National Highways Authority Of India vs S & P Infrastructures Dev (Pvt) Ltd on 30 July, 2026

    0
    3
    ADVERTISEMENT

    Delhi High Court

    National Highways Authority Of India vs S & P Infrastructures Dev (Pvt) Ltd on 30 July, 2026

                     $~11
                     *         IN THE HIGH COURT OF DELHI AT NEW DELHI
                     +         O.M.P. (COMM) 8/2017, I.A. 286/2017 & I.A. 5452/2021
                               NATIONAL HIGHWAYS AUTHORITY OF INDIA
                                                                     .....Petitioner
                                            Through: Mr. Amit Singh Chauhan, Mr.
                                                     Kuldeep Kasana and Mr.
                                                     Arindam Bhardwaj, Advocates.
                                            versus
    
                               S & P INFRASTRUCTURES DEV (PVT) LTD
                                                                                        .....Respondent
                                                       Through:          Mr. Raghvendra Upadhyay, Ms.
                                                                         Kanika Singh, Ms. Radhika
                                                                         Jindal and Ms. Purnima Jain,
                                                                         Advocates.
                               CORAM:
                               HON'BLE MR. JUSTICE OM PRAKASH SHUKLA
                                                       JUDGMENT(ORAL)
    

    % 30.07.2026

    1. The present petition filed under Section 34 of the Arbitration and
    Conciliation Act, 19961 seeks to interdict the arbitral award2 dated
    13.07.2016 passed by the Arbitral Tribunal3 comprising of Shri J.C.
    Shah, Presiding Arbitrator, Shri B.D. Joshi and Shri Ashok Wasson,
    Co-arbitrators.

    SPONSORED

    2. The brief facts of the present case would reveal that the
    Petitioner, namely, National Highways Authority of India4 is a statutory
    authority constituted under Section 3 of the National Highways
    Authority of India Act, 1988, for the development, maintenance and

    1
    “Act”, hereinafter
    2
    Also referred to as “award” or “impugned award”

    3

    “Tribunal”, hereinafter
    4
    “NHAI”, hereinafter
    Signature Not Verified
    Signed By:GUNN
    O.M.P. (COMM) 8/2017
    Signing Date:05.08.2026 Page 1 of 26
    20:46:53
    management of National Highways. The Central Government entrusted
    NHAI with the work of short-term improvement and routine
    maintenance of the Kanpur-Fatehpur section (km 457.377 to km
    508.877) and Fatehpur-Thariyaon section (km 508.877 to km 571.197)
    on NH-2 in the State of Uttar Pradesh5.

    3. Accordingly, NHAI issued a Notice Inviting Tender (NIT) in
    2012, wherein the Respondent emerged as the successful bidder quoting
    Rs.11,19,76,925/-. Thus, a Letter of Acceptance came to be issued to
    the Respondent on 06.12.2012 and in furtherance thereof, Contract
    Agreement dated 09.01.2013 was executed between the parties. The
    contract was an item-rate contract based on the bill of quantities. The
    stipulated period for execution of the work was from 25.01.2013 to
    24.01.2014.

    4. Subsequently, a Supplementary Agreement dated 01.12.2014
    was also executed between the parties relating to amendment of Clause
    25 relating to arbitration. Pursuant thereto, due to certain disputes, the
    Respondent requested NHAI for constitution of an Arbitral Tribunal.
    The Tribunal came to be constituted and after exchanging pleadings and
    arguments, the Tribunal rendered its award on 13.07.2016, which was
    received by NHAI on 14.09.2016, whereby five claims of the
    Respondent were allowed.

    5. It emerges from the record that the Tribunal awarded, (i) Claim
    No.1 relating to Loss of Profit; (ii) Claim No.3 relating to Finance

    5
    “work”, hereinafter
    Signature Not Verified
    Signed By:GUNN
    O.M.P. (COMM) 8/2017
    Signing Date:05.08.2026 Page 2 of 26
    20:46:53
    Charges; (iii) Claim No.4 relating to Final Bill/EOT Bills; (iv) Claim
    No.5 relating to Security Deposit and (v) Claim No.6 relating to RO &
    HO Overheads. However, Claim No.2 relating to Claims for idling
    charges and arbitration costs and Claim No.7 relating to cost of
    Arbitration were rejected.

    6. Aggrieved by the award, NHAI has filed the present petition
    under Section 34 of the Act challenging the said award in respect of
    Claim Nos. 1, 3, 4, 6 and the interest component.

    7. The fulcrum of the arguments advanced by the learned Counsel
    for the Petitioner is that there was absolutely no dispute regarding the
    impugned claims during execution of the work in question or even
    while submitting the final bill. Thus, according to him, the claims were
    barred by the principles of waiver, acquiescence and estoppel.

    8. The learned Counsel, as far as grant of Claim No.1 relating to
    loss of profit is concerned, has vehemently submitted that the Tribunal
    could not have awarded any compensation for loss of profit, particularly
    when the contract had been fully performed. According to him, the
    contract was never terminated and there was no contention between the
    parties relating to the performance of contract. Further, since the
    contract was fully performed, there was no question of grant of any loss
    of profit. In this regard, it is submitted that no correspondence has been
    placed on record requesting additional work or complaining of
    insufficient work fronts. Further, it is also averred that the Respondent
    never sought any variation as per Clause 38 and hence, there was no
    contractual or factual basis for any claim of loss of profit.

