Registrar General, vs . State Of Meghalaya & Ors on 29 April, 2026

    0
    19
    ADVERTISEMENT

    Meghalaya High Court

    Registrar General, vs . State Of Meghalaya & Ors on 29 April, 2026

    Author: W. Diengdoh

    Bench: W. Diengdoh

    Serial No. 01
    Supplementary List
    
                         HIGH COURT OF MEGHALAYA
                               AT SHILLONG
    
     PIL No.6/2026
                                             Date of order: 29.04.2026
    
     Registrar General,         Vs.       State of Meghalaya & ors
     High Court of Meghalaya
     Coram:
           Hon'ble Mrs. Justice Revati Mohite Dere, Chief Justice
           Hon'ble Mr. Justice W. Diengdoh, Judge
    
     For the Petitioner     :   Mr. Philemon Nongbri, Amicus Curiae
    
     For the Respondents :      Mr. A. Kumar, Advocate General with

    Ms. R. Colney, GA
    Dr. N. Mozika, DSGI with
    Ms. K. Gurung, Adv

    On 22nd April, 2026, suo motu cognizance was taken of the

    SPONSORED

    incident which took place on 20th April, 2026, in which two

    persons lost their lives after being trapped inside the Mahindra

    Bolero Camper on the Shillong-Dawki Road. The incident was a

    result of massive boulders crashing on the vehicle, following a

    landslide at Mawlieh. In the said order, we had noted that two

    incidents had taken place on the same very stretch, one in 2023

    and the other in 2025, leading to loss of lives. By the said order,

    we had directed Mr. Kumar, learned Advocate General and Dr.

    Mozika, learned DSGI to submit a status report on the next date.

    Page 1 of 10
    We had also directed a senior responsible officer of NHIDCL to

    remain present on the next date i.e., today. Pursuant thereto, an

    officer of NHIDCL is present today. In order to assist us, we had

    also appointed Mr. Philemon Nongbri, as Amicus Curiae.

    2. Pursuant to the aforesaid order, Dr. Mozika, learned DSGI

    appearing for the respondent-NHIDCL has submitted a report of

    the said Corporation dated 28th April, 2026. The said report is

    taken on record. From the said report, it appears that initially the

    contract for package-II was awarded to M/s ARSS Infrastructure

    Projects Ltd., at a contract value of ₹210 crores on 24th November,

    2020, on Engineering Procurement and Construction (EPC) mode.

    The commencement date of the project was 26th December, 2020

    and the scheduled date of completion was 26th December, 2022

    (two years construction period). It further appears that the

    contract with M/s ARSS Infrastructure Projects Ltd. was

    terminated on 25th May, 2023 due to several reasons, mainly

    being slow progress and abandonment of the site by the

    contractor. It further appears that in view of the same, the

    balance work was awarded to M/s YFC Projects Private Limited in

    Page 2 of 10
    JV with M/s ACE Construction on 16th October, 2023 at a

    contract value of ₹200.69 crores on EPC mode. The

    commencement date of the project was 9th February, 2024 and

    the scheduled date of completion is 7th August, 2026 (2.5 years

    construction period). Further in the report, the topography of the

    area is mentioned and steps that are intended to be taken for

    permanent remedial measures are also mentioned.

    3. Mr. Kumar, learned Advocate General has also tendered the

    status report on behalf of the respondent-State dated 27th April,

    2026. The said report is also taken on record. It is further

    mentioned in paragraph 6 of the said status report that the State

    government through its concerned departments is taking

    immediate steps to address the safety concerns highlighted in the

    PIL and to prevent recurrence of such tragic incidents. The steps

    are:

    (a) strict enforcement of the road closure order dated 21st April,

    2026, with deployment of personnel at barricades erected at both

    ends of the affected stretch from Laitlyngkot to Mawlieh;

    Page 3 of 10

    (b) thorough spot inspection and ground safety assessment has

    been directed by the Sub-Divisional Officer, Pynursla to be

    conducted by competent authorities, including representatives of

    PWD (Roads), NHIDCL and its contractor to assess the current

    condition of the stretch and identify areas requiring immediate

    stabilization;

    (c) NHIDCL has been directed to take necessary and immediate

    measures in coordination with the contractor and the State

    departments concerned to ensure proper stabilization, storage

    and disposal of loose rocks resulting from blasting operations, so

    as to mitigate the risk of rockslides and landslides along the said

    corridor;

    (d) information pertaining to the incident and the road closure

    will be widely disseminated to the general public through

    appropriate channels and commuters will be advised to use

    alternative routes wherever available; and

    (e) that the State government has directed a detailed inquiry into

    the causes of the incident and will take appropriate action in

    accordance with law against all those found responsible for lapses

    in maintenance of safety standards.

    Page 4 of 10

    4. During the course of hearing, Mr. Kumar, learned Advocate

    General has submitted that the Government of Meghalaya has

    taken a decision to award ex-gratia payment of ₹4 lakhs to the

    next of kin of the victim whose lives were lost due to landslide,

    under the Pynursla C&RD Block. The said decision evidencing the

    same is taken on record. He states that the ex-gratia payment will

    be made at the earliest, once the next of kin are identified.

