M/S Tissa Hydro Power Private Limited vs H.P. State Electricity Regulatory … on 23 March, 2026

    0
    51
    ADVERTISEMENT

    Himachal Pradesh High Court

    M/S Tissa Hydro Power Private Limited vs H.P. State Electricity Regulatory … on 23 March, 2026

    Author: Jyotsna Rewal Dua

    Bench: Jyotsna Rewal Dua

        ( 2026:HHC:8409
    
         IN THE HIGH COURT OF HIMACHAL PRADESH, SHIMLA
                                            CWP No. 8610 of 2025 alongwith
                                            connected matters
                                            Decided on: 23rd March, 2026
        -------------------------------------------------------------------------------------
        1. CWP No.8610 of 2025
    
    
    
    
                                                                             .
    
        M/s Tissa Hydro Power Private Limited                             .....Petitioner
    
    
                                              Versus
    
    
    
    
    
        H.P. State Electricity Regulatory Commission
        and Ors.                                                     .....Respondents
    
    
    
    
                                                   of
        -------------------------------------------------------------------------------------
        2. CWP No.1520 of 2026
        M/s Shiv Shakti Solar Power Project                               .....Petitioner
                            rt                Versus
    
        H.P. State Electricity Regulatory Commission
        and another                                                  .....Respondents
        -------------------------------------------------------------------------------------
        3. CWP No. 1522 of 2026
    
    
    
        M/s Sher-E-Punjab Solar Power Project
                                            .....Petitioner
    
    
    
    
                                              Versus
    
    
    
    
    
        H.P. State Electricity Regulatory Commission
        and another                                                  .....Respondents
        -------------------------------------------------------------------------------------
    
    
    
    
    
        4. CWP No. 1003 of 2026
        M/s Richmit Solar Power Project
                                                             .....Petitioner
    
    
                                               Versus
        H.P. State Electricity Regulatory Commission
        and another                                                  .....Respondents
        -------------------------------------------------------------------------------------
        5. CWP No. 1019 of 2026
    
    
    
    
                                                            ::: Downloaded on - 30/03/2026 20:29:38 :::CIS
                                                 2
        ( 2026:HHC:8409
        Shri Mahunag Solar Power Project
                                                                     .....Petitioner
    
    
                                              Versus
    
    
    
    
                                                                             .
        H.P. State Electricity Regulatory Commission
                                                                     .....Respondents
    
    
    
    
    
        and another
        -------------------------------------------------------------------------------------
        6. CWP No. 1519 of 2026
    
    
    
    
    
        Siya Solar Power Project
                                                                     .....Petitioner
    
    
    
    
                                                    of
                                              Versus
    
    
        H.P. State Electricity Regulatory Commission
        and another         rt                                       .....Respondents
        -------------------------------------------------------------------------------------
        7. CWP No. 1521 of 2026
        M/s Bajrang Constructions Solar Power Project
    
                                                 .....Petitioner
    
    
                                              Versus
    
    
    
        H.P. State Electricity Regulatory Commission
        and another                                                  .....Respondents
    
    
    
    
        -------------------------------------------------------------------------------------
        8. CWP No. 11256 of 2025
    
    
    
    
    
        M/s Chevron Hydel (P) Ltd.
                                                                     .....Petitioner
    
    
    
    
    
                                              Versus
    
    
        H.P. State Electricity Board Ltd.
        and another                                                  .....Respondents
        -------------------------------------------------------------------------------------
        9. CWP No. 13220 of 2025
        M/s IQU Power Company Private Limited
                                                                     .....Petitioner
    
    
    
    
                                                            ::: Downloaded on - 30/03/2026 20:29:38 :::CIS
                                                 3
        ( 2026:HHC:8409
                                              Versus
    
    
        H.P. State Electricity Regulatory Commission
        And Ors.                                             .....Respondents
        -------------------------------------------------------------------------------------
        10. CWP No. 14042 of 2025
    
    
    
    
                                                                             .
        M/s Door Sanchar Hydro Power Pvt. Ltd.
    
    
    
    
    
                                                                     .....Petitioner
    
    
    
    
    
                                              Versus
    
    
        H.P. State Electricity Regulatory Commission
        and Ors.                                                     .....Respondents
    
    
    
    
                                                    of
        -------------------------------------------------------------------------------------
        11. CWP No. 14086 of 2025
        M/s Aleo Manali Hydro Power Pvt. Ltd.
                                                                     .....Petitioner
                            rt
                                              Versus
    
        H.P. State Electricity Regulatory Commission
        and Ors.                                             .....Respondents
    
    
        -------------------------------------------------------------------------------------
        12. CWP No. 13223 of 2025
        M/s Awa Power Company Pvt. Ltd.
                                                                     .....Petitioner
    
    
    
    
    
    
                                              Versus
    
    
        H.P. State Electricity Regulatory Commission
    
    
    
    
    
        and Ors.                                             .....Respondents
        -------------------------------------------------------------------------------------
        13. CWP No. 13095 of 2025
        M/s Neogal Power Company Pvt. Ltd.
                                                                     .....Petitioner
    
    
                                              Versus
    
    
        H.P. State Electricity Regulatory Commission
    
    
    
    
                                                            ::: Downloaded on - 30/03/2026 20:29:38 :::CIS
                                                            4
        ( 2026:HHC:8409
        and Ors.                                             .....Respondents
        -------------------------------------------------------------------------------------
        14. CWP No. 10230 of 2024
        M/s Greenko HIM Kailash Hydro Power Pvt. Ltd.
    
                                                                                     .....Petitioner
    
    
    
    
                                                                                              .
                                               Versus
    
    
    
    
    
        H.P. State Electricity Regulatory Commission
        and Ors.                                             .....Respondents
        -------------------------------------------------------------------------------------
        15. CWP No. 2024 of 2026
    
    
    
    
    
        M/s Hamal Hydel Project Braza Tyre.
                                                                                     .....Petitioner
                                                        Versus
    
    
    
    
                                                               of
        H.P. State Electricity Regulatory Commission
        and Ors.
                               rt          .....Respondents
    
        -------------------------------------------------------------------------------------
        Coram
    
        Ms. Justice Jyotsna Rewal DuaWhether approved for
    
        reporting?1
    
    
    
        For the Petitioners:                   Mr. Rajneesh Maniktala, Mr. Suneet
                                               Goel, Senior Advocates, Mr. Ajay
                                               Vaidya, Ms. Shalini Thakur, Mr.
    
    
    
    
                                               Dinkar Bhaskar, Mr. Shivalik Bhaik,
                                               Mr. Vivek Negi, with Mr. Amit Kumar
    
    
    
    
    
                                               Dhumal and Ms. Parul Negi,
                                               Advocates.
        For the Respondents: Mr. N.K. Sood, Senior Advocate with Mr.
    
    
    
    
    
                             Vinay Mehta, Advocate, for respondent-
                             HPERC.
                                               Ms. Sunita Sharma, Senior Advocate
                                               with Mr. Dhananjay Sharma, Mr.
                                               Abhishek Verma and Mr. Saurav
                                               Upadhyay, Advocates, for respondent-
                                               HPSEBL.
    
    
               1
                   Whether reporters of print and electronic media may be allowed to see the order? Yes.
    
    
    
    
                                                                          ::: Downloaded on - 30/03/2026 20:29:38 :::CIS
                                                5
        ( 2026:HHC:8409
    
    
                                       Mr. Vikas Chauhan, Advocate, for
                                       respondents-Bonafide                  Himachalies
                                       Hydro Power Developers Association in
                                       CWP Nos. 8610/2025 & 10230/2024
        ------------------------------------------------------------------------------------
        Jyotsna Rewal Dua, Judge
    

    .

    All these petitions are based upon almost similar

    SPONSORED

    pleadings, claiming almost similar reliefs arising out of

    similar cause of actions, hence, are taken up together.