    Signature Not Verified
    Signed By:GUNN

    O.M.P. (COMM) 8/2017
    Signing Date:05.08.2026 Page 3 of 26
    20:46:53

    9. Learned Counsel has taken this Court to the facts and figures of
    the contract executed between the parties. It is evident from the record
    that the Petitioner issued indents worth Rs.5.91 crores, but the
    Respondent only executed work worth approximately Rs.3.18 crores,
    which depicts that the Respondent was ill-equipped to carry out the
    entire work. Further, it is argued that the Respondent produced no
    evidence to demonstrate deployment of machinery or manpower at the
    work site. It is thus averred that a dichotomy existed in awarding the
    claims in favour of the Respondent since on one hand, the Tribunal
    rejected Claim No. 2 relating to idling charges for want of evidence,
    and on the other hand, it held that adequate machinery and manpower
    had been deployed while allowing Claim No. 1. According to the
    learned Counsel, the Tribunal overlooked the minutes of meeting6 of
    the Evaluation Committee wherein it was recorded that the
    Respondent’s quoted price was already 16% below the estimated
    contract value, buttressing the fact that no profit could arise. It is argued
    that further work could only be granted once the indent already given
    stood completed, hence, the arbitral award is in breach of the
    contractual mechanism governing work through indents.

    10. As far as Claim No. 3 is concerned, the learned Counsel has
    submitted that furnishing performance guarantees was an express
    contractual obligation of the Respondent and hence, finance charges for
    obtaining guarantees cannot be shifted to the Petitioner. The learned
    Counsel has stoutly submitted that finance charges are built-in and form

    6
    “MoM”, hereinafter
    Signature Not Verified
    Signed By:GUNN
    O.M.P. (COMM) 8/2017
    Signing Date:05.08.2026 Page 4 of 26
    20:46:53
    a part of overheads and cannot be separately recovered. According to
    him, no evidence was furnished regarding blocked finances, margin
    money or the expenditure actually incurred by the Respondent. Further,
    in any case, the Respondent never raised this claim during execution or
    in the final bill. It is also submitted that no independent findings were
    rendered under this claim. Thus, the finding under Claim No. 3 is liable
    to be set aside.

    11. As far as Claim No.4 for the Final Bill and Extension of Time7
    bills/letters along with interest is concerned, it is submitted that
    payments were withheld because of poor contractual performance by
    the Respondent and that numerous letters were also issued requiring
    improvement in their performance. Further, a joint inspection revealed
    substantial mortality of median plants, giving rise to the Petitioner’s
    claim of Rs.23.13 lakh against the Respondent for the dried-up plants.
    It is also pointed out that upon request of Respondent, a re-inspection
    was also organised but Respondent did not participate in the same and
    unfortunately, the Tribunal completely ignored this correspondence and
    wrongly disallowed recoveries. According to the learned Counsel, the
    Petitioner had already legally recovered the said amount due from the
    Respondent, hence, there was no occasion for the Tribunal to have
    allowed the said claim, as it was essentially in the nature of
    counterclaim against the recoveries already made by the Petitioner.
    With respect to interest awarded, it is submitted that since the
    underlying claims are wrongly awarded, interest thereof does not arise

    7
    “EOT”, hereinafter
    Signature Not Verified
    Signed By:GUNN
    O.M.P. (COMM) 8/2017
    Signing Date:05.08.2026 Page 5 of 26
    20:46:53
    and even otherwise, it is not tenable since interest is granted from dates
    when the claim did not arise.

    12. Similarly, in regard to Claim No. 6 for reimbursement of
    underutilised Regional Office8 and Head Office9 overheads, the learned
    Counsel has contended that the Respondent failed to prove mobilisation
    or actual expenditure under the RO/HO heads and also that these
    expenses are accounted for under the overhead charges. Further, no
    evidence to this effect was produced, which was also observed by the
    Tribunal, however, the Tribunal in the most illegal manner went ahead
    in awarding this claim. It is also submitted that the standard objections
    of the claim having been never been included in monthly statements or
    the final bill, was also considered for the present claim.

    13. The learned Counsel, whilst concluding his arguments, has
    contended that the award is contrary to the terms of the contract and the
    Tribunal ignored material documentary evidence and as such the
    findings are perverse and unsupported by evidence. Additionally, the
    award seeks to rewrite the contractual bargain, which is impressible in
    law. According to him, the award is patently illegal and contrary to
    public policy warranting interference under Section 34 of the Act.

    14. In support of his arguments, learned Counsel placed reliance on
    Kanchan Udyog Ltd. v. United Spirits Ltd.10, C&P Haulage v.
    Middleton11, the Board of Trustees of V.O. Chidambaranar Port Trust

    8
    “RO”, hereinafter
    9
    “HO”, hereinafter
    10
    (2017) 8 SCC 237, Para 28-30
    11
    (1983) 3 ALL ER 94 (Pg. 117)
    Signature Not Verified
    Signed By:GUNN
    O.M.P. (COMM) 8/2017
    Signing Date:05.08.2026 Page 6 of 26
    20:46:53
    v. PSA Social Terminals Ltd. & Ors.12, Batliboi Environmental
    Engineers Ltd. v. Hindustan Petroleum Coproration Ltd. & Anr13
    . and
    Unibros v. All India Radio14.

    15. Per contra, the learned Counsel for the Respondent has
    supported the arbitral award and submits that the present petition has
    been filed by the Petitioner in the nature of an appeal, which is not
    within the scope of Section 34 of the Act, and hence, the petition
    deserves to be dismissed at the outset. According to the learned
    Counsel, the Award does not suffer from any patent illegality,
    perversity and is not in conflict with the terms of the contract or public
    policy of India.

    16. According to the learned Counsel, the Petitioner essentially
    seeks re-appreciation of evidence from this Court, which is untenable,
    as held in a catena of judgments.

    17. As far as the merits are concerned, the learned Counsel has
    submitted that the Petitioner failed to make available work
    corresponding to the tendered contract value of Rs.11.19 crores.
    According to the learned Counsel, only partial work fronts were made
    available and although machinery and manpower had been mobilised
    for execution of the entire contract, however, the desired work could
    not be achieved because of reasons directly attributable to the
    Petitioner. Consequently, the Respondent suffered expected loss of
    profit, which was rightly awarded by the Tribunal. It is also submitted

    12
    MANU/TN/3681/2017, Para 30-32
    13
    (2024) 2 SCC 375
    14
    2023 SCC OnLine SC 1366
    Signature Not Verified
    Signed By:GUNN
    O.M.P. (COMM) 8/2017
    Signing Date:05.08.2026 Page 7 of 26
    20:46:53
    that the Petitioner did not undertake any action with respect to the
    Respondent’s failure to execute the work, and instead released the
    performance guarantee and security deposit as well.

