Sarada Metals And Alloys Ltd vs A.P. Electricity Regulatory … on 22 April, 2026

    0
    32
    ADVERTISEMENT

    Andhra Pradesh High Court – Amravati

    Sarada Metals And Alloys Ltd vs A.P. Electricity Regulatory … on 22 April, 2026

     APHC010465652024                                                           Bench
                             IN THE HIGH COURT OF ANDHRA PRADESH
                                                                                [3483]
                                          AT AMARAVATI
    
                                 WRIT PETITION NO: 24693 of 2024
    
    Sarada Metals and Alloys Ltd.                                         ...Petitioner
    
         Vs.
    
    A.P. Electricity Regulatory Commission                              ...Respondent
    
                                          **********
    
    Advocate for Petitioner:                   Mr. P. Chidambaram, learned Senior
                                               Counsel appearing vice Mr. Sai Sanjay
                                               Suraneni
    
    Advocate for Respondent:                   Mr. V. R. N. Prashanth
    
             CORAM : THE CHIEF JUSTICE DHIRAJ SINGH THAKUR
                     SRI JUSTICE RAVI CHEEMALAPATI
    
             DATE       : 22nd April, 2026.
    
    
    Per DHIRAJ SINGH THAKUR, CJ:
    
    
           The petitioner in the present Writ Petition challenges inter alia the
    
    validity and vires of Regulation 3.3 of the Andhra Pradesh Electricity
    
    Regulatory Commission Renewable Power Purchase Obligation (Compliance
    
    by   purchase       of    Renewable   Energy/Renewable     Energy    Certificates)
    
    Regulations, 2017 and 2022, issued by the Andhra Pradesh Electricity
    
    Regulatory Commission (for short, "the APERC").
    
    
    2.     With a view to understand in the correct perspective the background in
    
    which the present controversy arises, it is necessary to give in brief the
    
    material facts:
                                              2
                                                                               HCJ & RCJ
                                                                           WP_24693_2024
    
    
          The petitioner is engaged in the business of manufacturing and export
    
    of manganese - based Ferro Alloys which is a primary element of steel
    
    making. For this the petitioner claims to operate the Ferro Alloys Plant at
    
    Vizianagaram in Andhra Pradesh. The petitioner also claims to operate an 80
    
    MW Captive Power Plant within the premises of the Ferro Alloy Plant. The
    
    petitioner further claims that it synchronized its Captive Power Plant on
    
    03.02.2013 and therefore, fell within the ambit of Ministry of Power‟s directive
    
    dated 01.10.2019, reference whereto shall be made in the later paragraphs.
    
    
    3.    At this stage, it is also deemed apt to refer to the statutory provisions
    
    which are relevant for the decision in the instant case.
    
    
          The Electricity Act, 2003 (for short, "the Act of 2003") was enacted with
    
    a view to consolidate the laws relating to generation, transmission,
    
    distribution, trading and use of electricity and also for taking measures
    
    conducive to the development of the electricity industry, rationalisation of
    
    electricity tariff and for constitution of Central Electricity Authority, Regulatory
    
    Commissions and establishment of Appellate Tribunal and matters connected
    
    therewith.
    
    
    4.    Before the promulgation of the Act of 2003, the electricity supply in India
    
    was governed by three enactments namely the Indian Electricity Act, 1910,
    
    the Electricity (Supply) Act, 1948 and the Electricity Regulatory Commissions
    
    Act, 1998.
                                             3
                                                                             HCJ & RCJ
                                                                         WP_24693_2024
    
    
    5.    While the Indian Electricity Act, 1910 created the basic framework for
    
    electricity supply in India, the Electricity (Supply) Act, 1948 envisaged the
    
    creation of State Electricity Boards, on whom a duty was enjoined to arrange
    
    the supply of electricity. However, the performance of SEBs is said to have
    
    deteriorated on account of various factors and in that backdrop with a view to
    
    encourage private sector participation in generation, transmission and
    
    distribution and with the objective of distancing the regulatory responsibilities
    
    from the Government to the Regulatory Commissions and with a view to
    
    harmonise and rationalise the provisions of the Indian Electricity Act, 1910, the
    
    Electricity (Supply) Act, 1948 and the Electricity Regulatory Commissions Act,
    
    1998, there was a need felt for self-contained comprehensive legislation which
    
    finally assumed the shape of the Electricity Act, 2003.
    
    
    6.    At this stage, it would be apt to refer to some of the provisions of the Act
    
    of 2003:
    
    
          While Section 2 of the Act pertains to definitions, Section 3 envisages
    
    that the Central Government shall from time to time prepare "the National
    
    Electricity Policy and Tariff Policy" in consultation with State Governments and
    
    the authority for development of the power systems.
    
    
    7.    Sub-section (2) of Section 3 envisages that the Central Government
    
    shall publish the National Electricity Policy and Tariff Policy from time to time
    
    and further, Section 3(3) of the Act confers the Central Government with the
                                              4
                                                                            HCJ & RCJ
                                                                        WP_24693_2024
    
    
    power to review and revise the National Electricity Policy and the Tariff Policy,
    
    in consultation with the State Governments and the Authority.
    
