United India Insurance Company Limited vs Upl Limited on 22 April, 2026

    0
    39
    ADVERTISEMENT

    Bombay High Court

    United India Insurance Company Limited vs Upl Limited on 22 April, 2026

    2026:BHC-OS:10324
                 Neeta Sawant                                                                 CARBP-10809-2024
    
    
    
    
                                  IN THE HIGH COURT OF JUDICATURE AT BOMBAY
    
                                     ORDINARY ORIGINAL CIVIL JURISDICTION
    
                      COMMERCIAL ARBITRATION PETITION (L) NO. 10809 OF 2024
                                                        WITH
                                    INTERIM APPLICATION (L) NO. 11225 OF 2024
                                                        WITH
                                    INTERIM APPLICATION (L) NO. 11117 OF 2024
    
                 United India Insurance
                 Company Limited                                   ....PETITIONER/APPLICANT
    
                                VERSUS
    
                 UPL Limited                                                       .... RESPONDENT
    
    
    
                 Mr. Sharan Jagtiani, Senior Advocate with Ms. Surbhi Agarwal & Ms.
                 Netra Haldankar i/b Dhruve Liladhar & Co., for the Petitioner/ Applicant.
    
                 Mr. Shiraz Rustomjee, Senior Advocate with Ms. Shreya Parikh, Mr.
                 Archit Jayakar, Ms. Pooja Yadav, Mr. Mihir Kakade & Mr. Kshitij Abbhi i/b
                 Jayakar & Partners, for the Respondent.
    
    
    
                                                             CORAM : SANDEEP V. MARNE, J.
    
                                                             Reserved On : 1 April, 2026.
    
                                                             Pronounced On: 22 April 2026.
    
                 Judgment :
    
    
                 1)                 When a Gas Turbine Engine is damaged due to an accident
                 and the insured is required to get the Engine overhauled and raises a
                 claim towards the overhauling expenses and the insurer sanctions only
                 the expenses for accidental repairs, whether the dispute relating to non-
                 _____________________________________________________________________________
    
                                                       PAGE NO. 1 OF 77
    
                                                         22 April 2026
    
    
    
    
                        ::: Uploaded on - 23/04/2026                      ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                 CARBP-10809-2024
    
    
    
    
    payment of balance claim is a dispute of 'quantum' or dispute of 'liability'
    is the issue that this Court is tasked upon to decide in the present
    Petition. To paraphrase, whether it is permissible for the insurer to
    segregate the claim in respect of the damage to the Engine into 'repairs
    claim' and 'overhaul claim' and take a stand that mere payment for the
    former claim does not amount to acceptance of liability in respect of the
    latter claim, making the latter claim non-arbitrable? The issue arises in
    the light of typical clause in the Insurance Policy providing for arbitration
    only in respect of disputes involving quantum and not in respect of those
    for which the liability is not expressly admitted.
    
    
    2)                Petitioner-Insurance Company has filed the present petition
    under Section 34 of the Arbitration and Conciliation Act, 1996
    (Arbitration Act) challenging the arbitral Award dated 8 December 2023
    passed by the learned sole Arbitrator. The Tribunal has treated the claim
    of the Respondent as a single indivisible claim and has held that since the
    claim is partially awarded, the dispute relates to 'quantum' and not to
    'liability'. The Tribunal has further held that the accident was the
    proximate cause of overhauling of the Gas Turbine Engine. By the
    impugned Award, the Tribunal has awarded a sum of Rs.41,98,12,970/- in
    favour of the Respondent along with simple interest @ 12% p.a. on the
    entire awarded amount from the date of the award. The Tribunal has also
    awarded costs of arbitration of Rs. 2 crores in favour of the Respondent.
    
    
    3)                This is the second round of arbitration after the previous
    award by the Three Member Arbitral Tribunal was set aside by this Court.
    
    _____________________________________________________________________________
    
                                          PAGE NO. 2 OF 77
    
                                            22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                      ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                 CARBP-10809-2024
    
    
    
    
    FACTS
    
    
    4)                Petitioner is a public limited and nationalised general
    insurance company incorporated in the year 1938 under the Companies
    Act, 1913. Respondent, who was previously known as United Phosphorus
    Limited, is a Public Limited Company incorporated in the year 1985 and is
    engaged in the business of agrochemicals such as pesticides. Respondent
    is also a successor in interest of its erstwhile subsidiary of Search Chem
    Industries Ltd. (SCIL) which has merged into the Respondent.
    
    
    5)                On 22 February 2001, SCIL purchased Industrial All Risk
    Policy to insure its Captive Power Plant which was installed by the
    Respondent in its factory at Jhagadia, Gujarat. The Power Plant used a Gas
    Turbine Engine              bearing No. 185-195         (GT   Engine) which was
    manufactured by GE Packard Power Inc. (GE). The policy was valid from
    22 February 2001 to 21 February 2002 and covered (i) material damage
    with the sum insured of Rs.156,00,00,000/- and (ii) business interruption
    with the sum insured of Rs.11,71,31,000/-
    
    
    6)                The Industrial All Risk Policy included exclusion causes
    under which the policy did not cover damage to the property incurred by
    latent defect, gradual deterioration, distortion or wear and tear. The
    policy also did not include coverage in respect of the damage caused
    inter-alia by corrosion, rusting, etc. Clause 12 of the insurance policy
    included agreement for arbitration in respect of the disputes relating to
    quantum to be paid under the policy where the liability is otherwise
    admitted. However, where the company disputed or not accepted the
    _____________________________________________________________________________
    
                                          PAGE NO. 3 OF 77
    
                                            22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                      ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                 CARBP-10809-2024
    
    
    
    
    liability under or in respect of the policy, the disputes were not agreed to
    be referred to arbitration.
    
    
    7)                In April 2001, there was an oil leakage in the hot section area
    of the GT Engine which was decommissioned and sent for repairs. The
    problem was found in the 4B bearing and a new 4B bearing was installed
    whereafter the GT Engine was reinstalled sometime in June 2001 and
    commissioned. Those repairs were carried out at the Air India Workshop.
    The Petitioner honored the claims for such repairs. On 15 September
    2001, the GT Engine started to have issues. A metal chip detector
    installed in the Oil Sump-B showed a fluctuating resistance reading
    between 160 to 300 ohms as against the normal level of 500 ohms. The
    fluctuations continued for about an hour before the resistance returned to
    the optimum levels. At around 10.49 a.m., on 16 September 2001, the
    metal chip detector sounded an alarm and again fluctuations were noticed
    in the resistance. Another alarm was sounded at 12.20 a.m. on the same
    day whereafter the GT Engine tripped for about 16 seconds. A Borescope
    Inspection of the GT Engine was carried out on 16 September 2001 by
    General Electric Energy Plant Operations LLP, (GEEPO) a subsidiary of GE
    and operation and maintenance contractor of the Respondent, which
    showed that the Sump-B was not in good order and the 4B bearing cage
    was broken. Upon being informed about the incident, Petitioner
    appointed Bhatawedekar & Co. and Mehta & Padamsey Pvt. Ltd. as its
    joint surveyors.
    
    
    
    
    _____________________________________________________________________________
    
                                          PAGE NO. 4 OF 77
    
                                            22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                      ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                 CARBP-10809-2024
    
    
    
    
    8)                On the basis of borescope inspection and in consultation
    with GEEPO, the Petitioner decided to send the GT Engine to
    manufacturer's facility at Houston, Texas USA. On 16 October 2001, the
    GT Engine reached GE facility for inspection. On 19 October 2001 and 22
    October 2001, GE issued reports. According to the Petitioner, the issues
    reported by GE included observations of corrosion, discoloration, reddish
    yellow rust, etc in diverse components of the GT Engine over and above
    the Sump-B. On 30 October 2001, the GE recommended that the GT
    Engine be overhauled. Petitioner appointed M/s. McLarens Toplis as its
    surveyors in the USA. The US Surveyors informed the Petitioner of GE's
    recommendations for complete overhaul of the GT Engine.
    
    
    9)                In the above backdrop, the Petitioner issued letters dated 5
    December 2001 and 18 December 2001 to the Respondent recommending
    complete overhaul of the GT Engine. In the letter dated 18 December
    2001, Petitioners communicated that if the GT Engine was not overhauled
    as recommended by GE, future claims were eminent which would cause
    problem at the time of underwriting of the risk.
    
    
    
    
    10)               On 6/7 December 2001, the GT Engine was reassembled and
    taken for testing after the GE completed limited repairs to Sump-B.
    During testing, it was found that the GT Engine was still not working
    properly and heavy vibrations were noticed. GE recommended 3 options
    to the Respondent, (i) attend only rotating parts of the High Pressure
    Compressor (HPC) and High Pressure Turbine (HPT), (ii) attend to the
    
    _____________________________________________________________________________
    
                                          PAGE NO. 5 OF 77
    
                                            22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                      ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                 CARBP-10809-2024
    
    
    
    
    repairs of the stator and rotors of both HPC and HPT, (iii) HPC, HPT, LPC
    and LPT and all assemblers should be inspected and repaired by
    completing the overhaul of the GT Engine. On 24 December 2001,
    Respondent wrote to the Petitioner conveying its intention to go for
    complete overhauling of the GT Engine. On 27 December 2001, Petitioner
    clarified to the Respondent that the overhauling costs would not fall
    within the purview of the policy and that Petitioner's liability would only
    extend to the actual damage directly caused to the GT Engine by the
    incident. The Respondent communicated its intention to go ahead with
    complete overhaul of the GT Engine by letter dated 28 December 2001. In
    response, Petitioner issued a letter on 25 January 2002 reiterating that the
    expenses claimed towards costs of overhauling were not payable.
    Respondent once again stated that they would be claiming costs of
    overhauling and repairs from the Petitioner vide letter dated 4 February
    2002. On 17 February 2002, Respondent wrote to the joint surveyors
    enclosing its claim bill towards material damage in the sum of
    Rs.24,02,15,358/-. On 26 March 2002, the GT Engine was successfully
    tested post the completion of repairs. The US surveyors issued its survey
    report on 23 April 2002 regarding GT Engine and the repairs carried out.
    On 30 April 2002, Respondent purchased another storage and erection
    policy from the Petitioner for erection of the GT Engine in its captive
    power plant at Gujarat by paying premium of Rs.11,58,697/-
    
    
    11)               On 10 May 2002, the joint surveyors issued their first interim
    report. In May/June 2002, the GT Engine was dispatched from Houston,
    Texas and it resumed its normal functioning at Respondent's captive
    
    _____________________________________________________________________________
    
                                          PAGE NO. 6 OF 77
    
                                            22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                      ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                        CARBP-10809-2024
    
    
    
    
    power plant on 13 June 2002. On 25 July 2002, Respondent revised its
    claim          bill    for   material    damage      by       reducing     the      same      from
    Rs.24,02,15,358/- to Rs.16,71,61,286/-. It also raised its claim bill for
    business interruption loss for sum of Rs.5,27,83,000/-. On 1 February
    2003, second interim report and final survey report was issued by the joint
    surveyors.            The    joint    surveyors   assessed       Respondent's          claim      by
    considering the business interruption loss and material damage
    attributable only to the damage arising out of the incident and not in the
    context of the overhaul claim. According to the joint surveyors, the
    breakdown was caused as a result of the incident which necessitated
    repairs to Sump-B and repairs that would have corrected transient
    vibrations noticed during the testing on 6/7 December 2001. On 20 March
    2003, Respondent submitted a revised claim bill for loss of profit in the
    sum of Rs.8,23,08,525/- based on the audited balance sheet and gross
    profit ratio on the basis of the trend of Naphtha price.
    
    
    12)                   On 18 December 2003, Petitioner sent the Settlement
    Intimation Voucher (SIV) to the Respondent by which Petitioner offered
    to pay total of Rs.7,69,69,369/- as full and final discharge of Respondent's
    claim falling within the policy. The amount included Rs.5,01,41,230/-
    towards material damage and Rs.2,68,28,139/- towards loss of business
    profits. Petitioner accepted the voucher under protest on 19 December
    2003. Petitioner accordingly issued cheque of Rs.7,69,69,369/- to the
    Respondent on 29 December 2003.
    
    
    13)                   Thus disputes and differences arose between the Petitioner
    and Respondent over the balance amount of Respondent's claim.
    _____________________________________________________________________________
    
                                                PAGE NO. 7 OF 77
    
                                                  22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                             ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                 CARBP-10809-2024
    
    
    
    
    Respondent accordingly initiated arbitration on the basis of arbitration
    agreement set out at Clause 12 of the policy. The disputes and difference
    were referred to arbitration before the Three Member Arbitral Tribunal.
    On 14 September 2012, the Arbitral Tribunal delivered award which was
    not unanimous. The majority award dismissed Respondent's claim on the
    ground that amount of Rs.7,69,69,369/- was accepted by the Respondent
    in full and final satisfaction of its claim and that such acceptance
    amounted to a complete discharge. It was also held that Petitioner was
    not liable to pay overhaul costs and was liable to pay only for the damage
    caused by the incident. In a separate minority award, Respondent was
    held entitled to entire balance amount of Rs. 17,03,49,393/-
    
    
    14)               The majority award was challenged by the Respondent before
    this Court under Section 34 of the Arbitration Act. This Court set aside
    the majority award by order dated 15 February 2019 holding inter-alia that
    the conclusion of Arbitral Tribunal about acceptance of Rs.7,69,69,369/-
    amounting to complete discharge was contrary to the admitted records of
    the case and was an impossible view. The majority award was also set
    aside on the ground that it did not discuss the extensive evidence led on
    merits by the Petitioner and the Respondent.
    
    
    15)               Upon setting aside of the majority award in the first
    arbitration, Respondents once again invoked arbitration on 28 January
    2020. Parties jointly appointed learned sole Arbitrator (Mr. Justice R.M.
    Lodha, former Chief Justice of India) and Arbitral Tribunal was thus
    constituted on 5 February 2020. Respondent filed its Statement Of Claim
    before the Tribunal on 30 June 2020 claiming Rs. 69,52,41,839/- with
    _____________________________________________________________________________
    
                                          PAGE NO. 8 OF 77
    
                                            22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                      ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                 CARBP-10809-2024
    
    
    
    
    interest as well as costs of first round of arbitration. Petitioner filed
    application under Section 16 of the Arbitration Act contending that
    determination of issue of Petitioner's liability to pay for overhauling costs
    was not arbitrable since the same did not concern quantum under Section
    12 of the policy and contended that Respondent's acceptance of
    Rs.7,69,69,369/- amounted to complete accord and satisfaction. The
    Arbitral Tribunal however deferred adjudication of Section 16 application
    and directed the same to be heard after leading of evidence by the parties.
    Section 16 application was thus heard at the final hearing stage.
    
    
    16)               At the end of the arbitral proceedings, the Tribunal has
    passed final Award dated 8 December 2023 holding inter-alia that the
    disputes in the subject arbitration pertained only to quantum and not to
    liability. The Tribunal has rejected Petitioner's objections and has partly
    allowed Respondent's claim including the claim towards business
    interruption losses and awarded total sum of Rs.43,98,12,970/- which
    includes an amount of Rs.41,98,12,970/- towards claim and Rs.2 crores
    towards costs. The Tribunal has also granted post award interest @ 12%
    p.a. from the date of the award.
    
    
    17)               Aggrieved by the Award dated 8 December 2023, the
    Petitioner has filed the present petition under Section 34 of the
    Arbitration Act. By order dated 5 February 2025, this Court permitted the
    Petitioner to deposit the awarded amount along with interest upto 5
    February 2023 and subject to deposit being made, execution of the Award
    was stayed. Accordingly, the Petitioner has deposited an amount of Rs.
    50,14,10,885/- on 5 March 2025. There is delay of 19 days in filing the
    _____________________________________________________________________________
    
                                          PAGE NO. 9 OF 77
    
                                            22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                      ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                  CARBP-10809-2024
    
    
    
    
    present Petition, for condonation of which Petitioner has filed I.A.(L) No.
    11117 of 2024. Considering the averments in the interim application and
    the length of delay, in my view same deserves to be condoned. The delay
    is accordingly condoned.
    
    
    18)               With the consent of the learned counsel appearing for
    parties, the petition is taken up for final hearing. Accordingly, I have
    heard extensive submissions canvassed by the learned counsel appearing
    for the parties.
    
    
    SUBMISSIONS
    
    
    19)               Mr. Jagtiani the learned Senior Advocate appearing for
    Petitioner would submit that the impugned award distorts the arbitration
    agreement contained in Clause 12 of the policy to hold that the dispute
    between the parties pertained only to quantum and was therefore
    arbitrable. That Clause 12 confines arbitration to cases only where there is
    difference as to quantum to be paid under the policy and where the
    liability is otherwise admitted. That both conditions must be cumulatively
    satisfied. That second part of Clause 12 reinforces this by providing that
    no difference or dispute shall be referable to arbitration if the insurer has
    disputed or not accepted liability under or in respect of the policy. That
    the fundamental interpretation of arbitration agreement is that there has
    to be admission of liability and that the dispute cannot be submitted to
    arbitration if the liability has been disputed or not accepted under the
    policy. That this aspect is completely ignored by the Arbitral Tribunal and
    
    
    _____________________________________________________________________________
    
                                          PAGE NO. 10 OF 77
    
                                            22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                       ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                  CARBP-10809-2024
    
    
    
    
    the standard which has been applied by the Tribunal is that Petitioner's
    absence of repudiation or denial of liability renders the dispute arbitrable.
    
    
    20)               Mr. Jagtiani further submits that award relies on letters dated
    5 and 18 December 2001 regarding overhauling of GT Engine without
    appreciating that nothing in those letters amounted to admission or
    acceptance of liability of overhauling costs. Those letters were issued
    prior to raising of any claim for overhauling of GT Engine and were issued
    at the time when Respondent's own decision was to undertake limited
    repairs to address the incident dated 16 September 2001. That Petitioner
    denied liability to pay overhauling by letters 27 December 2001 and 25
    January 2002. That once the liability for overhauling claim was denied,
    the dispute ceased to be the one of mere quantum for it to be arbitrable.
    He relies on judgment of English Court in New Hampshire Insurance
    Company Versus. Strabag Bau AG 1. That Respondent's argument to
    negate letters dated 27 December 2001 and 25 January 2002 that they
    have been issued before raising of claim is completely incorrect as
    Respondent in its letter dated 24 December 2001 had clearly referred to a
    "claim". That mere absence of claim bill at that stage was irrelevant since
    there was a claim in the form of Respondent's letter dated 27 December
    2001. That itemization of overhauling cost of GT Engine in letter dated 24
    December 2001 is identical to claim bill dated 17 February 2002. That
    therefore Arbitral Tribunal's finding that Respondent's claim was not
    repudiated is patently erroneous and perverse.
    
