims for damages, compensation

    and interest against the Corporation, pursuant to the contract which had

    been cancelled and declared void ab initio, were not enforceable.

    41. The Director of the claimant as the principal officer, filed two sets of

    Affidavit of Evidence before the learned Arbitrator. The former Managing

    Director and the then Advisor and Director of the Corporation filed Affidavit

    of Evidence, on behalf of the Corporation. The witnesses were examined by

    the learned Advocates for the respective parties. Upon appreciating the

    background of the case, the learned Arbitrator framed the followings points

    for decision:-

    “1. Whether in view of the decision of the Supreme Court in the
    case of Manohar Lal Sharma vs Principal Secretary and Ors.
    (supra), followed by the subsequent enactment of 2015 Act by the
    27

    Parliament, the various claims made by the claimant in the SOC
    as quoted above were maintainable in law.

    1) If the answer to the above point was answered in the
    affirmative, whether the claimant is entitled to reliefs under
    different heads claimed in the SOC.”

    42. The allotment of the coal mine was cancelled by the Supreme Court as

    the allotment had been held to be contrary to the provisions of the Coal

    Mines (Nationalization) Act, 1973 (CMN Act). Consequently, the learned

    Arbitrator held that on account of cancellation of the coal mine allocation,

    the contract for mining had become void. The subject matter of the contract

    was illegal, for violating the CMN Act.

    43. There is no dispute that, in terms of the contract between the parties,

    the Corporation, in whose favour mining allotment was made by the Central

    Government, in its turn, entrusted the claimant with the duties of mining on

    the terms and conditions mentioned in the subject contract between the

    parties. There is also no dispute that the Supreme Court, in the

    abovementioned decision, had categorically held that the allotment of

    mining right by the Central Government in favour of the Corporation was

    against the provisions of the CNM Act and consequently, quashed the

    allotment. Hence, if the allotment in favour of the Corporation was against

    the provisions of the CMN Act, it necessarily followed that the contract

    between the Corporation and the claimant for coal mining, was also void

    because such right of mining, which was the subject-matter of the contract,

    was violative of CMN Act. The learned Arbitrator rightly held that contract

    between the parties was void.

    28

    44. This Court now proceeds to consider how the learned Arbitrator dealt

    with the disputes. Before the learned Arbitrator, the contention of the

    learned senior advocate for the claimant was that, the parties did not

    contemplate what would happen in future and had entered with an

    agreement considering the mining to be a valid one and not in conflict with

    the CMN Act. None of the parties could foresee that the enforcement of the

    mining rights in favour of the Corporation with regard to the Trans-Damodar

    sector would become illegal, pursuant to a decision of the Supreme Court.

    The decision of the Supreme Court would not stand in the way of the

    claimant to enforce the contract. The position would be different if the

    parties had knowingly entered into an illegal contract. Such argument was

    not accepted by the learned Arbitrator. The Arbitrator held that the law was

    well settled that, once the Supreme Court declared something as illegal,

    upon an interpretation of any provision of law, it should be presumed that

    such thing was illegal from the very beginning, unless the Supreme Court

    specifically held that its decision would be prospective. Reference was made

    to the decision of M.A. Murthi vs State of Karnataka and Ors. reported in

    AIR 2003 SC 3821, The decision of the Supreme Court, enunciating a

    principle of law would be applicable to all cases, irrespective of its stage of

    pendency, because it would be assumed that what was enunciated by the

    Supreme Court was in fact the law from its inception. The doctrine of

    prospective overruling was an exception to the normal principle of law. It

    was a device innovated to avoid reopening of settled issues, to prevent

    multiplicity of proceedings, and to avoid uncertainty and avoidable litigation.
    29

    In other words, actions taken contrary to the law prior to the date of

    declaration were validated in larger public interest. In this case, the doctrine

    of prospective overruling could not be applied. By following the decision of

    the Hon’ble Supreme Court, the learned Arbitrator held that the agreement

    between the parties was void from the very beginning. Allotment of coal mine

    for the purpose of mining, which was granted in favour of the Corporation,

    was contrary to the provisions of CMN Act.

    45. The learned Arbitrator held that the claimant was a third party who

    had entered into a contract with the Corporation, that is, the prior allottee,

    in respect of coal mining operation within the meaning of 2015 Act. He held

    that, as per the decision of the Supreme Court, the contract was void and

    such contract was in violation of Section 23 of the Contract Act. The parties

    were remediless for the purpose of enforcing the terms of such void contract,

    and could not be compensated for any breach. The prior allottee and the

    third party with whom the contract had been made by the prior allottee,

    were equally remediless as the contract was prohibited by law. Thus, the

    prayers of the claimant towards compensation for future loss of profit,

    interest on delayed payment of dues etc. were not allowed. It was observed

    as follows :-

    “24. The above decision of the Supreme Court was in connection with
    a contract which became void being hit by Section 23 of the Contract
    Act, like the present one, and the State was restrained from realizing
    its dues after the 26th January, 1950 when the contract became void
    although the Respondent therein enjoyed the monopoly right by
    plying its buses till 30th November, 1951 and earned income.

    25. Thus, even by taking aid of Section 65 of the Contract Act, a
    party to a contract cannot compel the other party to a contract which
    is void for being violative of Section 23 of the Act to return the benefit
    received under the void contract as a beneficiary thereof. This
    30

    Tribunal, thus, finds that the contention of Mr. Mitra that the
    contract is not void as both the parties bona fide entered into the
    contract by treating the same as a valid one is not tenable in the eye
    of law. In the above decision of The State of Rajasthan, the contract
    was entered into at a point of time when the Constitution was not in
    force and consequently, it was a valid one; even in such a fact, the
    Supreme Court restrained the Appellant from realizing its dues the
    moment the contract became invalid.

    The other contention of Mr. Mitra that the Supreme Court, in the
    facts of the present case, did not go into the question as to the
    validity of the contract between the Claimant and the Respondent is
    equally inconsequential. The moment the Supreme Court declared
    the allotment in favour of the Respondent by the Central Government
    as illegal and violative of CMN Act, any contract between the
    Respondent and the Claimant for implementing the illegal allotment
    of right of mining is bound to be in violation of CMN Act. Thus, a
    party to void contract in violation of Section 23 of the Act is
    remediless if he wants to get back money that he has spent in aid of
    such contract.”

    46. The above finding was in consonance with the contentions of the

    learned Advocate General. However, it was held that, in spite of the above

    position of law, the Parliament, which was presumed to be aware of all the

    existing laws of the land as well as all the judgments of the Supreme Court

    interpreting such laws, enacted the 2015 Act for the purpose of

    implementing the void contract at least to a limited extent, by deviating from

    the Contract Act by use of non-obstante clauses in some of the Sections of

    the 2015 Act. This interpretation of the 2015 Act, by the learned Arbitrator,

    was a consequence of the second contention to the learned senior Advocate

    of the claimant.

    47. The Arbitrator rightly held that, if the contract was void, any party

    who may have taken advantage under such a void contract, should refund

    the advantage or compensate to the person from whom such advantage was
    31

    received, under the provision of Contract Act. The principle emanates from

    Section 65 of the Contract Act which is quoted below:-

    “65. Obligation of person who has received advantage under
    void agreement, or contract that becomes void.–
    When an agreement is discovered to be void, or when a contract
    becomes void, any person who has received any advantage under
    such agreement or contract is bound to restore it, or to make
    compensation for it to the person from whom he received it.”

    48. Section 65 embodies the principles of restitution and prevention of

    unjust enrichment. This is a case where the contact was held to be void by

    the learned Arbitrator. Undoubtedly, there was an agreement between the

    parties. The agreement became void on account of the decision of the

    Supreme Court. The Arbitrator found that certain advantages were received

    by the Corporation and those advantages must be either restored or

    compensated. The decision of the learned Arbitrator was made on the

    principle of equity, that no one should unjustly enrich himself at another’s

    expense. The principle of restitution would not be applicable if the

    agreement was void ab initio, and the parties knowingly entered into the

    illegal or void contract.

    49. Thus, the Arbitrator proposed to consider some of the Sections of the

    2015 Act, namely :-

    “11. Discharge or adoption of third party contracts with prior
    allottees.–(1) Notwithstanding anything contained in any other
    law for the time being in force, a successful bidder or allottee, as
    the case may be, in respect of Schedule I coal mines, may elect,
    to adopt and continue such contracts which may be existing with
    any of the prior allottees in relation to coal mining operations and
    the same shall constitute a novation for the residual term or
    residual performance of such contract: Provided that in such an
    event, the successful bidder or allottee or the prior allottee shall
    32

    notify the nominated authority to include the vesting of any
    contracts adopted by the successful bidder. (2) In the event that a
    successful bidder or allottee elects not to adopt or continue with
    existing contracts which had been entered into by the prior
    allottees with third parties, in that case all such contracts which
    have not been adopted or continued shall cease to be enforceable
    against the successful bidder or allottee in relation to the
    Schedule I coal mine and the remedy of such contracting parties
    shall be against the prior allottees.

    12. Provisions in relation to secured creditors.–(1) The
    secured creditors of the prior allottees which had any security
    interest in any part of the land or mine infrastructure of a
    Schedule I coal mine shall be entitled to– (a) continue with such
    facility agreements and security interest with the prior allottee if
    such prior allottee is a successful bidder or allottee; and (b) in the
    event that the prior allottee is not a successful bidder or allottee,
    then the security interest of such secured creditor shall only be
    satisfied out of the compensation payable to such prior allottee,
    to the extent determined in accordance with such rules as may
    be prescribed and the outstanding debt shall be recoverable from
    the prior allottee. (2) The Central Government shall, taking into
    consideration the provisions contained in section 9, prescribe the
    manner in which the secured creditor shall be paid out of the
    compensation in respect of any prior allottee.

    13. Void alienations and permitted security interests.–Any
    and all alienations of land and mine infrastructure and creation
    of any encumbrances of whatsoever nature thereon which relate
    to Schedule I coal mines, made by any prior allottee after the
    25th day of August, 2014 shall be void, save and except any
    registered security interest and charge over the land and mine
    infrastructure as registered by a bank or a financial institution or
    any other secured lender.

    14. Liabilities of prior allottees.–(1) Notwithstanding anything
    contained in any other law for the time being in force, no
    proceedings, orders of attachment, distress, receivership,
    execution or the like, suits for the recovery of money,
    enforcement of a security or guarantee (except as otherwise
    provided for under this Act), prior to the date of commencement
    of this Act shall lie, or be proceeded further with and no remedies
    shall be available against the successful bidder, or allottee, as the
    case may be, or against the land and mine infrastructure in
    respect of Schedule I coal mines. (2) The proceedings as referred
    to in sub-section (1), shall continue as a personal remedy against
    the prior allottee but shall not be maintainable or continued
    against the land or mine infrastructure of Schedule I coal mine or
    the successful bidder or allottee, pursuant to this Act. (3) Every
    liability of any prior allottee in relation to a Schedule I coal mine
    in respect of any period prior to the vesting order or allotment
    33

    order, shall be the liability of such prior allottee and shall be
    enforceable against it and not against the successful bidder or
    allottee or the Central Government. (4) All unsecured loans shall
    continue to remain the liability of the prior allottee. (5) The
    additional levy imposed against the prior allottees of Schedule II
    coal mines shall continue to remain the liability of such prior
    allottees and such additional levy shall be collected by the
    Central Government in such manner as may be prescribed. (6)
    For the removal of doubts, it is hereby declared that– (a) no
    claim for wages, bonus, royalty, rate, rent, taxes, provident fund,
    pension, gratuity or any other dues in relation to a Schedule I
    coal mine in respect of any period prior to the date of vesting
    order or allotment order, as the case may be, shall be enforceable
    against the Central Government or the successful bidder or the
    allottee, as the case may be; (b) no award, decree, attachment or
    order of any court, tribunal or other authority in relation to any
    Schedule I coal mine passed prior to the date of commencement
    of this Act, in relation to the land and mine infrastructure of
    Schedule I coal mines, shall be enforceable against the Central
    Government or the successful bidder or the allottee, as the case
    may be; (c) no liability for the contravention of any provision of
    law for the time being in force, relating to any act or omission
    prior to the date of vesting order or allotment order, as the case
    may be, shall be enforceable against the successful bidder or
    allottee or the Central Government.

    15. Commissioner of payments to be appointed and his
    powers.–(1) For the purposes of disbursing the amounts payable
    to the prior allottees of Schedule I coal mines, the Central
    Government shall appoint an officer not below the rank of Joint
    Secretary to the Government of India, to be the Commissioner of
    payments. (2) The Central Government may appoint such other
    officers and staff as it may think fit to assist the Commissioner
    and thereupon the Commissioner may authorise one or more of
    such officers also to exercise all or any of the powers exercisable
    by him under this Act. (3) Any officer authorised by the
    Commissioner to exercise any powers may exercise those powers
    in the same manner and with the same effect as if they have been
    conferred on him directly by this Act and not by way of
    authorisation. (4) The salaries and allowances and other terms
    and conditions of service of the Commissioner and other officers
    and staff appointed under this section shall be such as may be
    prescribed. (5) The Central Government shall, within a period of
    thirty days from such date as may be notified, pay to the
    Commissioner for payment to the prior allottee, an amount equal
    to the compensation determined by the nominated authority. (6)
    Separate records shall be maintained by the Commissioner in
    respect of each Schedule I coal mine in relation to which
    payments have been made to him under this Act.

    34

    27. Dispute settlement and Bar of Jurisdiction of civil
    courts.–(1) Any dispute arising out of any action of the Central
    Government, nominated authority or Commissioner of payment
    or designated custodian, or any dispute between the successful
    bidder or allottee and prior allottee arising out of any issue
    connected with the Act shall be adjudicated by the Tribunal
    constituted under the Coal Bearing Areas (Acquisition and
    Development) Act, 1957
    (20 of 1957).

    (2) Where the Central Government is of the opinion that any
    dispute arising out of any issue connected with the Act exists or
    is apprehended and the dispute should be adjudicated by the
    Tribunal referred to in sub-section (1), then, the Central
    Government may by order in writing, refer the dispute or any
    matter appearing to be connected with, or relevant to, the
    dispute, to the Tribunal for adjudication. (3) The Tribunal
    referred to in sub-section (1) shall, after hearing the parties to the
    dispute, make an award in writing within a period of ninety days
    from the institution or reference of the dispute. (4) On and from
    the commencement of the Act, no court or other authority, except
    the Supreme Court and a High Court, shall have, or be entitled to
    exercise, any jurisdiction, powers or authority, in relation to
    matters connected with the Act.”

    50. The Arbitrator held that, Section 11(1) had given liberty to the

    successful bidder or allottee in relation to the coal blocks/sectors in

    Schedule I (Trans Damodar), to adopt or continue any contract between the

    prior allottee and the third party in relation to the coal mining operation,

    which was a void agreement. If such agreement was adopted by the

    successful bidder or the allottee, the same should constitute novation of

    such contract for the residual term or performance of such residual part of

    the contract although the original contract was void. The above novation

    would, however, be on condition that the successful bidder or allottee or the

    prior allottee should notify the nominated authority to include the vesting of

    any contract adopted by the successful bidder or allottee. Section 11(2), on

    the other hand, spoke of a situation where a successful bidder or the allottee

    elected not to adopt or continue with existing contracts which had been
    35

    entered into by the prior allottees with third parties, which was the position

    of the claimant in this case. According to sub-section (2), in that event, all

    such contracts which had not been adopted or continued would cease to be

    enforceable against the successful bidder or allottee in relation to the

    Schedule I coal mines and the remedy of such contracting parties, that is

    the claimant in this case, would be against the prior allottee, i.e., the

    Corporation. The learned Arbitrator held as follows :-

    “29………….

