― Advertisement ―

ONE WEEK VIRTUAL INTERNATIONAL FACULTY DEVELOPMENT PROGRAMME BY KIIT SCHOOL OF LAW

THE ORGANISATIONThis Faculty Development Program is being hosted by KIIT Deemed to be University (KIIT-DU), Bhubaneswar, Odisha, through its School of Law. It...
HomeNew India Insurance Company vs Seapol Port Private Limited on 23 April,...

New India Insurance Company vs Seapol Port Private Limited on 23 April, 2026

ADVERTISEMENT

Bombay High Court

New India Insurance Company vs Seapol Port Private Limited on 23 April, 2026

    2026:BHC-OS:10430

                                                                    901-CARBPL-6069-2023*.docx


        rrpillai                 IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                                        ORDINARY ORIGINAL CIVIL JURISDICTION
                        COMMERCIAL ARBITRATION PETITION (L) NO. 6069 OF 2023

                        The New India Assurance Co. Ltd.
                        Regional Office (Claims Hub)
                        Dewa Towers, 3rd Floor, 770-A,
                        Anna Salai, Near Spencer Plaza                          ..... Petitioner
                        Chennai-600 002
                                  Vs.
                        M/s. Seapol Port Pvt. Ltd.
                        A Private Limited Company
                        Having their office at Dheen Estate
                        2nd Floor, Moore Street,
                        Chennai-600 001                                         ..... Respondents

                        Mr. Sanjit Shenoy (through VC) a/w. Mr. Vipul Shukla i/b. S. Shenoy
                        and Associates for the Petitioner.
                        Mr. Aseem Naphade a/w. Mr. Rahul Mehta, Mr. Nikhil Mehta and Ms.
                        Deepanjali Mishra i/b. KMC Legal Venture for the Respondent.

                                                CORAM : GAURI GODSE J
                                                RESERVED ON : 12th DECEMBER 2025
                                                 PRONOUNCED ON : 23rd APRIL 2026
                        JUDGMENT :

BASIC FACTS:

1. This petition is filed under Section 34 of the Arbitration and

Conciliation Act 1996 (“the Arbitration Act“) by the original respondent
Digitally
signed by
RAJESHWARI
RAJESHWARI RAMESH
RAMESH PILLAI
PILLAI Date: 1/24
2026.04.23
18:27:59
+0530

::: Uploaded on – 23/04/2026 ::: Downloaded on – 23/04/2026 23:29:33 :::
901-CARBPL-6069-2023*.docx

(“the Insurance Company”) for setting aside the majority Award dated

27th September 2022 by the presiding arbitrator and the co-arbitrator

of the Arbitral Tribunal consisting of three members. By the impugned

Award, the petitioner is directed to pay to the respondent (“claimant”)

a sum of Rs. 3,73,88,393/- together with future interest thereon

@18% per annum from 11th March 2021, i.e. the date of the claim, till

realisation. The tribunal also directed the Insurance Company to pay

the claimant’s share towards the arbitration fees.

2. The claim is based on an insurance policy, namely

“Contractor’s Plant and Machinery Insurance Policy” (“the said

policy”). The sum insured under the said policy was Rs.

25,80,00,000/-. The said policy insured a machine known as

SPONSORED

“Leibherr- Harbour Crane” bearing Serial No. 140836 (“the said

machine”) for a period from 10 th August 2019 to 9 th August 2020. On

26th August 2019, a fire incident occurred at the claimant’s premises

at the Vishakhapatnam Port Trust, where the said machine was

stationed. Hence, the claim for the loss suffered due to the damage to

the machine.

SUBMISSIONS ON BEHALF OF THE PETITIONER:

3. The impugned Award grants a speculative claim with no basis

in evidence. The assessment in the impugned Award is in conflict

2/24

::: Uploaded on – 23/04/2026 ::: Downloaded on – 23/04/2026 23:29:33 :::
901-CARBPL-6069-2023*.docx

with the public policy of India and therefore invites intervention under

Section 34(2)(b)(ii) of the Arbitration Act. The impugned Award is

inconsistent with IRDAI and public accountability norms applicable to

PSUs. The impugned Award erroneously accepts a 15%

improvement in the upgraded crane model as per the second

addendum to the surveyor’s report, without any OEM corroboration.

