Ntpc Ltd vs Ampl Resources Private Limited on 26 February, 2026

    0
    54
    ADVERTISEMENT

    Delhi High Court

    Ntpc Ltd vs Ampl Resources Private Limited on 26 February, 2026

    Author: Purushaindra Kumar Kaurav

    Bench: Purushaindra Kumar Kaurav

                        $~
                        *       IN THE HIGH COURT OF DELHI AT NEW DELHI
                                                          BEFORE
                              HON'BLE MR. JUSTICE PURUSHAINDRA KUMAR KAURAV
                        +       O.M.P. (COMM) 186/2025, I.A. 12141/2025&I.A. 12142/2025
    
                                NTPC LTD
                                THROUGH ITS AUTHORISED REPRESENTATIVE MR. SALIL
                                KUMAR PANDEY
                                REGD. OFFICE AT:
                                NTPC BHAWAN, CORE-7, SCOPE COMPLEX, 7
                                INSTITUTIONAL
                                AREA, LODHI ROAD, NEW DELHI - 110003 .....Petitioner
                                (Through: Mr. Adarsh Tripathi, Mr. Vikram Singh Baid and Mr.
                                Ajitesh Garg, Advs.)
    
                                                 versus
    
                                AMPL RESOURCES PRIVATE LIMITED
                                (ERSTWHILE AMBEY MINING PRIVATE
                                LIMITED)
                                THROUGH ITS DIRECTORS / AUTHORIZED
                                REPRESENTATIVE,
                                REGD. OFFICE AT: 8, AJC BOSE ROAD,
                                CIRCULAR COURT,
                                9TH FLOOR, UNIT-92, KOLKATA,
                                WEST BENGAL, 700017                            .....Respondent
                                (Through: Mr. Udayan Jain, Ms. Kajal Sharma, Mr. Ranjan
                                Mishra, Mr. Harsh Jaiswal, Ms. Amiti Gupta, Ms. Geetika Vyas, and
                                Mr. Sonal Jain, Advs.)
    
                        +       O.M.P. (COMM) 240/2025
                                AMPL RESOURCES PRIVATE LIMITED
                                THROUGH ITS AUTHORISED REPRESENTATIVE
                                CIRCULAR ROAD, 9TH FLOOR,
    
    Signature Not Verified                                                    Signature Not Verified
    Signed By:AMIT KUMAR                                                      Signed
    SHARMA
    Signing Date:10.03.2026                                                   By:PURUSHAINDRA
    19:43:06                                              Page 1 of 32        KUMAR KAURAV
                                  BLOCK-92, 8, AJC BOSE ROAD,
                                 KOLKATA-700017                                 .....Petitioner
                                 (Through: Mr. Udayan Jain, Ms. Kajal Sharma, Mr. Ranjan
                                 Mishra, Mr. Harsh Jaiswal, Ms. Amiti Gupta, Ms. Geetika Vyas, and
                                 Mr. Sonal Jain, Advs.)
    
                                                        versus
    
                                 NTPC LIMITED
                                 THROUGH ITS AUTHORISED SIGNATORY NTPC
                                 BHAWAN, CORE -7,
                                 SCOPE COMPLEX, INSTITUTIONAL AREA, LODHI
                                 ROAD, NEW DELHI - 110003                    .....Respondent
                                 (Through: Mr. Adarsh Tripathi, Mr. Vikram Singh Baid and Mr.
                                 Ajitesh Garg, Advs.)
    
    
                              ------------------------------------------------------------------------------------
                        %                                               Reserved on:           20.12.2025
                                                                        Pronounced on: 26.02.2026
                              -----------------------------------------------------------------------------------
                                                               JUDGMENT
    

    The present set of petitions has been filed both by the claimant as well
    as the respondent against the award dated 19.12.2024 (hereinafter referred
    to as the “impugned award”). The claimant, AMPL Resources Private
    Limited (hereinafter referred to as “petitioner”) is the petitioner in OMP
    (COMM) 240/2025 and the respondent, NTPC Limited (hereinafter referred
    to as the “respondent”), is the petitioner in OMP (COMM) 186/2025. The
    petitioner had instituted arbitration proceedings against the respondent
    seeking recovery of money allegedly due under Contract dated 17.12.2019
    (hereinafter referred to as “the Contract”). In the impugned award, the

    Signature Not Verified Signature Not Verified
    Signed By:AMIT KUMAR Signed
    SHARMA
    Signing Date:10.03.2026 By:PURUSHAINDRA
    19:43:06 Page 2 of 32 KUMAR KAURAV
    claim of the petitioner has been partly allowed and the petitioner seeks
    severance and setting aside of the part rejecting its claim and award of the
    full claim in its favour. The respondent seeks that the award be set aside in
    toto.

    SPONSORED

    Facts

    2. The petitioner was awarded the Contract for coal transportation from
    a designated mine to designated railway sidings for a period of one year with
    effect from 26.11.2019, which was extendable for a further period of six
    months. The terms of the Contract were contained in the General Conditions
    of Contract (hereinafter referred to as the “GCC”), Special Conditions of
    Contract (hereinafter referred to as the “SCC”), the Technical specifications
    and drawings, Schedule of Quantities, Contractor‟s Bid Proposal No. 50727,
    and the Purchase Order dated 18.11.2019 (hereinafter referred to as the
    “Purchase Order”), among other documents. Under the terms thereof, the
    respondent would provide monthly schedules to the petitioner, specifying
    the quantity of coal to be transported.

    3. After commencement of the work at the scheduled time, the
    respondent, vide letter dated 13.04.2020, citing lower coal requirements,
    directed the petitioner to suspend transportation till further notice. The
    petitioner, thereafter, on various dates, claimed dues under various heads.
    The respondent, in its letter dated 04.12.2020, refuted the claims, stating that
    the Contract stipulated payment only according to the quantity of coal which
    is transported, and therefore, the petitioner‟s claim for the whole contract
    was not acceptable. Disputes persisted with regard to the petitioner‟s claims,
    leading to the institution of arbitral proceedings.

    Signature Not Verified Signature Not Verified

    Signed By:AMIT KUMAR                                                           Signed
    SHARMA
    Signing Date:10.03.2026                                                        By:PURUSHAINDRA
    19:43:06                                              Page 3 of 32             KUMAR KAURAV
    

    4. In the arbitral proceedings, the petitioner sought recovery of its
    purported dues (principal amount) as per the table extracted below:

                        Sl. No.       Particulars                                      Amount (in Rs)
                              1.      Fixed       Cost   Claim      (Depreciation, 8,16,66,916.00
                                      Interest,     Insurance,     Tax,     Salary,
                                      Minimum            Guarantee,             Camp
                                      Establishment)
                              2.      Fixed Office Expenses                            3,32,90,985.00
                              3.      Retention Money Dues                             95,25,979.00
                              4.      Loss of Profit Claim                             11,75,71,640.00
                                                                                Total 24,20,55,520.00
    
    

    5. The claims for loss of profit and retention money dues were allowed,
    and the claims for fixed office expenses and fixed costs were rejected.

    Findings in the Impugned Award

    6. The following points for determination were framed by the sole
    arbitrator:

    1. Whether the Claimant is entitled to the outstanding principal amount
    in the sum of Rs. 24,20,55,520.00?

    2. Whether the claimant is entitled to interest on the outstanding
    principal @12% per annum up to 31.03.2023 in the sum of Rs.
    6,77,22,492.00?

    3. Whether the Claimant is entitled to pendente lite and future interest
    @12% p.a. on the allowed outstanding principal and interest amounts
    cumulatively?

