Uem India Pvt. Ltd vs Ongc Ltd on 28 March, 2026

    0
    54
    ADVERTISEMENT

    Delhi High Court

    Uem India Pvt. Ltd vs Ongc Ltd on 28 March, 2026

                        *      IN THE HIGH COURTOF DELHI AT NEW DELHI
                        %                              Judgment reserved on: 19.03.2026
                                                    Judgment pronounced on: 28.03.2026
                        +      O.M.P. (COMM) 393/2018, I.A. 12438/2018, I.A. 9666/2020 &
                               I.A. 2738/2022
    
                               UEM INDIA PVT. LTD.                               .....Petitioner
    
                                                  Through:    Mr. Gaurav Pachnanda, Sr.
                                                              Adv. with Mr. Samir Malik,
                                                              Ms. Snehal Kaila, Ms. Yachana
                                                              Gupta, Mr. Udbhav Gady &
                                                              Mr. Krishan Kumar, Advs.
                                                  versus
                               ONGC LIMITED                               .....Respondent
    
                                                  Through:    Mr. Abhishek Puri, Ms. Surbhi
                                                              Gupta & Mr. Sahil Grewal,
                                                              Advs.
                               CORAM:
                               HON'BLE MR. JUSTICE AVNEESH JHINGAN
                                                  JUDGMENT
    

    1. This petition is filed under Section 34 of the Arbitration and
    Conciliation Act, 1996 (for short „the Act‟) for setting aside of the
    award dated 14.12.2017.

    2. The brief facts are that the petitioner M/s UEM India Private
    Limited, a registered company was the successful bidder in a tender
    invited by Oil and Natural Gas Corporation („ONGC‟) for installation
    of one Effluent Treatment Plant (for short „ETP‟) and three ETP-cum
    Water Injection Plants at four sites in Assam along with maintenance
    for seven years. The parties entered into contract on lump sum turnkey

    SPONSORED

    Signature Not Verified
    O.M.P. (COMM) 393/2018 Page 1 of 17
    Signed By:HONEY
    ARORA
    Signing Date:28.03.2026
    15:01:03
    basis. The work was awarded on 30.03.2011 for a lump sum amount
    of Rs.119,34,58,347/-. The project was to be completed within thirty
    four months from the date of issuance of the Notification of Award
    (for short „NOA‟) i.e. by 29.01.2014.

    2.1 Clause 27 of the General Conditions of Contract (for short
    „GCC‟) provided for dispute resolution through arbitration and the
    petitioner invoked arbitration. The petitioner claimed prolongation
    costs aggregating to Rs.10,30,00,000/-; losses to the tune of
    Rs.7,23,55,402/- due to breach of contract; losses amounting to
    Rs.105,60,00,000/- on account of being placed on a holiday list and
    amounts towards resources committed/consumed, damages, interest
    on capital cost and illegal invocation of the advance bank guarantee
    (for short „ABG‟) and performance bank guarantee (for short „PBG‟).
    2.2 The respondent filed counter claims claiming:

    (i) Compensation amount of Rs.86,54,26,860.44/- towards
    restitution of loss and damages on account of payments
    made to third party vendors;

    (ii) Rs.15,19,72,222.33/- for production and revenue loss due to
    non-performance of various acts by the petitioner;

    (iii) Rs.5,70,84,812/- incurred towards establishment costs for
    various acts of omission by the petitioner;

    (iv) Cost of re-tendering to the tune of Rs.130,65,41,652/-;

    (v) Rs.7,35,82,647/- as Liquidated damages (for short „LD‟);

    (vi) Refund of Rs.2,95,00,483.61/- for provisional progressive
    payments;

    (vii) Rs.11,93,45,835/- towards PBG;

    Signature Not Verified
    O.M.P. (COMM) 393/2018 Page 2 of 17
    Signed By:HONEY
    ARORA
    Signing Date:28.03.2026
    15:01:03

    (viii) Rs.53,93,047/- for interest on non-utilization of advances
    given by the respondent to the petitioner; and

    (ix) Lastly Rs.23,86,91,669/- towards compensation of the loss
    and damages suffered due to wilful non-performance of the
    contract by the petitioner.