    18. It was also averred that the MoM of the Evaluation Committee
    were not part of the contract and that the Respondent was not a party to
    these minutes.

    19. With respect to the claims awarded relating to finance charges,
    the learned Counsel has submitted that the Respondent, while quoting
    rates, had factored in finance charges for bank guarantees, working
    capital and margin money for performance of the overall work and not
    for the truncated work, which the Respondent was compelled to execute
    because of the Petitioner. According to him, since the entire tendered
    quantity was allegedly not made available, those finance costs remained
    unrecovered and therefore, the Respondent sought reimbursement,
    which was rightly allowed by the Tribunal.

    20. Further, as regards the Final Bill/EOT Bills, it is submitted that
    almost thirteen running bills were submitted during the original contract
    period, out of which the 13th bill was unpaid by the Petitioner. Further,
    six additional bills submitted during the extension period also remained
    unpaid. Therefore, the Tribunal has rightly awarded the claim for
    release of outstanding bill amounts along with interest. It is averred with
    respect to the claim of RO & HO overheads that the Respondent
    claimed reimbursement of RO and HO overheads at 1% and 2%
    respectively as per trade practice, which was rightly allowed by the
    Tribunal. Moreover, the claim was based on the allegation that the
    Signature Not Verified
    Signed By:GUNN
    O.M.P. (COMM) 8/2017
    Signing Date:05.08.2026 Page 8 of 26
    20:46:53
    Petitioner failed to provide work for the entire contract value, resulting
    in under-utilisation of resources and therefore the same was rightly
    awarded in favour of the Respondent.

    21. Having heard the learned Counsel for the parties and perused the
    material on record, this Court is not inclined to allow the present
    petition for the reasons to follow.

    22. At the very outset, it is well-settled by plethora of judgments that
    the scope of interference by this Court under Section 34 of the Act is
    circumscribed. The Court exercising jurisdiction under Section 34 does
    not sit in appeal over the findings of the Arbitral Tribunal and cannot
    undertake a re-appreciation or re-evaluation of the evidence merely
    because another view may be possible. The interference is warranted
    only within the limited parameters prescribed under the statute.
    Furthermore, interference is not warranted even if the award appears to
    be unreasoned or non-speaking, unless one of the statutory grounds is
    made out.

    23. In Associate Builders v. Delhi Development Authority15, the
    Supreme Court made the following observations:

    “31. The third juristic principle is that a decision which is
    perverse or so irrational that no reasonable person would have
    arrived at the same is important and requires some degree of
    explanation. It is settled law that where:

    (i) a finding is based on no evidence, or

    (ii) an Arbitral Tribunal takes into account something irrelevant to
    the decision which it arrives at; or

    (iii) ignores vital evidence in arriving at its decision, such decision
    would necessarily be perverse.

    15

    (2015) 3 SCC 49
    Signature Not Verified
    Signed By:GUNN
    O.M.P. (COMM) 8/2017
    Signing Date:05.08.2026 Page 9 of 26
    20:46:53
    ***

    33. It must clearly be understood that when a court is applying
    the “public policy” test to an arbitration award, it does not act as a
    court of appeal and consequently errors of fact cannot be corrected.

    A possible view by the arbitrator on facts has necessarily to pass
    muster as the arbitrator is the ultimate master of the quantity and
    quality of evidence to be relied upon when he delivers his arbitral
    award. Thus an award based on little evidence or on evidence which
    does not measure up in quality to a trained legal mind would not be
    held to be invalid on this score [ Very often an arbitrator is a lay
    person not necessarily trained in law. Lord Mansfield, a famous
    English Judge, once advised a high military officer in Jamaica who
    needed to act as a Judge as follows:”General, you have a sound
    head, and a good heart; take courage and you will do very well, in
    your occupation, in a court of equity. My advice is, to make your
    decrees as your head and your heart dictate, to hear both sides
    patiently, to decide with firmness in the best manner you can; but be
    careful not to assign your reasons, since your determination may be
    substantially right, although your reasons may be very bad, or
    essentially wrong”. It is very important to bear this in mind when
    awards of lay arbitrators are challenged.] . Once it is found that the
    arbitrators approach is not arbitrary or capricious, then he is the
    last word on facts.

    ***
    42.1. (a) A contravention of the substantive law of India would
    result in the death knell of an arbitral award. This must be
    understood in the sense that such illegality must go to the root of the
    matter and cannot be of a trivial nature. This again is really a
    contravention of Section 28(1)(a) of the Act…
    42.2. (b) A contravention of the Arbitration Act itself would be
    regarded as a patent illegality — for example if an arbitrator gives
    no reasons for an award in contravention of Section 31(3) of the Act,
    such award will be liable to be set aside.”

    24. Further, in DMRC Ltd. v. Delhi Airport Metro Express (P)
    Ltd.16, the Supreme Court made the following observations:

    “34. The contours of the power of the competent court to set aside
    an award under Section 34 has been explored in several decisions
    of this Court. In addition to the grounds on which an arbitral award
    can be assailed laid down in Section 34(2), there is another ground
    for challenge against domestic awards, such as the award in the
    present case. Under Section 34(2-A) of the Arbitration Act, a

    16
    (2024) 6 SCC 357
    Signature Not Verified
    Signed By:GUNN
    O.M.P. (COMM) 8/2017
    Signing Date:05.08.2026 Page 10 of 26
    20:46:53
    domestic award may be set aside if the Court finds that it is vitiated
    by “patent illegality” appearing on the face of the award.

    ***

    36. Patent illegality may also arise where the award is in breach
    of the provisions of the arbitration statute, as when for instance the
    award contains no reasons at all, so as to be described as
    unreasoned.