    Signature Not Verified Signature Not Verified

    Signed By:AMIT KUMAR                                                                   Signed
    SHARMA
    Signing Date:10.03.2026                                                                By:PURUSHAINDRA
    19:43:06                                                     Page 4 of 32              KUMAR KAURAV
    

    4. Whether the Claimant is entitled to the legal expenses as per actuals?

    7. One of the questions framed by the sole-arbitrator for adjudicating the
    claim for the outstanding principal amount, which also has a bearing on the
    claim for interest on the principal amount, was whether the contract
    envisaged the transportation of a fixed quantity of coal.

    8. The sole-arbitrator has examined the relevant clauses and recitals in
    the Contract, more particularly, the Bill of Quantity forming a part of the
    Letter of Intent, the Bill of Quantity forming a part of the Purchase Order,
    and Clause 8 of the SCC. It is pertinent to note that the petitioner‟s case
    before the sole-arbitrator was that the Contract was for transportation of
    13,69,000 MT (Thirteen Lakh and Sixty-Nine Thousand Metric Tonne) of
    coal, with a permissible limit of deviation of (+/-) 30% (thirty per cent). The
    respondent‟s case, on the other hand, was that the contract envisaged
    transportation of coal according to the needs of the respondent, and did not
    guarantee any fixed quantity. Ultimately, in line with the petitioner‟s
    submissions and as contained in Clause 8.0 of the SCC, the sole-arbitrator
    held that the contract was for a fixed quantity of coal, with a permissible
    limit of deviation of (+/-) 30% (thirty per cent).

    9. Upon adjudication of various other questions, the sole-arbitrator,
    finally, concluded that the respondent has breached the contract.

    10. The claim for principal amount, under each of the four heads as per
    the table extracted above, was examined separately. At the outset, the sole-
    arbitrator rejected the contention of the respondent that the petitioner had not
    taken any steps to mitigate its losses, and, therefore, its claim for the entire
    principal amount could not be accepted, upon consideration of the evidence
    adduced.

    Signature Not Verified Signature Not Verified

    Signed By:AMIT KUMAR                                                            Signed
    SHARMA
    Signing Date:10.03.2026                                                         By:PURUSHAINDRA
    19:43:06                                                Page 5 of 32            KUMAR KAURAV
                         Claim for Fixed Costs
    

    11. The sole arbitrator noted the petitioner‟s submission that it had
    incurred costs towards the deployment of manpower and machinery for the
    performance of its contractual obligations and that the machinery were
    subject to wear and tear during the period of contract, all of which were to
    be recoverable from the respondent. She also considered the submission that
    the petitioner was entitled to recover the interest liability it incurred on the
    loans taken for purchase of the aforesaid machinery. Documentary evidence
    of the same, namely, depreciation certificate for the machinery duly certified
    by a chartered accountant, interest certificate/repayment schedule for the
    machinery, copy of the insurance acquired towards the same, and various
    invoices for vehicles, equipment, materials, fuel, manpower, etc., as well as
    a bank guarantee, were appreciated by the sole arbitrator before holding that
    the petitioner had incurred the said costs.

    12. The respondent‟s submission that the costs for arranging manpower
    and machinery stood included in the contract amount and no additional
    amount was payable to the petitioner was also noted, as also the submission
    that the claim for depreciation costs was expressly barred under the terms
    enumerated in the Purchase Order, and that it was the petitioner which was
    solely liable for procuring insurance policies for the machinery.

    13. The sole arbitrator proceeded to note that the law of damages required
    the party which was not in breach of a contract, to be placed, as far as
    possible, in the same position as it would have been if the contract had not
    been breached by the other party. She noted that if there had not been any
    breach by the respondent, the petitioner would have received the entire
    contract amount of Rs. 1,16,77,57,000.00 (Rupees One Billion One Hundred

    Signature Not Verified Signature Not Verified
    Signed By:AMIT KUMAR Signed
    SHARMA
    Signing Date:10.03.2026 By:PURUSHAINDRA
    19:43:06 Page 6 of 32 KUMAR KAURAV
    and Sixty-Seven Million Seven Hundred and Fifty Seven Thousand only).
    However, noting that the petitioner would have, anyhow, incurred the
    aforesaid fixed costs in its performance of the Contract, it held that the same
    were not additional costs and expenses incurred on account of breach by the
    respondent and therefore, the petitioner was held as not entitled to recover
    the same.

    Claim for Fixed Office Expenses

    14. The petitioner had sought to recover certain costs and expenses
    allegedly incurred by it during the contract period for running its offices.
    Upon noting that there was no pleading by the petitioner that it would not
    have incurred the same if the respondent had fulfilled its part of the
    Contract, the sole arbitrator held that for the same reasons, as assigned for
    rejecting the claim for fixed costs, the claim for fixed office expenses could
    not be accepted.

    Claim for Retention Money Dues

    15. The sole-arbitrator noted that as per Clause 4 of Point C of the
    Purchase Order, only ninety per cent of the Running Account Bill was paid
    to the petitioner for the works executed by it. The remaining ten per cent of
    the bill amount was to be paid as per quarterly reconciliation of the works
    executed.

    16. The parties made submissions on the aspect of „reconciliation of the
    works executed‟. The petitioner refuted the authenticity of the Statement of
    Final Deviation, which was prepared after assessment of the residual coal at
    the Katkamsandi siding, alleging that the same was prepared unilaterally,
    and was never supplied to the petitioner. The respondent contended that

    Signature Not Verified Signature Not Verified
    Signed By:AMIT KUMAR Signed
    SHARMA
    Signing Date:10.03.2026 By:PURUSHAINDRA
    19:43:06 Page 7 of 32 KUMAR KAURAV
    Statement of Final Deviation was prepared on the basis of assessment
    conducted in the presence of representatives of both parties and the same
    had not been objected to by the petitioner at the relevant time. Therefore, it
    was the respondent‟s case that the petitioner‟s challenge to the Statement of
    Final Deviation was only an afterthought.

    17. Upon noting the submissions of the parties, the sole-arbitrator held
    that the Statement of Final Deviation was irrelevant to the question at hand,
    after considering Clause 4 of Point C of the Purchase Order, as per the terms
    of which, the quarterly „re-conciliation‟ of the work executed required
    reconciliation of „the quantity of coal billed by the petitioner‟, „the quantity
    as received by the respondent in rakes‟, and „the quantity lying at the
    siding‟. However, considering that in the preparation of the Statement of
    Final Deviation, only the quantity of coal to be transported as per the Letter
    of Allotment with the finally executed quantity and amount are taken into
    account, therefore, according to the sole-arbitrator, the Statement of Final
    Deviation did not fulfill the conditions mandated in Clause 4 of Point C of
    the Purchase Order.

    18. Thereafter, the sole-arbitrator, considering that the respondent had not
    disputed the factum of its retention of an amount of Rs. 95,25,979.00
    (Rupees Ninety-Five Lakh Twenty-Five Thousand Nine Hundred and
    Seventy-Nine only) from the petitioner, held that the petitioner was entitled
    to the same.

    Claim for Loss of Profits

    19. Considering the earlier finding that the Contract was for a fixed
    quantity and the respondent had breached it by not assigning work to the

    Signature Not Verified Signature Not Verified
    Signed By:AMIT KUMAR Signed
    SHARMA
    Signing Date:10.03.2026 By:PURUSHAINDRA
    19:43:06 Page 8 of 32 KUMAR KAURAV
    petitioner, the sole-arbitrator allowed the petitioner‟s claim for loss of
    profits. The sole-arbitrator again reasoned that the well settled principle of
    the law of damages was that the non-breaching party should, as far as
    possible, be placed in the same position as if the contract has been
    performed by the breaching party, and held that the petitioner was entitled to
    fifteen per cent of the amount that the petitioner would have earned if the
    balance work had been performed. The balance work was calculated by
    subtracting the quantity of coal transported by the petitioner from the
    stipulated contractual quantity from the contractual fixed quantity of
    13,69,000 MT (Thirteen Lakh Sixty-Nine Thousand Metric Tonne). The
    profits were calculated at fifteen per cent on the basis of the „Earnings
    Before Interest, Taxes, Depreciation and Amortisation‟ and the „Profits
    Before Taxes‟ as submitted by the petitioner, as well as reports of auditors
    for the preceding financial years and a duly certified statement of long-term
    and short-term profits by the petitioner‟s chartered accountants.