    
    8.    Section 3(4) envisages preparation of National Electricity Plan in
    
    accordance with the National Electricity Policy and is required to be notified
    
    once in five years.
    
    
    9.    Section 9 of the Act deals with captive generation and envisages that a
    
    person may construct, maintain and operate a captive generating plant and
    
    dedicated transmission lines with a right inter alia to an open access for
    
    purposes of carrying electricity from its captive generation plant to the
    
    destination of its use which further is made subject to availability of adequate
    
    transmission facility.
    
    
    10.   Section 61 falling in Part VII of the Act deals with Tariff Regulations and
    
    envisages that the Appropriate Commission shall subject to the provisions of
    
    the Act, specify the terms and conditions for determination of tariff. It further
    
    envisages that the determination of tariff shall inter alia be guided by the
    
    National Electricity Policy and Tariff Policy.
    
    
    11.   According to Section 2(4), Appropriate Commission means the Central
    
    Regulatory Commission referred to in sub-section (1) of Section 76 or the
    
    State Regulatory Commission referred to in Section 82 or the Joint
    
    Commission referred to in Section 83, as the case may be.
                                                5
                                                                                    HCJ & RCJ
                                                                                WP_24693_2024
    
    
    12.   Section 82 envisages constitution of Electricity Regulatory Commission
    
    which would be prefixed by the name of the respective States. The State
    
    Governments were enjoined to constitute the State Electricity Regulatory
    
    Commissions within six months from the appointed date, by notification.
    
    However, as per the proviso to Section 82, the State Electricity Regulatory
    
    Commission established by the State Governments under Section 17 of the
    
    Electricity Regulatory Commissions Act, 1988, and functioning immediately
    
    before the appointed date, would continue to be the State Commission for
    
    purposes of the Act of 2003.
    
    
    13.   The State Electricity Regulatory Commissions would be deemed to be a
    
    body corporate having perpetual succession and common seal.
    
    
    14.   Section 86 of the Act of 2003 envisages the functions to be discharged
    
    by the State Electricity Regulatory Commissions inter alia to determine the
    
    tariff for generation, supply, transmission and wheeling of electricity, within the
    
    State, facilitate intra-State transmission and wheeling of electricity, issue
    
    licences to persons seeking to act as transmission licensees, distribution
    
    licensees and electricity traders. Reference to Section 86(1)(e) is necessary,
    
    which reads as under:
    
                 "86. (1)(e) promote cogeneration and generation of
                 electricity from renewable sources of energy by providing
                 suitable measures for connectivity with the grid and sale of
                 electricity to any person, and also specify, for purchase of
                 electricity from such sources, a percentage of the total
                 consumption of electricity in the area of a distribution
                 licensee;"
                                                6
                                                                                    HCJ & RCJ
                                                                                WP_24693_2024
    
    
    15.   Section 86(4) is also important and envisages as under:
    
                (4) In discharge of its functions, the State Commission shall
                be guided by the National Electricity Policy, National
                Electricity Plan and tariff policy published under section 3.
    
    
    
    16.   Section 181 of the Act of 2003 further envisages the framing of
    
    regulations by the State Commission.
    
    
    17.   The Central Government on 06.01.2006 notified the Tariff Policy which
    
    was   further   amended      on     31.03.2008,     20.01.2011       and    08.07.2011.
    
    Subsequently, the Ministry of Power notified its revised Tariff Policy vide
    
    notification dated 28.01.2016, in accordance with the powers vested in it
    
    under Section 3 of the Electricity Act, 2003.
    
    
    18.   According to Clause 2.2 of the Tariff Policy the Central Electricity
    
    Regulatory Commission and State Electricity Regulatory Commissions were
    
    enjoined to be guided by the Tariff Policy in discharging their functions
    
    including framing of regulations.
    
    
    19.   Clause 4 of the Tariff Policy clearly envisaged inter alia that the
    
    objective of the policy was to promote generation of electricity from renewable
    
    sources.
    
    
    20.   Clause 6.4 further envisaged as under:
    
                "6.4 Renewable sources of energy generation including Co-
                generation from renewable energy sources:
    
                (1) Pursuant to provisions of section 86(1)(e) of the Act, the
                Appropriate Commission shall fix a minimum percentage of the
                total consumption of electricity in the area of a distribution
                                                      7
                                                                                          HCJ & RCJ
                                                                                      WP_24693_2024
    
                     licensee for purchase of energy from renewable energy
                     sources, taking into account availability of such resources and
                     its impact on retail tariffs. Cost of purchase of renewable energy
                     shall be taken into account while determining tariff by SERCs.
                     Long term growth trajectory of Renewable Purchase
                     Obligations (RPOs) will be prescribed by the Ministry of
                     Power in consultation with MNRE."
    