    2.3 The claim of the petitioner of Rs.13,56,376/- for services
    rendered for soil investigation was accepted, the invocation of ABG of
    Rs.2,95,00,484/- was held to be illegal and the respondent was
    directed to refund it along with interest @ 12%, from the date of
    encashment till filing of the statement of claim. Interest pendente lite
    was awarded @ 9% per annum.

    2.4 The counter claim for LD of Rs.7,35,82,647/- was accepted,
    interest @12% was granted from the date of termination of the
    contract till filing of the counter claim and pendente lite interest @ 9%
    per annum. The amount of PBG was determined as the quantum of
    damages over and above the LD. Both parties filed applications under
    Section 33 of the Act for correction of the errors. The application of
    the respondent was accepted and the typographical error in
    mentioning the LD in paragraph 474 of the award as Rs.73,58,264/-
    instead of Rs.7,35,82,647/- was corrected. Consequently, the interest
    awarded on the amount was modified. The application filed by the
    petitioner was rejected by the majority decision, being time-barred but
    the minority held that once the rectification application of one of the
    party was entertained, the errors pointed out by the other party should
    also be corrected.

    Signature Not Verified
    O.M.P. (COMM) 393/2018 Page 3 of 17
    Signed By:HONEY
    ARORA
    Signing Date:28.03.2026
    15:01:03

    2.5 The only dispute pressed in the present petition is with regard to
    damages awarded over and above the LD, quantified equivalent to the
    PBG and the grant of interest thereon.

    2.6 During the pendency of the petition vide order dated
    30.04.2019, this court while exercising power under Section 34(4) of
    the Act considered the argument of the petitioner that the tribunal had
    not awarded damages to the tune of Rs.11,93,45,835/- as was evident
    from paragraph 474 of the award. The submission on behalf of the
    petitioner was that there was no grievance with regard to the other
    findings in the award. The respondent relied upon paragraphs 460 and
    461 of the award to contend that the damages were awarded. This
    Court vide order dated 08.02.2019 exercised the power under Section
    34(4)
    of the Act and the operative portion of the order is reproduced
    below:

    “8. The above quoted findings of the Arbitral Tribunal
    leave a doubt as to whether the Arbitral Tribunal has
    allowed the amount of Performance Bank Guarantee in
    favour of the respondent over and above the liquidated
    damages allowed under Counter Claim No.5. This is
    more so because in the Award the Arbitral Tribunal has
    observed that no damages over and above as prescribed
    in Clause 6.6 of the Agreement can be allowed in
    favour of the respondent, however, at the same time in
    paragraph 460 the Arbitral Tribunal has held that
    amount of the Performance Bank Guarantee furnished
    by the claimant cannot be said to be wholly
    unreasonable and in paragraph 461 it has held that the
    amount of the Performance Bank Guarantee furnished
    by the claimant is also treated as quantum of reasonable
    damages. In paragraph 457 the Tribunal has further

    Signature Not Verified
    O.M.P. (COMM) 393/2018 Page 4 of 17
    Signed By:HONEY
    ARORA
    Signing Date:28.03.2026
    15:01:03
    held that the respondent is entitled to damages in
    addition to the liquidated damages.

    9. In view of the above, the present proceedings deserve
    to be adjourned, enabling the Arbitral Tribunal to
    consider the observations made hereinabove and act in
    terms of Section 34(4) of the Act, if so advised.”

    2.7 During the pendency of the proceedings pursuant to Section
    34(4)
    of the Act, one of the members of the tribunal Justice (Retd.)
    S.B. Sinha expired and with the consent of the parties Justice (Retd.)
    Rameshwar Singh Malik was appointed as an arbitrator. The majority
    of the tribunal decided that damages to the extent of the PBG were
    awarded over and above the LD. The minority view was that the
    counter claim no. 7 claiming the amount of PBG was rejected and the
    direction for the refund of the PBG amount was inadvertently not
    given by the tribunal.

    3. Learned counsel for the petitioner argued that from a reading of
    the award dated 14.12.2017 it is evident that no amount in excess of
    LD was awarded. Albeit, the PBG was held to be validly invoked but
    there was no quantification of damages. It was contended that the
    tribunal rejected the counter claim nos. 1 to 3 for failure of the
    respondent to prove damages and yet illegally awarded damages under
    Section 73 of the Indian Contract Act, 1872 (for short „CA‟). Reliance
    is placed on the decisions of the Supreme Court in Kailash Nath
    Associates v. DDA
    , (2015) 4 SCC 136 and Fateh Chand v.
    Balkishan Dass
    , 1963 SCC OnLine SC 49.