    Claim for Interest

    20. The sole-arbitrator noted that it was not the respondent‟s case that the
    Contract did not allow for grant of interest, as also the fact that neither party
    led evidence with regard to the applicable rate of interest. Accordingly, it
    proceeded to award pre-litigation and pendente-lite interest on the awarded
    amount at the rate of twelve per cent per annum, which according to the
    arbitrator, was reasonable. Post award interest was also awarded at a rate
    which is „two per cent higher than the rate of interest prevalent at the time of
    the award‟, in accordance with Section 31(7)(b) of the Act.

    
                        Claim for Legal Expenses
    
    Signature Not Verified                                                          Signature Not Verified
    Signed By:AMIT KUMAR                                                            Signed
    SHARMA
    Signing Date:10.03.2026                                                         By:PURUSHAINDRA
    19:43:06                                              Page 9 of 32              KUMAR KAURAV
    

    21. On the reasoning that the petitioner has been awarded an amount of
    about fifty per cent of the claimed amount, the sole-arbitrator awarded the
    petitioner fifty per cent of the legal expenses claimed by it.

    Submissions

    22. Mr. Udayan Jain, learned counsel for the petitioner, submits that the
    award has been assailed on the following grounds:

    22.1. The award suffers from perversity insofar as the petitioner‟s
    claims for „fixed costs‟ and „fixed office expenses‟ were
    rejected despite a clear finding that the petitioner had incurred
    such costs. He submits that the sole-arbitrator had proceeded on
    a perverse understanding of principles of contractual business
    and on the presumption that the aforesaid fixed costs/fixed
    office expenses were to be borne by the petitioner even if the
    respondent had not breached the contract. According to him, it
    is a first principle of contractual business that such costs are to
    be recovered from the contractual amount. Therefore, the
    petitioner was entitled to recover the fixed costs from the
    amount that would be paid in consideration for the work that
    would have been done if the contract was not breached.
    22.2. The award is perverse insofar as the award of only fifty per cent
    of the claimed amount towards legal expenses is concerned, as
    the same is de hors any reasonable justification. He submits
    that the reasoning assigned for the same, being that since only
    fifty per cent of the claimed amount has been awarded, it would

    Signature Not Verified Signature Not Verified
    Signed By:AMIT KUMAR Signed
    SHARMA
    Signing Date:10.03.2026 By:PURUSHAINDRA
    19:43:06 Page 10 of 32 KUMAR KAURAV
    be fit to award fifty per cent of the claim towards legal
    expenses, is based on an erroneous analogy.

    23. He submits that the impugned portions of the award are separable
    from the rest, and prays that the award be modified to the extent of allowing
    the petitioner‟s claims for fixed costs, fixed office expenditure and legal
    expenses, in full.

    24. Mr. Adarsh Tripathi, learned counsel for the respondent opposes the
    aforesaid submissions and contends as follows:

    24.1. The rejection of the petitioner‟s claims for fixed costs and fixed
    office expenses is neither perverse nor patently illegal. The
    fixed costs are factored into the contractual amount and once
    compensation for loss of profits is awarded, a separate award
    for fixed costs would amount to double liability on the
    respondent, which is contrary to the principle underlying
    Section 73 of the Contract Act, 1862.

    24.2. The award of fifty per cent of the legal expenses claimed by the
    petitioner is justified, since, the determination of the amount to
    be awarded as costs is left to the discretion of the arbitrator
    under Section 31A(1) of the Act. Therefore, there can be no
    question of challenge to the same on the grounds of perversity
    or patent illegality under Section 34 of the Act.

    25. Mr. Adarsh Tripathi submits that the respondent‟s independent
    challenge to the award is based on the following grounds:

    25.1. The award is perverse insofar as the petitioner has been
    awarded loss of profits and interest calculated against the
    „balance work‟ taking the contractual quantity to be 13,69,000

    Signature Not Verified Signature Not Verified
    Signed By:AMIT KUMAR Signed
    SHARMA
    Signing Date:10.03.2026 By:PURUSHAINDRA
    19:43:06 Page 11 of 32 KUMAR KAURAV
    MT (Thirteen Lakh and Sixty-Nine Thousand Metric Tonne),
    despite expressly finding that the said quantity was subject to
    permissible deviation of (+/-) 30% (thirty per cent). According
    to him, therefore, the loss of profits, if any, was to be calculated
    against seventy per cent of 13,69,000 MT, since the Contract
    envisaged the same to be the lower permissible contractual
    quantity, even as per the findings in the award.

    25.2. The award is perverse and patently illegal insofar as the sole-

    arbitrator has awarded loss of profits in the teeth of the law laid
    down by the Supreme Court in the decisions inBatliboi
    Environmental Engineers Limited v Hindustan Petroleum
    Corp. Ltd.
    , 1All India Radio v. Unibros and Anr., 2and Unibros
    v. All India
    Radio,3and without any evidentiary basis. He
    contends that such damages could not have been awarded
    unless the petitioner proved that it had actually lost out on
    opportunities due to the breach of the Contract. He further
    points out that the petitioner had not produced any document
    showing any other work that it may have lost out on, on
    account of the breach. He submits that the principle laid down
    in
    the aforesaid cases has erroneously been interpreted in the
    award to apply only to cases involving delay in the completion
    of the contractual work, whereas it would be applicable even to
    cases involving breach during the original contractual period.

    
    
                        1
                          (2024) 2 SCC 375
                        2
                          2010 (115) DRJ 573
                        3
                          2023 SCC OnLine SC 1366
    
    Signature Not Verified                                                            Signature Not Verified
    Signed By:AMIT KUMAR                                                              Signed
    SHARMA
    Signing Date:10.03.2026                                                           By:PURUSHAINDRA
    19:43:06                                               Page 12 of 32              KUMAR KAURAV
    

    25.3. The award is perverse as the rate at which the damages for loss
    of profits have been awarded, i.e., fifteen per cent, has been
    arrived at without any evidence having been led on that aspect
    by the petitioner. He submits that the sole-arbitrator has also not
    independently ascertained the rate at which the damages had to
    be awarded, and has proceeded on the premise that the rate
    claimed by the petitioner seemed reasonable. He places reliance
    on the decisions of the Supreme Court in J.G. Engineers
    Private Limited v. Union of India
    and Another,4M/s A.T. Brij
    Paul Singh and Others v. State of Gujarat,5
    and Mohd.
    Salamatullah and Others v. Government of Andhra Pradesh.6

    25.4. The award is perverse insofar as the petitioner has been
    awarded interest on the awarded amount, without the Contract
    providing for the same. Further, with specific reference to the
    interest awarded on the retention money, he submits that the
    retention amount was not released to the petitioner only
    because the procedure prescribed under the Contract for the
    same could not be completed on account of the conduct of the
    petitioner and onset of the COVID pandemic. The sole-
    arbitrator, according to him, has failed to appreciate the said
    aspect.