    37. A fundamental breach of the principles of natural justice will
    result in a patent illegality, where for instance the arbitrator has let
    in evidence behind the back of a party.

    ***

    39. In essence, the ground of patent illegality is available for
    setting aside a domestic award, if the decision of the arbitrator is
    found to be perverse, or so irrational that no reasonable person
    would have arrived at it; or the construction of the contract is such
    that no fair or reasonable person would take; or, that the view of the
    arbitrator is not even a possible view. A “finding” based on no
    evidence at all or an award which ignores vital evidence in arriving
    at its decision would be perverse and liable to be set aside under the
    head of “patent illegality”. An Award without reasons would suffer
    from patent illegality. The arbitrator commits a patent illegality by
    deciding a matter not within his jurisdiction or violating a
    fundamental principle of natural justice.”

    25. In Parsa Kente Collieries Limited v. Rajasthan Rajya Vidyut
    Utpadan Nigam Ltd.17
    , it was held inter alia that construction of the
    terms of a contract is primarily for the Arbitrator/Tribunal to decide,
    unless an interpretation is adopted which no reasonable person could
    arrive at. Moreover, it has been consistently held in a catena of
    judgments of the Supreme Court that the Tribunal is the master of
    evidence and the Section 34 Courts cannot reassess evidence or
    substitute its own conclusions merely because another view is probable.

    17

    AIR 2019 SC 2908
    Signature Not Verified
    Signed By:GUNN
    O.M.P. (COMM) 8/2017
    Signing Date:05.08.2026 Page 11 of 26
    20:46:53

    26. Having traced the statutory contours within which an arbitral
    award shall be tested and the guiding principles of interpretation of
    contracts, this Court finds that the Petitioner is attempting to assail the
    arbitral award by contesting the interpretation of the Tribunal on facts,
    such as the finding that the MoM of the Evaluation Committee is not
    part of the contract. In the same breath, this Court also finds that the
    contract depicts in categorical and clear terms that the MoM were never
    the part of the contract.

    27. Furthermore, the Petitioner also seeks to challenge the finding
    of the Tribunal that it did not provide work fronts to the Respondent.
    This is challenged on the premise that there were no contemporaneous
    letters or any other record during execution of the contract voicing
    concerns about non-availability of work fronts. In my considered view,
    this ground seeks to challenge the interpretation of evidence by the
    Tribunal and calls for review of the case on merits. Such an enquiry
    would necessitate re-evaluation of evidence, which is beyond the
    permissible scope of jurisdiction under Section 34 of the Act.

    28. As far as the contention of the Petitioner is concerned that the
    Tribunal essentially re-wrote the contract by ignoring the MoM dated
    06.11.2012, which according to them formed part of the contract and
    that the Tribunal committed patent illegality and perversity, this Court
    finds no merit in the said submission in view of the explicit finding of
    the Tribunal that the MoM was not part of the contract and that the
    MoM was not binding. In this regard, it is trite that Courts should
    ordinarily refrain from substituting their interpretation for that of the
    arbitrator. This Court is clear in its mind that the Petitioner cannot
    Signature Not Verified
    Signed By:GUNN
    O.M.P. (COMM) 8/2017
    Signing Date:05.08.2026 Page 12 of 26
    20:46:53
    challenge the quality of the interpretation of evidence taken into
    consideration for arriving at such a decision. In my considered view,
    scope of interference would only arise in the miniscule window when
    the Tribunal, upon considering the facts presented before it, fails to
    draw an inference that ought to have been drawn or, conversely, draws
    an inference that is manifestly untenable, resulting in a gross
    miscarriage of justice.

    29. Upon a perusal of the reasoning adopted in the award, this Court
    is of the view that whether the MoM were a part of contract or not, the
    Tribunal has already rendered a clear and reasonable finding in view of
    the unambiguous stipulation in the contract as to what all
    documents/instruments are included within tits ambit. It is glaringly
    evident from a prima facie reading of the contract that the aforesaid
    MoM are not included in the list delineating the documents forming part
    of the contract. Therefore, the view taken by the Tribunal that the said
    MoM were not binding on the parties is a plausible and reasonable
    interpretation of the contractual terms, which does not warrant my
    interference under Section 34 of the Act.

    30. The contentions of the Petitioner that there were no
    contemporaneous letters or records during execution of the contract
    voicing concerns about the non-availability of work fronts and that the
    Petitioner’s non-providing of work fronts is a baseless assertion, are of
    no avail. This challenge is also based on the scope and manner in which
    the evidence has been appreciated by the Tribunal. At the cost of
    repetition, such an endeavour is well-within the competence of the
    Tribunal.

    Signature Not Verified
    Signed By:GUNN

    O.M.P. (COMM) 8/2017
    Signing Date:05.08.2026 Page 13 of 26
    20:46:53

    31. Further, the contention that the Tribunal had grossly erred in
    accepting the said evidence without an affidavit under Section 65B of
    the Indian Evidence Act, 187218 is difficult to accept. This is because
    of two reasons. Firstly, Section 1 of the IEA stipulates that it is not
    applicable to proceedings before the Arbitrator and Section 19 of the
    Act mandates that an Arbitrator shall not be bound by the IEA.
    Secondly, no such objection was taken on behalf of the Petitioners at
    the appropriate stage, that is, before the Tribunal.

    32. Having failed to raise the aforesaid objection before the
    Tribunal, the Petitioner cannot be permitted to raise the same for the
    first time in the present proceedings. The fact as to whether the adequate
    evidence has been provided by the Respondent about non-availability
    of work fronts along with the onus of proving availability of work fronts
    is undoubtedly a factual determination, which cannot be undertaken by
    this Court in the light of the precedents cited above.

    33. It also emerges from the record that the work which was
    provided to Respondent was satisfactorily completed, as is evident from
    the Petitioner’s Office Note dated 12.09.2014 that the “contractor has
    completed the work” and the release of performance bank guarantees.
    The onus was on the Petitioner to provide evidence to support its
    contention that the work fronts were duly provided but the Respondent
    did not complete the same.

