M/S National Highways Authority Of … vs M/S Bel-Acc(Jv) on 24 March, 2026

    0
    31
    ADVERTISEMENT

    Delhi High Court

    M/S National Highways Authority Of … vs M/S Bel-Acc(Jv) on 24 March, 2026

    Author: Subramonium Prasad

    Bench: Subramonium Prasad

                              *      IN THE HIGH COURT OF DELHI AT NEW DELHI
                                                                       Date of decision: 24th MARCH, 2026
                                     IN THE MATTER OF:
                              +      O.M.P. (COMM) 341/2020
                                     M/S NATIONAL HIGHWAYS AUTHORITY OF INDIA
                                                                                .....Petitioner
                                                  Through: Mr. A. P. Singh and Mr. Varnit
                                                           Vashistha, Advocates
    
                                                         versus
    
                                     M/S BEL-ACC(JV)                                       .....Respondent
                                                   Through:           Dr. Swaroop George, Mr. Sunny
                                                                      Thomas, Mr. Abhinandan Jain, Mr.
                                                                      Shivam Prajapati, Mr. Abhigyan
                                                                      Dwivedi, Mr. Kartikey, Advocates
    
    
                                     CORAM:
                                     HON'BLE MR. JUSTICE SUBRAMONIUM PRASAD
                                                         JUDGMENT
    

    1. The present Petition under Section 34 of the Arbitration &
    Conciliation Act, 1996, has been filed by the Petitioner herein against the
    Arbitral Award dated 27.05.2010 passed by a three-Member Arbitral
    Tribunal.

    2. Brief facts of the case as discernible from the material on record are
    stated as under:-

    SPONSORED

    i. The Petitioner invited bids from pre-qualified contractors for the
    project of strengthening and four-laning of existing two lane
    sections between Km. 307.500-Km. 231.00 of Etawah Bypass on
    NH-2 in Uttar Pradesh (hereinafter referred to as the ‘Project’).
    ii. On the basis of the evaluation of the bids, the Respondent was
    Signature Not Verified
    Signed By:PRATEEK O.M.P. (COMM) 341/2020 Page 1 of 29
    Signing Date:24.03.2026
    15:59:10
    awarded the contract dated 01.02.2001 bearing No.
    11025/2/99/TECH/GM(WB)/ETAWAH (01.02.2001) for contract
    price of Rs.69,44,17,782/- (hereinafter referred to as the
    „Contract‟).

    iii. The Contract was an item rate contract wherein the Respondent
    quoted its rates for various items of activities as per the details
    given in the bill of quantities conforming to the relevant technical
    specifications and other provisions of the contract.
    iv. The Contract involved two separate phases. In Phase-I, the works
    to be undertaken by the Respondent was to provide two additional
    lanes by widening in the left hand side of the existing 7.3 Km.
    long two lanes, which was later changed to placing one lane on
    either side of the existing two lanes within the same land. The
    Phase-II involved entirely new construction of four lanes of 6.7
    Km., scope of which remain unchanged. The percentage of the
    works involved in these two phases of the Project is stated to be in
    the proportion of 28% for Phase-I and 72% in Phase-II.
    v. It is stated that the Respondent accepted the variation in Phase-I,
    thereby committing itself to execute the varied works within the
    provisions of the Contract without any reservations. However, the
    Respondent inter alia raised disputes with respect to the rates
    approved by the Petitioner for the varied items of work which
    were involved mainly in Phase-I of the Project.
    vi. These disputes and differences between the parties were referred
    to the Engineer in the first instance as per Clause 67.1 of the
    General Conditions of Contract (hereinafter referred to as the
    „GCC‟).

    Signature Not Verified
    Signed By:PRATEEK O.M.P. (COMM) 341/2020 Page 2 of 29
    Signing Date:24.03.2026
    15:59:10

    vii. The Engineer rejected the claims of the Respondent and
    communicated his decision in writing to both the parties.
    Aggrieved by the decision of the Engineer, the Respondent gave
    notice to the Petitioner of its intention to commence arbitration for
    resolution of disputes by way of a letter dated 24.06.2004.
    viii. A three-Member Arbitral Tribunal was constituted and the
    Respondent came to file its Statement of Claim on 25.10.2004
    raising the following Claims:-

    “Claim No.1: Payment at revised rate for items of work under
    Clause 51 & 52 GCC in respect of the work executed upto

    3.10.2003, the original date of completion -Rs. 1,63,85,553.60

    Claim No.2: Compensation by way of revision of rate for the
    work executed during the extended period i.e. for the period
    between 3.10.2003 to 31.8.2004 with escalation-Rs. 2,85,68,783

    Claim No.3:Extension of time sought upto 31.10.2006 for the
    alleged breach by the Employer.

    Claim No.4: Compensation for loss of overheads profit and
    reduce productivity from the machinery and equipment
    deployed and loss of bonus upto 3.10.2003-Rs. 17,49,10,739.70

    Claim No.5: Cost of deployment of additional resources for
    executing additional work from 1.1.2003 till date-Rs.
    1,80,000,00

    Claim No.6: Refund of royalty for ordinary earth deducted upto
    31.8.2004-Rs. 25,62,622/-

    Claim No.7: Interest: To past, pendente lite and future interest
    for delayed payment of amount certified by the Engineer upto
    28.6.2004, the date of commencement of arbitration
    proceedings.”

    ix. In response the above claims of the Respondent, the Petitioner
    Signature Not Verified
    Signed By:PRATEEK O.M.P. (COMM) 341/2020 Page 3 of 29
    Signing Date:24.03.2026
    15:59:10
    came to file its Statement of Defence on 13.12.2004.
    x. On the basis of the pleadings and the evidence produced by the
    parties, the learned Arbitral Tribunal passed the impugned Arbitral
    Award and by way of a majority, awarded an amount of
    Rs.1,93,19,530/- towards Claims No.1, 4 and 5 in favour of the
    Respondent, along with pendente lite and future interest @ 10%
    from 24.06.2004 till the date of the impugned Award and from the
    date of the Award till the date of payment respectively. The
    Claims No.2, 3 and 6 were rejected by the learned Arbitral
    Tribunal.

    xi. It is this Arbitral Award rendered by the majority of the Arbitral
    Tribunal, that is under challenge in the present Petition.