    26. He submits that aforesaid aspects go to the root of the award, and
    therefore, the impugned portions cannot be separated from the rest of the

    4
    (2011) 5 SCC 758
    5
    (1984) 4 SCC 59
    6
    (1977) 3 SCC 590

    Signature Not Verified Signature Not Verified
    Signed By:AMIT KUMAR Signed
    SHARMA
    Signing Date:10.03.2026 By:PURUSHAINDRA
    19:43:06 Page 13 of 32 KUMAR KAURAV
    award. Therefore, according to him, the award is liable to be set aside in
    toto.

    27. Mr. Udayan Jain opposes the aforesaid submissions and contends as
    follows:

    27.1. The respondent is seeking re-evaluation of the findings in the
    award on merits and re-appreciation of the evidence, which are
    beyond the scope of the Court‟s power under Section 34 of the
    Act. Reliance is placed in this regard, on the decision of the
    Supreme Court in Gayatri Balaswamy v. ISG Novasoft
    Technologies Limited.7

    27.2. The award of damages on account of loss of profits is justified
    as the petitioner had duly established the existence of the
    essential ingredients in this case; a. breach of the Contract, b.

    injury caused to the petitioner on account of the breach c. the
    injury caused is proximate to and attributable as a direct
    consequence of the breach. Reliance is placed on the decision
    of this Court in Sudhershan Kumar Bhayana v. Vinod Seth,8
    in this regard. He further submits that Courts have consistently
    held that loss of profits is a necessary and direct consequence of
    illegal/arbitrary cancellation/abandonment of a contract.

    Reliance is placed on the decisions in Dwaraka Das v. State of
    M.P.
    , 9and Union of India v. M/s J. Sons Eng. Corp Ltd.

    
    
    
    
                        7
                           2025 INSC 605
                        8
                          2023:DHC:7053-DB
                        9
                           (1999) 3 SCC 500
    
    Signature Not Verified                                                            Signature Not Verified
    Signed By:AMIT KUMAR                                                              Signed
    SHARMA
    Signing Date:10.03.2026                                                           By:PURUSHAINDRA
    19:43:06                                                Page 14 of 32             KUMAR KAURAV
    

    &Anr.10Therefore, according to him, there is no perversity in
    the impugned portion of the award.

    27.3. He submits that the contention that the Contract allowed for a
    deviation of thirty per cent against the contractual quantity, and
    hence, any loss of profits, if awarded, could only be against
    seventy per cent of the contractual quantity, was not taken as a
    defence in the respondent‟s statement of defence and was only
    raised in the written submissions as an afterthought. Therefore,
    according to him, the respondent is foreclosed from raising
    such objection in a proceeding under Section 34 of the Act.
    27.4. The award of interest is also justified despite there being no
    express provision in the Contract providing for the same, since
    the Contract did not prohibit the same.

    Analysis

    28. The scope for interference under Section 34 of the Act is quite limited
    and is only permissible when one or more of the explicit grounds laid down
    in
    the provision are satisfied. Section 34 is a carefully guarded provision
    which not only lays down the grounds which permit interference, but also
    cautions against any excessive interference by misconstruction of the
    grounds.The explanations in sub-section (2), starting with the words “for the
    avoidance of doubt”, are suggestive of the legislative intent to not turn this
    limited remedy into a roving inquiry into the merits of the arbitral award or
    into a full-fledged appeal. In Ramesh Kumar Jain vs. Bharat Aluminium

    10
    2015:DHC:3350

    Signature Not Verified Signature Not Verified
    Signed By:AMIT KUMAR Signed
    SHARMA
    Signing Date:10.03.2026 By:PURUSHAINDRA
    19:43:06 Page 15 of 32 KUMAR KAURAV
    Company Limited,11 the Supreme Court noted the narrow scope of this
    supervisory jurisdiction and the availability of four narrow grounds of
    challenge. The relevant part reads thus:

    “28. The bare perusal of section 34 mandates a narrow lens of supervisory
    jurisdiction to set aside the arbitral award strictly on the grounds and
    parameters enumerated in sub-section (2) & (3) thereof. The interference
    is permitted where the award is found to be in contravention to public
    policy of India; is contrary to the fundamental policy of Indian Law; or
    offends the most basic notions of morality or justice. Hence, a plain and
    purposive reading of the section 34 makes it abundantly clear that the
    scope of interference by a judicial body is extremely narrow. It is a settled
    proposition of law as has been constantly observed by this court and we
    reiterate, the courts exercising jurisdiction under section 34 do not sit in
    appeal over the arbitral award hence they are not expected to examine the
    legality, reasonableness or correctness of findings on facts or law unless
    they come under any of grounds mandated in the said provision. In ONGC
    Limited. v. Saw Pipes Limited, this court held that an award can be set
    aside under Section 34 on the following grounds: “(a) contravention of
    fundamental
    policy of Indian law; or (b) the interest of India; or (c) justice or morality,
    or (d) in addition, if it is patently illegal.”

    29. It is equally settled that the Court, while exercising its supervisory
    jurisdiction under Section 34, is not supposed to act like an Appellate Court.
    The scope of examination is not akin to a review of the merits of the dispute,
    rather, it is limited to situations wherein the findings are arbitrary, capricious
    or perverse, or when the conscience of the Court is shocked or the illegality
    is not trivial but goes to the root of the matter. The following observation of
    the Supreme Court in MMTC Ltd. v. Vedanta Ltd.,12 is quite instructive:

    “12. It is only if one of these conditions is met that the Court may interfere
    with an arbitral award in terms of Section 34(2)(b)(ii), but such
    interference does not entail a review of the merits of the dispute, and is
    limited to situations where the findings of the arbitrator are arbitrary,
    capricious or perverse, or when the conscience of the Court is shocked, or

    11
    2025 SCC OnLine SC 2857
    12
    (2019) 4 SCC 163

    Signature Not Verified Signature Not Verified
    Signed By:AMIT KUMAR Signed
    SHARMA
    Signing Date:10.03.2026 By:PURUSHAINDRA
    19:43:06 Page 16 of 32 KUMAR KAURAV
    when the illegality is not trivial but goes to the root of the matter. An
    arbitral award may not be interfered with if the view taken by the
    arbitrator is a possible view based on facts …”

    30. In the present case, the cross-challenges to the impugned award are
    primarily based on the ground of perversity. The Supreme Court, in its
    decision in Delhi Metro Rail Corporation Limited v. Delhi Airport Metro
    Private Limited,13
    examined the scope of the term „perversity‟ as interpreted
    in its earlier decisions, and held that a finding would be perverse if it is so
    irrational that no reasonable person could have arrived at the same. The
    instant challenges, therefore, allege that the impugned portions are perverse,
    being contrary to the sole-arbitrator‟s own findings in the award and as such,
    could not have been arrived at by any reasonable person.

    31. The petitioner‟s challenge to the impugned award, on the aspect of
    rejection of its claim for fixed costs and fixed office expenses, is primarily
    based on the ground that the sole-arbitrator has given an explicit finding that
    the petitioner had incurred the said costs, but owing to a perverse
    understanding of business-practices, has proceeded on the presumption that
    the said costs were to be incurred by the petitioner, even if the Contract had
    not been breached by the respondent.

