National Projects Construction … vs Bharat Scouts And Guides on 20 July, 2026

    0
    4
    ADVERTISEMENT

    Delhi High Court

    National Projects Construction … vs Bharat Scouts And Guides on 20 July, 2026

                      $~1
                      *       IN THE HIGH COURT OF DELHI AT NEW DELHI
    
                      %                                        Date of decision: 20.07.2026
                      +       ARB.P. 327/2025, I.A. 4149/2025 & I.A. 5700/2026
    
                              NATIONAL PROJECTS CONSTRUCTION CORPORATION
                              LIMITED                         .....Petitioner
    
                                                Through:     Mr. Paritosh Budhiraja and Ms.
                                                             Larika Khandelwal, Advs.
    
                                                Versus
    
                              BHARAT SCOUTS AND GUIDES                       .....Respondent
    
                                                Through:     Ms. Tusha Chawla, Adv.
    
                              CORAM:
                              HON'BLE MR. JUSTICE AVNEESH JHINGAN
    
                      AVNEESH JHINGAN, J. (ORAL)
    

    1. The present petition is filed under Section 11(6) of the
    Arbitration and Conciliation Act, 1996 (for short „the Act‟) for the
    appointment of an arbitrator.

    2. The brief facts are that the parties to the lis entered into an
    agreement dated 24.02.2015 (for short „the agreement‟) for
    “Renovation and Modernization of NTC and NAI at Pachmarhi.” The
    cost submitted by the petitioner was approved by the respondent on
    30.09.2015. The petitioner issued a Notice Inviting Tender (NIT) and

    SPONSORED

    Signature Not Verified
    Signed By:CHANCHAL ARB.P. 327/2025 Page 1 of 6
    Signing Date:21.07.2026
    15:51:12
    M/s Team Engineers (for short „contractor‟) was the successful bidder.
    The project was completed and handed over to the respondent on
    25.07.2018. The final bill was raised on 28.07.2018 but was not paid.
    The respondent alleged substandard work and demanded a penalty of
    Rs. 34,18,393/-.

    2.1 The contractor filed a civil suit against the petitioner for
    recovery of the unpaid bills in December, 2022. On 01.04.2024, the
    petitioner approached the Ministry of Jal Shakti (for short „the
    Ministry‟) for resolution of the disputes through the Administrative
    Mechanism for Resolution of Central Public Enterprises Disputes
    (AMRCD) in terms of Clause 7 of the Agreement.

    2.2 The Ministry vide communication dated 20.05.2024, conveyed
    the decision of the Department of Public Enterprises dated 17.05.2024
    that the matter cannot be taken up for resolution under the AMRCD
    mechanism. The petitioner was advised to explore the resolution of
    the disputes through legal or other mechanisms. Hence, the present
    petition.

    3. Learned counsel for the petitioner contends that from Clause 7
    of the agreement, it is evident that the intention of the parties was to
    resolve the disputes through arbitration and that the intention is to be
    seen.

    4. Learned counsel for the respondent contends that there is no
    arbitration clause in the agreement and Clause 7 of the agreement

    Signature Not Verified
    Signed By:CHANCHAL ARB.P. 327/2025 Page 2 of 6
    Signing Date:21.07.2026
    15:51:12
    specifically mentions that the provisions of the Act shall not apply.
    The prayer is for dismissal of the petition.

    5. It would be relevant to quote Clause 7 of the agreement, which
    reads as under:

    “7.0 ARBITRATION OF DISPUTE
    7.1 In the event of any dispute or difference
    relating to the interpretation and application of the
    provisions of the contracts, such disputes or difference
    shall be referred by either party (OWNER &
    AGENCY) for arbitration to the Sole Arbitrator in the
    department of Public Enterprises to be nominated by
    the Secretary to the Govt, of India in-charge of the
    department of Public .Enterprises. The Arbitration and
    Conciliation Act
    1996 shall not be applicable to
    arbitration under this clause. The award of the
    arbitrator shall be binding upon the parties to the
    dispute, provided, however, any party aggrieved by
    such award made a further reference for setting aside
    or revision of the award to the law secretary, Deptt of
    Legal Affairs, Ministry of Law and Justice, Govt, of
    India, Upon such reference the dispute shall be decided
    by the law Secretary or the special
    Secretary/Additional Secretary, when so authorized by
    the Law Secretary, whose decision shall bind the
    parties conclusively. The parties to the dispute will
    share equally the cost of arbitration as intimated by the
    arbitrator.

