The State Of Jharkhand vs Rameshwar Singh on 9 July, 2026

    0
    5
    ADVERTISEMENT

    Jharkhand High Court

    The State Of Jharkhand vs Rameshwar Singh on 9 July, 2026

    Author: Sujit Narayan Prasad

    Bench: Sujit Narayan Prasad, Sanjay Prasad

                                                              [2026:JHHC:20422-DB]
    
    
    
    
           IN THE HIGH COURT OF JHARKHAND AT RANCHI
                         L.P.A. No. 490 of 2025
                                With
                         I.A. No. 7136 of 2025
                                        ------
       1. The State of Jharkhand.
       2. The Secretary, Department of Drinking Water and Sanitation,
          Nepal House, Government of Jharkhand, P.O. & P.S. Doranda,
          District Ranchi.
       3. The Engineer-in-Chief, Department of Drinking Water and
          Sanitation, Nepal House, Government of Jharkhand, P.O. & P.S.
          Doranda, District Ranchi.
       4. The Deputy Secretary, Department of Drinking Water and
          Sanitation, Nepal House, Government of Jharkhand, P.O. & P.S.
          Doranda, District-Ranchi.
    
                                         .... .... Appellants/ Respondents
                                   Versus
       Rameshwar Singh, aged about 59 years, son of Late Khublal Singh,
       resident of Shil Kothi, Bompass Town, Khoradah Road, P.O.
       Devasangh, P.S. Deoghar, Sadar, District-Deoghar, Jharkhand.
    
                                                 ... ... Respondent/Petitioner
                                     -----
    CORAM       : HON'BLE MR. JUSTICE SUJIT NARAYAN PRASAD
                    HON'BLE MR. JUSTICE SANJAY PRASAD
                                 ------
    For the Appellants    : Mr. Sahbaj Akhtar, AC to AAG-III
                                   ------
                         th
    Order No.03/Dated: 09 July, 2026
    
    Per Sujit Narayan Prasad, J.:
    

    1. The instant intra-court appeal, under clause 10 of the Letters
    Patent, is directed against the order/judgment dated 13.03.2024
    passed by learned Single Judge of this Court in W.P.(S) No. 618 of
    2019 by which the writ petition has been allowed.

    I.A. No. 7136 of 2025:

    SPONSORED

    2. The instant appeal is admittedly barred by limitation since as per
    the office note dated 28.11.2024, there is delay of 197 days in
    preferring the appeal, therefore, an application being I.A. No.7136
    of 2025 has been filed for condoning such delay.

    3. This Court, after taking into consideration the fact that the instant

    Page | 1
    [2026:JHHC:20422-DB]

    intra-court appeal has been field after inordinate delay of 197 days,
    deems it fit and proper, to first consider the delay condonation
    application before going into the legality and propriety of the
    impugned order on merit.

    4. Learned counsel for the applicant-appellant has submitted that
    delay in preferring the appeal may be condoned by allowing the
    Interlocutory Application on the basis of grounds shown therein
    treating the same to be sufficient.

    5. The grounds for condoning the delay in preferring the appeal, as
    has been mentioned in the interlocutory application is that the
    judgment in W.P.(S) No. 618 of 2019 was passed on 13.03.2024
    and in the meantime the Parliamentary Election was notified and
    the officials of the Department was involved in the said process.
    Thereafter, the impugned judgment came to the knowledge of the
    appellant/respondent, thereafter on 29.05.2024, the same was put
    up before the Under Secretary for further action.

    Thereafter, the Under Secretary placed the file before the
    Special Secretary for the needful and on 30.05.2024 the Special
    Secretary immediately placed the file before the Secretary with the
    aforesaid order. Thereafter, Secretary desired various inputs in the
    matter and opined for holding a meeting and on 12.06.2024,
    Section Officer submitted the details sought in the matter.

    Thereafter on 13.06.2024 it was desired to place the file
    along with the Grounds of Appeal. Thereafter on 20.06.2024,
    Assistant Section Officer placed the file before the Section Officer
    with respect to taking opinion for filing an appeal and on
    09.07.2024, Section Officer placed the file before the Under
    Secretary for taking opinion from the Learned Advocate General.