The 49% depreciation accepted is based on operating hours, which is

technically unjustified. In accordance with industry practice, OEM

benchmarks, and crane usage history, the minority Award correctly

applied 60% depreciation. The impugned Award accepted the

surveyor’s report without requiring an examination of the surveyor,

unfairly shifting the burden onto the Insurance Company. The

impugned Award accepts the claim of Rs. 11.30 Crores despite the

absence of OEM invoices, an independent valuation, or proof of

actual loss.

4. The impugned Award erroneously dismisses Mr Navin Jain’s

report due to the absence of a surveyor’s license. Mr. Jain was

appointed as a technical expert under Section 64UM of the Insurance

Act and not as a surveyor; hence, his analysis remains credible. The

claimant’s figures are on assumptions without OEM confirmation or

proof of replacement cost, and in the absence of OEM-backed

3/24

::: Uploaded on – 23/04/2026 ::: Downloaded on – 23/04/2026 23:29:33 :::
901-CARBPL-6069-2023*.docx

valuation or market quotes. Hence, the claimant failed to prove actual

loss.

5. The reasons recorded in the impugned Award are erroneous in

law and fact, ignoring settled regulatory understanding. The

impugned Award incorrectly infers malice from delay, without

appreciating the mandatory public-sector approvals and the

unprecedented COVID situation prevailing at the material time.

6. The estimates accepted by the impugned Award are patently

illegal and in conflict with the Evidence Act and insurance law. The

grant of interest @ 18% per annum from 29 th November 2019 to 9 th

July 2020 and further from the date of statement of claim till

realisation is excessive and contrary to section 3(1) of the Interest

Act, which mandates that interest should not exceed the current

lending rate unless supported by a usage of trade or contract, which

is absent in the present case. It is further submitted that awarding

penal interest in such a case would violate settled legal norms. It was

argued on behalf of the Insurance Company that the grant of such a

rate of interest is on the assumption that the insurance claim is akin

to a commercial receivable, which is not tenable. The interest granted

is excessive and contrary to Section 3(1) of the Interest Act, 1978,

4/24

::: Uploaded on – 23/04/2026 ::: Downloaded on – 23/04/2026 23:29:33 :::
901-CARBPL-6069-2023*.docx

which mandates that interest should not exceed the current lending

rate unless supported by a usage of trade or contract. Thus, awarding

penal interest lacks a legal or contractual foundation and is manifestly

arbitrary and against public interest. Public sector insurers operate

under fiduciary and regulatory constraints. Therefore, imposing

punitive interest results in wrongful depletion of public funds, violating

fiscal discipline and solvency standards.

7. The well-reasoned Minority Award dated 3rd October 2022

should be upheld as it reflects the lawful application of contractual

indemnity, judicial precedent, and regulatory compliance. The

reasoning of the Minority Award passes muster under Section 34(2)

(b)(ii) of the Arbitration Act and avoids the pitfalls of perversity that

afflict the Majority Award.

SUBMISSIONS ON BEHALF OF THE RESPONDENT:

8. The claimant is, inter alia, engaged in the business of handling

and unloading cargo from vessels using cranes. The claimant availed

from the petitioner the said policy on 9 th August 2019. The sum

insured under the said policy was Rs. 25,80,00,000/-. The claimant

paid a premium of Rs. 4,16,000/- inclusive of GST. The said policy

5/24

::: Uploaded on – 23/04/2026 ::: Downloaded on – 23/04/2026 23:29:33 :::
901-CARBPL-6069-2023*.docx

insured the said machine for a period from 10 th August 2019 to

9th August 2020.

9. On 26th August 2019, a fire incident occurred at the claimant’s

premises at the Vishakhapatnam Port Trust, where the said machine

was stationed. As a result, the said machine was substantially

damaged. The claimant immediately informed the Insurance

Company of the incident by email dated 26 th August 2019. Thereafter,

the claimant lodged its claim on 24 th December 2019 for a sum of Rs.