    3. Learned Counsel for the Petitioner has submitted as under:-

    i. It is the case of the Petitioner that the Respondent was handed
    over the Project Site as per the work programme which was
    submitted by the Respondent itself in consonance with Clause
    42.1 of the GCC as the Contract nowhere provided that the entire
    land is to be handed over on the date of commencement of the
    work.

    ii. It is submitted that the handing over of the Project Site was
    admittedly done in phases, however, enough land was handed over
    to the Respondent to carry out the works without any delay or
    hindrances.

    iii. It is stated that all the construction drawings were timely issued to
    the Respondent on 26.05.2001, that is much before the acceptance
    of the work programme by the Petitioner.
    iv. It is submitted that the Respondent was itself responsible for the
    Signature Not Verified
    Signed By:PRATEEK O.M.P. (COMM) 341/2020 Page 4 of 29
    Signing Date:24.03.2026
    15:59:10
    slow progress of work due to its poor resources and work
    management.

    v. It is stated that the changes which were made by the Petitioner in
    the provisions of the Contract were mainly for Phase-I of the
    Project which only constituted for 28% of the total contract price,
    as opposed to Phase-II of the project which was for 72% of the
    total contract price.

    vi. Since the Respondent itself agreed to execute the variations
    brought in by the Petitioner in the Contract, it cannot be said that
    any novation of the Contract took place. Moreover, since it is an
    admitted case that the Respondent itself wanted the new rates to
    be fixed as per Clauses 51 & 52 of the GCC, there can be no
    question of there being a new agreement or novation of contract.
    vii. Even after agreeing to the variations, the Respondent itself
    disputed the rates and on 08.04.2003, sent a proposal of rates for
    varied items to the Petitioner, for which approval was
    communicated by the Petitioner‟s engineer without the work of
    service road, however, the Respondent did not agree to the same.
    viii. It was subsequently observed that the Respondent itself could not
    adhere to its own work programme and as such the Petitioner was
    constrained to issue show cause notices on 02.01.2004,
    12.02.2004 and 06.03.2004. Despite these notices, there was no
    improvement in the progress of work by the Respondent.
    ix. In respect of Claim No.1 which has been awarded by the learned
    Arbitral Tribunal by majority in favour of the Respondent, it is
    submitted that no details regarding how the rates have been
    worked out and what components have been taken into
    Signature Not Verified
    Signed By:PRATEEK O.M.P. (COMM) 341/2020 Page 5 of 29
    Signing Date:24.03.2026
    15:59:10
    consideration while arriving at the rates of variation have been
    discussed in the impugned Award. Rather, a reading of the
    impugned Award clearly shows that the rates awarded are based
    simply on the experience of the learned Members of the learned
    Arbitral Tribunal.

    x. It is submitted that despite rejecting variation on many of the
    items claimed by the Respondent, the learned Arbitral Tribunal
    still awarded nearly 80% of the amount demanded by the
    Respondent. For instance, for some items like BOQ Item 7.3
    “Earthwork in excavation for PCC” the rate worked out by the
    learned Arbitral Tribunal (i.e., Rs.55/- per cubic metre) was more
    than what was claimed by the Respondent (i.e. Rs.49.79/- per
    cubic metre).

    xi. As regards Claim No.4 which was awarded in favour of the
    Respondent, it is submitted that though the Respondent had
    quoted 28% below the estimated cost put in response to the tender,
    it still claimed loss of profit and compensation on account of
    overheads and machinery.

    xii. It is submitted that findings in the impugned Award are
    completely contradictory. On a reading of the impugned Award it
    can be noted that while the learned Arbitral Tribunal gives a
    finding that the Respondent was also responsible for delay in
    completion of works, overhead charges are still allowed in favour
    of the Respondent. This is in clear ignorance of the fact that
    accrual of overhead charges emanates from the quality of work
    executed and is not payable when the delay is attributable to the
    contractor itself.

    Signature Not Verified
    Signed By:PRATEEK O.M.P. (COMM) 341/2020 Page 6 of 29
    Signing Date:24.03.2026
    15:59:10

    xiii. In awarding compensation for overhead charges, the learned
    Arbitral Tribunal ignores the principle that merely spending time
    without any actual execution of works involved in the project will
    not entitle a contractor to the overhead charges.
    xiv. It is submitted that the amounts claimed towards compensation
    under Claim No.4 are hypothetical, imaginary and without any
    basis as the Respondent failed to achieve the target set by
    themselves in the various work programme, which led to the
    termination of the contract.

    xv. Insofar as awarding of amounts under Claim No.5 is concerned, it
    is submitted that the findings of the learned Arbitral Tribunal are
    based on no evidence whatsoever, since no log books were
    supplied by the Respondent for machinery and equipment, and as
    such it appears that the learned Arbitral Tribunal has awarded the
    amount allegedly on the basis of equity.

    4. Per contra, learned Counsel for the Respondent submits that the
    entire case brought by the Petitioner before this Court requires a re-
    appreciation of the merits of the dispute before the Arbitral Tribunal as well
    as the evidence produced by the parties. He further states that the Petitioner
    has failed to carve out exactly which parameter under Section 34 of the
    Arbitration & Conciliation Act is attracted to the facts of the present case,
    which would warrant interference by this Court. He submits that since the
    impugned Arbitral Award is comprehensive and well-reasoned, the instant
    Petition warrants dismissal by this Court.

    5. The scope of adjudication before this Court has been delineated only
    to the award of amounts by the learned Arbitral Tribunal under Claims No.1,
    4 and 5 in favour of the Respondent. Therefore, this Court shall restrict its
    Signature Not Verified
    Signed By:PRATEEK O.M.P. (COMM) 341/2020 Page 7 of 29
    Signing Date:24.03.2026
    15:59:10
    analysis only within these parameters.