    3.1 It is emphasised that the award is contradictory as on the one
    hand counter claim no. 7 claiming the amount towards PBG was

    Signature Not Verified
    O.M.P. (COMM) 393/2018 Page 5 of 17
    Signed By:HONEY
    ARORA
    Signing Date:28.03.2026
    15:01:03
    rejected and on the other hand by the order passed pursuant to Section
    34(4)
    the majority held that damages equivalent to the PBG were
    awarded. It is argued that while rejecting counter claim nos. 6 and 9, it
    was stated that the respondent was entitled only to LD. The decision
    in Union of India & Anr. v. Sanghu Chakra Hotels (P) Ltd., 2008
    SCC OnLine Del 912 is relied upon to fortify the contention that a
    contradictary award deserves to be set aside. The decision in Vishnu
    Aggarwal v. Hindustan Petroleum Corpn. Ltd.
    , 2019 SCC OnLine
    Del 9300 is relied upon to submit that a vague award is liable to be set
    aside being violative of Section 31(3) of the Act.

    4. Per contra, the PBG was furnished as per clause 3.3 of the GCC
    and could be invoked upon failure of the petitioner to honour the
    contractual obligations. The LD under clause 6.3.2 pertains to delay in
    completion of work. Both the clauses operate in distinct fields. It is
    argued that the upholding of invocation of the PBG by the tribunal is
    not under challenge and there were no pleadings for refund of the
    PBG amount. The impugned award and the order passed under
    Section 34(4) is defended by stating that a reasoned decision was
    rendered holding respondent to be entitled to damages of
    Rs.11,93,45,835/- over and above the LD. Reliance is on the decision
    of the Supreme Court in SAIL v. Gupta Brother Steel Tubes Ltd.,
    (2009) 10 SCC 63 and the decision of the Calcutta High Court in
    MBL Infrastructures Ltd. v. Ircon International Ltd., 2017 SCC
    OnLine Cal 21457 to buttress the argument that damages under heads
    not covered by the LD can be awarded.

    Signature Not Verified
    O.M.P. (COMM) 393/2018 Page 6 of 17
    Signed By:HONEY
    ARORA
    Signing Date:28.03.2026
    15:01:03

    5. Heard learned counsel for the parties at length. Even though
    written submissions have been filed, learned counsel for the parties
    while arguing the matter at length have pressed only the contentions
    noted above.

    6. The bone of controversy is limited to awarding of damages of
    Rs.11,93,45,835/-. The issue arises in two parts: first, as to whether
    damages were awarded in the original award despite not being
    reflected in the concluding paragraph and second, whether the
    damages if awarded are legally sustainable?

    7. In paragraph 454 of award, the tribunal considered that the
    petitioner had performed only 5.86% of the contract and held that the
    respondent was entitled to encash the PBG. Referring to the decision
    of the Supreme Court in Kailash Nath Associates (supra) the tribunal
    in paragraph 461 held that in view of the miniscule fraction of the
    total work done by the petitioner, the economic viability of the project
    and the abandonment of the contract by the petitioner, the amount of
    PBG furnished is to be treated as the quantum of reasonable damages.

    The decision of the Calcutta High Court in MBL Infrastructures
    Ltd.
    (supra) was relied upon for upholding the invocation of the PBG
    and awarding damages. In paragraph 466 it was observed that 10% of
    the contract value cannot be said to be unreasonable as damages.
    Paragraphs 454, 460, 461,465 and 466 of the award are reproduced
    below:

    “454. The materials brought on record by the parties so
    far as breaches of contract on the part of the Claimant is
    concerned show that the Claimant has performed only
    5.86% of the total Contract, in that view of the matter the

    Signature Not Verified
    O.M.P. (COMM) 393/2018 Page 7 of 17
    Signed By:HONEY
    ARORA
    Signing Date:28.03.2026
    15:01:03
    Claimant was entitled to encash the Performance Bank
    Guarantee to the extent of Rs.11,93,45,835/-.

