National Technical Research … vs M/S Corporate Infotech Private Limited on 1 April, 2026

    0
    46
    ADVERTISEMENT

    Delhi High Court

    National Technical Research … vs M/S Corporate Infotech Private Limited on 1 April, 2026

                      $~
                      *  IN THE HIGH COURT OF DELHI AT NEW DELHI
                      %                                    Judgment reserved on: 05.02.2026
                                                        Judgment pronounced on: 01.04.2026
    
                      +         O.M.P. (COMM) 378/2024, I.A. 38340/2024 (Stay) & I.A.
                                10172/2025 (Dir.)
                                NATIONAL TECHNICAL RESEARCH ORGANISATION
                                                                              .....Petitioner
                                                  Through: Mr. Vikramjit Banerjee, ASG
                                                           with Ms. Arunima Dwivedi
                                                           CGSC, Ms. Pinki Pawar GP,
                                                           Ms. Himanshi Singh and Mr.
                                                           Abhishek, Advocates, Mr. Amit
                                                           Kumar (NTRO) and Mr.
                                                           Bhaskhar Ghosh (NTRO).
                                                  versus
                                M/S CORPORATE INFOTECH PRIVATE LIMITED
                                                                          .....Respondent
                                                  Through: Mr. Amit Sibal, Senior
                                                           Advocate along with Mr.
                                                           Bharat Arora and Mr. Gourav
                                                           Arora, Advocates.
                                CORAM:
                                HON'BLE MR. JUSTICE HARISH VAIDYANATHAN
                                SHANKAR
                                                   JUDGMENT
    

    HARISH VAIDYANATHAN SHANKAR, J.

    1. This Petition has been filed under Section 34 of the Arbitration
    and Conciliation Act, 19961, assailing the Arbitral Award dated
    02.04.20242 passed by the learned Sole Arbitrator in the arbitration
    proceedings titled as “M/S Corporate Infotech Pvt. Ltd. v. National
    Technical Research Organisation
    “. By the Impugned Award, the
    1
    Act
    2
    Impugned Award
    Signature Not Verified
    Digitally Signed
    By:VARNIKA O.M.P. (COMM) 378/2024 Page 1 of 38
    Signing Date:03.04.2026
    14:23:38
    learned Arbitral Tribunal3 substantially allowed the claims of the
    Respondent herein.

    SPONSORED

    BRIEF FACTS:

    2. The Petitioner, National Technical Research Organisation4,
    floated a limited tender enquiry bearing No. NTRO/CPC/07/2017
    dated 09.11.2017 for the supply, installation and integration of a
    network solution for the establishment of a secure intranet
    infrastructure at various locations across India.

    3. Pursuant to the tender process, a contract dated 10.08.20185
    was executed between NTRO and the Respondent, for the supply,
    installation and integration of a secure and reliable network
    infrastructure across twenty-three (23) locations, including the
    establishment of a wide area network and local area networks,
    together with associated training, testing and support obligations.

    4. The said contract also provides for the payment terms between
    the parties, which are to be made in different stages, and it also
    contemplated the provision of a comprehensive warranty and
    incorporated clauses relating to performance milestones, testing
    procedures, liquidated damages, and performance security.

    5. Under the contractual framework, the Respondent was required
    to furnish a Performance Bank Guarantee6 equivalent to ten (10)
    per cent of the contract value within thirty (30) days of signing the
    contract, valid up to sixty (60) days beyond the completion of the
    warranty period and to complete the project within the stipulated

    3
    Tribunal
    4
    NTRO
    5
    Contract
    6
    PBG
    Signature Not Verified
    Digitally Signed
    By:VARNIKA O.M.P. (COMM) 378/2024 Page 2 of 38
    Signing Date:03.04.2026
    14:23:38
    timeline of twenty-eight (28) weeks, i.e. 20.02.2019. The contract
    further envisaged completion of Acceptance Testing procedures7
    and On-Site Acceptance Tests8, upon successful completion of which
    the system would be treated as fully commissioned, and the warranty
    obligations would commence.

    6. The Respondent furnished the PBG to the Petitioner after the
    execution of the contract, leading to a delay of eighteen (18) days.

    Besides, during the course of execution of the contract, the
    Respondent completed the supply of equipment with a delay of
    twenty-four (24) weeks, and thereby, the Petitioner, as per the
    contractual terms, released seventy (70) per cent of the payment to the
    Respondent.

    7. It is not in dispute that, in the backdrop of circumstances
    prevailing during the COVID-19 pandemic, the payment terms inter
    se the parties were amended, whereby the remaining 30% of the
    contract price was bifurcated into two components, namely 20% and
    10%, to be released upon satisfaction of the Respondent. Pursuant
    thereto, the amount constituting twenty (20) per cent was released to
    the Respondent, and the only amount remaining payable to the
    Respondent was ten (10) per cent.

    8. The parties thereafter engaged in the process of finalisation of
    ATPs, following which phases of OSAT were conducted. During this
    period, issues arose between the parties regarding the progress of
    testing, operational readiness of the system, attribution of delays, and
    compliance with contractual obligations, including renewal of licences

    7
    ATP
    8
    OSAT
    Signature Not Verified
    Digitally Signed
    By:VARNIKA O.M.P. (COMM) 378/2024 Page 3 of 38
    Signing Date:03.04.2026
    14:23:38
    and provision of support services, with each party attributing default
    and delay to the other.

    9. Subsequently, the Petitioner, vide Legal Notice dated
    08.07.2022, addressed to the Respondent, crystallised the disputes
    inter alia in relation to: (i) attribution of delay in completion of the
    project and testing phases; (ii) the entitlement of NTRO to levy
    Liquidated Damages9 (iii) the commencement of the warranty
    period; (iv) the release and continued validity of the PBG; and (v)
    entitlement to the balance payments. In this backdrop, the Petitioner,
    in accordance with the contractual terms, withheld the ten (10) per
    cent balance payment, inter alia, on account of LD and the
    subsistence of the PBG.

    10. The Respondent, in its reply dated 20.07.2022 to the said
    notice, called upon the Petitioner to remit the remaining ten (10) per
    cent of the contract price allegedly due and payable, and further
    sought return of the PBG.

    11. Aggrieved thereby, the Respondent approached this Court by
    way of preferring a petition, bearing OMP.(I)(COMM.) 228/2022,
    under Section 9 of the Act, wherein this Court vide its Order dated
    27.07.2022, granted interim protection in favour of the Respondent
    herein, subject to extension of the PBG for a further six months.

    12. Thereafter, vide Order dated 24.11.2022, this Court directed
    that the said Section 9 petition be treated as an application under
    Section 17 of the Act and proceeded to appoint a learned Sole
    Arbitrator, Justice (Retd.) R.K. Gauba, to adjudicate the disputes inter
    se the parties.

    9

    LD
    Signature Not Verified
    Digitally Signed
    By:VARNIKA O.M.P. (COMM) 378/2024 Page 4 of 38
    Signing Date:03.04.2026
    14:23:38

    13. Pursuant to the constitution of the learned Tribunal, both parties
    filed their respective pleadings, including the Statement of Claim,
    Statement of Defence, and documents in support thereof. Evidence
    was led by the Respondent, whereas the Petitioner chose not to lead
    any evidence.

    14. Vide Award dated 02.04.2024, the learned Tribunal adjudicated
    the disputes inter se the parties, including claims pertaining to
    payments, levy of LD, commencement of the warranty period, and
    other contractual obligations.

    15. Aggrieved by the said Award, the Petitioner has preferred the
    present Petition under Section 34 of the Act, assailing the Impugned
    Award on various grounds.

    CONTENTIONS ON BEHALF OF THE PETITIONER/ NTRO:

    16. Learned Additional Solicitor General10 appearing for the
    Petitioner would submit that the Impugned Award is liable to be set
    aside as it suffers from patent illegality and is contrary to the terms of
    the contract as well as the evidence on record.

    17. It would be contended that the learned Tribunal failed to
    properly appreciate the contractual framework governing timelines,
    testing requirements and consequences of delay, and has returned
    findings which are contrary to the material placed before it.

    18. Learned ASG appearing for the Petitioner would further submit
    that the learned Tribunal erred in holding that the delay in execution
    of the project was attributable to both parties. As per the learned ASG,
    the delay was occasioned primarily on account of the Respondent’s

    10
    ASG
    Signature Not Verified
    Digitally Signed
    By:VARNIKA O.M.P. (COMM) 378/2024 Page 5 of 38
    Signing Date:03.04.2026
    14:23:38
    failure to supply equipment, complete installation, and successfully
    demonstrate the system in accordance with contractual requirements.

    19. Learned ASG appearing for the Petitioner would contend that
    the learned Tribunal has failed to appreciate the admission of CW-1,
    who unequivocally stated that media links could not be utilised
    without the supply of routers. On this basis, it would be argued that
    since routers had not been delivered at the relevant time, the absence
    of media connectivity cannot be treated as a contributing factor to
    delay, and consequently, the delay could not have been attributed to
    both parties.

    20. According to the learned ASG, this admission establishes that
    commissioning was impossible in the absence of routers, and
    therefore, the entire delay ought to have been fastened upon the
    Claimant alone, rendering the learned Tribunal’s finding of shared
    responsibility perverse and contrary to the evidence on record.

    21. It is further contended that the learned Tribunal incorrectly
    determined the date of completion of OSAT and consequently erred in
    fixing the commencement of the warranty period. According to the
    learned ASG, successful completion of OSAT never occurred in terms
    of the contract, and therefore, the warranty could not have been
    treated as having commenced.

    22. Learned ASG appearing for the Petitioner would further submit
    that the learned Tribunal failed to properly appreciate the contractual
    framework, which expressly entitled NTRO to levy LD on account of
    delay and to retain the PBG as security for due performance. It would
    be contended that the rejection of the Petitioner’s claim for LD is
    contrary to the express terms of the contract and amounts to an

    Signature Not Verified
    Digitally Signed
    By:VARNIKA O.M.P. (COMM) 378/2024 Page 6 of 38
    Signing Date:03.04.2026
    14:23:38
    erroneous interpretation thereof. In support of this submission,
    reliance is placed upon the decision of the Hon’ble Supreme Court in
    Consolidated Construction Consortium Limited v. Software
    Technology Parks of India11
    to contend that contractual stipulations
    relating to LD must ordinarily be given effect to in accordance with
    their terms.

