National Highway Authority Of India vs Gmr Highways Ltd on 6 May, 2026

    0
    21
    ADVERTISEMENT

    Delhi High Court

    National Highway Authority Of India vs Gmr Highways Ltd on 6 May, 2026

                      *      IN THE HIGH COURT OF DELHI AT NEW DELHI
    
                      %                                Judgment reserved on: 28.04.2026
                                                     Judgment pronounced on: 06.05.2026
    
                      +      O.M.P. (COMM) 263/2018 & I.A. 3084/2023
                             NATIONAL HIGHWAY AUTHORITY OF
                             INDIA                                             .....Petitioner
                                                 Through:   Mr. Arun Kumar Varma, Sr.
                                                            Adv. with Mrs. Asha Gopalan
                                                            Nair, Mr. Sandeep Narain &
                                                            Ms. Nivedita Nair, Advs.
                                                 versus
    
                             GMR HIGHWAYS LTD                                .....Respondent
                                                 Through:   Mr. Rajshekhar Rao, Sr. Adv.
                                                            with Ms. Richa Kapoor, Mr.
                                                            Kunal Anand, Ms. Aditi
                                                            Rathore & Mr. Wamic Wasim
                                                            Nargal, Advs.
                             CORAM:
                             HON'BLE MR. JUSTICE AVNEESH JHINGAN
                                                 JUDGMENT
    

    1. This petition is filed under Section 34 of the Arbitration and
    Conciliation Act, 1996 (for short „the Act‟) against the arbitral award
    dated 24.02.2018 (for brevity „the award‟).

    2. The brief facts are that the Government of India through the
    petitioner/National Highways Authority of India (for short „NHAI‟)
    invited bids for development of the stretch of National Highway from
    28 km to 121 km of Tambaram-Tindivanam section of NH-45 in
    Tamil Nadu. The respondent through a consortium was a successful

    SPONSORED

    Signature Not Verified
    Signed By:CHANCHAL O.M.P. (COMM) 263/2018 Page 1 of 13
    Signing Date:06.05.2026
    12:32:09
    bidder and was issued a Letter of Acceptance dated 16.08.2001. In
    terms of the proposal, the consortium incorporated a special purpose
    vehicle i.e. the respondent for implementing the project. The
    Concession Agreement dated 09.10.2001 (for short „CA‟) was entered
    between the petitioner and the respondent. The project was on Build
    Operate and Transfer (for short „BOT‟) basis. The construction was
    completed on 11.10.2004, and the concession period was of seventeen
    years and six months, ending on 08.11.2019. The project was
    successfully completed and there is no dispute relating to the
    completion and operation of the project. The respondent raised a claim
    for additional cost incurred consequent to change in rates of Minimum
    Alternate Tax (for short „MAT‟) under Chapter XII-B of the Income
    Tax Act, 1961
    (for brevity „1961 Act‟), Fringe Benefit Tax (for short
    „FBT‟) under Chapter XII-H of the 1961 Act and Service Tax (for
    short „ST‟) under Chapter V of the Finance Act, 1994.

    2.1 The change in rates was subsequent to the proposal due date i.e.
    31.05.2001. The respondent vide letter dated 19.04.2012, raised claim.
    The Independent Engineer forwarded the claim to the independent
    auditor in terms of Article 11.3(b) of the CA. The petitioner on
    05.12.2014, rejected the claim for reimbursement of additional cost.
    The terms and conditions agreed between the parties provided for
    dispute resolution through arbitration. The arbitration was invoked at
    the instance of the respondent and culminated in the impugned award.
    The claim of the respondent to the tune of Rs.14,51,57,902/- was
    allowed. Interest in terms of Article 19.2 of the CA up to the date of

    Signature Not Verified
    Signed By:CHANCHAL O.M.P. (COMM) 263/2018 Page 2 of 13
    Signing Date:06.05.2026
    12:32:09
    the award was granted and on failure to pay the awarded amount by
    07.04.2018, interest at the rate of 7% from the date of the award till
    actual payment was awarded.

    3. Learned senior counsel for the petitioner contended that the
    claim was barred by limitation. The cause of action arose to the
    respondent when the rates of tax varied in financial years (for short
    „FY‟) 2007-08 but the claim was raised after three years vide
    communication dated 19.04.2012.

    3.1 It is argued that the variation in rates of tax under the 1961 Act
    does not fall within the ambit of „additional cost‟ and under Article 11
    of the CA. The submission is that the tribunal erred in reading the
    definition of „tax‟ in isolation and not along with the definition of
    „additional cost‟.