    2. Grievance of the petitioners emanates from an

    of
    order passed by the respondent–Himachal Pradesh

    Electricity Regulatory Commission (HPERC), Shimla on
    rt
    23.02.2024 in Suo Motu Petition No. 08/2023, fixing

    normative Operation & Maintenance (O&M) charges.

    Challenge has also been laid to the consequent demand

    notices issued to the petitioners by the respondent–

    Himachal Pradesh State Electricity Board Limited.

    A petition under Section 86 of the Electricity Act,

    2003 was filed before the HPERC by the ‘Bonafide

    Himachalies Hydro Power Developers Association’. This

    petition, bearing No. 29/2023, pertained to the adjudication

    of a dispute between independent power producers and the

    H.P. State Electricity Board Limited concerning Operation &

    Maintenance (O&M) charges being levied by the Board in

    respect of inter connection facility/bay provided to the

    generating companies, who had set up Small Hydro Electric

    ::: Downloaded on – 30/03/2026 20:29:38 :::CIS
    6
    ( 2026:HHC:8409
    Power Projects in the State. HPERC decided the petition on

    16.10.2023, observing that the proposal to fix normative

    O&M charges of bay(s) was required to undergo a prior

    publication process by floating the proposal on the website

    .

    of HPERC, so as to provide equal opportunity to all

    stakeholders to file their objections/suggestions. Pursuant

    to the directions issued in the order dated 16.10.2023, a

    proposal was placed before the Commission, which was

    of
    registered as Suo Motu Petition No. 08/2023, on the subject

    of Fixation of normative O&M charges to be paid by the Small
    rt
    Hydro Power Project(s) and other RE generators connected at

    Sub-Stations owned by the Distribution Licensee where

    maximum nominal voltage level at any point in such Sub-

    stations does not excess 33 kV. The Commission proceed to

    fix normative O&M charges to be paid by Small Hydro Power

    Producers and other Renewable Energy Generators selling

    power to the Distribution Licensee, as well as Renewable

    Energy Developers selling power under open access for

    utilizing its infrastructure. HPERC invited public objections

    and suggestions by issuing public notices in newspapers as

    well as on its website. HPERC, vide its letter dated

    06.11.2023, requested all major stakeholders, including the

    Small Hydro Project Welfare Association, State Government,

    Directorate of Energy HIMURJA, and the Distribution

    ::: Downloaded on – 30/03/2026 20:29:38 :::CIS
    7
    ( 2026:HHC:8409
    Licensee, to submit their objections/suggestions in terms of

    the aforesaid public notices. HPERC received

    comments/suggestions on the draft proposal from some of

    the stake holders. ‘Bonafide Himachalies Hydro Power

    .

    Developers Association’ approached HPERC for sharing data

    inputs, which was allowed to be collected from HPSEBL.

    Public hearing in the matter was held on 06.12.2023.

    Thereafter, order was passed by HPERC on 23.02.2024 in

    of
    Suo Motu Petition No. 08/2023 fixing normative O&M

    charges. Petitioners are aggrieved against order dated
    rt
    23.02.2024 passed by the HPERC in Suo Moto Petition No.8

    of 2023, as also the consequent demand notices issued to

    them by the HPSEBL on the strength of above order.

    3. According to the petitioners, HPERC lacks the

    jurisdiction to issue the impugned order fixing O&M charges.

    The impugned order has re-written the contracts entered into

    between the parties fixing the O&M charges for use of

    interconnection facilities. It has also been submitted that

    though in some cases, O&M charges agreement have been

    entered into between parties and those agreements have

    been rewritten by HPERC under the impugned order, but in

    number of the cases, such agreements have not been

    executed between the parties, O&M charges could not have

    been fixed under the impugned order without hearing the

    ::: Downloaded on – 30/03/2026 20:29:38 :::CIS
    8
    ( 2026:HHC:8409
    petitioners. As per the petitioners, in view of the grievance

    raised, the writ petitions are maintainable. Reliance was

    placed upon Haryana Power Purchase Centre Versus

    Sasan Power Limited and others 2 & PTC India Limited

    .

    Versus Central Electricity Regulatory Commission 3 as

    also upon Radha Krishan Industries Versus State of

    Himachal Pradesh and others4 and Whirlpool

    Corporation Versus Registrar of Trade Marks, Mumbai

    of
    and others5 on the point that alternate remedy is not a bar

    where order rt impugned, has been passed without

    jurisdiction.

    Whereas, according to the respondents:- the

    O&M charges duly form part of tariff charges. They are a

    component of the aggregate revenue requirement provided

    under Rule 34 of the H.P.E.R.C (Terms and Conditions for

    Determination of Hydro Generation Tariff) Regulations,

    2024. The Rule is as under:-

    “34. Aggregate Revenue Requirement (ARR).
    34.1 The ARR of a hydro generating station shall comprise of

    the following elements: (a) Operation and Maintenance
    Expenses; b) Return on Equity Capital; c) Tax on Return
    on Equity; d) Interest on Loan Capital; e) Interest on
    Working Capital; and f) Depreciation.”

    2

    (2024) 1 SCC 247
    3
    (2010) 4 SCC 603
    4
    (2021) 6 SCC 771
    5
    (1998) 8 SCC 1

    ::: Downloaded on – 30/03/2026 20:29:38 :::CIS
    9
    ( 2026:HHC:8409
    The HPERC (Promotion of Generation from the

    Renewable Energy Sources and Terms and Conditions for

    Tariff Determination) Regulations, 2017 provides: –

    “12. Tariff design.- (1) The single part levellised tariff structure

    .

    shall be followed for the renewable energy technologies:

    Provided that for renewable energy technologies
    having fuel cost component, like biomass power projects
    and non-fossil fuel based cogeneration, single part tariff

    with two components, i.e. fixed cost component and fuel
    cost component, shall be determined. (a) The following
    fixed cost components shall be included for determining
    the tariff.- (b) Return on equity; (c) Interest on loan

    of
    capital; (d) Depreciation; (e) Interest on working capital;
    and (e) Operation and maintenance expenses.

    28. Operation and maintenance expenses.– (1) Operation
    and maintenance expenses mean the expenditure
    rt
    incurred on operation and maintenance of the project, or
    part thereof, and includes, without limitation, the
    expenditure on manpower, establishment (including

    employees expense, administrative and general
    expenses), repairs, spares, consumables, insurance and
    overheads as well as the taxes, duties and other levies
    on any or all such activities.

    (2) Operation and maintenance expenses shall be
    determined for the tariff period based on normative
    operation and maintenance expenses specified in
    Chapter-V of these Regulations for the small hydro

    projects and as stipulated in relevant orders of the
    Commission for other renewable technologies.

    State Commission or Central Commission, as

    the case may be, determines tariff under the governing law

    primarily the Electricity Act, 2003. O&M charges are

    recognized components of Tariff, alongwith (a) return on

    equity (b) interest on loans (c) depreciation (d) interest on

    working capital. The Commission generally specifies

    normative O&M expenses through tariff regulations and

    ::: Downloaded on – 30/03/2026 20:29:38 :::CIS
    10
    ( 2026:HHC:8409
    allows excalation factors i.e. inflation linked increase year

    to year. The Commission may also consider actual against

    norms depending upon tariff framework. The Commission

    issues Tariff regulations as per its Regulatory framework

    .

    i.e. Multi Year Tariff Regulations which include (a) Lay

    down formulae and norms for O&M (b) avoid arbitrary

    claims by utilities (c) Ensure efficiency and consumer

    protection.

    
    
    
    
                                                           of
                           It     has       been        further        emphasized            that
    
    

    determination of O & M charges by the Commission does not
    rt
    amount to rewriting the contract under the Electricity Act.