    32. It is seen that in paragraphs 122 to 124 of the award, an explicit
    finding has been rendered that the petitioner had deployed such workforce
    and machinery at the site as it reasonably expected to be necessary to
    complete the work as and when required by the respondent. The said
    paragraphs are extracted below, for reference:

    “122. The Tribunal notes, that in the letter dated 13.04.2020, NIL

    13
    2024 INSC 2024

    Signature Not Verified Signature Not Verified
    Signed By:AMIT KUMAR Signed
    SHARMA
    Signing Date:10.03.2026 By:PURUSHAINDRA
    19:43:06 Page 17 of 32 KUMAR KAURAV
    schedules or any of the communications issued by it, the Respondent
    had not indicated recommencement of the works. It also did not
    direct the Claimant to reduce or demobilize the manpower and
    machinery. The Respondent did not terminate the Contract with the
    Claimant but kept it alive. It is the case of the Respondent that the
    transportation of the coal is dependent on the Respondent’s
    requirement for it for generation of electricity. Thus, it was the
    Respondent, rather than the Claimant, who was the positioned to
    assess/determine as to the time when the works will recommence.
    The NIL schedules were being issued on the monthly basis. Thus, the
    Tribunal cannot find fault with the Claimant expecting that the works
    can be recommenced at any time and in maintaining the manpower
    & machinery at the site.

    123. The Respondent does not dispute that the Claimant was
    required to maintain adequate machine and manpower at the site to
    execute the works as and when schedules are issued by the
    Respondent. It is also not in dispute that the Respondent was
    empowered to impose heavy penalty and damages if the Claimant
    failed to perform the works as per the schedules issued to it.

    124. The Tribunal also finds merit in the submission of the Claimant
    that the machinery and equipment at the site are specialised and
    included heavy items which are not easy to demobilize and
    remobilize when the works recommenced. Despite this position, the
    Tribunal notes that, the Claimant made effort to and did demobilize
    certain machinery and equipment such as Hyva tipper trucks and
    other vehicles. It also reduced the workforce and facilities.”

    33. In paragraph 130 of the award, the sole arbitrator records the
    respondent‟s submission that the cost component, to be incurred initially by
    the petitioner, was included in the contractual price. In paragraph no. 131,
    the submission that as per the terms of the Contract, the petitioner was not
    entitled for any claim with respect to idleness of its machinery/manpower
    has been noted. The said paragraphs are reproduced below, for reference:

    “130. The Respondent denies the claims of the Claimant. The
    Respondent has submitted that the costs incurred by the Claimant on
    account of arranging manpower and machinery stood included in the
    price to be paid to the Claimant under the Contract and no such
    expenses can be held to be additionally payable to the Claimant
    under the Contract.

    131. Referring to Clause 12 of Point G under Important Notes in the

    Signature Not Verified Signature Not Verified
    Signed By:AMIT KUMAR Signed
    SHARMA
    Signing Date:10.03.2026 By:PURUSHAINDRA
    19:43:06 Page 18 of 32 KUMAR KAURAV
    PO, the Respondent submits that, the Claimant is not entitled for any
    claim whatsoever for the idleness of its tipping/trucks/Pay
    loaders/equipment/ employees for want of coal or lack of space
    available at the unloading site or any dislocation, reroute or non-
    availability of third-party Sampling team or any other reasons.”

    34. Further, in paragraph 135 of the award, the principle of law of
    damages, requiring the non-breaching party to be placed in the same
    position as it would have been but for the breach of the contract, is noted.
    The sole-arbitrator proceeds to observe that under the Contract, the
    petitioner would have been entitled to the contractual amount, which would
    be the sum of the costs to be initially incurred by the petitioner and the
    profits that it would earn out of the contract. In paragraph 137, it is then held
    that the said costs were not additional costs and expenses incurred by the
    petitioner on account of the breach of the Contract and therefore, the
    petitioner was not entitled to the same. The said paragraphs are reproduced
    below, for reference:

    “135. At the outset the Tribunal notes that it is a trite principle of the
    law if damages that the party which has not committed breach of the
    contract should be as far as possible be placed in the same position
    as if the contract had been performed by the breaching party. In the
    present case, the Contract was for transportation of 13,69,000 MT
    coal with a permissible deviation of +/-30%. Thus, had the parties
    performed the Contract without any breach or failure, at the end of
    the Contract Period, the Claimant would have been in a position
    where it would receive the Contact Price of 116,77,57,000.00.
    However, at the same time the Claimant would have incurred all
    costs and expenses for performing its part of the Contract. To put it
    differently, at the end of the Contract Period, the Claimant would
    have earned certain profit in the ordinary course of business, which
    is the difference between the total Contract Price and the expenses
    that the Claimant would have incurred to perform the Contract.
    Thus, essentially, this loss of profit would be the damages which
    would have been incurred by the Claimant. The Claimant’s claims
    should be analysed in this context.

                                XXXX
    
    Signature Not Verified                                                                   Signature Not Verified
    Signed By:AMIT KUMAR                                                                     Signed
    SHARMA
    Signing Date:10.03.2026                                                                  By:PURUSHAINDRA
    19:43:06                                                  Page 19 of 32                  KUMAR KAURAV
    

    137. Thus, the Tribunal finds that the Fixed Costs claimed by the
    Claimant are not additional costs and expenses incurred to the
    Claimant on account of breach of the Contract by the Respondent.
    Hence, it cannot be considered as losses or damages to the
    Claimant.”

    35. The petitioner‟s claim for fixed expenses has also been rejected on the
    same grounds as the claim for fixed costs, as noted above.

    36. The aforesaid findings categorically suggest that as per the tribunal‟s
    understanding of the contract and respective obligations of the parties
    thereunder, the petitioner was only entitled to the contract price. It further
    implies that the contractual arrangement between the parties did not provide
    for any stipulation for payment of fixed costs or expenses in addition to the
    said contract price. Thus, as per the findings of the tribunal, it was an
    inherent part of the petitioner‟s contractual obligations to make
    arrangements for machinery, manpower and other facilities for the proper
    fulfilment of its part of the bargain and in lieu thereof, a contract price was
    fixed. The tribunal‟s view, furthermore, indicates that the petitioner was
    supposed to deduct the expenses/costs incurred by it from the contract price
    and to ascertain its profits after such deductions. The view taken by the
    tribunal is a possible view in light of the terms of contract, more specifically
    in light of the fact that there is no express stipulation for payment of fixed
    costs/expenses to the petitioner, over and above the contract price. Even if,
    arguendo, the entire contract would have been performed, there is nothing to
    suggest that the additional costs/expenses incurred by the petitioner in
    performance thereof were recoverable from the respondent, in addition to
    the payment of contract price. The tribunal‟s view that the respondent‟s
    obligation was limited to the payment of contract price and fixed

    Signature Not Verified Signature Not Verified
    Signed By:AMIT KUMAR Signed
    SHARMA
    Signing Date:10.03.2026 By:PURUSHAINDRA
    19:43:06 Page 20 of 32 KUMAR KAURAV
    costs/expenses were adjustable from the contract price itself and profits were
    to be ascertained after such adjustment, is a view which could have been
    taken by a reasonable man in light of the terms of the contract.

    37. Therefore, the view taken by the sole arbitrator cannot be termed as
    perverse as it is a possible view of the contractual arrangement between the
    parties. It would be apposite, at this stage, to refer to the decision of the
    Supreme Court in Consolidated Construction Consortium Limited Vs.
    Software Technology Parks of India,14
    wherein the Court discussed the
    scope of Section 34 of the Act and unequivocally noted that the remedy
    under Section 34 is not meant for re-appreciation of evidence or to discard a
    possible view of the matter. The relevant part reads thus:

    “46. Scope of Section 34 of the 1996 Act is now well crystallized by a
    plethora of judgments of this Court. Section 34 is not in the nature of an
    appellate provision. It provides for setting aside an arbitral award that too
    only on very limited grounds i.e. as those contained in Sub-sections (2) and
    (2-A) of Section 34. It is the only remedy for setting aside an arbitral award.
    An arbitral award is not liable to be interfered with only on the ground that
    the award is illegal or is erroneous in law which would require re-appraisal
    of the evidence adduced before the arbitral tribunal. If two views are
    possible, there is no scope for the court to re-appraise the evidence and to
    take the view other than the one taken by the arbitrator. The view taken by
    the arbitral tribunal is ordinarily to be accepted and allowed to prevail.
    Thus, the scope of interference in arbitral matters is only confined to the
    extent envisaged Under Section 34 of the Act. The court exercising powers
    Under Section 34 has perforce to limit its jurisdiction within the four
    corners of Section 34. It cannot travel beyond Section 34. Thus, proceedings
    Under Section 34 are summary in nature and not like a full-fledged civil suit
    or a civil appeal. The award as such cannot be touched unless it is contrary
    to the substantive provisions of law or Section 34 of the 1996 Act or the
    terms of the agreement.”