    
    
     21.       Pursuant to the notification of the Tariff Policy by way of publication in
    
     Gazette on 28.01.2016, the Government of India, Ministry of Power issued
    
     guidelines for long term growth trajectory of Renewable Purchase Obligations
    
     (RPOs) dated 22.07.2016. The following was notified as the growth trajectory
    
     for non-solar as well as solar, uniformly for all States and Union Territories for
    
     three years from 2016-17 to 2018 to 2019:
    
    
    Long term trajectory        2016-17                  2017-18                 2018-19
    Non-solar                   8.75%                    9.50%                   10.25%
    Solar                       2.75%                    4.75%                   6.75%
           Total                11.50%                   14.25%                  17.00%
    
    
     22.       The obligation to purchase renewable energy was cast on obligated
    
     entities excluding consumption met from hydro sources of power which was to
    
     be calculated on total consumption of electricity by a particular obligated
    
     entity.
    
    
     23.       An obligated entity as per the APERC RPO Regulations, 2012, means
    
     an entity obligated to purchase renewable power under clause (3) of
    
     Regulations.
    
    
     24.       The Government of India, Ministry of Power, subsequently, by virtue of
    
     the notification dated 14.06.2018, issued the long term growth trajectory of
                                                 8
                                                                                    HCJ & RCJ
                                                                                WP_24693_2024
    
    
     Renewable Purchase Obligations for Solar and Non-solar, uniformly for all the
    
     States and Union Territories for three years, i.e., 2019-20 to 2021-22 as
    
     under:
    
    
    Long term trajectory   2019-20                  2020-21                2021-22
    Non-solar              10.25%                   10.25%                 10.50%
    Solar                  7.25%                    8.75%                  10.50%
           Total           17.50%                   19.00%                 21.00%
    
    
     25.   At this point, it is relevant to refer to the Clarification, dated 01.02.2019,
    
     issued by the Government of India, Ministry of Power, clarifying that the long
    
     term growth trajectory of Renewable Purchase Obligation of Solar and Non-
    
     solar for the period 2016-19 and 2019-22 as prescribed in the Ministry‟s
    
     notification, dated 22.07.2016, at the request of various stakeholders, had
    
     been examined in consultation with Ministry of New and Renewable Energy
    
     and it was therefore clarified that RPO of the Captive Power Plant may be
    
     pegged at the RPO level applicable in the year in which the Captive Power
    
     Plant was commissioned. For facility of reference, the clarification is
    
     reproduced hereunder:
    
                 "I am directed to refer to the Ministry of Power's Order of even
                 number dated 22ndJuly, 2016 and 14thJune, 2018 regarding long
                 term growth trajectory of Renewable Purchase Obligation
                 (RPO) for Solar and Non-solar for the period 2016-19 and 2019-
                 22 respectively.
    
                 2. The request of various stakeholders regarding capping of
                 RPO for Captive Power Plants (CPP) has been examined in
                 consultation with Ministry of New and Renewable Energy and it
                 is clarified that RPO of the CPP may be pegged at the RPO
                 level applicable in the year in which the CPP was
                 commissioned. As and when the company adds to the capacity
                 of the CPP it will have to provide for additional RPO as
                 obligated in the year in which new capacity is commissioned.
                                                9
                                                                                   HCJ & RCJ
                                                                               WP_24693_2024
    
                There should not be an increase in RPO of CPP without any
                additional fossil fuel capacity being added.
    
                3. This issues with the approval of Hon'ble MoS(I/C) for Power
                and NRE."
    
    
    26.   Subsequently, another clarification, dated 01.10.2019, was issued by
    
    the Ministry of Power, which reads as under:
    
                "I am directed to refer to the Ministry of Power's Order of even
                number dated 22nd July, 2016 and 14th June, 2018 regarding
                long term growth trajectory of Renewable Purchase Obligation
                (RPO) for Solar and Non-solar for the period 2016-19 and 2019-
                22 respectively.
    
                2       A clarification was issued by Ministry of Power, vide
                letter dated 1 February, 2019 regarding capping of RPO for
                Captive Power Plants (CPP) (copy enclosed).
    
                3       Based on the concern raised by various stakeholders
                and after due consultation with MNRE, GEA and CERC it is
                further clarified that
    
                i)      For CPPs commissioned before 1.04.2016, RPO should
                be at the level as mandated by the appropriate Commission for
                the year 2015-16. For CPPs commissioned from 1.04.2016
                onwards, the RPO level as mandated by the appropriate
                Commission or Ministry of Power, whichever is higher, for the
                year of commissioning of the CPP shall be applicable.
    
                ii)     In case of any augmentation in the capacity, the RPO
                for augmented capacity shall be the RPO applicable for the year
                in which the CPP has been augmented.
    
                iii)    In case, for meeting the RPO obligation, CPP has
                surplus power than its consumption requirement, such a CPP
                may sell its surplus power to the DISCOMS under the prevailing
                arrangements or in the power exchange.
                                              10
                                                                                 HCJ & RCJ
                                                                             WP_24693_2024
    
                This issues with the approval of Hon'ble MoS(I/C) for Power
                and NRE."
    