3.25 million Euros. The Insurance Company appointed one Mr

Vijaykumar S. Saokar as a surveyor as required by Section 64 UM of

the Insurance Act, 1938. The said surveyor visited the site in question

to examine the machine on 5 occasions, i.e., 28 th August 2019, 29th

August 2019, 10th September 2019, 23rd September 2019, and 15th

October 2019. On 1st September 2019, the surveyor also prepared a

preliminary report and issued a final survey report dated 8 th

November 2019, thereby assessing the claimant’s loss in the sum of

Rs. 11,49,33,500/-. Thereafter, the surveyor issued the 1 st Addendum

Report dated 7th January 2020, wherein the loss assessed was in the

sum of Rs. 11,40,59,325/-, thereby reducing a sum of approximately

Rs. 9 lakhs. Thereafter, the surveyor issued the 2 nd Addendum Report

dated 20th February 2020, wherein the loss assessed was in the sum

6/24

::: Uploaded on – 23/04/2026 ::: Downloaded on – 23/04/2026 23:29:33 :::
901-CARBPL-6069-2023*.docx

of Rs. 11,30,19,619/- , thereby reducing the total sum of

approximately Rs. 19 lakhs.

10. The Insurance company was still not satisfied with the reduction

and had appointed an expert, Mr Navin Jain. The said expert issued

an opinion dated 17th June 2020, wherein it was opined that the net

loss suffered by the claimant was in the sum of Rs. 8,37,86,320/-. It is

pertinent to note that through the said opinion, the Insurance

company disregarded the claim assessed by its surveyor. However,

the said opinion was not tendered to the claimant, and the Insurance

company offered only an amount of Rs.8,36,68,320/-. The claimant

executed a settlement voucher on 26 th June 2020, accepting the

aforesaid sum under protest and without prejudice to their rights.

Eventually, the claimant initiated arbitral proceedings and sought an

award in terms of the surveyor’s assessment of loss in his report of 8 th

November 2019. The Insurance Company led evidence through its

Deputy Manager and through Mr Navin Jain, who was the expert who

submitted the said report dated 17 th June 2020. It is settled law that

an application under Section 34 of the Arbitration Act to set aside an

arbitral award is not akin to an appeal, and therefore, the Court, while

examining the arbitral award, is not required to reappreciate the

evidence.

7/24

::: Uploaded on – 23/04/2026 ::: Downloaded on – 23/04/2026 23:29:33 :::

901-CARBPL-6069-2023*.docx

11. An arbitral award can be set aside only if it is against the public

policy of India, in contravention of the fundamental policy of Indian

law, or in conflict with the most basic notions of morality or justice. In

PSA Sical Terminals Pvt. Ltd. V/s. Board of Trustees, 1 the Hon’ble

Apex Court has held that an arbitral award can be set aside only if the

award suffers from a patent illegality on the face of the award and

which goes to the root of the matter. It is also held that while

examining an award, the Court is not expected to act as an Appellate

Court and reappreciate evidence. In the present case, all the grounds

raised in this petition amount to a reappreciation of the evidence

which has already been considered by the Arbitral Tribunal in the

totality of the facts and circumstances. This cannot be a ground for

interference under Section 34 of the Arbitration Act.

12. The Insurance Company, not satisfied with the surveyor’s

reports, proceeded to appoint an expert who reduced the loss

assessment. Although Section 64 UM of the Insurance Act gives a

right to the insurance company to settle a claim at an amount

different from the one assessed by the surveyor, all the same, the

insurance company cannot keep insisting on multiple survey reports

or appoint more than one surveyor only to get a tailor-made report. In

1
(2023) 15 SCC 781

8/24

::: Uploaded on – 23/04/2026 ::: Downloaded on – 23/04/2026 23:29:33 :::
901-CARBPL-6069-2023*.docx