    Thereafter on 10.07.2024 Under Secretary put up the file
    before the Special Secretary for the needful and thereafter on
    10.07.2024, Special Secretary placed the file before the Secretary
    for the needful and thereafter, the file was placed before the
    Learned Advocate General for opinion against the judgment dated

    Page | 2
    [2026:JHHC:20422-DB]

    13.03.2024 passed in W.P.(S) No.618 of 2019. Thereafter, it was
    opined to file an appeal against the judgment dated 13.03.2024
    passed in W.P. (S) No. 618 of 2019 and the same was received on
    12.07.2024. Thereafter, the file was returned to the department for
    needful.

    Thereafter, on 16.07.2024 the file was put up before the
    Section Officer with the opinion for needful and the Section Officer
    put up the file before the Secretary with the opinion and for sending
    the file to the retainer for preparation of Grounds of Appeal.

    Thereafter, on 25.07.2024 Grounds of Appeal was
    submitted by the retainer and was placed for approval. Thereafter,
    on 31.07.2024, Assistant Section Officer put up the file before the
    Section Officer for approval of Grounds of Appeal. Thereafter, on
    05.08.2024, Section Officer put up the file before the Under
    Secretary for approval of Grounds of Appeal and on 06.08.2024,
    Under Secretary put up the file before the Special Secretary for
    approval of Grounds of Appeal. Thereafter, on 06.08.2024, Special
    Secretary put up the file before the Secretary for approval of
    Grounds of Appeal and on 10.08.2024 Grounds of appeal was
    approved.

    Thereafter, authorization letter was prepared and the same
    was issued on 12.08.2024. and the file was forwarded to the
    concerned law officer to prepare the memo of appeal against the
    Judgment dated 13.03.2024 passed in W.P.(S) No. 618 of 2019 and
    thereafter, the entire file was handed over to the concerned law
    officer for doing needful for filing of LPA and thereafter the appeal
    was drafted and the entire writ court pleadings were required, as
    such, the same was accordingly arranged and handed over but some
    documents was missing in the matter. The same were thereafter
    arranged and handed over and the appeal was filed on 12.09.2024
    without any further delay.

    6. We have heard the learned counsel for the appellants on delay
    condonation application and before considering the same, this

    Page | 3
    [2026:JHHC:20422-DB]

    Court, deems it fit and proper to refer certain legal proposition as
    has been propounded by the Hon’ble Apex Court with respect to
    the approach of the Court in condoning the inordinate delay.

    7. There is no dispute about the fact that generally the lis is not to be
    rejected on the technical ground of limitation but certainly if the
    filing of appeal suffers from inordinate delay, then the duty of the
    Court is to consider the application to condone the delay before
    entering into the merit of the lis.

    8. It needs to refer herein that the Law of limitation is enshrined in the
    legal maxim interest reipublicae ut sit finis litium (it is for the
    general welfare that a period be put to litigation). Rules of
    limitation are not meant to destroy the rights of the parties, rather
    the idea is that every legal remedy must be kept alive for a
    legislatively fixed period of time, as has been held in the judgment
    rendered by the Hon’ble Apex Court in Brijesh Kumar & Ors. Vrs.
    State of Haryana & Ors., (2014) 11 SCC 351.

    The Privy Council in General Accident Fire and Life
    Assurance Corpn. Ltd. v. Janmahomed Abdul Rahim
    , (1939-40)
    67 IA 416, relied upon the writings of Mr. Mitra in Tagore Law
    Lecturers, 1932, wherein, it has been said that:

    “A Law of limitation and prescription may appear to operate
    harshly and unjustly in a particular case, but if the law provides
    for a limitation, it is to be enforced even at the risk of hardship to
    a particular party as the Judge cannot, on equitable grounds,
    enlarge the time allowed by the law, postpone its operation, or
    introduce exceptions not recognized by law.”

    In P.K. Ramachandran v. State of Kerala, (1997) 7 SCC
    556, the Apex Court while considering a case of condonation of
    delay of 565 days, wherein no explanation much less a reasonable
    or satisfactory explanation for condonation of delay had been
    given, held at paragraph-6 as under:

    “6. Law of limitation may harshly affect a particular party
    but it has to be applied with all its rigour when the statute so
    prescribes and the courts have no power to extend the period
    of limitation on equitable grounds.”

    While considering the similar issue, this Court in Esha

    Page | 4
    [2026:JHHC:20422-DB]

    Bhattacharjee v. Raghunathpur Nafar Academy, (2013) 12 SCC
    649, wherein, it has been held as under:

    “21.5 (v) Lack of bona fides imputable to a party seeking
    condonation of delay is a significant and relevant fact.
    21.7. (vii) The concept of liberal approach has to
    encapsulate the conception of reasonableness and it cannot
    be allowed a totally unfettered free play.