    27.   On a reading of the above two clarifications, it becomes clear that while
    
    the clarification, dated 01.02.2019, pegged the RPO of a Captive Power Plant
    
    at the RPO level applicable in the year in which the Captive Power Plant was
    
    commissioned, as per the subsequent clarification, dated 01.10.2019, all
    
    Captive Power Plants commissioned before 01.04.2016, RPO was required to
    
    be at the level mandated by the Appropriate Commission for the year 2015-16
    
    and for all Captive Power Plants commissioned from 01.04.2016 onwards, the
    
    RPO level as mandated by the Appropriate Commission or Ministry of Power,
    
    whichever was higher, for the year of commissioning would be applicable.
    
    
    28.   In exercise of powers conferred in Sections 61, 66, 86(1) (e) and 181 of
    
    the Electricity Act, 2003, the Andhra Pradesh Electricity Regulatory
    
    Commission framed the regulations called the Renewable Power Purchase
    
    Obligation (Compliance by Purchase of Renewable Energy/Renewable
    
    Energy Certificates) Regulations, 2012 (for short, "APERC RPO Regulations,
    
    2012,").
    
    
    29.   Regulation 3.3 of the aforementioned regulations provided as under:
    
                "3.3 Every consumer owning a captive generating plant of
                installed capacity of One (1) MW shall purchase Renewable
                Energy Certificates issued under the Central Electricity
                Regulatory Commission (Terms and Conditions for
                recognition and issue of Renewable Energy Certificate for
                Renewable Energy Generation) Regulations, 2010 as
                amended from time to time, corresponding to a quantum of
                not less than 5% of its consumption of energy, during each
                of the years from 2012-13 to 2016-17 (each year
                commencing from 1stApril of the Calendar Year and ending
                                                  11
                                                                                       HCJ & RCJ
                                                                                   WP_24693_2024
    
                    on 31stMarch of the subsequent Calendar Year) provided
                    that the purchase of energy from renewable energy sources
                    shall also be treated as fulfillment of the Renewable Power
                    Purchase Obligation (RPPO) prescribed herein;"
    
    
    30.   Subsequently, the APERC notified Regulation No.1 of 2017 (APERC
    
    RPO Regulations, 2017). According to Clause 3.3 whereof, every consumer
    
    owning a captive generating plant of installed capacity at 1 MW and above
    
    and connected to the grid was required to purchase Renewable Energy
    
    Certificates issued under the Central Electricity Regulatory Commission
    
    (Terms and Conditions for recognition and issue of Renewable Energy
    
    Certificate for Renewable Energy Generation) Regulations, 2010, as amended
    
    from time to time corresponding to a minimum quantity of electricity expressed
    
    as a percentage of its consumption of energy, during FY2017-18 to FY 2021-
    
    22 as specified in TABLE-I under clause 3.1 of this Regulation, which
    
    envisaged as under:
    
    
                                              TABLE-I
    
    
            Year             2017-18      2018-19     2019-20      2020-21          2021-22
      Non-solar             6%           7%           8%          9%              10%
      Solar                 3%           4%           5%          6%              7%
            Total           9%           11%          13%         15%             17%
    
    
          Proviso to Regulation 3.3 further provided that, the purchase of energy
    
    from renewable energy sources would also be treated as fulfillment of
    
    Renewable Power Purchase Obligation.
    
    
    31.   Subsequently, the APERC framed Regulation No.5 of 2022 (APERC
    
    RPO Regulations, 2022) and notified the same on 29.09.2022, which enjoined
                                            12
                                                                            HCJ & RCJ
                                                                        WP_24693_2024
    
    
    a consumer owning a captive generating plant to purchase renewable energy
    
    as per the specifications below:
    
    
                             From the date
                             of publication
                                of these
                             Regulations in       FY        FY          FY         FY
            Period
                               the official     2023-24   2024-25     2025-26    2026-27
                             gazette to the
                               end of FY
                                2022-23
    RPPO, i.e. the                18%            19%        20%         22%        24%
    minimum quantity of
    renewable electricity
    to be purchased as a
    percentage of total
    consumption
    
    
    
    32.   As per Clause 7.1 of the 2017 Regulations, framed by the APERC, if an
    
    obligated entity does not fulfill the Renewable Power Purchase Obligation as
    
    provided in Clause 3 thereof, during any year, the Commission was given the
    
    power to direct the obligated entity to deposit such amount as the Commission
    
    may determine on the basis of the shortfall in units of the Renewable Power
    
    Purchase Obligation.
    
    
    33.   Not only this, in terms of Clause 7.2 of the Regulation, in addition to the
    
    compliance of the directions under clause (7.1), a penalty can as well be
    
    imposed by the Commission to an extent to be decided by the Commission
    
    under Section 142 of the Electricity Act, 2003.
    