    3.2 The award is challenged to be perverse as the claim was
    allowed in the absence of evidence to establish that the taxes at the
    enhanced rates were actually paid by the respondent and that the tax
    rates varied after the proposal due date.

    3.3 The grievance is that the contentions raised in the statement of
    defence (for short „SOD‟) were not considered by the tribunal. The
    notifications dated 27.07.2009 and 20.06.2012 were relied to contend
    that no ST was payable on services provided by respondent to
    petitioner.

    4. Per contra, the claim is within limitation. It is contended that
    the cause of action arose in the year 2010 when the additional cost
    incurred exceeded rupees one crore and thereafter the respondent

    Signature Not Verified
    Signed By:CHANCHAL O.M.P. (COMM) 263/2018 Page 3 of 13
    Signing Date:06.05.2026
    12:32:09
    proceeded in terms of Article 11 of the CA to raise the claim vide
    communication dated 19.04.2012.

    4.1 The submission is that the petitioner for rejecting the claim
    erred in relying upon the definition of „tax‟ in the Model Concession
    Agreement which came into existence subsequent to the execution of
    the CA and more so when „tax‟ is defined in the CA. It is emphasised
    that the project was on BOT basis, after construction the project was
    handed over to the petitioner for collection of toll and the respondent
    was to receive payment of annuity for the stipulated period. Reliance
    is on communication dated 30.01.2012, to contend that petitioner was
    put to notice that the profitability of the respondent reduced due to
    variation in tax rates. The argument is that the share of additional cost
    for FY 2007-08 to 2012-13 to be borne by the respondent amounting
    to rupees six crores was reduced and only the balance amount was
    claimed.

    4.2 The argument is that the notifications relied upon by the
    petitioner to contend that no ST was leviable on services provided for
    construction and maintenance of roads used by the general public are
    not applicable. The claim for ST by the respondent was in respect of
    services rendered by the professionals engaged by the respondent and
    the hiring of the professionals was in compliance with the terms of the
    CA.

    4.3 Reliance is on the decision of the Supreme Court in Som Datt
    Builders Ltd. v. State of Kerala
    , (2009) 10 SCC 259 to contend that
    reasoned award is not to be equated with a judgment of a court. The

    Signature Not Verified
    Signed By:CHANCHAL O.M.P. (COMM) 263/2018 Page 4 of 13
    Signing Date:06.05.2026
    12:32:09
    reasons implicit from the reading of award as a whole would suffice.
    Learned senior counsel refers to the written submissions filed before
    the tribunal to demonstrate that the award is reasoned.

    4.4 It is contended that the definition of „tax‟ and „additional cost‟
    is widely worded and would include the variation in rates of MAT,
    FBT and ST and claim was illegally rejected by the petitioner. It was
    not considered that the respondent is an SPV and would not be able to
    avail the credit of MAT after completion of the project.

    5. Before proceeding further it would be apposite to reproduce
    Article 11 of the CA and the definitions of „tax‟ and „additional cost‟:-

    ARTICLE 11
    11.1
    Change In Law
    Change in Law means the occurrence or coming into force
    of any of the following, after the Proposal Due Date:

    a) the enactment of any new Indian law;

    b) the repeal, modification or re-enactment of any existing
    Indian law;

    c) a change in the interpretation or application of any
    Indian law by a court of record;

    d) any change in the rates of any of the Taxes.
    Provided that Change in Law shall not include;

    (i) coming into effect, after the Proposal Due Date, of any
    provision of a statute which is already in place as of the
    Proposal Due Date or

    (ii) any new law or any change in the existing law under
    the active consideration of or in the contemplation of any
    government as of the Proposal Due Date, which is a matter
    of public knowledge.

    11.2 Relief to Concessionaire

    Signature Not Verified
    Signed By:CHANCHAL O.M.P. (COMM) 263/2018 Page 5 of 13
    Signing Date:06.05.2026
    12:32:09
    Subject to the Concessionaire taking necessary measures to
    mitigate the impact or the likely impact of Change in Law
    on the Project, if as a direct consequence of a Change in
    Law, the Concessionaire is obliged to incur Additional
    Cost in any Accounting Year, such Additional Cost shall
    (without duplication) be allocated and shared between the
    Concessionaire and NHAI as under:

                             Increase    in    Capital        NHAI‟s Share
                             Expenditure    (Rs. In
                             Million)
                             From Rs. 0 to 60 Million 0%
                             Above Rs. 60 Million      100%     of    the    capital
                                                       expenditure in excess of Rs.
                                                       60 Million.
    