    
    
    
    1      1990 ILPR 334
    _____________________________________________________________________________
    
                                          PAGE NO. 11 OF 77
    
                                            22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                       ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                  CARBP-10809-2024
    
    
    
    
    21)               Mr. Jagtiani further submits that the Petitioner itself
    maintained a clear distinction between incident claim and overhauling
    claim. That GE's letter dated 15 January 2002 to the Respondent uses the
    term 'rebuild the engine' signifying overhauling. That from Petitioner's
    standpoint, incident claim and overhaul claim arose from distinct legal
    obligations, one that was admitted and another that was not. The
    payment under settlement intimation voucher is of only that part of claim
    for which liability was always accepted. For the remaining, the liability for
    overhaul claim was expressly denied.
    
    
    22)               Mr. Jagtiani further submits that liability is a legal obligation
    and under the policy, the claims may involve distinct legal obligations.
    That insurer may treat them distinctly either because of time at which
    they arise or separate coverage for equipment or nature of claim being
    only partly covered. That in each case where there was no admission or
    acceptance of liability, the claim was not arbitrable in respect of that part.
    
    
    23)               Mr. Jagtiani further submits that the award suffers from
    another legal perversity as it draws wholly unsustainable conclusion from
    the two interim survey reports by the joint surveyors to suggest that
    Respondent's claim was admissible under the policy as a singular claim
    arising out of the incident. That none of the two reports give any
    suggestion of admissibility of Respondent's claim arising out of the
    incident. He takes me through both the interim reports in support of his
    contention that the survey assessment was limited by surveyors only to
    
    
    
    _____________________________________________________________________________
    
                                          PAGE NO. 12 OF 77
    
                                            22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                       ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                    CARBP-10809-2024
    
    
    
    
    Option 1 and that therefore admissibility was in respect of the claim
    covered by Option 1 only.
    
    
    24)                Mr. Jagtiani further submits that while interpreting similar
    arbitration clause, Courts have repeatedly held that an insurer can always
    reject liability in respect of part of the claim and that mere sanction of
    part of claim does not mean that there is dispute relating to quantum in
    respect of that part for which liability itself is disputed. In support of his
    contention, he relies on following judgments:
    
    
    1) United India Insurance Company Limited and Another Versus.
    Hyundai Engineering And Construction Company Limited And Others 2
    2) Oriental Insurance Company Limited Versus. Narbheram Power And
    Steel Private Limited 3
    3) The Vulcan Insurance co. Ltd. Versus. Maharaj Singh and Another4
    4) M/s. Mallak Specialties Pvt. Ltd. Versus. The New India Assurance
    Co. Ltd.       5
    
    
    
    5) Sanghi Industries Ltd. Versus. United India Insurance Company
    Limited6
    6) Kohinoor Steel Pvt. Ltd. Versus. Bajaj Allianz Insurance Company 7
    7) Metal Crafts Engineering Pvt. Ltd. Versus. National Insurance
    Company Limited and another 8
    8) New India Assurance Co. Ltd. Versus. M/s. Ampoules and Vails
    Manufacturing Co. Ltd. 9
    9) Ec Wheels India Private Limited Versus. Shriram General Insurance
    Company Limited 10
    
    2 2018 17 SCC 607
    3  2018 6 SCC 534
    4  1976 1 SCC 943
    5  CARAP No. 65 Of 2022 decided on 30 November 2022
    6  2013 SCC Online Guj 5732
    7  2011 SCC Online Cal 3252
    8  2011 SCC Online Cal 1929
    9  2018 SCC Online Bom 5845
    10 2025 SCC Online Cal 4267
    _____________________________________________________________________________
    
                                            PAGE NO. 13 OF 77
    
                                              22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                         ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                  CARBP-10809-2024
    
    
    
    
    10) D.C. Bars Limited and another Versus. QIC Europe limited 11
    
    
    25)               About merits of the award, Mr. Jagtiani submits that there is
    perversity in findings of the Arbitral Tribunal while holding that accident
    was proximate cause for overhauling of GT Engine. That Arbitral Tribunal
    has conflated two distinct issues of excluded causes and the accident
    being the proximate cause of overhauling. That the finding on one issue
    cannot support the findings on the other. That excluded causes would
    entail that the claim is not covered by the policy at all. That even if it is
    assumed arguendo that the claim falls outside the excluded causes, the
    Tribunal was required to record clear and independent findings for
    holding that the accident was the proximate cause for overhauling. That
    on the issue of proximate cause, the Tribunal has merely recorded a vague
    finding in para 153 of award about availability of ample material on record
    including various letters/communication of GE, McLarens Toplis and the
    letters of the Respondent. However, none of the said material indicates
    accident as proximate cause of overhauling of the GT Engine. The
    Tribunal itself has not identified letters/reports or communications which
    purportedly establish the incident as the proximate cause for overhauling.
    That this finding is completely perverse. Mr. Jagtiani takes me through
    letters and communications of GE, McLarens Toplis report as well as
    letters of Respondent to demonstrate that none of them state, in any
    manner, that the accident was proximate cause of overhauling.                              He
    submits that the ratio of the judgment of the Apex Court in OPG Power
    Generations Private Limited Versus. Enexio Power Solution India
    
    
    11    2023 EWHC 245 COMM
    _____________________________________________________________________________
    
                                          PAGE NO. 14 OF 77
    
                                            22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                       ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                     CARBP-10809-2024
    
    
    
    
    Private Limited 12 cannot be invoked in the present case for upholding an
    unreasoned award. That new documents referred to by Respondent during
    final hearing of petition cannot be relied upon to fill any gaps of
    Respondent's case by misapplying the ratio of the judgment in OPG
    Power Generations Private Limited. That on the contrary, the
    contemporaneous documents and reports consistently establish that
    overhauling was not carried out on account of the incident.
    
    
    26)               Mr.      Jagtiani   further   submits       that      Tribunal        applied
    inconsistent evidentiary standards while dealing with GE documents.
    That it has disregarded GE Reports suggesting rust, corrosion, oxidation,
    wear and tear and other pre-existing conditions on the ground of
    Petitioner not leading oral evidence of GE personnel. However, on the
    other hand, the Tribunal relies on various letters/communications of GE
    to conclude that the incident was proximate cause of overhauling.
    
    
    27)               Mr. Jagtiani submits that Respondent's reliance of judgment
    of the Apex Court in SBI General Insurance Company Limited Versus
    Krish Spinning 13 is misplaced as the same is rendered in the context of
    limited jurisdiction of Court under Section 11 of the Arbitration Act. That
    the same is the case with various other judgments relied upon by the
    Respondent. That in none of the judgments cited by the Respondent, the
    insurer had expressly repudiated or denied its liability for a particular
    claim as is done in the present case. Mr. Jagtiani concludes by submitting
    
    
    12     2025 2 SCC 417
    
    13  Civil Appeal No. 7821 of 2024 decided on 18 July 2024.
    _____________________________________________________________________________
    
                                             PAGE NO. 15 OF 77
    
                                               22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                          ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                  CARBP-10809-2024
    
    
    
    
    that Petitioner's clear and consistent denial of liability for overhaul claim
    takes the dispute outside the scope of arbitration agreement rendering
    the award patently illegal and perverse and not a plausible view. That the
    award is woefully short of reasons, ignores vital evidence and misapplies
    the arbitration agreement. He prays for setting aside the award.
    
    
    28)               Mr. Rustomjee, the learned Senior Advocate appearing for
    the Respondent submits that no interference is warranted in the
    impugned award in limited scope for interference under Section 34 of the
    Arbitration Act. That interpretation of contract and evaluation of
    evidence falls within the purview of the Arbitral Tribunal. That Court
    cannot re-evaluate evidence or substitute its own interpretation of
    contract merely because another interpretation is preferable. That the
    Petitioner has urged this Court to re-examine and re-evaluate the
    evidence with a view to arrive at a different conclusion, which is
    impermissible. That the view taken by the arbitrator is not egregious or
    perverse to such an extent that no reasonable person could ever take the
    same. That the mandate under Section 34 is to respect the finality of the
    arbitral award. He relies on judgments of the Apex Court in Ssangyong
    Engineering and Construction Company Limited Versus National
    Highways Authority of India (NHAI) 14, Prakash Atlanta (JV) Versus.
    National Highways Authority of India 15 and OPG Power Generations
    Private Limited (supra).
    
    
    
    
    14  2019 15 SCC 131
    15 2026 SCC Online SC 98
    _____________________________________________________________________________
    
                                          PAGE NO. 16 OF 77
    
                                            22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                       ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                  CARBP-10809-2024
    
    
    
    
    29)               Mr. Rustomjee further submits that the dispute is clearly
    arbitrable under Clause 12 of the Industrial All Risk Policy. That the
    dispute between the parties is primarily a question of "how much" and
    not "whether" an amount is payable. That the Tribunal has correctly held
    that the dispute with respect to balance claim is an issue of quantum and
    not liability. He submits that on 18 December 2003, when Petitioner
    issued its settlement intimation voucher, it accepted its liability regarding
    the accident. That Petitioner never repudiated its liability with respect to
    the overhauling cost. That even at the stage of issuing of cheque,
    Petitioner did not state that it was disputing the liability. That no
    statement was made as to which part of the claim was paid and which was
    rejected. That the clarification came for the first time when statement of
    defense was filed. That liability is admitted as Petitioner claims to have
    made payment towards Respondent's claims under both heads of
    "material          damage" and "business interruption". That even joint
    surveyors held that the claim was admissible and that no exclusions
    applied with respect of the same. That even 2 nd interim survey report
    treated claim as admissible under the policy. That the tone and tenor of
    letters dated 5 and 18 December 2001 clearly suggest that the Petitioner
    would cover the costs of overhauling.
    
    
    30)               Mr. Rustomjee further submits that it is impermissible to
    split the cause of action or claim. That Petitioner has sought to create
    artificial bifurcation of cause of action into "incident claim" and
    "overhauling claim". That such bifurcation is artificially aimed at creating
    disputes with regard to liability for portion of the claim. That this is
    
    _____________________________________________________________________________
    
                                          PAGE NO. 17 OF 77
    
                                            22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                       ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                  CARBP-10809-2024
    
    
    
    
    evident from three options of repairs presented in the joint surveyor's
    first report dated 10 May 2002, which shows that the difference in the
    options were only to the extent of repairs. That Options 1 and 2 were
    included in Option 3. That by accepting Option 1, Petitioner has
    effectively admitted/accepted liability for Option 3 as well. That the
    arbitrator has rightly rejected this approach of artificial bifurcation.
    
    
    31)               Mr. Rustomjee further submits that Petitioner's reliance on
    letters 27 December 2001 and 25 January 2002 is misplaced as none of the
    letters bear out an unequivocal denial of liability of the Petitioner with
    respect to overhauling costs. That the wordings of the letters shows that
    the view expressed therein was tentative and qualified and did not reflect
    Petitioner's final position on the matter. That letters were issued at an
    earlier stage before filing of claim. That subsequent conduct and
    correspondence between the parties show that the issue as to whether
    accident was the proximate cause of overhauling was still being
    considered and discussed by the Petitioner as late as in 2003. That there
    was no repudiation of liability at any point of time after issuance of claim
    bills by the Respondent. That the said two letters were, in any case,
    premature as the same didn't discuss the three repair options. That the
    issue of overhauling remained under consideration for long after issuance
    of letters. That letters dated 27 December 2001 and 25 January 2002
    cannot be read in isolation by ignoring letters of 5 December 2001 and 18
    December 2001.
    
    
    
    
    _____________________________________________________________________________
    
                                          PAGE NO. 18 OF 77
    
                                            22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                       ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                  CARBP-10809-2024
    
    
    
    
    32)               Mr. Rustomjee further submits that the Petitioner expressly
    admitted that the issue is one of quantum and not of liability, which is
    clear from Petitioner's response to the previous Section 34 petition
    (challenging award dated 14 September 2012) in which it took a stand
    that the dispute between the parties with respect to balance claim was
    one of quantum and not a liability issue. That Petitioner cannot now be
    permitted to alter its stand by seeking to blow hot and cold in the same
    breath. That even in the joint surveyor's report the claim has been
    admitted.
    
    
    33)               Mr. Rustomjee further submits that the view taken by
    Arbitral Tribunal is strongly supported by several judgment of Apex Court
    and various High Court. He relies on judgments in Amlagora Cold
    Storage Versus. National Insurance Company Limited 16 ,Krish Spinning
    (supra), Oriental Insurance Company Limited Versus. Nagarjuna
    Agrichem Limited (supra), Tagros Chemicals India Private Limited
    Versus. United India Insurance Company Limited 17 , M/s. LS Automotive
    India Private Limited Versus. Oriental Insurance Company Limited 18,
    M/s. TRS Lift and Shift Servises Pvt Ltd. Versus. Reliance General
    Insurance Company Limited 19, and Karan Synthetics India Private
    Limited Versus. Divisional Manager 20. That in those judgments it is
    repeatedly held that where part payment has been approved/made under
    the policy and the balance amount is claimed, the dispute relates to
    
    16  1993 SCC Online Cal 89
    17 ARB. O.P. Comm Div No. 319 of 2024 decided on 6 December 2024
    18 ARB. O.P. Comm Div No. 174 of 2025 decided on 19 June 2025
    19 AP-COMM 344 of 2024 decided on 4 July 2024
    20 Petition Under Arbitration Act No. 35 of 2015 decided on 14 August 2015
    _____________________________________________________________________________
    
                                          PAGE NO. 19 OF 77
    
                                            22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                       ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                  CARBP-10809-2024
    
    
    
    
    quantum and not to the liability. It is held in those judgments that even if
    payment is made towards one head of claim for 'material damage' but was
    refused in respect of another, the dispute relates to quantum and not to
    the liability. There has been a shift in the legal position with the
    judgment of the Apex Court in SBI Vs. Krish Spinning, (supra) by which
    principles discussed in various judgments relied upon by Petitioner have
    been watered down. Mr. Rustomjee also relies upon judgment of United
    State District Court Keller N. AM Inc. Versus. Certain Underwriters 21
    wherein it is held that once insurer admits the liability to some extent, it
    is reasonable to describe the remaining dispute as a dispute as to "how
    much" the insurer is required to pay rather than "whether" it is required
    to pay. That the judgment also recognizes the heavy presumption of
    arbitrability and that the Court should decide the question in favour of
    arbitration. He also relies on judgment of Federal Court of Malaysia in
    Press Metal Sarawak SDN BHD Versus. Etiqa Takaful BHD 22 in support
    of his contention that where insurer has admitted liability in respect of
    part of the claim, the question as to whether the remaining part of the
    claim was barred by exclusions was a part of quantum dispute falling
    within the ambit of arbitration clause.
    
    
    34)               Mr. Rustomjee further submits that in the event this Court
    arrives at conclusion that reasons provided in the award are inadequate or
    insufficient, the same can be explained while upholding the award and in
    support he relies on judgment of the Apex Court in OPG Power
    Generations Private Limited (supra) as followed by this Court in Sanjeev
    21 687 F. Supp 3d 712
    22 2016 MLJU 404
    _____________________________________________________________________________
    
                                          PAGE NO. 20 OF 77
    
                                            22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                       ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                  CARBP-10809-2024
    
    
    
                                                                                         23
    Malhotra Versus. SBI Global Factors Ltd. And Another                                      and
    Securitrans India Pvt Limited Versus FIS Payment Solutions and
    Services Pvt Limited24 . Mr. Rustomjee also distinguishes various
    judgments cited by Mr. Jagtiani.
    
    
    35)               Mr. Rustomjee further submits that the claim was not barred
    by excluded causes and that the accident was proximate cause for
    damage, necessitating overhauling. That the onus of proving applicability
    of exclusion causes is rightly put by the Arbitral Tribunal on the
    Petitioner and it has concluded that the Petitioner has failed to discharge
    the said onus. That Petitioner's reliance on GE Reports of 19 October 2001
    and 22 October 2001 for suggesting that GT Engine was suffering from
    pre-existing damage of corrosion, erosion, discoloration etc is misplaced
    as the reports themselves do not state or indicate that there were any
    preexisting conditions in the engine. That additionally the Tribunal has
    held that Petitioner did not lead evidence of any personnel from the GE.
    On the other hand, Respondent led evidence of expert whose testimony is
    accepted by Arbitral Tribunal. He takes me through various findings in the
    arbitral award to demonstrate that the findings are based on
    comprehensive evaluation of evidence. That the Arbitral Tribunal has
    recorded finding of fact that the accident was the proximate cause of
    damage rectified by overhauling. That therefore findings of the Arbitral
    Tribunal on merits of the claim also do not warrant any interference by
    this Court in exercise of powers under Section 34 of the Arbitration Act.
    
    
    23      2025 SCC Online Bom 5402
    24     2025 SCC Online Bom 5401
    _____________________________________________________________________________
    
                                          PAGE NO. 21 OF 77
    
                                            22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                       ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                  CARBP-10809-2024
    
    
    
    
    On above broad submissions, Mr. Rustomjee prays for dismissal of the
    Petition.
    
    
    REASONS AND ANALYSIS
    
    
    36)               Petitioner has sought invalidation of the arbitral award on
    two broad grounds: (i) that the dispute relating to rejection of claim for
    overhauling of GT engine is not arbitrable under Clause 12 of the
    Industrial All Risk Policy and (ii) that the accident/incident is not the
    proximate cause for overhauling of GT Engine and that the claim is
    otherwise liable to be rejected on merits. The Tribunal has answered both
    the issues against the Petitioner. It has held that Respondent's claim for
    balance amount towards overhauling cost of GT Engine was a 'quantum'
    dispute and therefore arbitrable under Clause-12 of the Industrial All Risk
    Policy. The Arbitral Tribunal has further held that the accident/incident
    was the proximate cause for overhauling of GT Engine and that therefore
    rejection of claim for overhauling was erroneous.
    