Sri Venkateswara Syndicate V/s. Oriental Insurance Co. 2, Hon’ble

Supreme Court has held that while an insurance company may be

entitled to appoint more than one surveyor, they cannot appoint more

than one surveyor only to get a tailor-made report. If, after receiving a

survey report, an insurance company disagrees with it and wishes to

appoint another surveyor, it must record valid reasons and thereafter

appoint the second surveyor. In the present case, the appointment of

an expert itself is contrary to the law. Section 64 UM of the Insurance

Act only gives the right to appoint a surveyor. Regulation 13(p) of the

Insurance Regulatory and Development Authority of India (Insurance

Surveyors and Loss Assessors) Regulations, 2015 gives the right to

appoint an expert only to the surveyor. Thus, if the surveyor, while

discharging his/her duty, feels that an expert opinion is required, then

he/she is entitled to appoint an expert and avail such expert opinion.

However, the insurance company cannot appoint such an expert.

13. Regulation 15(9) of the Insurance Regulatory Development

Authority of India (Protection of Policyholders Interests) Regulations,

2017 provides that, if the amount admitted as payable by the insurer

is less than the amount claimed, the insurer shall inform the insured

in writing of the basis of settlement. In the present case, admittedly,

2
(2009) 8 SCC 507

9/24

::: Uploaded on – 23/04/2026 ::: Downloaded on – 23/04/2026 23:29:33 :::
901-CARBPL-6069-2023*.docx

this has not been done, and in fact, the Insurance Company did not

even inform the claimant about the appointment of Mr Navin Jain as

an expert. When a Court or a judicial forum is confronted with two or

more expert opinions, the court has to consider the soundness of the

reasons given by the expert to form its own opinion on the matters in

question. In the present case, the Arbitral Tribunal has held that the

surveyor, Mr Vijaykumar Saokar, conducted multiple visits to examine

the machine, whereas the cross-examination of Mr Navin Jain

revealed that he had not physically inspected the machine. In these

circumstances, the Arbitral Tribunal rightly held that Mr Navin Jain

cannot be a competent witness in law to technically rebut Mr Saokar’s

report, who had actually conducted multiple site visits and inspected

the damaged machine before issuing the report.

14. Admittedly, no appointment letter was issued to Mr Navin Jain,

which would indicate the scope of his work. The Arbitral Tribunal has

recorded that Mr Navin Jain was appointed only to address the

aspect of depreciation. However, a bare perusal of the expert opinion

dated 17th June 2020, given by him, clearly indicates that, apart from

depreciation, he has opined on the “replacement value of similar type

of machines,” which was clearly not within the scope of his work, as

per the evidence of the Insurance Company. Mr Navin Jain has

10/24

::: Uploaded on – 23/04/2026 ::: Downloaded on – 23/04/2026 23:29:33 :::
901-CARBPL-6069-2023*.docx

compared the technical parameters of the damaged machine and an

upgraded model, and, observing a 20% difference, has concluded

that the price difference between the two models would also be 20%.

There is no rationale in his opinion for why the technical parameters

are directly comparable to the price of the machine.

15. Insofar as the interest is concerned, the Arbitral Tribunal has

held that since there was an inordinate delay by the Insurance

Company in making payment to the claimant, interest is ordered to be

paid at the rate of 18% per annum. The grant of interest is in the

discretion of the Arbitral Tribunal, which is ordinarily not interfered

with. The finding of substantial delay on the part of the Insurance

Company in paying the Claimant is a factual finding supported by

evidence. Thus, the award of interest, by the Arbitral Tribunal, on the

ground of substantial delay is reasonable, and thus the aspect of

interest ought not to be interfered with.

