― Advertisement ―

Employer vs Employee — Reality Beyond the Narrative

The discourse around employer–employee relations in India is often framed as adversarial: management versus labour, profit versus rights, control versus resistance. However, this...
HomeMipl Draipl Jv vs Eastern Railway on 27 April, 2026

Mipl Draipl Jv vs Eastern Railway on 27 April, 2026

ADVERTISEMENT

Calcutta High Court

Mipl Draipl Jv vs Eastern Railway on 27 April, 2026

                     IN THE HIGH COURT AT CALCUTTA
                          COMMERCIAL DIVISION                                        2026:CHC-OS:140

                             ORIGINAL SIDE
                         RESERVED ON: 08.04.2026
                         DELIVERED ON: 27.04.2026
                                 PRESENT:
                      HON'BLE JUSTICE GAURANG KANTH
                            AP-COM 1007 OF 2025
                                MIPL DRAIPL JV
                                   VERSUS
                               EASTERN RAILWAY
Ms. Debanjana De, Adv.

                                                             ..... for the petitioner


Mr. Sukanta Ghosh, Adv.
Mr. Arabinda Sen, Adv.
Mr. Rohan Chamria, Adv.
                                                           ..... for the respondent

                                   JUDGMENT

Gaurang Kanth, J.:-

1. The present petition has been preferred by the Petitioner under Sections 14

and 15 of the Arbitration and Conciliation Act, 1996, seeking termination of

the mandate of the learned Sole Arbitrator and appointment of a substitute

arbitrator, in view of the fact that the learned Sole Arbitrator, Hon’ble Mr.

Justice Tapan Kumar Dutt (Retd.), by his communication dated

19.06.2025, has withdrawn from the arbitral proceedings and has thereby

been released from his mandate.

2. The brief facts giving rise to the present petition are set out herein below:

SPONSORED

3. The Petitioner is a joint venture constituted between Maxout Infrastructure

Pvt. Ltd. and Dineshchandra R. Aggarwal Pvt. Ltd. pursuant to a Joint

Venture Agreement dated 15.07.2012. The Respondent, upon the Petitioner

being declared the lowest bidder, awarded the work vide Memorandum of
2
2026:CHC-OS:140
Agreement dated 05.09.2013 for construction of Composite Girder Bridge

No. 123 (24 spans of 15.24 metres over River Mayurakshi) and Bridge No.

125 (3 spans of 16.5 metres), including RCC bored cast-in-situ piles,

retaining walls, protective works, and other ancillary works, in connection

with the construction of the third railway line from Sainthia to Tarapith in

the Howrah Division of Eastern Railway.

4. Disputes arose between the parties during the execution of the aforesaid

works, culminating in termination of the contract by the Respondent vide

letter dated 08.08.2017. Thereafter, the Petitioner invoked the arbitration

clause contained in the agreement by issuing a notice dated 06.02.2019

under Section 21 of the Arbitration and Conciliation Act, 1996.

5. As the parties failed to arrive at a consensus regarding the appointment of

an arbitrator, the Petitioner approached this Hon’ble Court by filing AP No.

81/2020. This Hon’ble Court, vide order dated 04.02.2021, was pleased to

appoint Hon’ble Mr. Justice Tapan Kumar Dutt (Retd.) as the Sole

Arbitrator to adjudicate the disputes between the parties.

6. Owing to financial constraints and attendant circumstances, the Petitioner

could not immediately take steps to operationalize the arbitral proceedings

or communicate the aforesaid order to the learned Sole Arbitrator.

Subsequently, in the year 2025, the Petitioner, under a mistaken

understanding of certain facts, preferred a petition being AP (Com) No.

381/2025 challenging the mandate of the Arbitral Tribunal. Upon realizing

the error, the said petition was withdrawn vide order dated 14.05.2025.

7. Thereafter, the Petitioner, with the intent to proceed with the arbitration,

communicated the order dated 04.02.2021 to the learned Sole Arbitrator

vide letter dated 11.06.2025. However, upon receipt thereof, the learned
3

Sole Arbitrator, by communication dated 19.06.2025, was pleased 2026:CHC-OS:140
to

withdraw from acting as the Sole Arbitrator.