    460. Even if the Respondent has not been able to quantify
    the actual direct losses suffered by it, in the opinion of
    the Tribunal the amount of Performance Bank Guarantee
    furnished by the Claimant cannot be said to be wholly
    unreasonable.

    461. The Tribunal is therefore of the opinion that taking
    into consideration the peculiar facts and circumstances of
    the case, interest of justice will be served if the amount of
    Performance Bank Guarantee furnished by the Claimant
    is also treated to be the quantum of reasonable damages.

    465. In view of the aforementioned authoritative
    pronouncement the Tribunal is of the opinion that the
    counter Claimant cannot be said to have acted illegally in
    invoking the Performance Bank Guarantee.

    466. In the aforementioned fact situation the Tribunal is
    of the opinion that 10% of the contract value cannot be
    said to be unreasonable and in that view of the matter the
    Counter Claimant is entitled thereto.”

    8. While the matter was being considered pursuant to Section
    34(4)
    of the Act, one of the members of the tribunal expired and a new
    member was substituted. The proceedings were decided by majority
    and one of the original members dissented and recorded that damages
    over and above the LD were not awarded but the majority held that
    the damages were awarded. Without entering into the validity of the
    decision pursuant to Section 34(4) of the Act and in view of the settled
    position that an award has to be read as a whole, it is evident that 10%
    of the contract value was awarded as damages albeit, the figure was
    not mentioned in the concluding portion of the award. From the

    Signature Not Verified
    O.M.P. (COMM) 393/2018 Page 8 of 17
    Signed By:HONEY
    ARORA
    Signing Date:28.03.2026
    15:01:03
    extracted paragraphs of the award, it is clear that the tribunal not only
    upheld the invocation of the PBG but also recorded a finding that the
    respondent was entitled to reasonable damages over and above the
    LD, quantified damages equivalent to the PBG amount.

    9. Before dealing with the second limb that as to whether the
    damages awarded over and above the LD are legally sustainable, it
    would be relevant to quote the following decisions:

    9.1 The Supreme Court in Unibros vs. All India Radio, 2023 SCC
    OnLine SC 1366 while dealing with a claim for redressal of loss of
    profit made under Section 73 of the CA arising from prolongation of
    the contract held:

    “19. The law, as it should stand thus, is that for claims
    related to loss of profit, profitability or opportunities to
    succeed, one would be required to establish the following
    conditions : first, there was a delay in the completion of
    the contract; second, such delay is not attributable to the
    claimant; third, the claimant’s status as an established
    contractor, handling substantial projects; and fourth,
    credible evidence to substantiate the claim of loss of
    profitability. On perusal of the records, we are satisfied
    that the fourth condition, namely, the evidence to
    substantiate the claim of loss of profitability remains
    unfulfilled in the present case.”

    9.2 The Supreme Court in Kailash Nath Associates (supra) held:

    “43.6. The expression “whether or not actual damage or
    loss is proved to have been caused thereby” means that
    where it is possible to prove actual damage or loss, such
    proof is not dispensed with. It is only in cases where
    damage or loss is difficult or impossible to prove that the
    liquidated amount named in the contract, if a genuine
    pre-estimate of damage or loss, can be awarded.”

    Signature Not Verified
    O.M.P. (COMM) 393/2018 Page 9 of 17
    Signed By:HONEY
    ARORA
    Signing Date:28.03.2026
    15:01:03

    9.3 The Supreme Court in State of Rajasthan v. Ferro Concrete
    Construction (P) Ltd.
    , (2009) 12 SCC 1 held:

    “55.While the quantum of evidence required to accept a
    claim may be a matter within the exclusive jurisdiction of
    the arbitrator to decide, if there was no evidence at all
    and if the arbitrator makes an award of the amount
    claimed in the claim statement, merely on the basis of the
    claim statement without anything more, it has to be held
    that the award on that account would be invalid. Suffice
    it to say that the entire award under this head is wholly
    illegal and beyond the jurisdiction of the arbitrator, and
    wholly unsustainable.”