16. In PAM Developers Pvt. Ltd. Vs. State of West Bengal 3, the

Hon’ble Supreme Court, while construing Section 31(7) of the

Arbitration Act, held that in the event the contract is silent as regards

the interest, the Arbitral Tribunal has the power to award the same. It

is further held that the grant of pre-reference interest is governed by
3
(2024) 10 SCC 715

11/24

::: Uploaded on – 23/04/2026 ::: Downloaded on – 23/04/2026 23:29:33 :::
901-CARBPL-6069-2023*.docx

substantive law. In Sayeed Ahmed and Company vs. State of Uttar

Pradesh and Others4, the Hon’ble Supreme Court has held that the

court should not alter the rate of interest granted by the Arbitral

Tribunal unless the award of interest is found to be unwarranted. In

the present case, the Arbitral Tribunal has recorded a reason of

inordinate delay in making the payment for awarding interest. The

Supreme Court has further held that an Arbitral Tribunal may award

interest at such a rate as it deems reasonable for the whole or any

part of the period unless otherwise agreed by the parties. In the

present case, the insurance policy does not prohibit the grant of

interest. Therefore, the present petition ought not to be entertained by

this court.

CONSIDERATION OF THE SUBMISSIONS AND ANALYSIS:

17. I have carefully examined the pleadings, documents, and

evidence with the assistance of the learned counsel for the parties.

The basic facts regarding the nature of the policy and the terms and

conditions of the policy are not in dispute. The claimant had

immediately intimated to the Insurance Company of the fire incident

and the damages and loss suffered by the claimant. The reports of

the surveyor appointed by the Insurance Company provide for the
4
(2009) 12 SCC 26

12/24

::: Uploaded on – 23/04/2026 ::: Downloaded on – 23/04/2026 23:29:33 :::
901-CARBPL-6069-2023*.docx

particulars of the damage to the insured machinery and the loss

suffered by the claimant. The record shows that all documents and

information requested by the surveyor and the Insurance Company

were provided by the claimant. The particulars of the reports

submitted by the surveyor and the final assessment made by the

surveyor are rightly pointed out by the learned counsel for the

claimant, which are recorded in the above paragraphs.

18. On 8th November 2019, a final survey report was issued for an

assessment of Rs. 11,49,33,500/-. The record shows that the

Insurance Company made repeated requests to reassess the

amount. It is alleged that on 2 nd October 2020, the Insurance

Company instructed the surveyor to issue an addendum report

without intimation to the claimant. The record shows that after six

months the surveyor issued an addendum report dated 7 th January

2020 and reduced the amount of loss assessment as per the final

survey report supplied to the claimant. Thereafter, again without the

claimant’s consent, a second addendum report was issued on 20 th

February 2020, further reducing the assessment of the loss. Despite

repeated requests, the Insurance company did not settle the claim,

and the payment was delayed. Ultimately, only Rs. 8,37,86,320/- was

approved on 25th June 2020 as against the final assessment report

13/24

::: Uploaded on – 23/04/2026 ::: Downloaded on – 23/04/2026 23:29:33 :::
901-CARBPL-6069-2023*.docx

for Rs 11,30,19,602/-. Thus, after a period of more than ten months

from the date of loss and after a period of almost eight months from

the final survey report issued by the surveyor appointed by the

Insurance Company, the claim was approved on the lower side.

19. After examining the evidence on record, the Tribunal concluded

that there was no justification to reduce the assessment made by the

surveyor appointed by the Insurance Company. It is held that the

Insurance Company failed to examine the surveyor to prove that his

assessment was wrong. The arguments made on behalf of the

Insurance Company on the depreciation factor are rightly discarded

by the Tribunal by referring to the admissions given by the Insurance

company’s witness and on the ground that the surveyor was not

examined to refute his technical assessment in the final report. The

expert opinion’s report is also rightly not accepted by the Tribunal. It

is held that the expert was appointed without any intimation to the

claimant. Although the Insurance Company contended that the expert

was appointed on the aspect of depreciation, the Tribunal, on an

appreciation of the pleadings and evidence, held that the expert had

given an opinion not only on depreciation but also on improvement,

salvage, and other technical factors. Nothing is shown in this petition

that the appointment of an expert by the Insurance company is

14/24

::: Uploaded on – 23/04/2026 ::: Downloaded on – 23/04/2026 23:29:33 :::
901-CARBPL-6069-2023*.docx

permissible for independently assessing the loss and discarding the

surveyor’s assessment, which is as per the applicable rules.

