National Highways Authority Of India vs M/S Kurukshetra Expressway Private Ltd on 28 July, 2026

    0
    2
    ADVERTISEMENT

    Delhi High Court

    National Highways Authority Of India vs M/S Kurukshetra Expressway Private Ltd on 28 July, 2026

    Author: Sachin Datta

    Bench: Sachin Datta

                              $~J
                              *     IN THE HIGH COURT OF DELHI AT NEW DELHI
                              %                                 Judgment pronounced on: 28.07.2026
                              +     O.M.P. (COMM) 542/2024, IA No.48442/2024, IA No.540/2025
    
                                    NATIONAL HIGHWAYS AUTHORITY OF INDIA ..... Petitioner
                                                 Through: Mr. A.K. Nijhawan and Mr. Abdul
                                                          Vahiel, Advocates.
                                                 versus
                                    M/S KURUKSHETRA EXPRESSWAY PRIVATE LTD.
                                                                              ..... Respondent
                                                 Through: Mr. Sandeep Sethi, Sr. Adv., Mr.
                                                          Dayan Krishnan, Sr. Adv., Mr. Rishi
                                                          Aggarwal, Mr. Sunil Mittal, Mr.
                                                          Daksh Arora, Ms. Shruti Arora, Mr.
                                                          Anant Shukla and Mr. Sukrit Seth,
                                                          Advocates.
                                    CORAM:
                                    HON'BLE MR. JUSTICE SACHIN DATTA
    
                                                       JUDGMENT
    

    IA No.540/2025

    1. The present application has been filed by the respondent seeking
    dismissal of the petition filed under Section 34 of the Arbitration and
    Conciliation Act, 1996 challenging the arbitral award dated 16.08.2024,
    primarily on two grounds: (i) limitation, and (ii) suppression of material
    documents.

    SPONSORED

    2. The respondent contends that the petition has been filed beyond the
    mandatory limitation period prescribed under Section 34(3) of the Act. The
    award was passed on 16.08.2024 and the statutory period of three months
    expired on 16.11.2024.

    O.M.P. (COMM) 542/2024 Page 1 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51

    3. It is submitted that as per case history, as on 29.11.2024 no award, no
    Vakalatnama, and not even the memo of parties was filed. In fact, only 69
    pages were filed. No single document/Annexure was filed. It is contended
    that the same amounts to a ‘non-est’ filing.

    4. Reliance has been placed on Brahmaputra Cracker & Polymer Ltd.
    v. Rajshekhar Construction Pvt. Ltd., 2023/DHC/000642
    .

    5. It is submitted that the petition was effectively filed only on
    12.12.2024 (registered on 13.12.2024) without any application seeking
    condonation of delay and is therefore liable to be dismissed as time-barred.

    6. The respondent further alleges that the petitioner deliberately
    suppressed material documents. While the arbitral record comprised
    approximately 4,574 pages, the petitioner filed only 134 pages, omitting
    several documents that formed the very basis of the Tribunal’s findings.

    7. It is submitted that the omitted documents include the
    “Disaggregation Letter” dated 04.02.2019, Independent Engineer’s Letter
    dated 27.01.2022 and 29.03.2022, Statement of Claim, Statement of
    Defence, evidence affidavits, cross-examination transcripts, letter dated
    25.02.2022 issued by Bank of Baroda, relevant provisions of the Concession
    Agreement, the Financial Model, and the Loan Agreement.

    8. The respondent submits that the petitioner has selectively placed
    documents on record to present an incomplete and misleading picture.

    9. The petitioner opposes the respondent’s application for dismissal and
    contends that the Section 34 petition is within the prescribed limitation
    period and is not liable to be rejected on technical grounds.

    10. The petitioner submits that the arbitral award was passed on
    16.08.2024 and the Section 34 petition was initially filed on 13.11.2024,

    O.M.P. (COMM) 542/2024 Page 2 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51
    well within the statutory period of three months. As per the submissions of
    the petitioner, the petition was accompanied by the arbitral award, relevant
    portions of the Concession Agreement, the vakalatnama, and the memo of
    parties. The subsequent re-filings were only to cure defects raised by the
    Registry and to place additional pages of the Concession Agreement on
    record pursuant to instructions from NHAI. The objections were ultimately
    removed on 12.12.2024, and the petition was listed on 17.12.2024. It is,
    therefore, asserted that the petition does not suffer from delay or latches, and
    the judgments relied upon by the Respondent to make out a case of ‘non-est’
    filing, are inapplicable.

    11. The petitioner further denies any suppression of material documents,
    contending that the entire Concession Agreement was eventually placed on
    record and that the petition itself sought summoning of the complete arbitral
    record, which is the normal practice in proceedings under Section 34.

    12. The petitioner maintains that the petition complies with all procedural
    requirements and that there has been no concealment of facts or documents.

    13. It is further prayed that, in the event this Court comes to the
    conclusion that the present petition has been filed beyond the prescribed
    period of three months, this Court may be pleased to condone the delay.

    14. Having heard the learned counsel for the parties this Court is not
    inclined to allow the present application. It is the petitioner’s case that the
    present petition was initially instituted on 13.11.2024, well within the
    prescribed limitation period of three months under Section 34(3) of the
    Arbitration and Conciliation Act, 1996. The petitioner has specifically
    averred that, at the time of the initial filing, the petition was accompanied by
    the arbitral award, the relevant extracts of the Concession Agreement, the

    O.M.P. (COMM) 542/2024 Page 3 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51
    Vakalatnama, and the Memo of Parties. The subsequent re-filings were
    undertaken to cure the defects pointed out by the Registry. The Registry’s
    objections were ultimately removed on 12.12.2024, whereafter the matter
    was listed before the Court on 17.12.2024.

    15. The specific averments made by the petitioner in its reply dated
    04.02.2025 are reproduced as under –

    “That the contents of para no.4 of the Application, It is contended by
    the Respondent that “as on 29.11.2024, no Award, no Vakalatnama
    and not even the Memo of Parties was filed”. In fact, on 13.11.2024,
    the Petition alongwith Award and the relevant pages of the Contract
    Agreement, Vakalatnama and Memo of Parties was filed before this
    Hon’ble Court, to which the Registry of this Hon’ble Court had raised
    objections. It is submitted here that during the process of removing the
    Objections NHAI instructed the Counsel to file the more Agreement
    pages may be filed such that during admission, in case certain queries
    are raised’ by the Hon’ble Court the same could be replied effectively.
    It may be relevant to mention that the Agreement was apart of the
    Arbitration record and Petitioner had prayed that the same be called
    for, however, in view of the instructions Petitioner refiled the Petition
    with while removing fresh objections raised by the Registry, on
    14.11.2024,”‘02.12.2024, 07.12.2024, 11.12.2024. Finally objection
    were removed on 12.12.2024 and petition listed on 17.12.2024.”

    16. Even in a situation where the petition under Section 34 was not filed
    within the initial period of three months from the date on which the
    petitioner received the arbitral award, Section 34(3) of the Arbitration and
    Conciliation Act, 1996 expressly empowers the Court to entertain such an
    application within a further period of thirty days, provided the applicant
    establishes sufficient cause for not filing the application within the
    prescribed period of three months. Section 34(3) reads as under –

    “(3) An application for setting aside may not be made after three
    months have elapsed from the date on which the party making that
    application had received the arbitral award or, if a request had been
    made under section 33, from the date on which that request had been
    disposed of by the arbitral tribunal:

    O.M.P. (COMM) 542/2024 Page 4 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51

    Provided that if the Court is satisfied that the applicant was prevented
    by sufficient cause from making the application within the said period
    of three months it may entertain the application within a further
    period of thirty days, but not thereafter.”

    17. In Panjab Ali Alias Punjab Ali and Ors. v. State of West Bengal and
    Ors., AP/92/2025 (order dated 19.1.2026), the Calcutta High Court has
    observed as under –

    Section 34(3) of the Arbitration and Conciliation Act, 1996 mandates
    that an application for setting aside an arbitral award must be made
    within a period of three months from the date on which the party
    making the application receives the arbitral award. The proviso to
    Section 34(3) permits the Court, upon sufficient cause being shown, to
    entertain the application within a further period of thirty days, but not
    thereafter. Thus, the outer limit prescribed by law for filing a petition
    under Section 34 is three months plus thirty days, i.e., a total of 120
    days from the date of receipt of the award.

    This position has been consistently reaffirmed, inter alia, in Simplex
    Infrastructure Ltd. v. Union of India
    , (2019) 2 SCC 455, wherein the
    Supreme Court reiterated that an application for setting aside an
    arbitral award must be filed within three months from the date of
    receipt of the award, extendable only by a further period of thirty days
    on sufficient cause being shown, and not beyond. Any delay beyond
    the outer limit of 120 days renders the application non-maintainable,
    and the Court is rendered functus officio for the purpose of condoning
    such delay.”