    23. Learned ASG appearing for the Petitioner would further
    contend that the learned Tribunal has erred in its findings relating to
    the PBG. It would be submitted that the learned Tribunal has wrongly
    treated the issue of the PBG as consequential to its findings on LD
    and attribution of delay. According to the learned ASG, the
    contractual stipulation governing the PBG operates independently and
    entitles NTRO to retain or invoke the same as security for due
    performance of contractual obligations.

    24. Learned ASG appearing for the Petitioner would also submit
    that the learned Tribunal overlooked material evidence regarding non-
    renewal of licences and alleged deficiencies in performance, which
    demonstrated continued non-compliance by the Respondent of its
    contractual obligations.

    25. It would further be contended that the learned Tribunal erred in
    directing the release of the PBG and in allowing claims for payment,
    and that the conclusions reached amount to rewriting the contract and
    ignoring binding contractual stipulations.

    26. Learned ASG appearing for the Petitioner would further
    contend that the learned Tribunal has failed to properly appreciate the
    admitted delay in completion of the project. Even if, arguendo, the

    11
    (2025) 7 SCC 757
    Signature Not Verified
    Digitally Signed
    By:VARNIKA O.M.P. (COMM) 378/2024 Page 7 of 38
    Signing Date:03.04.2026
    14:23:38
    date of 17.03.2020 is accepted as the relevant completion date, the
    delay of several weeks beyond the stipulated contractual timeline
    renders the Respondent liable for the levy of LD in terms of the
    contract.

    27. Learned ASG appearing for the Petitioner would submit that the
    learned Tribunal, despite noting the delay, has erroneously declined to
    permit levy of LD and has instead proceeded to award the balance
    consideration amounting to Rs. 7,14,61,511/- as due and payable as on
    17.03.2020. According to the learned ASG, such a conclusion is
    inconsistent with the contractual framework governing delay and LD
    and overlooks the consequence of breach expressly agreed between
    the parties.

    28. It would be contended that once a delay beyond the contractual
    completion period stood established, the entitlement of the Petitioner
    to impose LD arose automatically under the contract, and the learned
    Tribunal’s refusal to give effect to the same amounts to an erroneous
    interpretation of the contract and non-consideration of material facts
    on record.

    29. Learned ASG appearing for the Petitioner additionally
    questions the award of interest as being excessive and unwarranted in
    the facts of the case and places reliance upon the ruling of the Hon’ble
    Apex Court in ONGC v. Saw Pipes12, to contend that the Impugned
    Award is patently illegal and contrary to the terms of the contract.

    30. On the aforesaid grounds, it would be urged by the learned
    ASG appearing for the Petitioner that the Impugned Award warrants
    interference under Section 34 of the Act.

    12

    (2003) 5 SCC 705
    Signature Not Verified
    Digitally Signed
    By:VARNIKA O.M.P. (COMM) 378/2024 Page 8 of 38
    Signing Date:03.04.2026
    14:23:38
    CONTENTIONS ON BEHALF OF THE RESPONDENT:

    31. Per contra, learned senior counsel appearing for the
    Respondent would submit that the present petition is nothing but an
    attempt to re-agitate factual issues and to seek a re-appreciation of
    evidence, which is impermissible in proceedings under Section 34 of
    the Act.

    32. It would be contended that the learned Tribunal has undertaken
    a detailed examination of the contractual provisions, correspondence
    exchanged between the parties, evidence led during the proceedings,
    and the conduct of the parties, and has returned a reasoned Award
    which does not warrant interference.

    33. Learned senior counsel appearing for the Respondent would
    submit that issues relating to attribution of delay, progress of testing
    phases, operational readiness of the system and interpretation of
    contractual provisions were all examined by the learned Tribunal,
    which concluded that responsibility for delay could not be attributed
    exclusively to one party.

    34. It would further be contended that the learned Tribunal rightly
    considered the operationalisation of the system, including the handing
    over of credentials and conduct of testing, and arrived at a plausible
    conclusion regarding completion of contractual milestones and
    commencement of warranty obligations.

    35. It would also be submitted that the Petitioner did not lead any
    evidence before the learned Tribunal. Despite having raised serious
    allegations regarding delay, non-compliance, and deficiencies in
    performance, the Petitioner chose not to examine any witness or
    adduce independent oral evidence in support of its assertions. In such
    Signature Not Verified
    Digitally Signed
    By:VARNIKA O.M.P. (COMM) 378/2024 Page 9 of 38
    Signing Date:03.04.2026
    14:23:38
    circumstances, the learned Tribunal was constrained to decide the
    issues on the basis of the pleadings, documentary record, and the
    evidence led by the Respondent.

    36. It would be submitted that the Petitioner, having elected not to
    substantiate its case by leading evidence, cannot now assail the factual
    findings of the learned Tribunal or seek a re-appreciation of the
    evidentiary record under the limited jurisdiction of Section 34 of the
    Act.

    37. Learned senior counsel appearing for the Respondent would
    submit that the learned Tribunal rightly rejected the Petitioner’s claim
    for levy of liquidated damages, having found that such levy was not
    justified in the factual matrix of the case, particularly in view of the
    shared nature of delays. It would be contended that the learned
    Tribunal correctly applied the settled principles governing liquidated
    damages and reasonable compensation.

    38. In this regard, reliance would be placed upon the judgments of
    the Hon’ble Supreme Court in Kailash Nath Associates v. Delhi
    Development Authority & Anr13
    and the decision of this Court in
    Vishal Engineers Builders v. Indian Oil Corporation Limited14 to
    submit that even where a contract provides for liquidated damages,
    compensation must be reasonable and cannot be imposed
    mechanically in the absence of established loss or breach exclusively
    attributable to the contractor.

    39. It would be argued that the findings relating to the PBG and
    payment obligations are based on an interpretation of the contract and

    13
    (2015) 4 SCC 136
    14
    (2011) SCC Online Del 5124
    Signature Not Verified
    Digitally Signed
    By:VARNIKA O.M.P. (COMM) 378/2024 Page 10 of 38
    Signing Date:03.04.2026
    14:23:38
    appreciation of evidence and fall squarely within the jurisdiction of
    the learned Tribunal.

    40. Learned senior counsel appearing for the Respondent would
    further submit that in prayer clauses (c), (d), (e) and (g) of the present
    Petition, the Petitioner seeks, inter alia, imposition of liquidated
    damages, forfeiture of the PBG, and other consequential reliefs.
    However, no such independent counter-claims or substantive reliefs
    were sought by the Petitioner before the learned Arbitrator, and
    therefore, the present Petition is liable to be dismissed.

    41. Learned senior counsel appearing for the Respondent would
    further submit that the Impugned Award does not suffer from any
    perversity, patent illegality or violation of public policy, and that the
    challenge is in substance an appeal on merits, which is not
    maintainable.

    42. On these grounds, learned senior counsel appearing for the
    Respondent would pray for dismissal of the petition.

    ANALYSIS:

    43. This Court has heard the learned counsel appearing on behalf
    of the parties at length and, with their able assistance, carefully
    perused the paper-book and other material documents placed on
    record, including the record of the learned Tribunal, as well as the
    written submissions filed by the respective parties.

    44. At the outset, it is apposite to note that this Court is conscious
    of the limited scope of its jurisdiction while examining an objection
    petition under Section 34 of the Act. The contours of judicial
    intervention in such proceedings have been authoritatively delineated

    Signature Not Verified
    Digitally Signed
    By:VARNIKA O.M.P. (COMM) 378/2024 Page 11 of 38
    Signing Date:03.04.2026
    14:23:38
    and settled by a consistent and evolving line of precedents of the
    Hon’ble Supreme Court.

    45. In this regard, a three-Judge Bench of the Hon’ble Supreme
    Court, after an exhaustive consideration of a catena of earlier
    decisions, in OPG Power Generation (P) Ltd. v. Enexio Power
    Cooling Solutions (India) (P) Ltd.15
    , while dealing with the grounds
    of conflict with the public policy of India and perversity, grounds
    which have also been urged in the present case, made certain
    pertinent observations, which are reproduced hereunder:

    “Relevant legal principles governing a challenge to an arbitral
    award

    30. Before we delve into the issue/sub-issues culled out above, it
    would be useful to have a look at the relevant legal principles
    governing a challenge to an arbitral award. Recourse to a court
    against an arbitral award may be made through an application for
    setting aside such award in accordance with sub-sections (2), (2-A)
    and (3) of Section 34 of the 1996 Act. Sub-section (2) of Section
    34
    has two clauses, (a) and (b). Clause (a) has five sub-clauses
    which are not relevant to the issues raised before us. Insofar as
    clause (b) is concerned, it has two sub-clauses, namely, (i) and (ii).
    Sub-clause (i) of clause (b) is not relevant to the controversy in
    hand. Sub-clause (ii) of clause (b) provides that if the Court finds
    that the arbitral award is in conflict with the public policy of India,
    it may set aside the award.

    Public policy

    31. “Public policy” is a concept not statutorily defined, though it
    has been used in statutes, rules, notification, etc. since long, and is
    also a part of common law. Section 23 of the Contract Act, 1872
    uses the expression by stating that the consideration or object of an
    agreement is lawful, unless, inter alia, opposed to public policy.
    That is, a contract which is opposed to public policy is void.

    *****

    35. In Renusagar Power Co. Ltd. v. General Electric Co., 1994
    Supp (1) SCC 644, a three-Judge Bench of this Court observed
    that the doctrine of public policy is somewhat open–textured and
    flexible. By citing earlier decisions, it was observed that there are
    two conflicting positions which are referred to as the “narrow
    view” and the “broad view”. According to the narrow view, courts
    cannot create new heads of public policy whereas the broad view

    15
    (2025) 2 SCC 417
    Signature Not Verified
    Digitally Signed
    By:VARNIKA O.M.P. (COMM) 378/2024 Page 12 of 38
    Signing Date:03.04.2026
    14:23:38
    countenances judicial law making in these areas. In the field of
    private international law, it was pointed out, courts refuse to apply
    a rule of foreign law or recognise a foreign judgment or a foreign
    arbitral award if it is found that the same is contrary to the public
    policy of the country in which it is sought to be invoked or
    enforced. However, it was clarified, a distinction is to be drawn
    while applying the rule of public policy between a matter governed
    by domestic law and a matter involving conflict of laws. It was
    observed that the application of the doctrine of public policy in the
    field of conflict of laws is more limited than that in the domestic
    law and the courts are slower to invoke public policy in cases
    involving a foreign element than when a purely municipal legal
    issue is involved. It was held that contravention of law alone will
    not attract the bar of public policy, and something more than
    contravention of law is required.