    According to sub-section (2), in that event, all such contracts
    which have not been adopted or continued shall cease to be
    enforceable against the successful bidder or allottee in relation to
    the Schedule I coal mine and the remedy of such contracting
    parties, the Claimant in this case, shall be against the prior
    allottees. Thus, in the present case, the Parliament knowing full
    well that the third party by virtue of such void contract is
    remediless against the prior allottee under the existing law of the
    land, has consciously conferred such remedy under its contract
    with the prior allottee, which is otherwise void, by treating the
    same as if it is a valid contract because of the non-obstante
    clause at the beginning of Section 11 to the extent indicated in
    the 2015 Act.”

    51. The learned Advocate General urged that, the above finding of the

    learned Arbitrator was not supported by the provisions of Section 11. The

    2015 Act did not protect the third party/claimant. The learned Arbitrator

    took note of the provisions of Section 11(2) and the fact that Section 11

    began with a non obstante clause i.e., “notwithstanding anything contained

    in any other law for the time being is force” and held that, even if a contract

    was found to be void under Section 23 of the Contract Act, in the event the

    successful bidder or the allottee elected not to adopt the existing contract

    entered between the prior allottee (Corporation) and the third party
    36

    (claimant), in such cases all the contracts in relation to Schedule 1, had

    been kept alive and the remedy of such contracting party/claimant would be

    against the prior allottee (corporation).

    52. Thereafter, the learned Arbitrator proceeded to consider Section 12 of

    the 2015 Act. Section 12 had been incorporated for the benefit of the

    secured creditors of the prior allottees who, but for this provision, would

    have suffered because of the fact that their contract with the prior allottee

    would also be void, as one of the purpose behind such contract would be in

    aid of implementing a void contract. Under sub-(1) of Section 12, in the

    event the prior allottee was not a successful bidder or allottee, even then,

    the security interest of such secured creditor would be satisfied out of the

    compensation payable to such prior allottee, to the extent determined in

    accordance with such rules as may be prescribed and the outstanding debt

    would be recoverable from the prior allottee. Sub-section (2) of Section 12 on

    the other hand, vested the Central Government with the power to prescribe

    the manner in which the secured creditors would be paid out of the

    compensation money payable to prior allottees after taking into

    consideration the provisions of Section 9 of the 2015 Act. Thus, it was

    observed by the learned Arbitrator that, the Parliament incorporated Section

    12 in the 2015 Act, notwithstanding the fact that under a void contract,

    even the secured creditors were remediless.

    53. It was further observed by the learned Arbitrator that, Section 13 had

    been inserted for the protection of the Banks or financial institutions or any

    other secured lender in respect of alienation of land and mine infrastructure
    37

    or creation of encumbrances which are related to Schedule I coal mines,

    made by the prior allottee in respect of any registered security interest and

    charge over the land and mine infrastructure, as registered by a bank or a

    financial institution or any other secured lender which was not otherwise

    possible in connection with a void contract, but for the protection given

    under the said Section. By enacting Section 14 of the 2015 Act, the

    Parliament had protected the Central Government, the successful bidder

    and the subsequent allottees in respect of proceedings, orders of

    attachment, distress, receivership, execution or like, suits for recovery of

    money, enforcement of security or guarantee prior to the date of

    commencement of the 2015 Act in respect of Schedule I coalmines, by

    providing that those would continue only against prior allottee as their

    personal liability. At the same time, the additional levy in respect of

    Schedule II coalmines, imposed under the 2015 Act would continue to

    remain the liability of the prior allottee and would be collected by the

    Central Government in such manner as may be prescribed by Rules. By the

    enactment of Section 27, the Parliament had created a new forum for

    adjudication of disputes by excluding the jurisdiction of the Civil Court, in

    respect of any dispute arising out of any action of the Central Government,

    Nominated Authority or Commissioner of payment or designated custodian,

    or any dispute between the successful bidder or allottee and prior allottee

    arising out of any issue connected with the 2015 Act, for adjudication by the

    Tribunal constituted under the Coal Bearing Areas (Acquisition and

    Development) Act, 1957.

    38

    54. Thus, the above sections of 2015 Act were elaborately discussed by

    the learned Arbitrator. It was held that the 2015 Act, was enacted with the

    object to give protections to the Central Government, allottees, successful

    bidders, Banks and financial institutions and other secured creditors

    referred to therein and also the third parties who had contracted with the

    prior allottee in respect mining of the coal mines referred to in Schedule I

    and Schedule II of the 2015 Act, from the rigours of a void contract by

    shifting the liability to the prior allottees under the various contracts as

    their personal liability. It was held that the 2015 Act, was enacted primarily

    to give remedy to those remediless parties, except the prior allottees before

    different fora, by treating the liabilities under the contract as personal

    liability of the prior allottee subject to the restriction, if any, imposed by the

    2015 Act.

    55. The learned Arbitrator held that, so far as a third party, like the

    present claimant who had contracted with the prior allottee for

    implementation of the mining contract was concerned, its remedy was not

    covered under Section 27 of 2015 Act. The language used in sub-section (1)

    of Section 27 justifies such finding. Such claim should be made either before

    the Civil Court or before the Arbitral Tribunal, if there was any such

    agreement between the parties to the extent indicated in the 2015 Act. The

    contention of the learned Advocate General with regard to the alternative

    remedy under Section 27 of the 2015 Act was rightly negated by considering

    the provisions of Section 27 of 2015 Act. Paragraph 30 of the Award is

    quoted below:-

    39

    “30. Thus, the above Sections of the 2015 Act are enacted with
    the object to give protections to the Central Government,
    allottes, successful bidders, Banks and financial institutions
    and other secured creditors referred to therein and also the
    third parties who have contracted with the prior allottee in
    respect mining contract of coal mines referred to in Schedule I
    and Schedule II of the Act from the rigour of a void contract
    entered into by the Central Government and the prior allottees
    by shifting the liability to the prior allottees under the various
    contracts as their personal liability. The above facts clearly
    indicate that the Parliament was quite conscious of the position
    of law that if a contract is void by reason of violation of Section
    23
    of the Contract Act, the parties to it and also the parties to
    any other contracts in aid of or for implementation of such void
    contract are remediless and consequently, has enacted the 2015
    Act primarily to give remedy to those remediless parties except
    the prior allottees before different forums by treating the
    liabilities under the contract as personal liability of the prior
    allottee subject to the restriction, if any, imposed by the 2015
    Act. So far as the third parties like the present claimant who
    had contracted with the prior allottes for implementation of the
    mining contract are concerned, their remedy is not covered
    under Section 27 of 2015 Act as it appears from the language
    used in sub-section (1) of Section 27, and thus, to be enforced
    either before the civil court or before Arbitral Tribunal, if there is
    any such agreement between the parties to the extent indicated
    in the 2015 Act. Thus, this Tribunal does not find substance in
    the contention of the learned Advocate for the Respondent that
    the present disputes are also covered under Section 27 of the
    Act.

    The Respondent in this proceeding has given a short note of
    submission on the present aspect of the matter regarding the
    scope of remedy of the contracting parties with the prior
    allottees and the same is quoted below:

    “Various provisions of the Coal Mine (Special Provisions) Act,
    2015 has only protected the right, title and interest of the
    successful bidder / allottee. However only Section 11 (2) of the
    said Act has specified that in the event a successful bidder or
    allottee elects not to adopt or continue with existing contract
    which had been entered into by the prior allottee with third
    parties, in that case all such contracts which have not been
    adopted or continued shall cease to be enforceable against the
    successful bidder or allottee in relation to Schedule-I Coal Mine
    and the remedy of such contracting parties shall be against the
    prior allottee.

    In the present case, the respondent is the prior allottee and
    claimant is the contracting party. The term “remedy” and its
    40

    procedure for recovery has been defined in Section 14 of the
    said Act. Sub-Section 1, Section 14 specify that-
    notwithstanding anything contents in any other Law for the
    time being in force, no proceeding, order of attachment,
    distress, receivership, execution or the like suits for recovery for
    money, enforcement of a security or guarantee (except as
    otherwise provided for under this act) prior to the date of
    commencement of this act shall lie or be proceeded further with
    and no remedies shall be available against the successful
    bidder, or allottee, as the case may be, or against the land and
    mines infrastructure in respect of Schedule – I Coal Mine.
    Sub-Section 2 of Section 14 specify that- the proceeding as
    referred to in Sub-Section 1 shall continue against the prior
    allottee but shall not be maintainable or continued against the
    land or mines infrastructure of Schedule – I Coal Mine or the
    successful bidder of allottee, pursuant to this Act.
    According to Section 14(3) of the Coal Mine (Special Provision)
    Act, 2015 every liability of any prior allottee in relation to a
    Schedule I Coal Mine in respect of any period prior to the
    vesting order or allotment order shall be the liability of such
    prior allottee and shall be enforceable against it and not against
    successful bidder or allottee or the Central Government. In the
    present case the liability of the prior allottee being respondent
    herein prior to the vesting order is only restricted to the land
    advance given by the claimant in favour of the respondent
    around Rs. 33.50 crores. Therefore the claim of the claimant
    against the respondent can be sustained / enforceable with
    regard to the land advance only, which the respondent has
    admitted in its SOD. So far as the other claims are concern all
    are related to sharing of amount out of an illegal allotment of
    coal block and interpretation of various clauses of the illegal
    agreement and enforcement thereof which can not be done
    according to the Indian Contract Act.

    Therefore, in order to maintain a proceeding by the contracting
    party in terms of Section 11(2) of the Coal Mine (Special
    Provision) Act, 2015 there must be a proceeding against the
    prior allottee by the contracting party on the day of
    commencement of the Act. Whereas in the present case, the
    instant dispute has been raised at the end of 2017. Therefore,
    the claimant has no right / remedy against the respondent
    according to the Coal Mine (Special Provision) Act, 2015.
    The remedy of the claimant against the respondent, if any, the
    same is the contractual and is covered under the Indian
    Contract Act
    . Needless to mention here that various
    agreement/contracts executed between the parties were the
    subsequent events of an illegal allotment of Coal Block by the
    Ministry of Coal in favour of the respondent. Therefore, any
    agreement that was executed for implementing the illegal
    41

    allocation of Coal Block is also illegal and cannot be enforceable
    by any of the parties.

    As a consequence of the illegal allocation of Coal Block, the
    claimant as well as the respondent both have been benefited.
    The claimant received much more benefits than the respondent
    which would be evident from the detail breakup of the sale
    proceeds of coal which has been distributed between the
    parties.”

    (Emphasis supplied)
    In the opinion of this Tribunal, the above interpretation of the
    provisions of the 2015 Act is wholly misconceived for the
    following reasons:

    First, the submission that “Various provisions of the Coal Mine
    (Special Provisions) Act, 2015 has only protected the right, title
    and interest of the successful bidder / allottee” is totally without
    basis. On the other hand, this Tribunal has already pointed out
    that except the interest of prior allottees, the interests of the
    other stake holders involved in the mining business pursuant to
    illegal allotment have been protected as will appear from a mere
    reading of the provisions of 2015 Act. In the very second
    sentence of the written submission, the Respondent has
    admitted that if a case is covered by Section 11(2) of the 2015
    Act, the remedy of the contracting party is only against the prior
    allottee. There is no dispute that the Respondent is a prior
    allottee and the Claimant is a contracting party with the prior
    allottee and that the present disputes are within the ambit of
    Section 11(2) of the 2015 Act as the successful bidder or the
    allottee has not agreed to adopt the contract between the
    Claimant and the Respondent.

    Secondly the submission of the Respondent that “The term
    “remedy” and its procedure for recovery has been defined in
    Section 14 of the said Act.” is an absurd contention inasmuch
    as, there is no definition of “remedy” given in the entire 2015
    Act although some other terms are defined in Section 3(1) of the
    above Act. Moreover, Section 14(1) of the 2015 Act does not
    protect the interest of the prior allottee in any way but it
    protects the interest of the successful bidders or allottees or
    against the land and mine infrastructure in respect of Schedule
    1 coal mines. The present proceeding against the prior allottee
    is, therefore, outside the scope of Section 14(1). It is a wrong
    submission of the Respondent that the claim of land advance
    against the Respondent by the Claimant falls within Section
    14(1)
    but is really covered under the scope of Section 11(2) of
    the Act. Lastly, it is equally preposterous to submit that “in
    order to maintain a proceeding by the contracting party in terms
    of Section 11(2) of the Coal Mine (Special Provision) Act, 2015
    there must be a proceeding against the prior allottee by the
    contracting party on the day of commencement of the Act”

    42

    because in that event the object of giving remedy to the
    contracting third party against a prior allottee under Section
    11(2)
    of the Act would be totally frustrated as would appear
    from the language used in Section 11(2) which is quoted below:
    (2) In the event that a successful bidder or allottee elects not to
    adopt or continue with existing contracts which had been
    entered into by the prior allottees with third parties, in that case
    all such contracts which have not been adopted or continued
    shall cease to be enforceable against the successful bidder or
    allottee in relation to the Schedule I coal mine and the remedy
    of such contracting parties shall be against the prior allottees.

    (Emphasis supplied).

    If the intention of the Parliament was to give remedy only to
    pending proceeding on the date of commencement of the 2015
    Act as contented by the Respondent, in that event, the
    Parliament would not have used future tense in the sub-section
    (2) of Section 11 by using the phrase “in the event a successful
    bidders or allottes elects” or the word shall”.

    Thus, this Tribunal does not find substance in the contention of
    the learned Advocate for the Respondent raised in the written
    notes.”

    56. The claimant was neither the successful bidder nor an allottee or prior

    allottee. The dispute between the parties arose out of a contract entered

    between the parties, prior to the promulgation of 2015 Act, which was a void

    contract.

    57. Learned Advocate General submitted that, the provisions of 2015 Act,

    had only protected the right, title and interest of the successful

    bidder/allottee. Such contention is not correct. Section 11(2) of the 2015 Act

    provided that, in the event a successful bidder or allottee elected not to

    adopt or continue with the existing contract which had been entered into

    between the prior allottee, i.e., (Corporation) and a third party (claimant), all

    such contracts which had been adopted or continued would cease to be

    enforceable against the successful bidder or allottee in relation to Schedule-I
    43

    coal mines and the remedy of such contracting party (claimant) shall be

    against the prior allottee (Corporation).

    58. Section 14(2) provided that, the proceeding as referred in sub-section

    (1) shall continue against the prior allottee, but shall not be maintainable or

    continued against the land or mines infrastructure of Schedule -I Coal Mine

    or the successful bidder or allottee, pursuant to the 2015 Act. Section 14(3)

    of the 2015 Act, provided that every liability of any prior allottee in relation

    to a Schedule I coal mine in respect of any period prior to the vesting order

    or allotment order shall be the liability of such prior allottee and shall be

    enforceable against it and not against a successful bidder. Thus, the learned

    Arbitrator opined that, in the present case Section 14(3) must apply and the

    claim of the claimant against the respondent could be sustained/enforced

    with regard to the land advance, which the respondent had admitted in its

    statement of defence.

    59. The contention of the learned Advocate General that the provisions of

    2015, Act had only protected the right, title and interest of the successful

    bidder/allottee, was dealt with by the learned Arbitrator. The Arbitrator held

    that, except for the interest of the prior allottee, the interest of all other

    stake holders involved in the mining business had been protected by the

    2015 Act. The learned Arbitrator held that Section 14 of 2015 Act, did not

    protect the interest of the prior allottee in any way. It protected the interest

    of the successful bidder/allottee in respect of the land and mine

    infrastructure in under Schedule I coal mines. The proceeding against the

    prior allottee was therefore outside the scope of Section 14(1). The
    44

    submission of the Corporation that the claim of land advance by the

    claimant fell within the Section 14(1) was negated. The learned Arbitrator

    held that the claim was really covered under Section 11(2) of the 2015 Act.

