Rajendra Kumar Ameria & Anr vs Union Of India & Ors on 27 July, 2026

    0
    7
    ADVERTISEMENT

    Calcutta High Court (Appellete Side)

    Rajendra Kumar Ameria & Anr vs Union Of India & Ors on 27 July, 2026

    S/L 3
    27.07.2026
    Court. No. 25
    Suvayan
                                    WPA 16764 of 2026
    
                               Rajendra Kumar Ameria & Anr.
                                            Vs.
                                   Union of India & Ors.
    
                    Mr. Jishnu Saha, Sr. Adv.
                    Mr. Ishan Saha
                    Ms. Ayushi Mishra
                    Mr. Satyam Bhimsarin
                                                            ...for the petitioners.
    
                    Mr. Sanajit Kr. Ghosh
                    Ms. Mary Datta
                    Mr. Siddharta Gupta
                                                         ...for the Union of India.
    
    
                    1.   The petitioners have filed the present writ application
    
                         challenging the impugned notice dated July 3, 2026
    
                         wherein the railway authorities have claimed an amount
    
                         of Rs. 1,40,57,835.32 from the petitioners being the
    
                         maintenance and inspection as well as OHE maintenance
    
                         charges from 2017-2018 to 2022-2025.
    
                    2. Mr. Saha, learned Senior Advocate appearing for the
    
                         petitioners submits    that   in the said   notice the
    
                         respondents have threatened the petitioners that if the

    petitioners will not pay the aforementioned amount, the

    respondent authorities adjust the amount from the

    SPONSORED

    existing pending dues of the petitioners against the

    Eastern Railway.

    3. Learned counsel for the petitioners submits that there

    are two agreements entered between the parties, one is

    with regard to the private siding agreement No. 567

    dated February 6, 2018 and another is with regard to the

    manufacture and supply of wagons. He submits that
    2

    under the siding agreement there is no provision or

    clause that the railway authorities can adjust the pending

    amount of the petitioners from the existing pending dues

    of the petitioners. Learned counsel for the petitioners

    further submits that though in the agreement there is a

    clause of arbitration but the claim raised by the railway

    authorities are beyond the purview of the agreement. He

    submits that siding agreement executed on October 25,

    2019 and the claim made by the respondents are from

    2017-2018 onwards. Thus the arbitration clause will not

    apply with regard to the said claim.

    4. Learned counsel for the petitioners further submits that

    by a letter dated January 30, 2026 the railway

    authorities have informed that OHE maintenance cost in

    respect of the petitioners for siding, Baruipur is not

    applicable and it is to be exempted but the respondent

    authorities in the impugned notice have claimed the

    OHE maintenance charges.

    5. Learned counsel for the petitioners has relied upon the

    judgment in the case of Bharti Airtel Limited & Anr.

    vs. Vijaykumar V. Iyer & Ors. reported in 2024

    SCC OnLine SC 4 and submits that for set off in law,

    the obligations existing between the two parties must be

    debts which are for liquidated sums or money demands

    which can be ascertained with authority.

    6. Learned counsel for the petitioners further relied upon

    the judgment in the case of Gangotri Enterprises

    Limited vs. Union of India & Ors. reported in

    (2016) 11 SCC 720 and submits that a person who
    3

    commits a breach of the contract incurs any pecuniary

    liability, nor would it be true to say that the other party

    to the contract who complaints for the breach has any

    amount due to him from the other party the only right

    which he is the right to go to the Court of law and recover

    damages.

    7. He further relied upon the judgment in the case of M/s

    H. M. Kamaluddin Ansari & Co. vs. Union of

    India & Ors. reported in (1983) 4 SCC 417 and

    submits that the question whether any amounts were

    payable by the petitioner to the respondents under other

    contracts was not the subject matter of the arbitration

    proceeding.

    8. Per contra learned counsel appearing for the railway

    authorities raised the preliminary objection with regard

    to the maintainability of the present writ application on

    the ground that the siding agreement dated September

    25, 2019 contains the arbitration clause and the

    petitioners by a notice dated July 11, 2026 has admitted

    that dispute between the parties is to decide under the

    arbitration but instead of initiating the arbitration

    proceeding, the petitioners have filed the present writ

    application.