                             Increase in Costs/ Taxes            NHAI‟s Share
                             (Rs. In Million)
                             From Rs. 0 to 10 Million     0%
                             Above Rs. 10 Million         100% of the amount in
                                                          excess of Rs. 10 Million.
    
                             11.3 Obligations of the Concessionaire
                             (a) Upon occurrence of a Change in Law, the
    

    Concessionaire may, if it is entitled to claim relief
    under the provisions of Article 11.3, notify NHAI and
    the Independent Engineer, of the following:-

    i. the nature and the impact of Change in Law on the
    Project;

    ii. in sufficient detail, the estimate of the Additional
    Cost likely to be incurred by the Concessionaire on
    account of the Change in Law;

    iii. the measures, which the Concessionaire has taken or
    proposes to take to mitigate the impact of Change in
    Law; including in particular, minimising the
    Additional Cost;

    Signature Not Verified
    Signed By:CHANCHAL O.M.P. (COMM) 263/2018 Page 6 of 13
    Signing Date:06.05.2026
    12:32:09

    iv. the relief sought by the Concessionaire.

    (b) Upon receipt of the notice of Change in Law issued by
    the Concessionaire pursuant to the preceding sub-

    article(a), NHAI and the Concessionaire shall along
    with the Independent Engineer hold discussions and
    take all such steps as may be necessary including
    determination/certification by the Independent Engineer
    and where necessary by the Independent Auditor of the
    Additional Cost and to determine the quantum of the
    Additional Cost to be borne and paid by NHAI.

    (c) NHAI shall within 30 days from the date of
    determination of quantum of Additional Cost, provide
    relief to the Concessionaire in either of the following
    ways:

    i. by lump-sum reimbursement of the Additional Cost
    to the Concessionaire:

    ii. reimbursement of the Additional Cost to the
    Concessionaire, in not exceeding four half yearly
    instalments, subject to payment of interest at SBI
    PLR + 2% on the amount the payment of which is
    deferred.”

    “Additional Cost means the additional capital
    expenditure and/or the additional operating costs or
    additional taxes or both as the case may be, which the
    Concessionaire has or would be required to incur and
    which has arisen as a result of Change of Scope or Change
    in Law.”

    “Tax means and includes all taxes, fees, cesses, levies that
    may be payable by the Concessionaire under any
    Applicable Law.

    Provided that for the purpose of Article 11.2, Tax shall not
    include any penalty, interest or other penal sum levied on

    Signature Not Verified
    Signed By:CHANCHAL O.M.P. (COMM) 263/2018 Page 7 of 13
    Signing Date:06.05.2026
    12:32:09
    or payable by the Concessionaire on account of non-
    payment, short payment or delayed payment of Tax or on
    account of any other default.”

    6. The construction of the project was completed on 11.10.2004,
    and the concession period ended on 08.11.2019. The claim for
    additional expenses due to variation in rates of MAT, FBT and ST is
    from the FY 2007-08 to 2015-16. The cause of action arose in 2010
    when the quantum of additional cost incurred exceeded rupees one
    crore. The respondent proceeded under Article 11 of the CA and after
    rejection of the claim on 05.12.2014, arbitration was invoked. The
    objection of limitation does not merit acceptance. The tribunal rightly
    held the claim to be within limitation and no ground is made out for
    interference with the finding.

    7. The respondent claimed that the additional cost incurred due to
    variation in rates of MAT, FBT and ST was covered under Article 11.

    Before proceeding to deal with the issue as to whether this claim was
    maintainable under Article 11 it is necessary to consider as to whether
    the claim made was proved before the tribunal.

    8. The respondent vide communication dated 18.08.2014 invoked
    Article 11 for raising a claim for the FY 2007-08 to 2012-13
    tabulating the variation in tax rates, the effect thereof and the share of
    the additional cost to be borne by the petitioner but the claim was
    rejected. In the statement of claim filed before the tribunal, the
    respondent furnished a tabulated statement for the FY 2007-08 to
    2015-16. Both the tabulated statements are reproduced hereunder:-

    Signature Not Verified
    Signed By:CHANCHAL O.M.P. (COMM) 263/2018 Page 8 of 13
    Signing Date:06.05.2026
    12:32:09

    Additional Cost/ Taxes incurred under
    Financial Minimum Fringe Service Tax Total of Amount to be Share of
    Year Alternate Benefit (ST) Additional borne by Additional
    Tax (MAT) Tax (c) Cost Concessionaire cost to be