    Tariff determination is statutory function of the Commission

    and the Statute can always override the contracts, if

    executed between the parties. Determination of tariff is in

    exclusive domain of Commission. Regulatory intervention

    does not amount to altering or rewriting the contracts but

    enforcing the statutory schemes. Placing reliance upon

    Jaipur Vidyut Vitran Nigam Limited and Others Vs. MB

    Power (Madhya Pradesh) Limited and Others 6, The State

    of Himachal Pradesh and Anr. Vs. JSW Hydro Energy

    Limited & Ors.7 and Himachal Pradesh Electricity

    6
    2024 (8) SCC 513
    7
    Civil Appeal No.12883 of 2024, decided on 16.07.2025

    ::: Downloaded on – 30/03/2026 20:29:38 :::CIS
    11
    ( 2026:HHC:8409
    Board Ltd. Vs. Kundan Hydro (Lui) Pvt. Ltd. & Anr.8,

    prayer was made to dismiss the petitions being not

    maintainable in view of availability of statutory appeal

    against the impugned order.

    .

    4. HPERC has carried out the impugned exercise of

    fixing normative O & M charges order dated 23.02.2024 in

    terms of power vested in it under Section 86 of the Electricity

    Act (reproduced at para 4(ii)(a) of this judgment). Admittedly

    of
    order dated 16.10.2023 passed by HPERC, is subject matter

    of appeal No. 920 of 2023 pending before Appellate Tribunal
    rt
    for Electricity (APTEL). Against the impugned order dated

    23.02.2024 passed by HPERC, petitioners have statutory

    remedies available to them under Section 111 of the

    Electricity Act, 2003 by preferring an appeal/revision to the

    Appellate Tribunal. The Section reads as under:-

    “111. Appeal to Appellate Tribunal.–(1) Any person
    aggrieved by an order made by an adjudicating
    officer under this Act (except under section 127) or

    an order made by the Appropriate Commission
    under this Act may prefer an appeal to the
    Appellate Tribunal for Electricity:

    Provided that any person appealing against the
    order of the adjudicating officer levying any penalty
    shall, while filing the appeal, deposit the amount of such
    penalty:

    Provided further that where in any particular
    case, the Appellate Tribunal is of the opinion that the
    deposit of such penalty would cause undue hardship to
    such person, it may dispense with such deposit subject

    8
    LPA No. 492 of 2024 decided on 09.01.2026

    ::: Downloaded on – 30/03/2026 20:29:38 :::CIS
    12
    ( 2026:HHC:8409
    to such conditions as it may deem fit to impose so as to
    safeguard the realisation of penalty.
    (2) Every appeal under sub-section (1) shall be filed
    within a period of forty-five days from the date on which
    a copy of the order made by the adjudicating officer or
    the Appropriate Commission is received by the aggrieved
    person and it shall be in such form, verified in such

    .

    manner and be accompanied by such fee as may be

    prescribed:

    Provided that the Appellate Tribunal may
    entertain an appeal after the expiry of the said period of
    forty-five days if it is satisfied that there was sufficient

    cause for not filing it within that period.

    (3) On receipt of an appeal under sub-section (1), the
    Appellate Tribunal may, after giving the parties to the

    of
    appeal an opportunity of being heard, pass such orders
    thereon as it thinks fit, confirming, modifying or setting
    aside the order appealed against.

    (4)rt The Appellate Tribunal shall send a copy of every
    order made by it to the parties to the appeal and to the
    concerned adjudicating officer or the Appropriate
    Commission, as the case may be.

    (5) The appeal filed before the Appellate Tribunal
    under sub-section (1) shall be dealt with by it as
    expeditiously as possible and endeavor shall be made by
    it to dispose of the appeal finally within one hundred and

    eighty days from the date of receipt of the appeal:

    Provided that where any appeal could not be
    disposed of within the said period of one hundred and

    eighty days, the Appellate Tribunal shall record its
    reasons in writing for not disposing of the appeal within
    the said period.

    (6) The Appellate Tribunal may, for the purpose
    of examining the legality, propriety or correctness
    of any order made by the adjudicating officer or the

    Appropriate Commission under this Act, as the case
    may be, in relation to any proceeding, on its own
    motion or otherwise, call for the records of such
    proceedings and make such order in the case as it
    thinks fit.”

    4(i) In Radha Krishan Industries4, Hon’ble Apex

    Court summarized the principles of law regarding

    ::: Downloaded on – 30/03/2026 20:29:38 :::CIS
    13
    ( 2026:HHC:8409
    maintainability of writ petition before the High Court under

    Article 226 of the Constitution vis-à-vis the rule of alternate

    remedy as under:-

    “27. The principles of law which emerge are that:

    .

    27.1. The power under Article 226 of the Constitution to
    issue writs can be exercised not only for the enforcement
    of fundamental rights, but for any other purpose as well.
    27.2. The High Court has the discretion not to entertain

    a writ petition. One of the restrictions placed on the power
    of the High Court is where an effective alternate remedy
    is available to the aggrieved person.

    of
    27.3. Exceptions to the rule of alternate remedy arise
    where: (a) the writ petition has been filed for the
    enforcement of a fundamental right protected by Part III
    of the Constitution; (b) there has been a violation of the
    principles of natural justice; (c) the order or proceedings
    rt
    are wholly without jurisdiction; or (d) the vires of a
    legislation is challenged.

    27.4. An alternate remedy by itself does not divest the
    High Court of its powers under Article 226 of the
    Constitution in an appropriate case though ordinarily, a
    writ petition should not be entertained when an
    efficacious alternate remedy is provided by law.

    27.5. When a right is created by a statute, which itself
    prescribes the remedy or procedure for enforcing the right
    or liability, resort must be had to that particular statutory

    remedy before invoking the discretionary remedy under
    Article 226 of the Constitution. This rule of exhaustion of

    statutory remedies is a rule of policy, convenience and
    discretion.

    27.6. In cases where there are disputed questions of

    fact, the High Court may decide to decline jurisdiction in
    a writ petition. However, if the High Court is objectively
    of the view that the nature of the controversy requires the
    exercise of its writ jurisdiction, such a view would not
    readily be interfered with.”

    4(ii)(a) In Kundan Hydro (Luni) Pvt. Ltd. Vs. State of

    H.P. through its Additional Chief Secretary (MPP &

    ::: Downloaded on – 30/03/2026 20:29:38 :::CIS
    14
    ( 2026:HHC:8409
    Power) & Anr.9, respondents had questioned

    maintainability of the writ petition as under: –

    “5(iii) Maintainability of Writ Petition
    5(iii)(a) Respondents have also questioned the

    .

    maintainability of the writ petition. According to the

    respondents, the Electricity Act, 2003 is an exhaustive
    legislation which provides complete machinery for
    adjudication of the disputes between the distribution licensee

    and generating companies or to refer the same for arbitration
    under section 86(1)(f) of the Act. Being relevant, the Section is
    extracted hereinafter: –

    of
    “86. (1) The State Commission shall discharge the following
    functions, namely: –

    (a) determine the tariff for generation, supply, transmission
    rt
    and wheeling of electricity, wholesale, bulk or retail, as the
    case may be, within the State:

    Providing that where open access has been permitted to a
    category of consumers under section 42, the State
    Commission shall determine only the wheeling charges and
    surcharge thereon, if any, for the said category of

    consumers;

    (b) regulate electricity purchase and procurement process of
    distribution licensees including the price at which electricity

    shall be procured from the generating companies or

    licensees or from other sources through agreements for
    purchase of power for distribution and supply within the
    State;

    (c) facilitate intra-state transmission and wheeling of
    electricity;

    (d) issue licences to persons seeking to act as transmission
    licensees, distribution licensees and electricity traders with
    respect to their operations within the State;

    9

    CWP No. 7177/2024 decided on 10.09.2024

    ::: Downloaded on – 30/03/2026 20:29:38 :::CIS
    15
    ( 2026:HHC:8409

    (e) promote cogeneration and generation of electricity from
    renewable sources of energy by providing suitable
    measures for connectivity with the grid and sale of
    electricity to any person, and also specify, for purchase of
    electricity from such sources, a percentage of the total

    .

    consumption of electricity in the area of a distribution

    licence;

    (f) adjudicate upon the disputes between the licensees, and
    generating companies and to refer any dispute for

    arbitration;

    (g) levy fee for the purposes of this Act; (h) specify State Grid
    Code consistent with the Grid Code specified under clause

    of

    (h) of sub-section (1) of section 79;

    (i) specify or enforce standards with respect to quality,
    continuity and reliability of service by licensees;
    rt

    (j) fix the trading margin in the intra-State trading of
    electricity, if considered, necessary; and

    (k) discharge such other functions as may be assigned to it

    under this Act.