    18. It is also well settled that Section 34(3) of the A&C Act governs the
    initial institution of a petition; it has no application to delay thereafter
    occasioned in curing defects pointed out by the Registry and in re-filing. In
    Northern Railway v. Pioneer Publicity Corporation Pvt. Ltd., (2017) 11
    SCC 234, the Supreme Court held that the rigours of Section 34(3) are
    confined to the original presentation of the petition, and that delay in
    removal of office objections and re-filing does not attract the same standard,
    nor does it relate back so as to render an originally timely petition time-

    O.M.P. (COMM) 542/2024 Page 5 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51

    barred. The several re-filings effected by the petitioner on 14.11.2024,
    02.12.2024, 07.12.2024 and 11.12.2024, culminating in removal of
    objections on 12.12.2024, were accordingly steps in the process of curing
    defects in a petition already instituted within limitation on 13.11.2024, and
    stand on a wholly different footing from the institution of a fresh petition.

    19. In the present case, the arbitral award is dated 16.08.2024. The
    petition was initially filed on 13.11.2024, and after curing all the defects
    pointed out by the Registry, it was ultimately re-filed on 12.12.2024. Thus,
    even reckoning the period up to the date of re-filing, the petition was
    brought on record within the outer limit of 120 days contemplated under
    Section 34(3) of the Act. Considering that the aforesaid outer limit has not
    been breached, even assuming that there was some delay (although it does
    not appear to be so), the same would be liable to be condoned given the
    voluminous nature of the record and the attendant facts and circumstances.
    As such, no ground is made out to reject the petition on the ground of
    limitation.

    20. It is also significant to note that the petitioner has, in the prayer clause
    of the petition itself, sought summoning of the records from the learned
    Arbitral Tribunal. Had there been any intention on the part of the petitioner
    to suppress any material document, such a prayer would not have been
    made. This circumstance lends support to the petitioner’s contention that
    there was no deliberate concealment or withholding of any document from
    the Court.

    21. In view of the aforesaid facts and circumstances, this Court finds no
    merit in the present application. The same is, accordingly, dismissed.

    O.M.P. (COMM) 542/2024 Page 6 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51

    O.M.P. (COMM) 542/2024 and IA No.48442/2024

    22. The present petition assails an arbitral award dated 16.08.2024
    rendered in relation to disputes between the parties arising under a
    Concession Agreement dated 13.07.2010. The said Agreement pertains to
    the design, construction, development, finance, operation and maintenance
    of the four-laning of the Rohtak-Bawal Section of NH-71, from KM
    363.300 (design KM 363.300) to KM 450.800 (design KM 445.853), under
    NHDP III in the State of Haryana.

    23. The claimant (respondent herein), M/s Kurukshetra Expressway Pvt.
    Ltd., is a Special Purpose Vehicle jointly promoted by M/s JMC Projects
    (India) Ltd (Lead member) and M/s SREI Infrastructure Finance Limited.

    24. The request for qualification for the short-listing of bidders in
    connection with the aforesaid project was issued by the National Highways
    Authority of India (NHAI) on 16.04.2009. Pursuant thereto, a bidding
    process was conducted, culminating in the issuance of the Letter of Award
    dated 04.02.2010 in favour of the respondent/concessionaire. Thereafter, the
    Concession Agreement was executed on 13.07.2010, contemplating a
    concession period of 28 years from the appointed date, i.e., 10.05.2011.

    25. Provisional Completion Certificates were issued on 24.08.2013 and
    30.09.2014 upon the substantial completion of the works. Toll collection
    commenced on 01.09.2013. The Completion Certificate was issued on
    13.08.2018.

    26. On 08.04.2014, the concessionaire applied to the Authority for the
    deferment of the annual premium payable by it, on the ground that the
    project was under financial stress. Vide letter dated 08.12.2014, the NHAI

    O.M.P. (COMM) 542/2024 Page 7 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51
    sanctioned the deferment of the premium. Thereafter, certain disputes
    arising under the Concession Agreement became the subject matter of an
    arbitral reference, which culminated in an award dated 03.11.2018.
    Subsequently, certain claims raised by the Respondent/Concessionaire on
    account of the financial losses suffered by it were also referred to arbitration
    for adjudication.

    27. The impugned Award in the present proceedings effectively arise out
    of the third round of arbitration between the parties. The same was
    occasioned by the termination of the Concession Agreement by the
    respondent/concessionaire in exercise of its rights under Clause 34.8 of the
    Concession Agreement, which provides as follows:-

    28. Vide letter dated 07.10.2021, the respondent/concessionaire
    terminated the Concession Agreement on the ground of an “Indirect Political
    Force Majeure Event” and sought a termination payment of Rs.1347.53
    Crore, along with certain other sums. For the adjudication of the aforesaid

    O.M.P. (COMM) 542/2024 Page 8 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51
    disputes, the concerned Arbitral Tribunal, which has rendered the impugned
    Award, was constituted.

    29. A statement of claim came to be filed on 01.10.2022, wherein the
    following claims were raised:-

    O.M.P. (COMM) 542/2024 Page 9 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51

    30. NHAI filed its Statement of Defence on 19.01.2023 along with
    counter-claims as under:

    31. A summary of amounts awarded under the various claims and
    counter-claims are as under:-

                              CLAIMS of KEPL            AMOUNT        AMOUNT AWARDED (IN RUPEES)
                                                        CLAIMED
                                                        (IN RUPEES)
                              Claim No. 1 towards       1347.53 Cr                  911.13 Cr
                              Termination Payment
                              Claim No. 2 towards       120.93 Cr     Interest on the amount awarded by way
                              Interest on Termination                 of termination payment as follows:
    
    
                              O.M.P. (COMM) 542/2024                                         Page 10 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51
                               Payment                                      Amount payable by way of interest @
                                                                           3% above the bank rate for 90 days
                                                                           (22.10.2021 to 20.01.2022).
                                                                           Thereafter, interest @ 5% over and
                                                                           above the bank rate on the said amount
                                                                           from 21.01.2022 till 23.07.2022.
                                                                           With effect from 24.07.2022, the
                                                                           Concessionaire shall be entitled to
                                                                           interest on this amount @ 9% per annum
                                                                           till the date of realization.
                              Claim No. 3 towards        Covid Rs.         Covid Rs. 15.13 Cr Farmer Agitation Rs.
                              loss suffered on account   15.13 Cr          11.19 Cr
                              of force majeure events    Farmers           Total 26.32 Cr
                                                         Agitation Rs.     ________________________
                                                         15.80 Cr          The Concessionaire shall be entitled to
                                                         ______________    interest on this amount @ 9% per annum
                                                         ____              from 11.06.2022 till the date of
                                                         Total Rs. 30.93   realization
                                                         Cr.
                              Claim No. 4 towards        539 Cr                            Rejected
                              Additional Costs and
                              foregone benefits
                              Claim No. 5 towards        1768.60 Cr                        Rejected
                              Loss of Opportunity
                              Claim No. 6 towards        1,30,86,294                        1,30,86,294
                              Refund of Insurance                          The Concessionaire is entitled to recover
                              Premium                                      interest @9% per annum from
                                                                           23.11.2021 till the date of realization.
                              Claim No. 7 towards               _          Concessionaire is entitled for interest on
                              Interest                                     the sums awarded under Claim Nos.1, 2,
                                                                           3 & 6 @9% per annum from the dates
                                                                           mentioned in respect claims till the date
                                                                           of realization.
                              Claim No. 8 towards               _          Rs. 1,10,00,000/- In case the payment is
                              Costs                                        not made within 2 months from the date
                                                                           of Award, the Concessionaire shall be
                                                                           entitled for the interest @9% per annum
                                                                           thereafter till the date of realization.
    
    
    
                                                          COUNTER CLAIMS
                              COUNTER CLAIMS               AMOUNT             AMOUNT AWARDED (IN
                                                           CLAIMED            RUPEES)
    
    
                              O.M.P. (COMM) 542/2024                                                Page 11 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51
                                                           (IN RUPEES)
    
                              Claim No. 1 towards cost      183.28 Cr    80.49 Cr with 9% interest from
                              of maintenance of project                  25.03.2022 till the date of Award. The
                              highway                                    amount maybe adjusted against the
                                                                         Award in favour of the Concessionaire.
                              Claim No. 2 towards           158.95 Cr    Allowed subject to directions as
                              outstanding dues of                        contained in Paragraph 138 of the
                              deferred premium                           Award
                              Claim No. 3 towards            13.49 Cr    3.50 Cr with 9% interest from
                              outstanding payments to                    28.12.2021 till the date of Award. The
                              agencies                                   amount may be adjusted against the
                                                                         Award in favour of the Concessionaire.
                              Claim No. 4 towards non        12.18 Cr                    Rejected
                              rectification of various
                              defects
                              Claim No. 5 towards            59.49 Cr                  Rejected
                              remuneration paid to the
                              I.E.
    
    

    32. Although the present petition, filed under Section 34 of the
    Arbitration and Conciliation Act, 1996 (hereinafter referred to as the ‘A&C
    Act’), assails the award on various grounds, the primary controversy raised
    by the Petitioner during the course of arguments pertains to the amount
    awarded to the Respondent towards the “Termination Payment” (Claim No.

    1).

