    Gaurang Kanth, J. :-

    SPONSORED

    1. The present Petition has been filed under Section 29A of the Arbitration

    and Conciliation Act, 1996, seeking extension of the mandate of the

    arbitral tribunal for completion of the arbitral proceedings and for

    publication of the arbitral award.

    2. The brief facts giving rise to the present Petition are set out hereunder:

    3. The Petitioner extended a credit limit of Rs. 4,00,00,000/- to the

    Respondent vide facility agreement dated 30.03.2019. During Covid period,

    there was default in repayment and hence the parties renegotiated and

    2026:CHC-OS:79
    entered in to a supplementary agreement dated 30.06.2021. However, the

    Respondents defaulted in repayment as per the terms of the said

    supplementary agreement. Disputes having arisen between the parties,

    the Petitioner, by letter dated 22.03.2022, invoked the arbitration clause

    as contained in the Facility Agreement dated 30.03.2019 and

    supplementary agreement dated 30.06.2021 executed between the parties.