    (2) The State Commission shall advise the State Government
    on all or any of the following matters, namely :-

    (i) promotion of competition, efficiency and economy in
    activities of the electricity industry;

    (ii) promotion of investment in electricity industry;

    (iii) reorganization and restructuring of electricity industry in
    the State;

    (iv) matters concerning generation, transmission,
    distribution and trading of electricity or any other matter

    referred to the State Commission by that Government.
    (3) The State Commission shall ensure transparency while
    exercising its powers and discharging its functions.
    (4) In discharge of its functions the State Commission shall
    be guided by the National Electricity Policy, National
    Electricity Plan and tariff policy published under Section 3.”

    According to the respondents, the issue involved in
    the matter has to be considered & decided in accordance with

    ::: Downloaded on – 30/03/2026 20:29:38 :::CIS
    16
    ( 2026:HHC:8409
    Regulation 17 of the HPERC Regulations-2017 by filing
    appropriate proceedings before the HPERC. Writ petition is
    therefore not maintainable. Placing reliance upon Noble
    Resources Ltd. vs. State of Orissa
    & anr.10; State of U.P.
    & ors. vs. Bridge & Roof Company (India) Ltd.11; and New

    .

    India Assurance Co. Ltd. vs. Vipin Behari Lal

    Srivastava12, it has been contended that writ petition stems
    from a contractual dispute, therefore, is beyond the purview of
    Article 226 of the Constitution.”

    Opposing the issue of maintainability raised by

    the respondent, petitioner had stressed that: –

    of
    “Whereas according to the petitioner, plea of non
    maintainability of the writ petition, is a misconceived
    contention in view of settled law that existence of an
    rt
    alternate remedy is not a bar on maintainability of the writ
    petition under Article 226 of the Constitution. The present

    case involves rank arbitrariness leading to perversity on
    part of respondents in attempting to enforce a third party
    contract against a non-signatory, contrary to law &
    applicable Regulations. The writ petition, therefore, is

    maintainable.”

    Holding that petitioner was not seeking to

    determine tariff for sale/purchase of electricity generated at

    its power plant but raising the issue whether PPA in question

    would bind the petitioner, the objection of maintainability

    was turned down as under: –

    “5(iii)(b) Petitioner in the instant case is not seeking to
    determine tariff for sale/purchase of the electricity
    generated from LHEP 4.50 MW. The question involved in the

    10
    (2006) 10 SCC 236
    11
    (1996) 6 SCC 22
    12
    (2008) 3 SCC 446

    ::: Downloaded on – 30/03/2026 20:29:38 :::CIS
    17
    ( 2026:HHC:8409
    lis is as to whether the PPA dated 31.05.2000 can be held
    to be binding upon the petitioner.

    In M.P. Power Management Company Limited,
    Jabalpur vs. Sky Power Southeast Solar India Private
    Limited
    & ors13 the appellant had challenged the judgment

    .

    passed by the High Court whereby an order passed by the

    appellant terminating PPA entered into by the appellant &
    respondent, was quashed. Hon’ble Apex Court held that
    PPA is not a statutory contract. The mere fact that relief is

    sought under a contract which is not statutory will not
    entitle the State in a case by itself to ward off scrutiny of its
    action or inaction under the contract, if complaining party is

    of
    able to establish that such action/inaction is per se
    arbitrary. It was also held that an action will lie when
    State’s action relates to the stage prior to the contract being
    rt
    entered into. Even after the contract is entered into there can
    be a variety of circumstances which may provide a cause of
    action to a party to the contract with the State to seek relief

    by filing a writ petition. Relevant paras from the judgment
    are as under……”

    Kundan Hydro9 was allowed with following

    directions: –

    “7. The Result
    The sum total of above discussions is that this writ petition

    succeeds. Following directions are issued:-

    (i) Impugned communication dated 16.07.2024 is
    quashed and set aside.

    (ii) It is held that Power Purchase Agreement dated
    31.05.2000 executed between respondent No. 2-HPSEBL
    and M/s Subhash Projects & Marketing Limited (Original
    Project Developer) is not binding upon the petitioner and
    cannot be enforced against it.

    (iii) Respondent No. 2 is directed to execute a Power
    Purchase Agreement with the petitioner in respect of the
    entire Project capacity of 4.50 MW at the HPERC determined
    tariff applicable as on Scheduled Commercial Operation

    13
    (2023) 2 SCC 703

    ::: Downloaded on – 30/03/2026 20:29:38 :::CIS
    18
    ( 2026:HHC:8409
    Date of the Project in accordance with law and complete all
    codal formalities in furtherance thereof without
    unnecessary delay.

    (iv) In order to avoid loss of electricity generated at the
    Project, it is ordered that till the determination of tariff as on
    the date of commissioning of the Project by the HPERC in
    terms of direction No. (iii) above, the petitioner shall be

    .

    permitted by the respondents to sell the electricity generated

    from its Power Project to third parties after adjusting the free
    power supply to the respondents in accordance with law.”

    4(ii)(b) The above decision was overturned in Himachal

    Pradesh Electricity Board Ltd. vs. Kundan Hydro (Luni)

    of
    Pvt. Ltd & Anr.14 holding, as per Section 86(b) of the

    Electricity Act, it is the function of State Electricity

    Regulatory Commission to regulate electricity purchase and
    rt
    procurement process of distribution licenses including the

    price at which electricity is to be procured and to determine

    tariff. The exercise undertaken in Kundan Hydro (Luni)9 was

    held to be that of tariff determination, which falls within the

    exclusive domain of Electricity Regulatory Commission.

    Relevant paras from the decision are as under: –

    “31. As per Section 86(b) of the Electricity Act, 2003, the
    functions of the State Electricity Commission are to regulate

    electricity purchase and procurement process of distribution
    licensees including the price at which electricity is to be
    procured and to determine the tariff. Section 86(1) (a) & (b)
    of the said Act reads as under:-

    xxx xxx xxx

    36. This aspect apparently skipped the notice of the
    learned Single Judge while allowing the writ petition. It is

    14
    LPA No. 492/2024 decided on 09.01.2026

    ::: Downloaded on – 30/03/2026 20:29:38 :::CIS
    19
    ( 2026:HHC:8409
    thus apparent that the Writ Court has taken over the
    exercise as such of tariff determination which falls within
    the exclusive domain of the Electricity Regulation
    Commission and therefore an error of law has occurred
    while issuance of the necessary directions. It is not for this

    .

    Court to substitute its opinion as to whether the petitioners

    have to sell power at what rate and therefore the fixation of
    tariff by the learned Single Judge was not justified. The
    Project having not seen the light of the day and not being

    commissioned for all these years, it was an exercise which
    was to be determined by the Electricity Regulatory
    Commission rather than forcing the Board as such to enter

    of
    into an Agreement at the prevalent rates and re-fixing the
    terms of the Contract as such. It was beyond the purview of
    the Writ Court on the ground by granting relief 7(iii) that the
    rt
    action was arbitrary and would thus be an exercise by
    which the power of the Commission has been taken over
    and the directions have been issued by the Writ Court which

    is not permissible.

    38. The judgment was delivered recently only on
    16.07.2025 and therefore, the learned Single Judge did not

    have the benefit of the said judgment. Another judgment
    arising from this Court in KKK Hydro Power Limited case
    (supra) also while dealing with the issue of tariff fixation at

    the rate of Rs.2.87 and 2.95 per kWh and while dealing with
    the Appellate Tribunals order has held that while referring

    to Section 86(1) (b) of the ‘Act’ that the fixing of the price of
    purchase of electricity is not a matter of private negotiations

    and Agreements between the generating company and a
    distribution licensees, while upholding the order of the
    Appellate Tribunal the Apex Court had come to the
    conclusion that it required no determination for the 3
    Megawatts Hydel Power Projects but only for the additional
    1.9 Megawatts was required to be re-determined.