    
    34.   In the backdrop of the aforementioned legal provisions, a notice dated
    
    27.12.2021, came to be served upon the petitioner intimating the petitioner
                                             13
                                                                              HCJ & RCJ
                                                                          WP_24693_2024
    
    
    regarding non-compliance of Clause 3.2/3.3 of the RPPO in its capacity as an
    
    obligated entity for the period 2012-13 to 2018-19, it was therefore required to
    
    show-cause as to why it not be directed to deposit an amount of
    
    Rs.16,46,90,400/-.
    
    
    35.   An appropriate response, dated 07.04.2022, according to the petitioner,
    
    was submitted to the show-cause notice, which was considered by the
    
    APERC but the same came to be rejected on 30.05.2023 and an amount of
    
    Rs.16,24,90,400/- was determined as payable by the petitioner on account of
    
    its failure to meet the RPPO for the energy consumed.
    
    
    36.   An Original Petition bearing No.82 of 2023 came to be filed before the
    
    APERC in which the petitioner inter alia sought a declaration that the
    
    petitioner‟s RPPO liability be capped as per the Ministry of Power‟s
    
    clarification, dated 01.10.2019, for Captive Power Plants.
    
    
    37.   By virtue of the order dated 03.09.2024, the APERC dismissed the
    
    Original Petition by holding that it was vested with exclusive powers of
    
    regulating tariffs and all other aspects related thereto, and further that the
    
    National Electricity Policy, National Electricity Plan and the Tariff Policy
    
    published under Section 3 of the Act would only be a guiding factor.
    
    
    38.   It rejected the contention of the counsel for the petitioner that the
    
    clarificatory orders passed by the Ministry of Power were in any way binding
    
    on the Commission and that if at all it had only a guiding force. It held:
                                                 14
                                                                                     HCJ & RCJ
                                                                                 WP_24693_2024
    
                 ".... No doubt, the clarificatory orders of the MoP sought to limit
                 the CPPs' liability for RPPO; the same would certainly be a
                 material consideration for this Commission while making its
                 Regulations for the future. However, as the obligation is for the
                 past periods, which is already governed by Regulations issued
                 by this Commission, in due exercise of the statutory powers, in
                 the opinion of this Commission, such Clarificatory Orders,
                 despite having statutory flavor, cannot displace the Regulations
                 already in force. In other words, to act on a Clarificatory Order
                 of the MoP would be to negate the Regulations framed and
                 notified by this Commission. Such a course is not desirable so
                 long as the Regulations continue to be enforced for the
                 Obligated Entities concerned."
    
    
    
    39.   While placing reliance on Tata Power Company Limited (supra), it
    
    was held that the Tariff Policy was not per se binding on the Commission but
    
    would be one of the material considerations only.
    
    
    40.   Although the Electricity Act did provide for an appeal under Section 111
    
    before the Appellate Tribunal for Electricity (APTEL), yet since the petitioner
    
    challenges the vires of the Regulations of 2017 & 2022, the present petition
    
    has been filed challenging the 3.3 RPPO Regulations of 2017 and 2022 as
    
    ultra vires to the Electricity Act, 2003. Apart from this, a direction is sought to
    
    APERC to amend Regulation 3.3 of the 2017 and 2022 Regulations to give
    
    effect to the Ministry of Power‟s directive, dated 01.10.2019, regarding long
    
    term growth trajectory of RPO Captive Power Plants, which envisaged a cap
    
    on RPO of Captive Power Plant commissioned before 01.04.2016 at the RPO
    
    prescribed by the APERC for F.Y. 2015-16, which was at 5% of the power
    
    consumed.
    
    
    41.   Mr. P. Chidambaram, learned Senior Counsel, would submit that the
    
    impugned regulations and, in particular, Regulation 3.3 of APERC RPPO
                                              15
                                                                               HCJ & RCJ
                                                                           WP_24693_2024
    
    
    Regulations of 2017 and 2022, are ultra vires the Electricity Act, 2003
    
    inasmuch as the regulations failed to give effect to the Ministry of Powers
    
    Directive, dated 01.10.2019, which mandates capping the RPO for Captive
    
    Power Plants commissioned before 01.04.2016 at 5%, which was applicable
    
    in the case of the petitioner herein. It was urged that the directive issued by
    
    the Ministry of Power was rooted in Clause 6.4.1 of the Tariff Policy, 2016,
    
    was therefore statutory in nature, and possessed the force of law and APERC
    
    being a delegate under the Electricity Act was statutorily bound to be guided
    
    by the Tariff Policy and the directives issued thereunder.
    
    
    42.   It was stated that Section 86(4) of the Electricity Act mandated that
    
    APERC shall be guided by the National Electricity Policy and the Tariff Policy
    
    and by disregarding the Ministry of Powers Directive, APERC had acted in
    
    contravention of these statutory provisions which rendered the impugned
    
    regulations ultra vires.
    
    
    43.   Reliance was finally placed upon the judgment of the Apex Court
    
    rendered in Reliance Infrastructure Ltd. v. State of Maharashtra and Tata
    
    Power Company Limited v. MERC &Ors.
    