    34. With respect to the contention that the award is not in
    consonance with Sections 54 and 73 of the IEA, the Petitioner failed to

    18
    “IEA”, hereinafter
    Signature Not Verified
    Signed By:GUNN
    O.M.P. (COMM) 8/2017
    Signing Date:05.08.2026 Page 14 of 26
    20:46:53
    specifically mention or demonstrate as to how these provisions have not
    been complied with by the Tribunal. In any case, this Court is conscious
    of the fact that the Supreme Court has authoritatively clarified that a
    mere erroneous application of law does not warrant any interference on
    the ground of patent illegality. Paragraph 37 of the decision in
    Ssangyong Engg. & Construction Co. Ltd. v. NHAI19, is relevant to
    the present context, it is reproduced thus:

    “37. Insofar as domestic awards made in India are concerned, an
    additional ground is now available under sub-section (2-A), added by the
    Amendment Act, 2015, to Section 34. Here, there must be patent illegality
    appearing on the face of the award, which refers to such illegality as goes
    to the root of the matter but which does not amount to mere erroneous
    application of the law. In short, what is not subsumed within “the
    fundamental policy of Indian law”, namely, the contravention of a statute
    not linked to public policy or public interest, cannot be brought in by the
    backdoor when it comes to setting aside an award on the ground of
    patent illegality.”

    (emphasis supplied)

    35. In relation to Claim No.1 pertaining to loss of profit, the relevant
    consideration is not merely the value of indents issued by the Petitioner,
    but whether the Respondent was prevented from executing the balance
    contractual work due to circumstances attributable to the Petitioner. The
    Tribunal, after examining the material on record, returned the finding
    that the Respondent completed the entire work made available to it
    amounting to Rs.3,18,66,623.93/- and was prevented from completing
    the balance work amounting to Rs.8,01,10,301/- due to non-handing
    over by the Petitioner. Such a finding, even if open to another
    interpretation, cannot be substituted by this Court unless it is shown to

    19
    {2019) 15 SCC 131
    Signature Not Verified
    Signed By:GUNN
    O.M.P. (COMM) 8/2017
    Signing Date:05.08.2026 Page 15 of 26
    20:46:53
    be wholly perverse, unreasonable, unsupported by evidence or going to
    the root of the matter.

    36. Although, it has been contended by the Petitioner that it had
    issued the indents amounting to Rs.5,91,68,860/- and the Respondent
    could only complete the work amounting to Rs.3,18,66,923.93/-,
    thereby, demonstrating the Respondent’s inability to complete the
    indented work; therefore, is it submitted that no question of any loss of
    profits arises for the balance work for which, admittedly, indents were
    not issued. This contention proceeds on an erroneous premise.
    According to this Court, the said assumption appears to be a wrong
    understanding on the part of the Petitioner for the simple reason that it
    is evident from the record that the contract was about Rs.11 crores and
    the Respondent could execute work of around Rs. 3 crores. The non-
    availability of work is also attributed to the Petitioner. Therefore, this
    Court finds no anomaly in the grant of loss of profit to the Respondent
    and hence, the conclusion arrived at by the Tribunal cannot be said to
    suffer from any patent illegality or perversity. The Tribunal has
    considered the relevant contractual provisions and the evidence placed
    before it while awarding compensation towards loss of profit on the
    unexecuted portion of the contract. This Court finds no apparent
    infirmity in the reasoning adopted by the Tribunal, which appears to be
    a plausible and reasonable view based on the material available on
    record.

    37. Further, it would be profitable to quote the reasoning arrived by
    the Tribunal, which seems to be plausible and reasonable and forms the
    basis for allowing the said claim. This reasoning demonstrates that the
    Signature Not Verified
    Signed By:GUNN
    O.M.P. (COMM) 8/2017
    Signing Date:05.08.2026 Page 16 of 26
    20:46:53
    Tribunal applied its mind to the facts and circumstances of the case and
    arrived at a conclusion which, at the very least, represents a possible
    and legally permissible view. Consequently, not warranting
    interference by this Court. The relevant excerpt is as under:

    “65.16. With regard to the Respondent’s submission that the
    Letter of Acceptance was de facto limited to Rs.6,96,19,750/-. AT
    noticed from the facts on record that in response to the Notice
    inviting Tender for the Project for specified Quantities referred in
    the Bill of Quantities for whole works to be completed, the Claimant
    submitted its Bid quoting rate for the Items referred in the Bill of
    Quantities at the tendered amount of Rs. 11,19,76,925/-.

    65.17. The Respondent vide letter dated 06.12.2012 communicated
    to the Claimant acceptance of its tender at the tendered amount of
    Rs.11,19,76,925/-. Accordingly, based on such tendered/Contract
    amount, the Claimant was called upon to furnish Performance
    Securities of Rs.1,11,97,692/- & Rs. 11,19,769/- as per paras 33.2
    & 33.1 of ITB i.e. 10% % 1% respectively.

    65.18. Thereafter, Agreement dated 09.01.2013 was signed by the
    parties in that reiterating the Respondent has accepted the
    Claimant’s Bid for execution and completion of the work and
    remedying the defects at a cost of Rs. 11,19,76,925/-.

    65.19. However, the Respondent as an afterthought for the first time
    in its Amended Reply dated 07.03.2016 to the Claim Statement has
    come up with a plea that the total value of the Contract was
    Rs.6,96,19,750/- by referring minutes of meeting of their evaluation
    committee.