    33. The primary bone of contention is the award in respect of claim no.1.
    The same reads as under:-

    O.M.P. (COMM) 542/2024 Page 12 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51
    O.M.P. (COMM) 542/2024 Page 13 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51
    O.M.P. (COMM) 542/2024 Page 14 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51
    O.M.P. (COMM) 542/2024 Page 15 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51
    O.M.P. (COMM) 542/2024 Page 16 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51
    O.M.P. (COMM) 542/2024 Page 17 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51
    O.M.P. (COMM) 542/2024 Page 18 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51
    O.M.P. (COMM) 542/2024 Page 19 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51
    O.M.P. (COMM) 542/2024 Page 20 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51
    O.M.P. (COMM) 542/2024 Page 21 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51
    O.M.P. (COMM) 542/2024 Page 22 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51
    O.M.P. (COMM) 542/2024 Page 23 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51
    O.M.P. (COMM) 542/2024 Page 24 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51
    O.M.P. (COMM) 542/2024 Page 25 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51
    O.M.P. (COMM) 542/2024 Page 26 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51

    34. It is the case of the petitioner that in determining the “termination
    payment” to which the respondent is entitled, the impugned Award has
    completely disregarded the framework and provisions of the Concession
    Agreement.

    35. Concededly, the “termination payment” is to be assessed on the basis
    of the stipulation set out in Article 34.9.2 of the Concession Agreement
    which provides as under:-

    O.M.P. (COMM) 542/2024 Page 27 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51

    36. In terms of the aforesaid provision, the respondent is entitled to: (i)
    Debt Due; and (ii) Adjusted Equity. It is the case of the petitioner that the
    components of the “termination payment” (debt due and adjusted equity),
    form part of the “Total Project Cost”, which is defined as under:-

    37. It is submitted that in view of the above definition (in terms of which
    the TPC is the lowest of the “capital cost”, the “actual capital cost” or
    “Rs.650 Crore”), it is wholly untenable to work out the “termination
    payment” on the basis that the “total project cost” is Rs.1045.5 Crore.

    38. It is submitted that the award of Rs.911.13 Crore under the head of
    “termination payment” is grossly excessive and in complete disregard of the
    express terms of the Concession Agreement.

    O.M.P. (COMM) 542/2024 Page 28 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51

    39. On the contrary, it has been submitted on behalf of the respondent as
    under:-

    i. Article 34.9.2 does not limit the quantum of the “Termination
    Payment” in any manner, including by reference to the lowest of the
    “Total Project Cost”, as defined in Article 48.1;

    ii. The definition of “Termination Payment” makes it clear that it is the
    amount payable by the Authority to the concessionaire upon
    termination of the Concession Agreement. The definition does not
    prescribe any limitation on the quantum of such payment. It provides
    what elements the Termination Payment “may” consist of which form
    part of the Total Project Cost as per the CA.

    iii. Thus, the elements of the “Termination Payment” are neither fixed
    nor inflexible. The definition further clarifies that “the Concessionaire
    shall notify to the Authority, the Total Project Cost as on COD and its
    disaggregation between Debt Due and Equity.”;

    iv. The estimated Capital Cost, i.e., the “Total Project Cost” as reflected
    in the Financial Package, was Rs. 992.58 Crore. It is also noteworthy
    that, in terms of Article 4.1.3(e) and (f), the Financing Agreement, the
    Financial Package and the Financial Model were required to be
    submitted to the NHAI upon their execution and prior thereto, in
    terms of Articles 5.2.2 and 5.2.3, drafts thereof, were required to be
    submitted, and, once executed, no changes or amendments could be
    made thereto without the written consent of the NHAI. In the present
    case, the Financial Package was approved by the NHAI;
    v. There is no dispute that the actual “Total Project Cost” as on the COD
    (i.e., 13.08.2018) was Rs.1045 Crore and that prior thereto, at the time

    O.M.P. (COMM) 542/2024 Page 29 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51
    of the Financing Agreement and the Financial Package, the “Total
    Project Cost” was estimated at Rs. 992.58 Crore;

    vi. Even though sub-clause (c) of the definition of the “Total Project
    Cost” mentions Rs.650 Crore, the capital cost in the Financial
    Package cannot be lost sight of and because of the expression “unless
    repugnant to the context” in the opening sentence of the definition
    would become irrelevant for “Termination Payment”. Any other
    reading of definition of “Total Project Cost” would make large parts
    of the contract otiose. Harmonious construction leads to only one
    interpretation that if there is repugnancy to the context the definition
    is to be ignored. The “Total Project Cost” as defined can mean larger
    sums than Rs.650 Crore and due to the construction attributed to
    Article 34.9.2, the limitation in sub clause (c) of the definition of
    “Total Project Cost” becomes repugnant to the context;
    vii. The definition of the “Termination Payment” contains critical words
    that are destructive to the NHAI’s interpretation. These words are
    “..and only the amounts so conveyed shall form the basis of
    computing Termination Payment”. In other words, where the
    concessionaire has notified the Total Project Cost as on the COD and
    provided its disaggregation between the Debt Due and Equity in
    respect of that actual “Total Project Cost”, the Concession Agreement
    expressly restricts these amounts i.e. Debt Due, Equity and Total
    Project Cost as on COD notified by the respondent as being the only
    basis for computing the “Termination Payment”. No other basis could
    therefore be used for the purpose of computing “Termination
    Payment”;

    O.M.P. (COMM) 542/2024 Page 30 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51

    viii. NHAI is precluded from resorting to and relying on any lower amount
    in the definition of “Total Project Cost” once the concessionaire
    (respondent) has notified its actual “Total Project Cost” – “the
    Concessionaire shall notify to the Authority, the Total Project Cost as
    on COD and its disaggregation between Debt Due and Equity and
    only the amounts so conveyed shall form the basis of computing
    Termination Payment…”;

    ix. The context in which therefore the “Total Project Cost” on COD is
    used, is repugnant to the meaning sought to be given by NHAI in the
    definition of the “Total Project Cost” as the lowest of the three
    figures. In support of this contention, reliance is placed on the
    judgments of the Supreme Court in Pernod Ricard India Ltd. vs. The
    State of Madhya Pradesh
    , 2024 INSC 327; K.V. Muthu Vs.
    Angamuthu Ammal, (1972) 2 SCC 53; Ramdev Food Products Ltd.
    Vs. Arvindbhai Rambhai Patel
    , (2006) 8 SCC 726; Dy. Chief
    Controller of Imports & K. T. Kosalram, (1970) 3 SCC 22.
    x. Reliance is also placed on the judgment of the English Commercial
    Court in the matter of Europa Plus SCA SIF v Anthracite
    Investments (Ireland) Plc, [2016] EWHC 437 (Comm), wherein, the
    Court explained the interplay between a definition clause and
    operative parts of a contract. In particular, the Court noted that when
    interpreting a contract, it should not be automatically assumed that the
    parties intended a defined term to bear its defined meaning at all
    times. Instead, the process of interpretation requires the Court to
    consider whether giving effect to the defined meaning in a specific
    context would lead to absurd commercial consequences; and

    O.M.P. (COMM) 542/2024 Page 31 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51
    xi. It is submitted that the “Total Project Cost” of Rs.650 Crore becomes
    relevant only if the concessionaire completely fails to notify the
    “Total Project Cost” on COD with disaggregation of the Debt and
    Equity on the said date.

    REASONING AND CONCLUSION

    40. As noticed, the fulcrum of the controversy is the award in respect of
    claim no.1. The central issue is whether the award of Termination Payment
    (under claim no.1) amounting to Rs.911.13 crore is liable to be interfered
    with in the exercise of jurisdiction under Section 34 of the A&C Act.

    41. At the outset, it is necessary for this Court to take note of the limited
    scope of interference with an arbitral award under Section 34 of the A&C
    Act. The legal position is well settled and has been reiterated time and again
    by the Supreme Court that this Court would not interfere with the
    interpretative exercise undertaken by an Arbitral Tribunal or with findings
    of fact. The jurisdiction under Section 34 of the A&C Act is not akin to
    appellate jurisdiction; rather, it is confined to scrutinizing the award within
    the narrow confines and limited scope of Section 34. The view taken by the
    Arbitral Tribunal, as long as it is a possible view (even if it is not the most
    plausible view), must be sustained. In support of the said proposition, the
    respondent has rightly placed reliance on Hindustan Construction
    Company v. National Highways Authority of India
    , 2023 INSC 768; NHAI
    v. ITD Cementation India Ltd., (2015) 14 SCC 21; Konkan Railway
    Corporation Limited v. Chenab Bridge Project Undertaking
    , 2023 INSC
    742; and Raghunath Builders Pvt. Ltd. v. Anant Raj Limited, 2023 DHC
    8143-DB.

    O.M.P. (COMM) 542/2024 Page 32 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51

    42. At the same time, the deference which informs the exercise of
    jurisdiction under Section 34 of the A&C Act has its own well-defined
    limits. In Associate Builders v. Delhi Development Authority, (2015) 3
    SCC 49 (at paragraph 42.3)1, the Supreme Court held that although the
    construction of the terms of a contract is primarily a matter for the arbitrator,
    the position is otherwise where the arbitrator construes the contract in such a
    way that no fair-minded or reasonable person could do so. The said principle
    stands codified in the ground of “patent illegality” under Section 34(2A) of
    the A&C Act, as authoritatively expounded in Ssangyong Engineering &
    Construction Co. Ltd. v. National Highways Authority of India
    , (2019) 15
    SCC 131, wherein it was held as under:-

    “40. The change made in Section 28(3) by the Amendment Act
    really follows what is stated in paragraphs 42.3 to 45 in
    Associate Builders (supra), namely, that the construction of the
    terms of a contract is primarily for an arbitrator to decide,
    unless the arbitrator construes the contract in a manner that no
    fair-minded or reasonable person would; in short, that the
    arbitrator’s view is not even a possible view to take. Also, if the
    arbitrator wanders outside the contract and deals with matters
    not allotted to him, he commits an error of jurisdiction. This
    ground of challenge will now fall within the new ground added
    under Section 34(2A).”