8. In view of the aforesaid withdrawal, the mandate of the learned Sole

Arbitrator stands terminated within the meaning of Section 14 of the

Arbitration and Conciliation Act, 1996. Consequently, in terms of Section

15 of the Act, the Petitioner has approached this Hon’ble Court seeking

appointment of a substitute arbitrator to adjudicate the disputes between

the parties.

Submissions on behalf of the Petitioner

9. Ms. Debanjana De, learned Counsel for the Petitioner submitted that the

present petition under Sections 14 and 15 of the Arbitration and

Conciliation Act, 1996 is maintainable and arises in peculiar but bona fide

circumstances warranting interference of this Court. This Hon’ble Court,

vide order dated 04.02.2021, was pleased to appoint Hon’ble Mr. Justice

Tapan Kumar Dutt (Retd.) as the learned Sole Arbitrator to adjudicate the

disputes between the parties. The appointment having been made by this

Court, the arbitral process stood duly constituted.

10. In the year 2025, under a mistaken understanding of certain facts, the

petitioner approached this Court by filing a petition challenging the

mandate of the learned Arbitrator. Upon realizing the error, the said petition

was withdrawn. This conduct, it is submitted, clearly demonstrates that the

Petitioner at all material times intended to pursue arbitration and had not

abandoned the proceedings. Thereafter, the Petitioner, with the bona fide

intention of proceeding with arbitration, communicated the order dated

04.02.2021 to the learned Sole Arbitrator on 11.06.2025. However, upon

receipt thereof, the learned Arbitrator, vide communication dated
4
2026:CHC-OS:140
19.06.2025, withdrew from acting as the Sole Arbitrator. Consequently, the

mandate of the learned Arbitrator stands terminated within the meaning of

Section 14 of the Act.

11. Learned Counsel further submitted that, due to genuine financial

constraints and attendant circumstances, the Petitioner was unable to

immediately communicate the said order to the learned Arbitrator or take

steps to operationalize the arbitral proceedings. The said delay, was neither

deliberate nor indicative of any intention to abandon the arbitral remedy.

12. In such circumstances, it is submitted that the present case squarely

attracts the provisions of Sections 14 and 15 of the Act, which contemplate

termination of mandate and substitution of an arbitrator so as to ensure

continuity of the arbitral process. The statutory framework is intended to

facilitate adjudication of disputes on merits and not to defeat the same on

account of procedural delays. It is further submitted that the delay in the

present case does not amount to abandonment of arbitration. The Petitioner

has, through its conduct, consistently evinced its intention to pursue the

arbitral remedy, and the intervening circumstances sufficiently explain the

delay. No prejudice whatsoever has been caused to the Respondent.

13. In view of the aforesaid, it is prayed that this Hon’ble Court may be pleased

to terminate the mandate of the learned Sole Arbitrator and appoint a

substitute arbitrator in accordance with Section 15 of the Arbitration and

Conciliation Act, 1996.

Submission on behalf of the Respondent

14. Mr. Sukanta Ghosh, learned Counsel for the Respondent submits that the

present petition under Sections 14 and 15 of the Arbitration and

Conciliation Act, 1996 is wholly misconceived, barred by limitation, and
5
2026:CHC-OS:140
liable to be dismissed in limine. Learned Counsel points out that this

Court, vide order dated 04.02.2021, appointed Mr. Justice Tapan Kumar

Dutt (Retd.) as the Sole Arbitrator to adjudicate the disputes. However, the

Petitioner failed to take any steps whatsoever to operationalize the arbitral

proceedings for an inordinate period of more than four years. The Petitioner

did not even communicate the said order to the learned Arbitrator until

11.06.2025.

15. Learned Counsel for the Respondent submits that such prolonged and

unexplained inaction clearly demonstrates gross negligence and lack of

diligence on the part of the Petitioner. The explanation sought to be offered,

namely “financial constraints”, is vague, unsupported, and wholly

insufficient to justify a delay of this magnitude. No material particulars or

contemporaneous record have been placed on record to substantiate the

said plea. It is further submitted that the Petitioner’s conduct unmistakably

establishes that the arbitral proceedings were effectively abandoned. Mere

appointment of an arbitrator does not, by itself, sustain the arbitral process

in perpetuity in the absence of any steps being taken to prosecute the

same.