    21.9. (ix) the conduct, behavior and attitude of a party
    relating to its inaction or negligence are relevant factors to
    be taken into consideration. It is so as the fundamental
    principle is that the courts are required to weigh the scale of
    balance of justice in respect of both parties and the said
    principle cannot be given a total go-by in the name of liberal
    approach.

    22.4. (d) The increasing tendency to perceive delay as a non-
    serious matter and, hence, lackadaisical propensity can be
    exhibited in a nonchalant manner requires to be curbed, of
    course, within legal parameters.”

    9. It is settled position of Law that when a litigant does not act with
    bona fide motive and at the same time, due to inaction and laches
    on its part, the period of limitation for filing the appeal expires,
    such lack of bona fide and gross inaction and negligence are the
    vital factors which should be taken into consideration while
    considering the question of condonation of delay. Reference in this
    regard may be made to the judgment rendered by the Division
    Bench of Gujarat High Court in State of Gujarat through
    Secretary & Anr. Vrs. Kanubhai Kantilal Rana, 2013 SCC Online
    Guj. 4202, wherein, at pargraph-17, it has been held that “Law
    having prescribed a fixed period of limitation of 30 days for
    preferring the appeal, the Government cannot ignore the provisions
    of the period of limitation as it was never the intention of the
    legislature that there should be a different period of limitation when
    the Government is the appellant.”

    In the case of Post Master General & Ors. Vrs. Living
    Media India Limited & Anr., [(2012) 3 SCC 563], it has been held
    by the Hon’ble Apex Court at paragraphs 27 to 29 as under:

    “27. It is not in dispute that the person(s) concerned were
    well aware or conversant with the issues involved including
    the prescribed period of limitation for taking up the matter
    by way of filing a special leave petition in this Court. They
    cannot claim that they have a separate period of limitation
    when the Department was possessed with competent persons

    Page | 5
    [2026:JHHC:20422-DB]

    familiar with court proceedings. In the absence of plausible
    and acceptable explanation, we are posing a question why
    the delay is to be condoned mechanically merely because the
    Government or a wing of the Government is a party before
    us.

    28. Though we are conscious of the fact that in a matter of
    condonation of delay when there was no gross negligence or
    deliberate inaction or lack of bona fides, a liberal concession
    has to be adopted to advance substantial justice, we are of
    the view that in the facts and circumstances, the Department
    cannot take advantage of various earlier decisions. The
    claim on account of impersonal machinery and inherited
    bureaucratic methodology of making several notes cannot be
    accepted in view of the modern technologies being used and
    available. The law of limitation undoubtedly binds
    everybody, including the Government.

    29. In our view, it is the right time to inform all the
    government bodies, their agencies and instrumentalities that
    unless they have reasonable and acceptable explanation for
    the delay and there was bona fide effort, there is no need to
    accept the usual explanation that the file was kept pending
    for several months/years due to considerable degree of
    procedural red tape in the process. The government
    departments are under a special obligation to ensure that
    they perform their duties with diligence and commitment.
    Condonation of delay is an exception and should not be used
    as an anticipated benefit for the government departments.
    The law shelters everyone under the same light and should
    not be swirled for the benefit of a few.”

    Likewise, the Hon’ble Apex Court in State of Madhya
    Pradesh & Anr. Vrs. Chaitram Maywade, [(2020) 10 SCC 667],
    after referring to the judgment rendered by the Hon’ble Apex Court
    in Post Master General & Ors. Vrs. Living Media India Limited
    & Anr.
    (supra,) has held at paragraphs 1 to 5 as hereunder:

    “1. The State of Madhya Pradesh continues to do the same thing
    again and again and the conduct seems to be incorrigible. The
    special leave petition has been filed after a delay of 588 days. We
    had an occasion to deal with such inordinately delayed filing of
    the appeal by the State of Madhya Pradesh in State of
    M.P. v. Bherulal [State of M.P.
    v. Bherulal, (2020) 10 SCC 654]
    in terms of our order dated 15-10-2020.