    6. This Court reminds itself that the Impugned Award herein was passed
    in the year 2010, and in the same year, the present Petition was filed.
    Keeping the same in mind, it is apposite to recall the law under Section 34
    of the Arbitration & Conciliation Act as it existed prior to the 2015
    Amendment. This Court refers to the Judgment passed by the Apex Court in
    Associate Builders v. DDA, (2015) 3 SCC 49 wherein the Apex Court has
    observed as under:

    “14. Section 34 of the Arbitration and Conciliation
    Act reads as follows:

    “34.Application for setting aside arbitral award.–
    (1) Recourse to a court against an arbitral award may
    be made only by an application for setting aside such
    award in accordance with sub-section (2) and sub-
    section (3).

    (2) An arbitral award may be set aside by the court
    only if–

    (a) the party making the application furnishes proof
    that–

    (i) a party was under some incapacity; or

    (ii) the arbitration agreement is not valid under the
    law to which the parties have subjected it or, failing
    any indication thereon, under the law for the time
    being in force; or

    (iii) the party making the application was not given
    proper notice of the appointment of an arbitrator or of
    the arbitral proceedings or was otherwise unable to
    present his case; or

    (iv) the arbitral award deals with a dispute not
    contemplated by or not falling within the terms of the
    submission to arbitration, or it contains decisions on
    matters beyond the scope of the submission to
    arbitration:

    Signature Not Verified
    Signed By:PRATEEK O.M.P. (COMM) 341/2020 Page 8 of 29
    Signing Date:24.03.2026
    15:59:10

    Provided that, if the decisions on matters submitted
    to arbitration can be separated from those not so
    submitted, only that part of the arbitral award which
    contains decisions on matters not submitted to
    arbitration may be set aside; or

    (v) the composition of the Arbitral Tribunal or the
    arbitral procedure was not in accordance with the
    agreement of the parties, unless such agreement was in
    conflict with a provision of this Part from which the
    parties cannot derogate, or, failing such agreement,
    was not in accordance with this Part; or

    (b) the court finds that–

    (i) the subject-matter of the dispute is not capable of
    settlement by arbitration under the law for the time
    being in force, or

    (ii) the arbitral award is in conflict with the public
    policy of India.

    Explanation.–Without prejudice to the generality
    of sub-clause (ii), it is hereby declared, for the
    avoidance of any doubt, that an award is in conflict
    with the public policy of India if the making of the
    award was induced or affected by fraud or corruption
    or was in violation of Section 75 or Section 81.
    (3) An application for setting aside may not be
    made after three months have elapsed from the date on
    which the party making that application had received
    the arbitral award or, if a request had been made
    under Section 33, from the date on which that request
    had been disposed of by the Arbitral Tribunal:

    Provided that if the court is satisfied that the
    applicant was prevented by sufficient cause from
    making the application within the said period of three
    months it may entertain the application within a
    further period of thirty days, but not thereafter.
    (4) On receipt of an application under sub-section
    (1), the court may, where it is appropriate and it is so
    requested by a party, adjourn the proceedings for a
    period of time determined by it in order to give the
    Arbitral Tribunal an opportunity to resume the arbitral
    Signature Not Verified
    Signed By:PRATEEK O.M.P. (COMM) 341/2020 Page 9 of 29
    Signing Date:24.03.2026
    15:59:10
    proceedings or to take such other action as in the
    opinion of Arbitral Tribunal will eliminate the grounds
    for setting aside the arbitral award.”

    xxx

    19. When it came to construing the expression “the
    public policy of India” contained in Section
    34(2)(b)(ii)
    of the Arbitration Act, 1996, this Court
    in ONGC Ltd. v. Saw Pipes Ltd. [(2003) 5 SCC 705 :

    AIR 2003 SC 2629] held : (SCC pp. 727-28 & 744-45,
    paras 31 & 74)

    “31. Therefore, in our view, the phrase „public
    policy of India‟ used in Section 34 in context is
    required to be given a wider meaning. It can be stated
    that the concept of public policy connotes some matter
    which concerns public good and the public interest.

    What is for public good or in public interest or what
    would be injurious or harmful to the public good or
    public interest has varied from time to time. However,
    the award which is, on the face of it, patently in
    violation of statutory provisions cannot be said to be in
    public interest. Such award/judgment/decision is likely
    to adversely affect the administration of justice. Hence,
    in our view in addition to narrower meaning given to
    the term „public policy‟ in Renusagar case [Renusagar
    Power Co. Ltd. v. General Electric Co.
    , 1994 Supp (1)
    SCC 644] it is required to be held that the award could
    be set aside if it is patently illegal. The result would
    be–award could be set aside if it is contrary to:

    (a) fundamental policy of Indian law; or

    (b) the interest of India; or

    (c) justice or morality, or

    (d) in addition, if it is patently illegal.

    Illegality must go to the root of the matter and if the
    illegality is of trivial nature it cannot be held that
    award is against the public policy. Award could also

    Signature Not Verified
    Signed By:PRATEEK O.M.P. (COMM) 341/2020 Page 10 of 29
    Signing Date:24.03.2026
    15:59:10
    be set aside if it is so unfair and unreasonable that it
    shocks the conscience of the court. Such award is
    opposed to public policy and is required to be
    adjudged void.

    ***

    74. In the result, it is held that:

    (A)(1) The court can set aside the arbitral award
    under Section 34(2) of the Act if the party making the
    application furnishes proof that:

    (i) a party was under some incapacity, or

    (ii) the arbitration agreement is not valid under the
    law to which the parties have subjected it or, failing
    any indication thereon, under the law for the time
    being in force; or

    (iii) the party making the application was not given
    proper notice of the appointment of an arbitrator or of
    the arbitral proceedings or was otherwise unable to
    present his case; or

    (iv) the arbitral award deals with a dispute not
    contemplated by or not falling within the terms of the
    submission to arbitration, or it contains decisions on
    matters beyond the scope of the submission to
    arbitration.

    (2) The court may set aside the award:

    (i)(a) if the composition of the Arbitral Tribunal
    was not in accordance with the agreement of the
    parties,

    (b) failing such agreement, the composition of the
    Arbitral Tribunal was not in accordance with Part I of
    the Act
    ,

    (ii) if the arbitral procedure was not in accordance
    with:

    (a) the agreement of the parties, or

    (b) failing such agreement, the arbitral procedure was
    not in accordance with Part I of the Act.