    
    37)               In the present case, the incident/accident occurred on 16
    September 2001, when the GT Engine tripped and was required to be sent
    for repairs to the facility of GE in the USA. There were two options for the
    Respondent viz. to carry out repairs necessary for recommissioning of GT
    engine or to overhaul the entire GT Engine. Initially Respondents opted
    for the first option but since mere repairs to the damaged parts were not
    found sufficient, the Respondent opted for overhauling the GT Engine
    and claimed the entire expenses incurred for overhauling in addition to
    
    _____________________________________________________________________________
    
                                          PAGE NO. 22 OF 77
    
                                            22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                       ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                  CARBP-10809-2024
    
    
    
    
    claim for business interruption. The Petitioner has sanctioned only the
    claims for repairs/costs in respect of the actual damages directly caused
    during the accident/incident of 16 September 2001 and for business
    interruption and has accordingly paid an amount of Rs.7,69,69,369/- to
    the Respondent. This included amount of Rs.5,01,41,230/- towards
    'material damage' and Rs. 2,68,28,139/- towards 'loss of business
    profits/business interruption'. Since the claim for balance expenses
    incurred towards overhauling of GT Engine is not honored by the
    Petitioner, the Respondent initiated arbitration, which has resulted in
    impugned award dated 8 December 2023 by which the Arbitral Tribunal
    has sanctioned the claim in the sum of Rs.16,38,57,408.84/- under the
    head 'material damage' which essentially is unpaid amount of expenses
    incurred by the Respondents towards overhauling of the GT Engine.
    Additionally, the Arbitral Tribunal has sanctioned claim in sum of
    Rs.6,23,79,114/- towards 'business interruption'. This is how total claim
    in the sum of Rs.22,62,36,523/- is awarded by the Arbitral Tribunal in
    Respondent's favour under the Industrial All Risk Policy. Since amount of
    Rs.7,69,69,369/- is already paid to the Respondent, the Arbitral Tribunal
    has directed payment of balance amount of Rs.14,92,66,884/- with simple
    interest thereon @ 9 percent p.a. from 20 September 2003 upto the date
    of award. The amount of interest comes to Rs.27,05,46,086/- upto the
    date of the award. This is how the Arbitral Tribunal has directed payment
    of total sum of Rs.41,98,12,970/- by the Petitioner to the Respondent.
    The Arbitral Tribunal has also awarded costs of Rs.2 crores in favour of
    the Respondent. It has also awarded post award interest @ 12 percent p.a.
    on the awarded sums.
    
    _____________________________________________________________________________
    
                                          PAGE NO. 23 OF 77
    
                                            22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                       ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                      CARBP-10809-2024
    
    
    
    
    WHETHER DISPUTE IS ONE OF 'LIABILITY' OR OF 'QUANTUM'
    
    
    38)               Petitioner issued Industrial All Risk Policy to the Respondent
    for insuring its captive power plant for the period from 22 February 2001
    to 21 February 2002. Under the policy, the sum insured for material
    damage was Rs.156 crores whereas for business interruption, the sum
    insured was Rs.11.17 crores. The insurance policy contained arbitration
    agreement under Clause 12 which provided thus:
    
    
                      12. If any difference shall arise as to the quantum to be paid under this
                      policy (liability being otherwise admitted) such difference shall
                      independently of all other questions be referred to the decision of an
                      arbitrator to be appointed in writing by the parties in difference, or if
                      they cannot agree upon a single arbitrator, to the decision of two
                      disinterested persons as arbitrators of whom one shall be appointed in
                      writing by each of the parties within two calendar months after having
                      been required so to do in writing by the other party in accordance with
                      the provision of the Arbitration Act, 1940, as amended from time to time
                      and for the time being in force. In case either party shall refuse or fail to
                      appoint arbitrator within two calendar months after receipt of notice in
                      writing requiring an appointment, the other party shall be at liberty to
                      appoint sole arbitrator and in case of disagreement between the
                      arbitrators, the difference shall be referred to the decision of an umpire
                      who shall have been appointed by them in writing before entering on the
                      reference and who shall sit with the arbitrators and preside at their
                      meetings.
    
                      It is clearly agreed and understood that no difference or dispute shall be
                      referable to arbitration as hereinbefore provided, if the Company has
                      disputed or not accepted liability under or in respect of this policy.
    
                      It is hereby expressly stipulated and declared that it shall be a condition
                      precedent to any right of action or suit upon this policy that the award
                      by such arbitrator, arbitrators or umpire of the amount of the loss or
                      damage shall be first obtained.
    
    
    
    
    _____________________________________________________________________________
    
                                              PAGE NO. 24 OF 77
    
                                                 22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                           ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                      CARBP-10809-2024
    
    
    
    
    39)               Thus, only differences or disputes as to the quantum to be
    paid under the policy, where liability is otherwise admitted, were capable
    of being settled through arbitration. In case where the Petitioner disputed
    or not accepted the liability under or in respect of the policy, the dispute
    or difference could not be referred to arbitration.
    
    
    40)               In the light of the above quoted Clause 12 containing the
    arbitration agreement                 between the parties, the core issue for
    consideration is whether Respondent's claim for overhauling cost of GT
    Engine is a dispute as to 'quantum' to be paid or whether the same relates
    to 'liability' which is disputed or not accepted by the Petitioner.
    Respondent contends that it had filed a singular claim in respect of the
    costs incurred in overhauling, which included the expenses for damage to
    the GT Engine and that since the Petitioner has admitted liability in
    respect of part of such claim and has paid to the Respondent partial claim,
    the dispute essentially is in respect of the quantum and not in respect of
    the liability. On the other hand, it is the case of the Petitioner that
    Respondent's claims were under two distinct heads of costs incurred for
    repairs to GT Engine due to the incident and costs incurred for
    overhauling the entire GT Engine. It is Petitioner's case that it has treated
    the two claims as different and distinct and has allowed the former claim
    while rejecting the latter. That there is rejection of liability in respect of
    the later claim for overhauling of GT Engine. It is Petitioner's contention
    that the case involves disputes relating to rejection of liability or non-
    acceptance of liability qua the claim for overhauling of GT engine. The
    Petitioner contends that the issue does not relate to quantum but the
    
    _____________________________________________________________________________
    
                                              PAGE NO. 25 OF 77
    
                                                22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                           ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                  CARBP-10809-2024
    
    
    
    
    same relates to liability. This is how the two parties raised a dispute
    before the learned arbitrator about nature of rejection of claim raised by
    the Respondent.
    
    
    41)               If rejection of claim for overhauling of GT Engine is treated
    as rejection of liability under or in respect of the policy, the dispute is not
    capable of being resolved through arbitration since there is no arbitration
    agreement for resolution of such dispute. If on the other hand, if the
    entire claim of the Respondent for costs incurred towards repairs and
    overhauling of GT Engine is treated as a singular indivisible claim, since
    the liability in respect of part thereof is admitted, rejection of the other
    part would be a dispute relating to quantum, which is capable of being
    resolved through arbitration. Therefore, the issue which is at the heart of
    controversy is whether the claim raised by the Respondent for incurring
    of expenditure towards overhauling of the GT Engine is to be treated as a
    single indivisible claim or there are two distinct claims involved in respect
    of repairs to engine arising out of accident and overhauling/rebuilding of
    the entire engine. The Arbitral Tribunal has treated the dispute between
    the parties as the one relating to quantum and has accordingly answered
    issue of arbitrability in favour of Respondent and against Petitioner.
    Correctness of that finding is questioned before this Court.
    
    
    42)               The Gas Turbine Engine is essentially an aero-derivative
    engine which is often used in airplanes and which is smaller than an
    industrial gas turbine. Because of its compactness, the clearance between
    the rotating parts is almost nil. The primary components of GT Engine,
    
    _____________________________________________________________________________
    
                                          PAGE NO. 26 OF 77
    
                                            22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                       ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                  CARBP-10809-2024
    
    
    
    
    i.e., the compressors, turbines and combustor are all fastened on two
    shafts that run through the entire GT Engine. The movement of these
    shafts is facilitated through bearings (including a 4B bearing) which are
    fixed along the shafts. The 4B bearing is housed in Sump-B Section of the
    GT Engine.
    
    
    43)               In April 2001, the GT Engine of Respondent encountered oil
    leakage in the hot section and repairs were carried out by installation of a
    new 4B bearing. The GT Engine was reinstalled and recommissioned in
    June 2001. There is no dispute to position that the Petitioner duly paid
    the claim raised by the Respondent in respect of the incident of oil
    leakage.
    
    
    44)               On 16 September 2001, the incident/accident occurred when
    metal chip detector installed in oil Sump-B sounded an alarm and
    fluctuations were noticed in the resistance and the GT Engine tripped.
    
    
    45)               The GT Engine was under Operation and Maintenance
    Contract dated 15 September 2000 with GEEPO, a subsidiary/sister
    concern of GE.
    
    
    46)               GEEPO carried out Borescope Inspection of GT Engine which
    showed that Sump-B was not in good order and 4B bearing cage was
    broken. Respondent sent the GT Engine to GE's facility in Houston, Texas
    and the engine reached the facility of GE in the USA in October 2001. The
    GE issued two reports dated 19 October 2001 and 22 October 2001.
    
    _____________________________________________________________________________
    
                                          PAGE NO. 27 OF 77
    
                                            22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                       ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                      CARBP-10809-2024
    
    
    
    
    Petitioner particularly relies on observations in report dated 19 October
    2001 which recorded some additional issues over and above the Sump-B
    issue such as corrosion, discoloration, reddish yellow rust etc. in respect
    of several components of the engine.
    
    
    47)               The Petitioner appointed McLarens Toplis as its surveyors in
    the USA. McLarens Toplis issued report on 28 November 2001 to the
    Petitioner, in which it was stated as under:
    
    
                      We report that the scope of repairs requested from Search Chem are
                      completed and final Testing will be conducted on Dec. 5 or 6th, 2001. We
                      advise that the repair scope was not what GE had recommended, More
                      particular GE recommended in their inspection report that the LPT also
                      he rebuilt/repaired and possible the entire angine be rebuilt before they
                      would offer a warranty.
    
                      Our concern here is a limited repair on this engine that may eventually
                      fail again and thus placing yourselves in another claim for
                      damages/repairs. Though these other areas nay be wear and tear issues
                      and/or aggravated from the previous failure. Experts at GE cannot say
                      which issue this addresses, only that at some time they will need to be
                      addressed.
    
                      It appears we are looking at two different possibilities in this case;
    
                      A) The loss of oil during the first incident caused the No. 4 bearing to
                      fatigue and ultimately fail.
    
                      B) The over torqueing of the bearing resulted in the bearing failure.
    
                      C) Or the combination of both the above contributed to the bearings
                      failure.
    
                      The data sheet provided shows no remarkable patterns. It is a
                      spreadsheet type data sheet that has the information imputed every 4
                      hours. (I believe manually, as allegedly read from the sensors.
    
                      Over all GE has found the entire engine in need of a complete overhaul
                      due their findings during the break down. As we reported earlier, Search
    _____________________________________________________________________________
    
                                              PAGE NO. 28 OF 77
    
                                                 22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                           ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                     CARBP-10809-2024
    
    
    
    
                      Chem has not agreed to this and has limited their scope of repair to the
                      areas of failure, only.
    
    
    48)               After receipt of report of McLarens Toplis, the Petitioner
    wrote to the Respondent on 5 December 2001 stating as under:
    
                      We have received a communication from our Head office regarding
                      report of M/s Mclarens Toplis, Houston, USA.
    
                      In terms of the said report, G.E have recommended to overhaul the
                      entire engine and not limit the repairs for the present accident alone.
                      Unless the engine is completely overhauled, another loss could occur in
                      the near future. It is thus evident that engine has to be overhauled
                      thoroughly to fit to run continuously.
    
                      Further it is also reported that unless the engine is overhauled, the
                      repairers are also not willing to give guarantee-for the engine with
                      respect to the present repairs.
    
                      From the above, it would be observed that it is imperative to carry
                      out complete overhauling of the entire engine as per G.E. 's
                      recommendations instead of limiting the scope of repairs to the
                      areas of failure (present accident loss only).
    
                      We would request you to kindly ensure that this is done before the
                      engine is dispatched to India and Iet us have your confirmation to
                      enable us to revert to our Head Office (We are informed that the final
                      testing is to be conducted on 5th or 6th December, 2001). Kindly treat
                      this matter as most urgent.
    
                                                                (emphasis and underlining added)
    
    
    49)               In the meantime, Petitioner sought advice from its Head
    Office and once again wrote to the Respondent on 18 December 2001
    stating as under :
    
                      We had sought the advice of our Head Office/Regional Office with regard
                      to contents of your letter dated 12.12.2001.
    
                      Our Head Office have received a communication from M/s. McLarens
                      Toplis in terms of which they had found excessive transit vibration and
    
    _____________________________________________________________________________
    
                                            PAGE NO. 29 OF 77
    
                                               22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                          ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                     CARBP-10809-2024
    
    
    
    
                      it was also revealed that no.4 bearing failure was not due to bad bearing
                      but something which is not incidental to the earlier accidental damage.
                      Our Head Office has therefore once again reiterated that it would
                      be advisable for yourselves to repair the entire engine now itself as
                      recommended by G. E. so that the engine may not have any
                      problem in the future. if it is not done as recommended by G. E.
                      then future claim is imminent as observed by McLarens and it will
                      pose problem at the time of underwriting of the risk.
    
                      We would request you to kindly look into the above aspects and let us
                      have your confirmation to enable us to revert to our Head Office. Kindly
                      treat this as most urgent.
                                                             (emphasis and underlining added)
    
    
    
    50)               Thus, by its letter dated 5 December 2001, the Petitioner
    referred to the report of the M/s. McLarens Toplis and suggested that 'it is
    imperative to carry out complete overhauling of the entire engine as per GE's
    recommendations instead of limiting the scope of repairs to the areas of
    failure caused by the accident'. However, it appears that the Respondents
    opted for limited repairs of Sump-B bearing. GE completed the repairs of
    Sump-B bearing and the engine was tested on 7 December 2001. During
    the testing, core rotor vibrations were noticed during transient conditions
    beyond acceptable limits. It appears that on 17/18 December 2001, a
    meeting took place between the representatives of GE and Respondent,
    minutes whereof were recorded in the subsequent letter dated 24
    December 2001, which read thus :
    
    
                      GE completed the repair of Sump B bearing failure and the engine was
                      tested on December 7, 2001 During this testing the core rotor vibrations
                      were found to be 3.5 to 4.0 mils during transient conditions. the
                      acceptable limit of these vibrations is 3.0 mils.
    
                      GE has suggested to attend to these vibrations by opening HPC and HPT
                      modules and performing a balance. But this HPC & HPT balance will
    
    _____________________________________________________________________________
    
                                             PAGE NO. 30 OF 77
    
                                               22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                          ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                     CARBP-10809-2024
    
    
    
    
                      only take care of transient vibrations, which is not a solution to the
                      complete problems. Therefore GE further suggested to do complete
                      overhaul for which GE would extend a full guarantee SCIL agreed to this.
    
                      The complete overhaul will take 50-60 days from the induction and the
                      engine can be inducted earliest on December 27, 2001 for full tear down
                      into each module for complete inspection and repairs.
    
                      The estimated cost of repairs indicated above will be $ 2,645,280. This is
                      in addition to Sump B repair cost of $ 454,720
    
    
    51)               Thus, through its two letters dated 5 December 2001 and 18
    December 2001, Petitioner specifically advised the Respondent to go for
    complete overhauling of GT Engine instead of restricting the repairs to
    the areas of failure caused by the accident. In fact, in the letter dated 18
    December 2001, Petitioner expressed apprehension of creation of
    problems at the time of underwriting of the risk if overhauling of the
    engine was not done as recommended by the GE.
    
    
    52)               In the above background, the Respondent wrote to the
    Petitioner on 24 December 2001 giving details of overhauling of the GT
    Engine and intimated to the Petitioner that it would claim entire costs of
    repairs and also the incidental expenses incurred by it, which is clear from
    following portion of letter dated 24 December 2001:
    
                      While we will be claiming on you for the entire cost of repairs as also all
                      incidental expenses incurred by us in connection with repairs to be
                      carried out by G.E. we would request you to send any instruction that
                      you may wish to send your surveyors abroad for their lissing with G.E.
                      and facilitating speedy completion of repairs and turn of the engine to
                      us.
    
                      Kindly acknowledge receipt and advise us the steps Inken by you, if we
                      don't receive any reply from you immediately we shall assume that you
    
    
    _____________________________________________________________________________
    
                                             PAGE NO. 31 OF 77
    
                                                22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                          ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                     CARBP-10809-2024
    
    
    
    
                      have concurred with our line of action and have advised your surveyors
                      abroad suitably in this connection.
    
    
    53)               Upon receipt of letter dated 24 December 2001 from the
    Respondent, Petitioner did a U-turn. While it kept on pestering the
    Respondent vide letters dated 5 December 2001 and 18 December 2001 to
    go for complete overhauling of the GT Engine, after receipt of details of
    overhauling costs vide letter dated 24 December 2001, the Petitioner
    apparently realized the risk involved in recommending overhauling of GT
    Engine on account of claim of entire costs of overhauling likely to be
    raised by the Respondent. Accordingly, on 27 December 2001, Petitioner
    wrote to the Respondent as under:
    
    
                      We are in receipt of your Letter dated 24 December, 2001 and have noted
                      the contents thereof.
    
                      It is observed that you had made a claim totaling to $32.19,497.11
                      approximately Rs. 15 Crores. In this connection, you will kindly
                      appreciate that our liability, subject to adequacy of sum insured, would
                      be restricted to repair cost in respect of actual damages directly caused
                      during the accident/incident on 16 September, 2001 necessitating
                      despatch of the damaged equipment to Houston, USA for repair.
                      Overhauling coat etc. would not fall within the purview of the policy.
    