    65.20. AT has carefully analysed and find that neither Letter of
    Acceptance dated 06.12.2012 пor Contract Agreement dated
    09.01.2013 made a suggests Minutes of Meeting of the Respondent’s
    evaluation Committee as part of it. Further, the Claimant is not a
    party to the said Minutes of the Meeting of the Respondent’s
    Evaluation Committee, rather the last para of it is self-explanation
    that “The evaluation committee recommended to award the work to
    the lowest bidder i.e. “M/s. S&P Infrastructure Developers (P) Ltd
    at a bid amount of Rs.11,19,76,925/- (Rupees Eleven Crore Nineteen
    Lakhs Seventy Six Thousand Nine Hundred Twenty Five only)
    subject to the submission of performance security of 10% as per
    Clause 33.1 of the bid document and to furnish additional BG
    corresponding to 1% amount of the quoted rates i.e. 11,19,769/- due
    to the bid being below more than 15%”. Accordingly, the
    Respondent issued Letter of Acceptance dated 06.12.2012 stating
    Signature Not Verified
    Signed By:GUNN
    O.M.P. (COMM) 8/2017
    Signing Date:05.08.2026 Page 17 of 26
    20:46:53
    the Contract Price of Rs.11,19,76,925/-and the Contract Agreement
    dated 09.01.2013 was signed by the parties referring the Contract
    price of Rs.11,19,76,925/- for completion of whole works and more
    so, the Respondent did not raise such a contention either in their
    earlier Reply to the Claim statement or in the Evidence by way of
    Affidavit, further there is no document on record which suggests the
    Contract was for Rs.6,96,19,750/- or such Minutes of Meeting are
    part of the Letter of Acceptance or it has effect of reducing the scope
    of Agreement or the Claimant was aware of such reduction in the
    scope of Agreement. The observation of the Evaluation Committee
    in the Minutes of Meeting that the Project Director of the
    Respondent be directed not to get executive positive and negative
    variation about 25% in respect of specified items does not conclude
    or suggest that the Letter of Acceptance was de fecto limited to
    Rs.6,96,19,750/-.

    65.21. Thus, for the facts as aforesaid, the AT does not agree with
    the Respondent’s submission that the total value of the Contract was
    Rs.6,96,19,750/-by referring to the minutes of meeting of its
    evaluation committee contending that the Letter of Award was de
    facto limited to the said amount of Rs.6,96,19,750/- as it is a part of
    the Agreement. However, AT accepts the submissions of the
    Claimant that the tendered/Contract amount for which Letter of
    Acceptance & the execution of Agreement was for Rs.11,19,76,925/-

    65.22. With regard to the Respondent’s submission the Claimant
    hardly completed the work of Rs.3,18,66,923/- against the Indents
    value of Rs.5,91,68,860/- despite having issued Indent as per Clause
    27.1 of Agreement, the AT noticed that admittedly, totally value of
    the work done by the Claimant during contractual period till
    24.01.2014 is Rs.3,18,66,623.93. It is also an admitted fact that the
    Respondent’s Project Director is his Office Note dated 12.09.2014
    (filed by the Claimant along with its Rejoinder at Page 457)
    confirmed that “The Contractor was mobilized at site and
    commenced the work from 25.01.2013. The Contractor took up the
    work as per the programme given by the Engineer….. The Original
    Contract period of one year expired on 24.01.2014 and accordingly
    the defect liability period of 6 Months is expired on 24.07.2014. The
    Contractor has completed the work and the Defect Liability period
    is over so the bank guarantee may be released (Clause 33, 44.2 &
    47.1 of the Contract Agreement). Accordingly, Performance Bank
    Guarantee were released by the Respondent. However, the
    Respondent did not produce any letter/notice on record or the
    Engineer’s Report that the Claimant was not having the required
    manpower or machinery since 25.01.2013 over the period till
    completion of Contract i.e. 24.01.2014 or it has caused delay in
    execution of that it was not interested in execution of work beyond

    Signature Not Verified
    Signed By:GUNN
    O.M.P. (COMM) 8/2017
    Signing Date:05.08.2026 Page 18 of 26
    20:46:53
    Rs. 3,18,66,623.93 despite availability of work fronts. The
    Respondent also did not clarify and substantiate:

    (i) Why no notice was issued to the Claimant for completing
    remaining works of the indents;

    (ii) Why no action was initiated under risk & cost for the balance
    incomplete work of the Indents:

    (iii) What is the exact location of the work fronts for the balance
    works of Indents stated to be-not executed by the Claimant?

    (iv) Why no action was initiated under Clauses 45 & 53 of the
    Contract Agreement;

    (v) Why Indents were not issued confirming to provisions of
    contact data (Page 95,/C.A) in piecemeal?

    (vi) Why the indents contract/tendered for entire amount of
    Rs.1,19,76,925/- were not issued as per Clause 27.1 of the
    Agreement within the contract period of 12-months;

    (vii) Why the time was not extended for completing the balance
    intended work and/or for the balance contract
    value/tendered amount.

    (viii) Why no Management meetings were called by the Engineer
    as per the provision of contract Clause 3G(Page 81,
    Contract Agreement, C.A.), when the Claimant contractor
    was not executing the work for months together?

    65.23. The Respondent also did not deny or dispute the correctness
    of facts recorded in its Office Note dated 12.09.2014 wherein
    admitting that The Contractor was mobilized at site and commenced
    the work from 25.01.2013. The Contractor took up the work as per
    programme given by the Engineer. The Original Contract period of
    one year expired on 24.01.2014 and accordingly the defect liability
    period of 6 Months is expired on 24.07.2014. The Contactor has
    completed the work and the Defect Liability Period is over so the
    bank guarantee may be released (Clause: 33. 44.2 & 47.1 of the
    Contract Agreement). The Respondent further failed to furnish any
    reason as to why Performance Bank Guarantees were released by
    it, when it is contended that the Claimant did not complete the work
    of the value of Rs.5,91,68,860/- indented.

    65.24. Thus, AT does not agree with the Respondent’s submission
    that the Claimant hardly completed the work of Rs.3,18,66,923/-
    against the Indents value of Rs.5,91,68,86/- despite having issued
    the Indents as per Clause 27.1 of Agreement. However. AT is of the
    consul view that the Claimant has completed the entire work of
    Rs.3,18,66,623.93 on the work fronts made available to against the
    tendered/contract amount of Rs.11,19,76,925/-and agree with the
    Claimant’s submissions that it was prevented from completing
    balance tendered/contract amount of Rs.8,01,10,301/-
    (Rs.11,19,76.925.00- Rs.3,18,66,623.93) due to it non-handling
    over the work fronts for such balance work of Rs.8,01,10,301/-.