    *****

    37. What is clear from above is that for an award to be against
    public policy of India a mere infraction of the municipal laws of
    India is not enough. There must be, inter alia, infraction of
    fundamental policy of Indian law including a law meant to serve
    public interest or public good.

    *****

    40. In ONGC Ltd. v. Western Geco International Ltd., (2014) 9
    SCC 263, paras 35, 38 & 39, which also related to the period prior
    to the 2015 Amendment of Section 34(2)(b)(ii), a three-Judge
    Bench of this Court, after considering the decision inONGC
    Ltd. v. Saw Pipes Ltd.
    , (2003) 5 SCC 705, without exhaustively
    enumerating the purport of the expression “fundamental policy of
    Indian law”, observed that it would include all such fundamental
    principles as providing a basis for administration of justice and
    enforcement of law in this country. The Court thereafter
    illustratively referred to three fundamental juristic principles,
    namely:

    (a) that in every determination that affects the rights of a citizen or
    leads to any civil consequences, the court or authority or quasi-

    judicial body must adopt a judicial approach, that is, it must act
    bona fide and deal with the subject in a fair, reasonable and
    objective manner and not actuated by any extraneous
    consideration;

    (b) that while determining the rights and obligations of parties the
    court or Tribunal or authority must act in accordance with the
    principles of natural justice and must apply its mind to the
    attendant facts and circumstances while taking a view one way or
    the other; and

    (c) that its decision must not be perverse or so irrational that no
    reasonable person would have arrived at the same.

    41. InAssociate Builders v. DDA, (2015) 3 SCC 49, a two-Judge
    Bench of this Court, held that audi alteram partem principle is
    Signature Not Verified
    Digitally Signed
    By:VARNIKA O.M.P. (COMM) 378/2024 Page 13 of 38
    Signing Date:03.04.2026
    14:23:38
    undoubtedly a fundamental juristic principle in Indian law and is
    enshrined in Sections 18 and 34(2)(a)(iii) of the 1996 Act. In
    addition to the earlier recognised principles forming fundamental
    policy of Indian law, it was held that disregarding:

    (a) orders of superior courts in India; and

    (b) the binding effect of the judgment of a superior court would
    also be regarded as being contrary to the fundamental policy of
    Indian law.

    Further, elaborating upon the third juristic principle (i.e. qua
    perversity), as laid down in ONGC Ltd. v. Western Geco
    International Ltd.
    , (2014) 9 SCC 263, it was observed that where:

    (i) a finding is based on no evidence; or

    (ii) an Arbitral Tribunal takes into account something irrelevant to
    the decision which it arrives at; or

    (iii) ignores vital evidence in arriving at its decision, such decision
    would necessarily be perverse [Associate Builders case, (2015) 3
    SCC 49, para 31].

    To this a caveat was added by observing that when a court applies
    the “public policy test” to an arbitration award, it does not act as a
    court of appeal and, consequently, errors of fact cannot be
    corrected; and a possible view by the arbitrator on facts has
    necessarily to pass muster as the arbitrator is the ultimate master of
    the quantity and quality of evidence to be relied upon when he
    delivers his arbitral award. It was also observed that an award
    based on little evidence or on evidence which does not measure up
    in quality to a trained legal mind would not be held to be invalid on
    that score. Thus, once it is found that the arbitrator’s approach is
    not arbitrary or capricious, it is to be taken as the last word on
    facts.

    The 2015 Amendment in Sections 34 and 48

    42. The aforementioned judicial pronouncements were all prior to
    the 2015 Amendment. Notably, prior to the 2015 Amendment the
    expression “in contravention with the fundamental policy of Indian
    law” was not used by the legislature in either Section 34(2)(b)(ii)
    or Section 48(2)(b). The pre-amended Section 34(2)(b)(ii) and its
    Explanation read:

    *****

    44. By the 2015 Amendment, in place of the old Explanation to
    Section 34(2)(b)(ii), Explanations 1 and 2 were added to remove
    any doubt as to when an arbitral award is in conflict with the public
    policy of India.

    45. At this stage, it would be pertinent to note that we are dealing
    with a case where the application under Section 34 of the 1996 Act
    was filed after the 2015 Amendment, therefore the newly
    substituted/added Explanations would apply [SsangyongEngg. &
    Construction Co. Ltd. v. NHAI, (2019) 15 SCC 131].

    46. The 2015 Amendment adds two Explanations to each of the
    two sections, namely, Section 34(2)(b)(ii) and Section 48(2)(b), in
    Signature Not Verified
    Digitally Signed
    By:VARNIKA O.M.P. (COMM) 378/2024 Page 14 of 38
    Signing Date:03.04.2026
    14:23:38
    place of the earlier Explanation. The significance of the newly
    inserted Explanation 1 in both the sections is two-fold. First, it
    does away with the use of words : (a) “without prejudice to the
    generality of sub-clause (ii)” in the opening part of the pre-

    amended Explanation to Section 34(2)(b)(ii); and (b) “without
    prejudice to the generality of clause (b) of this section” in the
    opening part of the pre-amended Explanation to Section 48(2)(b);
    secondly, it limits the expanse of public policy of India to the three
    specified categories by using the words “only if”.
    Whereas, Explanation 2 lays down the standard for adjudging
    whether there is a contravention with the fundamental policy of
    Indian law by providing that a review on merits of the dispute shall
    not be done. This limits the scope of the enquiry on an application
    under either Section 34(2)(b)(ii) or Section 48(2)(b) of the 1996
    Act.

    47. The 2015 Amendment by inserting sub-section (2-A) in
    Section 34, carves out an additional ground for annulment of an
    arbitral award arising out of arbitrations other than international
    commercial arbitrations. Sub-section (2-A) provides that the Court
    may also set aside an award if that is vitiated by patent illegality
    appearing on the face of the award. This power of the Court is,
    however, circumscribed by the proviso, which states that an award
    shall not be set aside merely on the ground of an erroneous
    application of the law or by reappreciation of evidence.

    48. Explanation 1 to Section 34(2)(b)(ii), specifies that an arbitral
    award is in conflict with the public policy of India, only if:

    (i) the making of the award was induced or affected by fraud or
    corruption or was in violation of Section 75 or Section 81; or

    (ii) it is in contravention with the fundamental policy of Indian
    law; or

    (iii) it is in conflict with the most basic notions of morality or
    justice.

    49. In the instant case, there is no allegation that the making of the
    award was induced or affected by fraud or corruption, or was in
    violation of Section 75 or Section 81. Therefore, we shall confine
    our exercise in assessing as to whether the arbitral award is in
    contravention with the fundamental policy of Indian law, and/or
    whether it conflicts with the most basic notions of morality or
    justice. Additionally, in the light of the provisions of sub-section
    (2-A) of Section 34, we shall examine whether there is any patent
    illegality on the face of the award.

    50. Before undertaking the aforesaid exercise, it would be apposite
    to consider as to how the expressions:

    (a) “in contravention with the fundamental policy of Indian law”;

    (b) “in conflict with the most basic notions of morality or justice”;
    and

    (c) “patent illegality” have been construed.

    In contravention with the fundamental policy of Indian law
    Signature Not Verified
    Digitally Signed
    By:VARNIKA O.M.P. (COMM) 378/2024 Page 15 of 38
    Signing Date:03.04.2026
    14:23:38

    51. As discussed above, till the 2015 Amendment the expression
    “in contravention with the fundamental policy of Indian law” was
    not found in the 1996 Act. Yet, in Renusagar Power Co.
    Ltd. v. General Electric Co.
    , 1994 Supp (1) SCC 644, in the
    context of enforcement of a foreign award, while construing the
    phrase “contrary to the public policy”, this Court held that for a
    foreign award to be contrary to public policy mere contravention of
    law would not be enough rather it should be contrary to:

    (a) the fundamental policy of Indian law; and/or

    (b) the interest of India; and/or

    (c) justice or morality.

    *****

    55. The legal position which emerges from the aforesaid discussion
    is that after “the 2015 Amendments” in Section 34(2)(b)(ii) and
    Section 48(2)(b) of the 1996 Act, the phrase “in conflict with the
    public policy of India” must be accorded a restricted meaning in
    terms of Explanation 1. The expression “in contravention with the
    fundamental policy of Indian law” by use of the word
    “fundamental” before the phrase “policy of Indian law” makes the
    expression narrower in its application than the phrase “in
    contravention with the policy of Indian law”, which means mere
    contravention of law is not enough to make an award vulnerable.
    To bring the contravention within the fold of fundamental policy of
    Indian law, the award must contravene all or any of such
    fundamental principles that provide a basis for administration of
    justice and enforcement of law in this country.

    56. Without intending to exhaustively enumerate instances of such
    contravention, by way of illustration, it could be said that:

    (a) violation of the principles of natural justice;

    (b) disregarding orders of superior courts in India or the binding
    effect of the judgment of a superior court; and

    (c) violating law of India linked to public good or public interest,
    are considered contravention of the fundamental policy of Indian
    law.

    However, while assessing whether there has been a contravention
    of the fundamental policy of Indian law, the extent of judicial
    scrutiny must not exceed the limit as set out in Explanation 2 to
    Section 34(2)(b)(ii).

    *****
    Patent illegality

    65. Sub-section (2-A) of Section 34 of the 1996 Act, which was
    inserted by the 2015 Amendment, provides that an arbitral award
    not arising out of international commercial arbitrations, may also
    be set aside by the Court, if the Court finds that the award is visited
    by patent illegality appearing on the face of the award. The proviso
    to sub-section (2-A) states that an award shall not be set aside
    merely on the ground of an erroneous application of the law or by
    reappreciation of evidence.

    Signature Not Verified
    Digitally Signed
    By:VARNIKA O.M.P. (COMM) 378/2024 Page 16 of 38
    Signing Date:03.04.2026
    14:23:38

    66. In ONGC Ltd. v. Saw Pipes Ltd., (2003) 5 SCC 705, while
    dealing with the phrase “public policy of India” as used in Section
    34
    , this Court took the view that the concept of public policy
    connotes some matter which concerns public good and public
    interest. If the award, on the face of it, patently violates statutory
    provisions, it cannot be said to be in public interest. Thus, an award
    could also be set aside if it is patently illegal. It was, however,
    clarified that illegality must go to the root of the matter and if the
    illegality is of trivial nature, it cannot be held that award is against
    public policy.

    67. In Associate Builders v. DDA, (2015) 3 SCC 49, this Court
    held that an award would be patently illegal, if it is contrary to:

    (a) substantive provisions of law of India;

    (b) provisions of the 1996 Act; and

    (c) terms of the contract [See also three-Judge Bench decision of
    this Court in State of Chhattisgarh v. SAL Udyog (P) Ltd., (2022)
    2 SCC 275].