    (a) (FBT) (d)= (e) borne by

    (b) (a)+(b)+(c) NHAI

    (f)= (d)-(e)
    2007-08 92,05,272 6,15,225 11,49,441 1,09,69,938 1,00,00,000 9,69,938
    2008-09 1,03,70,252 4,44,324 6,66,995 1,14,81,571 1,00,00,000 14,81,571
    2009-10 4,05,80,618 0 22,22,327 4,28,02,945 1,00,00,000 3,28,02,945
    2010-11 2,62,33,044 0 19,84,999 2,82,18,043 1,00,00,000 1,82,18,043
    2011-12 2,91,56,640 0 28,55,846 3,20,12,486 1,00,00,000 2,20,12,486
    2012-13 1,59,87,589 0 42,90,447 2,02,78,036 1,00,00,000 1,02,78,036
    TOTAL 13,15,33,415 10,59,549 1,31,70,055 14,57,63,019 6,00,00,000 8,57,63,019

    Financial Year Increase in tax Increase in tax Increase in tax Share of Additional cost
    (FY) rate under rate under rate under ST to be borne by NHAI due
    MAT (In %) FBT (In %) (In %) to differential tax
    liability caused by
    increase in MAT, FBT
    and ST (in Rupees)
    2007-08 11.330 30.00 12.24 & 12.36 9,69,939
    2008-09 11.330 30.00 12.36 & 10.30 14,81,571
    2009-10 16.995 30.00 10.30 3,28,02,945
    2010-11 19.9305 – 10.30 1,82,18,043
    2011-12 20.0077 – 10.30 2,20,12,486
    2012-13 20.0077 – 12.36 1,02,78,037
    2013-14 20.9605 – 12.36 1,97,96,105
    2014-15 20.9605 – 12.36 2,08,74,346
    2015-16 21.3416 – 14.00 & 14.50 1,87,24,430
    TOTAL 14,51,57,902

    9. Apart from the tabulated claim, no evidence was led by the
    respondent to prove the change in rates of tax after the proposal due
    date and that the tax at the enhanced rates was actually paid by the
    respondent. Copies of the returns and proof of tax deposited were not
    produced. The fundamental requirement under Article 11 was the
    incurring of additional cost and in the absence of proof of tax having
    been paid at the enhanced rates the foundation of the claim for
    additional cost is missing.

    Signature Not Verified
    Signed By:CHANCHAL O.M.P. (COMM) 263/2018 Page 9 of 13
    Signing Date:06.05.2026
    12:32:09

    10. The law is well settled that filing of a claim by itself is not a
    proof to substantiate the claim. Reference is to the following decisions
    of the Supreme Court:

    10.1 In Ssangyong Engg. & Construction Co. Ltd. v. NHAI,
    (2019) 15 SCC 131 wherein it was held as under:

    “41. What is important to note is that a decision which is
    perverse, as understood in paras 31 and 32 of Associate
    Builders [Associate Builders v. DDA
    , (2015) 3 SCC 49 :
    (2015) 2 SCC (Civ) 204] , while no longer being a ground
    for challenge under “public policy of India”, would
    certainly amount to a patent illegality appearing on the
    face of the award. Thus, a finding based on no evidence
    at all or an award which ignores vital evidence in arriving
    at its decision would be perverse and liable to be set aside
    on the ground of patent illegality. Additionally, a finding
    based on documents taken behind the back of the parties
    by the arbitrator would also qualify as a decision based on
    no evidence inasmuch as such decision is not based on
    evidence led by the parties, and therefore, would also
    have to be characterised as perverse.”

    10.2 In State of Rajasthan and Anr. v. Ferro Concrete
    Construction Private Limited
    (2009) 12 SCC 1 it was held:

    “55.While the quantum of evidence required to accept a
    claim may be a matter within the exclusive jurisdiction of
    the arbitrator to decide, if there was no evidence at all and
    if the arbitrator makes an award of the amount claimed in
    the claim statement, merely on the basis of the claim
    statement without anything more, it has to be held that the
    award on that account would be invalid. Suffice it to say
    that the entire award under this head is wholly illegal and
    beyond the jurisdiction of the arbitrator, and wholly
    unsustainable.”