    Signature Not Verified
    Signed By:GUNN

    O.M.P. (COMM) 8/2017
    Signing Date:05.08.2026 Page 19 of 26
    20:46:53
    65.25. Herein, AT does not find necessary that the Claimant has to
    make a prayer separately for deciding the breach in respect of its
    Claim, when the Claim of the Claimant is itself for the breach of the
    Respondent for allowing the execution of work of Rs.3,18,66,623.93
    only against the tendered/contract amount of Rs.11,19,76,925/-
    resulted in loss of profit due to very less work provided by the
    Respondent.

    65.26. With regard to the claim in respect of Dispute No.l has not
    been included in the final bill, hence it is barred, in this context the
    finding of the AT are given in para 31 to 60 above.

    65.27. The reference to the provisions contained in Clause 39 & 41
    of the Agreement in defence to the claim of the Claimant are not
    applicable, as the present claim of the Claimant is neither under the
    ‘Compensation Events’ described under Clause 41 or for the
    Variation. Thus, it was not necessary upon the Claimant to raise
    such a claim for the loss of profit due to very less work provided by
    the Respondent in the Bills or the Final Bill. This claim of the
    Claimant is well maintainable under the law. namely Sections 73 &
    54 of the Contract Act, 1872.

    65.28. The Respondent’s submission that the Claimant had failed to
    demonstrate the rate of profit, it is noticed that the Respondent does
    not deny or dispute the 10% profit claimed by the Claimant as per
    usage of trade referred in the Standard Data Book for Analysis of
    Rates of MORTH applicable in its Department.

    65.29. Considering the evidence on record. AT is of the considered
    view that the Claimant had deployed the required manpower and
    machinery all throughout over the Project length of113.82 Km as
    per detail furnished in its letter dated 07.03.2016, samely the
    Claimant’s own machinery and the machinery arranged on lease
    and deployed the required manpower for carrying on the work of
    Rs.11,19,76,925/-within the contract period months commencing of
    12-from 25.01.2013 to 24.01.2014. The claimant was having the
    required machinery and the manpower at Site for completing
    balance work of Rs.8,01 J 0.301/-within the contractual period of 12
    months and thus, entitled for loss of profit due to very less work
    provided by the Respondent and hold that the breach is on the part
    of the Respondent in not providing the work fronts for the balance
    tendered/contract amount of Rs.8,01,10,301/-.

    65.30. For the reasons aforesaid, AT agrees with the arguments of
    the Claimant that it was prevented in completing the balance work
    of Rs.8.01.10,301/- as such entitled to the Loss of Profit @10% on
    less work provided by the Respondent. Accordingly, AT accept the
    Signature Not Verified
    Signed By:GUNN
    O.M.P. (COMM) 8/2017
    Signing Date:05.08.2026 Page 20 of 26
    20:46:53
    claim of the Claimant for loss of profit @10% based upon Standard
    Data Book for Analysis of Rates of MORTH, UPPWD and the
    citations (judgments on record) due to very less work provided by
    the Respondent.”

    38. The contention advanced by the Petitioner that there is a
    dichotomy in the findings of the Tribunal, inasmuch as it applied
    different standards by rejecting one claim due to lack of
    contemporaneous evidence and accepting another claim based largely
    on a disputed letter dated 12.04.2014, also does not merit acceptance
    since Claim Nos.1 and 2 were completely different. Claim No.1 was for
    loss of profits for the non-executed amount of present contract, which
    was granted by the Tribunal as it was attributable to the Petitioner for
    not providing the complete work front. On the other hand, Claim No.2
    was for the loss of profits due to idling of machines and other resources,
    which could have been earned by the Respondent in the time period
    when the delay was caused and it could not take up another work due
    to utilization of resources in the current contract. This claim was denied
    by the Tribunal since no “contemporary record” or other sufficient
    evidence was produced to this effect and that the Respondent did not
    mention this before or while invoking arbitration. Thus, the distinction
    drawn by the Tribunal between loss of profit on unexecuted contract
    value and idling charges is sound and legally sustainable. While the
    former concerns loss arising from non-execution of the balance work
    due to alleged breach, whereas the latter requires specific proof of
    actual idling of resources, deployment and corresponding financial loss.
    Therefore, rejection of idling charges while allowing loss of profit does
    not by itself constitute an inconsistent or contradictory approach.

    Signature Not Verified
    Signed By:GUNN

    O.M.P. (COMM) 8/2017
    Signing Date:05.08.2026 Page 21 of 26
    20:46:53

    39. Similarly, the other ground taken by the Petitioner relating to the
    finance charges and RO/HO overheads being wrongly awarded
    separately because the Standard Data Book already includes such
    components within overheads, is again based on re-appreciation of
    evidence. Thus, in substance, the Petitioner’s challenge in this regard is
    limited to the Tribunal’s evaluation of the evidence led by parties. As
    noted above, the scope of examination of an arbitral award is extremely
    limited. Nonetheless, this contention is also not factually correct in view
    of the specific finding in the award that the Respondent can make
    separate claim for the constituents falling under “overheads” so long as
    they do not exceed the maximum threshold of 10% of the tendered
    amount, as provided by the Standard Data Book. Thus, the Arbitral
    Tribunal did not permit any unrestricted or double recovery. The
    objection raised by the Petitioner essentially concerns the manner in
    which the Tribunal appreciated contractual provisions and assessed
    evidence regarding entitlement. Unless such appreciation results in a
    finding which ignores the contract altogether or clearly permits double
    recovery, the same cannot constitute patent illegality within the
    meaning of Section 34 of the Act.