    Signature Not Verified
    Signed By:PRATEEK O.M.P. (COMM) 341/2020 Page 11 of 29
    Signing Date:24.03.2026
    15:59:10

    However, exception for setting aside the award on the
    ground of composition of Arbitral Tribunal or illegality
    of arbitral procedure is that the agreement should not
    be in conflict with the provisions of Part I of the Act
    from which parties cannot derogate.

    (c) If the award passed by the Arbitral Tribunal is in
    contravention of the provisions of the Act or any other
    substantive law governing the parties or is against the
    terms of the contract.

    (3) The award could be set aside if it is against the
    public policy of India, that is to say, if it is contrary to:

    (a) fundamental policy of Indian law; or

    (b) the interest of India; or

    (c) justice or morality; or

    (d) if it is patently illegal.

    (4) It could be challenged:

    (a) as provided under Section 13(5); and

    (b) Section 16(6) of the Act.

    (B)(1) The impugned award requires to be set aside
    mainly on the grounds:

    (i) there is specific stipulation in the agreement that
    the time and date of delivery of the goods was of the
    essence of the contract;

    (ii) in case of failure to deliver the goods within the
    period fixed for such delivery in the schedule, ONGC
    was entitled to recover from the contractor liquidated
    damages as agreed;

    (iii) it was also explicitly understood that the
    agreed liquidated damages were genuine pre-estimate
    of damages;

    (iv) on the request of the respondent to extend the
    time-limit for supply of goods, ONGC informed
    specifically that time was extended but stipulated
    liquidated damages as agreed would be recovered;

    (v) liquidated damages for delay in supply of goods
    were to be recovered by paying authorities from the

    Signature Not Verified
    Signed By:PRATEEK O.M.P. (COMM) 341/2020 Page 12 of 29
    Signing Date:24.03.2026
    15:59:10
    bills for payment of cost of material supplied by the
    contractor;

    (vi) there is nothing on record to suggest that
    stipulation for recovering liquidated damages was by
    way of penalty or that the said sum was in any way
    unreasonable;

    (vii) in certain contracts, it is impossible to assess
    the damages or prove the same. Such situation is taken
    care of by Sections 73 and 74 of the Contract Act and
    in the present case by specific terms of the contract.”

    xxx

    21. In Hindustan Zinc Ltd. v. Friends Coal
    Carbonisation
    [(2006) 4 SCC 445] , this Court held :

    (SCC p. 451, para 14)

    “14. The High Court did not have the benefit of the
    principles laid down in Saw Pipes [(2003) 5 SCC 705 :

    AIR 2003 SC 2629] , and had proceeded on the
    assumption that award cannot be interfered with even
    if it was contrary to the terms of the contract. It went to
    the extent of holding that contract terms cannot even
    be looked into for examining the correctness of the
    award. This Court in Saw Pipes [(2003) 5 SCC 705 :
    AIR 2003 SC 2629] has made it clear that it is open to
    the court to consider whether the award is against the
    specific terms of contract and if so, interfere with it on
    the ground that it is patently illegal and opposed to the
    public policy of India.”

    22. In McDermott International Inc. v. Burn
    Standard Co. Ltd. [McDermott International
    Inc.
    v. Burn Standard Co. Ltd., (2006) 11 SCC 181] ,
    this Court held : (SCC pp. 209-10, paras 58-60)

    “58. In Renusagar Power Co. Ltd. v. General
    Electric Co. [Renusagar Power Co. Ltd.
    v. General

    Signature Not Verified
    Signed By:PRATEEK O.M.P. (COMM) 341/2020 Page 13 of 29
    Signing Date:24.03.2026
    15:59:10
    Electric Co., 1994 Supp (1) SCC 644] this Court laid
    down that the arbitral award can be set aside if it is
    contrary to (a) fundamental policy of Indian law; (b)
    the interests of India; or (c) justice or morality. A
    narrower meaning to the expression „public policy‟
    was given therein by confining judicial review of the
    arbitral award only on the aforementioned three
    grounds. An apparent shift can, however, be noticed
    from the decision of this Court in ONGC Ltd. v. Saw
    Pipes Ltd.
    [(2003) 5 SCC 705 : AIR 2003 SC 2629]
    (for short „ONGC‟).
    This Court therein referred to an
    earlier decision of this Court in Central Inland Water
    Transport Corpn. Ltd. v. Brojo Nath Ganguly
    [(1986)
    3 SCC 156 : 1986 SCC (L&S) 429 : (1986) 1 ATC 103]
    wherein the applicability of the expression „public
    policy‟ on the touchstone of Section 23 of the Contract
    Act, 1872 and Article 14 of the Constitution of India
    came to be considered. This Court therein was dealing
    with unequal bargaining power of the workmen and
    the employer and came to the conclusion that any term
    of the agreement which is patently arbitrary and/or
    otherwise arrived at because of the unequal bargaining
    power would not only be ultra vires Article 14 of the
    Constitution of India but also hit by Section 23 of the
    Contract Act, 1872. In ONGC [(2003) 5 SCC 705 :

    AIR 2003 SC 2629] this Court, apart from the three
    grounds stated in Renusagar [Renusagar Power Co.
    Ltd. v. General Electric Co.
    , 1994 Supp (1) SCC 644] ,
    added another ground thereto for exercise of the
    court’s jurisdiction in setting aside the award if it is
    patently arbitrary.

    59. Such patent illegality, however, must go to the
    root of the matter. The public policy violation,
    indisputably, should be so unfair and unreasonable as
    to shock the conscience of the court. Where the
    arbitrator, however, has gone contrary to or beyond
    the expressed law of the contract or granted relief in
    the matter not in dispute would come within the
    purview of Section 34 of the Act. However, we would
    Signature Not Verified
    Signed By:PRATEEK O.M.P. (COMM) 341/2020 Page 14 of 29
    Signing Date:24.03.2026
    15:59:10
    consider the applicability of the aforementioned
    principles while noticing the merits of the matter.