    The further contention of the Corporation that, in order to maintain a

    proceeding by the contracting party in terms of Section 11(2) of the 2015

    Act, pendency of a proceeding against the prior allottee by the contracting

    party on the date of commencement of the Act was not mandatory, was

    rightly rejected by the learned Arbitrator. It was held that the object of giving

    remedy to the contracting third party against a prior allottee under Section

    11(2) of the Act would be totally frustrated if such contention was accepted.

    The learned Arbitrator held that, if the intention of the Parliament was to

    provide a remedy only to proceedings pending on the date of commencement

    of the 2015 Act, as contented by the Corporation, in that event the

    Parliament would not have used the phrase, “the remedy of such contracting

    parties shall be against the prior allottees” in Section 11(2) of the 2015 Act.

    60. The legislature left it open to the third party (claimant) to proceed

    against the Corporation (prior allottee) for claims arising out of the contract,

    in the event the successful bidder or the allottee, did not adopt the contract.

    The Parliament had consciously used a future tense in sub-section 11(2) by

    using the phrase “in the event that the successful bidder or allottee elects

    not to adopt or continue with the existing contracts”. Thus, the intention of

    the legislature was rightly interpreted by the learned Arbitrator to hold that,

    if the successful bidder or the allottee did not adopt the existing contract

    entered into between the claimant and the Corporation in that event, the
    45

    contract would not be enforceable against the successful bidder or the

    allottee, but the remedy of such contracting party (claimant) shall be against

    the prior allottee i.e., the Corporation.

    61. The views expressed by the learned Arbitrator were plausible views.

    The findings are not patently illegal. The interpretations of law are not found

    to be wholly misconceived. Moreover, the preamble to the 2015 Act provides

    that the Act was also promulgated to deal with matters incidental to and

    connected with allocation of coal mines and vesting of right title and interest

    of successful bidders and allottees pursuant to the decision of the Hon’ble

    Supreme Court. Reference is made to the following decisions in support of

    the contention that an award should not be set aside if the views of the

    Arbitrator are possible views.

    62. In Hindusthan Construction Company Limited vs National

    Highways Authority of India reported in (2024) 2 SCC 613, the Hon’ble

    Supreme Court held that, even if a second view is possible, the court should

    accept the view of the arbitrator as a possible view. The relevant portions of

    the said judgment are quoted below :-

    “26. The prevailing view about the standard of scrutiny — not judicial
    review, of an award, by persons of the disputants’ choice being that
    of their decisions to stand — and not interfered with, (save a small
    area where it is established that such a view is premised on patent
    illegality or their interpretation of the facts or terms, perverse, as to
    qualify for interference, courts have to necessarily choose the path
    of least interference, except when absolutely necessary). By training,
    inclination and experience, Judges tend to adopt a corrective lens;
    usually, commended for appellate review. However, that lens is
    unavailable when exercising jurisdiction under Section 34 of the Act.
    Courts cannot, through process of primary contract interpretation,
    thus, create pathways to the kind of review which is forbidden under
    Section 34. So viewed, the Division Bench’s approach, of appellate
    46

    review, twice removed, so to say (under Section 37), and conclusions
    drawn by it, resulted in displacing the majority view of the tribunal,
    and in many cases, the unanimous view, of other tribunals, and
    substitution of another view. As long as the view adopted by the
    majority was plausible — and this Court finds no reason to hold
    otherwise (because concededly the work was completed and the
    finished embankment was made of composite, compacted matter,
    comprising both soil and fly ash), such a substitution was
    impermissible.

    27. For a long time, it is the settled jurisprudence of the courts in the
    country that awards which contain reasons, especially when they
    interpret contractual terms, ought not to be interfered with, lightly.
    The proposition was placed in State of U.P. v. Allied
    Constructions [State of U.P.
    v. Allied Constructions, (2003) 7 SCC 396]
    : (SCC p. 398, para 4)
    “4. … It was within his jurisdiction to interpret Clause 47 of the
    Agreement having regard to the fact-situation obtaining therein. It is
    submitted that an award made by an arbitrator may be wrong either
    on law or on fact and error of law on the face of it could not nullify an
    award. The award is a speaking one. The arbitrator has assigned
    sufficient and cogent reasons in support thereof.
    Interpretation of a
    contract, it is trite, is a matter for the arbitrator to determine
    (see Sudarsan Trading Co. v. State of Kerala [Sudarsan Trading
    Co. v. State of Kerala, (1989) 2 SCC 38] ). Section 30 of the
    Arbitration Act, 1940 providing for setting aside an award is
    restrictive in its operation. Unless one or the other condition
    contained in Section 30 is satisfied, an award cannot be set aside.
    The arbitrator is a Judge chosen by the parties and his decision is
    final. The Court is precluded from reappraising the evidence. Even in
    a case where the award contains reasons, the interference therewith
    would still be not available within the jurisdiction of the Court
    unless, of course, the reasons are totally perverse or the judgment is
    based on a wrong proposition of law.”

    28. This enunciation has been endorsed in several cases
    (Ref. McDermott International Inc. v. Burn Standard Co.
    Ltd. [McDermott International Inc.
    v. Burn Standard Co. Ltd., (2006) 11
    SCC 181] ).
    In MSK Projects (I) (JV) Ltd. v. State of Rajasthan [MSK
    Projects (I) (JV) Ltd. v. State of Rajasthan, (2011) 10 SCC 573 : (2012)
    3 SCC (Civ) 818] it was held that an error in interpretation of a
    contract by an arbitrator is “an error within his jurisdiction”. The
    position was spelt out even more clearly in Associate
    Builders [Associate Builders v. DDA
    , (2015) 3 SCC 49 : (2015) 2 SCC
    (Civ) 204] , where the Court said that : (Associate Builders
    case [Associate Builders v. DDA, (2015) 3 SCC 49 : (2015) 2 SCC (Civ)
    204] , SCC p. 81, para 42)
    47

    “42. … 42.3. … if an arbitrator construes a term of the contract in a
    reasonable manner, it will not mean that the award can be set aside
    on this ground. Construction of the terms of a contract is primarily
    for an arbitrator to decide unless the arbitrator construes the
    contract in such a way that it could be said to be something that no
    fair-minded or reasonable person could do.”

    63. The Court, under Section 34 of the A & C Act cannot correct the

    award, because it is not a court of appeal. In Consolidated Construction

    Consortium Limited vs Software Technology Parks of India reported in

    2025 INSC 574, the same legal principles were reiterated. The following

    portions are quoted below :-

    “23. Scope of Section 34 of the 1996 Act is now well crystallized
    by a plethora of judgments of this Court. Section 34 is not in
    the nature of an appellate provision. It provides for setting aside
    an arbitral award that too only on very limited grounds i.e. as
    those contained in sub-sections (2) and (2A) of Section 34. It is
    the only remedy for setting aside an arbitral award. An arbitral
    award is not liable to be interfered with only on the ground that
    the award is illegal or is erroneous in law which would require
    re-appraisal of the evidence adduced before the arbitral
    tribunal. If two views are possible, there is no scope for the
    court to re-appraise the evidence and to take the view other
    than the one taken by the arbitrator. The view taken by the
    arbitral tribunal is ordinarily to be accepted and allowed to
    prevail. Thus, the scope of interference in arbitral matters is
    only confined to the extent envisaged under Section 34 of the
    Act. The court exercising powers under Section 34 has perforce
    to limit its jurisdiction within the four corners of Section 34. It
    cannot travel beyond Section 34. Thus, proceedings under
    Section 34 are summary in nature and not like a full-fledged
    civil suit or a civil appeal. The award as such cannot be touched
    unless it is contrary to the substantive provisions of law or
    Section 34 of the 1996 Act or the terms of the agreement.

    24. Therefore, the role of the court under Section 34 of the 1996
    Act is clearly demarcated. It is a restrictive jurisdiction and has
    to be invoked in a conservative manner. The reason is that
    arbitral autonomy must be respected and judicial interference
    should remain minimal otherwise it will defeat the very object of
    the 1996 Act.

    48

    25. Keeping the above in view, let us now deal with the order of
    the learned Single Judge dated 02.01.2019 passed under
    Section 34 of the 1996 Act.

    26. In the aforesaid order, learned Single Judge noted that the
    contract work was required to be executed within a period of 10
    months. Appellant could not complete the work within the
    contract period due to land slides and rains. Ultimately,
    appellant could complete the work on 30.11.2007 by seeking
    extension of time which was granted by the respondent. There is
    no complaint about the construction. Learned Single Judge also
    noted that there were rains and land slides during the contract
    period which is not in dispute. Thereafter, learned Single Judge
    observed as under:

    If the building had been erected and there were
    landslides, it would affect the building constructed and
    there would not only have been loss of money, but also
    loss of lives and that the 1st respondent should thank
    the stars that no untoward event took place.

    27. Learned Single Judge also observed that clause 26 of the
    contract agreement could not be read in isolation without
    reference to clause 27. The fact that appellant was allowed to
    carry on the contract work and to subsequently complete the
    same cannot be denied. Once there is extension of time, there
    cannot be a narrow interpretation to clause 26. Purpose of
    extension of time was only for completion of work. Extension of
    time and levy of liquidated damages cannot go hand in hand.

    Contention of the respondent would have been acceptable had
    there been no extension in time or the work remained
    incomplete even after the extended period. In such an event,
    respondent would have been justified to levy and recover
    liquidated damages. Once the appellant had completed the work
    during the extended period of time, claim of liquidated damages
    by the respondent could not be accepted. Therefore, the arbitral
    award dated 10.05.2010 was set aside.

    28. We are afraid learned Single Judge had clearly gone beyond
    the grounds provided in Section 34 of the 1996 Act to set aside
    the arbitral award. Learned Single Judge exceeded the
    jurisdiction under Section 34 of the 1996 Act. There was no
    justification for setting aside the arbitral award by taking a
    different view. View taken by the arbitral tribunal is certainly a
    possible and plausible view. A different interpretation of clause
    26 other than the one taken by the arbitral tribunal is possible
    but that will not bring the challenge to the arbitral award within
    the four corners of Section 34. In any view of the matter, mere
    setting aside of the arbitral award did not confer any benefit to
    the appellant. In the circumstances, the Division Bench was
    49

    justified in reversing the order of the learned Single Judge
    under Section 37 of the 1996 Act.”

    64. Before this court, the learned Advocate General placed reliance on the

    report of the select committee of The Coal Mines (Special provisions) Bill,

    2015 in order to lay emphasis on the purpose behind the Bill, and the

    relevant portion is quoted below:-

    “1.6 The Coal Mines (Special Provisions) Bill, 2015 provides for
    allocation of coal mines and vesting of the right, title and interest
    in and over the land and mining infrastructure together with
    mining leases to successful bidders and allottees through a
    transparent bidding process with a view to ensure continuity in
    coal mining operations and production of coal, and for promoting
    optimum utilization of coal resources consistent with the
    requirement of the country in national interest.

    Further, the Bill, having regard to the coordinated and scientific
    development and utilization of coal resources consistent with the
    growing requirement of the country, prescribed the conditions to
    rationalise the coal sector for mining operations, consumption and
    sale.”

    65. The learned Advocate General referred to the paragraph Nos. 2, 2.1,

    2.3, 2.6, 2.8, 4.8, 4.6, 4.13.1, 4.19, of the report to substantiate that the

    learned Arbitrator had wrongly imported the provisions of the 2015 Act in

    order to allow some of the claims of the third party, although the protection

    under the 2015 Act was given only to the successful bidder or allottee, and

    the Act was promulgated in public interest and to enable the Central

    Government to take immediate action to allocate coal mines to successful

    bidders and allottees, keeping in view the energy security of the country and

    to minimize any impact on core sectors such as steel, cement and power
    50

    utilities which were vital for the development of the nation. The need was to

    protect public interest and ensure the supply of energy to the core sectors.

    66. In Manohar Lal Sharma (2), the Hon’ble Apex Court held as follows:-

    “1. On 25-8-2014 [Manohar Lal Sharma v. Principal Secy., (2014)
    9 SCC 516] the judgment was delivered in these cases and it was
    held, inter alia, that the allotment of coal blocks made by the
    Screening Committee of the Government of India, as also the
    allotments made through the Government Dispensation Route
    are arbitrary and illegal. Since the conclusion arrived at would
    have potentially had far-reaching consequences, on which
    submissions were not made when the case was heard, the
    question of what should be the consequences of the declaration
    was left open for hearing.

    2. The relevant paragraphs of the judgment dated 25-8-2014
    [Manohar Lal Sharma v. Principal Secy., (2014) 9 SCC 516] read
    as follows: (Manohar Lal Sharma case [Manohar Lal
    Sharma v. Principal Secy.
    , (2014) 9 SCC 516] , SCC p. 613, paras
    164-166)
    “164. The allocation of coal blocks through Government
    Dispensation Route, however laudable the object may be, also is
    illegal since it is impermissible as per the scheme of the CMN Act.
    No State Government or public sector undertakings of the State
    Governments are eligible for mining coal for commercial use.
    Since allocation of coal is permissible only to those categories
    under Sections 3(3) and (4), the joint venture arrangement with
    ineligible firms is also impermissible. Equally, there is also no
    question of any consortium/leader/association in allocation.
    Only an undertaking satisfying the eligibility criteria referred to in
    Section 3(3) of the CMN Act viz. which has a unit engaged in the
    production of iron and steel and generation of power, washing of
    coal obtained from mine or production of cement, is entitled to
    the allocation in addition to Central Government, a Central
    Government company or a Central Government corporation.

    165. In this context, it is worthwhile to note that the 1957 Act
    has been amended introducing Section 11-A w.e.f. 13-2-2012. As
    per the said amendment, the grant of reconnaissance permit or
    prospecting licence or mining lease in respect of an area
    containing coal or lignite can be made only through selection
    through auction by competitive bidding even among the eligible
    entities under Section 3(3)(a)(iii), referred to above. However, the
    government companies, government corporations or companies
    or corporations, which have been awarded power projects on the
    basis of competitive bids for tariff (including Ultra Mega Power
    51

    Projects) have been exempted of allocation in favour of them is
    not meant to be through the competitive bidding process.

    166. As we have already found that the allocations made, both
    under the Screening Committee Route and the Government
    Dispensation Route, are arbitrary and illegal, what should be the
    consequences, is the issue which remains to be tackled. We are of
    the view that, to this limited extent, the matter requires further
    hearing.”

    ***
    ***

    5. Therefore, the affidavit is quite clear that 40 coal blocks are
    already producing coal and 6 coal blocks are in a position to
    produce coal virtually with immediate effect. The question is
    whether the allotment of these coal blocks should be cancelled or
    not.

    6. It was submitted by the learned Attorney General that after the
    declaration of law and the conclusion that the allotment of coal
    blocks was arbitrary and illegal, only two consequences flow from
    the judgment [Manohar Lal Sharma v. Principal Secy., (2014) 9
    SCC 516] . The first is the natural consequence, that is, the
    allotment of the coal blocks (other than those mentioned in the
    judgment) should be cancelled and the Central Government is
    fully prepared to take things forward. The second option is that
    46 coal blocks (as above) be left undisturbed (subject to
    conditions) and the allotment of the remaining coal blocks should
    be cancelled.

    7. Expounding on the alternative consequence, it was submitted
    that Coal India Limited (CIL), a public sector undertaking, can
    take over and continue the extraction of coal from these 44 coal
    blocks without adversely affecting the rights of those employed
    therein. However, it was submitted that CIL would require some
    time to take over the coal blocks and manage its affairs for
    continuing the mining process. Effectively therefore, it was
    submitted that even if the allotment of these 44 coal blocks is
    cancelled, the Central Government can ensure that coal
    production will not stop.