    The Court clarified that if an award is contrary to the substantive
    provisions of law of India, in effect, it is in contravention of
    Section 28(1)(a) of the 1996 Act. Similarly, violating terms of the
    contract, in effect, is in contravention of Section 28(3) of the 1996
    Act.

    68. In Ssangyong Engg. & Construction Co. Ltd. v. NHAI, (2019)
    15 SCC 131 this Court specifically dealt with the 2015
    Amendment which inserted sub-section (2-A) in Section 34 of the
    1996 Act. It was held that “patent illegality appearing on the face
    of the award” refers to such illegality as goes to the root of matter,
    but which does not amount to mere erroneous application of law.
    It
    was also clarified that what is not subsumed within “the
    fundamental policy of Indian law”, namely, the contravention of a
    statute not linked to “public policy” or “public interest”, cannot be
    brought in by the backdoor when it comes to setting aside an award
    on the ground of patent illegality [See Ssangyong Engg. &
    Construction Co. Ltd. v. NHAI
    , (2019) 15 SCC 131].
    Further, it
    was observed, reappreciation of evidence is not permissible under
    this category of challenge to an arbitral award [See Ssangyong
    Engg. & Construction Co. Ltd. v. NHAI
    , (2019) 15 SCC 131].
    Perversity as a ground of challenge

    69. Perversity as a ground for setting aside an arbitral award was
    recognised in ONGC Ltd. v. Western Geco International Ltd.,
    (2014) 9 SCC 263. Therein it was observed that an arbitral
    decision must not be perverse or so irrational that no reasonable
    person would have arrived at the same. It was observed that if an
    award is perverse, it would be against the public policy of India.

    70. In Associate Builders v. DDA, (2015) 3 SCC 49 certain tests
    were laid down to determine whether a decision of an Arbitral
    Tribunal could be considered perverse. In this context, it was
    observed that where:

    Signature Not Verified
    Digitally Signed
    By:VARNIKA O.M.P. (COMM) 378/2024 Page 17 of 38
    Signing Date:03.04.2026
    14:23:38

    (i) a finding is based on no evidence; or

    (ii) an Arbitral Tribunal takes into account something irrelevant to
    the decision which it arrives at; or

    (iii) ignores vital evidence in arriving at its decision, such decision
    would necessarily be perverse.

    However, by way of a note of caution, it was observed that when a
    court applies these tests it does not act as a court of appeal and,
    consequently, errors of fact cannot be corrected. Though, a
    possible view by the arbitrator on facts has necessarily to pass
    muster as the arbitrator is the ultimate master of the quantity and
    quality of evidence to be relied upon. It was also observed that an
    award based on little evidence or on evidence which does not
    measure up in quality to a trained legal mind would not be held to
    be invalid on that score.

    71. In Ssangyong Engg. & Construction Co. Ltd. v. NHAI, (2019)
    15 SCC 131, which dealt with the legal position post the 2015
    Amendment in Section 34 of the 1996 Act, it was observed that a
    decision which is perverse, while no longer being a ground for
    challenge under “public policy of India”, would certainly amount
    to a patent illegality appearing on the face of the award. It was
    pointed out that an award based on no evidence, or which ignores
    vital evidence, would be perverse and thus patently illegal.
    It was
    also observed that a finding based on documents taken behind the
    back of the parties by the arbitrator would also qualify as a
    decision based on no evidence inasmuch as such decision is not
    based on evidence led by the parties, and therefore, would also
    have to be characterised as perverse [See Ssangyong Engg. &
    Construction Co. Ltd. v. NHAI
    , (2019) 15 SCC 131].

    72. The tests laid down in Associate Builders v. DDA, (2015) 3
    SCC 49 to determine perversity were followed in Ssangyong
    Engg. & Construction Co. Ltd. v. NHAI
    , (2019) 15 SCC 131 and
    later approved by a three-Judge Bench of this Court in Patel Engg.
    Ltd. v. North Eastern Electric Power Corpn. Ltd.
    , (2020) 7 SCC

    167.

    73. In a recent three-Judge Bench decision of this Court in DMRC
    Ltd. v. Delhi Airport Metro Express (P) Ltd., (2024) 6 SCC 357,
    the ground of patent illegality/perversity was delineated in the
    following terms: (SCC p. 376, para 39)
    “39. In essence, the ground of patent illegality is available for
    setting aside a domestic award, if the decision of the arbitrator is
    found to be perverse, or so irrational that no reasonable person
    would have arrived at it; or the construction of the contract is such
    that no fair or reasonable person would take; or, that the view of
    the arbitrator is not even a possible view. A finding based on no
    evidence at all or an award which ignores vital evidence in arriving
    at its decision would be perverse and liable to be set aside under
    the head of “patent illegality”. An award without reasons would
    suffer from patent illegality. The arbitrator commits a patent
    Signature Not Verified
    Digitally Signed
    By:VARNIKA O.M.P. (COMM) 378/2024 Page 18 of 38
    Signing Date:03.04.2026
    14:23:38
    illegality by deciding a matter not within its jurisdiction or
    violating a fundamental principle of natural justice.”
    Scope of interference with an arbitral award

    74. The aforesaid judicial precedents make it clear that while
    exercising power under Section 34 of the 1996 Act the Court does
    not sit in appeal over the arbitral award. Interference with an
    arbitral award is only on limited grounds as set out in Section 34 of
    the 1996 Act. A possible view by the arbitrator on facts is to be
    respected as the arbitrator is the ultimate master of the quantity and
    quality of evidence to be relied upon. It is only when an arbitral
    award could be categorised as perverse, that on an error of fact an
    arbitral award may be set aside. Further, a mere erroneous
    application of the law or wrong appreciation of evidence by itself
    is not a ground to set aside an award as is clear from the provisions
    of sub-section (2-A) of Section 34 of the 1996 Act.

    75. In Dyna Technologies (P) Ltd. v. Crompton Greaves Ltd.,
    (2019) 20 SCC 1, paras 27-43, a three-Judge Bench of this Court
    held that courts need to be cognizant of the fact that arbitral awards
    are not to be interfered with in a casual and cavalier manner, unless
    the court concludes that the perversity of the award goes to the root
    of the matter and there is no possibility of an alternative
    interpretation that may sustain the arbitral award. It was observed
    that jurisdiction under Section 34 cannot be equated with the
    normal appellate jurisdiction. Rather, the approach ought to be to
    respect the finality of the arbitral award as well as party’s
    autonomy to get their dispute adjudicated by an alternative forum
    as provided under the law.

    *****
    Scope of interference with the interpretation/construction of a
    contract accorded in an arbitral award

    84. An Arbitral Tribunal must decide in accordance with the terms
    of the contract. In a case where an Arbitral Tribunal passes an
    award against the terms of the contract, the award would be
    patently illegal. However, an Arbitral Tribunal has jurisdiction to
    interpret a contract having regard to terms and conditions of the
    contract, conduct of the parties including correspondences
    exchanged, circumstances of the case and pleadings of the parties.
    If the conclusion of the arbitrator is based on a possible view of the
    matter, the Court should not interfere [See: SAIL v. Gupta Brother
    Steel Tubes Ltd.
    , (2009) 10 SCC 63; Pure Helium India (P)
    Ltd. v. ONGC, (2003) 8 SCC 593; McDermott International
    Inc. v. Burn Standard Co. Ltd.
    , (2006) 11 SCC 181; MMTC
    Ltd. v. Vedanta Ltd.
    , (2019) 4 SCC 163].
    But where, on a full
    reading of the contract, the view of the Arbitral Tribunal on the
    terms of a contract is not a possible view, the award would be
    considered perverse and as such amenable to interference [South
    East Asia Marine Engg. & Constructions Ltd. v. Oil India Ltd.
    ,
    (2020) 5 SCC 164].

    Signature Not Verified
    Digitally Signed
    By:VARNIKA O.M.P. (COMM) 378/2024 Page 19 of 38
    Signing Date:03.04.2026
    14:23:38

    Whether unexpressed term can be read into a contract as an
    implied condition

    85. Ordinarily, terms of the contract are to be understood in the
    way the parties wanted and intended them to be. In agreements of
    arbitration, where party autonomy is the grund norm, how the
    parties worked out the agreement, is one of the indicators to
    decipher the intention, apart from the plain or grammatical
    meaning of the expressions used [BALCO v. Kaiser Aluminium
    Technical Services Inc., (2016) 4 SCC 126].

    86. However, reading an unexpressed term in an agreement would
    be justified on the basis that such a term was always and obviously
    intended by the parties thereto. An unexpressed term can be
    implied if, and only if, the court finds that the parties must have
    intended that term to form part of their contract. It is not enough
    for the court to find that such a term would have been adopted by
    the parties as reasonable men if it had been suggested to them.
    Rather, it must have been a term that went without saying, a term
    necessary to give business efficacy to the contract, a term which,
    although tacit, forms part of the contract [Adani Power (Mundra)
    Ltd. v. Gujarat ERC, (2019) 19 SCC 9].

    87. But before an implied condition, not expressly found in the
    contract, is read into a contract, by invoking the business efficacy
    doctrine, it must satisfy the following five conditions:

    (a) it must be reasonable and equitable;

    (b) it must be necessary to give business efficacy to the contract,
    that is, a term will not be implied if the contract is effective
    without it;

    (c) it must be obvious that “it goes without saying”;

    (d) it must be capable of clear expression;

    (e) it must not contradict any terms of the contract [Nabha Power
    Ltd. v. Punjab SPCL, (2018) 11 SCC 508, followed in Adani
    Power case, (2019) 19 SCC 9].

    (emphasis supplied)

    46. A careful and comprehensive perusal of the Impugned Award
    demonstrates that the learned Arbitrator has examined the pleadings,
    documentary material, correspondence exchanged between the parties,
    and the evidence led in support of their respective claims and
    assertions. The Impugned Award reflects due consideration of the
    relevant facts and surrounding circumstances germane to the disputes.
    The Petitioner has assailed the Impugned Award primarily on the
    grounds that the learned Tribunal (i) erred in attributing delay to both
    Signature Not Verified
    Digitally Signed
    By:VARNIKA O.M.P. (COMM) 378/2024 Page 20 of 38
    Signing Date:03.04.2026
    14:23:38
    parties, (ii) wrongly rejected the levy of LD, (iii) incorrectly
    determined the completion of OSAT and commencement of the
    warranty period, (iv) unjustifiably directed release of the PBG, and (v)
    incorrectly determined the entitlement to the balance payments. In
    view of the aforesaid, the grounds of challenge are addressed
    hereunder:

    (i) DELAY:

    47. The principal grievance of the Petitioner pertains to the
    attribution of delay in performance of the contract by the Respondent.
    It has been contended that the delay in execution and testing phases
    was solely attributable to the Respondent and that the learned Tribunal
    erred in holding that both parties contributed to the delay.