    14

    (2025) 7 SCC 75

    Signature Not Verified Signature Not Verified
    Signed By:AMIT KUMAR Signed
    SHARMA
    Signing Date:10.03.2026 By:PURUSHAINDRA
    19:43:06 Page 21 of 32 KUMAR KAURAV

    38. Further, Hindustan Construction Co. Ltd. v. NHAI,15 the Supreme
    Court has rendered the following observations on the scope of proceedings
    under Section 34 of the Act, especially when the arbitrator‟s interpretation of
    contract is challenged:

    “27. For a long time, it is the settled jurisprudence of the courts in the
    country that awards which contain reasons, especially when they
    interpret contractual terms, ought not to be interfered with, lightly. The
    proposition was placed in State of U.P. v. Allied Constructions [State of
    U.P.
    v. Allied Constructions, (2003) 7 SCC 396] : (SCC p. 398, para 4)
    “4. … It was within his jurisdiction to interpret Clause 47 of
    the Agreement having regard to the fact-situation obtaining
    therein. It is submitted that an award made by an arbitrator
    may be wrong either on law or on fact and error of law on the
    face of it could not nullify an award. The award is a speaking
    one. The arbitrator has assigned sufficient and cogent reasons
    in support thereof.
    Interpretation of a contract, it is trite, is a
    matter for the arbitrator to determine (see Sudarsan Trading
    Co. v. State of Kerala [Sudarsan Trading Co. v. State of
    Kerala, (1989) 2 SCC 38] ). Section 30 of the Arbitration Act,
    1940 providing for setting aside an award is restrictive in its
    operation. Unless one or the other condition contained in
    Section 30 is satisfied, an award cannot be set aside. The
    arbitrator is a Judge chosen by the parties and his decision is
    final. The Court is precluded from reappraising the evidence.
    Even in a case where the award contains reasons, the
    interference therewith would still be not available within the
    jurisdiction of the Court unless, of course, the reasons are
    totally perverse or the judgment is based on a wrong
    proposition of law.”

    28. This enunciation has been endorsed in several cases (Ref. McDermott
    International Inc. v. Burn Standard Co. Ltd. [McDermott International
    Inc.
    v. Burn Standard Co. Ltd., (2006) 11 SCC 181] ).
    In MSK Projects
    (I) (JV) Ltd. v. State of Rajasthan [MSK Projects (I) (JV) Ltd. v. State of
    Rajasthan, (2011) 10 SCC 573 : (2012) 3 SCC (Civ) 818] it was held that
    an error in interpretation of a contract by an arbitrator is “an error
    within his jurisdiction”. The position was spelt out even more clearly
    in Associate Builders [Associate Builders v. DDA, (2015) 3 SCC 49 :

    (2015) 2 SCC (Civ) 204] , where the Court said that : (Associate Builders

    15
    (2024) 2 SCC 613

    Signature Not Verified Signature Not Verified
    Signed By:AMIT KUMAR Signed
    SHARMA
    Signing Date:10.03.2026 By:PURUSHAINDRA
    19:43:06 Page 22 of 32 KUMAR KAURAV
    case [Associate Builders v. DDA, (2015) 3 SCC 49 : (2015) 2 SCC (Civ)
    204] , SCC p. 81, para 42)
    “42. … 42.3. … if an arbitrator construes a term of the
    contract in a reasonable manner, it will not mean that the
    award can be set aside on this ground. Construction of the
    terms of a contract is primarily for an arbitrator to decide
    unless the arbitrator construes the contract in such a way
    that it could be said to be something that no fair-minded or
    reasonable person could do.””

    39. As discussed above, the view taken by the sole arbitrator is a fairly
    possible view in light of the contractual controversy between the parties, and
    even if it is held that an alternate view is possible, this reason is not enough
    to discard the view taken by the sole arbitrator. The distinction between
    supervisory jurisdiction and appellate jurisdiction would effectively be
    obliterated if the Court enters into re-appreciation of evidence to alter a
    legally possible view.

    40. The award, therefore, insofar as it rejects the petitioner‟s claims for
    fixed costs and fixed expenses, cannot be termed as perverse.

    41. The petitioner‟s challenge to the award of fifty per cent of the amount
    claimed towards legal expenses is also meritless. As rightly pointed out by
    Mr. Adarsh Tripathi, the grant of costs and the determination of the amount
    thereof, is left to the discretion of the arbitrator under Section 31A of the
    Act. In fact, the said provision explicitly provides that „costs‟ would include
    „legal fees and expenses‟ and that in determining the amount, the arbitrator
    shall have regard to „whether the party has succeeded partly in the case‟. The
    said provision is extracted below, for reference:

    31A. Regime for costs.–(1) In relation to any arbitration proceeding
    or a proceeding under any of the provisions of this Act pertaining to
    the arbitration, the Court or arbitral tribunal, notwithstanding
    anything contained in the Code of Civil Procedure,1908 (5 of 1908),
    shall have the discretion to determine–

    Signature Not Verified Signature Not Verified

    Signed By:AMIT KUMAR                                                                Signed
    SHARMA
    Signing Date:10.03.2026                                                             By:PURUSHAINDRA
    19:43:06                                               Page 23 of 32                KUMAR KAURAV
    

    (a) whether costs are payable by one party to another;

    (b) the amount of such costs; and

    (c) when such costs are to be paid.

    Explanation.–For the purpose of this sub-section, “costs” means
    reasonable costs relating to–

    (i) the fees and expenses of the arbitrators, Courts and
    witnesses;

    (ii) legal fees and expenses;

    (iii) any administration fees of the institution supervising the
    arbitration; and

    (iv) any other expenses incurred in connection with the arbitral
    or Court proceedings and the arbitral award.

    (2) If the Court or arbitral tribunal decides to make an order as to
    payment of costs,–

    (a) the general rule is that the unsuccessful party shall be ordered to
    pay the costs of the successful party; or

    (b) the Court or arbitral tribunal may make a different order for
    reasons to be recorded in writing.

    (3) In determining the costs, the Court or arbitral tribunal shall have
    regard to all the circumstances, including–

    (a) the conduct of all the parties;

    (b) whether a party has succeeded partly in the case;

    (c) whether the party had made a frivolous counterclaim leading to
    delay in the disposal of the arbitral proceedings; and

    (d) whether any reasonable offer to settle the dispute is made by a
    party and refused by the other party.

    (4) The Court or arbitral tribunal may make any order under this
    section including the order that a party shall pay–

    (a) a proportion of another party’s costs;

    (b) a stated amount in respect of another party’s costs;

    (c) costs from or until a certain date only;

    (d) costs incurred before proceedings have begun;

    (e) costs relating to particular steps taken in the proceedings;

    (f) costs relating only to a distinct part of the proceedings; and

    (g) interest on costs from or until a certain date.

    (5) An agreement which has the effect that a party is to pay the whole
    or part of the costs of the arbitration in any event shall be only valid
    if such agreement is made after the dispute in question has arisen.

