Rattan Paul Padha vs Union Territory Of Jammu And Kashmir on 30 March, 2026

    0
    45
    ADVERTISEMENT

    Jammu & Kashmir High Court

    Rattan Paul Padha vs Union Territory Of Jammu And Kashmir on 30 March, 2026

          HIGH COURT OF JAMMU & KASHMIR AND LADAKH
                          AT JAMMU
                                              Case No.       WP(C) No. 1489/2021
    
                                                                    Reserved on: 10.03.2026
                                                                Pronounced on: 30.03.2026
                                                                   Uploaded on: 01.04.2026
                                                         Whether the operative part of
                                                        or full judgment is pronounced: Full
    
    
    Rattan Paul Padha                                         ..... Petitioner(s)/Appellant(s)
    S/o Sh. Balwant Raj
    R/o Dharamsal Kalakote, District Rajouri
    
    
                           Through :- Mr. Rajesh Bhushan, Advocate.
    
                      Vs
    
    1. Union Territory of Jammu and Kashmir                               .....Respondent(s)
       Through Principal Secretary, Housing
       and Urban Development Department,
       Civil Secretariat, Jammu.
    2. Director Urban Local Bodies, Near
       Jodhamal School, Lane No. 4 Adarsh
       Vihar, Deeli, Jammu.
    3. Executive Engineer, Local Bodies
       Division-I Gole Market, Gandhi Nagar,
       Jammu.
    
                           Through :- Mr. Suneel Malhotra, GA.
    
              CORAM:
              HON'BLE MR. JUSTICE WASIM SADIQ NARGAL, JUDGE
                                   JUDGMENT
    

    1. Through the medium of the instant petition, the petitioner has sought the

    following reliefs:-

    SPONSORED

    “Writ of Mandamus directing the respondents to release an
    amount of Rs. 50,96,950/- (Rupees Fifty Lakh Ninety Six
    Thousand Nine Hundred Fifty), which is an admitted liability
    for carrying out the work of construction of alternate road for

    WP(C) No. 1489/2021 Page 1 of 12
    decongestion of main bazaar traffic by way of construction of
    R-wall at RD 160 to 200 and RD 425-625 (Total aggregate
    length 260 Mtr.) Parapets 8 Nos 0.60 x 0.60 Mtr culverts for
    drainage and side drains including allied work at
    Sunderbani.”

    2. Respondent No. 2, vide Notice Inviting Tender (NIT) No. 11-LBJ-1 of

    2016-17 dated 02.11.2016, invited applications for carrying out the work

    namely construction of an alternate road for decongestion of main bazaar

    traffic by way of construction of R-wall at RD 160 to 200 and RD 425-

    625 (Total aggregate length 260 Mtr), parapets, 8 Nos 0.60 x 0.60 Mtr

    culverts for drainage and side drains including allied work at Sunderbani.

    The total value of the work was Rs. 64.44 Lacs.

    3. The petitioner, being eligible to apply for the said NIT, applied for the

    same. A copy of the certificate of registration of petitioner as an A-Class

    contractor issued in Form-II and renewed till date has been enclosed with

    the petition.

    4. It is the specific case of the petitioner that he has completed the work

    which was allocated to him vide allotment letter dated 07.12.2016 in

    conformity with the terms and conditions mentioned in the said

    communication and other conditions communicated to the petitioner from

    time to time.

    5. It is the specific case of the petitioner that he has incurred huge amount of

    Rs. 63,00,700 (Rupees Sixty-three lacs seven hundred) on completion of

    the aforesaid work allotted to him, which is evident from a bare perusal of

    communication dated 07.12.2016. The details of the expenditure incurred

    by the petitioner have also been enclosed along with the instant petition.

    WP(C) No. 1489/2021 Page 2 of 12

    6. It is worth mentioning that the work was started way back on 23.12.2016

    and was completed by the petitioner in terms of the conditions specified

    in the communication dated 07.12.2016 to the complete satisfaction of the

    respondent-authorities.

    7. The petitioner being the L-1 and having participated in the e-NIT, was granted

    allotment in his favour by virtue of allotment order dated 07.12.2016. Since the

    aforesaid amount, despite the admitted liability, was not released by the

    respondents, the petitioner made repeated requests to them. In response thereof,

    respondent No. 3, vide communication dated 17.07.2018, addressed to

    respondent No. 2, requesting him to release an amount of Rs. 62.83 lacs, so that

    the pending liability of the petitioner could be cleared. The petitioner, in order

    to fortify his claim, has placed the aforesaid communication on record.