    39. In Ramayana Ispat Private Limited and
    another Vs. State of Rajasthan & Others (2025) 8 SCC
    747, the statutory scheme of the Electricity Act, 2003 and

    ::: Downloaded on – 30/03/2026 20:29:38 :::CIS
    20
    ( 2026:HHC:8409
    the regulations framed by the State Commission were held
    to be facilitating intra-Sate transmissions and wheeling of
    electricity and for maintaining disciplines in power
    scheduling and ensuring that consumers do not gain unfair
    advantage by evading scheduling norms and for equitable

    .

    treatment of all market participants while safeguarding the

    integrity of the power grid. The relevant part reads as
    under:-

    “67. Furthermore, the 2003 Act, envisages a balance

    between the rights of open access consumers and the
    operational concerns of the power sector. The 2016
    Regulations, while imposing certain conditions, do not

    of
    outright deny open access but ensure that its
    implementation is equitable and does not jeopardise grid
    discipline. Open access remains available to consumers
    who comply with regulatory prerequisites, including
    rtscheduling obligations and financial commitments. Thus,
    the appellant’s assertion that their right to open access is

    foreclosed is misplaced. The 2016 Regulations are
    consistent with the legislative intent of the 2003 Act,
    ensuring that open access is exercised in a manner that
    does not compromise system stability, fairness, or economic

    viability. Therefore, the regulatory framework does not
    foreclose open access but rather operationalises it within
    reasonable constraints essential for sustaining the
    electricity sector.

    68. The statutory scheme under the 2003 Act mandates that
    regulations framed by State Commissions must serve the

    larger public interest. The respondents have successfully
    established that the impugned Regulations serve this

    purpose by ensuring equitable treatment of all market
    participants while safeguarding the integrity of the power
    grid.

    69. RERC derives its authority from the 2003 Act, which
    vests in it the power to frame regulations governing open
    access, scheduling, and penalties. Section 86(1)(c) of the
    2003 Act specifically empowers State Commissions to
    facilitate intra-State transmission and wheeling of
    electricity. Furthermore, Section 181 empowers the
    Commission to make regulations consistent with the 2003

    ::: Downloaded on – 30/03/2026 20:29:38 :::CIS
    21
    ( 2026:HHC:8409
    Act and its objectives. The impugned Regulations have been
    framed in exercise of these statutory powers. The
    requirement for scheduling, imposition of penalties, and
    limits on drawl are not arbitrary but are measures falling
    within the regulatory ambit of the Commission to ensure
    grid stability and fair competition. The 2003 Act envisions a

    .

    structured and fair mechanism for open access while

    ensuring that market participants do not engage in practices
    detrimental to the larger consumer base. Moreover, under
    Section 42 of the 2003 Act, the State Commission has the

    mandate to regulate open access in distribution and specify
    the charges and conditions applicable. The respondents
    have demonstrated that these conditions are necessary for

    of
    maintaining discipline in power scheduling and ensuring
    that open access consumers do not gain an unfair
    advantage over other consumers by evading scheduling
    norms or penalties.

    rt

    70. The Jodhpur Bench in common order dated 29-8-2016,
    which has been challenged before us in Civil Appeals

    Nos.7965 and 7966 of 2019, has rightly upheld the validity
    of the 2016 Regulations holding that any inconvenience
    caused or even some hardship faced by the captive power
    generators shall not make the Regulations illegal. The High

    Court also rightly pointed out that the appellants have failed
    to establish that the impugned Regulations are in
    contravention of their rights protected under Part III or any

    other provision of the Constitution of India or that the
    Regulations have been enacted without having the

    competence to do so or they are manifestly arbitrary or
    unreasonable. It has been rightly held by the High Court
    that the 2016 Regulations are in consonance with the

    objects of the 2003 Act and have been framed as per the
    competence available under Section 181 read with Section
    42
    of the 2003 Act.”

    Finally appeal was allowed as under holding the

    writ petition to be not maintainable: –

    ::: Downloaded on – 30/03/2026 20:29:38 :::CIS
    22

    ( 2026:HHC:8409

    “40. It is thus, apparent that the learned Single Judge has
    mis-directed itself by choosing to decide the issue on merits
    and also rejected the plea of alternate remedy on the ground
    that there was an arbitrary action as such. The Board as
    such had only recommended that the matter should be

    .

    placed before the Electricity Regulatory Commission,

    keeping in view the power as such of the Commission to fix
    the tariff and once the Regulations had come into force, it
    was for the Commission to see as to what would be the rate

    of the tariff to be fixed between the Board and the petitioner
    under the policy dated 15.05.2018 which makes it
    mandatory for the Board to purchase the electricity from

    of
    Projects below 10 MW.

    41. Therefore, the judgment passed by the learned Single
    Judge is not liable to be upheld and the appeal is liable to
    rt
    be allowed. Accordingly, we set aside the judgment dated
    10.09.2024 and relegate the parties to its alternate remedy
    as suggested by the appellant-Board dated 16.07.2024.

    Needless to say, it is for the Regulatory Commission as such
    to fix the tariff as such, keeping in mind all the relevant
    parameters and the fact that project has been hanging fire

    since the year 2000. Neither the Board nor the State or the
    petitioners can be prejudiced on account of the 25 years
    having been passed and the interest as such would have to

    be adjudicated, keeping in mind this aspect by the expert
    body.

    42. The appeal stands disposed of accordingly, as
    indicated hereinabove, along with pending miscellaneous

    applications, if any.”

    4(iii). Jaipur Vidyut Vitran Nigam Ltd.6 held that

    High Court was not justified in directly entertaining the writ

    petition when the petitioner had an adequate alternate remedy

    ::: Downloaded on – 30/03/2026 20:29:38 :::CIS
    23
    ( 2026:HHC:8409
    of approaching the State Electricity Commission. It was

    observed as under:-

    “127. It is needless to state that this Court, time and again, in
    various judgments including the one in the case of GMR
    Warora Energy Limited
    (supra) has recognised the

    .

    requirement of balancing the consumers’ interest with that

    of the interest of the generators. It will not be permissible
    to take a lopsided view only to protect the interest of the
    generators ignoring the consumers’ interest and public

    interest.

    128. We find that the High Court was not justified in
    entertaining the petition. The Constitution Bench of this
    Court in the case of PTC India Limited (supra) has held that

    of
    the Electricity Act is an exhaustive code on all matters
    concerning electricity. Under the Electricity Act, all issues
    dealing with electricity have to be considered by the
    authorities constituted under the said Act. As held by the
    Constitution Bench of this Court, the State Electricity
    rt
    Commission and the learned APTEL have ample powers to
    adjudicate in the matters with regard to electricity. Not
    only that, these Tribunals are tribunals consisting of

    experts having vast experience in the field of electricity. As
    such, we find that the High Court erred in directly
    entertaining the writ petition when the respondent No.1,
    i.e., the writ petitioner before the High Court had an

    adequate alternate remedy of approaching the State
    Electricity Commission.

    129. This Court in the case of Reliance Infrastructure Limited v.

    State of Maharashtra and others15 has held that while

    exercising its power of judicial review, the Court can step
    in where a case of manifest unreasonableness or

    arbitrariness is made out.

    130. In the present case, there is not even an allegation with
    regard to that effect. In such circumstances, recourse to a
    petition under Article 226 of the Constitution of India in the

    availability of efficacious alternate remedy under a
    statute, which is a complete code in itself, in our view, was
    not justified.