20. The Tribunal has also discussed in detail the oral evidence of

the expert, i.e. Mr. Navin Jain and held that he did not possess the

technical expertise required to assess the technical assessment done

by the surveyor. Admittedly, the expert’s opinion was prepared

without any physical inspection of the machine. The Tribunal rightly

discarded the expert’s opinion and his oral evidence as he admitted

that he had no basis for considering the 3.5% deduction in the value

of the machine. Thus, the expert opinion is correctly held as contrary

to Section 64 UM of the Insurance Act. The tribunal has further

examined the surveyor’s assessment reports in detail and found them

to be in accordance with the record produced by the claimant. The

Insurance Company discarded the surveyor’s final assessment report

only by referring to the expert opinion, which was obtained without

any intimation to the claimant.

21. The Tribunal held that the claimant had rightly relied upon the

Insurance Company’s Divisional Office, noting that it accepted the

report dated 8th November 2019 of the surveyor to be correct. The

Tribunal also held that admittedly, the Insurance company had not

even issued an appointment letter to Mr Navin Jain, which throws any

15/24

::: Uploaded on – 23/04/2026 ::: Downloaded on – 23/04/2026 23:29:33 :::
901-CARBPL-6069-2023*.docx

light on the scope of his assignment. The Insurance Company had

not recorded any valid reasons for appointing the expert after the

surveyor had submitted the final assessment report, and the expert’s

appointment was made without any intimation to the claimant. The

conduct of the Insurance Company in the present case, in repeatedly

calling upon the surveyor to submit an addendum to the surveyor’s

report and then relying upon the expert’s opinion obtained without

intimation to the claimant, is contrary to the law laid down by the

Hon’ble Apex Court in Sri Venkateswara Syndicate. In the said

decision, the Apex Court discussed the Insurance Surveyors and

Loss Assessors (Licensing, Professional Requirements and Code of

Conduct) Regulations, 2000, formulated by the Insurance Regulatory

Authority, which govern the licensing and work of surveyors. It is held

that the insurance company cannot continue appointing surveyors

one after another to obtain a tailor-made report to the satisfaction of

the officer concerned in the insurance company. It is also held that if,

for any reason, the surveyors’ report is not acceptable, the insurer

must provide a valid reason for not accepting it. With reference to the

scheme of Section 64-UM of the Insurance Act, it held that there is no

prohibition in the Insurance Act for the appointment of a second

surveyor by the insurance company, but while doing so, the

16/24

::: Uploaded on – 23/04/2026 ::: Downloaded on – 23/04/2026 23:29:33 :::
901-CARBPL-6069-2023*.docx

insurance company has to give satisfactory reasons for not accepting

the report of the first surveyor and the need to appoint a second

surveyor.

22. On the aspect of grant of interest, it is held in the facts of Sri

Venkateswara Syndicate that the insurer, after rejecting the

assessments of the surveyor and the joint surveyor, has accepted the

assessment made by the chartered accountant. Therefore, the

allegation of an unnecessary three-year delay was not accepted. It is

held that once the insurer has reached a settlement, he should make

the payment at the earliest and if further delay is caused by the

insurer in making the payment then he should be made liable to pay

the interest on the amount settled, as compensation at the current

rate of interest till the payment is made, as it has deprived the insured

from using his money for which he is legitimately entitled.

23. In Sayeed Ahmed and Company, before the Hon’ble Apex

Court, the arbitrator had awarded interest at the rate of 18% per

annum on the amount found due on finalisation of the final bill and

12% per annum on the security deposit amount that was found to be

refunded. The Hon’ble Apex Court held that the award of interest by

the arbitrator was not contrary to Section 31(7)( b) of the Act. It is held

that unless the award of interest is found to be unwarranted for

17/24

::: Uploaded on – 23/04/2026 ::: Downloaded on – 23/04/2026 23:29:33 :::
901-CARBPL-6069-2023*.docx

reasons to be recorded, the Court should not alter the rate of interest

awarded by the arbitrator. The reduction in the rate of interest by the

High Court was found to be without any reasons being recorded;

therefore, it was held to be unsustainable.