    43. In PSA SICAL Terminals Pvt. Ltd. v. Board of Trustees of V.O.

    1
    42.3. (c) Equally, the third subhead of patent illegality is really a contravention of Section 28(3) of the
    Arbitration Act, which reads as under:

    “28.Rules applicable to substance of dispute.–(1)-(2)***
    (3) In all cases, the Arbitral Tribunal shall decide in accordance with the terms of the contract and shall
    take into account the usages of the trade applicable to the transaction.”

    This last contravention must be understood with a caveat. An Arbitral Tribunal must decide in accordance
    with the terms of the contract, but if an arbitrator construes a term of the contract in a reasonable manner, it
    will not mean that the award can be set aside on this ground. Construction of the terms of a contract is
    primarily for an arbitrator to decide unless the arbitrator construes the contract in such a way that it could
    be said to be something that no fair-minded or reasonable person could do.

    O.M.P. (COMM) 542/2024 Page 33 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51

    Chidambranar Port Trust, Tuticorin, 2021 SCC OnLine SC 508, the
    Supreme Court, upon finding that the arbitral tribunal had, in effect, foisted
    upon the parties a bargain which they had never made, set aside the award,
    holding as under:-

    “85. ….In our view, re-writing a contract for the parties would
    be breach of fundamental principles of justice entitling a Court
    to interfere since such case would be one which shocks the
    conscience of the Court and as such, would fall in the
    exceptional category.”

    44. The touchstone which emerges from the aforesaid line of authority is
    that interpretation is an exercise performed upon the words of the contract; it
    consists in ascribing to those words a meaning which they are reasonably (or
    possibly) capable of bearing. Re-writing, on the other hand, is an operation
    performed upon the contract itself; it consists in adding to, subtracting from,
    or overriding the stipulations of the parties, so as to produce a bargain
    different from the one which they made. The former is the legitimate
    province of the arbitral tribunal, howsoever erroneous the outcome may
    appear to a court; the latter is a jurisdictional transgression which vitiates the
    award on the ground of patent illegality.

    45. In the above conspectus, this Court has examined the award insofar
    as it relates to the Termination Payment awarded under Claim No. 1 (Rs.
    911.13 crore), which is the primary bone of contention between the parties.

    46. At the outset, it is important to take note of the relevant contractual
    provisions governing the Termination Payment, which becomes payable in
    the event of termination of the Concession Agreement on account of an
    “Indirect Political Event”. The relevant provisions are set out hereunder:-

    O.M.P. (COMM) 542/2024 Page 34 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51

    i. Definition of Total Project Cost (TPC) (Article 48.1) is reproduced as
    under –

    ii. Definition of Debt Due (Article 48.1) is reproduced as under –

    iii. Definition of Equity (Article 48.1) is reproduced as under –

    O.M.P. (COMM) 542/2024 Page 35 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51

    iv. Definition of Termination Payment (Article 48.1) is reproduced as
    under –

    v. Termination Payment for Indirect Political Event is provided for in
    Article 34.9.2. The same is reproduced as under –

    O.M.P. (COMM) 542/2024 Page 36 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51

    47. In light of the aforesaid contractual provisions, the central question is
    whether the definition of TPC – with its lowest of three formulation and the
    Rs.650 Crore cap in sub-clause (c) – operates as a ceiling on the
    “Termination Payment” or whether the project cost as notified in the
    Disaggregation Letter (Rs.1045.55 crore) displaces it.

    48. The Tribunal answered the aforesaid question in favour of the
    respondent. It held that the contents of the disaggregation letter formed an
    integral part for the computation of the “Termination Payment”. (Para 45 of
    the award).

    49. It was further held that Rs.650 Crore cap in the definition of TPC
    would not be relevant in view of the fact that clause 1.4.2(a) of the Contract
    provides that “between two or more Clauses of this Agreement, the
    provisions of a specific Clause relevant to the issue under consideration shall
    prevail over those in other Clauses”. (Para 49 of the award)

    50. The Arbitral Tribunal held that in terms of the definition of the
    “Termination Payment” under Article 48.1, the disaggregation of debt and
    equity as notified to the authority had to be the basis for computing the
    Termination Payment. (Para 52 of the award)

    51. Having perused the award, this Court is of the opinion that the
    Arbitral Tribunal has grievously erred and committed patent illegality in
    arriving at the above conclusion; the error is of a nature that warrants
    interference under Section 34 of the A&C Act. The reasons are as under:

    THE AWARD DEFEATS THE VERY PURPOSE OF DEFINING
    “TOTAL PROJECT COST”

    52. As noticed hereinabove, Article 48.1 of the Concession Agreement

    O.M.P. (COMM) 542/2024 Page 37 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51
    defines “Total Project Cost” as the lowest of the following three alternatives:

    (a) the capital cost of the project as set-forth in the financial package; (b) the
    actual capital cost of the project upon completion of four laning of the
    project highway; and (c) a sum of Rs.650 Crore, less equity support.

    53. This three limbed definition, particularly the cap contained in sub-
    clause (c), lies at the very heart of the Concession Agreement and cannot be
    treated as surplusage for the purpose of determining the “Termination
    Payment”. The purpose of this provision is clearly to limit the financial
    exposure of NHAI upon termination. Indeed, this provision is at the very
    heart of risk allocation in the Concession Agreement.

    54. Evidently, NHAI, as a public authority, set out this cap in the RFP
    document itself so that its maximum financial exposure upon termination
    would be confined to the project cost. This cap serves a specific and vital
    commercial purpose; it protects NHAI against cost over-run incurred by the
    concessionaire (whether due to inefficiency, over borrowing or for any other
    reason) being passed on to NHAI in the guise of a “Termination Payment”.
    Without this cap, a concessionaire could borrow far in excess of the
    sanctioned project cost and on termination, present NHAI with a demand
    that NHAI never agreed to underwrite. The award by accepting the “total
    project cost” at Rs.1045.5 Crore has rendered sub-clause (c) entirely
    nugatory, effectively reducing it to a dead letter.

    55. A copy of Request for Proposal (RFP) has been filed by the
    Respondent. Clause 1.1.1 of the RFP clearly mentions the estimated project
    cost as Rs. 650 Crore. The relevant portion of the same is reproduced as
    under –

    O.M.P. (COMM) 542/2024 Page 38 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51

    56. Evidently, the figure of Rs. 650 crore represented the estimated
    Project Cost as reckoned at the time of bidding. By making it the ceiling in
    the definition of the “Total Project Cost,” the parties sought to ensure that,
    even if the actual cost exceeded this amount, NHAI’s financial exposure
    towards Termination Payment would continue to be anchored to this ceiling.
    The unmistakable commercial rationale underlying the contractual provision
    is that NHAI assumes the risk of cost overruns during construction only to
    the extent contemplated under sub-clause (c), and not in respect of any
    unlimited or excessive expenditure that the Concessionaire may incur.

    57. The Concession Agreement is founded upon a concession framework,
    under which the termination liabilities of the Authority are capped. It is on

    O.M.P. (COMM) 542/2024 Page 39 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51
    the strength of this risk matrix that bids were invited, that the premium of
    Rs.12 crore per annum (escalating at 5% annually) was offered by the
    respondent, and that the financial exposure of the public exchequer stood
    crystallised. The ceiling ensures that the consequence/s of any cost overrun
    or over-leveraging is not transmuted into a liability of the Authority upon
    termination. To construe the Agreement in a manner which dissolves this
    ceiling is to redistribute, ex post facto, the very risk which the parties had
    definitively allocated inter-se.

    THE APPROVAL OF THE FINANCIAL PACKAGE DOES NOT
    ASSIST THE RESPONDENT

    58. Considerable emphasis was laid on behalf of the respondent on the
    circumstance that the Financial Package (reflecting a capital cost of
    Rs.992.58 crore), the Financial Model and the Financing Agreements were
    scrutinised and approved by NHAI prior to financial close. The submission
    is of no avail to the respondent. Sub-clause (a) of the definition of “Total
    Project Cost” itself refers to “the capital cost of the Project, as set forth in
    the Financial Package”. The parties were, therefore, fully alive to the fact
    that the Financial Package would reflect a capital cost, and that such cost
    might well exceed Rs.650 crore; it is precisely for this reason that the
    definition stipulates that the Total Project Cost shall be the lowest of the
    three specified amounts. The Financial Package figure thus stands
    internalised within the definition itself – it supplies limb (a); it does not, and
    cannot, abolish limb (c). The scrutiny of the financing documents by the
    Authority serves an altogether distinct purpose, namely, to ensure that the
    Concessionaire does not enter into arrangements with its lenders which

    O.M.P. (COMM) 542/2024 Page 40 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51
    imperil the interests of the Authority; such scrutiny cannot be construed as
    an undertaking by the Authority to underwrite the entirety of the said cost
    upon termination. Moreover, in terms of Article 1.4.1 of the Concession
    Agreement, the Agreement prevails over all other documents.