                      In my case, as you are aware, MC LARENS TOPLIS Houston, USA (M/s
                      Mehta & Padmsey Associates, M/s. Bhatewadekar & Co.) have already
                      been appointed by our Head Office and their detailed report is awaited
                      and we would be in a position to write to you further only on receipt of
                      the same after receiving directives from our Head Office. In the
                      meantime, you may kindly note that at this juncture, we are not in a
                      position to accept liability as per the claim raised by yourselves in your
                      subject letter due to the reasons mentioned above and as per the terms
                      and conditions of the Policy.
    
    
    54)               Thus, after realising that the Respondent was likely to raise a
    claim of Rs.15 crores towards overhauling of the GT Engine, Petitioner
    
    _____________________________________________________________________________
    
                                             PAGE NO. 32 OF 77
    
                                                22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                          ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                     CARBP-10809-2024
    
    
    
    
    clarified on 27 December 2001 that it would restrict the claim only to
    repairs costs in respect of the actual damage directly caused by the
    incident and that overhauling costs would not fall within the purview of
    the policy. Respondent protested against the volte-face taken by the
    Petitioner vide letter dated 28 December 2001, in which it stated as
    under :
    
                      We are suprised to receive a casual letter of this nature from you in
                      connection with the claim which you will appreciate is very serious and
                      sensitive.
    
                      In this circumstances we repeat and reiterate that our total
                      expenses(which may not be restricted to Rs. 15 Crores as is indicated in
                      your letter and may be more because of duty element and other
                      incidental expenses until the equipment reaches our site) is payable by
                      you in full as per the terms of the policy. It is your responsibility to
                      explain to our satisfaction that some of the heads of expenses that we
                      might have incurred or be incurring fall under the exclusions of the said
                      policy in case you deny payment of the same to us.
    
                      Now that you have not advised us anything as regards further active
                      involvement of your surveyors abroad during the whole process of
                      repairs until the dispatch by GE, we are going ahead with the process as
                      indicated in our Jetter dt.24.12.2001.
    
    
    
    
    55)               Thus, Respondent made it clear to the Petitioner that it
    would go ahead with the overhauling of the GT Engine as indicated in
    letter dated 24 December 2001. Petitioners wrote to the Respondent on 25
    January 2002 once again intimating that the liability would be limited to
    the extent of actual damages before the turbine was dispatched to USA for
    repairs and that the expenses claimed towards costs of overhauling were
    not payable as per the terms and conditions of Industrial All Risk Policy.
    The letter dated 25 January 2002 reads thus:
    
    _____________________________________________________________________________
    
                                             PAGE NO. 33 OF 77
    
                                               22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                          ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                     CARBP-10809-2024
    
    
    
    
                      Further to our letter dated 30 December, 2001 in response to your letter
                      dated 28 December, 2001 we have now received advices from our
                      controlling office as under.
    
                      1) The detailed report from Mclarens Toplis North America, Inc.
                      Houston, USA is awaited and a detailed Letter will be issued on receipt of
                      the same.
    
                      2) In the meanwhile, it may please be noted that our liability would be
                      limited to the extent of actual damages before tire turbine was
                      despatched to USA for repairs. The expenses claimed towards cost of
                      overhauling are not payable as per the terms and conditions of IAR
                      Policy.
    
                      We shall revert to yourselves on receipt of detailed letter/advises from
                      our controlling offices.
    
    
    
    56)               Based on letters dated 27 December 2001 and 25 January
    2002, Petitioner has raised the plea that part of the claim relating to
    overhauling of GT Engine is rejected and/or not accepted by it and that
    therefore, adjudication of disputes relating to that claim is not arbitrable.
    Petitioner has criticized the Award of the Arbitral Tribunal contending
    that both the letters are virtually ignored by the Tribunal, which has given
    unnecessary weightage to the letters dated 5 December 2001 and 18
    December 2001.
    
    
    57)               The Arbitral Tribunal has recorded nine reasons for holding
    that even part of the claim relating to overhauling of GT Engine is
    covered by one and the same incident and that it is impermissible to split
    a single claim or cause of action in two separate parts. It would be
    apposite to reproduce the relevant parts of the nine findings recorded by
    the Arbitral Tribunal in the Award as under:
    
    
    _____________________________________________________________________________
    
                                             PAGE NO. 34 OF 77
    
                                                22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                          ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                      CARBP-10809-2024
    
    
    
    
                      40. The Tribunal has considered the rival submissions carefully. In the
                      Tribunal's view the submissions made on behalf of the Respondent are
                      not found to be meritorious for more than one reason.
    
                      41. First, admittedly the incident which caused damage to GT Engine
                      occurred on 16.09.2021 and the part of such claims was admittedly paid
                      by the Respondent to the Claimant. Rest of the claims was not accepted
                      being claim of Overhauling. As a necessary corollary, the dispute
                      between the parties is clearly seen to be relating to quantum, which is
                      squarely covered by Arbitration Clause 12 of the Policy.
    
                      42. Second, following the above aspect, the fact of the matter is that the
                      Respondent made the part payment of Rs. 7,69,69,369 to the Claimant
                      against the Claimant's claim of Rs. 24,73,18,765 under the Policy. At the
                      time of making payment, the Respondent did not indicate that the
                      balance of Rs. 17,03,49,396 was not being paid for the reason that
                      Respondent has denied its liability for the same. That was the first
                      occasion when the Respondent ought to have made its position clear
                      which it never did.
    
                      43. Third, and very significantly, the Respondent has not repudiated its
                      liability with respect to Claimant's claim at any point of time. This is not
                      even disputed by the Respondent. In the absence of any repudiation by
                      the Respondent of the Claimant's claim arising out of the incident that
                      occurred on 16.09.2001, no inference can be drawn that there is denial of
                      liability by the Respondent under or in respect of the Policy.
    
                      44. Fourth, in what has been noticed in the three reasons above, the
                      question of inference of implied denial of liability for the unpaid amount
                      does not arise.
    
                      45. Fifth, for the purpose of arbitrability of claim, the distinction drawn
                      by the Respondent between the 'incident claim' which was paid and
                      'overhauling claim' which was not paid by the Respondent, is wholly
                      misconceived. It is admitted case of the Respondent that even
                      Respondent recommended to the Claimant to have the GT Engine
                      overhauled. In this regard, the two letters of the Respondent dated
                      05.12.2001 and 18.12.2001 deserve to be noticed.
    
                      47. For whatever reason, if the Respondent was of the view that
                      Overhauling Claim was out of coverage or unpayable by them, there was
                      no occasion for the Respondent to insist for overhauling the engine. The
                      Insurance Company would have denied its liability of Overhauling Costs
                      when the G.E. recommended to overhaul the entire engine and not
                      further recommend to the Claimant to go in for overhauling. Rather, the
                      Insurance Company represented to the Claimant that it was imperative
    _____________________________________________________________________________
    
                                              PAGE NO. 35 OF 77
    
                                                22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                           ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                      CARBP-10809-2024
    
    
    
    
                      to carryout complete overhauling of the entire engine as per G.E. 's
                      recommendations.
    
                      48. Two things, in the Tribunal's view, were in the mind of the
                      Respondent and that was because the Engine was covered under the
                      Policy that, (i) the engine has to be overhauled thoroughly to fit to run
                      continuously and (ii) the repairs guarantee for the engine's present
                      repairs was a must. These could be achieved only if the engine was
                      overhauled. But for the coverage of Overhauling Costs under the Policy,
                      in the Tribunal's view, no recommendation of overhauling would have
                      been made by the Respondent. Why would the Insurance Company give
                      an unsolicited advice to the Claimant if overhauling costs under the
                      Policy were not covered?
    
                      50. Both these letters of 05.12.2001 and 18.12.2001 bear the Reference:
                      IAR POLICY NO. 022000/11/23/2990/2000-2001 CLAIM NO.
                      022000/11/23/0100001/2001-2002- DAMAGE TO GAS TURBINE.
    
                      51. In the Tribunal's view, the coverage of Overhauling Costs under and
                      in respect of the Policy becomes very clear in view of the above two
                      letters from the Respondent.
    
                      52. In light of the above two letters of the Respondent and what has
                      been discussed above, the conduct of the Respondent in communicating
                      to the Claimant vide subsequent letters, dated 27.12.2001 that
                      "Overhauling cost etc. would not fall within the purview of the policy ", and
                      dated 25.01.2002 that "The expenses claimed towards cost of overhauling
                      are not payable as per the terms and conditions of IAR Policy" would not
                      take the dispute out of arbitrability clause.
    
                      53. Sixth, the construction of the expression, "such difference shall
                      independently of all other questions be referred to the decision of an
                      arbitration" does not mean that each claim may be taken a separate
                      dispute as contended by the learned senior counsel for the Respondent.
                      Rather reading the clause in a holistic manner would rather show that
                      dispute with regard to amount payable as claimed by the Claimant or
                      unpayable part of the claim as per the Respondent would relate to
                      quantum dispute and shall be referred to the decision of an arbitration.
    
                      54. Seventh, the Joint Surveyors in their two Interim Survey Reports have
                      noted in unambiguous terms that claimant's claim was admissible under
                      the Policy. The only dispute between the parties, therefore, is about
                      quantum in as much as whether the Claimant is entitled to Rs.
                      7,69,69,369 which has been paid by the Respondent to the claimant or
                      claimant is entitled to full repair costs of the engine in the sum of Rs.
                      24,73, 18,765 as claimed by the Claimant.
    _____________________________________________________________________________
    
                                              PAGE NO. 36 OF 77
    
                                                 22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                           ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                      CARBP-10809-2024
    
    
    
    
                      55. Eighth, in the Tribunal's view, none of the Judgments cited by the
                      learned senior counsel for the Respondent actually helps the
                      Respondents. The cited Judgments are distinguishable on facts.
    
                      63. Ninth, the submission of the learned senior counsel for the
                      Respondent that Respondent has a right to split the cause of action
                      between the 'Incident Claim' and 'Overhauling Claim', in the Tribunal's
                      view is wholly misconceived. What Respondent seeks, is to divide a
                      single claim or cause of action into two separate parts which is
                      impermissible. The Arbitration and Conciliation Act, 1996 does not
                      provide for splitting up of the cause of action which is capable of
                      resolution through the mechanism of arbitration.
    
                      64. In the Tribunal's view the entire claim raised by the claimant is
                      arising out of one incident which cannot be split up as is sought to be
                      done by the Respondent to keep part of claim outside the arbitration. As
                      a matter of fact, the facts as noted in above discussion are eloquent and
                      clearly lead to the conclusion that in the absence of repudiation of
                      Claimant's Claim by the Respondent, the parties have their dispute
                      about quantum alone which is clearly arbitrable.
    
                      65. Even on the analogy of rule provided in Order 2 Rule 2 CPC, such
                      split of single claim into two is impermissible. The rule contained in
                      Order 2 Rule 2 CPC bars such split. What the rule lays down is that
                      where there is one entire cause of action, the plaintiff cannot split the
                      cause of action into parts so as to bring separate suits in respect of those
                      parts. This rule will equally apply in a situation such as this where the
                      Respondent intends to split cause of action and single claim of the
                      Claimant into two, namely, 'Incident Claim' and 'Overhauling Claim'.
    
                      66. Law does not countenance, rather discourages, splitting of claim and
                      remedies based on same cause of action.
    
                      67. The Tribunal, thus, holds that the dispute arising in this arbitration
                      between the parties is a quantum dispute and not a liability dispute. The
                      present dispute is therefore arbitrable.
    
    
    58)               Thus, broadly the Arbitral Tribunal has held that in respect of
    damage caused to GT Engine in the incident occurring on 16 September
    2001, part of the claim is admittedly paid by the Petitioner and since rest
    of the claim relating to overhauling is not accepted, the dispute between
    
    _____________________________________________________________________________
    
                                              PAGE NO. 37 OF 77
    
                                                22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                           ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                         CARBP-10809-2024
    
    
    
    
    parties relates to 'quantum' which is squarely covered by arbitration
    Clause-12 of the policy. The Tribunal has further held that while making
    part payment of Rs.7,69,69,369/- to the Respondent, Petitioner did not
    indicate that the balance amount was not being paid because liability was
    denied. It is further held that the liability has never been repudiated at
    any point of time. It is further held that the distinction between 'incident
    claim' and 'overhauling claim' is misconceived as Petitioner itself
    recommended that GT Engine must be overhauled vide letters dated 5
    December 2001 and 18 December 2001. It is further held that there was no
    reason for Petitioner-Insurance Company to give unsolicited advice for
    carrying out overhauling if liability in respect of that part of claim was
    denied. The Tribunal has held that subsequent letters dated 27 December
    2001 and 25 January 2002 did not take disputes out of arbitration clause
    on account of the previous letters dated 5 and 18 December 2001. The
    Tribunal has further held that the joint surveyors noted that the
    Respondent's claim was admissible under the policy and the dispute was
    only relating to quantum.
    
    
    59)               I am in broad agreement with the above findings recorded by
    the Arbitral Tribunal. The Tribunal had two sets of letters of Petitioner
    before it. The first set of letters issued on 5 December 2001 and 18
    December 2001 virtually directed Respondent to overhaul GT Engine
    rather         than    limiting       the   repairs    to       damage       caused        by     the
    incident/accident. The Petitioner stated in letter dated 5 December 2001
    that "it is imperative to carry out complete overhauling of the entire
    engine". In further letter dated 18 December 2001, Petitioner virtually
    
    _____________________________________________________________________________
    
                                                PAGE NO. 38 OF 77
    
                                                  22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                              ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                   CARBP-10809-2024
    
    
    
    
    issued a threat to the Respondent that it would not underwrite the risk if
    overhauling of GT Engine is not carried out. There was no occasion or
    reason for the Petitioner to insist for overhauling of the GT Engine. It did
    so with a view to avoid further breakdown of the GT Engine resulting in
    multiple and frequent claims. The Tribunal has rightly questioned as to
    why Petitioner would give an unsolicited advice to the Respondent if
    overhauling cost was not to be considered as covered under the policy.
    The findings recorded by the Arbitral Tribunal based on the first set of
    letters dated 5 and 18 December 2001 are plausible findings and it cannot
    be held, by any stretch of imagination, that the findings are of such nature
    that no fair-minded person would ever record the same.
    
    
    60)               Coming to the next set of letters dated 27 December 2001 and
    25 January 2002, I am in agreement with the Arbitral Tribunal that the
    said letters do not take the dispute out of arbitration clause. It is
    Petitioner's contention that the Tribunal has not recorded any reasons for
    holding so. I am unable to agree. The Tribunal has considered the effect
    of the said two letters in the context of earlier letters dated 5 and 18
    December 2001. This Court can undertake the exercise of explaining the
    existence of underlying reasons, which exercise does not supplant the
    reasons in the award but only explains it for better and clearer
    understanding thereof. In OPG Power Generation Private Limited (supra)
    the Apex Court has held in paragraph 168 as under:
    
    
                      168. We have given due consideration to the above submission. In our
                      view, a distinction would have to be drawn between an arbitral award
                      where reasons are either lacking/unintelligible or perverse and an
                      arbitral award where reasons are there but appear inadequate or
    _____________________________________________________________________________
    
                                           PAGE NO. 39 OF 77
    
                                             22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                        ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                     CARBP-10809-2024
    
    
    
    
                      insufficient [ See paras 79 to 83 of this judgment.] . In a case where
                      reasons appear insufficient or inadequate, if, on a careful reading of the
                      entire award, coupled with documents recited/relied therein, the
                      underlying reason, factual or legal, that forms the basis of the award, is
                      discernible/intelligible, and the same exhibits no perversity, the Court
                      need not set aside the award while exercising powers under Section 34 or
                      Section 37 of the 1996 Act, rather it may explain the existence of that
                      underlying reason while dealing with a challenge laid to the award. In
                      doing so, the Court does not supplant the reasons of the Arbitral
                      Tribunal but only explains it for a better and clearer understanding of
                      the award.
    
    
    61)               Following the ratio of the judgment in OPG Power
    Generation Private Limited (supra) this Court has held in Sanjeev
    Malhotra (supra) in paragraphs 39 to 43 as under:
    
                      39. It is a well settled position that inadequacy or insufficiency of
                      reasons in the Arbitral Award cannot be a ground for setting aside the
                      same. An Award would become susceptible to challenge as being
                      unintelligible when the Arbitral Tribunal fails to record any reasons for
                      arriving at a particular conclusion. On the other hand, the Arbitral
                      Tribunal may record some reasons, which may appear to be insufficient
                      or inadequate or inelaborate to the losing party. While deciding a
                      particular issue, the Arbitral Tribunal may not express itself by recording
                      very detailed and elaborate reasons, but may set forth some reasons to
                      support the conclusion. So long as the Court agrees with the ultimate
                      conclusion recorded by the Arbitral Tribunal, the Court cannot set aside
                      the Award on technicality of absence of elaborate or extensive reasons,
                      which the Court may expect the Arbitral Tribunal to record. The test is,
                      on meaningful reading of the entire Award, whether the Court can
                      extract what the Arbitral Tribunal wants to hold and why it has held so.
                      The test is not to match the expectation of the Section 34 Court about
                      the level of elaborateness of reasons. Given that the Court needs to show
                      significant deference to the arbitral awards and must grant broad
                      latitude to the factual findings recorded therein, all that needs to be seen
                      is whether the reasons are discernible from the award. Reasons in the
                      award need not be elaborate always, they can also be compendious. So
                      long as the recorded reasons pass the muster of conveying to the Court
                      what is meant to be said and why it is said, interference in the Award on
                      the objection of lack of reasons would be avoided. Arbitral Tribunal is
                      not a Court which is expected to record very detailed or elaborate
                      reasons in support of each of the finding. The Arbitral Tribunal can be
                      accused of passing non-speaking Award only if the Award contains no
    _____________________________________________________________________________
    
                                             PAGE NO. 40 OF 77
    
                                                22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                          ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                      CARBP-10809-2024
    
    
    
    
                      reasons at all. However, where some reasons can be discerned
                      supporting the ultimate conclusion reached, with which Section 34
                      Court ultimately concurs, there is no room for setting aside the award.
                      Under Section 34 of the Arbitration Act, the Court ultimately does not sit
                      as a court of appeal over the arbitral award.
    