24. In PAM Developers Pvt. Ltd., the Hon’ble Apex Court held that

Section 31(7)(a) of the 1996 Act provides pre-reference and

pendente lite interest, and it sanctifies party autonomy and restricts

the power to grant pre-reference and pendente lite interest the

moment the agreement bars payment of interest, even if it is not a

specific bar against the arbitrator. It is further held that the arbitrator’s

power to award pre-reference and pendente lite interest is not

restricted when the agreement is silent on whether interest may be

awarded.

25. In the present case, the Tribunal has discussed Regulation 9(6)

of the IRDA (Protection of Policy Holders Interest) Regulations 2002,

which provides that the claimant is entitled to interest on the delayed

payment in settlement of their claim @ 2% above the prevailing

lending rate for any delay beyond 90 days from the date of the

appointment of the surveyor. The Tribunal further observed that the

date of loss was 26th August 2019; the surveyor was appointed, who

visited the site on 29th August 2019; the final survey report was

18/24

::: Uploaded on – 23/04/2026 ::: Downloaded on – 23/04/2026 23:29:33 :::
901-CARBPL-6069-2023*.docx

issued on 8th November 2019; and the date of the discharge voucher

is 9th July 2020. Therefore, the tribunal held that there was a

substantial delay of 11 months from the date of appointment of the

surveyor till the date of making payment under the discharge

voucher. The Tribunal referred to the particulars of the claim, in which

the claimant has claimed interest on the principal amount at 18%

from 29th November 2019, i.e., three months from the date of

appointment of the surveyor, till 9th July 2020, being the date of

payment under the discharge voucher. The Tribunal has further

referred to the particulars of the claim, where the claimant has prayed

for further interest at 18% per annum on the principal amount from 9 th

July 2020, that is, the date of payment under the discharge voucher,

till 11th March 2021, being the date of filing of the statement of claim.

26. In the present case, the principal amount is the difference

between the amount assessed by the surveyor in the final survey

report and the amount settled by the Insurance Company, which is

lower. The Tribunal further referred to the particulars of the claim, in

which the total amount of Rs. 3,73,88,392/- is claimed by the

claimants, which is the principal amount plus interest from the date of

payment under the discharge voucher till the date of filing of the

statement of claim. The Tribunal has granted the claim of Rs.

19/24

::: Uploaded on – 23/04/2026 ::: Downloaded on – 23/04/2026 23:29:33 :::

901-CARBPL-6069-2023*.docx

3,73,88,392/- together with further interest @ 18% from the date of

the statement of claim till realisation. Therefore, the Tribunal has

allowed the prayer for interest on the principal amount from the date

of the discharge voucher until the date of filing the claim, and for

further interest from the date of the statement of claim until realisation

of the amount. Hence, it was argued on behalf of the Insurance

Company that the grant of such interest is excessive and contrary to

section 3(1) of the Interest Act, which mandates that interest should

not exceed the current lending rate unless supported by a usage of

trade or contract, which is absent in the present case.

27. However, the issue of grant of interest as per the Regulation

9(6) of the IRDA (Protection of Policy Holders Interest) Regulations

2002, which provides that the claimant is entitled to interest on the

delayed payment in settlement of their claim @ 2% above the

prevailing lending rate for any delay beyond 90 days from the date of

the appointment of the surveyor, is not necessary. As discussed in

the above paragraph, the Tribunal has not granted any interest from

the date of appointment of the surveyor till settlement of the claim.

What is granted is the interest on the principal amount (the difference

between the amount assessed by the surveyor in the final survey

report and the amount settled by the Insurance Company, which is

20/24

::: Uploaded on – 23/04/2026 ::: Downloaded on – 23/04/2026 23:29:33 :::
901-CARBPL-6069-2023*.docx

lower) from the date of settlement of the claim ( the date of Discharge

Voucher accepted by the claimant under protest) till filing of the

statement of claim and the further interest.