    8. It has been vehemently argued by learned counsel for the petitioner that

    despite the amount being admitted, the respondents have not released the

    same in his favour till date and have only released a part payment to the

    tune of Rs. 13.27 lacs out of the admitted liability to the tune of Rs. 62.83

    lacs.

    9. It has also been argued that after completion of the work assigned to the

    petitioner, requisite bills were also submitted to the respondents for

    release of the balance amount to the tune of Rs. 50,96,898/-, which

    amount, despite the admitted liability is still pending with the

    respondents. The petitioner was also constrained to issue a legal notice

    dated 27.01.2021 in this regard, but despite receipt of the same, the

    needful has not been done even though the work had been completed in

    conformity with the allotment letter dated 07.12.2016.

    WP(C) No. 1489/2021 Page 3 of 12

    10. Learned counsel for the petitioner with a view to advance his case has

    drawn the attention of the Court to the communication dated 18.02.2020

    issued by the Executive Engineer, Urban Local Bodies, Division Jammu,

    a perusal whereof reveals that the work executed by the petitioner has

    been duly verified by the concerned Executive Engineer and that a

    completion certificate has also been issued in this regard. Thus, according

    to the learned counsel, there is no impediment which comes in way of the

    respondents to release the aforesaid amount in favour of the petitioner,

    particularly when part payment has already been released out of the work

    allotted to him.

    11. Per contra, the reply stands filed on behalf of the respondents. The

    respondents have taken a preliminary objection that the claim projected

    by the petitioner can only be adjudicated by a Civil Court after leaving

    evidence, and therefore the petitioner cannot maintain the instant petition

    and the same deserves to be dismissed.

    12. A specific stand has also been taken by the respondents that though the

    allotment order dated 07.12.2016 was issued in favour of the petitioner,

    the same was subject to the condition that the contractor/petitioner was

    required to execute an agreement with the official respondents and would

    remain personally responsible not to exceed the work beyond the allotted

    amount and also for any contravention of any specifications of the

    material used.

    13. The respondents have further taken a specific stand that although the

    work in question was taken up by the petitioner on the directions of the

    WP(C) No. 1489/2021 Page 4 of 12
    Deputy Commissioner, Rajouri, the same was undertaken without the

    approval of the Administrative Department.

    14. The respondents, while filing the reply affidavit, have also admitted that

    the claim raised by the petitioner pertains to the work executed on a

    revised DPR without approval of the competent authority and since there

    was a deviation from the original contract, payment cannot be released to

    the contractor if the contractor has not executed the work strictly in terms

    of the e-NIT and the allotment order, as per the applicable rules.

    15. It has also been pleaded that since the contractor was under a legal

    obligation to execute the work strictly as per the terms and conditions of

    the e-NIT and the allotment order, any deviation therefrom and excess

    payment, if any, would disentitle him from claiming the payment for the

    said work. Accordingly, a prayer has been made that the writ petition

    deserves dismissal. In addition, the Finance Department has already

    issued guidelines/modalities vide circular dated 26.04.2021 for strict

    adherence by all departments regarding release of past liabilities in

    respect of works and in case of any violation, action can be initiated

    against the concerned officers.

    16. Lastly, it has been submitted by learned counsel for the respondents that

    this Court lacks inherent jurisdiction to entertain the instant writ petition

    in view of the efficacious remedy available to the petitioner to file a

    recovery suit.

    Legal Analysis:

    17. Having heard learned counsel for the parties at length and upon perusal

    of the record, this Court finds that the liability of the respondents towards

    WP(C) No. 1489/2021 Page 5 of 12
    the petitioner to the extent of Rs. 50,96,950/- is not in dispute. Once

    liability is admitted and the State continues to enjoy the fruits of the work

    executed by the petitioner, it cannot be permitted to turn around and deny

    payment without any justifiable reason. Besides, the state cannot retain

    payment when part payment has already been done. The liability in the

    present case is in the nature of a recurring liability. The work has been

    executed, utilized and the benefits continue to accrue to the respondents.

    In such cases, the cause of action is a continuing one and every day of

    non-payment constitutes a fresh infraction of the petitioner’s rights. The

    State and its instrumentalities are expected to act fairly and reasonably,

    particularly, in matters relating to payment of legitimate dues of

    contractors, who have executed public works.