    8. The learned Attorney General submitted that all the allottees of
    coal blocks should be directed to pay an additional levy of Rs 295
    per metric tonne of coal extracted from the date of extraction as
    per the Report of the Comptroller and Auditor General (CAG)
    dealing with the financial loss caused to the exchequer by the
    illegal and arbitrary allotments. It was further submitted that in
    the case of allottees supplying coal to the power sector, they
    should be mandated to enter into power purchase agreements
    (PPAs) with the State utility or distribution company (as the case
    may be) so that the benefit is passed on to the consumers.
    ***
    52

    ***

    10. To put the suggestions of the learned Attorney General in
    perspective, they are summarised below:

    10.1. All coal block allotments (except those mentioned in the
    judgment) may be cancelled.

    10.2. Alternatively,

    (a) extraction of coal from the 40 functional and 6 “ready” coal
    blocks may be permitted and the remaining coal blocks be
    cancelled;

    (b) the allottees of all 46 coal blocks be directed to pay an
    additional levy of Rs 295 per metric tonne of coal extracted from
    the date of extraction; and

    (c) the allottees of coal blocks for the power sector be also directed
    to enter into PPAs with the State utility or distribution company
    as the case may be.

    ***
    ***

    13. The consequences of cancellation of the coal blocks were
    categorised by Mr Venugopal under various heads and these are
    detailed below:

    13.1. It was submitted that government companies are not in a
    position to supply the required quantity of coal; in fact, a large
    number of applications are pending with the Ministry of Coal for
    long-term coal linkages; power stations have a supply of less than
    one week of coal and therefore there are possibilities of power
    outages; as many as 10 power plants of National Thermal Power
    Corporation (NTPC) and Damodar Valley Corporation (DVC) have
    been shut down because of shortage of coal supply by Coal India
    Ltd. (CIL); there is an issue of poor quality of coal supplied by
    CIL; huge investments up to about Rs 2.87 lakh crores have been
    made in 157 coal blocks as on December 2012; investments in
    end-use plants have been made to the extent of about Rs 4 lakh
    crores; the employment of almost 10 lakh people is at stake; end-

    use plants have been designed keeping in mind the specification
    of coal in the allocated coal block and cancellation of the coal
    blocks would result in the end-use plant becoming redundant;
    loans to the extent of about Rs 2.5 lakh crores given by banks
    and financial institutions would become non-performing assets;
    State Bank of India may suffer a loss of up to Rs 78,263 crores
    which is almost 7.9% of its net worth for the financial year 2013;
    other public sector banks such as Punjab National Bank and
    Union Bank will receive a massive setback; public sector
    corporations like Rural Electricity Corporation and Power Finance
    Corporation have an even higher exposure than banks; there will
    be global ramifications of the de-allotments such as a negative
    impact on investor’s confidence; acute distress in some
    53

    industries; the country’s dependence on coal as a primary fuel
    source with up to 60% for power generation may result in
    inflationary trends; 28,000 MW of power capacity will be affected
    due to de-allocation; closure of coal mines would result in an
    estimated loss of Rs 4.4 lakh crores in terms of loss of royalty,
    cess, direct and indirect taxes; coal imports (already very high)
    will go up even more in FY 2016-2017 to the extent of Rs 1.44
    lakh crores (without de-allocation); and on the other hand, the
    production of coal would substantially increase in case all coal
    blocks are made operational after the grant of necessary
    permission.

    13.2. It was submitted that the auction of coal blocks would take
    at least 1-2 years and from past experience, it is unlikely that the
    auction would be successful due to lack of bids or proper
    participation; it would take at least 5-6 years for making the
    auctioned coal blocks operational; in any event (based on the
    timelines given by the Ministry of Coal in the allocation letters) it
    would take 36-42 months to develop an open cast mine and
    about 48-54 months to develop an underground mine; and the
    commissioning of end-use plants after obtaining various
    clearances would take a minimum of 3-4 years.

    13.3. It was submitted on a positive note that the allottees have
    invested in basic infrastructure like road, rail links, etc. since the
    coal blocks allotted to them were in areas where CIL was not
    interested in making an investment; the allottees have made huge
    investments in setting up other infrastructure such as schools,
    hospitals, facilities for clean and potable water, residential
    colonies, community centres, playground, etc. and in creation of
    job opportunities; thousands of crores of rupees have already
    been paid by the coal block allottees by way of direct and indirect
    taxes and in the form of royalty, cess, etc.; and if the coal blocks
    are cancelled, the development activities initiated by the allottees
    would come to a standstill.

    13.4. It was submitted that the delay in development of coal
    blocks is not attributable to the allottees who are actually victims
    of the faults of the Screening Committee; delays are attributable
    to various reasons such as administrative delays on the part of
    the Ministry of Environment and Forests and the Ministry of
    Coal, the consent by the Pollution Control Boards was not given
    on time, Court orders, Naxalite issues in some areas, the State
    Governments directing that mining lease should not be executed,
    introduction of go/no-go areas or without statutory permission,
    etc.; this Court has tacitly acknowledged administrative delays in
    grant of clearances in an order passed on 1-9-2014 in Samaj
    Parivartana Samudaya v. State of Karnataka
    [(2014) 9 SCC 630] ;
    the appropriate course of action to adopt would be for this Court
    54

    to appoint a committee to examine the peculiar facts of each
    individual allotment.

    13.5. The figure of loss of revenue to the exchequer to the extent
    of Rs 295 per metric tonne of coal extracted is borrowed from the
    Report of CAG which Report is contested by the Government of
    India and is pending consideration before a Parliamentary
    Committee on Public Undertakings; the Report itself suggested
    that only a part of the financial gain could have accrued to the
    national exchequer; the Government of India has not applied its
    mind while suggesting the figure of Rs 295 per metric tonne and
    it has only considered the average price of coal as given by CIL for
    the year 2010-2011 (being Rs 1028 per metric tonne) and that
    cannot be adopted for earlier financial years; the coal extracted
    from the blocks allotted are of an inferior quality and the sale
    price thereof is much lower than the average sale price of CIL;
    CAG has not taken into consideration underground mines while
    calculating the alleged financial loss; the cost of production of
    coal for CIL is less since CIL has economically viable mines as
    compared to the mines allocated to the private sector which lack
    infrastructure and have several other problems; and penalty
    cannot be imposed with retrospective effect since the coal
    extracted by the allottees has already been utilised for production
    of power, steel, cement, etc.

    67. The Hon’ble Supreme Court held that the conclusion arrived at

    Manohar Lal Sharma (1) had far reaching consequences and the question

    as to what should be the consequence of the declaration made in Manohar

    Lal Sharma (1) would be decided later. Thus, it is obvious that the second

    judgment in Manohar Lal Sharma (2) was confined to the consequences of

    the cancellation of the coal block and most of the suggestions of the

    Attorney General were accepted, including the suggestion that the allottees

    of the coal block must pay a sum of amount of Rs. 295 per metric ton of coal

    extracted as an additional levy which was a compensatory amount to be

    paid by the prior allottee on the assessment by the CAG.

    68. The learned Arbitrator also interpreted that, the 2015 Act provided the

    consequences of the decision of the Hon’ble Supreme Court. He rightly held
    55

    that the Act was promulgated to deal with the far-reaching consequences of

    the cancellation of the allocation of coal blocks and was correct in holding

    that the non-obstante clauses in Sections 11, and 14 were intentionally

    used by the Parliament to somewhat protect other stakeholders and third

    party contractors.

    69. The Arbitrator thereafter considered each of the claims on the

    principles discussed hereinabove. With regard to the claim no. (a), i.e. the

    amount wrongly appropriated on account of additional levy as pleaded in

    paragraph 40 of the SOC, the learned Arbitrator held that the additional levy

    was imposed by the Supreme Court on the prior allottee, which was

    subsequently incorporated in the 2015 Act as an additional levy. The 2015

    Act clearly stipulated that the responsibility for payment of additional levy

    would be on the prior allottee. After September 24, 2014, for sale of coal till

    March 31, 2015, the Corporation had recovered proportionate additional

    levy on the quantity of coal sold from the end use customer. The very

    conduct of the Corporation made it clear that the additional levy had to be

    borne either by the Corporation or by the end use customer, from whom the

    Corporation was entitled to recover the additional levy. Even in terms of the

    contract, the Corporation was not entitled to raise a claim on account of the

    additional levy. The learned Arbitrator elaborately discussed the SOC and

    the SOD on this issue and also the documents submitted by the parties with

    regard to the demand for additional levy. The Corporation relied on the

    Annexure C of the agreement dated May 31, 2006 and Annexure C 1 of the

    amended agreement dated March 31, 2010 thereby emphasising that
    56

    additional levy would fall within the ambit of any other charge arising out of

    the tenure of contract and as such, any other charge under the contract

    would be the liability of the claimant. Accordingly, it was urged that, the full

    amount of the additional levy was payable by the claimant to the

    Corporation, which the Corporation would in turn remit to the Central

    Government. The claimant had denied such liability, inter alia, contending

    that the judgment of the Supreme Court cast the responsibility for payment

    of the additional levy on the prior allottee (the Corporation) and by no

    stretch of imagination could the claimant be saddled with such liability. The

    learned Arbitrator dealt with the submissions of the parties, the exhibits,

    letters exchanged between the parties and the evidence, to arrive at the

    finding that while enacting the 2015 Act, the Parliament was quite alive to

    the factual position that the prior allottees had agreements with the third

    parties for implementation of the mining arrangements and for the above

    reasons, had specifically reserved the remedy of the third party, which had

    an existing contract with the prior allottee. Additional levy was imposed by

    the Supreme Court for illegal mining. The liability to pay the levy was by way

    of a compensatory measure for revenue lost on account of illegal coal block

    allocation. The 2015 Act categorically defined the extent of liability of the

    aggrieved person who might have been involved in such illegal mining,

    including prior allottees. The Parliament had specifically fixed the liability to

    pay compensation for illegal extraction of coal, in the name of additional levy

    only upon the prior allottee and none else. The legislature was gainfully

    conscious that there were existing contract of prior allottees with third
    57

    parties and others, in respect of mining, which were ultimately found to be

    illegal. If the intention of the Parliament was also to compel the contracting

    parties to bear such liabilities, it would have specifically indicated so in the

    Act. Such liability of prior allottees to compensate the Union Government in

    the form of additional levy would then be subject to the contract with the

    third party. Even if it is assumed for arguments sake that the additional levy

    within the meaning of the 2015 Act would come within the purview of other

    statutory levy which was not in existence at the time of creation of

    agreement, but was incorporated in the 2015 Act, even then, the payment of

    additional levy was the liability of the prior allottees alone. The provision of

    the 2015 Act would prevail over the terms of the contract between the

    parties. Reference was made by the learned Arbitrator to the decision of the

    Mannalal Khetan vs. Kedar Nath Khetan reported in (1977) 2 SCC 424

    in this regard. The relevant paragraph from the award is quoted below :-

    “41. It appears that the Parliament while enacting 2015 Act was quite
    alive to the factual position that the prior allottees had agreements
    with the third parties for implementation of the mining arrangements
    and for the above reason, in the 2015 Act, it has specifically
    safeguarded the remedy of the third parties which had existing
    contracts with the prior allottees. As pointed out earlier, regarding
    additional levies for illegal mining, Supreme Court specifically cast the
    liability to pay such levies upon the prior allottees as a compensatory
    measure to the Central Government. The Parliament while enacting
    2015 Act, categorically defined the extent of liability of every person
    who might have been involved in such illegal mining including, prior
    allottes, secured creditors, banks, third-parties who had contracts
    with the prior allottees etc. In Section 14(5), the Parliament has
    specifically fixed the liability to pay the compensation for illegal
    trading of coal in the name of additional levies only upon the prior
    allottees and none else, being fully-conscious that there were existing
    contracts of prior allottees with the third parties and others in aid of
    illegal, mining. If the intention of the Parliament was to compel also
    the contracting parties to bear such liability in terms of their contract
    with the prior allottees, it would specifically indicate that such liability
    58

    of the prior allottees to compensate the Union of India in the form of
    additional levies would be subject to the contract with the third
    parties. Even if I assume for the sake of argument that the additional
    levies within the meaning of 2015 Act comes within the purview of
    other statutory levies which was then not in existence at the time of
    creation of agreement C-1, in view of the special provision in the
    subsequently enacted 2015 Act which makes additional levies a
    liability of the prior allottee alone, the provisions contained in the
    subsequent legislation will prevail over the terms of the contract
    between the parties. As pointed out earlier, the following observations
    of the Supreme Court in the case of Mannalal Khetan v Kedar nath
    Khetan reported in (1977) 2 SCC 424 = AIR 1977 SC 536 will fortify
    the above view of this Tribunal that the Clause in C-1 referred to
    above
    cannot have overridden effect on Section 14(5) of the 2015 Act
    by which the proposed additional levy has specifically been made the
    liability of the prior allottee alone:

    “20. It is well established that a contract which involves in its
    fulfilment the doing of an act prohibited by statute is void. The
    legal maxim a pactis privatorum publico juri non derogatur means
    that private agreements cannot alter the general law. Where a
    contract, express or implied, is expressly or by implication
    forbidden by statute, no Court can lend its assistance to give it
    effect. (See Melliss v. Shirley Local Board, (1885) 16 QBD 446).
    What is done in contravention of the provisions of an Act of the
    Legislature cannot be made the subject of an action.” Thus,
    although by the 2015 Act, a subsequent legislation, the additional
    levy referred to therein is the liability of the Respondent alone, it
    cannot by taking aid of C-1 force the Claimant to bear a part of its
    own burden.”

    70. Thereafter, the learned Arbitrator dealt with the question whether the

    additional levy as enacted in the 2015 Act really came within the purview of

    clause C-1. To appreciate the said issues relevant clause as quoted below is

    perused :-

    “Where Net Selling Price would mean: Gross Selling Price less
    Royalty, Cess, Surface Rent, Dead Rent and any other duties levied
    on Coal Mining, Excise Duties, Sales Tax, VAT, GST and other
    Central and State Government Taxes, as applicable under the law
    from time to time and any other similar charges duties or Cess or
    any statutory levies which may become applicable during the
    tenure of the contract.”

    59

    71. The Arbitrator held that expressions “royalty”, “cess”, “excise duties”

    etc. including other statutory levy were incorporated in C-1, with the

    understanding that during the running of a lawful business of coal mining

    and when the tenure of the contract continued, if those were levied by the

    appropriate government, the amount would be deducted from the gross sale

    price, to arrive at the figure of net price. What was pointed out by the

    Supreme Court was that the prior allottees were running illegal business of

    coal mining as in the present case, and running of such illegal business had

    caused losses to the nation. Thus, the prior allottees were directed to

    compensate the Union of India, upon imposition of compensatory amount in

    the name of additional levy. Consequently, any levy imposed by the

    Parliament for running of the illegal business by violating the law of the land

    as a compensatory measure, could not come within the purview of C-1. The

    learned Arbitrator held that, the contract made the claimant bound by any

    new enactment, rules, regulations or orders which may be applicable to the

    mining activity. In such case, the claimant would be obliged to implement

    the same without any delay. The clause provided that if specific rules, orders

    or regulations were published or notified with regard to mining activities, the

    claimant should be responsible for the same. Therefore, additional levy

    under the 2015 Act could not be equated with a liability arising out of a new

    enactment or as any other statutory levy within the meaning of C-1. Hence,

    the Arbitrator held that illegal deduction of the amount of Rs.

    54,91,79,927/- from the dues of the claimant should be refunded. I find the

    reasoning and interpretation of the statutory provisions as also the contents
    60

    of C-1 to be rational and logical. Section 14(5), 16 and 22 of the 2015 Act

    are quoted below for appreciation of the above issue:-

    14(5) The additional levy imposed against the prior allottees of
    Schedule II coal mines shall continue to remain the liability of such
    prior allottees and such additional levy shall be collected by the
    Central Government in such manner as may be prescribed.
    ***
    ***

    16. Valuation of compensation for payment to prior allottee.–(1) The
    quantum of compensation for the land in relation to Schedule I coal
    mines shall be as per the registered sale deeds lodged with the
    nominated authority in accordance with such rules as may be
    prescribed, together with twelve per cent. simple interest from the date
    of such purchase or acquisition, till the date of the execution of the
    vesting order or the allotment order, as the case may be.