    7.2 In the event of any dispute or difference
    relating to the interpretation and application of the
    provisions of the contracts between NPCC and its
    appointed contractors/vendors, such disputes or

    Signature Not Verified
    Signed By:CHANCHAL ARB.P. 327/2025 Page 3 of 6
    Signing Date:21.07.2026
    15:51:12
    difference shall be dealt as per contract conditions
    between them and expenditure on arbitration/court case
    shall be made by NPCC and shall be reimbursed by
    BSG including award/decree. The cost of favorable
    award/decree shall be property of the owner (BSG).”

    6. The heading of Clause 7 of the agreement is „Arbitration of
    Dispute‟ and the word „arbitration‟ has been used in the Clause. At
    first glance, it appears to be a clause for arbitration but in fact the
    clause provides a mechanism agreed between the parties for dispute
    resolution and the statutory provisions of the Act were ousted. Under
    the Clause, the Secretary to the Government of India in charge of the
    Department of Public Enterprises had to nominate an official to act as
    an arbitrator. In the eventuality of a party being aggrieved by the
    award, the remedy was provided before the Law Secretary or Special
    Secretary/Additional Secretary (authorised by the Law Secretary) and
    the decision was binding on the parties.

    7. The parties as per the unambiguous language of Clause 7 of the
    agreement agreed that the Act shall not apply to the dispute resolution
    mechanism provided under Clause 7 of the agreement.

    8. It is trite law that the words used in an arbitration agreement
    must disclose the determination and obligation of the parties to refer
    their disputes to arbitration. In the absence of an arbitration agreement
    the jurisdiction of the High Court under Section 11(6) of the Act
    cannot be invoked. Reference in this regard be made to the decision of
    the Supreme Court in Mahanadi Coalfields Ltd. v. IVRCL AMR

    Signature Not Verified
    Signed By:CHANCHAL ARB.P. 327/2025 Page 4 of 6
    Signing Date:21.07.2026
    15:51:12
    Joint Venture
    , (2022) 20 SCC 636:

    “9. In the present case, Clause 15 of the contract
    agreement is titled “Settlement of
    Disputes/Arbitration”. However, the substantive part of
    the provision makes it abundantly clear that there is no
    arbitration agreement between the parties agreeing to
    refer either present or future disputes to arbitration.

    *** *** ***

    18. For the above reasons, we have come to the
    conclusion that the invocation of the jurisdiction of the
    High Court under Section 11(6) of the 1996 Act was
    not valid and there being no arbitration agreement
    between the appellants and the respondent, no
    reference to arbitration could have been made. We
    accordingly allow the appeal and set aside the
    impugned judgment and order of the High Court dated
    29-11-2019. The respondent would, however, be at
    liberty to seek recourse to the remedy available in law
    to pursue the redressal of its grievances.

    (Emphasis supplied)

    9. The contention of learned counsel for the petitioner that the
    intention of the parties was to resolve the dispute through arbitration is
    ill-founded. The parties devised an alternative dispute resolution
    mechanism independent of the Act and the applicability of the
    provisions of the Act was agreed to be ousted. The remedy under
    Section 11(6) of the Act is not available to the petitioner aggrieved of
    refusal of the Ministry to refer the matter for dispute resolution under
    AMRCD.

    10. The petition is dismissed as not maintainable. Needless to say

    Signature Not Verified
    Signed By:CHANCHAL ARB.P. 327/2025 Page 5 of 6
    Signing Date:21.07.2026
    15:51:12
    the petitioner shall be at liberty to avail remedy in accordance with
    law.

    AVNEESH JHINGAN, J
    JULY 20, 2026/Pa

    Reportable:- Yes

    Signature Not Verified
    Signed By:CHANCHAL ARB.P. 327/2025 Page 6 of 6
    Signing Date:21.07.2026
    15:51:12



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here