    60. What would constitute public policy is a matter
    dependent upon the nature of transaction and nature of
    statute. For the said purpose, the pleadings of the
    parties and the materials brought on record would be
    relevant to enable the court to judge what is in public
    good or public interest, and what would otherwise be
    injurious to the public good at the relevant point, as
    contradistinguished from the policy of a particular
    Government. (See State of Rajasthan v. Basant
    Nahata
    [(2005) 12 SCC 77] .)”

    23. In Centrotrade Minerals & Metals
    Inc. v. Hindustan Copper Ltd.
    [(2006) 11 SCC 245] ,
    Sinha, J., held : (SCC p. 284, paras 103-04)

    “103. Such patent illegality, however, must go to
    the root of the matter. The public policy, indisputably,
    should be unfair and unreasonable so as to shock the
    conscience of the court. Where the arbitrator, however,
    has gone contrary to or beyond the expressed law of
    the contract or granted relief in the matter not in
    dispute would come within the purview of Section 34 of
    the Act.

    104. What would be a public policy would be a
    matter which would again depend upon the nature of
    transaction and the nature of statute. For the said
    purpose, the pleadings of the parties and the materials
    brought on record would be relevant so as to enable
    the court to judge the concept of what was a public
    good or public interest or what would otherwise be
    injurious to the public good at the relevant point as
    contradistinguished by the policy of a particular
    Government. (See State of Rajasthan v. Basant
    Nahata
    [(2005) 12 SCC 77] .)”

    Signature Not Verified
    Signed By:PRATEEK O.M.P. (COMM) 341/2020 Page 15 of 29
    Signing Date:24.03.2026
    15:59:10

    24. In DDA v. R.S. Sharma and Co. [(2008) 13 SCC
    80] , the Court summarised the law thus : (SCC pp. 91-
    92, para 21)

    “21. From the above decisions, the following
    principles emerge:

    (a) An award, which is

    (i) contrary to substantive provisions of law; or

    (ii) the provisions of the Arbitration and
    Conciliation Act, 1996
    ; or

    (iii) against the terms of the respective contract; or

    (iv) patently illegal; or

    (v) prejudicial to the rights of the parties;

    is open to interference by the court under Section 34(2)
    of the Act.

    (b) The award could be set aside if it is contrary to:

    (a) fundamental policy of Indian law; or

    (b) the interest of India; or

    (c) justice or morality.

    (c) The award could also be set aside if it is so
    unfair and unreasonable that it shocks the conscience
    of the court.

    (d) It is open to the court to consider whether the
    award is against the specific terms of contract and if
    so, interfere with it on the ground that it is patently
    illegal and opposed to the public policy of India.

    With these principles and statutory provisions,
    particularly, Section 34(2) of the Act, let us consider
    whether the arbitrator as well as the Division Bench of
    the High Court were justified in granting the award in
    respect of Claims 1 to 3 and Additional Claims 1 to 3
    of the claimant or the appellant DDA has made out a
    case for setting aside the award in respect of those
    claims with reference to the terms of the agreement
    duly executed by both parties.”

    Signature Not Verified
    Signed By:PRATEEK O.M.P. (COMM) 341/2020 Page 16 of 29
    Signing Date:24.03.2026
    15:59:10

    25.J.G. Engineers (P) Ltd. v. Union of India [(2011)
    5 SCC 758 : (2011) 3 SCC (Civ) 128] held : (SCC p.
    775, para 27)

    “27. Interpreting the said provisions, this Court
    in ONGC Ltd. v. Saw Pipes Ltd. [(2003) 5 SCC 705 :

    AIR 2003 SC 2629] held that a court can set aside an
    award under Section 34(2)(b)(ii) of the Act, as being in
    conflict with the public policy of India, if it is (a)
    contrary to the fundamental policy of Indian law; or

    (b) contrary to the interests of India; or (c) contrary to
    justice or morality; or (d) patently illegal. This Court
    explained that to hold an award to be opposed to
    public policy, the patent illegality should go to the very
    root of the matter and not a trivial illegality. It is also
    observed that an award could be set aside if it is so
    unfair and unreasonable that it shocks the conscience
    of the court, as then it would be opposed to public
    policy.”

    26.Union of India v. Col. L.S.N. Murthy [(2012) 1
    SCC 718 : (2012) 1 SCC (Civ) 368] held : (SCC p.
    724, para 22)

    “22. In ONGC Ltd. v. Saw Pipes Ltd. [(2003) 5
    SCC 705 : AIR 2003 SC 2629] this Court after
    examining the grounds on which an award of the
    arbitrator can be set aside under Section 34 of the Act
    has said : (SCC p. 727, para 31)

    „31. … However, the award which is, on the face of
    it, patently in violation of statutory provisions cannot
    be said to be in public interest. Such
    award/judgment/decision is likely to adversely affect
    the administration of justice. Hence, in our view in
    addition to narrower meaning given to the term
    “public policy” in Renusagar case [Renusagar Power
    Co. Ltd. v. General Electric Co.
    , 1994 Supp (1) SCC

    Signature Not Verified
    Signed By:PRATEEK O.M.P. (COMM) 341/2020 Page 17 of 29
    Signing Date:24.03.2026
    15:59:10
    644] it is required to be held that the award could be
    set aside if it is patently illegal‟.”