    THE DEFINITION “TOTAL PROJECT COST” INCORPORATES A
    TERMINATION SPECIFIC PROVISO – CONFIRMING ITS
    APPLICABILITY FOR THE PURPOSE OF DETERMINING
    “TERMINATION PAYMENT”

    59. The definition of “Total Project Cost” contains the following proviso:

    “provided that in the event of Termination, the Total Project Cost shall be
    deemed to be modified to the extent of variation in WPI or Reference
    Exchange Rate occurring in respect of Adjusted Equity and Debt Due, as
    the case may be, in accordance with the provisions of this Agreement;
    provided further that in the event WPI increases, on an average, by more
    than 6% (six per cent) per annum for the period between the date hereof
    and COD the Parties shall meet, as soon as reasonably practicable, and
    agree upon revision of the amount herein before specified such that the
    effect of increase in WPI, in excess of such 6% (six per cent), is reflected
    in the Total Project Cost;”

    60. This proviso is of significant importance. It expressly addresses the
    termination scenario and provides for the modification of the “Total Project
    Cost” figure, but only to the extent of variation in the WPI. The fact that the
    Concession Agreement itself incorporates a termination-specific proviso into
    the definition of the “Total Project Cost” conclusively establishes two
    things:

    (i) that the definition is intended to apply in the context of
    termination and is neither rendered inapplicable nor repugnant for
    the purpose of determining the “Termination Payment”. A definition
    which itself provides for the termination scenario cannot, in the
    same breath, be branded as repugnant to that very scenario ;

    O.M.P. (COMM) 542/2024 Page 41 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51

    (ii) that the parties specifically contemplated that the “Total
    Project Cost” might require upward revision in a termination
    scenario, but only by way of WPI adjustment and, where the WPI
    exceeded 6% per annum, through mutual agreement between the
    parties. There is no mechanism under the Concession Agreement
    permitting the Concessionaire to unilaterally enhance the “Total
    Project Cost” by relying upon a disbursement letter reflecting actual
    project costs far in excess of the contractual cap.

    61. If the parties had intended that the actual project cost notified in the
    disaggregation letter would entirely displace or render nugatory the
    definition of “total project cost”, there would have been no need whatsoever
    for this proviso. Its very existence, providing a measured / WPI linked
    adjustment mechanism, demonstrates that the parties never intended the
    contractual cap to be by-passed by a unilateral cost notification /
    disaggregation letter.

    62. A unilateral notification by the Concessionaire of its actual
    expenditure is not a mode of modification of the “Total Project Cost”

    recognised anywhere in the Agreement. It is elementary that a contract can
    be varied only in the manner provided therein or by the mutual agreement of
    the parties; it cannot be varied by the unilateral act of one party. Yet, the
    construction adopted by the Tribunal ascribes to the disaggregation letter (a
    unilateral communication), the effect of an amendment of the contractually
    defined “Total Project Cost” from Rs.650 crore to Rs.1045.55 crore. No
    canon of interpretation sanctions such an outcome.

    DEFINITION OF “TERMINATION PAYMENT” EXPRESSLY
    INCORPORATES THE CEILING REFERRED TO IN THE

    O.M.P. (COMM) 542/2024 Page 42 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51
    DEFINITION OF “TOTAL PROJECT COST”

    63. The definition of “Termination Payment” in Article 48.1 provides that
    it “may consist of payments on account of and restricted to, the Debt Due
    and Adjusted Equity, as the case may be, which form part of the Total
    Project Cost in accordance with the provisions of this Agreement”.

    64. Three expressions in this definition are of significant importance and,
    independently support the relevance of the ceiling for the purpose of
    determining the Termination Payment :

    (i) “Restricted to” – the use of these words is intended to limit the
    extent of the Termination Payment and to make it circumscribed;

    (ii) “Which form part of the Total Project Cost” – this is a qualifying
    and limiting stipulation. Only such Debt Due and Adjusted Equity as
    form part of the contractually defined “Total Project Cost” are
    payable. The inevitable consequence is that payments in excess of
    the “Total Project Cost” are expressly excluded;

    (iii) “In accordance with the provisions of this Agreement” – this
    cross-reference ties the computation of the “Termination Payment” to
    the definition of the “Total Project Cost” and precludes the
    possibility of importing a different “Total Project Cost” figure from
    outside that is at variance with, or inconsistent with, the contractual
    ceiling contained in the definition of the “Total Project Cost.”

    THE DISAGGREGATION LETTER CANNOT OVERRIDE THE
    CAP IN THE DEFINITION OF “TOTAL PROJECT COST”; IT
    OPERATES WITHIN IT

    65. The respondent’s principal submission, as accepted by the Arbitral
    Tribunal, is that the disaggregation letter clause contained in the definition

    O.M.P. (COMM) 542/2024 Page 43 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51
    of “Termination Payment” makes the notified “Total Project Cost” figure
    the sole basis for computing the “Termination Payment,” thereby displacing
    the contractual cap of Rs. 650 crore. This argument fundamentally
    misconstrues the function and purpose of the disaggregation letter.

    66. The disaggregation letter clause requires the Concessionaire to notify
    NHAI of the “Total Project Cost” as on the COD, together with its
    disaggregation into Debt Due and Equity. The purpose of this requirement is
    to inform NHAI how the “Total Project Cost”, already determined under the
    Concession Agreement as the lowest of the three alternatives, is apportioned
    between its Debt Due and Equity components so that the formula prescribed
    under Article 34.9.2 (Debt Due + 110% Adjusted Equity) can be correctly
    applied.

    67. The word “disaggregation” is itself dispositive. To disaggregate
    means to break down a whole into its component parts. The disaggregation
    letter mechanism is intended to allocate the “Total Project Cost” between
    Debt Due and Equity. It is not a mechanism by which the Concessionaire
    has been granted carte blanche to unilaterally ‘re-determine’ the “Total
    Project Cost” or to undermine or nullify the contractual ceiling prescribed
    thereunder.

    68. If the interpretation canvassed by the respondent were correct, the
    disaggregation letter would become an instrument by which the
    Concessionaire could inflate NHAI’s termination liability simply by
    notifying a higher “Total Project Cost” figure, regardless of the contractual
    ceiling prescribed for the same. This would lead to absurd consequences and
    would be manifestly contrary to the intention of the parties, who deliberately
    defined the “Total Project Cost” as the lowest of the three alternatives

    O.M.P. (COMM) 542/2024 Page 44 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51
    precisely to prevent such an outcome.

    69. No rational commercial party could have intended that the
    applicability of a ceiling, negotiated for the protection of one party, should
    depend upon the unilateral election of the very party whom it constrains.
    The deeming provision in the definition of “Termination Payment”

    demonstrates that whether or not a disaggregation letter is furnished, the
    contractually defined “Total Project Cost” remains operative; the letter fixes
    the internal apportionment between debt and equity, and nothing more. On
    the face of it, the letter is intended to convey a “disaggregation”, not a
    unilateral re-valuation.

    MISCONCEIVED RELIANCE ON THE EXPRESSION “ONLY THE
    AMOUNT SO CONVEYED SHALL FORM THE BASIS OF
    COMPUTING TERMINATION PAYMENT” (OCCURING IN THE
    DEFINITION OF “TERMINATION PAYMENT” AS DEFINED
    UNDER ARTICLE 48)

    70. The reliance placed by the Arbitral Tribunal on this expression is
    untenable. The Arbitral Tribunal has, unfortunately, laid emphasis on only a
    part of the relevant contractual provision while overlooking the preceding as
    well as the succeeding parts of the same clause. The first paragraph of the
    relevant clause defining “Termination Payment” makes it expressly clear
    that the “Termination Payment” is to be restricted to Debt Due and Adjusted
    Equity, which form part of the “Total Project Cost.” The succeeding
    clarificatory paragraph refers to the “Total Project Cost” and requires the
    Concessionaire to notify the Authority of its disaggregation into Debt Due
    and Equity. The stipulation that only the amount so conveyed or notified
    shall form the basis for computing the “Termination Payment” was clearly
    not intended to override the contractual ceiling contained in the definition of

    O.M.P. (COMM) 542/2024 Page 45 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51
    the “Total Project Cost.” Had that been the intention of the parties, nothing
    would have been easier than to expressly provide so.

    71. The use of the expression “only the amount so conveyed shall form
    the basis of computing the Termination Payment” was intended only to
    preclude reliance upon extraneous sources for the purpose of disaggregation.
    The concluding portion of the same paragraph is significant. It provides that,
    in the event such disaggregation is not notified to the Authority, the Equity
    shall be deemed to be the amount arrived at by subtracting the Debt Due
    from the “Total Project Cost.”

    72. The above clearly demonstrates that the disaggregation letter is only
    intended for the purpose of internal split between debt due and equity; the
    outer limit as set out in the definition of the “total project cost” is not
    rendered irrelevant.