    5. Mr. Nongbri, learned Amicus submits that the NHIDCL is

    bound to follow the guidelines issued by the Indian Roads

    Congress (IRC). He tendered the Hill Road Manual, the Guidelines

    on Safety in Road Construction Zones and the Judgment of the

    Apex Court in S. Rajaseekaran v. Union of India & ors

    reported in (2026) 2 SCC 207. He submits that as per the IRC

    manual, the authorities are bound to follow the guidelines

    stipulated therein i.e., with respect to slope stability, erosion

    control and landslide correction; safety on hill roads; traffic

    management and rock blasting. He further submits that members

    of the IRC be constituted to submit a report to this Court with

    Page 5 of 10
    respect to the shortfalls in the construction and non-compliance,

    if any, of the guidelines.

    6. Dr. Mozika, learned DSGI, at this stage, states that hill

    roads expert or empanelled experts in this field will be appointed

    at the earliest, in order to enable them to conduct safety

    assessment of the area, so that prompt and immediate steps can

    be taken to ensure that no further incident takes place.

    7. Infact, in the status report, Dr. Mozika has annexed the

    minutes of the meeting held on 11th April, 2026, just a few days

    prior to the incident. It is noted that, based on various site

    inspections carried out in Mawlieh village and a letter dated 6th

    April, 2026 received from the ADC, Pynursla Civil Sub-Division, it

    was observed that the existing protection wall from chainage

    35+180 to 35+500 (RHS) is inadequate and the area is currently

    exposed to high risk due to vulnerable terrain conditions. Further

    it is noted, that continuous landslides indicate that the existing

    situation poses a potential threat to the house of residents at the

    crest and in the vicinity of the hill cutting as well as impacts the

    safety of the general public at the said location. Accordingly, the

    Page 6 of 10
    EPC contractor was directed to remove the fractured rock to

    prevent further falling of boulders onto the existing road and to

    immediately undertake benching work. Subsequently, the slope

    was to be covered with 20-micron plastic sheet to prevent water

    percolation into the hill slope. Infact, paragraph 2 of the said

    letter reflects the shortfalls of the contractor and measures

    required to be taken by the EPC contractor.

    8. Paragraph 3 on page 22 of the said report also shows that

    the EPC contractor had informed that protection works are

    required at certain locations and accordingly, the Authority

    Engineer (AE) was directed to assess such locations based on site

    conditions. Thereafter, the AE was to instruct the EPC contractor

    to submit the COS proposal, if required. It further appears from

    the letter that the EPC contractor had submitted the pending

    designs and drawings of the foundation and structure of A1

    (minor bridge at Ch.60+445) to the AE for necessary approval and

    accordingly, the AE was directed to process and accord approval

    of the same. Further, the EPC contractor was directed to submit

    the pending designs and drawings for the minor bridge at

    Page 7 of 10
    Ch.60+900 by 20th April, 2026 without fail for necessary approval

    by the AE. In paragraph 3, it was also noted that the progress of

    structural work was significantly slow and, in this regard, the

    EPC contractor was directed to increase requisite machinery and

    manpower and to ensure adequate construction material

    available at the site to expedite the structural works. Further, it is

    noted in paragraph 3 that the condition of the existing road was

    found to be in very poor condition and in this regard, the EPC

    contractor was directed to immediately undertake maintenance of

    the existing road to keep it in a traffic-worthy condition and safe,

    for road commuters, failing which, the authority would undertake

    the maintenance at the contractor’s risk and cost, as per the

    contractual provisions.

    9. Thus, from the aforesaid, it appears that prima facie, there

    has been laxity on the part of the EPC contractor and other

    authorities that were supposed to overlook the said construction.

    In this view of the matter, we also deem it appropriate to direct

    the NHIDCL to pay compensation of ₹6 lakhs to the next of kin of

    each of the deceased within two weeks from today. The said

    Page 8 of 10
    amount to be transferred directly into the account of the next of

    kin and a receipt be submitted on the next date evidencing

    payment made to the next of kin of the deceased. Needless to

    state, that the NHIDCL to recover the said amount from the erring

    contractor and other authorities/officials responsible for the said

    incident after conducting a detailed inquiry.

    10. Dr. Mozika at this stage states that the report of the hill

    experts will also be placed before this Court on the next date.

    Needless to state, that the NHIDCL to abide by the guidelines

    published by the IRC i.e., on safety in road construction zones

    and hill road manual and any other guidelines as may be

    applicable to them. Needless to also state, that in the event

    learned Amicus intends to visit the area, all such facilities,

    including transportation, will be provided for his to-and-fro travel.

    11. Dr. Mozika to also place on record the basis on which

    contractors are selected while awarding such contract, and

    whether the contractor has the requisite expertise for

    construction of roads in hilly areas/region.

    Page 9 of 10

    12. Stand over to 18th May, 2026.

                                (W. Diengdoh)                       (Revati Mohite Dere)
                                    Judge                              Chief Justice
    
    
    
    
                      Meghalaya
                      29.04.2026
                      "Lam DR-PS"
    
    
    
    
    Signature Not Verified
                                                                                   Page 10 of 10
    Digitally signed by
    LAMPHRANG KHARCHANDY
    Date: 2026.05.05 10:35:25 IST
    



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here