    131. No doubt that availability of an alternate remedy is not a
    complete bar in the exercise of the power of judicial review
    by the High Courts. But, recourse to such a remedy would
    be permissible only if extraordinary and exceptional
    circumstances are made out. A reference in this respect

    15
    (2019) 3 SCC 352

    ::: Downloaded on – 30/03/2026 20:29:38 :::CIS
    24
    ( 2026:HHC:8409
    could be made to the judgments of this Court in the cases
    of Radha Krishan Industries v. State of Himachal
    Pradesh
    and others16 and South Indian Bank Ltd.

    and others v. Naveen Mathew Philip and another17.”

    After referring in para 132 to Radha Krishan

    .

    Industries v. State of H.P.4 and principles laid down therein, it

    was held as under:-

    “98. This Court has clearly held that when a right is created
    by a statute, which itself prescribes the remedy or
    procedure for enforcing the right or liability, resort must
    be had to that particular statutory remedy before

    of
    invoking the discretionary remedy under Article 226 of
    the Constitution of India.”

    4(iv). Following issues arose for determination in
    rt
    Power Grid Corporation of India Limited Versus Madhya

    Pradesh Power Transmission Company Limited & Ors.18:-

    “30. Having heard the learned counsel appearing for the
    parties and having gone through the materials on record,

    the following questions fall for our consideration:

    i. Whether the CERC, while exercising its functions
    under Section 79(1) of the Act, 2003, is
    circumscribed by statutory regulations enacted

    under Section 178 of the Act, 2003?

    ii. Whether the CERC exercises regulatory or

    adjudicatory functions under Section 79 of the Act,
    2003? In other words, what is the scope of the
    CERC’s power to regulate inter-state transmission
    of electricity and determine tariff for the same

    under clauses (c) and (d) of Section 79(1)?
    iii. Whether the grant of compensation by the CERC
    for the delay vide the orders dated 21.01.2020
    and 27.01.2020 respectively, is a regulatory or
    adjudicatory function and to what extent are the
    principles of natural justice applicable to the
    exercise of such functions?

    16

    (2021) 6 SCC 771
    17
    2023 SCC OnLine SC 435
    18
    Civil Appeal No.6847 of 2025, decided on 15.05.2025

    ::: Downloaded on – 30/03/2026 20:29:38 :::CIS
    25
    ( 2026:HHC:8409
    iv. Whether the High Court was justified in admitting
    the writ petition filed by the respondent no. 1
    herein challenging the order dated 21.01.2020 of
    the CERC when there existed an alternative
    remedy under Section 111 of the Act, 2003?”

    .

    Apex Court held that determination of tariff is an

    adjudicatory function of Electricity Regulatory Commissions.

    Even though determination of tariff like price fixation is a

    legislative act, yet such determination is appealable under the

    Electricity Act indicative of the fact that it is an adjudicatory

    of
    function. The orders passed under regulatory powers are

    appealable. Relevant portions are as under:-

    rt
    “50. This Court in PTC (supra) has held that the
    determination of tariff under Section 79(1) is an

    adjudicatory function of the CERC for the following
    reasons:

    (i) First, the actual determination/fixation of tariff is
    done by the appropriate commission between the parties

    before it under Section 62 of the Act, 2003. Although
    Section 61 is the enabling provision for framing of
    regulations while keeping in mind the generic
    propositions provided thereunder, yet the determination

    of tariff in respect of a specific generation unit, asset,
    transmission line, etc, is done by virtue of the power
    emanating from Section 62. Therefore, the determination

    of tariff is specific to an individual case and is not of
    general application under the Act, 2003. This is in
    consonance with the test laid down in Sitaram Sugar Co.

    Ltd. v. Union of India, reported in (1990) 3 SCC 223
    wherein it was held that one of the factors to determine
    if an order was issued in exercise of an adjudicatory
    function, is to ascertain whether it was specific to an
    individual or of general application.

    (ii) Secondly, even though determination of tariff like
    price fixation is a legislative act, yet such determination
    has been made appealable to the APTEL under Section

    111. The terms of the Act, 2003, therefore, clearly
    indicate that determination of tariff is an adjudicatory

    ::: Downloaded on – 30/03/2026 20:29:38 :::CIS
    26
    ( 2026:HHC:8409
    function. The relevant observations of this Court in PTC
    (supra) are reproduced below:

    “26. The term “tariff” is not defined in the 2003 Act.
    The term “tariff” includes within its ambit not only
    the fixation of rates but also the rules and
    regulations relating to it. If one reads Section 61
    with Section 62 of the 2003 Act, it becomes clear

    .

    that the appropriate Commission shall determine

    the actual tariff in accordance with the provisions of
    the Act, including the terms and conditions which
    may be specified by the appropriate Commission
    under Section 61 of the said Act. Under the 2003

    Act, if one reads Section 62 with Section 64, it
    becomes clear that although tariff fixation like price
    fixation is legislative in character, the same under

    of
    the Act is made appealable vide Section 111. These
    provisions, namely, Sections 61, 62 and 64 indicate
    the dual nature of functions performed by the
    Regulatory Commissions viz. decision-making and
    rtspecifying terms and conditions for tariff
    determination.

    49. On the above analysis of various sections of the 2003
    Act, we find that the decision-making and

    regulation-making functions are both assigned to
    CERC. Law comes into existence not only through
    legislation but also by regulation and litigation.
    Laws from all three sources are binding. According

    to Professor Wade, “between legislative and
    administrative functions we have regulatory
    functions”. A statutory instrument, such as a rule or
    regulation, emanates from the exercise of delegated

    legislative power which is a part of administrative
    process resembling enactment of law by the
    legislature whereas a quasi-judicial order comes

    from adjudication which is also a part of
    administrative process resembling a judicial
    decision by a court of law. (See Shri Sitaram

    Sugar Co. Ltd. v. Union of India [(1990) 3 SCC
    223].)

    50. Applying the above test, price fixation exercise is
    really legislative in character, unless by the terms
    of a particular statute it is made quasi-judicial as in
    the case of tariff fixation under Section 62 made
    appealable under Section 111 of the 2003 Act,
    though Section 61 is an enabling provision for the
    framing of regulations by CERC. If one takes “tariff”

    as a subject-matter, one finds that under Part VII of
    the 2003 Act actual determination/fixation of tariff

    ::: Downloaded on – 30/03/2026 20:29:38 :::CIS
    27
    ( 2026:HHC:8409
    is done by the appropriate Commission under
    Section 62 whereas Section 61 is the enabling
    provision for framing of regulations containing
    generic propositions in accordance with which the
    appropriate Commission has to fix the tariff. This
    basic scheme equally applies to the subject-matter
    “trading margin” in a different statutory context as

    .

    will be demonstrated by discussion hereinbelow.”

    (Emphasis supplied)

    57. The respondent no. 1 has averred that the CERC
    cannot conflate its powers of regulation with its

    adjudicatory functions and a regulation cannot be brought
    into force by way of a judicial order. In the specific case of
    Nuclear Power Corporation (supra), we are inclined to

    of
    agree with the submission of the respondent no. 1 to the
    extent that a regulation cannot be done through the
    process of adjudication. However, could it be said that
    there is a blanket ban on the CERC to exercise its
    regulatory functions by way of orders under Section 79(1)?

    rt
    In light of this Court’s dictum in AERA (supra), our answer
    to this question must be an emphatic ‘No’.

    58. We are of the view that even though the orders

    under Section 79 may not always be limpid as regards the
    matters where CERC is exercising its regulatory functions
    yet this cannot be the reason to conclude that the CERC
    passes all orders in its capacity as an adjudicator. The

    nomenclature “judicial order(s)” as used in Nuclear Power
    Corporation
    (supra) does not change the nature of a
    specific order that the CERC gives in its capacity as a
    regulator and the courts must understand the true import

    of an order to determine the nature thereof.

    59. The CERC granted liberty to the appellant herein to
    claim compensation from the respondent no. 1 to deal with

    a situation caused due to an unprecedented event not
    covered by any guidelines, regulations or contractual
    provisions between the parties. The dictum of this Court in

    paragraph 20 of Energy Watchdog (supra), indicates that
    in such a situation where there is an absence of
    regulations and guidelines, the Act, 2003 mandates the
    CERC to strike a judicious balance between the parties
    keeping in mind commercial principles and consumers’
    interest, in exercise of its general regulatory powers under
    Section 79(1).