    THE FINDINGS QUA THE DISAGGREGATION LETTER DO NOT
    CONCLUDE THE ISSUE

    73. The Tribunal has devoted considerable attention to establishing that
    the disaggregation letter dated 04.02.2019 exists; that the delay in its
    submission was not attributable to any default or malafide on the part of the
    Concessionaire; that its contents were not specifically traversed by the
    Authority in its pleadings; and that the Independent Engineer treated it as the
    formal disaggregation for the purpose of computing the Termination
    Payment (paras 33 to 46 of the award). This Court has no reason to disturb
    any of the said findings; they are findings of fact within the exclusive
    domain of the Tribunal. The said findings, however, do not carry the matter
    any further, inasmuch as the existence, genuineness and bona fides of the
    letter were never determinative of the controversy. The controversy

    O.M.P. (COMM) 542/2024 Page 46 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51
    concerns the legal effect of the letter under the Concession Agreement and
    as to whether it is capable in law of enlarging the “Total Project Cost”

    beyond the contractual ceiling.

    74. The reliance placed by the Tribunal on National Highway Authority
    of India v. PNC-BEL (JV
    ), 2019 SCC OnLine Del 9461 (at para 46 of the
    award) is misplaced. It was held therein that the certification by the
    Independent Engineer in that case, of rates in respect of non-BOQ items,
    which the Engineer had certified and submitted for approval, cannot be
    selectively disregarded by the Authority. Evidently, the certification in
    question pertained to a function which the contract contemplated from the
    Engineer. No such function (for re-determining “Total Project Cost” in
    derogation/disregard of the contractual ceiling) has been committed to the
    Independent Engineer in the present case (as is evident from contractual
    provisions noticed hereinbelow).

    75. The reliance on Jetpur Somnath Tollways Limited v. National
    Highways Authority of India
    , 2017 SCC OnLine Del 9453 (at para 53 of
    the award) is equally misplaced. The said decision was rendered on petitions
    under Section 9 of the A&C Act (by the concessionaire therein and by its
    lender), seeking interim measures of protection pending arbitration, in the
    nature of a direction to NHAI to secure the termination payment. The
    observations therein were, ex facie, rendered at a prima facie stage, for the
    limited purpose of moulding interim relief; they did not constitute a final
    adjudication of the quantum of the termination payment. Further, the
    question considered in paragraph 81 of the said decision was an altogether
    different one. NHAI had sought, on the strength of Recital B to the Common
    Loan Agreement dated 19.08.2011 executed in that case (which recorded a

    O.M.P. (COMM) 542/2024 Page 47 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51
    debt-equity ratio of 72.58:27.42 ) to import the said ratio so as to make a
    further adjustment to the “Debt Due”. It was in that context that the Court
    observed that there was “admittedly, no such stipulation in the Termination
    Payment clause that any such adjustment is to be made prior to payment of
    the Debt Due” and that “only the actual Debt Due has to be taken into
    account”. The decision thus declined to permit an adjustment extraneous to
    the contractual provisions. The said judgement did not deal with the
    operation of a definitional ceiling, forming an express part of the contractual
    text itself. The said decision points against the respondent rather than in its
    favour inasmuch as its ratio is fidelity to the ‘Termination Payment’
    provisions as written. In the present case, the award disregards the
    contractual ceiling of Rs.650 crore, and the words of restriction in the
    definition of “Termination Payment”.

    76. Pertinently also, the function assigned to the Independent Engineer
    under the Concession Agreement do not extend to determining the “Total
    Project Cost”. Article 23.2.1 provides that the Independent Engineer “shall
    discharge its duties and functions substantially in accordance with the terms
    of reference set forth in Schedule-Q.” The relevant portions of Schedule-Q
    read as under:-

    “3.1 The role and functions of the Independent Engineer shall include
    the following:

    (vi) determining, as required under the Agreement, the costs of any works
    or services and/or their reasonableness; …

    8.1 The Independent Engineer shall determine the costs and/or their
    reasonableness that are required to be determined by it under the
    Agreement”

    77. The cost-determination function of the Independent Engineer is a
    power exercisable only in respect of costs which the Agreement specifically

    O.M.P. (COMM) 542/2024 Page 48 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51
    requires his determination. No provision of the Concession Agreement
    commits the determination of “Total Project Cost” to the Independent
    Engineer. The definition of “Total Project Cost” in Article 48.1 is self-
    executing: it is the lowest of three arithmetically stated figures, subject only
    to the WPI proviso (as already noticed). What the Independent Engineer
    was called upon to examine was whether the disaggregation letter dated
    04.02.2019 “be considered by the Authority as acceptable within the
    definition as stipulated in the Concession Agreement” ( para 34 of the
    award). This is a question of the timeliness and procedural acceptability of
    the letter. The Tribunal’s treatment of the Independent Engineer’s
    recommendation as though it were a determination of quantum does
    violence to both the language and purport of the contract. The Agreement
    nowhere empowers the Independent Engineer to approve, sanction or certify
    a substitute “Total Project Cost” put forward unilaterally by the
    Concessionaire.

    REPUGNANCY ARGUMENTS

    78. The respondent has vehemently argued that the definition of the
    “Total Project Cost” as on the COD is repugnant to the meaning sought to
    be given by NHAI thereto. The said argument is thoroughly misconceived.

    79. Repugnancy can be said to arise only where the application of the
    contractual definition results in a direct contradiction or absurdity. It cannot
    be said to arise merely because the application of the contractual definition
    results in a financially inconvenient outcome or yields a lower recovery than
    that which the respondent would prefer.

    80. Applying the “Total Project Cost” cap in the context of “Termination

    O.M.P. (COMM) 542/2024 Page 49 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51
    Payment” does not create any absurdity or contradiction. On the contrary, it
    produces precisely the outcome that the parties agreed to when they
    executed the Concession Agreement. The cap is not repugnant to the context
    of the “Termination Payment”, rather, it is entirely consonant with it.

    81. Importantly, as noticed hereinabove, the definition of the “Total
    Project Cost” itself contains a termination-specific proviso addressing WPI
    adjustments. A definition that expressly accounts for a termination scenario
    cannot simultaneously be said to be repugnant to the context of
    “Termination Payment.”

    82. The authorities cited on behalf of the respondent in this behalf, far
    from advancing its case, affirm the settled position that the defined meaning
    is the rule and its displacement the exception. In K.V. Muthu v. Angamuthu
    Ammal
    , (1997) 2 SCC 53, the Supreme Court held that where a definition is
    preceded by the words “unless the context otherwise requires”, the definition
    is ordinarily to be applied and given effect to, and may be departed from
    only if there is something in the context to show that the definition could not
    be applied at all. (paragraphs 10 to 12) 2.

    2

    10. Apparently, it appears that the definition is conclusive as the word “means” has been used to specify
    the members, namely, spouse, son, daughter, grandchild or dependant parent, who would constitute the
    family. Section 2 of the Act in which various terms have been defined, opens with the words “in this Act,
    unless the context otherwise requires” which indicates that the definitions, as for example, that of “family”,
    which are indicated to be conclusive may not be treated to be conclusive if it was otherwise required by the
    context. This implies that a definition, like any other word in a statute, has to be read in the light of the
    context and scheme of the Act as also the object for which the Act was made by the legislature.

    11. While interpreting a definition, it has to be borne in mind that the interpretation placed on it should not
    only be not repugnant to the context, it should also be such as would aid the achievement of the purpose
    which is sought to be served by the Act. A construction which would defeat or was likely to defeat the
    purpose of the Act has to be ignored and not accepted.

    12. Where the definition or expression, as in the instant case, is preceded by the words “unless the context
    otherwise requires”, the said definition set out in the section is to be applied and given effect to but this
    rule, which is the normal rule may be departed from if there be something in the context to show that the
    definition could not be applied.

    O.M.P. (COMM) 542/2024 Page 50 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51

                               CLAUSE 1.4.2(a): NEITHER ATTRACTED                       NOR      OF    ANY
                              ASSISTANCE TO THE RESPONDENT
    
    

    83. The Arbitral Tribunal has relied upon Article 1.4.2(a), which provides
    that between two or more clauses, the specific clause relevant to the issue
    under consideration shall prevail. Article 34.9.2 is indeed the specific
    provision governing the quantum of the “Termination Payment” in the event
    of an Indirect Political Event. However, the impugned majority award
    overlooks the fact that Article 34.9.2 operates by reference to the defined
    terms “Debt Due” and “Adjusted Equity,” both of which are, in turn, defined
    by reference to the “Total Project Cost.”

    84. Thus, it is wholly untenable for the purpose of Article 34.9.2 to ignore
    the definition of “Total Project Cost” inasmuch as the latter gives content to
    the relevant components of “Termination Payment”.

    THE AWARD RE-WRITES THE CONTRACT NOT MERELY
    INTERPRETS THE RELEVANT PROVISIONS

    85. The Supreme Court has consistently drawn a line between the
    interpretation of a contract which is within the Arbitral Tribunal’s
    jurisdiction, and re-writing of a contract which constitutes patent illegality
    warranting interference under Section 34 of the A&C Act. An award that
    departs from an express, unambiguous contractual provision crosses this
    line. In the present case, the award does not merely re-interpret the
    Concession Agreement, it rewrites it in the following specific and
    identifiable ways –

    (i) It renders sub-clause (c) of the definition of the “Total Project

    O.M.P. (COMM) 542/2024 Page 51 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51
    Cost”, which prescribes the contractual cap of Rs. 650 crore,
    inoperative in the very context for which it was most significant,
    namely, the determination of the “Termination Payment.”