                      40. The principles discussed above find support in the judgment of the
                      Apex Court in OPG Power Generation Private Limited vs. Enexio Power
                      Cooling Solutions India Pvt. Ltd. and Another in which it is held thus:
    
                               xxx
    
                      41. The issue of adequacy of reasons has also been dealt with by the
                      Apex Court in Dyna Technologies Pvt. Ltd. vs. Crompton Greaves
                      Limited25, In which the Court has held in paragraph 35 as under:
    
                               35. When we consider the requirement of a reasoned order, three
                               characteristics of a reasoned order can be fathomed. They are:
                               proper, intelligible and adequate. If the reasonings in the order
                               are improper, they reveal a flaw in the decision-making process.
                               If the challenge to an award is based on impropriety or perversity
                               in the reasoning, then it can be challenged strictly on the
                               grounds provided under Section 34 of the Arbitration Act. If the
                               challenge to an award is based on the ground that the same
                               is unintelligible, the same would be equivalent of providing
                               no reasons at all. Coming to the last aspect concerning the
                               challenge on adequacy of reasons, the Court while exercising
                               jurisdiction under Section 34 has to adjudicate the validity
                               of such an award based on the degree of particularity of
                               reasoning required having regard to the nature of issues
                               falling for consideration. The degree of particularity cannot
                               be stated in a precise manner as the same would depend on
                               the complexity of the issue. Even if the Court comes to a
                               conclusion that there were gaps in the reasoning for the
                               conclusions reached by the Tribunal, the Court needs to
                               have regard to the documents submitted by the parties and
                               the contentions raised before the Tribunal so that awards
                               with inadequate reasons are not set aside in casual and
                               cavalier manner. On the other hand, ordinarily unintelligible
                               awards are to be set aside, subject to party autonomy to do away
                               with the reasoned award. Therefore, the courts are required to be
                               careful while distinguishing between inadequacy of reasons in an
                               award and unintelligible awards.
                                                                                (emphasis added)
    
    
    25 (2019) 20 SCC 1
    _____________________________________________________________________________
    
                                              PAGE NO. 41 OF 77
    
                                                 22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                           ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                       CARBP-10809-2024
    
    
    
    
                        42. In Ravi Raghunath Khanjode and others vs. Harasiddh
                        Corporation26, I have followed the ratio of the judgment in OPG Power
                        Generation Private Limited (supra) and it is held in paragraphs 46 and
                        47 as under:
    
                               46. It is also settled law that the Award need not be set aside on
                               the ground of inadequacy of reasons so long as the ultimate
                               conclusions reached by the Arbitral Tribunal are found to be
                               correct. Reference in this regard can be made to the judgment of
                               the Apex Court in OPG Power Generation Private Limited v. Enexio
                               Power Cooling Solutions India Private Limited in which it is held in
                               para-168 as under :--
    
                                    168. xxx
    
    
                               47. Therefore even if the reasons recorded by the arbitral tribunal
                               for repelling the objection of requirement to secure permission
                               under Section 43 of BTAL Act or Section 36A of the MLRC are to
                               be construed as inadequate or insufficient, I am of the view that
                               the Award is not rendered bad on that ground alone. It is not that
                               the learned Arbitrator has recorded absolutely no reasons. I am
                               in agreement with the ultimate conclusion reached by the
                               learned Arbitrator for the reasons indicated in the later part of
                               the judgment. The objection of failure to record reasons is
                               accordingly rejected.
    
                        43.    In my view therefore, the Award cannot be annulled only because
                        the Petitioner expects the Arbitral Tribunal to have recorded better
                        reasons while rejecting the objection of variation/novation of contract.
    
    
    
    62)            In Securitrans India Pvt. Ltd. (supra), this Court has once again
    followed the ratio of the judgment of the Apex Court in OPG Power
    Generation Private Limited (supra) and it is held in paragraphs 53 and 54
    of the judgment as under:
    
                        53. Also the Award has to be read in its entirety and the finding of
                        perversity can be recorded when there are absolutely no reasons for
                        reaching the conclusion. An arbitral award is not to be readily set aside
                        on the ground of inadequacy of reasons. Where the reasons do not
                        appear to be sufficient, Section 34 Court can consider all the documents
    
    26 2025 SCC Online Bom 4505
    _____________________________________________________________________________
    
                                               PAGE NO. 42 OF 77
    
                                                 22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                            ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                      CARBP-10809-2024
    
    
    
    
                      and discern the underlying reason from reading of the entire award.
                      Here, the judgment of the Apex Court in OPG Power Generation Private
                      Limited (supra) would be relevant, in which the Apex Court has held in
                      paragraphs 168 and 169 as under:--
                               xx
    
    
                      54. Thus in a case where reasons appear to be insufficient or inadequate,
                      but on a careful reading of the entire Award, the underlying reason is
                      intelligible, the Court need not set aside the Award and rather it can
                      explain the existence of that underlined reason while examining the
                      issue of invalidation of Award. Mere omission on the part of Arbitral
                      Tribunal to refer to a particular contractual clause would not ipso facto
                      render the conclusion recorded by Arbitral Tribunal perverse. The Court
                      can make meaningful reading of the entire reasons recorded by the
                      Arbitral Tribunal and can explain what exactly is meant to be said by the
                      Arbitral Tribunal. The ratio of the judgment in OPG Power Generation
                      Ltd. (supra) has been followed by me in CDSL v. Daksha Narendra
                      Bhausar (supra) in which it is held in paragraph 76 as under:
                               In the present case, the Arbitral Tribunal has recorded the
                               underlying reason of BRH acting in its capacity as DP during
                               some of its negligent and fraudulent acts and has accordingly
                               applied the provisions of Section 16 of the Depositories Act and
                               Clause 5.3.2 of CDSL Bye laws. The underlying reason discernible
                               from reading of the award cannot be termed as perverse. The
                               manner of enquriy conducted by Arbitral Tribunal or the detailed
                               findings recorded by it may not be to the liking of the Petitioner,
                               however so long as this Court has not found the final conclusion
                               of Arbitral Tribunal treating role of BRH as DP to be not perverse,
                               there is no warrant for exercising the powers under Section 34 of
                               the Arbitration Act for invalidating the Award.
    
    
    
    
    63)               Following ratio of the above quoted judgments, I now
    undertake the exercise of explaining existence of underlying reasons to
    the finding recorded by the Arbitral Tribunal in paragraph 52 of the Award
    in which it is held that letters dated 27 December 2001 and 25 January
    2002 do not take the dispute out of arbitrability clause. Firstly, it must be
    observed that the conclusion is reached on the basis of the findings that
    "in the light of the above two letters of the Respondent and what has been
    
    _____________________________________________________________________________
    
                                              PAGE NO. 43 OF 77
    
                                                 22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                           ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                     CARBP-10809-2024
    
    
    
    
    discussed above.....". Thus, the Tribunal has read letters dated 27
    December 2001 and 25 January 2002 in the light of the previous letters
    dated 5 December 2001 and 18 December 2001. Secondly, after going
    through letters dated 27 December 2001 and 25 January 2002, it is
    difficult to conclude that Respondent repudiated the claim in respect of
    overhauling expenses of the GT Engine. This is clear from the following:
    
    
                   i)     The contents of letters are not conclusive in nature as they
                   use words such as "in the meantime", "at this juncture", etc. and
                   the letters were issued awaiting directives from head office and
                   detailed report from M/s. McLarens Toplis. The letters are thus
                   both, tentative as well as qualified. It therefore cannot be
                   contended that the letters had the effect of final repudiation of the
                   claim for overhauling of GT Engine.
    
    
                   ii)    Both the letters were issued before submission of claim bills
                   to the Petitioner by the Respondent. The claim bill was submitted
                   by the Respondent on 17 February 2002 towards material damage.
    
    
                   iii)   Though tentative views about non-acceptance of overhauling
                   claim was expressed in the letters dated 27 December 2001 and 25
                   January 2002, after receipt of claim bill actually raising the claim
                   towards overhauling of GT Engine, Petitioner never repudiated the
                   said claim bill at any point of time. For the first time, artificial
                   distinction of 'incident claim' and 'overhaul claim' was sought to be
                   raised in the Statement of Defense.
    
    _____________________________________________________________________________
    
                                             PAGE NO. 44 OF 77
    
                                               22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                          ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                      CARBP-10809-2024
    
    
    
    
                   iv)   Long after issuance of the two letters, parties were in regular
                   discussion regarding condition of GT Engine prior to the accident,
                   necessity to overhaul the same and the extent of damage caused by
                   accident. This is evident from GE letter dated 28 January 2003
                   explaining that vibration noticed during testing were relatable to
                   accident. By its letter dated 19 June 2003 Petitioner raised the
                   queries about technical problems with the GT Engine, details of
                   overhauling    carried   out     prior    to   accident,       manufacturer's
                   specification of overhauling etc. This is also clear from
                   Respondent's response dated 24 June 2003 to the Petitioner's letter.
                   If liability in respect of the overhauling claim was already denied in
                   toto and if the Petitioner was firm with such denial, why Petitioner
                   called for details of overhauling carried out by the Respondent vide
                   letter dated 19 June 2003 is incomprehensible. This shows that the
                   admissibility of claim relating to overhauling remained under
                   active consideration of the Petitioner long after issuance of the
                   letter dated 27 December 2001 and 25 January 2002.
    
    
                   v)    The Tribunal was also justified in relying on letters dated 5
                   December 2001 and 18 December 2001 advising the Respondent to
                   overhaul the GT Engine for the purpose of concluding that the
                   subsequent two letters of 27 December 2001 and 25 January 2002 do
                   not take the dispute out of the arbitrability clause.
    
    
    64)                  Mr. Jagtiani has strenuously contended that though the two
    letters of 27 December 2001 and 25 January 2002 were issued before
    
    _____________________________________________________________________________
    
                                              PAGE NO. 45 OF 77
    
                                                  22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                           ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                      CARBP-10809-2024
    
    
    
    
    submission of actual 'claim bills', the same were issued in response to the
    'claim' raised by the Respondent on Petitioner on 24 December 2001. He
    has contended that the 'claim bill' ultimately submitted on 17 February
    2002 exactly matches the 'claim' indicated in letter dated 24 December
    2001. He submits that even letter dated 27 December 2001 refers to
    making of 'claim' by the Respondent. However, I am unable to read letters
    dated 27 December 2001 and 25 January 2002 as rejection/repudiation of
    the claim. By letter dated 24 December 2001, Respondent had given
    details of overhauling cost in response to Petitioner's own letter dated 18
    December 2001. By that letter dated 18 December 2001, Petitioner had
    virtually threatened the Respondent of not underwriting the risk if GT
    Engine was not overhauled. Respondent unwillingly went for overhauling
    of GT Engine on account of letters dated 5 December 2001 and 18
    December 2001. Before actually commencing overhauling work, it merely
    gave idea to the Petitioner of cost that would be incurred for overhauling
    of GT Engine. It therefore cannot be contended that on 24 December
    2001, Respondent raised a 'claim' which was capable of being adjudicated
    by the Petitioner. It therefore cannot be held that the letter dated 24
    December           2001      raised   a    claim,    which       was       considered         and
    rejected/repudiated by the Petitioner vide letters dated 27 December 2001
    and 25 January 2002. On the other hand, Petitioner received the claim bill
    only on 17 February 2002 claiming sum of Rs.24.02 crores for material
    damage alone, which included overhauling cost. Far from communicating
    the Respondent that it would treat the 'incident claim' distinct from
    'overhauling claim', the Petitioner treated the claim bill of the
    Respondent as 'one single composite claim' and proceeded to sanction
    
    _____________________________________________________________________________
    
                                              PAGE NO. 46 OF 77
    
                                                22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                           ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                  CARBP-10809-2024
    
    
    
    
    amount of Rs 7.69 crores. Even while sanctioning and releasing the
    payment of Rs.7.69 crores, Petitioner did not indicate to the Respondent
    that it was treating 'incident claim' separately from 'overhaul claim' and
    was repudiating the latter.
    
    
    65)               Even Joint Surveyors' interim reports which are discussed by
    the Arbitral Tribunal in paragraph 54 of the Award leave no manner of
    doubt that there was no dispute about admissibility of the claim. Merely
    because the survey assessment was done with regard to only Option No.1,
    it cannot be contended that the surveyors seggregated the claims into two
    and denied any liability in respect of Option No.3. Even joint surveyors
    held that the claim was admissible and that no exclusions applied with
    respect of the same. Even 2nd interim survey report treated claim as
    admissible under the policy
    
    
    
    66)               What is more shocking in the present case is the fact that the
    Petitioner, who is now enthusiastically and strenuously treating the
    dispute to be one of liability and not of quantum, pleaded to the contrary
    in Affidavit-in-Reply filed in Arbitration Petition No.430 of 2013, in which
    it contended that "I say that there being a dispute with regard to quantum,
    Petitioner had raised arbitration clause and the Respondent had, keeping in
    mind the said arbitration clause, named the Arbitrator and voluntarily
    submitted to arbitration". Again, the Petitioner contended that "the
    Respondent had offered to settle the claim as the liability was admitted and
    the Respondent had offered to settle the claim, there arose dispute with
    regard to quantum". Having admitted that the dispute between parties
    
    _____________________________________________________________________________
    
                                          PAGE NO. 47 OF 77
    
                                            22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                       ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                  CARBP-10809-2024
    
    
    
    
    related to quantum and not to liability in Affidavit-in-Reply filed in
    Arbitration Petition No.430 of 2013, Petitioner cannot now turn around
    and contend to the contrary.
    
    
    67)               Considering the above position, in my view, the finding
    recorded by the Arbitral Tribunal about arbitrability of dispute relating to
    rejection of claim for overhauling of GT Engine cannot be termed as so
    grossly perverse that this Court must interfere in the Award. Before
    proceeding to discuss the case laws relied upon by rival parties, it would
    also be necessary to make a quick observation about rejection of
    Petitioner's contention before Arbitral Tribunal that since overhauling
    claim was covered by exclusion causes, the same was not arbitrable. The
    Tribunal has rejected Petitioner's contention by holding in paragraph 93
    as under:
    
    
                 93. Having regard to the above legal position, the Tribunal. or
                 consideration of the factual aspects of the matter, finds it difficult to
                 hold that the Respondent-Insurer has discharged its burden for the
                 following reasons:
                 (i) The two inspection reports of GE dated 19.10.2001 and 22.10.2001, in
                 the absence of any oral evidence of GE official let in by the Insurer, do
                 not establish the pre-existing condition of the Engine prior to its
                 dismantling and disassembling.
                 (ii) The Chart which has been placed on record by the Insurer indicating
                 break down repairs during the period March 1999 to September 2001
                 does not lead to any conclusion that repairs were necessitated or break
                 down happened because of erosion, corrosion, rust, oxidation or wear
                 and tear or lack of maintenance.
                 (iii) The incident that happened to the Engine on 30.04.2001 led to its
                 repairs by Air India. The Engine was reinstalled in the month of June,
                 2001 after the repairs were carried out to the satisfaction of GE. The
                 repairs by Air India only few months before the subject Accident do not
                 show anything like erosion, corrosion, oxidation etc, the grounds on
                 which the Respondent seeks to avoid its liability by invoking Excluded
                 Causes.
    _____________________________________________________________________________
    
                                          PAGE NO. 48 OF 77
    
                                            22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                       ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                     CARBP-10809-2024
    
    
    
    
                      (iv) The Joint Surveyors (RW-1 and RW-2) in their oral evidence have
                      stood by their First Interim Survey Report and Second Interim Survey
                      Report which record that from March 1999, until subject Accident after
                      necessary repairs, the GT Engine was functioning smoothly.
                      (v) During the period March 1999 to June 2001, the Respondent has
                      renewed Insurance policy on year-on-year basis.
                      (vi) The Joint Surveyors in their First Interim Survey Report were very
                      clear and categorical that the damage was accidental and the claim was
                      admissible under Industrial All Risk Policy issued to and held by Insured.
    
    
    68)               Again, the above findings do not warrant interference in
    exercise of jurisdiction under Section 34 of the Arbitration Act as the
    same are well supported by evidence on record. In any case, no serious
    attempt is made before me to demonstrate that the overhauling claim was
    covered by exclusion causes. The only complaint is about conflating of
    issues relating to excluded causes and accident being proximate cause of
    overhauling. The issue of accident being proximate cause for overhauling
    is discussed in latter part of the judgment. The argument of overhauling
    claim being based on the exclusion causes is raised to support the
    contention of absence of arbitration agreement and the said contention is
    rightly rejected by the Arbitral Tribunal.
    