28. In the present case, inordinate delay by the Insurance

Company in making payment to the claimant is considered as an

important factor by the Arbitral Tribunal, which cannot be interfered

with in the absence of any valid ground to challenge the conclusions

recorded by the Tribunal. The finding of substantial delay on the part

of the Insurance Company in paying the claimant is a factual finding

recorded by the Tribunal, which is also supported by evidence. The

fire incident is of 26th August 2019, and the claimant immediately

informed the Insurance Company on the same day. The Insurance

Company appointed a surveyor who visited the site on 29 th August

2019. A preliminary report was submitted on 1 st September 2019. A

final report was issued on 8 th November 2019. Thereafter, the

Insurance company raised queries, and the claimant satisfied all the

surveyor’s requisitions, after which the surveyor issued an Addendum

Report on 7th January 2020. Thereafter, the second Addendum

Report was issued on 20th February 2020.

29. However, the claimant was not paid. The claimant addressed

emails requesting the Insurance Company to release payments and

21/24

::: Uploaded on – 23/04/2026 ::: Downloaded on – 23/04/2026 23:29:33 :::
901-CARBPL-6069-2023*.docx

informed that the claimant was facing difficulties as it had received

notices from their lender banks. The claimant also forwarded copies

of the notices and intimated that it was unable to meet its working

capital requirement due to the loss suffered, and thus requested the

release of the payment. The claimant issued emails and reminder

emails on 11th March 2020, 19th March 2020, 13th April 2020, 13th May

2020 and 27th May 2020. The claimant again requested to settle the

claim by issuing emails on 8th June 2020 and 15th June 2020. Finally,

the insurance company approved the amount on 25 th June 2020, but

on a very low side. However, the claimant accepted the amount

under protest and sent an email to the insurance company on 17 th

July 2020, requesting that they provide the final workings for the

amounts approved by the insurance company.

30. Based on the evidence on record, it was a considered view of

the Tribunal that the claimant was entitled to interest on the ground of

substantial delay caused by the Insurance Company to settle the

claim and make payment. Hence, the Tribunal has granted interest at

the rate of 18% per annum, as prayed by the claimant in terms of the

particulars of the claim. The Apex Court in PSA Sical Terminals Pvt.

Ltd. held that, while examining a challenge to an award, the Court

cannot act as an Appellate Court and reappreciate evidence.

22/24

::: Uploaded on – 23/04/2026 ::: Downloaded on – 23/04/2026 23:29:33 :::

901-CARBPL-6069-2023*.docx

31. I find substance in the submissions made by the learned

counsel for the claimant that any interference in the findings recorded

by the Tribunal would amount to reappreciating the evidence on

record, which is not permissible under Section 34 of the Arbitration

Act. The law regarding the permissibility of interference under Section

34 of the Arbitration Act is no longer res integra. The legal principle is

well-established that an arbitral award can be interfered with under

Section 34 of the Arbitration Act only on the grounds of judicial

approach, patent illegality, breach of the principles of natural justice,

contravention of law, and perversity. In view of the well-established

legal principles, the Section 34 Court must not lightly interfere with

arbitral awards in a casual and cavalier manner, unless a conclusion

can be drawn that the award is perverse and it goes to the root of the

matter. It is also well-settled that the mandate under Section 34 is to

respect the finality of the arbitral award and the party autonomy to get

their dispute adjudicated by an alternative forum; otherwise, the

alternative dispute resolution opted for would stand frustrated.

32. In the present case, the arguments raised on behalf of the

petitioner would amount to a reappreciation of the evidence. As

discussed in the aforesaid paragraphs, the Tribunal has considered

the entire evidence and recorded reasons to grant the claim. None of

23/24

::: Uploaded on – 23/04/2026 ::: Downloaded on – 23/04/2026 23:29:33 :::
901-CARBPL-6069-2023*.docx

the grounds raised by the petitioner would be covered under the

scope of interference under Section 34. Hence, in my view, by

applying the standards as set out in the various decisions as

discussed above, the arbitral award cannot be interfered with under

Section 34 of the Arbitration Act.

33. Hence, for the reasons recorded above, the Arbitration Petition

is rejected.

[GAURI GODSE, J.]

24/24

::: Uploaded on – 23/04/2026 ::: Downloaded on – 23/04/2026 23:29:33 :::



Source link