Sri Krishnendu Mondal vs Swapan Dey on 1 April, 2026

    0
    36
    ADVERTISEMENT

    Calcutta High Court

    Sri Krishnendu Mondal vs Swapan Dey on 1 April, 2026

    Author: Ravi Krishan Kapur

    Bench: Ravi Krishan Kapur

                                                                                            2026:CHC-OS:109
                           IN THE HIGH COURT AT CALCUTTA
                                     ORIGINAL SIDE
                                Original Civil Jurisdiction
    BEFORE:
    The Hon'ble Justice Ravi Krishan Kapur
    
                                       RVWO/23/2024
                                           WITH
                                        AP/818/2023
    
                                SRI KRISHNENDU MONDAL
                                          VS
                                      SWAPAN DEY
    
    
    For the petitioner          : Mr. Dibyendu Chatterjee, Advocate
                                  Ms. Rashmi Ghosh, Advocate
                                  Ms. Parna Mukherjee, Advocate
                                  Mr. Rahul Deb Goenka, Advocate
                                  Mr. S. Chatterjee, Advocate
    
    For the respondent          : Mr. Abhishek Kabir, Advocate
    
    Heard on                    : 1 April, 2026
    
    Judgment on                 : 1 April, 2026
    
    Ravi Krishan Kapur, J.:
    

    1. This is an application seeking review of an order dated 19 April 2024

    passed in an application under section 11 (6) of the Arbitration and

    SPONSORED

    Conciliation Act, 1996. For convenience, the order dated 19 April,

    2024 is set out below:

    “The Court: It is fairly submitted by the petitioner that the instant
    application is misconceived and there is no valid nor subsisting
    arbitration clause by and between the parties. The respondent is
    represented and submits that there has been gross fraud perpetrated
    by the petitioner and that on the basis of an invalid and inoperative
    arbitration clause, proceedings have also been filed under Section 9 of
    the Arbitration and Conciliation Act, 1996 before the District Judge at
    Alipore. For convenience, clause 17 of the agreement is set out
    hereinbelow;

    “17. That in event of any problem that the both party can appoint any
    Arbitrator with the consent of other party.”

    2

    2026:CHC-OS:109
    A perusal of the said clause would ex facie demonstrate that the same
    is unintelligible and meaningless. There is lack of mutuality and no
    consensus ad idem. In fact, there is no valid arbitration clause between
    the parties. In such circumstances, as prayed for by the petitioner,
    AP/818/2023 stands dismissed on the ground of maintainability.

    Needless to mention, the incidental proceedings under Section 9 of the
    Arbitration and Conciliation Act, 1996 are also misconceived and not
    maintainable. Both parties are at liberty to take appropriate steps,
    before the learned District Judge at Alipore in Misc. Case no. 15/2023,
    in accordance with law.”

    2. The present application for review has been filed on the ground that

    though the arbitration clause is cryptic but the intention is clear from

    the word “Arbitrator” that there was consensus to refer the disputes to

    arbitration. In this background, the applicants seeks review on the

    ground that there is an error apparent from the records and the

    application is liable to be allowed. In support of such contentions, the

    applicant relies on Jagdish Chander vs. Ramesh Chander & Ors.

    (2007) 5 SCC 719, Powertech World Wide Ltd. Vs. Delvin International

    General Trading LLC (2012) 1 SCC 361 and Visa International Ltd. Vs.

    Continental Resources (USA) Ltd. (2009) 2 SCC 55.

    3. On behalf of the respondent, it is submitted that there is no scope for

    review of an order passed under section 11 of the Act and the only

    remedy of the petitioner is to file an appeal. The jurisdiction of review

    cannot be invoked to reopen and reconsider a determination made

    under section 11 of the Act. In any event, in view of the recorded

    concession in the order dated 19 April, 2024, the applicant is

    estopped from seeking review of the order. There is no binding

    arbitration agreement between the parties. The word “Arbitrator” in

    the clause does not automatically make the same binding. In support
    3

    2026:CHC-OS:109
    of such contentions, the respondent relies on Jagdish Chander vs.