    
    69)               Both the sides have relied upon judgments in support of their
    contentions about dispute relating to overhauling claim being dispute of
    quantum and dispute of liability. It would be apposite to first take stock of
    various judgments relied upon by Mr. Jagtiani on behalf of the Petitioner:
    
    
    A)                In United India Insurance Company Versus. Hyundai
    Engineering and Construction Company Limited (supra), there was a
    similar clause in the policy. The case involved an accident, and the claim
    
    _____________________________________________________________________________
    
                                             PAGE NO. 49 OF 77
    
                                                22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                          ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                       CARBP-10809-2024
    
    
    
    
    was repudiated by the insurance company. The Apex Court relied upon its
    judgment in Vulcan Insurance Company Limited Versus. Maharaj Singh
    (supra) and held in paragraphs 11 and 12 of the judgment as under:
    
    
                      11. The other decision heavily relied upon by the High Court and also by
                      the respondents in Duro Felguera [ (2017) 9 SCC 729 ] , will be of no avail.
                      Firstly, because it is a two-Judge Bench decision and also because the
                      Court was not called upon to consider the question which arises in the
                      present case, in reference to Clause 7 of the subject Insurance Policy.
                      The exposition in this decision is a general observation about the effect
                      of the amended provision and not specific to the issue under
                      consideration. The issue under consideration has been directly dealt
                      with by a three-Judge Bench of this Court in Oriental Insurance Co.
                      Ltd. [(2018) 6 SCC 534] , following the exposition in Vulcan Insurance Co.
                      Ltd. v. Maharaj Singh [(1976) 1 SCC 943] , which, again, is a three-Judge
                      Bench decision having construed clause similar to the subject Clause 7
                      of the Insurance Policy. In paras 11 and 12 of Vulcan Insurance Co. Ltd. ,
                      the Court answered the issue thus : (SCC pp. 948-49)
                                   "11. Although the surveyors in their letter dated 26-4-1963
                               had raised a dispute as to the amount of any loss or damage
                               alleged to have been suffered by Respondent 1, the appellant at
                               no point of time raised any such dispute. The appellant company
                               in its letters dated 5-7-1963 and 29-7-1963 repudiated the claim
                               altogether. Under Clause 13 the company was not required to
                               mention any reason of rejection of the claim nor did it mention any.
                               But the repudiation of the claim could not amount to the raising of a
                               dispute as to the amount of any loss or damage alleged to have been
                               suffered by Respondent 1. If the rejection of the claim made by the
                               insured be on the ground that he had suffered no loss as a result of
                               the fire or the amount of loss was not to the extent claimed by him,
                               then and then only, a difference could have arisen as to the amount
                               of any loss or damage within the meaning of Clause 18. In this case,
                               however, the company repudiated its liability to pay any amount
                               of loss or damage as claimed by Respondent 1. In other words,
                               the dispute raised by the company appertained to its liability to
                               pay any amount of damage whatsoever. In our opinion,
                               therefore, the dispute raised by the appellant company was not
                               covered by the arbitration clause.
                                   12. As per Clause 13 on rejection of the claim by the company an
                               action or suit, meaning thereby a legal proceeding which almost
                               invariably in India will be in the nature of a suit, has got to be
                               commenced within three months from the date of such rejection;
                               otherwise, all benefits under the policy stand forfeited. The rejection
    _____________________________________________________________________________
    
                                               PAGE NO. 50 OF 77
    
                                                  22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                            ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                        CARBP-10809-2024
    
    
    
    
                               of the claim may be for the reasons indicated in the first part of
                               Clause 13, such as, false declaration, fraud or wilful neglect of the
                               claimant or on any other ground disclosed or undisclosed. But as
                               soon as there is a rejection of the claim and not the raising of a
                               dispute as to the amount of any loss or damage, the only remedy
                               open to the claimant is to commence a legal proceeding, namely,
                               a suit, for establishment of the company's liability. It may well be
                               that after the liability of the company is established in such a
                               suit, for determination of the quantum of the loss or damage,
                               reference to arbitration will have to be resorted to in accordance
                               with Clause 18. But the arbitration clause, restricted as it is by the
                               use of the words 'if any difference arises as to the amount of any loss
                               or damage', cannot take within its sweep a dispute as to the liability
                               of the company when it refuses to pay any damage at all."
                                                                                 (emphasis supplied)
                               Again in para 22, after analysing the relevant judicial precedents,
                               the Court concluded as follows : (SCC p. 952)
                                   "22. The two lines of cases clearly bear out the two distinct
                               situations      in     law.      A     clause      like     the    one
                               in Scott v. Avery [Scott v. Avery, (1856) 5 HLC 811 : 10 ER 1121]
                               bars any action or suit if commenced for determination of a
                               dispute covered by the arbitration clause. But if on the other hand
                               a dispute cropped up at the very outset which cannot be referred to
                               arbitration    as     being     not    covered     by     the   clause,
                               thenScott v. Avery [Scott v. Avery, (1856) 5 HLC 811 : 10 ER
                               1121] clause is rendered inoperative and cannot be pleaded as a bar
                               to the maintainability of the legal action or suit for determination of
                               the dispute which was outside the arbitration clause."
                                                                                 (emphasis supplied)
    
                      12. From the line of authorities, it is clear that the arbitration clause has
                      to be interpreted strictly. The subject Clause 7 which is in pari materia to
                      Clause 13 of the policy considered by a three-Judge Bench in Oriental
                      Insurance Co. Ltd. [Oriental Insurance Co. Ltd. v. Narbheram Power and
                      Steel (P) Ltd., (2018) 6 SCC 534 : (2018) 3 SCC (Civ) 484] , is a conditional
                      expression of intent. Such an arbitration clause will get activated or
                      kindled only if the dispute between the parties is limited to the quantum
                      to be paid under the policy. The liability should be unequivocally
                      admitted by the insurer. That is the precondition and sine qua non for
                      triggering the arbitration clause. To put it differently, an arbitration
                      clause would enliven or invigorate only if the insurer admits or accepts
                      its liability under or in respect of the policy concerned. That has been
                      expressly predicated in the opening part of Clause 7 as well as the
                      second paragraph of the same clause. In the opening part, it is stated
    
    
    _____________________________________________________________________________
    
                                                PAGE NO. 51 OF 77
    
                                                  22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                             ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                       CARBP-10809-2024
    
    
    
    
                      that the "(liability being otherwise admitted)". This is reinforced and
                      restated in the second paragraph in the following words:
                                    "It is clearly agreed and understood that no difference or
                               dispute shall be referable to arbitration as hereinbefore provided,
                               if the Company has disputed or not accepted liability under or in
                               respect of this Policy."
                      Thus understood, there can be no arbitration in cases where the
                      insurance company disputes or does not accept the liability under or in
                      respect of the policy.
    
    
    Thus, the judgments in Hyundai Engineering and Construction Company
    Limited (supra) and Vulcan Insurance Company Limited (supra) are
    authorities on the issue that there must be unequivocal admission of
    liability by the insurer which is a pre-condition and sine qua non for
    triggering the arbitration clause. I do not see much difficulty in accepting
    the proposition that for triggering of arbitration clause, unequivocal
    admission of liability is necessary. The judgment however provides little
    assistance for deciding the issue at hand as the ratio of the judgment
    would have been helpful only if this Court was to hold that the claim for
    overhauling was segregable or that the liability in respect thereof was
    denied by the Petitioner by repudiating the claim.
    
    
    B)                In Oriental Insurance Company Limited Versus. Narbheram
    Power and Steel Pvt. Ltd. (supra), clause 13 of the policy did not permit
    reference to arbitration if the insurer had disputed or not accepted the
    liability. In the facts of that case, the insurer had repudiated the claim by
    denying to accept the liability for various reasons. In the present case,
    this Court is unable to record a finding that there is any denial of liability
    by the Petitioner in respect of claim for overhauling of the GT Engine.
    
    
    _____________________________________________________________________________
    
                                               PAGE NO. 52 OF 77
    
                                                 22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                            ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                  CARBP-10809-2024
    
    
    
    
    C)                In M/s. Malak Specialities (P) Ltd (supra), the claim was
    rejected despite surveyor assessing the amount payable to the insured. By
    relying on judgments in Narbheram Power & Steel Private Limited and
    Hyundai Engineering & Construction Company Limited (supra), this
    Court held that the insurer had not accepted the liability under the policy
    and had in fact repudiated the claim by denying to accept the liability.
    The judgment is thus rendered in the facts of that case and cannot have
    any possible application to the present case.
    
    
    D)                In Sanghi Industries Limited (supra), there was similar
    arbitration clause No.12 restricting arbitration only to quantum disputes.
    The insurer treated the claim in two parts as the insured had claimed
    reimbursement of damage because of breakdown of machinery and a
    claim for loss of profits. The first claim of damage caused to the plant and
    machinery was cleared by the insurer and the claim for loss of profits was
    rejected. It is in the facts of that case that the Gujarat High Court held
    that the claim was in two parts and sanctioning of first part did not have
    any correlation with rejection of the second part.
    
    
    E)                In Kohinoor Steel Pvt. Ltd. (supra), Single Judge of Calcutta
    High Court has decided the application under Section 11 of Arbitration
    Act in a case involving similar arbitration clause. During commissioning
    of the plant, a thunderstorm had seriously damaged the crane and
    overhead water-tank. The insurer allowed the claim for overhead tank but
    refused the same in respect of the crane on the ground that the crane was
    already operationalised and a clause in the policy did not cover something
    
    _____________________________________________________________________________
    
                                          PAGE NO. 53 OF 77
    
                                            22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                       ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                      CARBP-10809-2024
    
    
    
    
    which was already operationalised. Therefore, liability in respect of the
    crane was denied. Thus, the case involved inadmissibility of claim in
    respect of the crane which was already operationalised and rejection of
    liability in respect thereof by the insurer. The judgment is clearly
    distinguishable and cannot have any application to the present case
    where the claim for overhauling is neither separable nor capable of being
    rejected by segregating the same from repair claim arising out of incident.
    The judgment in Kohinoor Steel Private Limited (supra) is otherwise
    distinguished in judgments relied upon by Mr. Rustomjee.
    
    
    F)                In Metal Crafts Engineering Pvt. Ltd. (supra), Single Judge of
    Calcutta High Court has again decided Application under Section 11 of
    Arbitration Act and the case involved total rejection of the claim in
    entirety unlike splitting of one claim into two parts as is done in the
    present case. The judgment is thus clearly distinguishable.
    
    
    G)                In     New      India   Assurance         Company       Limited       Versus.
    Ampoules and Vials Manufacturing Co. Ltd.(supra), Single Judge of this
    Court has dealt with similar clause in the insurance policy. The insurer
    had approved the claim for Rs 1.59 crores as against the claim of the
    insured of Rs.3.55 crores. The insured signed discharge voucher for
    Rs.1.59 crores and sought to raise claim in respect of balance non-
    sanctioned amount. The insurer repudiated the liability under the policy
    in respect of balance amount. In the facts of that case, this Court held
    that there was accord and satisfaction and complete discharge of liability
    upon signing of discharge voucher and the case involved repudiation of
    
    _____________________________________________________________________________
    
                                              PAGE NO. 54 OF 77
    
                                                22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                           ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                  CARBP-10809-2024
    
    
    
    
    liability. It must be observed here that the judgment in Ampoules and
    Vials Manufacturing Co. ltd. (supra) does not contain detailed discussion
    as to why non-sanctioning part of the claim could not be treated as
    dispute relating to quantum. Also, in view of law subsequently developed,
    it is difficult to hold that the judgment in Ampoules and Vials
    Manufacturing Co. ltd. can be read to mean an abstract proposition that
    in every case where discharge voucher is signed, the dispute relating to
    balance unpaid amount would be that of liability and not quantum. In
    recent judgment in Krish Spinning (supra) the Supreme Court has held to
    the contrary.
    
    
    H)                In EC Wheels India Private Ltd. (supra), a Single Judge of the
    Calcutta High Court has decided an application under Section 11 of the
    Arbitration Act for appointment of Arbitrator. The case involved
    repudiation of entire claim and not one part of the claim raised by the
    insured. An argument was sought to be raised before the High Court that
    negation of claim was also a dispute regarding quantum, which is not
    accepted in the judgment. The judgment in my view is clearly
    distinguishable and has no application to the facts of the present case.
    
    
    I)                In English judgment in New Hampshire Insurance Company
    Versus. Strabag Bug AG (supra) the case involved total repudiation of the
    entire claim which is the first distinguishing factor from the present case.
    The judgment is cited in support of proposition that though a dispute
    relates to amount arising out of prima-facie acceptance of liability, if it
    depends on application of particular provisos or exemptions in the policy,
    
    _____________________________________________________________________________
    
                                          PAGE NO. 55 OF 77
    
                                            22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                       ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                  CARBP-10809-2024
    
    
    
    
    the same would raise a question of liability rather than mere dispute of
    quantum. The judgment would have been relevant in the present case if
    Petitioner was in a position to demonstrate that the claim for overhauling
    of GT Engine was covered by exclusion causes, which the Petitioner has
    failed to demonstrate. The judgment therefore has no application to the
    facts of the present case.
    
    
    J)                Lastly, Mr. Jagtiani has relied on judgment of High Court of
    England in DC Bars Ltd. (supra). Apart from the fact that the decision
    would only have persuasive value, the case involved rejection of claims
    towards distinct and separate periods for which losses were claimed. It
    was held that the dispute related to liability in respect of each of those
    periods and the same did not relate to quantum. The judgment again is of
    little assistance to the Petitioner since the present case does not involve
    raising of multiple claims for different periods.
    
    
    70)               On the other hand, Mr. Rustomjee has relied upon various
    judgments in support of his contention that the dispute relating to
    overhaul claim is a dispute of quantum and not of liability. It would be
    apposite to discuss the ratios of the judgments relied upon by Mr.
    Rustomjee.
    
    
    A)                In M/s. LS Automotive India Private Limited (supra), Single
    Judge of Madras High Court, while deciding Section 11 Application has
    dealt with a case where the insurer's policy gave coverage for raw material
    as well. The insurer however sanctioned only the claim relating to damage
    
    _____________________________________________________________________________
    
                                          PAGE NO. 56 OF 77
    
                                            22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                       ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                  CARBP-10809-2024
    
    
    
    
    caused by floods. The insurer treated non-sanctioning of claim for
    damage/loss of raw materials as rejection of liability. The Single Judge of
    Madras High Court however held that the case involved making of part
    payment in respect of a single claim and that therefore the dispute was
    arbitrable. Though Mr. Jagtiani has sought to distinguish the judgment on
    the ground that Madras High Court has done only a limited scrutiny under
    Section 11 of the Arbitration Act, the judgment is ultimately based on
    Supreme Court judgment in Krish Spinning (supra), which is being
    discussed in latter part of the judgment.
    
    
    B)                In M/S. TRS Lift and Shift Services Pvt. Ltd. (supra) a Single
    Judge of Calcutta High Court, while dealing with application under
    Section 11 of Arbitration Act and dealing with similar clause in insurance
    policy, has held that the liability was partially admitted and that therefore
    dispute relating to non-payment of balance amount was that of quantum
    and not of liability.
    
    
    C)                In Tagros Chemicals India Pvt Ltd (supra), a Single Judge of
    Madras High Court, while deciding application under Section 11 of
    Arbitration Act, has discussed the entire case law on the subject. The case
    involved two claims for material damage and business interruption. The
    insurer sanctioned the claim for material damage, but disputed its
    liability in respect of business interruption claim. The Madras High Court
    considered the judgments in Hyundai Engineering & Construction
    Company Limited, Narbheram Power & Steel Pvt. Ltd., (supra) as well as
    judgment of the Delhi High Court in Kohinoor Steel Pvt. Ltd. (supra) and
    
    _____________________________________________________________________________
    
                                          PAGE NO. 57 OF 77
    
                                            22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                       ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                     CARBP-10809-2024
    
    
    
    
    held that the incident which triggered the claim was one and that the loss
    claimed under the head 'business interruption' was directly and
    substantially connected to claim for 'material damage', for which liability
    was admitted. It is held that the judgment of the Apex Court in Krish
    Spinning (supra) has watered down the ratio of the judgments in Hyundai
    Engineering and Construction Company Limited, Narbheram Power and
    Kohinoor Steel Private Limited (supra). The Madras High Court has held
    in paragraphs 22 to 24 and 26 as under:
    
    
                      22. I am unable to agree with the submissions of the learned Senior
                      Counsel appearing for the Respondent. The incident that has triggered
                      the claim is admittedly one, unlike in the case of Kohinoor Steel and the
                      loss claimed under the head 'business interruption' is directly and
                      substantially connected to 'material damage' which is admittedly
                      accepted to be indemnified by the insurance company. In fact, as already
                      discussed above, the Respondent has already released substantial
                      payments towards 'material damage' and they are only disputing the
                      claim of the Petitioner on quantum. Therefore, in my considered view
                      the claim for business interruption cannot be dissected or segregated
                      from the total claim made by the Petitioner, though it may be under two
                      heads for which separate premiums have been paid. The documents that
                      may be relied on by the parties and the evidence that may be let in would
                      also be the same, leave alone the same parties being examined as
                      witnesses before either the Arbitrator or the Court.
    
                      23. As held by Hon'ble Supreme Court in SBI General Insurance Co. Ltd.,
                      (referred herein supra) when a valid arbitration agreement exists, then
                      the reference cannot fall back on 'Eye of the Needle' and 'ex facie
                      meritless' tests, since the principles of modern arbitration place arbitral
                      autonomy and judicial non-interference on the highest pedestal. Here
                      having found that business interruption loss is related to material
                      damage, it is not open to the Insurance Company to contend that since
                      the claim 'business interruption loss' is repudiated, the said issue cannot
                      be referred to the decision of the Arbitrator.
    
                      24. The decisions relied on by learned Senior Counsel Mr.M.S.Krishnan
                      appearing for the Respondents is also clearly distinguishable on facts. In
                      fact, as held by the Hon'ble Delhi High Court in Payoo Payment's
                      case, (referred herein supra), there has been a shift in the legal
    _____________________________________________________________________________
    
                                             PAGE NO. 58 OF 77
    
                                                22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                          ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                     CARBP-10809-2024
    
    
    
    
                      position with the pronouncement of the Hon'ble Supreme Court in
                      SBI General Insurance Co. Ltd. v. Krish Spinning, and consequently
                      the decisions of the Hon'ble Supreme Court in Oriental Insurance
                      Company and United India Insurance Company, have been watered
                      down. In the decision of the Hon'ble Calcutta High Court, the claim was
                      in respect of two distinct items, namely, a crane and an overhead tank
                      and with the High Court finding that the claim on the count of the crane
                      was beyond the scope of the arbitration agreement, it was held that the
                      arbitration could proceed only in respect of the overhead tank and not
                      the crane. Though much reliance has been placed on by learned Senior
                      Counsel on this decision, to apply to the facts of the case, I am unable to
                      countenance the said contention, because in the said case before the
                      Hon'ble Calcutta High Court, the items in respect of which the claim was
                      made were entirely distinct and different, namely, a crane and an
                      overhead tank. However, in the present case, there is no such
                      distinctiveness in respect of the subject matter of the claim. Both the
                      'material damage' as well as the 'business interruption claim' arise out of
                      the fire accident that occurred on 07.04.2020 and in fact, as already
                      discussed even the claim under ' business interruption loss' is directly
                      associated with the 'material damage' claim.
    