    2. We have penned down a detailed order in that case and we see
    no purpose in repeating the same reasoning again except to
    record what are stated to be the facts on which the delay is sought
    to be condoned.
    On 5-1-2019, it is stated that the Government
    Advocate was approached in respect of the judgment delivered on
    13-11-2018 [Chaitram Maywade v. State of M.P., 2018 SCC
    OnLine HP 1632] and the Law Department permitted filing of the
    SLP against the impugned order on 26-5-2020. Thus, the Law
    Department took almost about 17 months’ time to decide whether
    the SLP had to be filed or not. What greater certificate of
    incompetence would there be for the Legal Department.

    3. We consider it appropriate to direct the Chief Secretary of the

    Page | 6
    [2026:JHHC:20422-DB]

    State of Madhya Pradesh to look into the aspect of revamping the
    Legal Department as it appears that the Department is unable to
    file appeals within any reasonable period of time much less within
    limitation. These kinds of excuses, as already recorded in the
    aforesaid order, are no more admissible in view of the judgment
    in Postmaster General v. Living Media (India) Ltd. [Postmaster
    General v. Living Media (India) Ltd., (2012) 3 SCC 563 : (2012)
    2 SCC (Civ) 327 : (2012) 2 SCC (Cri) 580 : (2012) 1 SCC (L&S)
    649]

    4. We have also expressed our concern that these kinds of the
    cases are only “certificate cases” to obtain a certificate of
    dismissal from the Supreme Court to put a quietus to the issue.
    The object is to save the skin of officers who may be in default.
    We have also recorded the irony of the situation where no action
    is taken against the officers who sit on these files and do nothing.

    5. Looking to the period of delay and the casual manner in which
    the application has been worded, the wastage of judicial time
    involved, we impose costs on the petitioner State of Rs 35,000 to
    be deposited with the Mediation and Conciliation Project
    Committee. The amount be deposited within four weeks. The
    amount be recovered from the officer(s) responsible for the delay
    in filing and sitting on the files and certificate of recovery of the
    said amount be also filed in this Court within the said period of
    time. We have put to Deputy Advocate General to caution that for
    any successive matters of this kind the costs will keep on going
    up.”

    The Hon’ble Apex Court in Ramlal, Motilal and
    Chhotelal Vrs. Rewa Coalfields Ltd., (1962) 2 SCR 762, has held
    that merely because sufficient cause has been made out in the facts
    of the given case, there is no right to the appellant to have delay
    condoned. At paragraph-12, it has been held as hereunder:-

    “12. It is, however, necessary to emphasise that even after
    sufficient cause has been shown a party is not entitled to the
    condonation of delay in question as a matter of right. The proof of
    a sufficient cause is a condition precedent for the exercise of the
    discretionary jurisdiction vested in the court by Section 5. If
    sufficient cause is not proved nothing further has to be done; the
    application for condoning delay has to be dismissed on that
    ground alone. If sufficient cause is shown then the court has to
    enquire whether in its discretion it should condone the delay. This
    aspect of the matter naturally introduces the consideration of all
    relevant facts and it is at this stage that diligence of the party or
    its bona fides may fall for consideration; but the scope of the
    enquiry while exercising the discretionary power after sufficient
    cause is shown would naturally be limited only to such facts as
    the court may regard as relevant. It cannot justify an enquiry as
    to why the party was sitting idle during all the time available to it.
    In this connection we may point out that considerations of bona
    fides or due diligence are always material and relevant when the
    court is dealing with applications made under Section 14 of the
    Limitation Act. In dealing with such applications the court is
    called upon to consider the effect of the combined provisions of
    Sections 5 and 14. Therefore, in our opinion, considerations
    which have been expressly made material and relevant by the

    Page | 7
    [2026:JHHC:20422-DB]

    provisions of Section 14 cannot to the same extent and in the
    same manner be invoked in dealing with applications which fall
    to be decided only under Section 5 without reference to Section

    14. In the present case there is no difficulty in holding that the
    discretion should be exercised in favour of the appellant because
    apart from the general criticism made against the appellant’s lack
    of diligence during the period of limitation no other fact had been
    adduced against it. Indeed, as we have already pointed out, the
    learned Judicial Commissioner rejected the appellant’s
    application for condonation of delay only on the ground that it
    was appellant’s duty to file the appeal as soon as possible within
    the period prescribed, and that, in our opinion, is not a valid
    ground.”

    Thus, it is evident that while considering the delay
    condonation application, the Court of Law is required to consider
    the sufficient cause for condonation of delay as also the approach
    of the litigant as to whether it is bona fide or not as because after
    expiry of the period of limitation, a right is accrued in favour of the
    other side and as such, it is necessary to look into the bona fide
    motive of the litigant and at the same time, due to inaction and
    laches on its part.