    (2) The quantum of compensation for the mine infrastructure in
    relation to Schedule I coal mines shall be determined as per the
    written down value reflected in the statutorily audited balance sheet of
    the previous financial year in accordance with such rules and in such
    manner as may be prescribed.

    (3) If the successful bidder or allottee is a prior allottee of any of the
    Schedule I coal mines, then, the compensation payable to such
    successful bidder or allottee shall be set off or adjusted against the
    auction sum or the allotment sum payable by such successful bidder
    or allottee, as the case may be, for any of the Schedule I coal mines.
    (4) The prior allottee shall not be entitled to compensation till the
    additional levy has been paid.

    ***
    ***

    22. Realisation of additional levy.–If a prior allottee of Schedule II
    coal mine fails to deposit the additional levy with the Central
    Government within the specified time, then, such additional levy shall
    be realised as the arrears of land revenue.

    72. The findings of the learned Arbitrator are quoted below:-

    “42. Now this Tribunal proposes to decide the question whether
    the additional levies indicated in the 2015 Act really comes
    within the purview of C-1. To appreciate the above question, it
    will appropriate to refer the provisions of C-1 which is quoted
    below:

    “Where Net Selling Price would mean: Gross Selling Price less
    Royalty, Cess, Surface Rent, Dead Rent and any other duties
    levied on Coal Mining, Excise Duties, Sales Tax, VAT, GST and
    other Central and State Government Taxes, as applicable under
    61

    the law from time to time and any other similar charges duties
    or Cess or any statutory levies which may become applicable
    during the tenure of the contract”.

    All the above expressions like Royalty, Cess, excise duties etc
    including other statutory levies as underlined above were
    incorporated in C-1 with the understanding that for running of
    a lawful business of coal mining if those are levied by the
    appropriate Government during the tenure of the Contract,
    those amount would be deducted from the Gross Sale Price to
    arrive at a figure of net price. All those items mentioned in C-1
    in the form of various levies are imposed for carrying on any
    lawful business. But as pointed out by the Supreme Court, the
    prior allottes were running illegal business of coal mining in the
    present case and for running such illegal business causing loss
    of the Nation, the Supreme Court directed the prior allottes to
    compensate the Union of India with a specified amount and the
    Parliament enacted 2015 Act by imposing that compensatory
    amount in the name of additional levy. The persons who are, on
    the other hand, carrying lawful business of coal mining are not
    required to pay such additional levies. Thus, the additional
    levies mentioned in the 2015 Act does not stand in the same
    platform with Royalty, Cess, Excise duties etc. mentioned in C-1
    which are imposed by the appropriate legislature for running of
    a lawful business. Consequently, any levy imposed by the
    Parliament for running of illegal business by violating the law of
    the land as compensatory measure upon a limited number of
    delinquent persons doing such illegal act was never
    contemplated in C-1. The parties in this case while arriving at
    the agreement mentioned as C-1, clearly intended to deduct all
    amount levied by the competent legislature for running of a
    lawful business of coal mining from the gross sale price to arrive
    at the figure of net sale price but it was never agreed to deduct
    compensation payable by the Respondent for violating any law
    of the land. The above interpretation of this Tribunal will find
    support from the averments made in paragraph 36 of the SOD
    while opposing claim (j) of paragraph 115 by the claimant. The
    relevant part of paragraph 36 of SOD is quoted below:

    “The cancellation of Trans Damodar coal mines, allotted in
    favour of the Respondent in terms of the order dated
    24.09.2014 of the Hon’ble Supreme Court of India, followed by
    the promulgation of Coal Mining (Special Provisions) Act 2015,
    was an act beyond the control of the Respondent. The order of
    the Hon’ble Supreme Court and the promulgation of Coal Mines
    (Special Provisions) Act
    2015 are Change in Law. Para XVIII on
    Change in Law in the Contract Agreement dated 31.05.2006,
    executed by and between the Respondent and the Claimant
    states the following:-

    62

    “During the period of Agreement, if any new Act, Rules,
    Regulations and Order come into force, which is applicable to
    the Mine, the Contractor (the Claimant herein) will be duty
    bound to implement the same without delay.”

    (Emphasis supplied).

    The above clause of the contract between the parties specifically
    states that the Contractor will be bound by any new enactments
    which are applicable to the Mine, meaning thereby, mine in
    general. The 2015 Act is not applicable to other mines than
    those mentioned in the schedules of the Act. This 2015 Act is
    applicable only for errant mining activities carried on by limited
    mine owners as specified above. Therefore, additional levies
    provided in the 2015 Act which are applicable only to the mines
    specified in the Schedules of the said Act cannot be said to a
    new enactment applicable to all coal mines and as such, are not
    coming within the expression “other statutory levies” within the
    meaning of C-1. Moreover, even in the new statute, it is
    specifically provided that the additional levies would be the
    liability of prior allottee.

    Consequently, this Tribunal holds that the Respondent illegally
    deducted the amount mentioned in Claim (a) amounting to Rs.
    54,91,79,927.00/- as an existing levy as if those are applicable
    to the persons doing mining of coal in general and the Claimant
    is entitled to the above amount as there is no dispute as regards
    the above figure.”

    73. Claim (b) amounting to Rs. 9,39,00,938/-, was for refund of the

    amount imposed as penalty for the shortfall in production in the financial

    year 2013-2014. The learned Arbitrator relied on the submissions of the

    parties, both oral and documentary evidence and came to the finding that

    the failure on the part of the claimant for not achieving yearly targeted

    extraction was on account of the non-compliance of the reciprocal obligation

    by the Corporation in failing to hand over unencumbered site for extraction.

    Relevant portions of the award are quoted below :-

    “49.

    63

    …….

    The above resolution of the Board of the Respondent itself suggests
    that the Respondent was satisfied that there was substance in the
    defences of the Claimant and for that reason, instead of imposing the
    penalty, it enhanced the target of mining and decided not to take
    penalty for the year 2013-14 on condition that the Claimant would
    achieve 50% of the added target of 2.75 lakh tonne in the next year
    which amounts to 1.375 lakh tonne although for the purpose of
    extraction of more than 1 lakh tonne of coal per year, environment
    clearance was necessary. It appears that in the year 2014-15, the
    Claimant had completed the production target of 1 million ton of coal
    by end of February, 2015/beginning March 2015 and they were in the
    process of mining more coal to meet the target as decided by the
    Respondent in its 213th Board Meeting for waiver of the penalty on
    account of shortfall in production in 2013-14. It further appears that
    for extraction of more coal than 1 million ton a year, Environmental
    Clearance was mandatory for extraction of additional quantity and it
    was the duty of the Respondent to obtain such permission by making
    application to the Government of India. The RW-1 has admitted that
    the respondent applied for such clearance but approval from MOEF
    for extraction of additional quantity of coal was not obtained.
    Therefore, in absence of clearance from the MOEF and also in view of
    the judgment of the Hon’ble Supreme Court cancelling the allotment
    of coal mines, the Respondent vide its letter Ref:

    No.MDTC/TDOCP/ENV/254 dated 26.02.2015 and also vide letter
    dated 03.03.2015 called upon the Claimant to stop coal-production
    after the Claimant reached the peak rated capacity of 1 million ton of
    coal at Transdamodar Sector Coal Block in the financial year 2014-

    15.(vide letters dated 26.02.2015 and 03.03.2015 of the Respondent
    marked as Exhibit, ‘AJ” of the SOC at page 795 of Volume IV.). Thus,
    there was no fault on the part of the Claimant for not complying with
    the Resolution of the Board of conditional waiver of the penalty.

    Moreover, this Tribunal finds that it has been established from the
    materials on record that the reasons for non-achievement of yearly
    target was fully established from the materials on record. At the
    relevant time, only 282 acres of land was in possession of the
    Claimant out of more than 600 acres of mining area. The plea of
    replacement of water pipeline affecting extraction of coal from
    substantial portion has also been proved. In such circumstances,
    there was no justification of imposing even additional target as a
    condition of waiver by the Board’s Resolution. Even, the Respondent
    could not produce any further resolution of its Board showing that it
    had subsequently passed any specific reasoned order holding non-
    compliance of the earlier order of the Board imposing conditional
    waiver.

    64

    50. On consideration of the entire materials on record this Tribunal
    holds that there was no violation on the part of the Claimant for not
    achieving the yearly targeted extraction and it was the Respondent
    who was responsible for non-compliance of its reciprocal obligation of
    handing over unencumbered site for extraction. The Claimant is, thus,
    entitled to Claim (b) of SOC amounting to Rs. 9,39,06,983.00 towards
    the refund of the amounts illegally imposed as penalty for the alleged
    shortfall in production in FY 2013-14.

    74. The next consideration was claim ‘c’ of the SOC for an amount of Rs.

    1,67,92,183/- towards refund of penalty wrongly deducted on account of

    alleged loss for transportation of coal from mine to railway siding, as averred

    in paragraph 74 of the SOC. The Arbitrator held that it appeared from the

    records and was also admitted by the RW1 in cross examination (question

    no. 223) that, for imposing penalty for the alleged loss in transit, the

    Corporation had not taken into consideration the weight of the coal sent

    from the mine head at the Durgapur Freight Terminal Discharge point.

    According to the procedure of measurement, the quantity of coal loaded in

    the truck at the mine head should be checked at the freight terminal, in

    order to ascertain whether the loss was at the instance of the claimant. For

    the purpose of finding out the liability of the freight centre owner for the loss

    in transit from the freight centre to the railway station, such measurement

    was an essential requirement, as the claimant did not have any liability

    beyond the freight centre. Therefore, by calculating the amount of loss in the

    total distance between the mine head and the railway station, the loss could

    not be attributed to the claimant, as it was not possible to ascertain the

    respective liability of the claimant and the freight centre owner. It could be a

    possibility that the entire loss in transit was for the fault of the freight centre
    65

    owner, who first stored the entire amount of coal in his godown and then re-

    loaded the coal for the purpose of conveying the same to the railway wagon

    and during that period, the entire responsibility was of the freight centre

    owner. The Corporation did not follow the procedure for measurement of

    loss in transit as mentioned in the tripartite agreement and consequently,

    the claimant did not get the benefit of 0.5% loss as per agreement between

    the parties.

    75. The answers to the questions 305, 308, 311, 314, 316, given by RW1

    were considered. It was held that the Corporation had illegally imposed the

    penalty for the alleged loss in transit upon the claimant and the claimant

    was entitled to the relief claimed under (c). Reference is made to the

    following paragraphs of the award :-

    “57.On consideration of the above materials, it appears from the
    work-order issued by the Respondent to the Claimant dated 31
    March 2015, (page 834 of paper book volume IV) that the
    respondent asked the claimant for transportation of coal from
    the coal mine up to the private freight terminal owned by
    Palogix Infrastructure private limited in favour of M/S West
    Bengal Power Development Corporation Limited and Durgapur
    Projects Limited with the stipulation that the said order was
    issued with retrospective effect from 20 September 2013 up to
    30 March 2015 and the charges for transportation will be at par
    with notified CII charges. It was further stipulated that the
    maximum transit loss allowable for transportation from Mine
    stockyards to Railway Siding and subsequent loading onto
    wagons will be 0.5% of the stock transferred from mine. In the
    event of shortfall beyond 0.5%, the coal value of the excess
    shortfall will be recovered from the bill of the claimant along
    with applicable taxes. Clause 8 of the tripartite agreement,
    however, provides for weighment of coal which is quoted below:

    “The basis of measurement of coal coming inside the said
    Durgapur Freight Terminal will be the measurement as recorded
    in the computerised weighbridge. The weighbridge shall conform
    66

    to standards and shall be examined periodically by an
    independent agency to test whether it is functioning properly.
    The weighbridge shall be installed by the FTO at the Unloading
    Points in adequate numbers and for rake weighment at its own
    cost. In the presence of both parties, the coal shall be weighed
    at the said Durgapur freight Terminal discharge point and
    Railway weighbridge for outward movement of coal. These two
    weights shall be reconciled. Both weighments shall be jointly
    signed by representatives of Mine Owners/Hirer and the FTO.
    For the purpose of billing, however, the recorded weight of the
    railway weighbridges shall be final.

    The procedure for measurement shall be that the loaded truck
    shall pass through the weighbridge before unloading the coal
    and after unloading of the same, the truck shall pass through
    the weighbridge for recording actual weight of such coal.
    Measurement is to be made only in the presence of the
    representative of Mine Owner. The weighment shall be recorded
    in ERP system of the Mine Owner for such purpose. The
    weighing system required to be synchronized with ERP system
    of Mine Owner for online recording which shall be final and
    binding on both the parties. Such dailies statement will form
    the basis of raising invoices and payment. In the Excess/Short
    up to 1% of receipt of quantity will be allowable as weighment
    difference.”

    58. As it appears from the record and also admitted by the RW-
    1 in cross-examination(Q-223), for imposing the penalty for the
    alleged loss in transit, the Respondent has not taken into
    consideration the weight of the Coal sent from Mine head at the
    Durgapur freight Terminal discharge point although according
    to the procedure of measurement, the quantity of coal loaded in
    the truck at the mine head should be checked at the freight
    terminal in order to ascertain the loss in transit at the instance
    of the Claimant. For the purpose of finding out the liability of
    the freight-center-owner for the loss in transit from freight
    center to Railway station such measurement is essentially
    required as the Claimant has no liability beyond freight centre.
    Therefore, by calculating the amount of loss in the total distance
    between mine head and the Railway Station, that-loss-cannot
    be attributable to the Claimant as we are not in position to
    ascertain the respective liability of the Claimant and the freight-
    centre-owner. It may be that the entire loss in transit was for
    the fault of the freight-center-owner who first stored the entire
    amount of coal in its godown and then reloaded for the purpose
    of conveying the same to the Railway wagon and during that
    period, the entire responsibility is of the freight-centre-owner.
    67

    Thus, it is well established that the Respondent has not followed
    the procedure of measurement of loss in transit as indicated in
    the tripartite agreement and consequently, the Claimant has not
    got the benefit of 0.5% loss as per agreement between the
    parties. Moreover, as appearing from the answers given by the
    RW-1 to Questions nos.305, 308-311,314-316 put to him, that
    he was constrained to admit that the basis of the above claim
    was patently illegal and not tenable. This Tribunal, thus, holds
    that the Respondent has illegally imposed the penalty for the
    alleged loss in transit upon the Claimant which is baseless and
    the claimant is entitled to the relief (c) made in paragraph 115 of
    the SOC amounting to Rs. 1,67,92,192/-.”

    76. Next came claims (d) and (e). The questions which the learned

    Arbitrator decided was, whether the claimant was entitled to Rs. 7,51,48,

    652/- towards alleged dues on account of mining charges and commission

    on the direct sale by the Corporation to the West Bengal Power Development

    Corporation Limited (WBPDCL) and a further sum of Rs. 4,73,45,333/-

    towards sale to Durgapur Power Limited (DPL). The Arbitrator held that the

    claimant was entitled to relief under claims (d) and (e) i.e. the claimant was

    entitled to receive the mining charges and the loss in time as legitimate

    dues. The defence of the Corporation that WBPDCL and DPL were

    Government Companies and the Corporation was entitled to deviate from

    the terms of the contract was not tenable, as the contract did not contain

    any such term, giving exemption from due compliance of the covenants

    therein, in case of sale to Government Companies. The terms of the contract

    and the relevant factors were taken into consideration. The findings are

    quoted below:-

    “65. From the above materials on record, it appears that the figure
    appearing at relief (d) in paragraph 115 showing Rs.7,51,48, 652.00 is
    not a correct figure having regard to the calculation given in Ext-BA at
    68

    pages 908-1059 of the paper book IV and the same should be
    Rs.73,50,27,745/- as correctly stated in paragraph 87 of the SOC and
    reiterated by the CW-1 in paragraph 64 of the affidavit of evidence and
    no cross-examination has been made by the learned counsel for the
    Respondent suggesting any different sum than the ones claimed by
    the CW-1 in his affidavit of evidence or any mistake in calculation.
    There is no dispute that there is specific agreement between the
    parties covering the present aspect which is quoted below:

    “Clause III – Rights, Duties & Obligation Of WBMDTC

    1…………………………….