    42. Therefore, on a bare reading of the said provision, it appears that the
    determination of costs falls within the discretionary realm of the arbitrator
    and the exercise of such discretion could be guided by the parameters laid

    Signature Not Verified Signature Not Verified
    Signed By:AMIT KUMAR Signed
    SHARMA
    Signing Date:10.03.2026 By:PURUSHAINDRA
    19:43:06 Page 24 of 32 KUMAR KAURAV
    down in sub-section (4) of Section 31A. Evidently, one of the parameters is
    part success of the winning party. Therefore, it is clear that the sole-
    arbitrator was fully justified in determining the legal expenses to be paid by
    the respondent to the petitioner at fifty per cent of the claimed amount, as
    around fifty per cent of the petitioner‟s total claim came to be allowed. In
    view thereof, there is no infirmity in the exercise of discretion by the sole-
    arbitrator in determination of cost.

    43. Adverting to the respondent‟s challenge to the award, it is seen that
    the dispute is with respect to the sole-arbitrator‟s perception of the quantity
    of coal envisaged under the Contract to be transported by the petitioner. In
    the award, the sole-arbitrator has proceeded on the basis that the contract
    stipulated the transportation of 13,69,000 MT (Thirteen Lakh Sixty Nine
    Thousand metric tonne only) of coal, despite explicitly finding that the said
    quantity was subject to a permissible limit of deviation of (+/-) 30% (Thirty
    per cent only). In paragraph 54 of the award, which is extracted below for
    reference, the sole-arbitrator records the said finding:

    ” 54. In view of the above discussion, the Tribunal holds that
    Contract was fixed quantity contract with a provision for deviation
    +/- 30%.”

    44. In paragraph 158 of the award, the submissions of the petitioner on its
    claim for loss of profits are recorded. The petitioner‟s claim, as recorded
    therein, was that under the Contract, it was to transport 13,69,000 MT
    (Thirteen Lakh Sixty-Nine Thousand metric tonne only) of coal and
    accordingly, the contractual amount was Rs. 1,16,77,57,000/-. Accordingly,
    the loss of profits was calculated against the balance amount out of Rs.
    1,16,77,57,000/-. In paragraph 170 of the award, the sole arbitrator has

    Signature Not Verified Signature Not Verified
    Signed By:AMIT KUMAR Signed
    SHARMA
    Signing Date:10.03.2026 By:PURUSHAINDRA
    19:43:06 Page 25 of 32 KUMAR KAURAV
    accepted the contractual amount, as urged by the petitioner, to be Rs.
    1,16,77,57,000/- and has proceeded to calculate the quantum of loss of
    profits accordingly. The aforesaid paragraphs are extracted below, for
    reference:

    “158. The next claim of the Claimant is loss of profit. The Claimant
    submits that in lieu of the resources, it would have earned certain
    profits in the ordinary course of business. The Claimant has
    submitted that under the Contract it was required to transport
    13,69,000.00 metric tonnes. Referring to the BOQ forming part of
    the LOA and the PO, the Claimant submits that the Tipper Loading
    of the mine end was to be carried out at the rate of ₹80.00 per metric
    tonnes and the Wagon Loading at Siding was to be carried out at the
    rate of 155.00 per metric tonne. Under the Contract, the Claimant
    was also required to transport a total quantity of 8,21,40,000 MK
    (metric tonnes per kilometre) (13,69,000 metric tonnes x 60 kms) of
    coal to be transported at the rate of ₹ 10.30 per MK. Thus, the total
    consideration of the Contract was ₹1,16,77,57,000.00.
    XXXXX

    170. The Tribunal has already noted above that the it is a well settled
    principle of the law of damages that the non-breaching party which
    is not at fault should be as far as possible be placed in the same
    position as if the contract has been performed by the breaching
    party. The Tribunal also found that had the parties performed the
    Contract without any breach or failure, at the end of the Contract
    Period, the Claimant would have been in a position where it would
    receive the Contact Price of ₹ 116,77,57,000.00, and would have
    earned certain profit in the ordinary course of business. Thus,
    essentially, the loss of profit is the damage which has enured to the
    Claimant.”

    45. On this aspect, the primary submission advanced on behalf of the
    petitioner is that the contention regarding permissible limits of deviation was
    not raised by the respondent in its statement of defence and hence, the same
    cannot be raised in a challenge under Section 34 of the Act. Essentially, it is
    an argument of default on the part of the respondent in raising this objection
    at the appropriate stage. Be that as it may, this Court does not find it
    necessary to examine this argument as the findings of the sole arbitrator are
    Signature Not Verified Signature Not Verified
    Signed By:AMIT KUMAR Signed
    SHARMA
    Signing Date:10.03.2026 By:PURUSHAINDRA
    19:43:06 Page 26 of 32 KUMAR KAURAV
    sustainable on merits. It is, no doubt, correct that the contract provided for a
    deviation of +/- 30% in the transferable quantity. It is also correct that the
    sole arbitrator has not taken the possible deviations into account and has
    proceeded to calculate the profits on the assumption that the entire
    transferable quantity of coal would have been transferred had the contract
    not been breached. However, it is of utmost importance to note that in
    calculation of loss of profits, the Court could only take into account the state
    of affairs in ordinary and natural course of events and the underlying
    assumption in the calculation of profits is the fulfilment of the contract,
    barring deviations or contingencies which may or may not have arisen.
    Essentially, the determination of loss of profits takes into account the
    „expected‟ profits and the expectation ought to be based on the fulfilment of
    the whole contract i.e. transfer of the full quantity of coal.

    46. The sole arbitrator has proceeded on the premise of fulfilment of the
    whole contract in ordinary course of events, without entering into the
    speculative zone of taking the deviations into account. This Court finds no
    perversity in the said view and again, it is a view which could flow from the
    mind of a reasonable man, as deviations are nothing but probable future
    contingencies. Furthermore, while calculating the loss of profits, an
    assumption of the quantity which ought to have been transferred by the
    petitioner to be 30% lesser than the fixed quantity would make it a
    vulnerable assumption, as such an assumption could also be made on the
    higher side to increase the quantity by 30%. Therefore, the sole arbitrator‟s
    finding is based on the fixed quantity of coal, without speculating any
    deviations, and the same is rightly intended to avoid any arbitrariness. This
    Court finds no infirmity in the said view, being a legally tenable view.

    Signature Not Verified Signature Not Verified

    Signed By:AMIT KUMAR                                                             Signed
    SHARMA
    Signing Date:10.03.2026                                                          By:PURUSHAINDRA
    19:43:06                                              Page 27 of 32              KUMAR KAURAV
    

    47. The submission advanced on behalf of the respondent that the award
    of loss of profits to the petitioner is in contravention of the law laid down by
    the Supreme Court in Batliboi Environmental Engineers Limited, All India
    Radio, and Unibros is unfounded. The sole-arbitrator, upon examination of
    the aforesaid decisions, has concluded that the said cases, having involved
    an aspect of delay in completion of the contract and the consequential claim
    for loss of profits during the extended contract period, were not applicable in
    the present case, where the breach of the Contract was within the original
    contractual period. A perusal of the said decisions indicates that the facts
    therein involved delay in completion of the Contract for reasons attributable
    to the employer. There is no indication in any of the three decisions that the
    principle enunciated therein would be applicable to cases not involving any
    such aspect of delay. Further, as noted, with approval, by the Supreme Court
    in McDermont International Inc v. Burn Standard Company Ltd.,16 the
    Court, in M.N. Gangappa v. Atmakur Nagabhushanam Setty & Co.,17 has
    held that the method used for computation of damages will depend on the
    facts and circumstances of each case. While allowing the claim for loss of
    profits, the sole-arbitrator has reasoned that the Contract being a fixed
    quantity contract, would have entitled the petitioner to a certain amount of
    profit, that, ultimately, did not accrue to it on account of the breach by the
    respondent. Therefore, according to the sole-arbitrator, no additional
    evidence was required for the petitioner to establish that on account of the
    breach, it had lost the profits that it would have otherwise earned out of the
    Contract. The said conclusion, as correctly highlighted by Mr Udayan Jain,