    9.4 The Division Bench of this court in Tower Vision India (P)
    Ltd. v. Procall (P) Ltd.,2012
    SCC OnLine Del 4396 held:

    “16. Consequence for breach of the contract are provided
    in Chapter VI of the Indian Contract Act, 1872, which
    contains three sections, namely, section 73 to section 75.
    As per section 73 of the Indian Contract Act, the party
    who suffers by the breach of contract is entitled to
    receive from the defaulting party, compensation for any
    loss or damage caused to him by such breach, which
    naturally arose in usual course of things from such
    breach, or which the two parties knew when they make
    the contract to be likely the result of the breach of
    contract. This provision makes it clear that such
    compensation is not to be given for any remote or
    indirect loss or damage sustained by reason of the breach.
    The underlying principle enshrined in this section is that
    a mere breach of contract by a defaulting party would not
    entitle the other side to claim damages unless the said
    party has in fact suffered damages because of such
    breach. Loss or damage which is actually suffered as a

    Signature Not Verified
    O.M.P. (COMM) 393/2018 Page 10 of 17
    Signed By:HONEY
    ARORA
    Signing Date:28.03.2026
    15:01:03
    result of breach has to be proved and the plaintiff is to be
    compensated to the extent of actual loss or damage
    suffered. When there is a breach of contract, the party
    who commits the breach does not eo instanti, i.e., at the
    instant incur any pecuniary obligation, nor does the party
    complaining of the breach becomes entitled to a debt due
    from the other party. The only right which the party
    aggrieved by the breach of the contract has is the right to
    sue for damages. No pecuniary liability thus arises till the
    court has determined that the party complaining of the
    breach is entitled to damages. The court in the first place
    must decide that the defendant is liable and then it should
    proceed to assess what the liability is. But, till that
    determination, there is no liability at all upon the
    defendant. The courts will give damages for breach of
    contract only by way of compensation for loss suffered
    and not by way of punishment. The rule applicable for
    determining the amount of damages for the breach of
    contract to perform a specified work is that the damages
    are to be assessed at the pecuniary amount of difference
    between the state of the plaintiff upon the breach of the
    contract and what it would have been if the contract had
    been performed and not the sum which it would cost to
    perform the contract, though in particular cases the result
    of either mode of calculation may be the same. The
    measure of compensation depends upon the
    circumstances of the case. The complained loss or
    claimed damage must be fairly attributed to the breach as
    a natural result or consequence of the same. The loss
    must be a real loss or actual damage and not merely a
    probable or a possible one. When it is not possible to
    calculate accurately or in a reasonable manner, the actual
    amount of loss incurred or when the plaintiff has not been
    able to prove the actual loss suffered, he will be, all the
    same, entitled to recover nominal damages for breach of
    contract. Where nominal damages only are to be
    awarded, the extent of the same should be estimated with
    reference to the facts and circumstances involved. The

    Signature Not Verified
    O.M.P. (COMM) 393/2018 Page 11 of 17
    Signed By:HONEY
    ARORA
    Signing Date:28.03.2026
    15:01:03
    general principle to be borne in mind is that the injured
    party may be put in the same position as that he would
    have been if he had not sustained the wrong.”

    (emphasis supplied)

    10. Clause 3.3 of the GCC deals with the PBG. Under clause 3.3.1
    the contractor within two weeks from the date of issue of the NOA
    had to furnish an unconditional and irrecoverable bank guarantee
    equivalent to 10% of the contract price for due performance of the
    contract. As per clause 3.3.3 the respondent was entitled to invoke the
    PBG on failure of the petitioner to honour the contractual obligations.
    Clause 3.3.5 provides that in case of a delay in completion of the
    project beyond the scheduled date of completion, the respondent
    without prejudice to other rights and remedies could operate the PBG
    for recovery of LD. Clause 6.3.2 deals with LD for non-completion of
    work within scheduled time and provides that the respondent may
    recover LD at the rate of 0.5% per week subject to maximum of 10%
    of the total contract price. The clause provides that upon partial
    completion and acceptance of part of the work the LD shall apply only
    to the balance work. A conjoint reading of clause 3.3 and clause 6.3.2
    indicates that they operate in different fields. Clause 3.3 pertains to
    securing due performance of the contract and enabling invocation of
    the PBG in case of breach whereas clause 6.3.2 governs the levy of
    LD for delay in completion of the work.