    9. Learned counsel for the respondents further submits that

    time and again the respondents have issued the demand

    notice with regard to the claim of the respondents but the

    petitioners have not paid the said amount and as such

    finding no other alternative, the respondent authorities

    have issued notice dated July 3, 2026 directing the
    4

    petitioners to pay the amount of Rs. 1,40,57,835.32

    failing which the pending dues will be adjusted from the

    pending bill of the petitioners. He has relied upon the

    clarification dated December 19, 2025 wherein the

    railway authorities have clarified regarding applicability

    of the OHE maintenance cost/charges for siding

    commission and submits that the query raised by the

    zonal railways have been clarified by the concerned

    authority wherein it is categorically mentioned that the

    siding/terminal commission prior to FMC 11 of 2016 are

    not supposed to pay the OHE maintenance charges as

    there are continued to be the responsibility of railways

    siding but subsequently it was further clarified that the

    revised guidelines for OHE maintenance charges (over

    siding commissioned under FMC 11 of 2016) are

    applicable with effect from June 23, 2020 that is from

    the date of issue of amendment letter. Prior to this date,

    sidings/terminals were governed as per their original

    agreement. He further submits that the authorities have

    further clarified that OHE maintenance is to be taken up

    by the railway and the costs thereof to be raised by

    railway as OHE maintenance charges as per guidelines

    mentioned in the Board’s letter dated March 6, 2024.

    10. Learned counsel for the respondents further submits that

    in Clause 8 of the siding agreement provides for

    maintenance and the other charges and as such the

    respondent authorities have raised the bill with regard to

    the maintenance and the inspection as well as the OHE

    maintenance charges in accordance with the agreement.
    5

    11. Learned counsel for the respondent further submits that

    in terms of the clarification dated December 19, 2025 the

    respondents can claim the OHE maintenance from June

    23, 2020 instead of October 25, 2022. He submits that

    the claim made by the respondents in the impugned

    notice dated July 3, 2026 the OHE maintenance charge

    is to be claimed only from June 23, 2020 not from

    October 25, 2022.

    12. Learned counsel for the respondent has also relied upon

    the judgment in the case of Kamaluddin Ansari &

    Co. vs. Union of India reported in 1984 AIR 29 and

    submits that the Hon’ble Supreme Court has

    categorically held that injunction order restraining the

    respondents from withholding the amount due under

    other pending bills to the contractor virtually amounts to

    a direction to pay the amount to the contractor. Such an

    order was clearly beyond the purview of Clause (b) of

    Section 41 of the Arbitration Act.

    13. By referring the said judgment, learned counsel for the

    respondents submits that if this Court passed any order

    restraining the respondents for realizing the amount

    claimed by the respondents, these amounts to allow the

    petitioners to pay the remaining pending bill of the

    petitioners.

    14. The petitioners have also relied upon the unreported

    judgment passed by the co-ordinate Bench of this Court

    in the case of Titagarh Wagons Limited & Anr. vs.

    Union of India, represented by the Principal

    Secretary, Ministry of Railways & Ors. in WPA
    6

    18852 of 2021 dated April 5, 2022 wherein the co-

    ordinate Bench of this Court held that the matter falls in

    the realm of private contract between the railways and

    the petitioners and the demand raised by the railways

    cannot be gone into or decided by the Court since it

    involves disputed questions of fact requiring a trial by

    evidence and the Hon’ble Judge has dismissed the writ

    application.

    15. Heard the learned counsel for the respective parties

    perused the materials on record.

    16. The respondents have claimed an amount of Rs.

    1,40,57,835.32 by the impugned notice dated July 3,

    2026 being the maintenance and the inspection as well

    as OHE maintenance charges. The maintenance and the

    inspection have been claimed from year 2017-2018,

    2021-2022, 2022-2023 and OHE maintenance charges

    have claimed from October 25, 2022 to October 24, 2025

    and July 24, 2022 to July 24, 2026.

    17. At the time of hearing, learned counsel for the

    respondents submits that the OHE maintenance charges

    is to be paid by the petitioners from June 23, 2020

    instead of October 25, 2022. The issue raised in the

    present writ application whether the claim made by the

    respondents are coming under the purview of the

    arbitration clause.