    2. WBMDTC will approve all the Buyers recommended by Contractor
    at its sole discretion and also reserve the right to book orders directly
    provided that the buyers fulfill the eligibility criteria under the
    Allotment Letter No. 13016/5/2002-GA dated 14th January 2005
    from the Ministry of Coal, Government of India and other guidelines
    as may be indicated by Government of India, State Government time
    to time and will pay the price of Coal in full advance by way of
    DD/PO/ Irrecoverable Letter of Credit in favour of WBMDTC.”

    The defence of the Respondent in selling coal without taking full
    advance is as follows:

    “(i) Being a government organization, the payment for coal supply from
    WBPDCL and DPL were assured;

    (ii) The Work Order issued by WBPDCL and DPL stipulated some
    payment conditions, which did not stipulate advance payments;

    iii) Power generation by WBPDCL and DPL are for public purposes
    and, therefore, mode of payment realization from these two companies
    were different from other private buyers of coal of Trans Damodar coal
    mine.”

    66. In the opinion of this Tribunal, the above defence for not
    complying with the terms of the contract is not tenable in the eye of
    law as such violation will affect the right of the Claimant of receiving
    its mining charges and commission in time and consequently, it will
    also cause financial loss for the delayed payment of its legitimate
    dues. In the above, circumstances, this Tribunal is left with no other
    alternative but to allow the reliefs claimed in serial no. (d) to the
    extent of Rs.73,50,27,745/-(not what is wrongly mentioned in
    paragraph 115 due to typographical mistake) and Rs.4,73,45,333/- in
    respect of prayer (e) of paragraph 115 due to typographical mistake)
    and Rs. 4,73,45,333 /- in respect of prayer (e) of paragraph 115 of the
    SOC as the Respondent has not adduced any evidence disputing the
    evidence adduced as regards the calculation of the Claimant given in
    his basic facts in paragraphs 84-89 of SOC and the statements made
    in paragraphs 62-65 of the affidavit of evidence by the CW-1 as
    69

    mentioned above and at the same time, the violation of the terms of
    the contract, as indicated above, is also admitted. The defence that as
    those two entities were Government Company, the Respondent was
    entitled to deviate from the terms of the contract, is also not tenable
    as the contract does not contain any such term giving exemption to
    the Respondent from complying with the same in case of Government
    Companies. The figure mentioned in relief (d) of paragraph 115 of the
    SOC is on the face of a typographical mistake as would appear from
    the materials on record.

    67. Regarding the claim of interest as prayed in prayers (f), (h) and (k)
    of paragraph 115 of the SOD, this Tribunal proposes to deal with the
    question separately after deciding the other claims of the Claimant.”

    77. The next question which was taken up was, claim (g). Whether the

    claimant was entitled to refund on account of land advance made by the

    claimant. Such advance was made pursuant to clause 12 of the contract

    agreement dated 31st May, 2006 and the claimant deposited Rs.

    43,68,22,071/- as advance for acquiring land for mining purpose in Trans

    Damodar Coal Mining Block. The said deposit was to be adjusted /repaid to

    the claimant at a pre-determined rate as contained in Annexure C1 of the

    contract agreement on the basis of per tonne of coal removed over 30 years

    of commercial production. The commercial production of coal commenced in

    the financial year 2012 to 2013. However, pursuant to the order of the

    Hon’ble Supreme Court in 2014, mining activities were stopped from the

    midnight of March 31, 2015. The Corporation directed the claimant to stop

    all mining activities upon reaching the 1 million metric tonne of coal target.

    Thus, the payment received by the claimant for coal mining from

    commencement of production in 2012 till March 31, 2015, was a sum of Rs.

    1,10,55,072/-. After adjustment of the said sum, a further sum of Rs.

    42,57,66,999/- was still being held and retained by the Corporation on
    70

    account of land purchase advance. In the premise, the claimant called upon

    the Corporation to refund the unadjusted amount along with interest

    aggregating to Rs. 54,83,87,894/-.

    78. Learned Arbitrator held that from the facts, the oral evidence and the

    trend of the cross examination it would be evident that the Corporation had

    admitted its liability to return the advance to the extent of Rs.

    33,56,15,678.35/-, whereas, the claim was for Rs. 38,72,48,826/- with

    interest. The learned Arbitrator held that interest would be payable. The

    moment the Supreme Court declared the agreement to be a nullity, there

    was no scope of continuing with the agreement, resulting in the liability of

    the Corporation to return the money advanced with effect from April 1,

    2015. Any delay in refunding the amount would incur the liability to pay

    interest on the net deposit. The learned Arbitrator held that, there was no

    evidence on record to prove that in the past, the Corporation had ever

    offered to return the amount and that the claimant had refused to accept.

    Consequently, it was held that the claimant was entitled to interest on the

    unpaid amount from April 1, 2015. It also appears that, as per the

    submissions of the learned advocates for the Corporation, the Corporation

    had returned a sum of Rs. 33,56,15,678.35/- as per the receipt dated April

    9, 2019. Therefore, it was held that, interest at the rate to be fixed on the

    above amount should be calculated from April 1, 2015 to April 9, 2019.

    79. The answers of the RW1 to questions put to him in cross examination

    clearly demonstrated that an incorrect defence had been taken by the
    71

    Corporation regarding the payment made over and above what the claimant

    had established. Paragraph 74 to 77 of the award are quoted below:-

    “74. It appears from the above material on record that the Respondent
    on the above issue has admitted its liability to return to the extent of
    Rs.33,56,15,678.35p whereas the claimant claimed a sum of
    Rs.38,72,48,826/- with interest. In the last sitting of this Arbitration
    Proceeding, the learned counsel for the Respondent also made
    submission from the instruction of his client to pay the above amount
    as will appear from paragraph 2 of the minutes of that day which is
    quoted below:

    2. Mr. Ghoshal, the Learned Senior Counsel on instructions from the
    respondent submits that his client would pay/transfer a sum of
    Rs.33,56,15,678.35p. (Rupees Thirty-Three Crore Fifty-six Lakh
    fifteen Thousand Six Hundred Seventy Eight and paise thirty five) on
    account of claim for refund of land advance, as disclosed in page 81 of
    the Statement of Defence, to the claimant within eight days from
    today. Mr. Mitra, the Learned Senior Counsel on instructions from his
    client, the claimant, informs this Tribunal that the said amount would
    be accepted by his client without prejudice to his client’s rights and
    claims in this arbitration proceeding.”

    75. Therefore, this Tribunal is required to decide whether the
    Claimant is entitled to Rs. Rs.38,72,48,826/- with interest.

    76. First, this Tribunal proposes to deal with the question of interest.
    It is true that in agreement between the parties it is provided that the
    said advance will be refunded in course of 30 years in a manner
    provided therein by way of adjustment with the claim of the Claimant
    towards mining charges. However, the moment Supreme Court
    declared the agreement as nullity, there was no scope of continuing
    with the said agreement resulting in the liability of the Respondent to
    return the said amount with effect from 1 April, 2015. Any delay in
    refunding the amount will incur liability to pay interest on the unpaid
    deposit. There is no evidence on record produced by the Respondent
    that in the past it ever offered to return the amount but the claimant
    refused to accept. Consequently, this Tribunal holds that the
    Claimant is entitled to interest on the unpaid amount from April 1,
    2015. It appears that pursuant to the submission of the learned
    Counsel for the Respondent at the last sitting of the Tribunal which
    has been recorded in the minutes of the last sitting, the Respondent
    has returned a sum of Rs.33,56,15,678.55 paise as it appears from
    the receipt dated 9th April, 2019 which has been sent to this Tribunal
    by speed post by learned Advocate for the Claimant. Therefore, the
    liability of paying interest at the rate to be fixed on the above amount
    will be till 9th April, 2019 from 1st April, 2015 and on the balance
    amount as per order of this Tribunal.

    72

    77. The next question is whether the Claimant is entitled to refund of
    Rs.38,72,48,826/ with interest. The specific case of the Claimant is
    that it has advanced a sum of Rs.43,68,22,071/-and after the
    commencement of product in the year 2012, till 31 March, 2015, a
    sum of Rs.1,10,55,072/-was adjusted and after such adjustment, the
    amount is reduced to Rs.42,57,66,999/-. Subsequently, the
    respondent issued a cheque dated 14th February, 2017 for a sum of
    Rs. 2,15,85,016/ and thus, a sum of Rs. 1,10,55,072 + Rs.
    2,15,85,016 = Rs.3,85,18,173/- has been received by the Claimant till
    the presentation of the SOC and the balance amount of Rs.
    43,68,22,071 – Rs. 3,85,18,173 = Rs.38,72,48,826/- is payable. If
    according to the Respondent, any amount in excess of
    Rs.3,85,18,173/-, in that event the onus is upon it to produce
    document in support of such payment which the Respondent has
    miserably failed. The answers given by the RW-1 in cross-examination
    in respect of questions nos.273,275,277-279,281-283,286,287,289-
    295,300 and 301, quoted above, clearly demonstrate that untrue
    defence has been taken by the Respondent regarding excess payment.
    This Tribunal, thus, holds that the Claimant is entitled to the relief
    claimed in (g) of paragraph 115 of the SOC amounting to Rs.
    38,72,48,826/ with interest rate of which I will deal separately.”

    80. The next question was whether the claimant was entitled to a claim

    towards loss in mine development, as claimed in paragraph 103 of the SOC.

    Initially, the claim was for Rs. 15,11,59,609. The claimant filed an

    application for amendment of the SOC and reduction of the amount to Rs.

    14,59,21,822/-. The application for amendment was allowed. The learned

    Arbitrator held that, according to the terms of the contract, it was the duty

    of the claimant to excavate without intervention of the respondent and the

    expenditure for such process should be borne by the claimant. The learned

    Arbitrator denied such claim. The learned Arbitrator held that the

    Corporation was not responsible for the stoppage of excavation. The position

    would have been different if the contract was illegally terminated, without

    any just cause and the Corporation would have stopped the excavation at a

    premature stage. Thus, the Arbitrator held that the claim (i) could not be
    73

    granted to the claimant. This finding was in consonance with the agreement

    made on behalf of the corporation.

    81. The next issue was whether claim (j) was admissible or not, on

    account of the loss of investment in fixed assets. The learned Arbitrator held

    that there was neither any agreement nor any clause in the agreement

    between the parties that, the Corporation would compensate the claimant in

    case of any loss suffered by the claimant with respect to the fixed assets. In

    the absence of such agreement, the Arbitrator rejected the claim (j).

    82. The next question was whether the claimant was entitled to loss of

    profit. It was held by the learned Arbitrator that as the case was not of

    unlawful termination of the agreement at the instance of the Corporation,

    but was a case of frustration of an agreement which was declared to be void

    by the Supreme Court of India, the claimant could not get the benefit of

    Section 73 of the Contract Act so as to claim future loss of profit for the

    balance 27 years of the term. Moreover, the 2015 Act had merely revived the

    share of the claimant to the extent it was a valid contract, restricting the

    remedy of the third party only against the prior allottee. The contract Act did

    not provide for remedy of damages, otherwise than as permitted under

    Section 73 and 74 of the Contract Act. Thus, it was rightly held that, there

    was no scope to grant relief for future loss of profit, in favour of the

    claimant. The position would have been different if the 2015 Act specifically

    provided for the relief of future loss of profit in favour of the third party.

    Therefore, claim (l) was also dismissed.

    83. Paragraphs 94 to 98 of the award are quoted below:-
    74

    “94. Now the prime question is whether in the facts of the present
    case, the claimant is at all entitled to claim loss of future profit for the
    balance term of the contract because of the order passed by the
    Supreme Court. In the opinion of this Tribunal, the term “loss of
    future profit” under the Contract Act can be availed of only when a
    valid contract has been illegally terminated by a party to the contract
    and the above term “loss of future profit” comes within the domain of
    the phrase “damage” caused to a victim.

    95. In the Contract Act, the Sections 53, 54, 55, 56, 65, 70 are the
    provisions providing for compensation for loss suffered by a party for
    the wrongful act of the other including failure of the other to perform
    reciprocal prior obligation or for restoration of the benefit or advantage
    received by one from another, as the case may be, where the contract
    is a void one. Sections 73 and 74, on the other hand, are the
    provisions providing for compensation for the loss or damage suffered
    by a party for the breach of the contract by the other party.

    96. The words “damage”, and “loss”, as a noun, have been defined in
    the Oxford Advanced Learner’s Dictionary of Current English, 4th
    Edition, by A.S. Hornby as under:

    “Damage”- noun. 1. (to something) loss of value, attractiveness or
    usefulness caused by an event, accident, etc. 2. Damages (pl) -money
    paid or claimed as compensation for damage (1), loss or injury.

    “Loss”-1. act, instance or process of losing:2.(a) Person or thing lost.

    (b) money lost in a business deal, etc. 3(sing) suffering caused by
    losing somebody or something; disadvantage:

    In the Contract Act, the word “damage” in plural has not been used
    but it is used in singular. Thus, the word used therein is not employed
    to mean “money paid or claimed as compensation for damage (1), loss
    or injury” but being used in singular, it’s meaning is more extensive
    than that of the word “loss” which is restricted to the actual suffering
    caused, whereas the word “damage” may include something more
    than actual loss, as for example, expectation of future loss of profit,
    earning etc. for the wrong done by the other party.
    ………

    97. Applying the above principles in the context of the Contract Act,
    one can reasonably contend that while in cases covered by Sections
    73
    and 74 of the Act, the amount of compensation are available not
    only for “loss” actually suffered by a party but also for “damage”

    caused to the aggrieved party in addition to the “loss” actually
    suffered, but in the cases covered by other sections mentioned above,
    the compensation must be restricted to the actual loss suffered
    because in those sections the word “damage” is conspicuously absent
    as the Legislature does not waste its words.

    98. Consequently, this Tribunal is of the opinion that the present
    case, not being the one for unlawful termination of the agreement
    75

    between the parties at the instance of one but being due to frustration
    of an agreement declared to be void by the Supreme Court of India,
    the Claimant can, in no case, get the benefit of Section 73 of the
    Contract Act so as to claim future loss of profit for the balance 27
    years of the terms. This Tribunal has already pointed out that the
    claimant has not even pleaded that the Respondent from the very
    beginning knew that the contract is against the law; on the other
    hand, stance taken in this proceeding by the parties is that they bona
    fide entered in to the contract by treating it as a valid one. Moreover,
    the 2015 Act has merely revived the remedy of the Claimant to the
    extent, as if it is a valid contract, however, by restricting the remedy of
    the third party only against the prior allottee. Accordingly, if the
    Contract Act does provide for remedy of damage otherwise than in a
    case under Sections 73 and 74, there is no scope of giving the relief of
    future loss of profit in favour of the Claimant. Position would have
    been different, if the 2015 Act specifically provided the relief of future
    loss of profit in favour of the third party against the prior allottee. The
    prayer of the Claimant in terms of relief (1) as made in Paragraph 115
    is, thus, dismissed on the above ground alone.”