    48. A perusal of the Award, however, demonstrates that the learned
    Tribunal undertook a detailed examination of the contractual
    milestones, the stipulated completion period of twenty-eight (28)
    weeks, the admitted delay in supply of equipment, the sequence of
    ATP finalisation, the conduct of OSAT in phases, and the
    correspondence exchanged between the parties.

    49. The learned Tribunal has recorded specific findings that the
    delay in operationalisation could not be attributed exclusively to one
    party. It has considered the issues relating to the availability of sites,
    provision of bulk encryption units and media connectivity, vetting of
    ATP documentation, and compilation of test results. On the basis of
    the material before it, the learned Tribunal concluded that both parties
    had contributed, in varying degrees, to the delay in completion of
    testing. The decision of the learned Tribunal pertaining to the delay in
    the Impugned Award is reproduced herein below:

    “On Delay
    Signature Not Verified
    Digitally Signed
    By:VARNIKA O.M.P. (COMM) 378/2024 Page 21 of 38
    Signing Date:03.04.2026
    14:23:38

    145. It is admitted case of the parties that there has been delay in
    “Delivery, Installation and Commissioning of the systems”

    stipulated “to be completed within 28 weeks from the date of
    signing of Contract (10,08.2018)”, as per Clause 4 of Part-I (Ex. C-
    I) which period would have ended on 08.02.2019. Each party
    accuses the other of being responsible for delay while defending
    itself with assertion that it did not contribute to delay in any
    manner.

    146. Indisputably, the supply of equipment, was completed by
    CIPL on 09.08.2019, entailing a delay of more than 26 weeks
    beyond the scheduled date of completion of the project, which was
    20.02.2019. The sequence admittedly was supply of more than
    85% of the equipment before 20.02.2019, equipment under 7-line
    items being pending at that stage, and out of them 4-line items
    having been delivered on 30.04.2019, 1-item on 03.06.2019 and
    the last 2 items delivered on 08.08.2019, copies of related delivery
    challans/invoices (Ex. R-2, Colly.) being not in dispute.

    147. It is admitted that vide letter nos.

    CIPL/PMO/NTRO_STTC/19 dated 25.10.2018 (Ex. C-9) and
    CIPL/PMO/NTRO_SITC/26 dated 31.10.2018 (Ex. C-10) along
    with location wise list of engineers, the Claimant sought
    permission for all the site engineers to access the sites but since the
    Respondent’s outstation sites were not ready for laying the LAN
    Cabling Infra, the work could not commence. The LAN Diagram
    for all the outstation sites were admittedly submitted vide CIPL
    letter No.CIPL/PMO/NTRO-SITC/64 dated 30.11.2018 (Ex. C-

    11). It is not in dispute that the Claimant vide its letter No.
    CIPL/PMO/NTRO_SITC/27 dated 31.10.2018 (Ex. C-13) stated
    that infra at the MDC was not ready. There was no 3-phase power
    supply in the UPS room No. 301 at MDC and 300 Meter 3 Phase
    power cable was provided by M/s CIPL as the UPS installation
    work was getting delayed after the request from NTRO vide Letter
    No. XXXIIII68/05/2018-SMNY-2545 dated 29.10.2018 (Ex. C-

    14). Further, the NTRO officials were informed by Claimant vide
    letter No CIPL/PMO/NTRO_SITC/331 dated 05.03.2019 (Ex. C-

    12) about completion of Lah/UTP & OFC Cabling at all the
    outstation sites. It is also not in dispute that the Respondent, vide
    its letter dated. 07.06.2019 (Ex. C-27), had acknowledged that
    MPLS Links for the project were being provided by M/s Railtel
    and delivery was under process and, further, that, to reduce the
    implementation delay, the Claimant might start configuration of
    network equipment as well as end terminal desktops at remote sites
    through their on-site reps.

    148. There is no denial that the Respondent was expected under the
    contract to provide the media links and sites to the claimant
    immediately on the award of the contract in the year 2018, it is also
    admitted that the Claimant had addressed Letters dated 14.06:2019
    (Ex. C-28) and 12.07.2019 (Ex. C-29) requesting the Respondent,
    Signature Not Verified
    Digitally Signed
    By:VARNIKA O.M.P. (COMM) 378/2024 Page 22 of 38
    Signing Date:03.04.2026
    14:23:38
    inter: alia, for media-connectivity and informing that non
    availability of the same (media-connectivity had caused an
    unnecessary and substantial delay in the project execution and loss
    to the Claimant. It is not denied that on 14:11.2019 (Ex. C-30), the
    Respondent wrote on the issue of non-availability of sites and
    media connectivity asking the Claimant to use the physical media
    connectivity of existing functional networks, albeit only at 7-8
    locations. Admittedly, the Claimant had to follow up by other
    letters (Ex. C-46 to C-49) lastly by email dated 09.12.2022 (Ex. C-

    50). Indisputably, three sites had not been provided by the
    respondent to the claimant for connectivity ie. even after more than
    4 years from the date of award of contract.

    149. There is no clear or cogent answer to the plea of the Claimant
    of lack of cooperation from the Respondent illustrated by no
    results having come forth in response to letter dated 24.05.2019,
    requesting the Respondent to comply with their obligations and
    provide media links at all the sites on an urgent basis, along with
    other network requirements i.e. cooling, earthing and input power
    supply to power on the devices, for progress of the project and to
    establish the network connectivity, Indeed, the letter dated
    07.06.2019 (Ex. C-27) of the Respondent, on the subject of MPLS
    Links for project HSTN to be provided by M/s Railtel, calling
    upon the Claimant to start configuration of network equipment as
    well as end terminal desktops at remote sites through their on-site
    reps, is reflective of the Respondent having contributed to the
    delay in as much as under Clause 1 of Enclosure 1B of the
    Contract (Ex. C-1), it was obliged to provide media-connectivity so
    essential for the installation and commissioning. The
    communications dated 14.06.2019 (Ex. C-28) and 12.07.2019 (Ex.
    C-29), do demonstrate that work at the remote sites was hampered
    due to non-provisioning of Media Links and bulk encryption units
    by the Respondent. The solution suggested by letter 14.11.2019
    (Ex. C-30), for use of the physical media connectivity of existing
    functional networks, albeit only at 7-8 locations, was nothing but a
    stop gap or ad-hoc one.

    150. It is clear from the Contract (Ex. C-1) that the Claimant was
    expected to arrange imports of the equipment from various
    international vendors, whose manufacturing plants were out-side
    China. It is the case of the Claimants that the said condition of non-
    China products had caused slight delay which was not objected to
    and instead the Claimant was allowed to proceed with installation
    and commissioning of the equipment as per the Contract. It is also
    the plea of Claimant that late delivery of last two items DX -80
    VoIP, delivered on 08.08.2019, was due to the force Majeure
    events and & other reasons, covered by para 7 in Part III of the
    Contract (Ex. C-1), and did not have any impact on commissioning
    of Network. In this context, reference is made to (i) Notification of
    Govt, of India (“Gol”), Ministry of Finance (“MoF”) regarding
    Signature Not Verified
    Digitally Signed
    By:VARNIKA O.M.P. (COMM) 378/2024 Page 23 of 38
    Signing Date:03.04.2026
    14:23:38
    enhancement in custom tariff vide notification no 6); (ii) Cisco
    Distributors Letter dated 19.03.2019 (Ex. C-7) clearly stated global
    material constraints as the material had to be of the latest
    manufacture for which reason Cisco started manufacturing
    components in different factories across globe thus getting delayed
    for adherence of the contract clause; (iii) BIS Certification made
    applicable after award of contract resulted in delayed delivery of
    Cisco products like IP. Phone which required BIS certification got
    delayed by BIS department and, thus, delivery was delayed for 16-
    18 weeks and finally effected on 09.08.2019; and (iv) Cisco letter
    dated 01.04.2019 (Ex. C-8) to NTRO mentioned challenges in
    delivering Cisco products due to global material constraints and
    supply chain issues.

    151. The argument of the Respondent that the Claimant was well
    aware of the condition in the contract that imports of the equipment
    be arranged, from various international vendors whose
    manufacturing plants were out-side China has merit. This obliged
    the Claimant to be in readiness in terms of its contractual
    obligations to arrange items and services as per the technical
    specifications and functional requirement given in the contract
    within contracted timelines, ever since the evaluation stage of the
    tender ie May 2018. The delay attributable to reasons such as
    Notification dated 11.10.2018 (Ex. C-6) of MoF (GOI) regarding
    enhancement in custom tariff, Cisco Distributors Letters dated
    19.03.2019 (Ex. C-7) and 01.04.2019 (Ex. C-8) on the subjects of
    global material constraints or BIS Certification made applicable
    after award of contract to Cisco products like IP Phone can also not
    be accepted as force majeure since these are not covered by the
    clause. But, even if the same are treated as having contributed they
    were not the sole cause of delay in commissioning, the end
    objective. Thus, nothing tums on this part of the controversy for
    the reason the contract was not merely for supply but also
    installation and commissioning of the equipment.

    152. The argument of the Respondent, founded on letter dated
    07.06.2019 (Ex. C-2T) asking the Claimant to finish LAN side
    infrastructure/Civil work and deployment and configuration of end
    points at all sites, to the effect that there was delay on the part of
    the Claimant in Configuration of Equipment and also LAN side
    infrastructure and deployment of end points as per contract
    requirement, such LAN side work having continued till July 2019
    and End point deployment till Oct 2019 does not impress since
    there were delays on its part as well primarily in making the sites
    available and providing media connectivity and bulk encryption
    units even as late as end of 2019.

    153. On the foregoing facts, and in the circumstances, both parties
    must share the blame for delay in meeting the time line specified as
    the Delivery Period under the contract (Ex. C-1).”

    Signature Not Verified
    Digitally Signed
    By:VARNIKA O.M.P. (COMM) 378/2024 Page 24 of 38
    Signing Date:03.04.2026
    14:23:38

    50. The petitioner’s contention that the learned Arbitrator ignored
    the admission of the Respondent’s witness is wholly misconceived.
    The statement of CW-1 that media links cannot be utilised without
    routers is merely a technical acknowledgement of the functional
    interdependence between connectivity infrastructure and routing
    hardware; it does not establish that routers were the sole prerequisite
    for commissioning nor that the Respondent had otherwise fulfilled its
    own contractual obligations. The proposition is reciprocal in nature;
    just as media links cannot function without routers, routers are equally
    incapable of establishing a network in the absence of media
    connectivity.