    (emphasis supplied)

    11. As per Article 11 the respondent was to bear the additional cost

    Signature Not Verified
    Signed By:CHANCHAL O.M.P. (COMM) 263/2018 Page 10 of 13
    Signing Date:06.05.2026
    12:32:09
    incurred up to rupees one crore in each accounting year and could
    claim only the amount in excess thereof. From the tabulated statement
    placed before the tribunal, it is not forthcoming that such deduction
    was made for the FY 2013-14 to 2015-16. No evidence was adduced
    to prove that the amount claimed for these FY was in accordance with
    Article 11 of the CA.

    12. Section 31(3) of the Act mandates a reasoned award. The law is
    well settled that the requirement of Section 31(3) of the Act is not a
    mere formality. The reasoning in an appropriate case can be implied
    upon a fair reading of the award and the documents referred to therein.
    Reference is to the decision of the Supreme Court in Dyna
    Technologies Pvt. Ltd. v. Crompton Greaves Ltd.
    (2019) 20 SCC 1
    wherein it was held as under:

    “34. The mandate under Section 31(3) of the Arbitration
    Act is to have reasoning which is intelligible and
    adequate and, which can in appropriate cases be even
    implied by the courts from a fair reading of the award and
    documents referred to thereunder, if the need be. The
    aforesaid provision does not require an elaborate
    judgment to be passed by the arbitrators having regard to
    the speedy resolution of dispute.”

    12.1 In Som Datt Builders Ltd. (supra), it was held as follows:

    “25. The requirement of reasons in support of the award
    under Section 31(3) is not an empty formality. It
    guarantees fair and legitimate consideration of the
    controversy by the Arbitral Tribunal. It is true that the
    Arbitral Tribunal is not expected to write a judgment like
    a court nor is it expected to give elaborate and detailed
    reasons in support of its finding(s) but mere noticing the

    Signature Not Verified
    Signed By:CHANCHAL O.M.P. (COMM) 263/2018 Page 11 of 13
    Signing Date:06.05.2026
    12:32:09
    submissions of the parties or reference to documents is no
    substitute for reasons which the Arbitral Tribunal is
    obliged to give……”

    (emphasis supplied)

    13. From the perusal of the award it is forthcoming that there is no
    discussion of the material relied upon to award the claimed amount.
    There is no material on record to prove the variation in rates of tax and
    tax deposited at the enhanced rates.

    14. The grievance of learned counsel for the petitioner regarding
    non-consideration of the issues raised in the SOD deserves acceptance
    and is fatal to the award. The petitioner relied upon notifications dated
    27.07.2009 and 20.06.2012, refuting the claims made for enhanced
    rate of ST. It was canvassed that no ST was leviable on the project
    awarded to the respondent. The defence of the petitioner was neither
    noted nor dealt with. The contention of learned counsel for the
    respondent that the notifications were not applicable was an issue to
    be considered by the tribunal for the award to be a reasoned award.

    15. There cannot be a quarrel with the proposition propounded by
    learned senior counsel for the respondent that the award is to be read
    as a whole, fairly and with the documents referred to therein to
    determine the compliance of Section 31(3) of the Act. However, in the
    case in hand the award is bereft of reasons. There is no discussion of
    the evidence produced and relied upon for awarding the claim. The
    contentions raised by the petitioner in the SOD were brushed under
    the carpet and the issue as to whether the ST was leviable in view of
    the notifications relied upon was not dealt with.

    Signature Not Verified
    Signed By:CHANCHAL O.M.P. (COMM) 263/2018 Page 12 of 13
    Signing Date:06.05.2026
    12:32:09

    16. Allowing the claim without evidence by an unreasoned award
    renders the award perverse and in conflict with the public policy of
    India and is consequently set aside.

    17. The issue as to whether variation of rates in tax of MAT, FBT
    and ST is covered under Article 11 read with the definition of „tax‟
    and „additional cost‟ would also involve the following issues: (i)
    whether the definition of „tax‟ would include direct taxes leviable
    under the 1961 Act and (ii) whether „additional cost‟ would cover
    taxes impacting only the profit earned by the respondent? These issues
    need not be dilated upon after the award having been set aside in view
    of the discussion above.

    18. Similarly, the issue as to whether the FBT arising from the
    division of remuneration of employees of the respondent in fringe
    benefits and cash emoluments would constitute an additional cost for
    the project or whether it affected the only profitability of the
    respondent need not be gone into.

    19. The petition is allowed and the award is set aside. Pending
    applications if any are disposed of.

    AVNEESH JHINGAN, J
    MAY 06, 2026
    Ch
    Reportable:- Yes

    Signature Not Verified
    Signed By:CHANCHAL O.M.P. (COMM) 263/2018 Page 13 of 13
    Signing Date:06.05.2026
    12:32:09



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here