    84. With regard to the claim (m) i.e. the share of the claimant in the

    balance in escrow account with the State Bank of India, the Arbitrator held

    that in paragraph 32 of the said SOD, the Corporation had mentioned that it

    had no objection if the claimant withdrew the same from the escrow

    account, for proportionate distribution between the parties. The relevant

    pleadings of the parties were considered and the claim was allowed as was

    follows:-

    “102. The learned Senior Counsel for the Respondent did not put any
    question denying the above Claim of the Claimant. The RW-1 has also
    not stated anything about the above claim of the Claimant. Thus, this
    Tribunal is of the view that the Claimant is entitled to the relief
    claimed as (m) of paragraph 115 of the SOC. The Respondent is
    directed to immediately give necessary instruction to the SBI,
    Commercial Branch, Jeevan Deep, 1, Middleton Street, Kolkata, to
    with whom the Escrow Account is maintained, to release
    Rs.8,16,784/- in favour of the Claimant out of the credit balance of
    Rs. 10,68,670.28 as per bank statement dated 12.3.2017. being Ext.
    BB at page 1060 of Paper Book vol. IV”

    76

    85. Next was claim (n) which was with regard to the claimants’ share in

    the fixed deposits with the State bank of India. The Learned Arbitrator

    opined that the claimant was entitled to the claim and held as follows :-

    “109. It appears that the RW-1 subsequently did not give any details
    of those cases, where according to him, the Claimant was party to the
    proceedings before High Court. As indicated above, specific suggestion
    was given that the Claimant was not a party in any of those alleged
    proceedings either before the High Courts or in the Supreme Court.
    Thus, the Respondent has failed to prove that the Claimant was a
    party to any of those proceedings as onus is upon the Respondent to
    prove the same when the claimant is denying the fact. A negative fact
    cannot be proved by giving any positive evidence. Thus, the Claimant
    cannot have any liability for the expenditure of any legal proceedings
    incurred by the Respondent. When the Respondent has virtually
    admitted the claim of the Claimant in the Escrow Accounts, there is
    no reason why it will be deprived of the interest accrued therein. The
    suggestion given to the CW-1 was that in the agreement there was no
    clause for right of interest which was admitted by the CW-1. But in
    order to deprive the Claimant of the right to interest, there must be
    specific-clause in the agreement to that effect. Absence of such clause
    means that right of interest is a matter of course. Thus, this Tribunal
    holds that the Claimant is entitled also to the interest as well as the
    principal of the Fixed Deposit automatically opened by SBI from the
    amount lying in deposit with the Escrow Account. The Claimant is
    therefore entitled to its prayer in terms of relief (n) of paragraph 115 of
    the SOC in full. The Respondent is directed to immediately give
    necessary instruction to the SBI, Commercial Branch, Jeevan Deep, 1,
    Middleton Street, Kolkata, to liquidate the fixed deposits in respect of
    Escrow Account maintained by the parties in the said Branch being
    Account no.32064045713 as mentioned at page 1063 of Paper Book
    no. IV so that the liquidated Value of the Fixed deposits along with the
    accrued interest to those accounts may be distributed to the Claimant
    and the Respondent in the Ratio as per agreement between the parties
    and the Bank Authority is directed to release the same both in favour
    of the Claimant and the Respondent as per their respective share of
    76.43:23.57 immediately on getting such instruction from the
    Respondent.”

    86. With regard to interest and cost, it was held as follows:-

    “110.

    ***
    77

    ***
    Bearing in mind the aforesaid provisions of the Act by which this
    Tribunal is governed, this Tribunal now proposes to consider the
    question of rate of interest payable by the Respondent to the
    Claimant.

    It appears from Section 31(7) of the Act that it has two parts. The first
    part, viz. sub-section (a) gives power to the Arbitral Tribunal to award
    interest unless otherwise agreed by the parties, for the period between
    the date on which the cause of action arose and the date on which the
    award is made at such rate as it deems reasonable for the whole or
    any part of the period on the whole or any part of the money found to
    be due and payable by the award it seeks to pass.

    The second part on the other hand, viz. sub-section (b) invests the
    Tribunal to grant post award interest which should unless the award
    otherwise directs, carry interest at the rate of two per cent higher than
    the current rate of interest prevalent on the date of award, from the
    date of award to the date of payment bearing in mind that the
    expression “current rate of interest” shall have the same meaning as
    assigned to it under clause (b) of Section 2 of the Interest Act, 1978
    (14 of 1978).

    According to Clause (b) of Section 2 of the Interest Act, 1978, “current
    rate of interest” means the highest of the maximum rates at which
    interest may be paid on different classes of deposits (other than those
    maintained in savings account or those maintained by charitable or
    religious institutions) by different classes of scheduled banks in
    accordance with the directions given or issued to banking companies
    generally by the Reserve Bank of India under the Banking Regulation
    Act, 1949
    . (10 of 1949) Explanation. In this clause,” scheduled bank”

    means a bank, not being a co-operative bank, transacting any
    business authorised by the Banking Regulation Act, 1949; (10 of
    1949).

    In this case, regarding payment of interest, there is no restriction in
    the agreement entered into between the parties. Therefore, this
    Tribunal is to fix the rate as it should deem reasonable.
    ***
    ***
    In this case, the Claimant is involved in the business of mining and
    the cause of action for raising different claims arose from 1 April,
    2015, the date the Supreme Court implemented the order of
    prohibition of mining in this case. After taking into consideration that
    huge amount of money was due and payable from the year 2015 and
    in the meantime four years have expired, this Tribunal proposes to
    grant pre-award interest at the rate of 12% per annum from 1st April
    2015 till the date of Award on the Awarded amount as mentioned in
    relief nos. (a), (b), (c), (d), (e), and (g) of paragraph 115 of the SOC. So
    78

    far the reliefs in terms of (m) and (n) are concerned, since this
    Tribunal has asked the SBI authority to release the amount with
    interest accrued thereon, this Tribunal does not propose to grant any
    further interest on that amount.

    111. The last question is the question of assessment of costs. Section
    31A
    of the Arbitration and Conciliation Act, 1996 deals with the
    Regime for costs which is quoted below:

    31-A. Regime for costs. (1) In relation to any arbitration proceeding or
    a proceeding under any of the provisions of this Act pertaining to the
    arbitration, the court or arbitral tribunal, notwithstanding anything
    contained in the Code of Civil Procedure, 1908 (5 of 1908), shall have
    the discretion to determine-

    (a) whether costs are payable by one party to another;

    (b) the amount of such costs; and

    (c) when such costs are to be paid.

    Explanation. For the purpose of this sub-section, “costs” means
    reasonable costs relating to-

    (i) the fees and expenses of the arbitrators, courts and witnesses;

    (ii) legal fees and expenses;

    (iii) any administration fees of the institution supervising the
    arbitration; and

    iv) any other expenses incurred in connection with the arbitral or
    court proceedings and the arbitral award.

    (2) If the court or arbitral tribunal decides to make an order as to
    payment of costs,-

    (a) the general rule is that the unsuccessful party will be ordered to
    pay the costs of the successful party; or

    (b) the court or arbitral tribunal may make a different order for
    reasons to be recorded in writing.

    (3) In determining the costs, the court or arbitral tribunal shall have
    regard to all the circumstances, including

    (a) the conduct of all the parties;

    79

    (b) whether a party has succeeded partly in the case;

    (c) whether the party had made a frivolous counter-claim leading to
    delay in the disposal of the arbitral proceedings; and

    (d) whether any reasonable offer to settle the dispute is made by a
    party and refused by the other party.

    (4) The court or arbitral tribunal may make any order under this
    section including the order that a party shall pay-

    (a) a proportion of another party’s costs;

    (b) a stated amount in respect of another party’s costs;

    (c) costs from or until a certain date only;

    (d) costs incurred before proceedings have begun;

    (e) costs relating to particular steps taken in the proceedings;

    (f) costs relating only to a distinct part of the proceedings; and

    (g) interest on costs from or until a certain date.

    (5) An agreement which has the effect that a party is to pay the whole
    or part of the costs of the arbitration in any event shall be only valid if
    such agreement is made after the dispute in question has arisen.”
    ***
    ***
    Thus, the summary of the expenditure incurred by the parties as
    follows:

    Claimant’s expenditures.

    1. Fees paid towards the Arbitrator- Rs. 18,75,000/-including TDS.

    2. Remuneration paid to the Clerk of the Tribunal- Rs. 42,500/-

    3. Remuneration paid to the Stenographer of the Tribunal-

    Rs.51,000/-.

    4. Fees paid to the learned Advocates, stenographer and clerkage-Rs.
    1,28,22,037/-

    6. Venue charge+ Food-Rs.70,843/-.

    Total- Rs.1,48,61,380/-

    80

    Respondent’s expenditures.

    1. Fees paid towards the Arbitrator- Rs. 18,75,000/-including TDS.

    2. Remuneration paid to the Clerk of the Tribunal- Rs. 42,500/-.

    3. Remuneration paid to the Stenographer of the Tribunal-
    Rs.51,000/-.

    4. Fees paid to the learned Advocates

    a) Mr. Animesh Kanti Ghosal- Rs.13,98,000/-

    b) Fees paid to the Clerks of Mr. Animesh Ghosal-Rs.42,500/-

    c)Mr. Sanjay Saha, Advocate-Rs. 1,18,976/- including clerkage and
    legal expenses.

    5. Srinivas Rao (Expenses towards photo copy- Rs.8,800/-

    6. Venue charge- Rs.69,880/-+ Refreshment-Rs. 19,885/-5. 7. Ashoke
    Kumar Maity-Stenographer- Rs.5000/-

    Total- Rs. 36,27,011/-

    112. As the Claimant has substantially succeeded except three out of
    its eleven claims, in the opinion of this Tribunal, the claimant is
    entitled to the 8/11th of the above amount of costs incurred by it less
    Rs. 70,843/- spent as cost of Food- Rs. 1,47,90,537/- as those are
    quite reasonable having regards to the amount of claim and the
    gravity of the subject-matter. This Tribunal accordingly pass an Award
    of costs of Rs.1,47,90,537/-x 8/11 = Rs. 1,07,56,754/- as costs in
    favour of the Claimant.”

    87. Thus, the Learned Arbitrator refused the claims which arose out of

    untimely and premature termination of the contract, inter alia, holding that

    the Corporation could not be made liable in any way for such termination,

    as the termination was not at the instance of the Corporation, but the

    contract was declared to be void by the Hon’ble Supreme Court upon

    cancellation of the allocation of the coal block in favour of the Corporation.

    Thus, the contention of the learned Advocate that the Learned Arbitrator did

    not retain jurisdiction to allow some of the claims upon holding that the
    81

    contract was a void one and the contractor was remediless was answered by

    the learned Arbitrator, in details. The Learned Arbitrator denied those

    claims which would not be available on account of the contract being

    declared void and rightly held that the claimant was remediless in respect of

    those claims which would be covered by Sections 73 and 74 of the Contract

    Act. However, by applying the principle of restitution and upon interpreting

    the non-obstante clauses under Section 11 and Section 14, the Arbitrator

    came to the conclusion that some of the claims should be allowed.

    88. Aviram Singh vs C.D. Commachen (Dead) by Legal

    Representatives and Ors. reported in (2017) 2 SCC 629 dealt with

    permission to utilise parliamentary material in construing the words of a

    statute. This court has considered the parliamentary material produced by

    the learned Advocate General, namely, report of the Select Committee on the

    Coal Mines “Special Provisions” Bill, 2015 and also the history of the

    legislation, and is of the opinion that the interpretation of the learned

    Arbitrator with regard to the rights of third parties against the prior allottee

    was protected under the 2015 Act. The view of the learned Arbitrator is

    fortified by the principle of restitution and is not opposed to the

    fundamental policy of India. This court is of the view that the interpretation

    of the learned Arbitrator is not patently illegal. There is no scope for

    interference by this court. The materials on record and the evidence were

    considered in details. The learned Arbitrator did not take resort to

    extraneous considerations, in allowing the claims. The laws have not been

    ignored and the learned Arbitrator adopted a judicial approach.
    82

    89. The relevant portions of MNCC Limited vs. Vedanta Limited (supra)

    are quoted below :-

    “11. As far as Section 34 is concerned, the position is well-
    settled by now that the Court does not sit in appeal over the
    arbitral award and may interfere on merits on the limited
    ground provided under Section 34(2)(b)(ii) i.e. if the award is
    against the public policy of India. As per the legal position
    clarified through decisions of this Court prior to the
    amendments to the 1996 Act in 2015, a violation of Indian
    public policy, in turn, includes a violation of the fundamental
    policy of Indian law, a violation of the interest of India, conflict
    with justice or morality, and the existence of patent illegality in
    the arbitral award. Additionally, the concept of the
    “fundamental policy of Indian law” would cover compliance with
    statutes and judicial precedents, adopting a judicial approach,
    compliance with the principles of natural justice,
    and Wednesbury [Associated Provincial Picture
    Houses v. Wednesbury Corpn., (1948) 1 KB 223 (CA)]
    reasonableness. Furthermore, “patent illegality” itself has been
    held to mean contravention of the substantive law of India,
    contravention of the 1996 Act, and contravention of the terms of
    the contract.

    12. It is only if one of these conditions is met that the Court
    may interfere with an arbitral award in terms of Section
    34(2)(b)(ii)
    , but such interference does not entail a review of the
    merits of the dispute, and is limited to situations where the
    findings of the arbitrator are arbitrary, capricious or perverse, or
    when the conscience of the Court is shocked, or when the
    illegality is not trivial but goes to the root of the matter. An
    arbitral award may not be interfered with if the view taken by
    the arbitrator is a possible view based on facts. (See Associate
    Builders v. DDA [Associate Builders
    v. DDA, (2015) 3 SCC 49 :

    (2015) 2 SCC (Civ) 204] . Also see ONGC Ltd. v. Saw Pipes
    Ltd. [ONGC Ltd.
    v. Saw Pipes Ltd., (2003) 5 SCC 705]
    ; Hindustan Zinc Ltd. v. Friends Coal Carbonisation [Hindustan
    Zinc Ltd.
    v. Friends Coal Carbonisation, (2006) 4 SCC 445] ;

    and McDermott International Inc. v. Burn Standard Co.
    Ltd. [McDermott International Inc.
    v. Burn Standard Co. Ltd.,
    (2006) 11 SCC 181] )

    13. It is relevant to note that after the 2015 Amendment to
    Section 34, the above position stands somewhat modified.
    Pursuant to the insertion of Explanation 1 to Section 34(2), the
    scope of contravention of Indian public policy has been modified
    to the extent that it now means fraud or corruption in the
    making of the award, violation of Section 75 or Section 81 of the
    83

    Act, contravention of the fundamental policy of Indian law, and
    conflict with the most basic notions of justice or morality.
    Additionally, sub-section (2-A) has been inserted in Section 34,
    which provides that in case of domestic arbitrations, violation of
    Indian public policy also includes patent illegality appearing on
    the face of the award. The proviso to the same states that an
    award shall not be set aside merely on the ground of an
    erroneous application of the law or by reappreciation of
    evidence.”

    90. The award does not shock the conscience of the Court. It conforms to

    the most basic notion of justice. The relevant portions of Ssangyong

    Engineering and Construction Company Limited vs National Highways

    Authority of India (NHAI) (supra), are quoted below :-

    “76. However, when it comes to the public policy of India,
    argument based upon “most basic notions of justice”, it is clear
    that this ground can be attracted only in very exceptional
    circumstances when the conscience of the Court is shocked by
    infraction of fundamental notions or principles of justice. It can
    be seen that the formula that was applied by the agreement
    continued to be applied till February 2013 — in short, it is not
    correct to say that the formula under the agreement could not be
    applied in view of the Ministry’s change in the base indices from
    1993-1994 to 2004-2005. Further, in order to apply a linking
    factor, a Circular, unilaterally issued by one party, cannot
    possibly bind the other party to the agreement without that other
    party’s consent. Indeed, the Circular itself expressly stipulates
    that it cannot apply unless the contractors furnish an
    undertaking/affidavit that the price adjustment under the
    Circular is acceptable to them. We have seen how the appellant
    gave such undertaking only conditionally and without prejudice
    to its argument that the Circular does not and cannot apply. This
    being the case, it is clear that the majority award has created a
    new contract for the parties by applying the said unilateral
    Circular and by substituting a workable formula under the
    agreement by another formula dehors the agreement. This being
    the case, a fundamental principle of justice has been breached,
    namely, that a unilateral addition or alteration of a contract can
    never be foisted upon an unwilling party, nor can a party to the
    agreement be liable to perform a bargain not entered into with
    the other party. Clearly, such a course of conduct would be
    84

    contrary to fundamental principles of justice as followed in this
    country, and shocks the conscience of this Court. However, we
    repeat that this ground is available only in very exceptional
    circumstances, such as the fact situation in the present case.
    Under no circumstance can any court interfere with an arbitral
    award on the ground that justice has not been done in the
    opinion of the Court. That would be an entry into the merits of
    the dispute which, as we have seen, is contrary to the ethos of
    Section 34 of the 1996 Act, as has been noted earlier in this
    judgment.”