    It also requires to refer herein that what is the meaning of
    ‘sufficient cause’. The consideration of meaning of ‘sufficient
    cause’ has been made in Basawaraj & Anr. Vrs. Spl. Land
    Acquisition Officer, [(2013) 14 SCC 81], wherein, it has been held
    by the Hon’ble Apex Court at paragraphs 9 to 15 hereunder:-

    “9. Sufficient cause is the cause for which the defendant could not
    be blamed for his absence. The meaning of the word “sufficient”

    is “adequate” or “enough”, inasmuch as may be necessary to
    answer the purpose intended. Therefore, the word “sufficient”
    embraces no more than that which provides a platitude, which
    when the act done suffices to accomplish the purpose intended in
    the facts and circumstances existing in a case, duly examined
    from the viewpoint of a reasonable standard of a cautious man. In
    this context, “sufficient cause” means that the party should not
    have acted in a negligent manner or there was a want of bona
    fide on its part in view of the facts and circumstances of a case or
    it cannot be alleged that the party has “not acted diligently” or
    “remained inactive”. However, the facts and circumstances of
    each case must afford sufficient ground to enable the court
    concerned to exercise discretion for the reason that whenever the
    court exercises discretion, it has to be exercised judiciously. The
    applicant must satisfy the court that he was prevented by any
    “sufficient cause” from prosecuting his case, and unless a
    satisfactory explanation is furnished, the court should not allow
    the application for condonation of delay. The court has to
    examine whether the mistake is bona fide or was merely a device
    to cover an ulterior purpose. (See Manindra Land and Building

    Page | 8
    [2026:JHHC:20422-DB]

    Corpn. Ltd. v. Bhutnath Banerjee [AIR 1964 SC 1336] , Mata
    Din v. A. Narayanan
    [(1969) 2 SCC 770 : AIR 1970 SC 1953]
    , Parimal v. Veena
    [(2011) 3 SCC 545 : (2011) 2 SCC (Civ) 1 :

    AIR 2011 SC 1150] and Maniben Devraj Shah v. Municipal
    Corpn. of Brihan Mumbai [(2012) 5 SCC 157 : (2012) 3 SCC
    (Civ) 24 : AIR 2012 SC 1629] .)

    10. In Arjun Singh v. Mohindra Kumar [AIR 1964 SC 993] this
    Court explained the difference between a “good cause” and a
    “sufficient cause” and observed that every “sufficient cause” is a
    good cause and vice versa. However, if any difference exists it
    can only be that the requirement of good cause is complied with
    on a lesser degree of proof than that of “sufficient cause”.

    11. The expression “sufficient cause” should be given a liberal
    interpretation to ensure that substantial justice is done, but
    only so long as negligence, inaction or lack of bona fides cannot
    be imputed to the party concerned, whether or not sufficient cause
    has been furnished, can be decided on the facts of a particular
    case and no straitjacket formula is possible.
    (Vide Madanlal v. Shyamlal [(2002) 1 SCC 535 : AIR 2002 SC
    100] and Ram Nath Sao v. Gobardhan Sao
    [(2002) 3 SCC 195 :

    AIR 2002 SC 1201] .)

    12. It is a settled legal proposition that law of limitation may
    harshly affect a particular party but it has to be applied with all
    its rigour when the statute so prescribes. The court has no power
    to extend the period of limitation on equitable grounds. “A result
    flowing from a statutory provision is never an evil. A court has no
    power to ignore that provision to relieve what it considers a
    distress resulting from its operation.” The statutory provision
    may cause hardship or inconvenience to a particular party but the
    court has no choice but to enforce it giving full effect to the same.
    The legal maxim dura lex sed lex which means “the law is hard
    but it is the law”, stands attracted in such a situation. It has
    consistently been held that, “inconvenience is not” a decisive
    factor to be considered while interpreting a statute.

    13. The statute of limitation is founded on public policy, its aim
    being to secure peace in the community, to suppress fraud and
    perjury, to quicken diligence and to prevent oppression. It seeks
    to bury all acts of the past which have not been agitated
    unexplainably and have from lapse of time become stale.
    According to Halsbury’s Laws of England, Vol. 28, p. 266:

    “605. Policy of the Limitation Acts.–The courts have expressed
    at least three differing reasons supporting the existence of
    statutes of limitations namely, (1) that long dormant claims have
    more of cruelty than justice in them, (2) that a defendant might
    have lost the evidence to disprove a stale claim, and (3) that
    persons with good causes of actions should pursue them with
    reasonable diligence.”