                      26. Be that as it may, in the present case I am unable to accept the
                      contention of the Insurance Company that since they are repudiating
                      the business interruption claim part, the same cannot be referred to
                      arbitration. Since the business interruption loss claim is clearly
                      dependent on the material damage claim which is accepted even by
                      the Insurance Company under the policy, it has to be decided by
                      arbitration alone. It is not as though the claims for material
                      damage and business interruption are totally distinct and
                      unconnected altogether. The very business interruption Clause in
                      Section II itself, clearly refers to the indemnity Clause to material
                      damage suffered by the policy holder. Therefore, both the claims are
                      intertwined and cannot be separated, relegating the parties to litigate
                      before different Forums, one before the Arbitrator and another before
                      the Civil Court.
                                                                          (emphasis added)
    
    
    
    Thus in Tagros Chemicals India Pvt Ltd Madras High Court has held
    rejection of business interruption claim did not mean that the same was
    non-arbitrable. The present case is far better than Tagros Chemicals
    India Pvt Ltd since both the claims are sanctioned here. The dispute
    
    
    _____________________________________________________________________________
    
                                             PAGE NO. 59 OF 77
    
                                                22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                          ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                      CARBP-10809-2024
    
    
    
    
    relates to only non-payment of part of the claim for repairs arising out of
    the accident.
    
    
    D)                The Delhi High Court, in Nagarjuna Agrichem Ltd. (supra),
    has decided Section 34 Petition. The issue before the Delhi High Court
    was about coverage in respect of stock when fire had caused damage to
    the plant. The Delhi High Court held that since part payment was made
    for material damage, the liability under the insurance policy was admitted
    and that therefore, the dispute related to the quantum which was clearly
    arbitrable. The Delhi High Court held in paragraphs 98, 120 and 121 as
    under:
    
                      98. It is pertinent to mention here that in the present case, the insurance
                      company has made part payment from the material damage process of
                      the respondent. It is also pertinent to mention here that if the liability
                      under the BPM Policy has been admitted, it is unjustified to deny the
                      liability under the stock policy. The Court considers that no fault can be
                      found with the finding of the learned AT.
    
                      120. Learned counsel for the petitioner has heavily relied upon United
                      India Insurance Co. Ltd. v. Hyundai Engineering and Construction Co.
                      Ltd. (2018) SCC OnLine SC 1045 and Oriental Insurance Co. Ltd. v.
                      Narbheram Power and Steel Pvt. Ltd. (2018) 6 SCC 534. However, the
                      case at hand is distinct from United India Insurance Co. Ltd. (Supra) and
                      Narbheram Power and Steel Pvt. Ltd. (Supra) on several fundamental
                      legal and factual grounds. Though, the cases concern insurance disputes,
                      yet they differ significantly in terms of arbitrability, the enforceability of
                      discharge vouchers, policy interpretation, and the weight given to
                      surveyor reports.
    
                      121. A key distinguishing factor is the question of arbitrability, which
                      played a decisive role in United India Insurance Co. Ltd. (Supra) and
                      Narbheram Power and Steel Pvt. Ltd. (Supra). In the aforesaid cases,
                      the Apex Court unequivocally ruled that when an insurance company
                      entirely denies liability, arbitration is not permissible under the terms of
                      the insurance contract. It was, inter alia, held that if the insurer
                      repudiates the claim altogether and there exists no dispute over
                      quantum. The Court, inter alia, held that such matters must be
                      adjudicated in a civil court. However, in the present case, the petitioner
    _____________________________________________________________________________
    
                                              PAGE NO. 60 OF 77
    
                                                 22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                           ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                      CARBP-10809-2024
    
    
    
    
                      did not completely repudiate liability but instead partially admitted
                      liability and even made partial payments under the material damage
                      policy. In the present case, the learned Arbitral Tribunal, inter alia,
                      found that the insurer, by making partial payments and engaging in
                      negotiations, had waived its right to object to arbitrability.
    
    
    
    E)                In Karan Synthetics (I) Pvt. Ltd. (supra), the issue before
    Single Judge of Gujarat High Court, involved fire causing loss in the
    factory and sanctioning of part of the claim. The Gujarat High Court has
    held in paragraph 4 as under:
    
    
                      4. Having heard learned counsel for the parties and having perused the
                      material on record, none of the objections can be accepted. Firstly, the
                      arbitration clause does envisage arbitration only in case of disputes
                      in quantum of the insurance to be paid and would not cover a case
                      where entire liability has been repudiated by the insurance
                      company. It is in this context clause13 provides that if any disputes of
                      difference arises as to quantum to be paid under the policy
                      (liability being otherwise admitted) such difference shall be referred to
                      arbitration. However, in the present case, there is nothing on record to
                      suggest that the insurance company disowned its liability. Firstly,
                      admittedly the insurance company has not formally repudiated
                      the claim by accepting its surveyor's opinion that the cause of fire
                      would not justify paying any insurance sum at all. Secondly, the
                      act     of    insurance company to appoint an arbitrator itself would
                      demonstrate that it is not a case of total denial of the liability. Thirdly,
                      the very offer of payment of Rs.1,56,000/ would negate any such stand of
                      the company. Lastly the opinions of the arbitrators already appointed by
                      the parties also would not be conclusive. The arbitration Tribunal
                      would be constituted only in the manner provided in clause13 when
                      two arbitrators appointed by rival parties would select and appoint a
                      third arbitrator. Till this time, this is done any opinion by the arbitrator
                      would not form final and binding opinion since no such Tribunal ever
                      came in existence. Regarding jurisdiction admittedly the insurance
                      policy was issued by the insurance company from Ahmedabad office.
                      Such objection is therefore, turned down.
    
    
    
    F)                In Amlagora Cold Storage (P) Ltd. (supra), Single Judge of
    Calcutta High Court has held in paragraphs 98 and 99 as under:
    
    _____________________________________________________________________________
    
                                              PAGE NO. 61 OF 77
    
                                                22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                           ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                      CARBP-10809-2024
    
    
    
    
                      98. It was submitted on behalf of the Insurance Company that the said
                      arbitration clause provides that if the company disclaims liability to the
                      insured for any claim and such claim was not within 12 calendar months
                      from the date of such disclaimer, made the subject-matter of a suit in a
                      Court of law, then the claim shall for all purposes be deemed to have
                      been abandoned and shall not thereafter be recoverable under the
                      policy. The policy also provides that if there is any difference with regard
                      to the quantum to be paid up under the said policy, the liability being
                      otherwise admitted such difference is referable to arbitration. The point
                      raised is, was it a case of disclaimer of liability or was it a case of
                      difference as to quantum to be paid where the liability was otherwise
                      admitted. It is apparent that the insurance company admitted the
                      liability and its Board of Directors approved the payment of such
                      liability. The quantum of such liability was fixed by the insurance
                      company at Rs. 12,19,060/-. Therefore in my opinion this was a case
                      where the dispute was with regard to the quantum to be payable. This
                      was not a case where the insurance company disclaimed liability. I am
                      unable to accept the submission made on behalf of the insurance
                      company that since the quantum was disputed by the insurance
                      company therefore there was a disclaimer of liability in respect of the
                      balance of the unpaid amount. If that contention is to be accepted then
                      it will lead to absurdities because in each and every case whereever there
                      is dispute as to the quantum of the liability the same cannot go to
                      arbitration as balance amount will in all cases be disclaimed. Such
                      interpretation will defeat the very purpose of the amended arbitration
                      clause which provides that in case where the quantum of the liability is
                      in dispute the same will be determined by reference to the arbitration.
    
                      99. In the instant case since there was a dispute as to the quantum of
                      liability, the plaintiff did commence the arbitration proceedings. The
                      said arbitration proceedings were ultimately disposed of by a consent
                      order made in the appeal being the order dated April 2, 1981.
    
    
    
    G)                In Keller N Am Inc. (supra), the US District Court has dealt
    with slightly similar clause and has held that when some liability is
    admitted, the question is about 'how much' the defendants are required
    to pay and not 'whether' they are required to pay.
    
    
    H)                In Press Metal Sarawak SDN BHD (supra), the Malaysian
    Federal Court has held that the question as to whether remaining part of
    _____________________________________________________________________________
    
                                              PAGE NO. 62 OF 77
    
                                                22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                           ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                     CARBP-10809-2024
    
    
    
    
    claim was barred by exclusion cause was a quantum dispute falling within
    the arbitration clause.
    
    
    71)               This brings the Court to the ratio of                  judgment of the
    Supreme Court in Krish Spinning (supra). The case before the Apex Court
    involved identical arbitration clause. Two incidents of fire had taken place
    at the factory premises of the Respondent therein. In respect of the first
    fire incident, a claim for Rs. 1.76 crores was raised, but the Appellant
    therein allowed the claim only in the sum of Rs. 84.19 lakh. The
    Respondent therein signed the advance discharge voucher and received
    Rs. 84.19 lakh towards full and final settlement of the claim arising out of
    the first fire incident. Thereafter, claim relating to second fire incident
    was raised and total amount of Rs.4.86 crores was released in three
    installments. Before release of second and third installments, Respondent
    sought to create dispute relating to surveyor's final assessment report in
    respect of the first fire incident and took a position that final discharge
    voucher was signed under duress. The Respondent therein pressed the
    claim for balance amount in respect of first fire incident. Petition under
    Section 11 was filed before the High Court which was resisted by the
    insurer The Apex Court held that since amount of Rs.84.19 lakhs was
    paid, there was admission of liability and the issue related only to
    quantum of liability. The Apex Court held as under:
    
    
                      38. A preliminary objection was raised on behalf of the appellant that
                      the arbitration clause as contained in the insurance policy referred to
                      above is not attracted in the present case as there is no admission of
                      liability on the part of the appellant, whereas the said arbitration clause
    
    
    _____________________________________________________________________________
    
                                             PAGE NO. 63 OF 77
    
                                                22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                          ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                      CARBP-10809-2024
    
    
    
    
                      envisages reference to arbitration only in cases where liability is
                      admitted and there is a dispute as regards the quantum of liability.
    
                      39. However, we find no merit in the aforesaid submission of the
                      appellant. It is evident from the record that the appellant had admitted
                      its liability with respect to the first claim and had even disbursed an
                      amount of Rs 84,19,579/- in pursuance of the signing of the advance
                      discharge voucher by the respondent. Thus, it is clearly a case of
                      admission of liability by the appellant. However, the quantum of liability
                      is in dispute as the amount claimed by the respondent is at variance with
                      the amount admitted by the appellant. Thus, the dispute being one of
                      quantum and not of liability, it falls within the ambit of the conditional
                      arbitration clause as contained in the insurance policy.
    
    
    
                      55. Thus, even if the contracting parties, in pursuance of a settlement,
                      agree to discharge each other of any obligations arising under the
                      contract, this does not ipso facto mean that the arbitration agreement
                      too would come to an end, unless the parties expressly agree to do the
                      same. The intention of the parties in discharging a contract by "accord
                      and satisfaction" is to relieve each other of the existing or any new
                      obligations under the contract. Such a discharge of obligations under the
                      substantive contract cannot be construed to mean that the parties also
                      intended to relieve each other of their obligation to settle any dispute
                      pertaining to the original contract through arbitration.
    
                      57. The aforesaid position of law has also been consistently followed by
                      this Court as evident from many decisions. In Boghara Polyfab (supra),
                      while rejecting the contention that the mere act of signing a "full and
                      final discharge voucher" would act as a bar to arbitration, this Court held
                      as follows:
                              "44. ... None of the three cases relied on by the appellant lay down a
                              proposition that mere execution of a full and final settlement receipt
                              or a discharge voucher is a bar to arbitration, even when the validity
                              thereof is challenged by the claimant on the ground of fraud,
                              coercion or undue influence. Nor do they lay down a proposition that
                              even if the discharge of contract is not genuine or legal, the claims
                              cannot be referred to arbitration. [...]"
    
                 59. The position that emerges from the aforesaid discussion is that there
                 is no rule of an absolute kind which precludes arbitration in cases where
                 a full and final settlement has been arrived at. In Boghara
                 Polyfab[National Insurance Co. Ltd. v. Boghara Polyfab (P) Ltd., (2009) 1
                 SCC 267 : (2009) 1 SCC (Civ) 117] , discussing in the context of a case
                 similar to the one at hand, wherein the discharge voucher was alleged to
                 have been obtained on ground of coercion, it was observed that the
    _____________________________________________________________________________
    
                                              PAGE NO. 64 OF 77
    
                                                 22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                           ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                     CARBP-10809-2024
    
    
    
    
                      discharge of a contract by full and final settlement by issuance of a
                      discharge voucher or a no-dues certificate extends only to those
                      vouchers or certificates which are validly and voluntarily executed. Thus,
                      if the party said to have executed the discharge voucher or the no-dues
                      certificate alleges that the execution was on account of fraud, coercion
                      or undue influence exercised by the other party and is able to establish
                      such an allegation, then the discharge of the contract by virtue of
                      issuance of such a discharge voucher or no-dues certificate is rendered
                      void and cannot be acted upon.
    
    
    
    72)               Thus, in Krish Spinning (supra) though a discharge voucher
    was signed and executed and claim was later raised for balance unpaid
    amount, the Apex Court has held that there was admission of liability of
    part of claim and that therefore the dispute related to quantum and not of
    liability. Though the judgment in Krish Spinning essentially applies to a
    case involving accord and satisfaction, it underscores an important point
    that once the liability is admitted and part payment in respect of the
    claim is made, the dispute relating to unpaid part is a dispute of quantum
    and not of liability. The Three Judge Bench judgment in Krish Spinning
    (supra) thus settles the law relating to arbitrability of disputes involving
    insurance claim where part of the liability is admitted and dispute exists
    in respect of unpaid part.
    
    
    73)               In the present case, one singular claim relating to expenses
    incurred by Respondent for repairing GT Engine was submitted.
    Petitioner admitted its liability in respect of part of the claim and paid
    amount of Rs.7.69 crores. The dispute was thus about 'how much' amount
    was payable and not 'whether' any amount is at all payable. Qua part of
    claim for which payment is not made, the dispute would obviously be the
    one relating to quantum and not a dispute relating to liability. I am not
    _____________________________________________________________________________
    
                                             PAGE NO. 65 OF 77
    
                                                22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                          ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                  CARBP-10809-2024
    
    
    
    
    inclined to accept the hair-splitting exercise sought to be now suggested
    by Petitioner that it always treated Respondent's claim as in two parts. It
    never did so. It always treated the entire claim as a single indivisible
    claim, but sanctioned part of it. It has taken a position that it would pay
    only the claim for part of repairs and not for the entire repairs. Repairs to
    the engine due to accident would also get covered by overhauling. If one
    considers the options given by GE, Option No.1 gets included in Option
    No.3. In Option No.1, repairs to only rotating parts (HPC, HPT) were to be
    carried out. In option, which envisaged overhauling of the engine, in
    addition to repairs of rotating parts of HPT and HPC, several other repairs
    in respect of various other parts of the engine were to be carried out. Thus
    even the option for overhauling ultimately included repairs to the GT
    Engine. In my view, the extent of repairs could not have been a factor for
    sub-dividing the claim into 'incident repairs' and 'overhauling'. The
    Petitioner itself never segregated the same into two claims. Therefore, the
    submission from Petitioner's standpoint, that incident claim and overhaul
    claim arose from distinct legal obligations is misplaced. Petitioner never
    directed Respondent to submit two separate claims for 'incident repairs'
    and for 'overhauling'. Initially it coaxed the Respondent to go for
    overhauling and later sought to restrict the insurance claim only for part
    of the repairs. Therefore, non-sanction of remaining part would clearly be
    a dispute relating to quantum. More importantly even at the stage of
    issuing of the cheque, Petitioner did not state that it was disputing
    liability for overhaul claim by segregating the Respondent's claim in two
    parts.
    
    
    
    _____________________________________________________________________________
    
                                          PAGE NO. 66 OF 77
    
                                            22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                       ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                  CARBP-10809-2024
    
    
    
    
    74)               Respondent raised two claims arising out of the incident, the
    first claim being the incident claim and the second one being for business
    interruption. Both the claims are sanctioned by the Petitioner. However
    the sanction of the first claim was only partial. Therefore non-sanction of
    the full amount for the first claim is obviously a dispute relating to
    quantum, which is arbitrable. Clause 12 would make a dispute non-
    arbitrable only if there is total denial of liability in respect of the claim.
    Once the claim is entertained and sanctioned partly, non-sanction of
    remaining part does not amount to denial of liability in respect of the
    claim. Once part of the claim is not accepted, dispute raised in respect of
    denied part cannot tantamount to non-acceptance or denial of liability in
    respect of the 'claim'. For being non-arbitrable the entire claim must be
    repudiated in toto. The moment the claim is sanctioned in part, the
    dispute relating to denied part becomes dispute relating to the quantum
    of the raised claim. The case thus involves admission of liability in respect
    of the first claim and the dispute was clearly arbitrable.
    
    
    75)               Therefore, no case is made out for invalidating the Arbitral
    Award in so far as it relates to the findings on the issue of arbitrability.
    