    51. The evidence on record demonstrates that media links, bulk
    encryption units, and complete site readiness were not made available
    in accordance with contractual timelines. Commissioning was the
    ultimate contractual objective, and it required simultaneous
    availability of equipment as well as connectivity and infrastructure.

    52. The learned Tribunal, upon a holistic appreciation of
    correspondence and admissions on both sides, concluded that the
    delay was attributable to both parties. The Petitioner’s argument is, in
    substance, an attempt to isolate one answer in cross-examination and
    invite a re-appreciation of evidence, which is impermissible within the
    limited scope of interference under Section 34 of the Act.

    (ii) REJECTION OF LIQUIDATED DAMAGES:

    53. Insofar as the challenge to the rejection of LD is concerned, this
    Court finds no infirmity in the reasoning adopted by the learned
    Tribunal. The learned Tribunal has noted that the Petitioner did not
    adduce evidence to establish actual loss suffered on account of the
    Signature Not Verified
    Digitally Signed
    By:VARNIKA O.M.P. (COMM) 378/2024 Page 25 of 38
    Signing Date:03.04.2026
    14:23:38
    alleged delay, nor demonstrate that the stipulated amount was justified
    in the factual context of the case.

    54. The Impugned Award reflects that the learned Tribunal
    considered the legal position governing LD, including the relevant
    judicial precedents on the requirement of reasonable compensation
    and the non-automatic nature of such clauses. Upon appreciation of
    the contractual terms, the conduct of the parties, and the evidentiary
    record, the learned Tribunal concluded that the levy of liquidated
    damages was not justified in the circumstances.

    55. The reliance placed upon Consolidated Construction
    Consortium Limited
    (supra) by the Petitioner does not advance its
    case. The said decision reiterates that contractual clauses must be
    interpreted in accordance with their terms; however, it equally
    recognises that the application of such clauses depends upon the
    factual determination of breach and entitlement. In the present case,
    the learned Tribunal’s interpretation of the clause and its conclusion
    that unilateral levy was not justified is a plausible construction of the
    contract based on an appreciation of the evidence.

    56. The contention regarding the levy of LD is also intrinsically
    linked to the finding on delay attribution. The contractual clause
    relating to LD presupposes delay, attributable to the contractor. Once
    the learned Tribunal, upon appreciation of evidence, has held that
    responsibility for delay was shared and not exclusively attributable to
    the Respondent, the rejection of unilateral levy of LD flows logically
    from such a finding. Thus, the view taken by the learned Tribunal is
    certainly a possible and plausible view and does not entail interference
    from this Court in the exercise of the present jurisdiction.

    Signature Not Verified
    Digitally Signed
    By:VARNIKA O.M.P. (COMM) 378/2024 Page 26 of 38
    Signing Date:03.04.2026
    14:23:38

    (iii) COMPLETION OF OSAT:

    57. The Petitioner has further contended that successful completion
    of OSAT never occurred in terms of the contract and, therefore, the
    learned Tribunal erred in determining the commencement of the
    warranty period.

    58. The Impugned Award, however, reveals that the learned
    Tribunal examined the phases of OSAT conducted, the operational
    readiness of the system, the handing over of credentials, and the
    conduct of parties subsequent to testing.

    59. A reading of the Impugned Award further indicates that the
    learned Tribunal has taken into consideration the sequence of events
    relating to the handing over of sites and operationalisation of the
    system. The learned Tribunal recorded that there were delays not only
    in the execution by the Respondent but also on the part of the
    Petitioner in making sites available and facilitating completion of
    testing. The learned Tribunal further noted that the login credentials
    were taken over by the Petitioner on 17.03.2020 and treated the OSAT
    as having been completed on that date.

    60. On that basis, the learned Tribunal determined that the warranty
    period stood commenced from 17.03.2020 and consequently expired
    on 16.03.2023. The computation of the warranty period thus flowed
    from a factual determination of completion and operational acceptance
    of the system. Such determination is rooted in an appreciation of
    material on record and contractual interpretation. The relevant
    portions of the Impugned Award dealing with completion of OSAT
    and commencement of the warranty period are extracted herein below:

    “On OSAT

    Signature Not Verified
    Digitally Signed
    By:VARNIKA O.M.P. (COMM) 378/2024 Page 27 of 38
    Signing Date:03.04.2026
    14:23:38

    162. It is admitted position under the contract (Ex. C-1) that upon
    successful completion of OSAT, the seller and buyer were to sign a
    certificate of conformity. This certificate was not issued and the
    grievance of the Claimant in this regard forms subject matter of the
    reliefs sought. The dispute came to the fore with the Respondent
    (buyer) issuing the notice dated 08.07.2022 (Ex. C-68), alleging
    non-fulfillment of contractual terms and conditions invoking the
    provisions mentioned in para 4, part-l of the contract stating, inter
    alia, that the Claimant (seller) could not successfully conduct
    OSAT, the Claimant having replied sending Demand Notice dated
    20.07.2022 (Ex. C-69) seeking balance payment and return of
    PBG.

    163. As noted earlier, On-Site Acceptance Test (“OSAT) is one of
    the important conditions of the contract, referred to in the preamble
    and stipulated in terms as pre-requisite, along with completion of
    training, for the discharge of contractual obligations of the
    Claimant and having a bearing on the commencement of the three-
    year free comprehensive onsite warranty with operational support
    for the Respondent. As also already noted, in terms of the original
    contract (Ex. C-1) the balance 30% of the contract value after
    payment of 70% against successful delivery for complete system
    Hardware, Software, related documents/ Certificate from OEM and
    PBG) was stipulated to be paid – per Clause 4 (b) of Part III – on
    “user’s certificate of successful completion of installation/
    Integration, commissioning, Site Acceptance Test (OST) and onsite
    training”. Admittedly, the above clause 4(b) post-amendment (Ex,
    C-43), carried on 28.05.2020, split the balance 30% into two
    tranches – one of 20% (on deployment of 70% of data terminals
    and commencement of services at minimum eight locations duly
    certified by the user) and the balance 10% still contingent on user’s
    certificate of successful completion of installation/ integration,
    commissioning Site Acceptance Test (OSAT) and onsite training”.
    It is clear from the pleadings and the evidence that 90% of the
    contract value has already been paid, the dispute being over the
    balance 10%, it being the case of the Respondent that OSAT has
    not been completed and so the amount has not become due.

    164. Closely connected to the above is also the case of the
    Respondent that the obligations of the Claimant towards three-year
    free comprehensive onsite warranty with operational support for
    the Respondent are yet to commence since that would occur only
    when OSAT is completed. Per contra, it is the case of the Claimant
    that the Respondent has abused its position to deny certificate of
    completion of OSAT even after six rounds, all tests having been
    successfully demonstrated, and redemonstrated, the process
    adopted being non-transparent, dilatory and unilateral, the denial of
    OSAT completion being not fair since the Claimant took control of
    all equipment to the exclusion of the Claimant after handing over
    of the log-in credentials on 17.03.2020, The Claimant relies upon,
    Signature Not Verified
    Digitally Signed
    By:VARNIKA O.M.P. (COMM) 378/2024 Page 28 of 38
    Signing Date:03.04.2026
    14:23:38
    inter alla, letter dated 01.07.2022 (Ex C-70) to assert that it had
    been informing the Respondent having successfully redemonstrated
    all the points to the OSAT committee at all available locations, It is
    contended that after completion of training before 07.10.2019, the
    project was complete and the 3-ycar on-site warranty had
    commenced from the said date i.e., 07.10.2019. It is pleaded that
    owing to immense financial pressure, the amendment of contract
    dated 28.05.2020 and consequent release of 20% payment was
    accepted, and 10% contract value and PBG left to be claimed later,
    the work of the Claimant being complete in all aspects.

    165. The submission of the Claimant that OSAT was to be
    conducted before the training (Part I Para 6 of Contract) cannot be
    accepted since the Contract (Ex. C-1) does not specify that to be
    the sequence of the two events. Further, the training of the
    personnel has nothing to do with the successful testing of
    functionality of the system, the latter being covered by OSAT, a
    requisite step separate from training.

    166. Under the contract (Ex. C-I), the OSAT was to be completed
    within four, weeks of commissioning of the services (Clause 17 of
    Part III). That the OSAT has been delayed is not in dispute. Since
    there was delay in installation and commissioning, and there was
    delay in ATP document being finalized, the delay in OSAT was a
    natural consequence to follow.

    167. Concededly, in terms of the procedure stipulated in para 17 of
    Part III of the contract (Ex. C-1) an Independent committee was
    required to undertake OSAT in accordance with the mutually
    formulated ATP, initiated by the Claimant and vetted by the
    Respondent, by verifying parameters and functionalities albeit in
    the presence of representatives of the Seller (the Claimant). In the
    context of letters (Ex. C-61 to Ex.

    C-64) relied upon by the Claimant, the Respondent has, inter alia,
    asserted that the OSAT team has 09 scientists, who had the
    requisite expertise and domain knowledge to conduct the OSAT as
    per the mutually agreed ATP document. The plea of the Claimant
    that the OSAT conducting team members had no domain
    experience is not supported by any evidence and, thus, need not be
    given any credence.

    168. The assertion of CW-I that there was no express provision in
    the contract as to the period within which document for ATP was
    to be submitted prior to offering OSAT cannot be accepted since
    the time-line for OSAT was prescribed (within 4 weeks after
    Installation and commissioning of the system”). At the same time,
    however, it cannot be ignored that ATP was to be vetted and
    accepted by the Respondent. This also took time. Admittedly, the
    ATP document was submitted on 12.11.2019, after a request was
    forwarded by the respondent vide letter dated 11.09.2019 (Ex.R-4),
    with reference to para 17(b) of part-Ill of contract agreement
    (Ex.C-1), Respondent having sought amendments of the ATP as
    Signature Not Verified
    Digitally Signed
    By:VARNIKA O.M.P. (COMM) 378/2024 Page 29 of 38
    Signing Date:03.04.2026
    14:23:38
    per letter dated 02.12.2019 (Ex.C-90), reference being made to
    letter dated 19.12.2019 (Ex.C-91) of the Claimant, the latter being
    agreeable to discuss and include specific tests as desired by the
    respondent. Concededly, the final vetted ATP document was
    submitted by the claimant on 10.02.2020 (Ex. R-6) and approved
    by the Respondent on 14.02.2020. In this chronology, neither side
    can blame the other exclusively for delay in ATP document being
    developed.