    An unlimited limitation would lead to a sense of insecurity and
    uncertainty, and therefore, limitation prevents disturbance or
    deprivation of what may have been acquired in equity and justice
    by long enjoyment or what may have been lost by a party’s own
    inaction, negligence or laches. (See Popat and Kotecha
    Property v. SBI Staff Assn.
    [(2005) 7 SCC 510] , Rajender
    Singh v. Santa Singh
    [(1973) 2 SCC 705 : AIR 1973 SC 2537]
    and Pundlik Jalam Patil v. Jalgaon Medium Project
    [(2008) 17
    SCC 448]

    Page | 9
    [2026:JHHC:20422-DB]

    14. In P. Ramachandra Rao v. State of Karnataka [(2002) 4 SCC
    578 ] this Court held that judicially engrafting principles of
    limitation amounts to legislating and would fly in the face of law
    laid down by the Constitution Bench in Abdul Rehman
    Antulay v. R.S. Nayak
    [(1992) 1 SCC 225].

    15. The law on the issue can be summarised to the effect that
    where a case has been presented in the court beyond limitation,
    the applicant has to explain the court as to what was the
    “sufficient cause” which means an adequate and enough reason
    which prevented him to approach the court within limitation. In
    case a party is found to be negligent, or for want of bona fide on
    his part in the facts and circumstances of the case, or found to
    have not acted diligently or remained inactive, there cannot be a
    justified ground to condone the delay. No court could be justified
    in condoning such an inordinate delay by imposing any condition
    whatsoever. The application is to be decided only within the
    parameters laid down by this Court in regard to the condonation
    of delay. In case there was no sufficient cause to prevent a litigant
    to approach the court on time condoning the delay without any
    justification, putting any condition whatsoever, amounts to
    passing an order in violation of the statutory provisions and it
    tantamounts to showing utter disregard to the legislature.”

    Thus, it is evident that the sufficient cause means that the
    party should not have acted in a negligent manner or there was a
    want of bona fide on its part in view of the facts and circumstances
    of a case or it cannot be alleged that the party has “not acted
    deliberately” or “remained inactive”. However, the facts and
    circumstances of each case must afford sufficient ground to enable
    the Court concerned to exercise discretion for the reason that
    whenever the Court exercises discretion, it has to be exercised
    judiciously. The applicant must satisfy the Court that he was
    prevented by any “sufficient cause” from prosecuting his case, and
    unless a satisfactory explanation is furnished, the Court should not
    allow the application for condonation of delay. The Court has to
    examine whether the mistake is bona fide or was merely a device to
    cover the ulterior purpose as has been held in Manindra Land and
    Building Corporation Ltd. Vrs. Bhutnath Banerjee & Ors., AIR
    1964 SC 1336, Lala Matadin Vrs. A. Narayanan, (1969) 2 SCC
    770, Parimal Vrs. Veena @ Bharti, (2011) 3 SCC 545 and
    Maniben Devraj Shah Vrs. Municipal Corporation of Brihan
    Mumbai, (2012) 5 SCC 157.

    It has further been held in the aforesaid judgments that the
    expression ‘sufficient cause’ should be given a liberal interpretation
    Page | 10
    [2026:JHHC:20422-DB]

    to ensure that substantial justice is done, but only so long as
    negligence, inaction or lack of bona fides cannot be imputed to the
    party concerned, whether or not sufficient cause has been
    furnished, can be decided on the facts of a particular case and no
    straitjacket formula is possible, reference in this regard may be
    made to the judgment rendered by the Hon’ble Apex Court in Ram
    Nath Sao @ Ram Nath Sahu & Ors. Vrs. Gobardhan Sao & Ors.,
    (2002) 3 SCC 195, wherein, at paragraph-12, it has been held as
    hereunder:-