    
    WHETHER INCIDENT/ACCIDENT IS A PROXIMATE CAUSE OF OVERHAULING OF
    GT ENGINE
    
    
    76)               A defense was taken by Petitioner-Insurance Company that
    overhauling of GT Engine was required to be undertaken on account of
    wear and tear resulting out of corrosion, rust etc. Petitioner contended
    that the incident of 16 September 2001 did not necessitate the
    _____________________________________________________________________________
    
                                          PAGE NO. 67 OF 77
    
                                            22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                       ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                     CARBP-10809-2024
    
    
    
    
    overhauling. The Tribunal has rejected the defence of the Petitioner and
    has held that the incident/accident was the proximate cause of
    overhauling. The Tribunal held in paragraphs 149 to 153 of the Award as
    under:
    
                      149. The question for consideration by the Tribunal is, whether the
                      Respondent was justified in declining to cover overhauling costs of the
                      GT Engine? The determination of this question would necessarily
                      require determination of the question, whether or not, overhauling was
                      necessitated by the incident of 16.09.2001.
                      150. As a matter of fact, the Respondent in its written submissions under
                      the head 'REASONS FOR DENIAL OF LIABILITY OF THE OVERHAULING
                      COSTS THE GT ENGINE' as taken up the position that Overhauling
                      Costs are specifically excluded in terms of 'Excluded Causes' under the
                      Policy. While dealing with the arbitrability issue, the Tribunal has
                      already negated this contention of the Respondent. The consideration of
                      the matter by the Tribunal in preceding paragraphs on the aspect of
                      Excluded causes shall form of part of consideration of this aspect here as
                      well. However, the reasons for the Tribunal's finding that the coverage of
                      Overhauling Costs under and in respect All Risk Policy is not excluded
                      under 'Excluded Causes' may be briefly noted here as well.
                             (i) First, the Respondent itself had insisted the Claimant to have
                             GT Engine overhauled as recommended by GE and its Surveyors
                             (Inspectors) in America. This is very clear from the Respondent's
                             letter dated 05.12.2023. It the Overhauling costs were excluded
                             and if they were out of coverage or unpayable by them, there was
                             no occasion for the Respondent to insist for overhauling the
                             Engine.
                             (ii) Second, By the time the above letter dated 05.12.2001 was
                             sent by the Respondent to Claimant, the Respondent had full
                             knowledge about the condition of the GT Engine which was
                             recorded by GE in its Detailed Report dated 19.10.2001. All issues
                             with the diverse components of GT
                             Engine including inter alia erosion, corrosion, rust, wear and tear
                             were
                             within the knowledge of the Respondent. If the Detailed Report
                             of GE dated 19 10 2001 were sufficient to bring the GT Engine
                             under Excluded Causes, the Respondent would not have written
                             the letter dated 05.12.2001 which it did. Rather on the other
                             hand, the Respondent made a clear representation to the
                             Claimant to go in for overhauling of the GT Engine in the
                             backdrop of entire available material available with it depicting
                             the condition of the GT Engine.
    _____________________________________________________________________________
    
                                             PAGE NO. 68 OF 77
    
                                                22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                          ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                      CARBP-10809-2024
    
    
    
    
                               (iii) Third, if the overhauling costs were not admissible under the
                               Policy, the first thing the Respondent would have done once it
                               got to know GE's Report dated 19.10.2001, and got its Inspectors'
                               communication for overhauling of the Engine to communicate to
                               the Claimant that Overhauling Costs fall in Excluded Causes and
                               therefore such claim was inadmissible. On the other hand, the
                               Respondent's letter dated 05.12.2001 to the Claimant was
                               followed by another letter dated 18.12.2001 (By that time limited
                               repairs of GT Engine were already carried out but transient
                               vibrations beyond permissible limits were detected in the Engine
                               during testing and GE had given three options including
                               overhauling to the Claimant) wherein the Respondent reiterated
                               that it would be advisable for the Claimant to repair the entire
                               Engine as recommended by GE.
                               (iv) Fourth, the two inspection reports of GE dated 19.10.2001
                               and 22.10.2001, in the absence of any oral evidence of GE official
                               let in by the Respondent, do not establish the pre-existing
                               condition of the Engine prior to its dismantling and
                               disassembling.
                               (v) Fifth, the events which the Respondent has highlighted about
                               the GT Engine from January 1999 to September 2001 in the
                               written submissions under the head 'The GT Engine was in poor
                               condition even pre-accident' are also summarised by way of chart
                               on arbitrability issue. In the Tribunal's considered opinion, the
                               chart does not lead to any conclusion that repairs were
                               necessitated or breakdown happened because of erosion,
                               corrosion, rust, oxidation or wear and tear or lack of
                               maintenance. As a matter of fact, the Respondent has admitted
                               in the written submissions that the GT Engine has been running
                               for the durations of 535- 735 hours per month in the year 1999. It
                               the Engine had the Issues which the Respondent has highlighted,
                               the GT Engine would not have been in position to run for so
                               many hours every month. GT Engine is a highly sophisticated
                               machine. While in use, it may have had certain issues which
                               needed corrections and in fact such corrections were done. This
                               leads to an inference that GT Engine was not in poor condition
                               prior to Accident as is sought to be made out by the Respondent.
                               As late as on 30.04.2001, some bearing issue with the Engine
                               arose. For repairs of this, the Engine was sent to Air India
                               workshop. The Engine was reinstalled in the month of June 2001
                               after the repairs were carried out to the satisfaction of GE. The
                               repairs by Air India carried out only few months before the
                               subject Accident do not show something like erosion, corrosion,
                               oxidation, rust etc., the grounds on which the Respondent seeks
                               to bring the case for overhauling costs under the Excluded Causes.
    
    
    _____________________________________________________________________________
    
                                              PAGE NO. 69 OF 77
    
                                                 22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                           ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                     CARBP-10809-2024
    
    
    
    
                      151. Respondent's own witness Mr. Soumil Menta (RW-3) has deposed in
                      his cross-exanimation that if overhauling was not carried out, GT Engine
                      would not have run after the accident. That the GT Engine was in a poor
                      condition prior to Accident has not been found meritorious by the
                      Tribunal. The Claimant at the first instance, despite recommendation of
                      GE for overhauling of the Engine and Respondent's insistence to go in
                      for overhauling of the Engine as advised by GE and the report of
                      McLarens Toplis, asked GE to carry out limited repairs. This act of the
                      Claimant was in consonance with the principle that as a prudent
                      insured, the Claimant was required to do a thing that would have
                      mitigated the loss to the insurer. However, the limited repairs were not
                      successful. The other two options given by the GE would not have
                      rendered the Engine fully fit and functional. It is, therefore, established
                      on record that GT Engine required overhauling after the Accident to run
                      smoothly and continuously.
    
                      152. In the Survey Reports, the Joint Surveyors have opined that the
                      damage suffered by the GT Engine could be rectified by the balancing of
                      HPC and HPT rotors. The Tribunal finds it difficult to accept the above
                      conclusion of the Joint Surveyors as RW3 has admitted in his cross-
                      examination that there was no technical basis to indicate that the GT
                      Engine would have run smoothly without overhauling.
    
                      153. As a matter of fact, there is ample material on record including
                      various letters/communications of GE, McLarens Toplis and the letters
                      of the Respondent itself which clearly show that it was imperative to
                      overhaul the GT Engine and the accident was the proximate cause of the
                      overhauling. The Tribunal does not find any merit in the argument of
                      the learned senior counsel for the Respondent that Claimant has failed
                      to discharge its burden of proving that overhauling was necessitated due
                      to the Accident. The judgment of the Supreme Court in Bajaj Allianz
                      General Insurance Company (supra), in the light of observations made
                      above, has no application to the fact situation of the present case.
    
    
    77)               Mr. Jagtiani has criticized the Arbitral Tribunal for having
    recorded the finding of accident being proximate cause of overhauling on
    the basis of "various letters/communications of GE, M/s. McLarens Toplis
    and letters of the Respondent". According to Mr. Jagtiani, none of the three
    quoted material even remotely suggest the accident to be the proximate
    cause requiring the overhauling. I am unable to accept the contention
    
    _____________________________________________________________________________
    
                                             PAGE NO. 70 OF 77
    
                                                22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                          ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                  CARBP-10809-2024
    
    
    
    
    raised by Mr. Jagtiani. The Arbitral Tribunal has used the word
    "including" meaning thereby that the material enumerated by it is not
    exhaustive and that the finding is recorded by considering several other
    materials available on record. Whether the incident/accident is a
    proximate cause for overhaul of GT Engine or not is a question of fact on
    which the Tribunal has ruled in favour of the Respondent. I have my own
    limitations in exercising jurisdiction under Section 34 of the Arbitration
    Act in examining correctness of those findings of fact. It is not necessary
    to discuss the settled position of law relating to limitations on jurisdiction
    of Section 34 Court in considering objections to Arbitral Award. It is only
    in cases where an extreme perversity is demonstrated or where the
    finding recorded by the Arbitral Tribunal is such that no fair-minded
    person can ever record the same that Section 34 Court would be justified
    in reversing the finding on fact. In my view, Petitioner has thoroughly
    failed to make out a case for interference in finding of fact recorded by the
    Arbitral Tribunal on the issue of accident/incident being the proximate
    cause for overhauling of the GT Engine. None the less I briefly discuss the
    material available on record of Arbitral Tribunal which can support its
    finding since this Court can explain existence of underlying finding even
    when reasons do not appear to be adequate enough as held in the
    judgment of the Apex Court in OPG Power Generation Private Limited
    (supra).
    
    
    78)               Petitioner has strenuously relied on the two GE's Reports of
    19 October 2001 and 22 October 2001 to suggest that the GT Engine was
    suffering from pre-existing damage of corrosion, rust, erosion,
    
    _____________________________________________________________________________
    
                                          PAGE NO. 71 OF 77
    
                                            22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                       ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                     CARBP-10809-2024
    
    
    
    
    discolouration etc. However, GE's letter dated 15 January 2002 clearly
    suggests that overhauling was needed on account of damage caused to
    various parts of GT Engine as a result of accident of 16 September 2001.
    Relevant part of GE's letter dated 15 January 2002 reads thus:
    
    
                      The Sump B repair was carried out and testing done on December 7,
                      2001. During this testing, the core rotor vibrations were found to be 3.5
                      to 4.0 mils during transient conditions. The acceptable limit of these
                      vibrations is 3.0 mils.
                              On December 7, 2001, GE suggested to attend to these vibrations
                      by opening HPC and HPT modules and performing a balance. In adition,
                      GE also suggested to do complete disassembly and conudct a full
                      examination and rebuild the engine to take care of all other damages
                      noted during prior inspections. GE believes that performing the HPC and
                      HPT balance would only take care of the transient vibration issues and
                      would not be a good solution to the complete possible problems with
                      this engine. GE offered to extend a full guarantee only if the engine is
                      fully overhauled per GE guidelines at a GE qualified shop.
                              As per Search Chem records, the engine has put in 21000 hours
                      and the type of vibrations seen during testing (Engine indicated to have
                      no transient vibration per the on site Plant Manager) indicate that the
                      damage to other parts also might be result of accident on
                      September 16, 2001.
                                                                           (emphasis added)
    
    
    
    79)               Thus, in the present case, the Sump B repairs were first
    carried out on 7 December 2001 whereafter the GT Engine was put for
    testing and core rotor vibrations were noticed during transient conditions
    beyond acceptable limits. Therefore, on 7 December 2001, GE gave
    suggestions for attending to those vibrations by opening HPC and HPT
    modules. Additionally, it also suggested to completely disassemble the
    engine and conduct full examination and to rebuild the engine and to
    take care of other damage noted during prior inspection. GE suggested
    that performing HPC and HPT balance would only take care of transient
    _____________________________________________________________________________
    
                                             PAGE NO. 72 OF 77
    
                                               22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                          ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                  CARBP-10809-2024
    
    
    
    
    vibration issues and was not a complete solution to problems in the
    engine. With these observations, GE concluded that since the engine had
    not indicated any transient vibrations as reported by Site Plant Manager
    of the Respondent, the damage to other parts would also be a result of the
    accident. The letter thus conclusively establishes accident to be the
    proximate cause for overhauling the GT Engine. If pre-existing condition
    of corrosion, rust, etc necessitated overhaul, the engine ought to have run
    smoothly after effecting the incident repairs. The engine used to run
    smoothly without vibration before the incident as reported by the                         Site
    Plant Manager. This is why GE opined that the accident must have
    damaged other parts which was causing vibrations in the engine even
    after carrying out incident repairs.
    
    
    80)               Respondent also led evidence of expert whose testimony is
    accepted by the Arbitrator and who deposed that GT Engine, being highly
    sophisticated one, the same could not have functioned if it suffered from
    corrosion, rust or wear and tear and that the accident might have caused
    oil to travel inside turbine parts causing coking and that the condition
    noted in GE reports must have been a result of accident or subsequent
    transportation or dismantling of the engine. The Arbitrator has also relied
    upon joint Surveyors' report, all three of which made a categorical
    observation that the GT Engine was operating smoothly, and was in good
    healthy condition and did not suffer from any pre-existing damage prior
    to the accident. Additionally, the Arbitral Tribunal has also relied upon
    letter of GE dated 27 September 2001 stating that GT Engine suffered
    serious internal component damage, GEEPO's letter dated 27 September
    
    _____________________________________________________________________________
    
                                          PAGE NO. 73 OF 77
    
                                            22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                       ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                  CARBP-10809-2024
    
    
    
    
    2001, GE's letter dated 12 April 2002 to the Respondent reporting
    sufferance of widespread damage of oil leakage extensively damaging
    various parts and GE's letter dated 28 May 2003 emphatically stating that
    the vibrations in LP and HP could be related to accident of 16 September
    2001. The Tribunal has also noted that GE recommended overhauling of
    GT Engine only after 50,000 hours of running and that the subject engine
    had run for only 27,000 hours and that the same was therefore not due for
    overhauling. The Tribunal has also noted performance of GT Engine at
    the optimum level prior to the accident based on joint surveyors' reports.
    
    
    81)               The Arbitral Tribunal thus had ample material before it for
    arriving at the conclusion that the accident was the proximate cause for
    overhauling of GT Engine. By no stretch of imagination, can it be
    contended that the findings recorded by the Arbitral Tribunal are so
    grossly perverse that this Court must invalidate the Award in exercise of
    powers under Section 34 of the Arbitration Act.
    
    
    82)               Mr. Jagtiani's criticism of the learned Arbitrator of giving
    discriminatory treatment is unfounded. He has relied upon finding
    recorded by the Arbitral Tribunal in paragraph 83 of the Award where the
    Tribunal has expected Petitioner to examine witness from GE to make out
    its case for pre-existing conditions of GT Engine. However, according to
    Mr. Jagtiani, several letters of GE favouring Respondent have been relied
    upon by the Arbitrator without any oral testimony of GE's personnel. In
    my view however, the contention is raised out of myopic reading of
    findings recorded in paragraph 83 of the Award. What the Tribunal has
    
    _____________________________________________________________________________
    
                                          PAGE NO. 74 OF 77
    
                                            22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                       ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                  CARBP-10809-2024
    
    
    
    
    observed in paragraph 83 of the Award is that the condition of GT Engine
    depicted in the two GE reports of 19 October 2001 and 22 October 2001
    was the condition that was found after the accident and at the time when
    the engine was already disassembled and opened. The Tribunal has held
    that reports by themselves did not establish 'pre-existing' condition of
    the GT Engine. The Tribunal has therefore held that if Petitioner wanted
    to prove that the condition of the engine found after disassembling was
    the same which existed prior to the accident, Petitioner ought to have
    examined a witness from GE to support its case and ought to have granted
    an opportunity to the Respondent to cross-examine such witness. The
    findings in paragraph 83 therefore cannot be read to mean as if the
    Tribunal has refused to take into consideration the GE's reports dated 19
    October 2001 or 22 October 2001. The Tribunal has considered both the
    reports, and has recorded a finding against Respondent that the reports
    depicted rusting etc. but has refused to believe that the rusting was pre-
    existing before the accident.
    
    
    83)               Therefore, the finding of fact recorded by the Arbitral
    Tribunal about accident being the proximate cause of accident does not
    warrant any interference in exercise of powers under Section 34 of the
    Arbitration Act.
    
    
    CONCLUSIONS
    
    
    84)               Considering the overall conspectus of the case, in my view,
    the Petitioner has failed to make out any valid ground of challenge to the
    impugned Arbitral Award. The findings recorded by the Arbitral Tribunal
    
    _____________________________________________________________________________
    
                                          PAGE NO. 75 OF 77
    
                                            22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                       ::: Downloaded on - 23/04/2026 21:39:43 :::
     Neeta Sawant                                                                  CARBP-10809-2024
    
    
    
    
    are well supported by the material on record. The scope of powers of this
    Court in examining objections to the Arbitral Award is well settled in
    several judgments, and I do not wish to burden this Judgment by
    discussing ratio of those judgments. In recent judgment of the Apex Court
    in Prakash Atlanta (JV) (supra) all the judgments relating to scope of
    interference by Section 34 Court are surveyed. Considering the extremely
    narrow scope of interference by Section 34 Court in the Arbitral Award, in
    my view, no case is made out for tracing an element of patent illegality,
    gross perversity, conflict with public policy of India or contravention with
    fundamental policy of Indian laws. The Tribunal has not violated the
    principles of natural justice nor has travelled beyond the scope of
    contractual terms. It has not ignored any vital piece of evidence or
    binding effect of any judgment. The findings recorded by the Tribunal are
    not such that no fair-minded person would ever record the same. The
    attempt on the part of the Petitioner is to impress upon the Court to take
    a different view based on the material considered by the Tribunal, which
    is impermissible. In fact the Petitioner has taken a volte-face in the second
    round of arbitration as it had pleaded in the first round that the dispute
    was about the quantum and therefore arbitrable.
    
    
    85)               No submissions are canvassed with regard to the quantum of
    claim awarded by the Arbitral Tribunal, award of interest as well as award
    of costs. The Award appears, to my mind, to be unexceptional. In that
    view of the matter, the Award deserves to be upheld by dismissing the
    Arbitration Petition.
    
    
    
    _____________________________________________________________________________
    
                                          PAGE NO. 76 OF 77
    
                                            22 April 2026
    
    
    
    
           ::: Uploaded on - 23/04/2026                       ::: Downloaded on - 23/04/2026 21:39:43 :::
                Neeta Sawant                                                                  CARBP-10809-2024
    
    
    
    
              ORDER
    

    86) Accordingly, I proceed to pass the following order:

    Commercial Arbitration Petition is dismissed. However, considering the
    facts and circumstances of the case, I deem it appropriate not to award
    any further costs in the Commercial Arbitration Petition. All pending
    Interim Applications are disposed of. The amount deposited in this Court
    in pursuance of order dated 5 February 2025 shall be paid over to the
    Respondent alongwith accrued interest.

    [SANDEEP V. MARNE, J.]

    87) After the judgment is pronounced, Mr. Jagtiani, the learned
    Senior Advocate appearing for the Petitioner prays for stay of direction
    for payment of deposited amount to the Respondent. Request is opposed
    by the learned counsel appearing for the Respondent. there shall be stay
    to the direction for payment of amount deposited in this Court for a
    period of six week.

    Digitally
    signed by
    NEETA
    NEETA SHAILESH
    SHAILESH SAWANT [SANDEEP V. MARNE, J.]
    SAWANT Date:

    SPONSORED

    2026.04.22
    21:11:06
    +0530

    _____________________________________________________________________________

    PAGE NO. 77 OF 77

    22 April 2026

    ::: Uploaded on – 23/04/2026 ::: Downloaded on – 23/04/2026 21:39:43 :::



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here