    Ramesh Chander & Ors. (Supra), BGM and M-Rpl-Jmct (JV) vs. Easter

    Coalfields Ltd. 2025 SCC OnLine SC 1471, (BVEPL Bhartia (JV) vs.

    State of West Bengal & Ors. Judgment dated 22.05.2025 passed by a

    Co-ordinate Bench in A.P.-Com 991 of 2024, Calcutta High Court and

    South Delhi Municipal Corporation of Delhi vs. SMS Ltd. (2026) 1 SCC

    545 and Vimaleshwar Nagappa Shet v. Noor Ahmed Shariff, (2011) 12

    SCC 658.

    4. At the outset, the order dated 9 April 2024 was passed at the

    invitation of the petitioner. The concession made by the Advocates

    appearing for the petitioner is expressly recorded in the opening

    sentence of the order. There is no challenge to the said recording in

    this application. A mere change of Advocates does not give a ground to

    review the recording in the order. There is no mistake of the Court

    which warrants interference. [Vimleshwar Nagappa Shet vs Noor

    Ahmad Sheriff and Ors. (Supra)].

    5. It is now well-settled that the Arbitration and Conciliation Act, 1996 is

    a self-contained Code and the scope for judicial intervention is limited

    in cases where an order is passed under section 11 of the Act. The

    only remedy available to a party is to approach the Hon’ble Supreme

    Court challenging the said order or raise the question of jurisdiction

    before the Arbitral Tribunal. It has been repeatedly reiterated that

    attempts to re-agitate issues through the back-door of what the

    statute has expressly prohibited is impermissible. Any attempt to

    review an order passed under Section 11(6) of the Act goes against the
    4

    2026:CHC-OS:109
    grain of the Act and undermines the principle of minimal judicial

    interference. [Hindustan Construction Company Ltd. Vs. Bihar Rajya

    Pul Nirman Nigam Ltd. (Supra), BSNL vs. Nortel Networks (India) (P) Ltd.

    (Supra)].

    6. In any event, apart from the question of maintainability even on

    merits there is no question for re-opening the order dated 19 April

    2024. The use of the expression ‘can’ in the arbitration clause does

    not indicate finality nor conclusiveness. An arbitration agreement

    must reflect a definitive and mutual intention to refer the disputes to

    arbitration. The agreement must contemplate a binding and

    enforceable resolution of disputes. There must be both clarity and

    certainty in an arbitration clause. There is something incomplete and

    tentative about the arbitration clause and the same requires the

    parties to arrive at a further agreement to go to arbitration. An

    agreement requiring further consent is not a binding arbitration

    agreement. There is an element of contingency which is left in the

    arbitration clause which makes the same tentative, optional and

    incapable of enforcement. It is not the role of any Court to fill in the

    gaps in case the arbitration clause is inaccurately or inartistically

    drafted. In this connection, the decision in Visa International Ltd.

    (Supra) is distinguishable. In the said decision, the arbitration clause

    provided that the disputes “shall be finally settled”. The use of the

    word ‘shall’ indicated a clear binding and unequivocal intention of the

    parties to refer the disputes to arbitration. To this extent, the mere

    use of the word ‘Arbitrator’ is irrelevant and is not conclusive insofar
    5

    2026:CHC-OS:109
    as the arbitration clause is concerned. [Jagdish Chander v. Ramesh

    Chander & Ors. (Supra), BGM and M-Rpl-Jmct (JV) v. Easter Coalfields

    Limited (Supra). BVEPL Bhartia (JV) v. State of West Bengal & Ors.

    (Supra). South Delhi Municipal Corporation of Delhi v. SMS Limited

    (Supra)].

    7. In view of the above, the present application is dismissed both on the

    grounds of maintainability and on the merits.

    (Ravi Krishan Kapur, J.)



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here