    “12. Thus, it becomes plain that the expression “sufficient cause”

    within the meaning of Section 5 of the Act or Order 22 Rule 9 of
    the Code or any other similar provision should receive a liberal
    construction so as to advance substantial justice when no
    negligence or inaction or want of bona fides is imputable to a
    party. In a particular case whether explanation furnished would
    constitute “sufficient cause” or not will be dependent upon facts
    of each case. There cannot be a straitjacket formula for accepting
    or rejecting explanation furnished for the delay caused in taking
    steps. But one thing is clear that the courts should not proceed
    with the tendency of finding fault with the cause shown and reject
    the petition by a slipshod order in over-jubilation of disposal
    drive. Acceptance of explanation furnished should be the rule and
    refusal, an exception, more so when no negligence or inaction or
    want of bona fides can be imputed to the defaulting party. On the
    other hand, while considering the matter the courts should not
    lose sight of the fact that by not taking steps within the time
    prescribed a valuable right has accrued to the other party which
    should not be lightly defeated by condoning delay in a routine-
    like manner. However, by taking a pedantic and hypertechnical
    view of the matter the explanation furnished should not be
    rejected when stakes are high and/or arguable points of facts and
    law are involved in the case, causing enormous loss and
    irreparable injury to the party against whom the lis terminates,
    either by default or inaction and defeating valuable right of such
    a party to have the decision on merit. While considering the
    matter, courts have to strike a balance between resultant effect of
    the order it is going to pass upon the parties either way.”

    10. It is evident from the judgments referred hereinabove, wherein,
    expression ‘sufficient cause’ has been dealt with which means that
    the party should not have acted in a negligent manner or there was
    a want of bona fide on its part in view of the facts and
    circumstances of a case or it cannot be alleged that the party has
    “not acted deliberately” or “remained inactive”.

    11. This Court, after considering the aforesaid proposition and the
    explanation furnished in the delay condonation application to

    Page | 11
    [2026:JHHC:20422-DB]

    condone the inordinate delay of 197 days, is proceeding to examine
    as to whether the explanation furnished can be said to be sufficient
    explanation for condoning the delay.

    12. As would appear from the explanation furnished, wherein, it has
    been stated in the interlocutory application that the judgment in
    W.P.(S) No. 618 of 2019 was passed on 13.03.2024 and in the
    meantime the Parliamentary Election was notified and the officials
    of the Department was involved in the said process. Thereafter, the
    impugned judgment came to the knowledge of the
    appellant/respondent, thereafter on 29.05.2024, the same was put
    up before the Under Secretary for further action.

    Thereafter, the Under Secretary placed the file before the
    Special Secretary for the needful and on 30.05.2024 the Special
    Secretary immediately placed the file before the Secretary with the
    aforesaid order. Thereafter, Secretary desired various inputs in the
    matter and opined for holding a meeting and on 12.06.2024,
    Section Officer submitted the details sought in the matter.

    Thereafter on 13.06.2024 it was desired to place the file
    along with the Grounds of Appeal. Thereafter on 20.06.2024,
    Assistant Section Officer placed the file before the Section Officer
    with respect to taking opinion for filing an appeal and on
    09.07.2024, Section Officer placed the file before the Under
    Secretary for taking opinion from the Learned Advocate General.

    Thereafter on 10.07.2024 Under Secretary put up the file
    before the Special Secretary for the needful and thereafter on
    10.07.2024, Special Secretary placed the file before the Secretary
    for the needful and thereafter, the file was placed before the
    Learned Advocate General for opinion against the judgment dated
    13.03.2024 passed in W.P.(S) No.618 of 2019. Thereafter, it was
    opined to file an appeal against the judgment dated 13.03.2024
    passed in W.P. (S) No. 618 of 2019 and the same was received on
    12.07.2024. Thereafter, the file was returned to the department for
    needful.

    Page | 12
    [2026:JHHC:20422-DB]

    Thereafter, on 16.07.2024 the file was put up before the
    Section Officer with the opinion for needful and the Section Officer
    put up the file before the Secretary with the opinion and for sending
    the file to the retainer for preparation of Grounds of Appeal.

    Thereafter, on 25.07.2024 Grounds of Appeal was
    submitted by the retainer and was placed for approval. Thereafter,
    on 31.07.2024, Assistant Section Officer put up the file before the
    Section Officer for approval of Grounds of Appeal. Thereafter, on
    05.08.2024, Section Officer put up the file before the Under
    Secretary for approval of Grounds of Appeal and on 06.08.2024,
    Under Secretary put up the file before the Special Secretary for
    approval of Grounds of Appeal. Thereafter, on 06.08.2024, Special
    Secretary put up the file before the Secretary for approval of
    Grounds of Appeal and on 10.08.2024 Grounds of appeal was
    approved.