    27. Coming to each of the heads contained in Saw
    Pipes [(2003) 5 SCC 705 : AIR 2003 SC 2629]
    judgment, we will first deal with the head
    “fundamental policy of Indian law”. It has already
    been seen from Renusagar [Renusagar Power Co.
    Ltd. v. General Electric Co.
    , 1994 Supp (1) SCC 644]
    judgment that violation of the Foreign Exchange Act
    and disregarding orders of superior courts in India
    would be regarded as being contrary to the
    fundamental policy of Indian law. To this it could be
    added that the binding effect of the judgment of a
    superior court being disregarded would be equally
    violative of the fundamental policy of Indian law.

    xxx

    40. We now come to the fourth head of public
    policy, namely, patent illegality. It must be
    remembered that under the Explanation to Section
    34(2)(b)
    , an award is said to be in conflict with the
    public policy of India if the making of the award was
    induced or affected by fraud or corruption. This
    ground is perhaps the earliest ground on which courts
    in England set aside awards under English law. Added
    to this ground (in 1802) is the ground that an arbitral
    award would be set aside if there were an error of law
    by the arbitrator. This is explained by Denning, L.J.
    in R. v. Northumberland Compensation Appeal
    Tribunal
    , ex p Shaw [(1952) 1 All ER 122 : (1952) 1
    KB 338 (CA)] : (All ER p. 130 D-E : KB p. 351)

    “Leaving now the statutory tribunals, I turn to the
    awards of the arbitrators. The Court of King’s Bench
    never interfered by certiorari with the award of an
    arbitrator, because it was a private tribunal and not
    subject to the prerogative writs. If the award was not
    Signature Not Verified
    Signed By:PRATEEK O.M.P. (COMM) 341/2020 Page 18 of 29
    Signing Date:24.03.2026
    15:59:10
    made a rule of court, the only course available to an
    aggrieved party was to resist an action on the award
    or to file a bill in equity. If the award was made a rule
    of court, a motion could be made to the court to set it
    aside for misconduct of the arbitrator on the ground
    that it was procured by corruption or other undue
    means (see Statutes 9 and 10 Will. III, C. 15). At one
    time an award could not be upset on the ground of
    error of law by the arbitrator because that could not be
    said to be misconduct or undue means, but ultimately it
    was held in Kent v. Elstob [(1802) 3 East 18 : 102 ER
    502] , that an award could be set aside for error of law
    on the face of it. This was regretted by Williams, J.,
    in Hodgkinson v. Fernie [(1857) 3 CB (NS) 189 : 140
    ER 712] , but is now well established.”

    41. This, in turn, led to the famous principle laid
    down in Champsey Bhara Co. v. Jivraj Balloo Spg. and
    Wvg. Co. Ltd.
    [AIR 1923 PC 66 : (1922-23) 50 IA 324
    : 1923 AC 480 : 1923 All ER Rep 235 (PC)] , where
    the Privy Council referred to Hodgkinson [(1857) 3 CB
    (NS) 189 : 140 ER 712] and then laid down : (IA pp.
    330-32)

    “The law on the subject has never been more
    clearly stated than by Williams, J.

    in Hodgkinson v. Fernie [(1857) 3 CB (NS) 189 : 140
    ER 712] : [CB(NS) p. 202 : ER p. 717]

    „The law has for many years been settled, and
    remains so at this day, that, where a cause or matters
    in difference are referred to an arbitrator, whether a
    lawyer or a layman, he is constituted the sole and final
    Judge of all questions both of law and of fact. … The
    only exceptions to that rule are cases where the award
    is the result of corruption or fraud, and one other,
    which, though it is to be regretted, is now, I think
    firmly established viz. where the question of law
    necessarily arises on the face of the award or upon
    Signature Not Verified
    Signed By:PRATEEK O.M.P. (COMM) 341/2020 Page 19 of 29
    Signing Date:24.03.2026
    15:59:10
    some paper accompanying and forming part of the
    award. Though the propriety of this latter may very
    well be doubted, I think it may be considered as
    established.‟
    ***
    Now the regret expressed by Williams, J.
    in Hodgkinson v. Fernie [(1857) 3 CB (NS) 189 : 140
    ER 712] has been repeated by more than one learned
    Judge, and it is certainly not to be desired that the
    exception should be in any way extended. An error in
    law on the face of the award means, in Their
    Lordships’ view, that you can find in the award or a
    document actually incorporated thereto, as for
    instance, a note appended by the arbitrator stating the
    reasons for his judgment, some legal proposition which
    is the basis of the award and which you can then say is
    erroneous. It does not mean that if in a narrative a
    reference is made to a contention of one party that
    opens the door to seeing first what that contention is,
    and then going to the contract on which the parties’
    rights depend to see if that contention is sound. Here it
    is impossible to say, from what is shown on the face of
    the award, what mistake the arbitrators made. The
    only way that the learned Judges have arrived at
    finding what the mistake was is by saying:„Inasmuch
    as the arbitrators awarded so and so, and inasmuch as
    the letter shows that the buyer rejected the cotton, the
    arbitrators can only have arrived at that result by
    totally misinterpreting Rule 52.‟ But they were entitled
    to give their own interpretation to Rule 52 or any other
    article, and the award will stand unless, on the face of
    it they have tied themselves down to some special legal
    proposition which then, when examined, appears to be
    unsound. Upon this point, therefore, Their Lordships
    think that the judgment of Pratt, J. was right and the
    conclusion of the learned Judges of the Court of
    Appeal [Jivraj Baloo Spg. and Wvg. Co.

    Ltd. v. Champsey Bhara and Co., ILR (1920) 44 Bom

    780. The judgment of Pratt, J. may be referred to at
    ILR p. 787.] erroneous.”

    Signature Not Verified
    Signed By:PRATEEK O.M.P. (COMM) 341/2020 Page 20 of 29
    Signing Date:24.03.2026
    15:59:10

    This judgment has been consistently followed in
    India to test awards under Section 30 of the Arbitration
    Act, 1940.

    42. In the 1996 Act, this principle is substituted by
    the “patent illegality” principle which, in turn,
    contains three subheads:

    42.1. (a) A contravention of the substantive law of
    India would result in the death knell of an arbitral
    award. This must be understood in the sense that such
    illegality must go to the root of the matter and cannot
    be of a trivial nature. This again is really a
    contravention of Section 28(1)(a) of the Act, which
    reads as under:

    “28.Rules applicable to substance of dispute.–(1)
    Where the place of arbitration is situated in India–

    (a) in an arbitration other than an international
    commercial arbitration, the Arbitral Tribunal shall
    decide the dispute submitted to arbitration in
    accordance with the substantive law for the time being
    in force in India;”

    42.2. (b) A contravention of the Arbitration Act
    itself would be regarded as a patent illegality — for
    example if an arbitrator gives no reasons for an award
    in contravention of Section 31(3) of the Act, such
    award will be liable to be set aside.