16. It is the contention of the Respondent that the present petition is also

barred by limitation. In terms of Section 43 of the Arbitration and

Conciliation Act, 1996, the provisions of the Limitation Act, 1963 apply to

arbitral proceedings as they apply to proceedings before a court. The

present petition, being an application for relief not otherwise specifically

provided for, is governed by Article 137 of the Limitation Act, which

prescribes a limitation period of three years. The right to seek appropriate

relief, if any, arose when the Petitioner failed to act upon the order dated
6
2026:CHC-OS:140
04.02.2021 within a reasonable time. The Petitioner, having remained

completely inactive for over four years, cannot now seek to revive a stale

and abandoned claim by invoking Sections 14 and 15 of the Act. It is

submitted that the subsequent filing of a petition in the year 2025,

admittedly based on “wrong information”, does not cure the fundamental

defect of prolonged inaction. On the contrary, it further reflects the casual

and negligent approach adopted by the Petitioner in prosecuting the

matter.

17. The Respondent further submits that Sections 14 and 15 of the Act cannot

be invoked as a device to revive proceedings that have lapsed on account of

abandonment and inordinate delay. The statutory scheme contemplates

substitution in a live and subsisting arbitration, and not resurrection of

proceedings that have been allowed to become dormant for years together.

In the present case, the Petitioner has failed to demonstrate any continuity

of intention to pursue arbitration. The conduct of the Petitioner disentitles

it from any discretionary relief from this Hon’ble Court.

18. In view of the aforesaid, it is respectfully submitted that the present

petition is barred by limitation, suffers from gross delay and laches, and is

liable to be dismissed as the Petitioner has, by its conduct, abandoned the

arbitral proceedings.

Legal Analysis.

19. This Court has heard the arguments advanced by the learned counsel for

the parties and has carefully examined the material placed on record.

20. The principal objection raised by the Respondent pertains to the inordinate

delay of approximately four years in intimating the learned Sole Arbitrator

of his appointment pursuant to the order dated 04.02.2021. It is contended
7

that such delay is unexplained, not liable to be condoned, and indicative 2026:CHC-OS:140
of

abandonment of the arbitral proceedings. It is further urged that, in view of

Section 43 of the Arbitration and Conciliation Act, 1996 read with Article

137 of the Limitation Act, 1963, the present petition is barred by limitation.

21. Per contra, the Petitioner submits that the delay was occasioned by

financial constraints and certain intervening circumstances, and that there

was no intention to abandon the arbitral proceedings. It is further

submitted that the withdrawal of the learned Arbitrator on 19.06.2025

necessitated the filing of the present petition under Sections 14 and 15 of

the Act for appointment of a substitute arbitrator.

22. At the outset, this Court notes that there has indeed been a substantial

delay on the part of the Petitioner in communicating the order of

appointment to the learned Arbitrator. The explanation offered for such

delay is neither entirely satisfactory nor supported by detailed particulars.

Ordinarily, such prolonged inaction would weigh against the grant of

discretionary relief. However, the matter cannot be examined in isolation

and must be considered in the overall factual and legal context.

23. It is not in dispute that the arbitration agreement between the parties was

duly invoked by the Petitioner within the prescribed period of limitation,

and that this Court, in exercise of its jurisdiction, had appointed the

learned Sole Arbitrator vide order dated 04.02.2021. Thus, the arbitral

process had been validly set in motion. Further, the inability to proceed has

arisen not on account of any adjudication on merits or termination for

default, but solely due to the subsequent withdrawal of the learned

Arbitrator from his mandate on 19.06.2025. Had the learned Arbitrator

continued, there would have been no impediment in proceeding with the
8
2026:CHC-OS:140
arbitration. The present petition, therefore, arises in the context of Sections

14 and 15 of the Act, which contemplate termination of mandate and

substitution of an arbitrator so as to ensure continuity of the arbitral

process.

24. The question that arises is whether such delay, by itself, amounts to

abandonment of the arbitral proceedings. The Hon’ble Supreme Court in

Dani Wooltex Corporation Vs Sheil Properties Pvt. Ltd. reported as

2024 (7) SCC 1, examined the concept of abandonment of arbitral

proceedings and observed as under:

“The abandonment of the claim can be either express or implied. The

abandonment cannot be readily inferred. There is an implied

abandonment when admitted or proved facts are so clinching that the

only inference which can be drawn is of the abandonment. Only if the

established conduct of a claimant is such that it leads only to one

conclusion that the claimant has given up his/her claim can an

inference of abandonment be drawn. Even if it is to be implied, there

must be convincing circumstances on record which lead to an

inevitable inference about the abandonment. Only because a claimant,

after filing his statement of claim, does not move the Arbitral Tribunal

to fix a date for the hearing, the failure of the claimant, per se, will not

amount to the abandonment of the claim.