    Thereafter, authorization letter was prepared and the same
    was issued on 12.08.2024. and the file was forwarded to the
    concerned law officer to prepare the memo of appeal against the
    Judgment dated 13.03.2024 passed in W.P.(S) No. 618 of 2019 and
    thereafter, the entire file was handed over to the concerned law
    officer for doing needful for filing of LPA and thereafter the appeal
    was drafted and the entire writ court pleadings were required, as
    such, the same was accordingly arranged and handed over but some
    documents was missing in the matter. The same were thereafter
    arranged and handed over and the appeal was filed on 12.09.2024
    without any further delay. Therefore, the delay of 197 days has
    occurred in filing the appeal.

    13. It appears from the stated grounds in the delay condonation
    application that the cause has been tried to be shown of engagement
    of the concerned officials of the department in the Parliamentary
    Election and movement of file from one department to another and
    no sufficient cause has been explained to condone the delay of 197
    days occurred in preferring the appeal.

    Page | 13
    [2026:JHHC:20422-DB]

    14. This Court, even if will accept the ground, as has been taken in the
    instant interlocutory application, of engagement of the concerned
    officials of the department in the Parliamentary Election, as per the
    statement made in the interlocutory application, the fate of the
    judgment dated 13.03.2024 passed in W.P.(S) No. 618 of 2019
    came to the knowledge and the file was put up before the Under
    Secretary on 29.05.2024, hence, this Court is of the view that the
    time taken in placing the file before the concerned official is about
    two and a half months and if the said ground will be accepted, then
    also, the other grounds for the further delay has been shown only of
    movement of file from one department to another and from table to
    table, which shows the lackadaisical approach of the appellant-
    State.

    15. This Court, therefore, is of the view that in such circumstances as
    per the reference made hereinabove about the conduct of the State-
    appellant, the same cannot be said to be sufficient cause to condone
    the delay of 197 days.

    16. The co-ordinate Bench of this Court has passed an order in L.P.A.
    No.86 of 2021 on 05.01.2022 rejecting the delay condonation
    application since the appeal was filed after delay of about 687 days
    without any sufficient cause to condone the delay.

    17. The reference of another case is required to be made herein of an
    order passed by the coordinate Bench of this Court in L.P.A.
    No.835 of 2019, wherein, the issue of condoning the delay of 568
    days was under consideration.

    The coordinate Bench of this Court has not found the
    reason furnished by the State appellants therein to be sufficient
    cause on the ground of movement of file from one table to another
    by putting reliance upon the judgment rendered by the Hon’ble
    Apex as referred hereinabove.

    18. The State appellant has travelled to the Hon’ble Apex Court by
    filing the SLP being SLP No.7755 of 2022 and has challenged the
    order passed in L.P.A. No.835 of 2019 but the said SLP No.7755 of

    Page | 14
    [2026:JHHC:20422-DB]

    2022 has been dismissed as would appear from the order dated
    13.05.2022.

    The Hon’ble Apex Court has also dismissed one Special
    Leave to Appeal (C) Nos.8378-8379/2023 on 28th April, 2023 filed
    by the State of Jharkhand which was filed against the order passed
    by this Court in L.P.A. No.99 of 2021, wherein the coordinate
    Bench of this Court dismissed the said appeal on the basis of delay
    of 534 days in filing of the appeal.

    19. The Hon’ble Apex Court has also dismissed S.L.P.(C) Diary No.(S)
    No.3188 of 2024 on 02.02.2024 filed by the State of Jharkhand
    against the order dated 14.08.2023 passed by this Court in L.P.A.
    No.401 of 2022, wherein, the delay of 259 days was not condoned.

    20. This Court, after taking into consideration the ratio laid by the
    Hon’ble Apex Court in the judgments referred hereinabove as also
    the explanation furnished in the delay condonation application, is
    of the view that no sufficient cause has been shown to condone
    inordinate delay of 197 days in filing the appeal.

    21. Accordingly, the delay condonation application being I.A. No.7136
    of 2025 is hereby dismissed.

    22. In consequence thereof, the instant appeal also stands dismissed.

    23. In consequence of dismissal of appeal, pending interlocutory
    application(s), if any, also stand dismissed.

    (Sujit Narayan Prasad, J.)

    (Sanjay Prasad, J.)

    09th July, 2026

    Saurabh/A.F.R.

    Uploaded on 13.07.2026

    Page | 15



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here