    60. The aforesaid leaves no manner of doubt in our
    mind that though the CERC’s orders dated 21.01.2020
    and 27.01.2020 respectively were for determination of
    tariff, yet the order granting liberty to the aggrieved

    ::: Downloaded on – 30/03/2026 20:29:38 :::CIS
    28
    ( 2026:HHC:8409
    appellant to claim compensation from the defaulting party
    is a consequence of a regulatory lacuna in the 2014 Tariff
    Regulations and therefore, is an instance of regulation of
    tariff between the parties.

    61. Since the CERC was not adjudicating the issue of
    delay between the parties but was only regulating the
    consequences of the delay to the commissioning of the

    .

    transmission elements, we are of the view that there was

    no requirement for a specific prayer in this regard. As a
    natural corollary, there was also no occasion for the
    respondent no. 1 to be afforded an opportunity to be heard
    at that stage. In our considered view, any dispute

    pertaining to the levy of transmission charges incurred
    before the concerned transmission assets were put to use,
    would arise only upon the appellant raising bills to the

    of
    respondent no. 1 in this regard. In such a scenario, it
    cannot be said that there was a contravention of the
    principles of natural justice by the CERC.

    62. As regards the contention of the respondent no. 1
    that the validity of a regulation cannot be looked into by
    rt
    the statutory authorities under the Act, 2003, we are of the
    view that the said submission was made without
    considering the general regulatory power under Section

    79(1). While we are in agreement with the submission of
    the respondent no. 1 that the vires of a regulation under
    Section 178 cannot be challenged before an authority that
    is the creation of the parent statute, the same cannot be

    said so for a specific regulation effected under Section
    79(1)
    .

    63. It is apposite to mention that the sources of power
    for enactment of a regulation under Section 178 and

    regulatory order under Section 79(1) are different. The
    former emanates from the power of delegated legislation
    whereas the latter is an ad hoc power which is limited to

    the specific parties and situation in context of which the
    order is given. Since the regulatory powers under Section
    79(1)
    are of an ad hoc nature and are not of general

    application, the orders thereunder are made appealable
    under Section 111.

    64. In view of the aforesaid exposition of law, we find
    that this Court’s observations in Whirlpool (supra) are of
    no avail to the respondent no. 1 as the present matter falls
    in none of the cases enumerated therein. Therefore, there
    was no occasion for the High Court to admit the writ
    petition of the respondent no. 1.”

    ::: Downloaded on – 30/03/2026 20:29:38 :::CIS
    29

    ( 2026:HHC:8409
    4(v) It would also be appropriate to refer to State of

    Himachal Pradesh & Anr. Vs. JSW Hydro Energy Limited

    & Ors.7 wherein the Hon’ble Apex Court considering the

    expertise and specialization of CERC as a statutory regulator

    .

    and the wide ranging jurisdiction it exercises under the

    Electricity Act, held the writ petition to be not maintainable

    before the High Court. Relevant observations are as under: –

    (a) The Electricity Act, 2003 is a complete and

    of
    comprehensive code for regulating the generation,

    transmission, distribution, trading and use of electricity. One
    rt
    of the core features of the Act is that it unbundles the

    functions of electricity generation, transmission, and

    distribution that were erstwhile performed by State

    Electricity Boards19 into separate utilities, and provides for

    their regulation through independent Regulatory

    Commissions20. (para 7 of the judgment)

    (b) The need for an independent and transparent

    regulatory mechanism was felt due to the regulatory failures

    under the erstwhile legal regime21, wherein SEBs constituted

    by the State Governments were entrusted with regulation 22.

    19

    Hereinafter “SEBs
    20
    PTC (supra), para 17.

    21

    Electricity Act, 1910 (hereinafter “the 1910 Act”); the Electricity (Supply) Act, 1948
    (hereinafter “the 1948 Act”).

    22

    K.C. Ninan v. Kerala State Electricity Board, (2023) 14 SCC 431, para 6.

    ::: Downloaded on – 30/03/2026 20:29:38 :::CIS
    30

    ( 2026:HHC:8409
    It was experienced that various problems plagued the power

    sector, including lack of rational retail tariffs, high level of

    cross-subsidies, poor planning and operation, inadequate

    capacity, neglect of consumer interest, and limited

    .

    involvement of the private sector’s skills and resources23. It

    is in this context that the Electricity Regulatory Commissions

    Act, 199824 was enacted to reform the governance of the

    sector by establishing an independent and transparent

    of
    regulatory mechanism.25 (para 8 of the judgment)

    (c) Finally, the Act provides for the constitution of
    rt
    permanent expert bodies, i.e., Central and State Electricity

    Regulatory Commissions, to regulate the production,

    transfer and use of electricity, as well as for the development

    of the sector through private sector participation and

    competitiveness to subserve consumer interests.

    Considering the specialised nature of functions performed by

    these bodies, the Act also provides for an appellate forum to

    challenge the Central and State Commissions’ decisions, i.e.,

    the APTEL, which can appreciate the technicalities and

    nuances of the sector. (para 9.6 of the judgment)

    23
    Statement of Objects and Reasons of the Electricity Regulatory Commissions Act, 1998
    24
    Hereinafter “the 1998 Act”.

    25

    W.B. Electricity Regulatory Commission v. CESC Ltd., (2002) 8 SCC 715, para 52; PTC
    (supra), para 17; Sesa Sterlite Ltd. v. Orissa Electricity Regulatory Commission, (2014) 8 SCC
    444, para 22.

    ::: Downloaded on – 30/03/2026 20:29:38 :::CIS
    31

    ( 2026:HHC:8409

    (d) While the Electricity Act has done away with the

    licensing requirement for generating companies, it continues

    to regulate electricity generation as the tariff at which the

    generating company supplies electricity to a distribution

    .

    licensee is determined by the Central or State Commission,

    as is appropriate, as per Section 62(1)(a) read with Section

    79 and Section 86 of the Act26. We will further deal with the

    tariff determination function of the CERC at a later stage.”

    of
    (para 13 of the judgment)

    (e) ……….CERC as an Expert and Specialised
    rt
    Regulator, and Extent of Judicial Interference: In order to

    appreciate the issue on maintainability of the writ petition, it

    is necessary to take note that postmodern legislation

    institutionalises governance through regulation. Under the

    Electricity Act, we see such a statutory incorporation of the

    regulators through the CERC and the State Commissions

    that are expert and specialised bodies to perform wide-

    ranging regulatory functions27. (para-26 of the judgment).

    26

    Section 62(1)(a) of the Electricity Act reads: “Section 62. (Determination of tariff): — (1)
    The Appropriate Commission shall determine the tariff in accordance with the provisions of
    this Act for – (a) supply of electricity by a generating company to a distribution licensee:

    Provided that the Appropriate Commission may, in case of shortage of supply of electricity, fix
    the minimum and maximum ceiling of tariff for sale or purchase of electricity in pursuance of
    an agreement, entered into between a generating company and a licensee or between licensees,
    for a period not exceeding one year to ensure reasonable prices of electricity;…”

    27

    See PTC (supra), para 17; Sai Renewable (supra), paras 36 and 38; Reliance Infrastructure
    Ltd. v. State of Maharashtra
    , (2019) 3 SCC 352, para 38.