    42.3. (c) Equally, the third subhead of patent
    illegality is really a contravention of Section 28(3) of
    the Arbitration Act, which reads as under:

    “28.Rules applicable to substance of dispute.–(1)-
    (2)***
    (3) In all cases, the Arbitral Tribunal shall decide
    in accordance with the terms of the contract and shall

    Signature Not Verified
    Signed By:PRATEEK O.M.P. (COMM) 341/2020 Page 21 of 29
    Signing Date:24.03.2026
    15:59:10
    take into account the usages of the trade applicable to
    the transaction.”

    This last contravention must be understood with a
    caveat. An Arbitral Tribunal must decide in
    accordance with the terms of the contract, but if an
    arbitrator construes a term of the contract in a
    reasonable manner, it will not mean that the award
    can be set aside on this ground. Construction of the
    terms of a contract is primarily for an arbitrator to
    decide unless the arbitrator construes the contract in
    such a way that it could be said to be something that
    no fair-minded or reasonable person could do.

    43. In McDermott International Inc. v. Burn
    Standard Co. Ltd. [McDermott International
    Inc.
    v. Burn Standard Co. Ltd., (2006) 11 SCC 181] ,
    this Court held as under : (SCC pp. 225-26, paras 112-

    13)
    “112. It is trite that the terms of the contract can be
    express or implied. The conduct of the parties would
    also be a relevant factor in the matter of construction
    of a contract. The construction of the contract
    agreement is within the jurisdiction of the arbitrators
    having regard to the wide nature, scope and ambit of
    the arbitration agreement and they cannot be said to
    have misdirected themselves in passing the award by
    taking into consideration the conduct of the parties. It
    is also trite that correspondences exchanged by the
    parties are required to be taken into consideration for
    the purpose of construction of a contract.
    Interpretation of a contract is a matter for the
    arbitrator to determine, even if it gives rise to
    determination of a question of law. [See Pure Helium
    India (P) Ltd. v. Oil and Natural Gas
    Commission
    [(2003) 8 SCC 593 : 2003 Supp (4) SCR
    561] and D.D. Sharma v. Union of India [(2004) 5
    SCC 325] .]

    Signature Not Verified
    Signed By:PRATEEK O.M.P. (COMM) 341/2020 Page 22 of 29
    Signing Date:24.03.2026
    15:59:10

    113. Once, thus, it is held that the arbitrator had the
    jurisdiction, no further question shall be raised and the
    court will not exercise its jurisdiction unless it is found
    that there exists any bar on the face of the award.”

    44. In MSK Projects (I) (JV) Ltd. v. State of
    Rajasthan
    [(2011) 10 SCC 573 : (2012) 3 SCC (Civ)
    818] , the Court held : (SCC pp. 581-82, para 17)

    “17. If the arbitrator commits an error in the
    construction of the contract, that is an error within his
    jurisdiction. But if he wanders outside the contract and
    deals with matters not allotted to him, he commits a
    jurisdictional error. Extrinsic evidence is admissible in
    such cases because the dispute is not something which
    arises under or in relation to the contract or dependent
    on the construction of the contract or to be determined
    within the award. The ambiguity of the award can, in
    such cases, be resolved by admitting extrinsic
    evidence. The rationale of this rule is that the nature of
    the dispute is something which has to be determined
    outside and independent of what appears in the award.
    Such a jurisdictional error needs to be proved by
    evidence extrinsic to the award. (See Gobardhan
    Das v. Lachhmi Ram
    [(1954) 1 SCC 566 : AIR 1954
    SC 689] , Thawardas Pherumal v. Union of India
    [AIR
    1955 SC 468] , Union of India v. Kishorilal Gupta &
    Bros.
    [AIR 1959 SC 1362] , Alopi Parshad & Sons
    Ltd. v. Union of India
    [AIR 1960 SC 588] , Jivarajbhai
    Ujamshi Sheth v. Chintamanrao Balaji
    [AIR 1965 SC
    214] and Renusagar Power Co. Ltd. v. General
    Electric Co.
    [(1984) 4 SCC 679 : AIR 1985 SC 1156]
    )”

    45. In Rashtriya Ispat Nigam Ltd. v. Dewan Chand
    Ram Saran
    [(2012) 5 SCC 306] , the Court held :

    (SCC pp. 320-21, paras 43-45)

    Signature Not Verified
    Signed By:PRATEEK O.M.P. (COMM) 341/2020 Page 23 of 29
    Signing Date:24.03.2026
    15:59:10
    “43. In any case, assuming that Clause 9.3 was
    capable of two interpretations, the view taken by the
    arbitrator was clearly a possible if not a plausible one.

    It is not possible to say that the arbitrator had
    travelled outside his jurisdiction, or that the view taken
    by him was against the terms of contract. That being
    the position, the High Court had no reason to interfere
    with the award and substitute its view in place of the
    interpretation accepted by the arbitrator.

    44. The legal position in this behalf has been
    summarised in para 18 of the judgment of this Court
    in SAIL v. Gupta Brother Steel Tubes Ltd. [(2009) 10
    SCC 63 : (2009) 4 SCC (Civ) 16] and which has been
    referred to above.
    Similar view has been taken later
    in Sumitomo Heavy Industries Ltd. v. ONGC
    Ltd. [(2010) 11 SCC 296 : (2010) 4 SCC (Civ) 459] to
    which one of us (Gokhale, J.) was a party. The
    observations in para 43 thereof are instructive in this
    behalf.