    (ii) It rendered the word “restricted to ……. which form part of the
    total project cost” in the definition of “Termination Payment” entirely
    meaningless and otiose. Such manifest disregard of contractual
    provision/s cannot pass muster under Section 34 of the A&C Act;

    (iii) It treats the disaggregation letter as a document capable of
    overriding express contractual definitions contrary to the priority
    clause in Article 1.4.1 which makes the Concession Agreement
    supreme over all other documents;

    (iv) In reaching the conclusion that the expression “Total Project
    Cost” as expressly defined in the Concession Agreement is not
    relevant for the purpose of “Termination Payment”, the award
    disregards the fact that the definition of the “Total Project Cost” itself
    expressly contemplates and speaks of termination and provides for a
    WPI based adjustment. It is thus wholly incongruous and contrary to
    express contractual provisions, to declare the definition of the “Total
    Project Cost” as being irrelevant for the purpose of assessing
    “Termination Payment”; and

    (v) It elevates a unilateral notification issued by the Concessionaire,
    to the status of a binding contractual mandate, and thereby effectively
    denudes the contractual stipulation/s of their intended effect.

    86. These are not errors within the permissible zone of arbitral
    interpretation. They are fundamental departures from express terms of the

    O.M.P. (COMM) 542/2024 Page 52 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51
    Concession Agreement resulting in excess payment of hundreds of crores, a
    sum which the Concession Agreement never authorised. The same constitute
    patent illegality on the face of the record within the meaning of Section
    34(2A)
    of the A&C Act.

    87. Before concluding the discussion on Claim No.1, it is again necessary
    to note that the law leans heavily, and rightly, against interference with
    arbitral awards. Arbitration is a forum of the parties’ own choosing, and a
    court which subjects awards to a review on merits defeats the very object of
    the A&C Act. This Court is conscious that judicial intervention with arbitral
    awards must be kept to the barest minimum, lest the efficacy of arbitration
    itself be undermined, and the endeavour of the Court must always be to
    sustain the view taken by the arbitral tribunal. However, the jurisdiction
    under Section 34 of the A&C Act, though narrow, is not akin to a ‘rubber
    stamp’. Restraint on the part of the Court and fidelity to the contract on the
    part of the tribunal are two sides of the same compact, and the first cannot
    be invoked where the second has not been kept. That is the position here; the
    parties wrote a ceiling into their bargain for the express eventuality of
    termination payment/s, and the award has erased it at the very moment it
    was meant to operate. Interference with such an award does not diminish the
    authority of arbitration; it is the award which does. In these circumstances,
    and with due circumspection, that this Court is unable to sustain the award
    in respect of Claim No.1.

    88. The award in respect of Claim No.1 is, accordingly, set aside.

    89. Under Claim No. 2, the Tribunal awarded interest on the Termination
    Payment. The relevant portion of the award is reproduced as under:-

    O.M.P. (COMM) 542/2024 Page 53 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51

    90. Since the Award on Claim No. 1, which determined the quantum of
    the Termination Payment, has been set aside by this Court, the foundation of
    Claim No. 2 no longer survives. Consequently, the award of interest, being
    entirely dependent upon the determination of the Termination Payment
    under Claim No. 1, cannot be sustained, and is also set aside.

    OTHER CLAIMS

    91. Insofar as the award in respect of other claims are concerned, this
    Court finds no basis to interfere therewith.

    92. The findings and conclusions in respect of other claims and counter
    claims are briefly summarized hereinbelow.

    A. Claim No. 3 – Claims arising out of loss suffered on account of Force
    Majeure Events being Covid-19 & Farmers’ Agitation
    i. The Concessionaire sought Rs. 30.93 crore towards losses arising
    from Force Majeure events, comprising Rs. 15.13 crore for the
    COVID-19 pandemic and Rs. 15.80 crore for the Farmers’
    Agitation.

    
    
                              O.M.P. (COMM) 542/2024                                           Page 54 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51
                                 ii.    As regards the claims made by the Concessionaire in relation to
                                       the   COVID-19       pandemic,    the   Tribunal    accepted   the
    

    Concessionaire’s claim for the period from March 2020 to
    September 2020. It noted that the Statutory Auditor had certified
    the claim at Rs. 15.80 crore, the Authority had neither challenged
    the certification nor cross-examined the witnesses with respect to
    the same, and the Independent Engineer’s recommendation
    covered only a shorter period. Considering the prolonged impact of
    the pandemic, the Tribunal allowed the claim of Rs. 15.13 crore. It
    further awarded interest at 9% per annum from 11.06.2022 until
    realization.

    iii. The Concessionaire claimed Rs. 15.8 crore towards Force Majeure
    costs arising from the Farmers’ Agitation. The Tribunal observed
    that the IE had assessed the claim in accordance with the NHAI
    Policy Guidelines dated 02.07.2021, which provided for
    reimbursement of 50% of O&M and interest, besides extension of
    period for the days tolling has been impacted. Since the Authority
    did not dispute the IE’s calculations and merely stated that the
    recommendation was pending approval, the Tribunal allowed the
    claim to the extent recommended by the IE, i.e., Rs.

    11,19,50,485.39, together with interest at 9% per annum from
    11.06.2022 till realization.

    iv. The aforesaid findings returned by the learned Arbitral Tribunal
    are findings of fact based on the appreciation of the evidence on
    record. This Court, while exercising its jurisdiction under Section
    34
    of the Arbitration and Conciliation Act, 1996, cannot

    O.M.P. (COMM) 542/2024 Page 55 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51
    reappreciate the evidence or interfere with such factual findings
    merely because another view may be possible.

    B. Claim No. 4 – Additional Cost and Foregone Benefits Claim – rejected
    by the Tribunal.

    C. Claim No. 5 – Loss of opportunity from the Termination date till the
    Concession Period – rejected by the Tribunal.

    D. Claim No. 6 – Refund of Insurance Premium
    i. The findings of the Tribunal with respect to the Claim No. 6 are
    reproduced as under –

    O.M.P. (COMM) 542/2024 Page 56 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51
    O.M.P. (COMM) 542/2024 Page 57 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51
    O.M.P. (COMM) 542/2024 Page 58 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51

    ii. The aforesaid findings recorded by the learned Arbitral Tribunal
    are largely factual in nature, predicated on contractual provisions,
    and are not amenable to reappreciation by this Court in
    proceedings under Section 34 of the Arbitration and Conciliation
    Act, 1996.

    E. Claim No. 7 – Interest

    i. The Arbitral Tribunal observed that an arbitrator is a creature of an
    agreement and therefore he cannot award interest if prohibited by
    the contractual terms. However, in absence of any stipulation in
    the Contract Agreement in this respect, the arbitrator is competent
    to award interest for pre-reference, pendente lite and post-award
    period at a reasonable rate as provided under Section 31 (7) of the
    Act, 1996.

    ii. It further observed that since interest had already been awarded
    wherever the Concessionaire’s claims were allowed, the Tribunal
    did not record any separate findings on this claim.

    iii. The Arbitral Tribunal has rightly observed that it is well settled
    that, in the absence of any contractual stipulation prohibiting the
    grant of interest, an arbitral tribunal is empowered to award
    interest for the pre-reference, pendente lite, and post-award
    periods.

    F. Claim No. 8 – Costs

    i. The Arbitral Tribunal held that under Section 31A of the
    Arbitration and Conciliation Act, 1996, costs ordinarily follow the

    O.M.P. (COMM) 542/2024 Page 59 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51
    event, and the successful party is entitled to recover the reasonable
    costs incurred in the proceedings. While awarding costs, the
    Tribunal considered factors such as the parties’ conduct and the
    outcome of the arbitration etc.

    ii. The Tribunal noted that the arbitration involved total claim of Rs.

    1,347.53 crore and counterclaim of Rs. 368 crore, which were
    adjudicated over 32 sittings. Despite repeated directions, the
    Authority failed to pay its share of the Tribunal’s fees, compelling
    the Concessionaire to deposit on behalf of the Authority as well.
    Considering the Authority’s conduct and the substantial expenses
    incurred by the Concessionaire in pursuing the arbitration, the
    Tribunal awarded Rs. 1.10 crore towards cost, inclusive of the
    Authority’s unpaid share of arbitral fees. The awarded cost was
    directed to be paid within two months, failing which, it was
    directed that, they would carry interest at 9% per annum until
    realization.

    iii. This Court finds no ground to interfere with the aforesaid findings
    of the learned Arbitral Tribunal in the exercise of its jurisdiction
    under Section 34 of the Arbitration and Conciliation Act, 1996,
    particularly when the petitioner failed to deposit its share of the
    arbitral tribunal’s fees.