    169. Would It be fair to blame one party or the other for delay in
    initiation or timely completion of OSAT at the connected sites?
    The answer is in the negative

    170. The case of the Respondent that the Claimant had been
    requested to first configure the central site, followed by single link
    connectivity with two remote sites, before replicating the
    configurations to other remote sites or further that the sites came
    up, one after another, owing to sequencing and rotation of
    manpower by CIPL is not substantiated by any evidence. There is
    nothing presented to refute the case of the Claimant that the sites
    were provided for connectivity in six (6) batches during the period
    of three years and accepted by the Respondent after successful
    testing and commissioning. Indeed, if there was any problem in
    functioning of any of the sites, the respondent would have been
    reluctant to provide the other sites. It is admitted in the pleadings
    by the Respondent that it had offered WAN connectivity after
    ascertaining viable configurations at the central’ site to ensure
    security of the network It is the plea of the Respondent itself that
    the Claimant was to complete the OSAT only at the connected
    sites, and joining issue with the Claimant on its contention based
    on non-availability of links and BUs at the other sites (terming it as
    a ruse), expressly stating that at no time it had sought conduct of
    OSAT for not connected sites. It is also own case of the
    Respondent, and conceded by CW-2, that OSAT arranged for the
    connected sites, accounted for most of the project resources, the
    configurations at each of the remote sites other than MDC and
    DRS being the same, such configuration, if completed at one
    remote site, being easily replicable at the other sites, even without
    connectivity.

    171. Though not denying that such arrangement by the Respondent
    under the contract was expected to be made by August 2018, it is
    own averment of the Respondent that the BEUs and links for the
    OSAT had been provided in December 2019 Le. when that
    Claimant was able to credibly show that the systems had been
    configured and the lines will be used. Notwithstanding denial by
    CW-1, it is established by letter dated 03.12.2019 (Ex. C-31) of the
    Claimant that OSAT was offered on 03.12.2019 and not earlier. It
    is, however, also conceded that OSAT had commenced in February
    2020, 194 out of 966 parametric test cases having failed in initial
    phase, per OSAT reports issued vide letter No.
    Signature Not Verified
    Digitally Signed
    By:VARNIKA O.M.P. (COMM) 378/2024 Page 30 of 38
    Signing Date:03.04.2026
    14:23:38
    XXXIII/68/05/2018-SMNY-Vol-III dated 28 May 2020 (Ex. R-

    24), also indicating 19 functional tests and 303 parametric tests as
    “not conducted”

    172. As noted earlier, it is conceded that the Respondent vide letter
    No. XXXIII/68/05/2018-SMNY-109 dated 13.01.2020 (Ex. R-21)
    had requested the Claimant to confirm implementation of network
    configurations of all devices and activation of data terminals for
    initiating OSAT whilst the Claimant vide their letter
    CIPL/PMO/NTRO_SITC/941 dated 15.01.2020 (Ex. R-22) had
    claimed that they had implemented all security policies and
    baseline configurations communicated by NTRO, also saying that
    they were prepared for OSAT only at MDC, Aya Nagar.

    173. As is expressly admitted by CW-1, there is no doubt that
    OSAT had to be conducted six times between February 2020 and
    June 2022, it covering 1269 tests (both parametric and functional),
    including VC, VolP, TP and Data Services, and since a number of
    parametric and functional tests were failing or had failed, they were
    re-demonstrated to OSAT team even after handing over of
    credentials. The first phase of OSAT was from 17.02.2020 to
    06.03.2020 whilst the last phase of OSAT was from 10.06.2022 to
    23.06.2022, Reference is to be made in this context to various
    communications such as letter dated 17.02.2020 (Ex, R-23), letter
    dated 17.03.2020 (Ex.C-38), letter dated 20.03.2020 (Ex.C-39),
    letter dated 07.04.2020 (Ex.C-40), letter dated 14.04.2020 (Ex.C-

    41) and letter dated 20.04.2020 (Ex.C-42), letter dated 28.05.2020
    (Ex. R-24), letter dated 1106.2020 (part of Ex.R-7), letter dated
    16.09.2021 (Ex. R-13), letter dated 01:10.2021 (Ex, R-9), letter
    dated 29.04.2022 (Ex.R-16), and letter dated 08.07.2022 (Ex: C-

    68). The plea of the Respondent, as put 1o CW-2, that the OSAT
    could not be conducted from March 2020 to November 2020, and
    again from April 2021 going beyond May 2021, due to COVID
    restrictions might be accepted based on judicial notice of the
    pandemic conditions then prevailing. Even after the last phase of
    OSAT (10.06.2022 to 23.06.2022), per communication dated
    08.07.2022 (Ex. C-68), based on conduct of OSAT, carried out in
    presence of representatives of the claimant, as admitted by CW-1,
    two tests viz. Test 1 and Test 3. (out of total 1269) had statedly
    failed to be successfully demonstrated, this being brought out
    during testimony of CW-2 based on the joint test reports,
    pertaining to “High Availability” Test (HA Test), particularly Test
    1, the observations to such effect having been endorsed by
    representatives of both sides.

    174. Indisputably. by email dated 27.06.2022 (Ex. C-67), the
    Respondent had communicated to the Claimant that OSAT team
    was compiling reports of OSATs done between 10.06.2022 to
    23.06.2022 at various sites and observations of OSAT team, if any,
    shall be communicated. No communication thereafter sharing the
    report of OSAT Committee has been shown the light of the day by
    Signature Not Verified
    Digitally Signed
    By:VARNIKA O.M.P. (COMM) 378/2024 Page 31 of 38
    Signing Date:03.04.2026
    14:23:38
    the Respondent, the notice dated 08.07.2022 (Ex. C-68),
    mentioning that the claimant had failed Test 1 and 3, two out of
    total 1269 tests.

    175. The “OSAT Document for Project “HSTN”, classified as
    “Confidential”, the respondent being the custodian, produced
    during the cross-examination of CW-2, reflected that representative
    of the claimant had signed relevant pages of the spiral book shown
    relating to tests conducted on 03.03.2020, 31.12.2020, 19.03.2021
    and some other dates post 05.03.2020. It was, however, also
    brought out that there are a number of pages of the said document
    pertaining to passed tests which do not bear signatures, CW-2
    having pointed out test nos. 4, 5, 6, 8 and 10 at page nos.6, 7, 8 and
    9 of the OSAT document to illustrate this point. The “Joint test
    reports conducted during /0.06.2022 to 23.06.2022” with which
    CW-2 was confronted during his cross-examination is a document
    similar to the “OSAT Document for Project “HSTN'”, also
    classified as “Confidential”. Seen in light of letter dated 08.07.2022
    (Ex. C-68) of the Respondent stating that two tests i.e, test 1 at two
    sites and test 3 at all sites remained to be successfully
    demonstrated, giving impression that all but the said two tests had
    been successfully demonstrated, the plea of the Claimant that its
    representative was allowed to sign only when the representative of
    the respondent would show the relevant page or specific place on a
    particular page of the book relating to the specific tests cannot be
    rejected, there being no evidence adduced to affirm to the contrary.

    176. As was highlighted by the Claimant at the final hearing, letter
    dated 28.05.2020 (Ex.R-24) and Annexure-1, mentioned total test
    conducted to be 966 and passed test 772 and test failed 194, no
    details of the balance 284 tests having been set out. Subsequent
    letter dated 16.09.2021 (Ex. R-13) put the number of failed tests as
    18 tests. However, Letter dated 23.09.2021 (Ex. R-14) relied upon
    by the Respondent itself stated that all tests had been successfully
    demonstrated to the members of S-NOC, and this would definitely
    include test 1 and 3. The response of the Respondent by letter dated
    01.10.2021 (Ex. R-9) did not take the position that S-NOC was not
    the authority for conducting tests, as was the argument raised at
    final hearing. The letter dated 01.10.2021 simply stated that
    verification by OSAT Committee was under progress. No records
    of the OSAT Committee have been shared nor any member of the
    said Committee was called In as a witness to explain as to how
    their assessment vis-à-vis Tests 1 and 3 was different from that of
    the S-NOC.

    177. The above deficiencies in the material relied upon by the
    Respondent put a question mark on the transparency, objectivity,
    and fairness of the procedure of OSAT which was expected to be a
    collaborative exercise.

    178. From the above, it emerges that the Respondent has also
    contributed substantially to the non-completion of OSAT in time. It
    Signature Not Verified
    Digitally Signed
    By:VARNIKA O.M.P. (COMM) 378/2024 Page 32 of 38
    Signing Date:03.04.2026
    14:23:38
    is granted in its favor that it could not be expected to wait
    indefinitely for the seller to complete the supply, installation and
    commissioning. There was inordinate delay in each of the said
    stages But as concluded earlier, the Respondent must partake the
    blame for this delay, it not having readily handed over all the sites,
    it being in default in timely providing BEUs and media
    connectivity, taking its own time in vetting the ATP document and
    compiling of test results of OSAT in various phases and such other
    indulgences. Just as the Respondent was entitled to fill delivery
    within time stipulated under the contract, the Claimant would also
    legitimately be expecting timely completion, discharge and exit.
    The delays on the part of the Respondent meant the Claimant was
    also stuck in uncertainty. The timelines having gone haywire, there
    had to be a fresh understanding of remaining obligations under the
    contract, and this required some initiative from the Buyer which is
    found amiss.

    179. Going by the text of the contract, the Claimant could not get
    the certificate of completion without Test 1 and 3 also being
    certified formally, Assuming, however, that they had failed to pass
    the muster, is it fair to expect the Claimant to have demonstrated
    them when the systems had not been in its control? This is where
    the takeover of the log-in credentials by the Respondent on
    17.03.2020 becomes crucial. It was not merely take-over of the
    log-in credentials but a direction accompanied by a command to
    the personnel of the Claimant to keep hands off, to maintain a be-
    at-bay approach. The use by the Respondent of the systems put in
    position by the Claimant under the contract (Ex C-1), and the sites
    where the same were installed and commissioned, to the absolute
    exclusion of the Claimant, except when called upon for operational
    support, with effect from 17.03.2020 made it difficult, if not
    impossible, for the Claimant to demonstrate (or redemonstrate the
    pending functional or parametric tests through an objective and
    transparent process, the Respondent controlling not only the access
    to the sites and the systems but also the documentation of conduct
    of OSAT, an exercise which has been rather opaque.