    11. There is no challenge to the LD awarded for delay in
    completion of the project. It is undisputed that only 5.86% of the
    project was completed by the petitioner and consequently the PBG

    Signature Not Verified
    O.M.P. (COMM) 393/2018 Page 12 of 17
    Signed By:HONEY
    ARORA
    Signing Date:28.03.2026
    15:01:03
    was invoked. The challenge is to the quantification of damages inspite
    of the failure of the respondent to prove actual loss. Clause 3.3
    provides for furnishing and invocation of the PBG but does not
    stipulate the quantification of damages. In counter claim nos. 1 to 3,
    the respondent claimed damages under various heads including
    payments to third-party vendor, production and revenue losses on
    account of non-performance, compensation towards establishment
    costs and for re-tendering of the project however, the claims were
    rejected for lack of proof. For claiming damages under Section 73 of
    the CA the claimant has to prove the loss suffered and in case it is not
    possible to prove the actual damages, a reasonable amount of damages
    is to be assessed. It was neither the case set up before the tribunal nor
    it was held that in the facts of present case the actual damages cannot
    be proved. Rather the respondent failed to prove the counter claims
    nos. 1 to 3 claiming damages under various heads. In absence of a
    proof of actual damages and without recording a finding that actual
    damages could not be proved the tribunal proceeded to conclude that
    10% of the contract value shall be a reasonable damages to be
    awarded over and above the LD. The basis for quantification is
    missing and the awarding of damages is vitiated for violating Section
    31(3)
    of the Act whereby a reasoned award is to be passed.

    12. The Supreme Court in Dyna Technologies Private Limited v.
    Crompton Greaves Limited
    , (2019) 20 SCC 1:

    “34. The mandate under Section 31(3) of the Arbitration Act
    is to have reasoning which is intelligible and adequate and,
    which can in appropriate cases be even implied by the courts
    from a fair reading of the award and documents referred to

    Signature Not Verified
    O.M.P. (COMM) 393/2018 Page 13 of 17
    Signed By:HONEY
    ARORA
    Signing Date:28.03.2026
    15:01:03
    thereunder, if the need be. The aforesaid provision does not
    require an elaborate judgment to be passed by the arbitrators
    having regard to the speedy resolution of dispute. 35. When
    we consider the requirement of a reasoned order, three
    characteristics of a reasoned order can be fathomed. They
    are: proper, intelligible and adequate. If the reasonings in the
    order are improper, they reveal a flaw in the decision-making
    process. If the challenge to an award is based on impropriety
    or perversity in the reasoning, then it can be challenged
    strictly on the grounds provided under Section 34 of the
    Arbitration Act. If the challenge to an award is based on the
    ground that the same is unintelligible, the same would be
    equivalent of providing no reasons at all. Coming to the last
    aspect concerning the challenge on adequacy ofreasons, the
    Court while exercising jurisdiction under Section 34 has to
    adjudicate the validity of such an award based on the degree
    of particularity of reasoning required having regard to the
    nature of issues falling for consideration. The degree of
    particularity cannot be stated in a precise manner as the same
    would depend on the complexity of the issue. Even if the
    Court comes to a conclusion that there were gaps in the
    reasoning for the conclusions reached by the Tribunal, the
    Court needs to have regard to the documents submitted by
    the parties and the contentions raised before the Tribunal so
    that awards with inadequate reasons are not set aside in
    casual and cavalier manner. On the other hand, ordinarily
    unintelligible awards are to be set aside, subject to party
    autonomy to do away with the reasoned award. Therefore,
    the courts are required to be careful while distinguishing
    between inadequacy of reasons in an award and unintelligible
    awards.”

    (emphasis supplied)

    13. Another aspect is that for want of evidence three different heads
    in counter claim nos. 1 to 3 were rejected by the tribunal but damages
    were quantified without discussing the heads under which the
    damages were being awarded. This renders the award self-

    Signature Not Verified
    O.M.P. (COMM) 393/2018 Page 14 of 17
    Signed By:HONEY
    ARORA
    Signing Date:28.03.2026
    15:01:03

    contradictory, on one hand the tribunal rejects the counter claims
    under specific heads for want of proof and on the other hand awards
    damages over and above the LD without identifying the heads of loss
    suffered. Further while deciding the counter claims for compensation
    and damages arising from wilful abandonment of the contract it was
    held that the respondent was only entitled to the LD and no other
    claims. The award of damages is contrary to public policy being
    against the law laid down by the Supreme Court and is in violation of
    Section 73 of the CA.