    G. Counter-Claim No. 1 – Claim for the Maintenance of the Project
    Highway

    i. Upon consideration of the record, the Tribunal observed that,
    following a joint inspection conducted by the Authority, the

    O.M.P. (COMM) 542/2024 Page 60 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51
    Independent Engineer, and the Concessionaire, the Independent
    Engineer had quantified the divestment cost at Rs. 80.49 crores, and
    the Concessionaire had expressly accepted this assessment by its letter
    dated 25.03.2022.

    ii. The Tribunal rejected the Authority’s reliance on subsequent letters
    dated 21.08.2022 and 21.10.2022, by which the claim had been
    increased first to Rs. 152.74 crores and then to Rs. 183.28 crores,
    including a 20% penalty under Article 17.9 of the Concession
    Agreement. It held that these letters were based on inspections
    conducted without notice to or participation of the Concessionaire,
    contrary to the mandatory procedure prescribed under Article 38.2.
    Moreover, these documents were merely internal communications of
    the Authority, were neither proved as admissible evidence nor shown
    to have been communicated to the Concessionaire.

    iii. The Tribunal further held that the Concessionaire’s contractual
    liability to maintain the Project Highway ceased on 04.02.2022, i.e.,
    120 days after termination (as per Article 39.1). Consequently,
    reliance on letters issued after that date was held to be legally
    inconsequential. The Tribunal also found that although several notices
    had been issued before termination, the Authority failed to establish
    compliance with the procedure prescribed under Article 17.9.

    iv. Accordingly, the Tribunal concluded that the Authority’s claim of Rs.
    183.28 crores was grossly exaggerated and unsupported by admissible
    evidence. However, observing that the Independent Engineer’s
    assessment of Rs. 80.49 crores, made on 02.02.2022, had been

    O.M.P. (COMM) 542/2024 Page 61 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51
    accepted by the Concessionaire on 25.03.2022, the Tribunal held that
    the Authority was entitled only to that amount.

    v. The Tribunal therefore partly allowed Counter-Claim No. 1, awarding
    the Authority Rs. 80.49 crores, together with interest at 9% per annum
    from 25.03.2022 till the date of the Award.

    vi. The learned Arbitral Tribunal, upon a due appreciation of the
    evidence on record and the relevant contractual provisions, has
    arrived at a reasoned finding of fact. Such a finding, being founded on
    an appreciation of the evidence and the terms of the contract, does not
    warrant interference in the exercise of this Court’s limited jurisdiction
    under Section 34.

    H. Counter-Claim No. 2 – Outstanding dues of Deferred Premium

    i. Upon consideration of the rival submissions, the Tribunal took note
    of all the relevant documents, the provisions of the Agreement, and
    the MoRTH Policy dated 04.03.2014. The Tribunal also examined
    the evidence on record, including the cross-examination of the
    Concessionaire’s witness.

    ii. It further took note of the Independent Engineer’s letter dated
    31.01.2022, which recommended recovery of the outstanding
    deferred premium and had quantified the dues at Rs. 132.98 crore.
    However, the Authority had ultimately claimed Rs. 158.95 crore on
    the basis of Annexure R-15 of the arbitral record, the contents of
    which had been specifically denied by the Concessionaire. The
    Tribunal held that the Authority had failed to formally prove the said

    O.M.P. (COMM) 542/2024 Page 62 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51
    document and, therefore, it could not be relied upon. Referring to
    Section 101 of the Evidence Act, 1872, as well as the principles of
    natural justice, the Tribunal held that the burden of proving the
    computation rested upon the Authority and that an unproved
    document could not constitute the basis for granting the claim.

    iii. The Tribunal thereafter interpreted Clause 25.4 of the Concession
    Agreement, which expressly provided as under –

    iv. Applying principles of contractual interpretation, the Tribunal held
    that the provision is clear and unambiguous and must be given its
    plain meaning. It concluded that the parties had consciously agreed
    that the premium would be payable only from the gross revenue of
    the project. It further observed that the entire gross revenue of the
    project goes to the Escrow Account. Consequently, it was observed
    that the Concessionaire could not be compelled to satisfy the
    premium liability from its own independent resources. The Tribunal
    further observed that the very purpose of the Premium Deferment
    Scheme was to protect the concessionaires from financial hardships.

    O.M.P. (COMM) 542/2024 Page 63 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51

    v. Accordingly, it was observed that the Concessionaire is not liable to
    pay any amount in this respect and if the payment is to be made, it is
    required to be made from the Escrow Account itself. It further
    observed that this factual and legal obligation has been conceded
    very fairly by the Learned Counsel for the Authority.

    vi. Liberty was given to the Authority to make the recovery as per the
    amount due and to the extent of availability of funds in the Escrow
    Account.

    vii. The conclusions arrived at by the learned Arbitral Tribunal cannot be
    said to have transgressed the limits of its jurisdiction. The Tribunal
    has adopted a plausible and reasonable interpretation of the relevant
    provisions of the Agreement.

    viii. The Tribunal has also independently recorded that the said position
    was fairly conceded by the learned counsel appearing for the
    Authority.

    ix. In the exercise of its jurisdiction under Section 34 of the Arbitration
    and Conciliation Act, 1996, this Court cannot substitute its own
    interpretation of the contractual provisions merely because an
    alternative view is possible. So long as the interpretation adopted by
    the learned Arbitral Tribunal is a possible one and does not suffer
    from any patent illegality or contravene the fundamental policy of
    Indian law, no interference is warranted.

    I. Counter-Claim No. 3 – Outstanding dues to the Agencies

    O.M.P. (COMM) 542/2024 Page 64 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51
    i. The findings of the Tribunal with respect to the Counter Claim No. 3
    are reproduced as under –

    O.M.P. (COMM) 542/2024 Page 65 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51

    ii. The Arbitral Tribunal has partly allowed the petitioner’s
    counterclaim after considering the IE’s letter dated 28.12.2021
    and the Concessionaire’s reply thereto. The Tribunal has observed
    that it is not the Authority‘s case that it had made the payment to
    any agency. Equally, in the absence of any specific pleadings or
    cogent evidence to establish that the Concessionaire had failed to

    O.M.P. (COMM) 542/2024 Page 66 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51
    make such payment to any agency, the Tribunal returned the
    aforesaid finding. The Tribunal has further placed reliance upon
    Clause 31.4 of the Concession Agreement as well as the
    provisions of the Escrow Agreement while adjudicating the issue.
    This Court finds no infirmity in the findings and conclusions
    arrived at by the learned Arbitral Tribunal. The view taken is a
    plausible one, based on the material available on record and the
    interpretation of the contractual provisions, and therefore warrants
    no interference in the exercise of this Court’s jurisdiction under
    Section 34 of the Arbitration and Conciliation Act, 1996.

    J. Counter- Claim no. 4 – For non-rectification of defects

    i. The Tribunal held that the Authority had failed to establish the
    essential prerequisites for recovery under the Concession Agreement,
    namely, issuance of notices by the IE or the Authority, failure of the
    Concessionaire to comply and execution of remedial works by the
    Authority, and the actual expenditure incurred. The Tribunal found
    that the chart (annexed as Annexure R-16 of the arbitral record) was
    inadmissible, as it was disputed by the Concessionaire and remained
    unproved.

    ii. It also held that the claims, largely relating to the period 2013-2020,
    were time barred under Section 43 of the Arbitration and Conciliation
    Act, 1996, and, except for two items, were additionally barred by the
    principles of Order II Rule 2 CPC.

    O.M.P. (COMM) 542/2024 Page 67 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51

    iii. Accordingly, the Tribunal rejected Counter-Claim No. 4 in its
    entirety.

    iv. The learned Arbitral Tribunal has recorded its findings on the basis of
    the evidence adduced before it and, upon an appreciation thereof, has
    arrived at findings of fact. Such findings are not amenable to
    interference by this Court in the exercise of its jurisdiction under
    Section 34 of the Arbitration and Conciliation Act, 1996.

    K. Counter- Claim no. 5 – Towards IE’s remuneration

    i. The Arbitral Tribunal observed that Article 23.3 requires the
    Concessionaire to reimburse 50% of the IE’s remuneration after
    receiving a statement of expenditure from the Authority. The Tribunal
    found that the Authority had failed to produce any evidence showing
    the amount paid by it in respect of the fees of the IE, the date on
    which such payment was made, or that it had issued any statement of
    expenditure or demand for reimbursement to the Concessionaire.

    ii. It is further observed that there is no pleading that the Authority had
    actually paid the IE’s fees after October 2020. Consequently,
    Counter-Claim No. 5 was rejected.

    L. Counter- Claim no. 6 – Interest

    A regards Claim No. 6, following observation has been made –

    O.M.P. (COMM) 542/2024 Page 68 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51

    M. Counter- Claim no. 7 – Cost

    Regarding Claim no. 7, following has been observed –

    93. Similarly, no interference is warranted with the findings recorded by
    the learned Arbitral Tribunal in respect of Counter Claim Nos. 5, 6 and 7.

    94. Thus, in respect of the aforesaid claims and counterclaims, the learned
    Arbitral Tribunal has duly considered the pleadings, the evidence, and the
    documents placed before it before recording its findings. The interpretation
    accorded by the Tribunal to the contractual provisions is a plausible and
    reasonable view based on the terms of the Agreement.

    95. In exercise of jurisdiction under Section 34 of the A&C Act, this
    Court is not inclined to interfere with the above (except in respect of Claim
    Nos.1 and 2).

    96. In the circumstances, the present petition is partly allowed; the
    impugned award in respect of Claim Nos.1 and 2 is set aside.

    97. Pending applications also stand disposed of.

    SACHIN DATTA, J
    JULY 28, 2026/r, sv

    O.M.P. (COMM) 542/2024 Page 69 of 69
    Signature Not Verified
    Digitally Signed
    By:ABHISHEK THAKUR
    Signing Date:28.07.2026
    13:38:51



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here