    40. Regarding the final bill and EOT bills, the Tribunal considered
    the rival assertions regarding recoveries, deductions and outstanding
    payments. The existence of disputed factual issues itself shows that the
    matter falls within the domain of the Tribunal. This Court, while
    exercising jurisdiction under Section 34, cannot reassess whether the
    deductions claimed by the Petitioner ought to be accepted or rejected,
    unless the findings of the Tribunal are shown to be perverse, irrational,
    or contrary to the fundamental legal principles. The Tribunal, after
    Signature Not Verified
    Signed By:GUNN
    O.M.P. (COMM) 8/2017
    Signing Date:05.08.2026 Page 22 of 26
    20:46:53
    considering the material placed before it, arrived at a cogent conclusion
    regarding entitlement of the Respondent towards the outstanding
    amounts. Such a determination, being based on appreciation of
    evidence and interpretation of contractual terms, does not warrant
    interference merely because a different view is possible.

    41. In the present case, no case has been made out by the Petitioner
    that the arbitral award is contrary to the fundamental policy of India.
    The arbitral award cannot, by any stretch of imagination, be considered
    to be opposed to justice or morality as well.

    42. The grounds essentially raised in the instant petition under
    Section 34 of the Act only pertain to re-appreciation of evidence and
    seeks a review on merits. Needless to state that there is no question that
    such an approach falls beyond the permissible limits of judicial
    interference under the statute.

    43. Insofar as the ground of patent illegality is concerned, it is clearly
    established in Associate Builders (supra), this Court does not sit in
    appeal while undertaking whilst scrutinising an arbitral award from the
    lens of public policy. Thus, an award merely based on little evidence or
    an award not of stout quality will not render it otiose. At the cost of
    repetition, the arbitrator “is the ultimate master of the quantity and
    quality of evidence”. Therefore, the correctness of the Tribunal’s
    factual conclusions cannot be tested by undertaking a fresh evaluation
    of the evidence. The limited question before this Court is only whether
    the view taken by the Tribunal is a possible and plausible view based
    upon the material placed before it and within the parameters of the
    Signature Not Verified
    Signed By:GUNN
    O.M.P. (COMM) 8/2017
    Signing Date:05.08.2026 Page 23 of 26
    20:46:53
    contract. Only if the award is based on no evidence, or if irrelevant
    evidence is considered or if something material has been overlooked,
    can this Court come to the rescue of the Petitioner.

    44. Accordingly, once this Court is of the view that the Tribunal’s
    approach is not arbitrary or capricious and is founded upon a reasonable
    appreciation of the material available on record, then the Tribunal has
    the last word on facts. The aforesaid view is also reiterated by the
    Supreme Court in P.R. Shah, Shares & Stock Brokers (P) Ltd. v.
    B.H.H. Securities (P) Ltd20
    .

    45. As is apparent from the foregoing, the evaluation of evidence by
    the Tribunal may, at best, be alleged to be erroneous and perhaps this
    Court may have taken a different view but that is not the scope of
    examination under Section 34 of the Act and this Court cannot interfere
    with the arbitral award merely on the ground that it does not concur
    with the inference drawn by the Tribunal from the evidence led by the
    parties. The legislative intent behind Section 34 is to restrict judicial
    intervention and not to provide a forum for an appeal on merits against
    the findings of the Tribunal. In Ssangyong Engineering (supra), the
    Supreme Court had authoritatively held that, “reappreciation of
    evidence, which is what an appellate Court is permitted to do, cannot
    be permitted under the ground of patent illegality appearing on the face
    of the award.”

    46. Turning to the precedents relied upon by the Petitioner, the
    reliance placed on Kanchan Udyog Ltd. (supra), Board of Trustees of

    20
    (2012) 1 SCC 594
    Signature Not Verified
    Signed By:GUNN
    O.M.P. (COMM) 8/2017
    Signing Date:05.08.2026 Page 24 of 26
    20:46:53
    V.O. Chidambaranar Port Trust (supra), Batliboi Environmental
    Engineers Ltd.
    (supra), Unibros (supra) and C&P Haulage (supra) is
    of no avail. Judgments are to be applied keeping in mind the entirety of
    facts and circumstances of the case at hand and not like Euclid’s
    theorem. These decisions do not come to the rescue of the Petitioner
    particularly in view of the cogent findings returned by the Tribunal
    based on evidence on record including the Petitioner’s admission in its
    office note that the Respondent had completed the work, which is also
    evident from release of the security deposit and performance guarantee
    and the categorical conclusion of the Tribunal that the Petitioner is
    liable for not providing the remaining work to the Respondent.

    47. As a sequitur to the foregoing, the Petitioner has failed to
    establish the existence of any ground contemplated under Section 34 of
    the Act warranting interference with the impugned award. The
    challenge raised by the Petitioner essentially seeks re-appreciation of
    evidence and re-consideration of the merits of the dispute, which is
    impermissible within the limited scope of jurisdiction available under
    Section 34 of the Act.

    48. This Court is unable to accept the contention that interference in
    the arbitral award is warranted merely because the Tribunal has arrived
    at an erroneous conclusion on the evidence led by the parties.

    49. In my considered view, the arbitral award does not offend any
    of the grounds envisaged under Section 34 of the Act. The findings of
    the Tribunal well-reasoned and are based on cogent inference and
    interpretation of the material on record. Therefore, no grounds for any
    Signature Not Verified
    Signed By:GUNN
    O.M.P. (COMM) 8/2017
    Signing Date:05.08.2026 Page 25 of 26
    20:46:53
    interference with the arbitral award are made out in terms of Section 34
    of the Act.

    50. The petition is accordingly dismissed. No order as to costs.

    51. Pending applications, if any, are disposed of.

    OM PRAKASH SHUKLA, J.

    JULY 30, 2026/gunn

    Signature Not Verified
    Signed By:GUNN
    O.M.P. (COMM) 8/2017
    Signing Date:05.08.2026 Page 26 of 26
    20:46:53



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here