    14. The contention that there were no pleadings for refund of the
    PBG is rejected. Suffice it to say that the petitioner is not aggrieved by
    the invocation of the PBG but by the appropriation of the PBG
    amount. From a perusal of the pleadings, it is evident that the reliefs
    claimed included the amount of the PBG.

    15. There is no quarrel with the proposition that damages for
    breaches not covered by a clause of LD can be awarded over and
    above the cap provided for which SAIL (supra) is relied upon.

    16. The decision of the Calcutta High Court in MBL
    Infrastructures Ltd.
    (supra) is not applicable to the facts of the
    present case. In that case, the court held that damages for lack of
    performance of the contract cannot be denied for the reason that the
    claim for additional expenses was disallowed and there was no nexus
    between the two claims.

    17. The Supreme Court in Gayatri Balasamy v. ISG Novasoft
    Technologies Ltd.
    , (2025) 7 SCC 1 held that while an arbitral award

    Signature Not Verified
    O.M.P. (COMM) 393/2018 Page 15 of 17
    Signed By:HONEY
    ARORA
    Signing Date:28.03.2026
    15:01:03
    cannot be modified under Section 34 of the Act, a severable part of the
    award may be set aside. The relevant paragraphs are quoted below:

    “32. In the present controversy, the proviso to Section
    34(2)(a)(iv)
    is particularly relevant. It states that if the
    decisions on matters submitted to arbitration can be
    separated from those not submitted, only that part of the
    arbitral award which contains decisions on matters non-
    submitted may be set aside. The proviso, therefore, permits
    courts to sever the non-arbitrable portions of an award from
    arbitrable ones. This serves a twofold purpose. First, it
    aligns with Section 16 of the 1996 Act, which affirms the
    principle of kompetenz-kompetenz, that is, the arbitrators’
    competence to determine their own jurisdiction. Secondly, it
    enables the Court to sever and preserve the “valid” part(s) of
    the award while setting aside the “invalid” ones. [ The
    “validity” and “invalidity”, as used here, does not refer to
    legal validity or merits examination, but validity in terms of
    the proviso to Section 34(2)(a)(iv) of the 1996 Act.] Indeed,
    before us, none of the parties have argued that the Court is
    not empowered to undertake such a segregation.

    33. We hold that the power conferred under the proviso to
    Section 34(2)(a)(iv) is clarificatory in nature. The authority
    to sever the “invalid” portion of an arbitral award from the
    “valid” portion, while remaining within the narrow confines
    of Section 34, is inherent in the Court’s jurisdiction when
    setting aside an award.

    34. To this extent, the doctrine of omne majus continet in se
    minus–the greater power includes the lesser–applies
    squarely. The authority to set aside an arbitral award
    necessarily encompasses the power to set it aside in part,
    rather than in its entirety. This interpretation is practical and
    pragmatic. It would be incongruous to hold that power to set
    aside would only mean power to set aside the award in its
    entirety and not in part. A contrary interpretation would not
    only be inconsistent with the statutory framework but may
    also result in valid determinations being unnecessarily
    nullified.

    Signature Not Verified
    O.M.P. (COMM) 393/2018 Page 16 of 17
    Signed By:HONEY
    ARORA
    Signing Date:28.03.2026
    15:01:03

    (emphasis supplied)

    18. In the case in hand, the claims of the petitioner for rendering
    services, refund of ABG and the counter claim of LD are separable
    and not inter-connected and shall not be affected by the setting aside
    of damages of Rs. Rs.11,93,45,835/- awarded to the respondent over
    and above the LD.

    19. The award to the extent of allowing the counter claim of the
    respondent awarding damages to the tune of PBG over and above the
    LD is set aside. The petition is allowed. All pending applications are
    also disposed of.

    AVNEESH JHINGAN, J.

    MARCH 28, 2026/Pa

    Reportable:-Yes

    Signature Not Verified
    O.M.P. (COMM) 393/2018 Page 17 of 17
    Signed By:HONEY
    ARORA
    Signing Date:28.03.2026