    
    44.   The stand of the official respondent was that APERC was an
    
    autonomous body and further that under Section 86(1)(e) of the Act of 2003,
    
    APERC was empowered to specify Renewable Power Purchase Obligations
    
    for obligated entities within the State. It is also stated that it was an exercise of
    
    the powers so vested in the Commission that the regulations came to be
                                             16
                                                                              HCJ & RCJ
                                                                          WP_24693_2024
    
    
    framed earlier in the year 2012, subsequently in 2017, and thereafter in the
    
    year 2022. It was also held that while Section 86(4) of the Electricity Act
    
    mandated the APERC to be "guided" by the National Electricity Policy and the
    
    Tariff Policy, it did not imply that every such directive issued by the Ministry of
    
    Power was automatically binding on the APERC. The term "guided", it was
    
    urged, suggested an advisory role rather than a mandatory obligation to follow
    
    each such directive.
    
    
    45.   Apart from this, Mr. V. R. N. Prashanth, learned Counsel appearing for
    
    APERC, would submit that the clarification, dated 01.02.2019, and the
    
    clarification, dated 01.10.2019, cannot be considered to be a part of the
    
    National Tariff Policy, inasmuch as while the National Tariff Policy authorizes
    
    the Ministry of Power to provide the long term growth trajectory, it did not
    
    empower the Ministry of Power to cap the Renewal Power Purchase
    
    Obligations and further that the Electricity Regulatory Commissions have been
    
    given unbridled powers to fix the percentage of Renewal Power Purchase
    
    Obligations by taking into consideration various factors including the
    
    availability of renewable power sources with a view to strike harmonious
    
    balance, which safeguarded the interest of the end consumer also.
    
    
    46.   We are not convinced with the argument of learned counsel for the
    
    respondent that the Ministry of Power had no authority to cap the Renewable
    
    Power Purchase Obligation at all and that it could have only provide for a long
    
    term growth trajectory as in terms of National Tariff Policy and, in particular, in
                                                     17
                                                                                             HCJ & RCJ
                                                                                         WP_24693_2024
    
    
    terms of clause 6.4 of the said Tariff policy. It goes without saying that if the
    
    Ministry of Power could prescribe a long term growth trajectory of Renewable
    
    Power Purchase Obligations, it would also carry with it the power to regulate
    
    the said growth trajectory or even cap it at a particular level and for a specific
    
    period and in the case of specific group of Captive Power Plants.
    
    
    47.     At this stage, it may be apt to refer to some of the judgments, which
    
    have a direct bearing on the issues that arise in the present petition. In
    
    Reliance Infrastructure Ltd. v. State of Maharashtra1, the Apex Court was
    
    examining the validity of the tariff regulation, framed by the Maharashtra ERC,
    
    which was challenged as being opposed to the National Tariff Policy. In that
    
    context, the Apex Court, while examining the purport with the interpretation in
    
    the case of Reliance Infrastructure Ltd. of the phrase „shall be guided‟ as
    
    contained in Section 61 of the 2003 Act, held:
    
    
                       "29. Section 181 empowers the State Commissions to make
                       regulations consistent with the Act and the Rules to carry out
                       the provisions of the Act. Among the matters for which the
                       regulations may provide are "the terms and conditions for the
                       determination of tariff under Section 61". In specifying the
                       terms and conditions for the determination of tariff, the
                       appropriate Commission (as Section 61 provides) "shall be
                       guided" by the factors which are set out in clauses (a) to (i).
                       The expression "shall be guided" comprises of two
                       elements: the "shall" and, the "guidance". Clauses (a) to
                       (i) provide guidance to the Commission in specifying the
                       terms and conditions for the determination of tariff. The
                       expression "shall" indicates that the factors which are
                       specified in clauses (a) to (i) have to be borne in mind by the
                       appropriate Commission. As guiding factors, they provide
                       considerations which are material to the determination of
                       tariffs by the appropriate Commission.
    
    
    
    
    1
    (2019) 3 SCC 352
                                                     18
                                                                                             HCJ & RCJ
                                                                                         WP_24693_2024
    
                      30. The National Tariff Policy has multi-faceted objectives.
                      Significant among them is the need to ensure to consumers
                      the availability of electricity at reasonable and competitive
                      rates. The policy also seeks to ensure the financial
                      viability of the sector and underlines the need to attract
                      investments. A financially sustainable electricity sector is an
                      important facet of the overall regulatory framework. The
                      objectives of the policy emphasise the need to promote
                      transparency,       consistency      and   predictability    in
                      regulatory approaches across jurisdictions. The policy
                      emphasises the need to minimise perceptions of regulatory
                      risk. Finally, the policy recognises the need to promote
                      competition, efficiency in operations and improvements in the
                      quality of supply. In designing and formulating the
                      regulatory framework for tariffs, the delegate of the
                      legislature has to bring about a balance between the
                      competing goals which the Tariff Policy incorporates.
    