    180. The decision of the Respondent to exclude the Claimant as
    above can only be construed as waiver on its part of the clause for
    completion of OSAT to the extent balance as on the said date
    (17.03.2020). The complete take over on 17.03.2020 only means
    the Claimant could not thereafter be held accountable, the
    respondent being in full control of all the systems and sites,
    independently making changes/modifications of system
    configurations, which had the effect on functioning of systems
    including OSAT. That the Claimant continued even subsequently
    to collaborate for remaining OSAT will be of no consequence.

    181. On the above facts, and in the circumstances, it is fair and just
    to deem the OSAT to have stood completed, for purposes of
    triggering the consequences in the contract to follow (viz.

    Signature Not Verified
    Digitally Signed
    By:VARNIKA O.M.P. (COMM) 378/2024 Page 33 of 38
    Signing Date:03.04.2026
    14:23:38

    commencement of warranty, period of validity of PBG, and
    payment obligations) on 17.03.2020. It is held accordingly.
    On Warranty

    182. As noted earlier, the preamble of the contract indisputably
    stated that “Seller is required to provide three-year free
    comprehensive onsite warranty with operational support to buyer
    from the date of completion of Site Acceptance Test (OSAT) and
    training …”. Admittedly, in terms of clause 8 of Part-I of the
    contract (Ex. C-1), the claimant was to supply the three (3) years
    comprehensive onsite warranty “at all 23 pan India locations
    mentioned in the contract” in respect of “(a)ll the equipment,
    hardware, software, components, services” of the project “against
    defective workmanship and materials, faulty designs or inferior
    quality of materials”, this covering “(a)ll consumables &g. LAN,
    OFC cables, Connectors, wires etc.”, the
    “comprehensive warranty services to also include software services
    and software upgrades and troubleshooting”, there being a liability
    on the part of the Claimant (seller) to have the defects or faults etc.
    to be “repaired / replaced / resolved at any site free of charges”.
    Crucially, the said clause 8 of the contract (Ex. C-1) stipulated that
    warranty period will commence from successful completion of Site
    Acceptance Test (ST) and training”.

    183. It is the case of the Claimant that after completion of training
    before 07.10.2019, the project was complete at the end of the
    Claimant and the 3-year on-site warranty had commenced from
    07.10.2019 ie. after completion of training. Per contra, it is
    contended by the Respondent that mere completion of training is
    not sufficient. The other requirement of successful completion of
    OSAT also had to be met, the training was to follow OSAT and not
    the other way around. It was pleaded that OSAT has not been
    completed and so the warranty period cannot be said to have
    commenced

    184. The contention of the Respondent that warranty is yet to
    commence and there is no question of determination of the end
    date cannot be accepted. The argument that OSAT must have
    preceded training has been rejected earlier. The core question to be
    addressed here is as to whether, in the given facts and
    circumstances, the warranty period had commenced with
    completion of training, notwithstanding the dispute over OSAT
    completion, as is contended by the Claimant.

    185. There can be no denial of the fact that the warranty, License
    and services from the original equipment manufacturer commences
    once the equipment is activated. It is admitted that the Specialized
    Advance Level training required the products under warranty, as
    installed at the site where training was organized, to come in usage
    by the Respondent from their date of activation ie., since
    07.10.2019. This naturally means that the OEM warranty period
    had commenced from 07.10.2019 in respect of such equipment.

    Signature Not Verified
    Digitally Signed
    By:VARNIKA O.M.P. (COMM) 378/2024 Page 34 of 38
    Signing Date:03.04.2026
    14:23:38

    Though some stray instances of deficiency in support in operations
    have been quoted, there is no denial in the course of evidence by
    the Respondent that the personnel of the Claimant (Ex. CW-1/3)
    had been stationed at the sites of the Respondent to provide on-site
    support and have continued beyond the period of three (3) years for
    operational support and that post the confirmation by the
    Respondent that VC, VolP, TP, Data services had been made
    functional at seven (7) sites and demanding handover, inter alia,
    vide Letter dated 06.03.2020 (Ex. C-36) & 10.03.2020 (Ex. C-37),
    the Claimant was made to hand over the login credentials of all the
    network equipment and devices of the seven sites including MDC
    & DRS to the employees of the Respondent vide Letter dated
    17.03.2020 (Ex. C-38), and thereafter, the Respondent has been
    using the equipment and services, provided by the claimant in
    terms of the contract, for the last more than three years, a fact
    proved by CW-1 and not refuted in evidence by the Respondent.
    Based on these facts, it has been concluded earlier that the
    Respondent had waived strict compliance with the balance OSAT
    and that the said exercise (OSAT) is deemed to have been
    completed on 17.03.2020.

    186. The plea of the Claimant, that the warranty clause in the
    contract (Ex. C l) would have come into play with completion of
    training (07.10,2019) cannot be accepted. As noted earlier, the
    other prerequisite was completion of OSAT which is found to be
    complete on 17.03.2020, the date on which the Respondent
    compelled the Claimant to hand over the log-in credentials and also
    the systems and sites, excluding the Claimant even from access,
    except when called for operational support. Since OSAT is deemed
    to have been completed on 17.03.2020, that is the date from which
    the consequences in the contract would follow, including
    commencement of warranty, and, thus, the warranty clause under
    the contract (Ex. C-1) would have begun from 17.03.2020 and,
    being for three years, ended on 16.03.2023.

    187. It needs to be examined if there have been breaches
    committed by the Claimant vis d vis the obligations under the
    warranty clause during the above-mentioned period and, if so, with
    what consequences. These issues are considered in context of case
    of the Respondent asserting its right to impose Liquidated
    Damages and invoke PBG.”

    61. It is also evident from the Impugned Award that the learned
    Tribunal did not determine the issue of completion of OSAT in
    isolation. The learned Tribunal took into account multiple relevant
    factors, including delays in handing over sites, the conduct of the
    parties during execution and testing, the contemporaneous
    Signature Not Verified
    Digitally Signed
    By:VARNIKA O.M.P. (COMM) 378/2024 Page 35 of 38
    Signing Date:03.04.2026
    14:23:38
    correspondence exchanged between them, the impact of the COVID-
    19 pandemic on contractual timelines, and the overall procedural
    fairness of the process adopted. The conclusion regarding completion
    of OSAT and commencement of the warranty period thus emerged
    from a cumulative assessment of factual and contractual
    circumstances, and cannot be said to be arbitrary or based on
    extraneous considerations.

    (iv) RELEASE OF PERFORMANCE GUARANTEE (PBG):

    62. Insofar as the PBG is concerned, the direction for its release is a
    corollary to the findings recorded on completion, shared delay, and
    rejection of LD. Retention of a performance security must have
    contractual justification. Once the learned Tribunal found the absence
    of exclusive default and unjustified levy of liquidated damages, the
    direction for release of the PBG cannot be termed arbitrary or contrary
    to the contract.

    63. The Petitioner has also alleged that the learned Tribunal
    overlooked material evidence regarding non-renewal of licences and
    deficiencies in performance. A reading of the Impugned Award,
    however, indicates that these aspects were noted and considered.
    Merely because the learned Tribunal did not accept the Petitioner’s
    interpretation of such material does not imply non-consideration. An
    erroneous appreciation of evidence, even if assumed, does not amount
    to patent illegality unless it goes to the root and renders the decision
    perverse.

    (v) RELEASE OF WITHHELD PAYMENT:

    64. With regard to entitlement to the balance payment, the learned
    Tribunal has recorded that it was an admitted position that ten (10) per
    Signature Not Verified
    Digitally Signed
    By:VARNIKA O.M.P. (COMM) 378/2024 Page 36 of 38
    Signing Date:03.04.2026
    14:23:38
    cent of the contract value remained withheld by the Petitioner. Having
    rejected the claim for levy of LD and having found no established loss
    or subsisting breach, justifying retention of the said amount, the
    learned Tribunal concluded that the Respondent was entitled to the
    release of the withheld balance consideration. The direction for
    payment thus flows as a natural consequence of the rejection of LD
    and the determination of completion of contractual milestones.

    65. The Impugned Award, in directing release of the balance
    amount, does not rewrite the contract but gives effect to the reciprocal
    obligations of the parties upon completion of performance. Such a
    finding, being founded on an appreciation of facts and an
    interpretation of contractual provisions, does not suffer from patent
    illegality or perversity warranting interference under Section 34 of the
    Act.

    66. The reliance placed by the Petitioner upon ONGC (supra) to
    contend that the Award is patently illegal must be examined in the
    context of the post-2015 statutory framework. The expression “patent
    illegality” does not permit re-appreciation of evidence or correction of
    errors of fact. The illegality must go to the root of the matter and be
    apparent on the face of the Award. No such illegality is demonstrated
    in the present case.

    CONCLUSION:

    67. In view of the law laid down by the Hon’ble Supreme Court in
    OPG Power (supra), and upon consideration of the detailed
    examination undertaken by the learned Tribunal of the contractual

    Signature Not Verified
    Digitally Signed
    By:VARNIKA O.M.P. (COMM) 378/2024 Page 37 of 38
    Signing Date:03.04.2026
    14:23:38
    provisions and the material on record, this Court finds no ground
    warranting interference under Section 34 of the Act.

    68. The Impugned Award reflects a plausible and reasoned
    interpretation of the contract and an evaluation of evidence within the
    jurisdiction of the learned Tribunal. It is well settled that a court
    exercising limited supervisory jurisdiction under Section 34 cannot re-
    appreciate evidence or substitute its own interpretation of contractual
    clauses where the view taken by the learned Tribunal is a possible and
    reasonable one.

    69. Viewed in its entirety, the Impugned Award reflects a reasoned
    and structured adjudication of the disputes by the learned Tribunal
    within the confines of the contractual terms agreed upon by the
    parties, the material placed on record, and the jurisdiction vested in
    the learned Arbitral Tribunal. The Impugned Award demonstrates due
    application of mind to the pleadings, evidence, and relevant
    contractual provisions.

    70. In view of the foregoing discussion, this Court is of the
    considered opinion that the Petitioner has failed to establish any
    ground under Section 34(2) or Section 34(2A) of the Act warranting
    interference with the Impugned Award.

    71. The present Petition, along with pending application(s), if any,
    stands disposed of in the above terms.

    72. No Order as to costs.

    HARISH VAIDYANATHAN SHANKAR, J.

    APRIL 1, 2026/jk

    Signature Not Verified
    Digitally Signed
    By:VARNIKA O.M.P. (COMM) 378/2024 Page 38 of 38
    Signing Date:03.04.2026
    14:23:38



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here