    16
    (2006) 11 SCC 181
    17
    (1973) 3 SCC 406

    Signature Not Verified Signature Not Verified
    Signed By:AMIT KUMAR Signed
    SHARMA
    Signing Date:10.03.2026 By:PURUSHAINDRA
    19:43:06 Page 28 of 32 KUMAR KAURAV
    is in line with the decision of the Supreme Court in Dwarka Das and of this
    Court in M/s J. Sons Engineers. Further, in A.T. Brij Paul Singh, the facts
    involved were similar to those before the Court herein. The facts therein
    involved two suits arising out of similar contracts for similar works. The
    Trial Court had awarded damages for loss of profits at the rate of fifteen per
    cent of the price of the balance works in both the suits. The decision of the
    Trial Court in both the cases had been appealed against, before the High
    Court. While in one of the cases, the High Court held that the Trial Court
    was justified in computing the damages for loss of profits at the rate of
    fifteen per cent of the balance works, in the other case, the High Court held
    that actual loss of profit had to be proved and a mere percentage, as
    specified by the parties, would not furnish adequate evidence to sustain the
    claim. The Supreme Court, on an appeal against the High Court decision
    setting aside the judgment of the Trial Court, observed that in works
    contracts, an expectation of reasonable profit is implicit and in case of
    breach of the same, any loss of the same has to be compensated. The
    relevant portion of the said decision is extracted below, for reference:

    “10. …..What would be the measure of profit would depend upon
    facts and circumstances of each case. But that there shall be a
    reasonable expectation of profit is implicit in a works contract and
    its loss has to be compensated by way of damages if the other party
    to the contract is guilty of breach of contract cannot be gainsaid. In
    this case we have the additional reason for rejecting the contention
    that for the same type of work, the work site being in the vicinity of
    each other and for identical type of work between the same parties, a
    Division Bench of the same High Court has accepted 15% of the
    value of the balance of the works contract would not be an
    unreasonable measure of damages for loss of profit. We are
    therefore, of the opinion that the High Court was in error in wholly
    rejecting the claim under this head.

    11. Now if it is well-established that the respondent was guilty of
    breach of contract in as much as the recission of contract by the
    Signature Not Verified Signature Not Verified
    Signed By:AMIT KUMAR Signed
    SHARMA
    Signing Date:10.03.2026 By:PURUSHAINDRA
    19:43:06 Page 29 of 32 KUMAR KAURAV
    respondent is held to be unjustified, and the plaintiff-contractor had
    executed a part of the works contract, the contractor would be
    entitled to damages by way of loss of profits. Adopting the measure
    accepted by the High Court in the facts and circumstances of the
    case between the same parties and for the same type of work at 15%
    of the value of the remaining parts of the work contract, the damages
    for loss of profit can be measured.”

    (Emphasis supplied)

    48. The submission that the rate at which the damages for loss of profits
    were computed is perverse, also cannot be accepted. The sole-arbitrator has
    clearly considered the documents produced by the petitioner in this regard,
    i.e., auditors‟ reports for the preceding years and certified statements from
    its chartered accountants regarding its short-term and long-term profits, and
    on the basis of the contents thereof, has found that the rate claimed by the
    petitioner, i.e., fifteen per cent of the balance contractual amount, was
    reasonable. The reliance placed by Mr. Adarsh Tripathi on the decisions of
    the Supreme Court in J.G. Engineers Private Limited, A.T. Brij Paul Singh,
    and Mohd. Salamatullah, is misplaced for the fact that none of the said
    decisions lay down any straightjacket formula for determination of the rate
    at which damages are to be calculated. In fact, as noted earlier, in the
    decision in A.T. Brij Paul Singh, the Supreme Court rejected the reasoning
    of the High Court that the Trial Court had computed the rate at which
    damages had been awarded on the basis of „inadequate evidence‟ and upheld
    the judgment of the Trial Court. Similarly, in Mohd. Salamatullah, the
    Supreme Court upheld the computation of damages by the Trial Court,
    which had been assailed before the High Court on the ground that the same
    had been arrived at without any evidentiary basis. Therefore, the award does
    not suffer from perversity or any illegality as far as the said aspect is
    concerned.

    Signature Not Verified Signature Not Verified

    Signed By:AMIT KUMAR                                                                 Signed
    SHARMA
    Signing Date:10.03.2026                                                              By:PURUSHAINDRA
    19:43:06                                                Page 30 of 32                KUMAR KAURAV
    

    49. The challenge to the award as regards the grant of interest at the rate
    of twelve per cent per annum is also sans merits. Under Section 31(7) of the
    Act, the arbitrator is expressly conferred with the power to include any
    interest component in the award, unless otherwise agreed by the parties.
    Further, the arbitrator is conferred with the discretion to determine the
    quantum of interest at such rate as he deems reasonable. The said provision
    is extracted below, for reference:

    “31. Form and contents of arbitral award.–

    XXXXX
    (7) (a) Unless otherwise agreed by the parties, where and in so far as
    an arbitral award is for the payment of money, the arbitral tribunal
    may include in the sum for which the award is made interest, at such
    rate as it deems reasonable, on the whole or any part of the money,
    for the whole or any part of the period between the date on which the
    cause of action arose and the date on which the award is made.”

    50. The respondent has not pointed out any clause in the Contract
    prohibiting the grant of interest. Further, the submission that while awarding
    interest on the retention money, the sole-arbitrator failed to appreciate that
    the delay in releasing the same was attributable to the conduct of the
    petitioner itself and the onset of the COVID pandemic and therefore, interest
    could not have been awarded on the same, also cannot be accepted. Under
    Section 34 of the Act, the scope of interference by the Court is restricted.
    The Court cannot undertake the role of a fact-finding authority, and has to
    accept the factual findings in the award as they are. Reference can be made
    to the decision in Gayatri Balaswamy. Therefore, it is not open for the
    respondent to urge the said submissions in the present proceedings.
    Therefore, there is no perversity or any other error in the award as far as the
    grant of interest is concerned.

    Signature Not Verified Signature Not Verified

    Signed By:AMIT KUMAR                                                                 Signed
    SHARMA
    Signing Date:10.03.2026                                                              By:PURUSHAINDRA
    19:43:06                                                Page 31 of 32                KUMAR KAURAV
                         Conclusion
    

    51. In view of the foregoing discussion, it is seen that the findings
    rendered in the impugned award do not suffer from any infirmity and the
    award, in its entirety, cannot be held as perverse or patently illegal. None of
    the grounds for setting aside the impugned award under Section 34 are
    attracted, and the issues raised by the parties herein essentially pertain to re-
    appreciation of the evidence for setting aside a legally possible view in the
    facts of the case, which is impermissible. Accordingly, the impugned award
    is upheld.

    52. Thus, both the petitions stand dismissed. No order as to costs.

    (PURUSHAINDRA KUMAR KAURAV)
    JUDGE
    FEBRUARY 26, 2026
    aks.

    Signature Not Verified Signature Not Verified

    Signed By:AMIT KUMAR                                                            Signed
    SHARMA
    Signing Date:10.03.2026                                                         By:PURUSHAINDRA
    19:43:06                                              Page 32 of 32             KUMAR KAURAV
     



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here