    18. Despite the petitioner having been duly allotted the contract as the L-1 bidder

    pursuant to the e-NIT, the respondents failed to release the outstanding

    amount. The record further reveals that the petitioner made repeated

    representations seeking disbursement of the pending dues. Significantly,

    these requests were not only persistent but were also acknowledged by the

    respondent authorities themselves. In this regard, Respondent No. 3, vide

    communication dated 17.07.2018 addressed to Respondent No. 2, requesting

    the release of an amount of Rs.62.83 lakhs for the purpose of clearing the

    petitioner’s pending liability. However, despite such acknowledgment at the

    departmental level, no consequential action was undertaken by the

    respondents to discharge the admitted liability. The inaction on part of the

    respondents to release the outstanding liability in light of the admitted stand,

    therefore, reflects arbitrariness and administrative apathy on part of the

    WP(C) No. 1489/2021 Page 6 of 12
    respondents. The relevant aforesaid communication for reference is

    reproduced hereunder:

    “The above noted work was allotted by the then Director
    Urban Local Bodies, Jammu vide allotment No.
    DULBJ/2016/10399-10403 dated: 7.12.2016 under UIDSSMT.
    The contractor has now submitted claim as 2nd C.C for an
    amount of Rs. 62.83 lacs. You are as such requested to release
    an amount of Rs. 62.83 lacs so that the pending liability of the
    contractor can be cleared.”

    19. This Court in the similar facts and circumstances has already dealt with a

    similar issue in case titled, “M/s Saint Soldier Engineer and Contractor

    Pvt. Ltd. Vs. U.T. of J&K and Others“, WP(C) No. 2472/2022, decided

    on 26.09.2025, wherein it has been held that once, the liability of the

    Government towards a contractor stands admitted, the respondents cannot

    indefinitely withhold the payment on the ground of administrative or

    procedural constraints and the admitted dues are required to be released

    within a reasonable time. The ratio laid down in the aforesaid judgment

    squarely applies to the facts of the present case. It was held as under:

    “17. What emerges from the record is that the liability is
    admitted by the respondents themselves. Once liability is
    admitted, the only question that remains is with respect
    to delay in release of payment. Such delay, in the
    opinion of this Court, requires to be enquired into so
    that responsibility can be fixed upon the officers
    concerned. If contractors are compelled to knock at the
    doors of the Court day in and day out for release of
    legitimate dues, the fault lies not with the petitioner but
    with the respondents.

    20. It is well settled that execution of work gives rise to
    a corresponding obligation upon the State to honour its
    financial commitments. Any administrative approval or
    availability of funds is a matter to be ensured by the

    WP(C) No. 1489/2021 Page 7 of 12
    department prior to the allotment of work. After the
    execution of the contract, no “post facto” objection can
    be raised to deny or delay payment.”

    20. Therefore, this Court cannot remain a passive onlooker where admitted

    dues are unjustifiably withheld under the guise of administrative delays or

    financial constraints. On numerous occasions, this court has been

    compelled to intervene in matters where contractors, having fulfilled their

    contractual obligations are denied timely release of their dues by

    government departments. The State and its instrumentalities, despite

    enjoying the benefit of completed works, unjustifiably withhold payment

    for years together, thereby compelling the contractors to litigate. Such

    unnecessary litigation clogs the docket of constitutional courts, drains

    public resources and erodes the confidence of citizens in the fairness of

    State action. This systemic malaise demands judicial correction and

    policy direction.

    21. Article 14 of the Constitution of India guarantees equality before the law

    and equal protection of the laws. Over time, its jurisprudence has evolved

    well beyond the notion of mere formal equality to embody a substantive

    guarantee against arbitrariness. It is now firmly settled that every State

    action, whether legislative, executive or arising out of contractual

    dealings must conform to the standards of fairness, reasonableness and

    non-arbitrariness.

    22. The Government, while entering into contracts or dealing with contractors

    does not divest itself of its constitutional obligations. Unlike a private

    party, the State is expected to act as a model litigant, adhering to

    WP(C) No. 1489/2021 Page 8 of 12
    standards of fairness and reasonableness. Once the liability stands

    admitted, particularly where the work has been duly executed, measured

    and certified, any unjustified withholding of payment constitutes arbitrary

    State action and is clearly violative of Article 14 of the Constitution.

    23. This Court is of the considered view that such conduct on part of the

    Government is wholly arbitrary and unfair. The State, as a model litigant

    is expected to act fairly and reasonably. Where the delay in releasing

    payments is attributable to the State and there is no legal impediment or

    contractual dispute, the Government must explain the cause of such delay.