    18. Clause 34 of the siding agreement dated September 25,

    2019 provides for arbitration which reads as follows:

    “34. Arbitration
    7

    (A) In the event of any dispute or difference of
    opinion between the parties as to the
    respective rights and obligations of the
    parties hereunder or as to the true intent and
    meaning of these presents or any or
    conditions thereof arising such dispute or
    difference of opinion (except the matters
    regarding which the decision has been
    specifically provided for in this agreement
    shall be referred to an arbitral tribunal
    consisting of at least 3 members to be
    appointed by the General Manager, Eastern
    Railway for the time being, and his decision
    shall be final conclusive and binding on the
    parties. For the purpose of this Agreement,
    the General will mean the head of the Eastern
    Railway Administration.”

    19. As per the said Clause any dispute or differences of

    opinion between the parties as to the respective rights

    and obligations of the parties hereunder or as to the true

    intent and meaning of these presents or any or

    conditions thereof arising such dispute or difference of

    the opinion the parties have to approach the arbitration.

    20. In the present case, the respondents have claimed the

    maintenance and the inspection charges from 2017 to

    2023 and the OHE maintenance charges from October

    25, 2022, now the respondents claiming that the claim

    should be from June 23, 2020 till July 24, 2025. The

    siding agreement was entered on September 25, 2019 but

    as per Clause 37 of the agreement, the agreement shall be

    deemed to have come into force on and from November

    7, 2003.

    8

    21. Learned counsel for the petitioners submits that the

    claim raised by the respondent authorities is not coming

    under the purview of the arbitration and the arbitrator

    cannot decide the said claim. Thus this Court has to

    decide whether the claim raised by the respondent

    authorities is legal or sustainable.

    22. This Court finds that though the siding agreement was

    entered on September 25, 2019 but the same was given

    effect on and from November 7, 2023 and the

    maintenance and other charges are also provided in the

    said agreement. But the respondent authorities by a

    letter dated January 30, 2026 have informed the

    petitioners that the OHE maintenance is not applicable

    and is exempted. This Court also finds that the

    petitioners by a communication dated July 11, 2026

    raised an objection with regard to the demand of

    maintenance and inspection charges of OHE

    maintenance charges.

    23. In the said letter the respondents have mentioned as

    follows:

    “In view of the aforesaid, we demand justice from
    your good self and request your office not to take
    any coercive steps or make any adjustments from
    our other bills pending resolution of the
    aforementioned disputes through mutual
    consultation or through the arbitration
    mechanism provided under Clause 34 of the
    Private Siding Agreement. We are pained to
    state that, in the event such deductions are
    effected despite our objection, we shall be
    constrained to treat the same as wrongful and
    9

    illegal recovery and shall pursue all available
    legal remedies and invoke the writ jurisdiction of
    the Hon’ble High Court at Calcutta to protect our
    interests and legal rights. We beseech your
    august office to intervene and request that a
    meeting be called urgently to resolve the issue as
    we have a long standing business relation with
    Indian Railways.”

    24. Subsequent to the said letter, the petitioners have issued

    the notice under Section 21 of the Arbitration and

    Conciliation Act. Once the petitioners have taken the

    plea with regard to the arbitration whether the claim

    made by the petitioners are coming under the purview of

    arbitration is to be decided by the arbitrator not by this

    Court.

    25. The Clause 34 of the agreement also prescribed with

    regard to the arbitration and the said agreement was also

    provided with regard to the maintenance charges.

    Whether OHE maintenance charges has been exempted

    or not is also the matter of evidence. The petitioners

    have to prove that the letter issued by the respondents

    with regard to exempting the OHE maintenance is in

    accordance with law or not. Accordingly, this Court did

    not find any merit in the matter.

    26. The petitioners instead of approaching the arbitration

    proceeding has filed the writ application thus this writ

    application is not maintainable.

    27. WPA 16764 of 2026 is dismissed.

    28. However, there shall be no order as to costs.
    10

    29. Urgent Xerox certified copy of this order, if applied for,

    be given to the parties upon compliance of all necessary

    formalities.

    (Krishna Rao, J.)



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here