                      31. As part of the process, the delegate has to bear in mind
                      the interests of diverse stakeholders including consumers and
                      producers. ...The operating norms must be designed to
                      promote efficiency and to ensure that the gains which accrue
                      on account of efficient operations are shared with the
                      consumers of electricity. The operating norms will, therefore,
                      have due regard to the performance in the past as well as
                      capacities for future achievement. These must be
                      dovetailed with all relevant considerations, bearing on
                      the requirements of the policy.
    
                      32. The Tariff Policy provides guidance to the appropriate
                      Commission when it frames regulations. The power to
                      frame regulations is legislative in nature. It is conferred upon
                      the appropriate Commission. The Commission weighs
                      numerous factors. Its discretion in carrying out a complex
                      exercise cannot be constrained. The delegate of the
                      legislature is therefore under a mandate to bring about a fair
                      and equitable balance between competing considerations.
                      Standing at the forefront of those considerations is above all
                      the need to ensure efficiency and to protect the interests of
                      consumers. ..."
    
    
    
    
    48.     In Tata Power Co. Ltd. Transmission v. MERC & Ors.2, the Apex
    
    Court was considering, inter alia, the issue as to whether the National Tariff
    
    Policy(NTP) framed under Section 3 of the Act is binding on the State
    
    Regulatory Commissions. In that context, the Apex Court held that the
    
    2
    (2023) 11 SCC 1
                                                 19
                                                                                          HCJ & RCJ
                                                                                      WP_24693_2024
    
    
    interpretation in the case of Reliance Infrastructure Ltd. of the phrase „shall
    
    be guided‟ as contained in Section 61 would be equally applicable to the said
    
    phrase as contained in Section 86(4) of the Act of 2003. It was held:
    
    
                "98. Section 181 of the Act stipulates that the State
                Commission(s) may by notification, make regulations
                consistent with the Act and the rules framed by the State
                Government under Section 180 of the Act to carry out the
                provisions of the Act. ...
    
                99. At this juncture, it is necessary to refer to Section 86 of the
                Act. Section 86 lists the functions of the State Commission.
                Section 86(a) states that the State Commission shall discharge
                the function of determining the tariff for transmission. Section
                86(c) stipulates that the State Commissions shall facilitate
                intra-State transmission of electricity. Section 86(4) provides
                that in the discharge of its functions, which includes the
                determination of tariff for the transmission of electricity under
                clause (a), the State Commission shall be guided by the NEP,
                National Electricity Plan and NTP notified under Section 3 of
                the Act.
    
                114. This      Court      in Reliance    Infrastructure [Reliance
                Infrastructure Ltd. v. State of Maharashtra, (2019) 3 SCC 352]
                held that the principles prescribed in Section 61 are all material
                considerations that must guide the appropriate Commission
                while it prescribes the terms and conditions for determining the
                tariff. It was held that it was the responsibility of the
                Commission to ensure a delicate balance of the principles
                prescribed under Section 61. Thus, while NTP which is
                prescribed as one of the principles under Section 61 shall
                be a material consideration, it cannot be interpreted to
                mean that it is the "only" material consideration. This
                interpretation of "shall be guided" is equally applicable to
                the use of the phrase in Section 86(3).
    
                121. While the determination and regulation of tariff falls within
                the exclusive domain of the Regulatory Commission, it is
                crucial to note that Sections 61 and 86 stipulate that the
                Commission shall be guided by NTP while specifying terms
                and conditions for determining tariff. The State Commission
                while exercising its power to make regulations under Section
                181(2)(zd) on the terms and conditions for determination of
                tariff under Section 61 must conform to the provisions of the
                Act. Thus, while framing regulations under Section
                                                20
                                                                                        HCJ & RCJ
                                                                                    WP_24693_2024
    
                181(2)(zd), the Commission must be guided by the
                principles mentioned in Section 61, which includes the
                NEP and NTP.
    
                122. This Court in Reliance Infrastructure Ltd. v. State of
                Maharashtra, (2019) 3 SCC 352 has already held that NTP is
                one of the material considerations. NTP is one of the many
                guidelines that the Commission must necessarily consider
                while regulating tariff. The State and the Central Government
                only have an advisory role in the regulation of tariff. The
                Electricity Regulatory Commissions Act, 1998, which was
                consolidated with other statutes on electricity while enacting
                the Electricity Act, 2003, was enacted to distance the
                governments from the determination of tariffs. Further, the Act
                does not seek to centralise the power to regulate tariff with the
                Centre. One of the objectives of the Act was to provide the
                "States enough flexibility to develop their power sector in
                the manner they consider appropriate". Thus, since the
                appropriate Commissions possess full autonomy in the
                determination and regulation of tariff, and the States have
                been provided flexibility to develop their power systems
                for intra-State transmission of electricity, the NTP 2016
                shall be oneof the material considerations...."
    