    Each day’s delay in the release of payment must be justified. In the

    absence of any cogent explanation, the Government would be liable to

    compensate the petitioner by way of interest for the period of delay.

    Additionally, it may also be held accountable for the financial hardship

    and mental distress occasioned to the petitioner as a result of such

    unjustified conduct. The doctrine of fairness does not countenance a

    situation where the State continues to enjoy the benefits of the executed

    work while simultaneously denying the contractor his legitimate dues.

    The State, therefore, cannot have a ‘win-win’ situation.

    24. The legal position regarding the payment of dues for contractual work

    executed is well-settled by the Hon’ble Supreme Court in several

    authoritative pronouncements. These judgments collectively underscore

    the imperative that “contractual payments must not be unduly delayed or

    withheld by the State without valid reasons.”

    WP(C) No. 1489/2021 Page 9 of 12

    25. As held by the Hon’ble Supreme Court in Ramakrishna Construction

    Co. v. Union of India, (2010) 3 SCC 579, it is a settled proposition that

    once work has been executed and the liability is admitted, the State

    cannot arbitrarily withhold payment.

    26. Similarly, in Surya Constructions v. State of U.P., (1986) 3 SCC 247,

    the Hon’ble Supreme Court observed that “courts can exercise writ

    jurisdiction under Article 226 of the Constitution in cases where admitted

    contractual dues are withheld without justification.”

    27. The Hon’ble Supreme Court of India has consistently held that the State,

    notwithstanding its sovereign character, is equally bound by its

    contractual obligations. It cannot claim immunity where its actions are

    arbitrary, unfair, or mala fide in the discharge of such obligations. In such

    circumstances, the State is amenable to judicial scrutiny and can be held

    accountable through appropriate intervention by the courts. In particular,

    the writ jurisdiction under Article 226 of the Constitution plays a crucial

    role in enforcing these obligations, especially in cases where the conduct

    of the State discloses manifest arbitrariness or an unjustified withholding

    of legitimate dues.

    28. The objection raised by the respondents that the petitioner ought to have

    first approached the civil court for redressal of his grievances is also

    without merit. The jurisdiction of a civil court is ordinarily invoked where

    there exists a disputed question of fact regarding the rights and liabilities

    of the parties arising out of a contract. In the present case, however, the

    respondents themselves have acknowledged the execution of the work as

    WP(C) No. 1489/2021 Page 10 of 12
    well as the liability arising therefrom and the amount payable to the

    petitioner is not shown to be the subject matter of any genuine dispute. In

    such circumstances, relegating the petitioner to a civil suit would serve no

    useful purpose, as the petitioner would merely be compelled to institute

    prolonged litigation for recovery of an amount which the respondents

    themselves do not dispute. Where the liability of the State stands admitted

    and the grievance of the petitioner pertains only to the withholding of

    payment, the matter assumes the character of arbitrary State action,

    thereby justifying the invocation of the writ jurisdiction of this Court

    rather than relegating the petitioner to the ordinary remedy of a civil suit.

    29. In view of the aforesaid facts and circumstances, the present petition is

    allowed and the respondents are directed to consider the case of the

    petitioner for the release of the balance admitted amount of Rs.

    50,96,950/- (Rupees Fifty Lakh Ninety Six Thousand Nine Hundred Fifty

    only) for the work executed, namely, construction of an alternate road for

    decongestion of main bazaar traffic by way of construction of R-wall at

    RD 160 to 200 and RD 425-625 (aggregate length 260 meters), parapets

    (08 Nos.), 0.60 × 0.60 meter culverts for drainage and side drains

    including allied works at Sunderbani, in case, if there is no legal

    impediment.

    30. The aforesaid exercise shall be carried out within a period of six weeks

    from the date a certified copy of this order is made available to the

    respondent No.3.

    WP(C) No. 1489/2021 Page 11 of 12

    31. It is made clear that in case, the amount is not released within the

    stipulated period, the petitioner shall be entitled to interest at the rate of

    6% per annum from the date the amount became due till its realization.

    32. Thus, in light of what has been discussed hereinabove coupled with

    settled legal position, the writ petition preferred by the petitioner is

    disposed of in the manner indicated above alongwith all connected

    applications.

    (WASIM SADIQ NARGAL)
    JUDGE

    JAMMU
    30.03.2026
    Mihul
    Whether the order is speaking : Yes/No
    Whether the order is reportable: Yes/No

    WP(C) No. 1489/2021 Page 12 of 12



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here