Mintech Global Pvt Ltd vs Ultra Tech Cement Limited on 16 March, 2026

    0
    37
    ADVERTISEMENT

    the Arbitral Tribunal.

    SPONSORED

    3. By the impugned judgement and order, learned Single Judge

    has partly set aside and modified the arbitral award dated March

    20, 2023. Learned Single Judge has set aside the claim from

    Commitment Charges of the claimant being claim No. A3 and

    modified the rate of interest on repayment of mobilisation

    advance from 9% to 14.5%.

    4. Learned senior advocate appearing for the claimant has

    submitted that, the parties entered into a contract dated January

    27, 2016. He has contended that, the objective of the contract

    was setting up of a captive manufacturing unit for cement end

    products with such manufacturing units being set up solely at

    the instance and for the captive consumption of the respondent.

    He has pointed out that the total project investment was of Rs.

    65.74 crores, out of which, respondent paid Rs. 31.98 crores as

    mobilization advance being 50% of the total project investment

    cost which was repayable by the claimant in 96 equated monthly

    installments at the rate of 14.5% interest on reducing balance

    principals. He has pointed out that, the lock in period was for 10

    years and extendable by 6 years. The respondent was liable to

    utilise 100% of the capacity of the plant.



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here