25. In law, abandonment cannot be readily inferred from mere inaction or

delay. It must be established that there was a clear, unequivocal, and

conscious intention on the part of the party to relinquish the arbitral

remedy. The test is not merely of lapse of time, but of intention as

discernible from the conduct of the party. In the present case, although
9
2026:CHC-OS:140
there has been considerable delay, the conduct of the Petitioner does not

disclose any such intention. On the contrary, the Petitioner approached

this Hon’ble Court in the year 2025, albeit under a mistaken

understanding, and subsequently withdrew the said petition. Thereafter,

steps were taken to communicate the order of appointment to the learned

Arbitrator. These actions, though belated, indicate a continuing intention to

pursue arbitration. Accordingly, the delay in the present case cannot be

construed as abandonment of the arbitral proceedings.

26. This Court now turns to the objection based on limitation. Section 43 of the

Arbitration and Conciliation Act, 1996 makes the provisions of the

Limitation Act applicable to arbitral proceedings. However, such application

must be understood in the context of the nature of the relief sought. The

present petition is not one for enforcement of a substantive claim, but for

termination of mandate and substitution of an arbitrator under Sections 14

and 15 of the Act. In such circumstances, the right to apply arises not from

the date of appointment of the arbitrator, but from the point at which the

mandate becomes incapable of being performed. In the present case, the

cause of action arose only upon the withdrawal of the learned Arbitrator on

19.06.2025. Even assuming that Article 137 applies, the period of

limitation would commence from the said date, and not from the earlier

date of appointment in 2021. The present petition, having been filed within

a reasonable time thereafter, cannot be held to be barred by limitation. The

provisions of Section 43 and Article 137 cannot be applied in a rigid or

mechanical manner so as to defeat the object of arbitration, particularly

where the statutory scheme under Sections 14 and 15 is designed to

ensure continuity of the arbitral process.

10

2026:CHC-OS:140

27. This Court is also mindful of the fact that arbitration is an efficacious

alternative dispute resolution mechanism, and that procedural lapses

ought not to defeat substantive rights, especially where disputes between

the parties remain unresolved. Denial of substitution in the present case

would effectively foreclose the Petitioner’s remedy despite the existence of a

valid arbitration agreement.

28. The Hon’ble Supreme Court has consistently held that where the mandate

of an arbitrator terminates, the Court must step in to ensure continuity of

the arbitral process through appointment of a substitute arbitrator. The

pro-arbitration approach mandates that disputes be resolved on merits

rather than being defeated on technical grounds.

29. In view of the aforesaid, this Court is of the considered opinion that the

ends of justice would be better served by permitting continuation of the

arbitral proceedings through appointment of a substitute arbitrator, rather

than terminating the same on account of procedural delay.

30. Accordingly, in exercise of powers under Sections 14 and 15 of the

Arbitration and Conciliation Act, 1996, the mandate of the learned Sole

Arbitrator stands terminated, and it is deemed appropriate to appoint a

substitute arbitrator to adjudicate the disputes between the parties.

31. In the aforesaid circumstances, Justice Pranab Kumar Chattopadhyay

(Retd.), a former Judge, of this Court is hereby appointed as the Sole

Arbitrator to adjudicate the disputes between the parties. The learned Sole

Arbitrator shall proceed with the arbitral proceedings from the stage at

which they stood prior to the withdrawal of the earlier Arbitrator, in

accordance with law.

11

2026:CHC-OS:140

32. The learned Sole Arbitrator shall, prior to entering upon the reference,

make the necessary disclosure in terms of Section 12(1) of the Arbitration

and Conciliation Act, 1996, read with the Fifth and Seventh Schedules

thereto, and shall be at liberty to fix his remuneration in accordance with

law.

33. With the aforesaid directions, the present petition stands allowed.

                                      .                 (GAURANG KANTH, J.)



Sakil Amed P.A.
 



Source link