    91. The relevant portions of Patel Engineering Limited vs. North

    Eastern Electric Power Corporation Ltd. reported in (2020) 7 SCC 167

    are quoted below :-

    “26. In MMTC [MMTC Ltd. v. Vedanta Ltd., (2019) 4 SCC 163 :

    (2019) 2 SCC (Civ) 293] , this Court took note of various decisions
    including that in Associate Builders [Associate Builders v. DDA,
    (2015) 3 SCC 49 : (2015) 2 SCC (Civ) 204] and exposited on the
    limited scope of interference under Section 34 and further
    narrower scope of appeal under Section 37 of the 1996 Act,
    particularly when dealing with the concurrent findings (of the
    arbitrator and then of the Court).
    This Court, inter alia, held as
    under : (MMTC case [MMTC Ltd. v. Vedanta Ltd., (2019) 4 SCC 163
    : (2019) 2 SCC (Civ) 293] , SCC pp. 166-67, paras 11-14)
    “11. As far as Section 34 is concerned, the position is well-

    settled by now that the Court does not sit in appeal over the
    arbitral award and may interfere on merits on the limited
    ground provided under Section 34(2)(b)(ii) i.e. if the award is
    against the public policy of India. As per the legal position
    clarified through decisions of this Court prior to the
    amendments to the 1996 Act in 2015, a violation of Indian
    public policy, in turn, includes a violation of the fundamental
    policy of Indian law, a violation of the interest of India, conflict
    with justice or morality, and the existence of patent illegality in
    the arbitral award. Additionally, the concept of the
    “fundamental policy of Indian law” would cover compliance with
    statutes and judicial precedents, adopting a judicial approach,
    compliance with the principles of natural justice,
    and Wednesbury [Associated Provincial Picture
    Houses v. Wednesbury Corpn., (1948) 1 KB 223 (CA)]
    reasonableness. Furthermore, “patent illegality” itself has been
    held to mean contravention of the substantive law of India,
    85

    contravention of the 1996 Act, and contravention of the terms of
    the contract.

    12. It is only if one of these conditions is met that the Court
    may interfere with an arbitral award in terms of Section
    34(2)(b)(ii)
    , but such interference does not entail a review of the
    merits of the dispute, and is limited to situations where the
    findings of the arbitrator are arbitrary, capricious or perverse, or
    when the conscience of the Court is shocked, or when the
    illegality is not trivial but goes to the root of the matter. An
    arbitral award may not be interfered with if the view taken by
    the arbitrator is a possible view based on facts. (See Associate
    Builders v. DDA [Associate Builders
    v. DDA, (2015) 3 SCC 49 :

    (2015) 2 SCC (Civ) 204] Also see ONGC Ltd. v. Saw Pipes
    Ltd. [ONGC Ltd.
    v. Saw Pipes Ltd., (2003) 5 SCC 705]
    ; Hindustan Zinc Ltd. v. Friends Coal Carbonisation [Hindustan
    Zinc Ltd.
    v. Friends Coal Carbonisation, (2006) 4 SCC 445] ;

    and McDermott International Inc. v. Burn Standard Co.
    Ltd. [McDermott International Inc.
    v. Burn Standard Co. Ltd.,
    (2006) 11 SCC 181] )

    13. It is relevant to note that after the 2015 Amendment to
    Section 34, the above position stands somewhat modified.
    Pursuant to the insertion of Explanation 1 to Section 34(2), the
    scope of contravention of Indian public policy has been modified
    to the extent that it now means fraud or corruption in the
    making of the award, violation of Section 75 or Section 81 of the
    Act, contravention of the fundamental policy of Indian law, and
    conflict with the most basic notions of justice or morality.
    Additionally, sub-section (2-A) has been inserted in Section 34,
    which provides that in case of domestic arbitrations, violation of
    Indian public policy also includes patent illegality appearing on
    the face of the award. The proviso to the same states that an
    award shall not be set aside merely on the ground of an
    erroneous application of the law or by reappreciation of
    evidence.

    14. As far as interference with an order made under Section 34,
    as per Section 37, is concerned, it cannot be disputed that such
    interference under Section 37 cannot travel beyond the
    restrictions laid down under Section 34. In other words, the
    Court cannot undertake an independent assessment of the
    merits of the award, and must only ascertain that the exercise
    of power by the Court under Section 34 has not exceeded the
    scope of the provision. Thus, it is evident that in case an
    arbitral award has been confirmed by the Court under Section
    34
    and by the Court in an appeal under Section 37, this Court
    must be extremely cautious and slow to disturb such
    concurrent findings.”

    86

    27. In Ssangyong Engg. [Ssangyong Engg. & Construction Co.
    Ltd. v. NHAI
    , (2019) 15 SCC 131 : (2020) 2 SCC (Civ) 213] , this
    Court has set out the scope of challenge under Section 34 of the
    1996 Act in further details in the following words : (SCC pp. 170-
    71, paras 37-41)
    “37. Insofar as domestic awards made in India are concerned,
    an additional ground is now available under sub-section (2-A),
    added by the Amendment Act, 2015, to Section 34. Here, there
    must be patent illegality appearing on the face of the award,
    which refers to such illegality as goes to the root of the matter
    but which does not amount to mere erroneous application of the
    law. In short, what is not subsumed within “the fundamental
    policy of Indian law”, namely, the contravention of a statute not
    linked to public policy or public interest, cannot be brought in
    by the backdoor when it comes to setting aside an award on the
    ground of patent illegality.

    38. Secondly, it is also made clear that reappreciation of
    evidence, which is what an appellate court is permitted to do,
    cannot be permitted under the ground of patent illegality
    appearing on the face of the award.

    39. To elucidate, para 42.1 of Associate Builders [Associate
    Builders v. DDA
    , (2015) 3 SCC 49 : (2015) 2 SCC (Civ) 204] ,
    namely, a mere contravention of the substantive law of India, by
    itself, is no longer a ground available to set aside an arbitral
    award.
    Para 42.2 of Associate Builders [Associate
    Builders v. DDA
    , (2015) 3 SCC 49 : (2015) 2 SCC (Civ) 204] ,
    however, would remain, for if an arbitrator gives no reasons for
    an award and contravenes Section 31(3) of the 1996 Act, that
    would certainly amount to a patent illegality on the face of the
    award.

    40. The change made in Section 28(3) by the Amendment Act
    really follows what is stated in paras 42.3 to 45 in Associate
    Builders [Associate Builders v. DDA
    , (2015) 3 SCC 49 : (2015) 2
    SCC (Civ) 204] , namely, that the construction of the terms of a
    contract is primarily for an arbitrator to decide, unless the
    arbitrator construes the contract in a manner that no fair-
    minded or reasonable person would; in short, that the
    arbitrator’s view is not even a possible view to take. Also, if the
    arbitrator wanders outside the contract and deals with matters
    not allotted to him, he commits an error of jurisdiction. This
    ground of challenge will now fall within the new ground added
    under Section 34(2-A).

    41. What is important to note is that a decision which is
    perverse, as understood in paras 31 and 32 of Associate
    Builders [Associate Builders v. DDA
    , (2015) 3 SCC 49 : (2015) 2
    SCC (Civ) 204] , while no longer being a ground for challenge
    under “public policy of India”, would certainly amount to a
    87

    patent illegality appearing on the face of the award. Thus, a
    finding based on no evidence at all or an award which ignores
    vital evidence in arriving at its decision would be perverse and
    liable to be set aside on the ground of patent illegality.
    Additionally, a finding based on documents taken behind the
    back of the parties by the arbitrator would also qualify as a
    decision based on no evidence inasmuch as such decision is not
    based on evidence led by the parties, and therefore, would also
    have to be characterised as perverse.”

    28. The limited scope of challenge under Section 34 of the Act was
    once again highlighted by this Court in PSA Sical Terminals [PSA
    Sical Terminals (P) Ltd. v. V.O. Chidambranar Port Trust
    , (2023) 15
    SCC 781 : 2021 SCC OnLine SC 508] and this Court particularly
    explained the relevant tests as under : (SCC paras 40 to 42)
    “40. It will thus appear to be a more than settled legal position,
    that in an application under Section 34, the Court is not
    expected to act as an appellate court and reappreciate the
    evidence. The scope of interference would be limited to grounds
    provided under Section 34 of the Arbitration Act. The
    interference would be so warranted when the award is in
    violation of “public policy of India”, which has been held to
    mean “the fundamental policy of Indian law”. A judicial
    intervention on account of interfering on the merits of the award
    would not be permissible. However, the principles of natural
    justice as contained in Sections 18 and 34(2)(a)(iii) of the
    Arbitration Act would continue to be the grounds of challenge of
    an award. The ground for interference on the basis that the
    award is in conflict with justice or morality is now to be
    understood as a conflict with the “most basic notions of morality
    or justice”. It is only such arbitral awards that shock the
    conscience of the Court, that can be set aside on the said
    ground. An award would be set aside on the ground of patent
    illegality appearing on the face of the award and as such, which
    goes to the roots of the matter. However, an illegality with
    regard to a mere erroneous application of law would not be a
    ground for interference. Equally, reappreciation of evidence
    would not be permissible on the ground of patent illegality
    appearing on the face of the award.

    41. A decision which is perverse, though would not be a ground
    for challenge under “public policy of India”, would certainly
    amount to a patent illegality appearing on the face of the award.
    However, a finding based on no evidence at all or an award
    which ignores vital evidence in arriving at its decision would be
    perverse and liable to be set aside on the ground of patent
    illegality.

    42. To understand the test of perversity, it will also be
    appropriate to refer to paras 31 and 32 from the judgment of
    88

    this Court in Associate Builders [Associate Builders v. DDA,
    (2015) 3 SCC 49 : (2015) 2 SCC (Civ) 204] , which read thus :

    (SCC pp. 75-76)
    ’31. The third juristic principle is that a decision which is
    perverse or so irrational that no reasonable person would
    have arrived at the same is important and requires some
    degree of explanation. It is settled law that where:

    (i) a finding is based on no evidence, or

    (ii) an Arbitral Tribunal takes into account something
    irrelevant to the decision which it arrives at; or

    (iii) ignores vital evidence in arriving at its decision,
    such decision would necessarily be perverse.

    32. A good working test of perversity is contained in two
    judgments. In CCE & Sales v. Gopi Nath & Sons [CCE &
    Sales
    v. Gopi Nath & Sons, 1992 Supp (2) SCC 312] , it was held
    : (SCC p. 317, para 7)
    “7. … It is, no doubt, true that if a finding of fact is arrived at
    by ignoring or excluding relevant material or by taking into
    consideration irrelevant material or if the finding so
    outrageously defies logic as to suffer from the vice of
    irrationality incurring the blame of being perverse, then, the
    finding is rendered infirm in law.” ‘ “

    92. The decision cited by the Learned Advocate General on Damodar

    Valley Corpn. v. K.K. Kar reported in (1974) 1 SCC 141 was on the

    principle that, when a contract is put to an end, the arbitration clause

    perishes along with it. This decision is no longer good law. In this regard,

    reference is made to the decision in Interplay between Arbitration

    Agreements under Arbitration and Conciliation Act 1996 and Stamp

    Act, 1899 reported in (2024) 6 SCC 1. The relevant portions of the same

    are quoted below :-

    “115. The separability presumption has undergone a significant
    evolution in India. Initially, the Indian courts viewed an
    arbitration agreement as an integral part of the underlying
    contract without any existence beyond such contract. For
    instance, in Union of India v. Kishorilal Gupta & Bros.
    [Union of
    India v. Kishorilal Gupta & Bros.
    , 1959 SCC OnLine SC 6] , the
    issue before this Court was whether an arbitration clause in the
    89

    original contract survived after the enactment of a subsequent
    contract. K. Subba Rao (as the learned Chief Justice then was)
    considered Heyman [Heyman v. Darwins Ltd., 1942 AC 356
    (HL)] but distinguished it on the ground that it only dealt with
    repudiation, where rights and obligations of parties survive the
    termination of contract. It was held that in situations where the
    original contract is superseded by a subsequent contract, the
    arbitration clause in the original contract will also cease to
    exist. K. Subba Rao, J., speaking for the majority, held
    that first, an arbitration clause is a collateral term of a contract
    as distinguished from its substantive terms, but nonetheless it
    is an integral part of it; second, the existence of the underlying
    contract is a necessary condition for the operation of an
    arbitration clause; third, if the underlying contract was non est
    in the sense that it never came legally into existence or was void
    ab initio, the arbitration clause also cannot operate; fourth, if
    the parties put an end to a validly executed contract and
    substitute it with a new contract, the arbitration clause of the
    original contract also perishes with it; and fifth, in situations
    such as repudiation, frustration, or breach of contract, only the
    performance of the contract comes to an end, the arbitration
    clause persists because the contract continues to exist for the
    purposes of disputes arising under it.

    116. In Damodar Valley Corpn. v. K.K. Kar [Damodar Valley
    Corpn.
    v. K.K. Kar, (1974) 1 SCC 141] , a two-Judge Bench of
    this Court held that the plea that a contract is void, illegal or
    fraudulent affects the entire contract along with the arbitration
    clause. However, the enactment of the Arbitration Act in 1996
    enabled the Indian Courts to give effect to the separability
    presumption with greater impetus.
    Section 16(1)(b), which
    provides that a decision by the Arbitral Tribunal that the
    contract is null and void shall not entail ipso jure the invalidity
    of the arbitration clause, renders the decisions in Kishorilal
    Gupta [Union of India v. Kishorilal Gupta & Bros., 1959 SCC
    OnLine SC 6] and Damodar Valley Corpn. [Damodar Valley
    Corpn. v. K.K. Kar
    , (1974) 1 SCC 141] redundant. Consequently,
    even if the underlying contract is declared null and void, it will
    not ipso jure result in the invalidity of the arbitration
    agreement.”

    93. Moreover, Section 16(1)(a) and 16(1)(b) of the A & C Act recognises the

    doctrine of separability and even if a contract is void, the arbitration clause

    survives and the Arbitrator retains the jurisdiction to proceed with the

    disputes arising out of such void contract. Thus, the argument of the
    90

    learned Advocate General that, when the contract itself did not subsist on

    account of the same being declared void, the disputes could not be further

    decided by the learned Arbitrator as the learned Arbitrator lost his

    jurisdiction to decide such disputes arising out of a void contract, is not

    supported by law.

    94. The steps laid down in Vidya Drolia and Ors. vs Durga Trading

    Corporation reported in (2021) 2 SCC 1, to determine whether the subject

    matter of a dispute was arbitrable or not, cannot be applied to the facts of

    this case, for the reasons already discussed hereinabove.

    95. Under such circumstances, AP-COM 171 of 2024 is dismissed without

    any interference with the award.

    96. AP-COM 172 of 2024 is accordingly disposed of, as per the

    observation made hereinabove.

    97. Urgent Photostat certified copies of this judgment, if applied for, be

    supplied to the parties upon fulfilment of requisite formalities.

    (Shampa Sarkar, J.)



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here