    
    
    49.   While the issue in Tata Power Co. Ltd. Transmission (supra) was not
    
    centered around the Renewable Power Purchase Obligations, yet the Apex
    
    Court did examine the phrase „shall be guided‟ as existing in Section 86(4) of
    
    the Act of 2003. The legal position which thus stands crystallized by the
    
    Hon‟ble Supreme Court leaves this Court in no doubt that framing of
    
    regulations with regard to the Power Purchase Obligations falls exclusively
    
    within the domain of the Commission, which however must consider the
    
    guidance as provided by the National Tariff Policy in terms of Section 86(4) of
    
    the Act.
                                           21
                                                                          HCJ & RCJ
                                                                      WP_24693_2024
    
    
    50.    It can also be seen that the guidance which is provided by the Central
    
    Government envisaged under Section 86(4) is a material consideration but not
    
    the only material consideration as was held in Tata Power Co. Ltd.
    
    Transmission (supra) and further that the role of the State and the Central
    
    Government was only advisory in nature and that the Electricity Regulatory
    
    Commissions had full autonomy and power in framing regulations which
    
    included the Regulations prescribing Renewable Power Purchase Obligations.
    
    
    51.    Mr. P. Chidambaram, learned Senior Counsel would, however, urge
    
    that while the clarifications dated 01.02.2019 and 01.10.2019 may not have
    
    any binding force, yet the Commission ought to have considered the same as
    
    to whether the regulations of RPPO of 2017 or for that matter, regulations of
    
    RPPO of 2022 required an amendment.
    
    
    52.    It was also urged that according to the stand taken by the APERC, it
    
    was nowhere reflected that the clarifications dated 01.02.2019 and
    
    01.10.2019, were at all considered for purposes of deciding whether an
    
    appropriate amendment to the Regulations of 2017 or 2022 were warranted or
    
    not.
    
    
    53.    At the very outset, we can see that the Regulations impugned of 2017
    
    were framed in the year 2017 when the clarification dated 01.02.2019 and the
    
    subsequent clarification dated 01.10.2019, were not in existence. The
    
    petitioner also did not challenge the said regulations on the grounds which are
    
    now sought to be urged before us and the petition came to be filed as late as
                                            22
                                                                            HCJ & RCJ
                                                                        WP_24693_2024
    
    
    in October, 2024. By that time, even when the petitioner could have
    
    approached this Court for purposes of seeking appropriate relief from this
    
    Court in regard to the Regulations of 2017, yet it chose to remain silent.
    
    54.   We are of the opinion that as far as the challenge to the Regulations of
    
    2017 is concerned, the same is belated. The regulations of 2017 are no longer
    
    in force and have worked itself out and, therefore, challenge to the same
    
    cannot be permitted at this stage. However, insofar as the Regulations of
    
    2022 are concerned, APERC was in fact obliged to at least consider the
    
    clarification, dated 01.02.2019 as also the clarification, dated 01.10.2019,
    
    before framing the 2022 Regulations. We are quite in agreement with the
    
    argument of Mr. P. Chidambaram, learned Senior Counsel that even when the
    
    notification dated 01.02.2019, and the subsequent clarifications had no
    
    binding effect on the APERC, yet it could be considered to be a material
    
    factor, which ought to have been considered, among others, before framing
    
    the Regulations of 2022.
    
    55.   Be that as it may, we direct the State Electricity Regulatory Commission
    
    to consider the clarification dated 01.10.2019, and to decide whether any
    
    amendment was necessary in the light of the said clarification. If the guidance
    
    given by the aforementioned clarification is accepted, the necessary
    
    amendment would be incorporated by the Commission in the Regulations of
    
    2022 and appropriate relief extended to the petitioner. Till such time as the
    
    matter is considered by the APERC in regard to the Regulations of 2022, no
    
    coercive action be taken for recovery of any amount, which would be beyond
                                             23
                                                                           HCJ & RCJ
                                                                       WP_24693_2024
    
    
    the obligation of the petitioner as was fixed by clarification dated 01.10.2019,
    
    for the period the said clarification remained in force.
    
    56.   However, it is made clear that in the event the APERC decides not to
    
    amend the regulations for any good reason, the petitioner would be under an
    
    obligation to show strict compliance to Regulations of 2022. We further hold
    
    that the petitioner would be under an obligation to satisfy the demand raised
    
    by the Commission in regard to the period covered under the 2017
    
    Regulations.
    
    
    57.   This Writ Petition is disposed of accordingly. No costs.
    
    
          Consequently, connected miscellaneous applications, if any, shall stand
    
    closed.
    
    
    
    
                                                      DHIRAJ SINGH THAKUR, CJ.
    
    
    
                                                          RAVI CHEEMALAPATI, J.
    

    SSN/AKN/KBS
    97
    24
    HCJ & RCJ
    WP_24693_2024

    HON’BLE MR.JUSTICE DHIRAJ SINGH THAKUR, CHIEF JUSTICE
    &
    HON’BLE MR. JUSTICERAVI CHEEMALAPATI

    SPONSORED

    Writ Petition No: 24693 of 2024

    DATE : 22.04.2026

    SSN/AKN/KBS



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here