    ::: Downloaded on – 30/03/2026 20:29:38 :::CIS
    32

    ( 2026:HHC:8409

    (f) ……..The jurisprudence on regulation is that

    independent regulators, armed with statutory powers and

    duties, were established to reduce the government’s control

    and interference with the market while safeguarding

    .

    consumer interests, preventing abuse of monopoly, and

    enabling private participation in the sector. Therefore, the

    regulator has socio-economic obligations of ensuring

    accessibility of goods and services, as well as the duties

    of
    towards the development of the industry by promoting

    efficiency and competition 28. The nature of functions and the
    rt
    jurisdiction of these regulatory bodies are wide and extensive

    as they perform a mix of legislative, executive and

    administrative, and judicial functions29. Concomitantly, they

    are sufficiently empowered under the statute, and legislative,

    executive and adjudicatory powers are telescoped into one

    institution. Regulators have the power to lay down rules and

    regulations; issue licenses; fix prices and scope and areas of

    operation; investigate and prosecute offences, and impose

    penalties; adjudicate disputes and interpret the law;

    implement and enforce the statute, the rules and regulations

    made thereunder, and their decisions; and exercise

    28
    H.W.R. Wade and C.F. Forsyth, Administrative Law (11th edn, Oxford University Press
    2014), 116-117.

    29

    ibid, 124.

    ::: Downloaded on – 30/03/2026 20:29:38 :::CIS
    33

    ( 2026:HHC:8409
    incidental and ancillary powers to deal with all aspects

    relating to the sector30. (para-27 of the judgment)

    (g) …………Specifically, in the context of the CERC

    under the Electricity Act, Section 79 sets out its functions,

    .

    including tariff determination. The relevant portion is

    extracted hereinbelow:

    Section 79. (Functions of Central Commission): — (1) The
    Central Commission shall discharge the following functions,

    of
    namely:- *** (b) to regulate the tariff of generating companies
    other than those owned or controlled by the Central
    Government specified in clause (a), if such generating
    companies enter into or otherwise have a composite scheme
    rt
    for generation and sale of electricity in more than one
    State…” (para-28 of the judgment).

    (h) ……..”Tariff” has not been defined under the

    Electricity Act, but it has been interpreted by this Court on

    several occasions. This Court in PTC (supra) held that “tariff”

    does not only mean fixation of rates but also the rules and

    regulations relating to it……. (para-29 of the judgment).

    (i) ……..This Court has time and again emphasised

    that since tariff determination, including the power to make

    regulations for this purpose, has been entrusted to a

    specialised and expert regulator constituted under the

    statute itself, it would not be proper for constitutional courts

    30
    ibid; Cellular Operators Assn. of India v. Union of India, (2003) 3 SCC 186, para 33; U.P.
    Power Corpn. Ltd. v. NTPC Ltd.
    , (2009) 6 SCC 235, paras 4, 22, 48.

    ::: Downloaded on – 30/03/2026 20:29:38 :::CIS
    34

    ( 2026:HHC:8409
    to interfere and assume these functions, or to examine tariff

    fixation on its merits and substitute its own determination

    for the one made by the expert body after duly considering

    all material circumstances31. We are of the opinion that this

    .

    is necessary not only to ensure that these specialised

    functions are performed by expert regulators but to also

    facilitate a systematic and consistent development of sectoral

    laws. (para-32 of the judgment).

    of

    (j) In this light, when a constitutional court is

    interpreting statutes, rules, or regulations that fall within the
    rt
    regulator’s domain, it must bear in mind the need to enable

    the regulator to exercise comprehensive jurisdiction. Courts

    must not impair the functioning of the regulator by taking

    away certain aspects of the sector outside the regulator’s

    scope, thereby fragmenting regulation and creating plurality

    of jurisdictions. It is in the interest of good governance

    through regulation to ensure that there is no proliferation of

    remedies and there are no parallel, multiple remedial forums.

    Further, this also ensures that the sectoral law is developed

    in a coordinated and systematic fashion by the regulator that

    31
    Sai Renewable (supra), paras 38, 40, 41; Reliance Infrastructure Ltd (supra), para 38;
    Transmission Corpn. of A.P. Ltd. v. Rain Calcining Ltd., (2021) 13 SCC 674, para 66;
    Maharashtra State Electricity Distribution Co. Ltd. v. Adani Power Maharashtra Ltd., (2023) 7
    SCC 401, paras 118-121.

    ::: Downloaded on – 30/03/2026 20:29:38 :::CIS
    35

    ( 2026:HHC:8409
    is equipped to deal with not only legal issues but also has

    specialised knowledge in other areas. (para-33 of the judgment).

    (k) The above principles are also reflected in a recent

    decision of this Court in Jaipur Vidyut Vitran Nigam Ltd.6.

    .

    Here, the High Court exercised writ jurisdiction and directed

    distribution companies to procure power from bidders, who

    are generating companies, at the prices quoted in their bids

    till the requisite quantum of power was procured. Allowing

    of
    the appeal of the distribution companies, this Court held that

    the High Court was not justified in entertaining the writ
    rt
    petition as the Electricity Act is an exhaustive code and all

    issues dealing with electricity must be considered by the

    expert bodies, i.e., the Regulatory Commissions constituted

    under the Act. The relevant portion is extracted hereinbelow:

    “128. We find that the High Court was not justified in
    entertaining the petition. The Constitution Bench of this

    Court in PTC has held that the Electricity Act is an
    exhaustive code on all matters concerning electricity. Under

    the Electricity Act, all issues dealing with electricity have to
    be considered by the authorities constituted under the said

    Act. As held by the Constitution Bench of this Court, the
    State Electricity Commission and the learned APTEL have
    ample powers to adjudicate in the matters with regard to
    electricity. Not only that, these Tribunals are tribunals
    consisting of experts having vast experience in the field of
    electricity. As such, we find that the High Court erred in
    directly entertaining the writ petition when Respondent 1
    i.e. the writ petitioner before the High Court had an

    ::: Downloaded on – 30/03/2026 20:29:38 :::CIS
    36
    ( 2026:HHC:8409
    adequate alternate remedy of approaching the State
    Electricity Commission.

    129. This Court in Reliance Infrastructure Ltd. v. State of
    Maharashtra
    has held that while exercising its power of
    judicial review, the Court can step in where a case of

    .

    manifest unreasonableness or arbitrariness is made out.

    130. In the present case, there is not even an allegation with
    regard to that effect. In such circumstances, recourse to a
    petition under Article 226 of the Constitution of India in the

    availability of efficacious alternate remedy under a statute,
    which is a complete code in itself, in our view, was not
    justified.” (emphasis supplied)

    of
    (Para 34 of the judgment)

    The Hon’ble Apex Court further held that under
    rt
    the Electricity Act, the statutory regulator has been

    entrusted with discharging the function of tariff

    determination, including making regulations for the purpose

    and interpreting the same. Constitutional courts must

    enable the regulator to comprehensively regulate all aspects

    of the sector such that remedies are not fragmented and

    certain issues are not left outside the regulator’s domain. The

    regulator has the expertise, specialisation, and institutional

    memory to conduct such an interpretative exercise to further

    the objective of the regulatory regime and systematically lay

    down legal principles. In this light, the High Court should not

    have entered into the domain of interpreting these

    Regulations which deal with tariff determination, as the

    same falls within the exclusive domain of the CERC. The

    ::: Downloaded on – 30/03/2026 20:29:38 :::CIS
    37
    ( 2026:HHC:8409
    Electricity Act itself provides the appellate mechanisms by

    establishing a specialised and permanent tribunal, namely

    the APTEL, and an appeal before this Court, against the

    CERC’s orders. In view of the existence of a statutory

    .

    regulatory forum, the High Court should not have

    entertained the writ petition by interpreting the CERC

    Regulations.

    5. For the forgoing, in view of statutory remedy

    of
    available to the petitioners, these writ petitions are disposed

    of reserving liberty to the petitioners to seek appropriate
    rt
    remedy in accordance with law. The period spent in pursuing

    these writ petitions shall not be computed for purposes of

    limitation.

    All the pending miscellaneous application(s), if

    any, to also stand disposed of.

    
    
    
    
                                                        Jyotsna Rewal Dua
    
    
    
    
    
        March 23, 2026                                        Judge
               rohit
    
    
    
    
    
                                                    ::: Downloaded on - 30/03/2026 20:29:38 :::CIS
     



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here