    45. This para 43 reads as follows : (Sumitomo
    case [(2010) 11 SCC 296 : (2010) 4 SCC (Civ) 459] ,
    SCC p. 313)

    „43. … The umpire has considered the fact situation
    and placed a construction on the clauses of the
    agreement which according to him was the correct
    one. One may at the highest say that one would have
    preferred another construction of Clause 17.3 but that
    cannot make the award in any way perverse. Nor can
    one substitute one’s own view in such a situation, in
    place of the one taken by the umpire, which would
    amount to sitting in appeal. As held by this Court
    in Kwality Mfg. Corpn. v. Central Warehousing
    Corpn.
    [(2009) 5 SCC 142 : (2009) 2 SCC (Civ) 406]
    the Court while considering challenge to arbitral
    award does not sit in appeal over the findings and
    decision of the arbitrator, which is what the High
    Signature Not Verified
    Signed By:PRATEEK O.M.P. (COMM) 341/2020 Page 24 of 29
    Signing Date:24.03.2026
    15:59:10
    Court has practically done in this matter. The umpire
    is legitimately entitled to take the view which he holds
    to be the correct one after considering the material
    before him and after interpreting the provisions of the
    agreement. If he does so, the decision of the umpire has
    to be accepted as final and binding.‟”

    7. Material on record indicates that amounts claimed under Claim No.1
    by the Respondent was on account of drastic and belated variations which
    were ordered by the Petitioner herein, including a shift from LHS widening
    to concentric widening as well the addition of three overpasses in a 7 km.
    stretch which substantially altered the scope of work under the Contract.

    8. Before the learned Arbitral Tribunal, the Respondent‟s grievance was
    that the alterations brought about by the Petitioner led to a construction of
    nearly 14 km. of RCC road retaining walls involving over 33,000 cubic
    meters of concrete which also resulted in the change of nature and character
    of the Contract. It was on this basis that the Respondent had claimed
    revision of rates for items where quantities varied beyond 25% and
    constituted more than 5% of the contract price which classified the claim
    into BOQ items, derived BOQ items and entirely new extra items.

    9. Before the learned Arbitral Tribunal the Petitioner opposed Claim
    No.1 by stating that the variations in question were neither drastic nor
    belated as being completely covered under Clauses 51 & 52 of the GCC, as
    such there was no alteration in the fundamental nature of the Contract. It
    was further contended that by executing the variations without protest, the
    Respondent had impliedly accepted the changes and relaxed the variation
    limits.

    10. The learned Arbitral Tribunal under Claim No.1 held that the revision
    of rates under Clause 52 of the GCC was permissible where both the

    Signature Not Verified
    Signed By:PRATEEK O.M.P. (COMM) 341/2020 Page 25 of 29
    Signing Date:24.03.2026
    15:59:10
    conditions were satisfied, i.e., the item constituted more than 5% of the
    contract price and that the executed quantity varied by more than 25% from
    the BOQ. It was further observed that the Respondent remained bound to
    execute the original quantities as per the BOQ at the quoted rates and
    accordingly the revised rates could only apply to the quantities in excess of
    the BOQ.

    11. While the learned Arbitral Tribunal rejected the Respondent‟s revised
    rate analysis, it carried out rate revision on the basis of experience the
    learned Members of the Arbitral Tribunal, thereby awarding a total of
    Rs.1,32,14,407/- in favour of the Respondent.

    12. In the opinion of this Court although detailed calculation or precise
    methodology for awarding of the amount under Claim No.1 in favour of the
    Respondent is not visible, this Court does not find the ultimate grant of the
    sum of Rs.1,32,14,407/- to be arbitrary or perverse. Admittedly, the
    difference between the revised rates already paid by the Respondent and
    those ultimately awarded by the learned Arbitral Tribunal is only marginal
    which means that the learned Arbitral Tribunal did not depart substantially
    from the contractual or contemporaneous pricing framework. Rather, with
    respect to the items related to the construction of diversions near the
    overpass the learned Arbitral Tribunal has in fact reduced the claimed
    revised rate from Rs.3,40,003/- to Rs.2,58,995/-. In the opinion of this Court
    this demonstrates the exercise of independent judicial discretion of the
    Arbitral Tribunal rather than a mechanical acceptance of the Respondent‟s
    case. As such, this Court does not see any reason to interfere with the
    findings returned by the learned Arbitral Tribunal under Claim No.1.

    13. Dealing next with Claim No.4 under which the Respondent claimed
    compensation for loss of overheads, profits, reduced productivity from
    Signature Not Verified
    Signed By:PRATEEK O.M.P. (COMM) 341/2020 Page 26 of 29
    Signing Date:24.03.2026
    15:59:10
    deployed machinery and equipment, and loss of bonus to the tune of
    Rs.17,49,10,739.70/- . In support of its claim, the Respondent argued before
    the learned Arbitral Tribunal that although complete mobilization was
    carried out, breach of the contractual terms by the Petitioner prevented the
    Respondent from progressing according to the schedule. The Respondent
    contended that their tendered rates accounted for 10% profits, 10%
    overheads, as well as 10% deployment costs which would enable them to be
    placed in the same financial situation had there been no breach on part of the
    Petitioner.

    14. Opposing Claim No.4 the Petitioner submitted that it was the
    Respondent who failed to timely mobilize key personnel and equipment, and
    the machinery provided by the Respondent was old and prone to breakdown.
    The Petitioner further pointed out that the Respondent‟s overall progress
    was only 22% and their bid was 28% below the estimated costs making their
    claims for high profits and overheads completely baseless.

    15. As per the learned Arbitral Tribunal, the Respondent was in fact
    responsible for the overall slow progress of work which was evident for
    merely 22% progress achieved by them. At the same time the learned
    Arbitral Tribunal also notes that specific delays under Phase-I occurring on
    account of hindrances on the site were also attributable to the Petitioner. On
    the basis of these findings the learned Arbitral Tribunal considered overhead
    charges at 8% of the contract price and calculated the additional overheads
    for Phase-I as well as ROB works during the 16.5 months extension period.
    After applying a 20% reduction for mitigation of losses, the learned Arbitral
    Tribunal by way of majority awarded an amount of Rs.56,95,123/- in favour
    of the Respondent.

    16. It is pertinent to note that against the findings on Claim No.4 a
    Signature Not Verified
    Signed By:PRATEEK O.M.P. (COMM) 341/2020 Page 27 of 29
    Signing Date:24.03.2026
    15:59:10
    dissenting opinion was also given by the Sh. H. P. Jamdar, learned
    Arbitrator, who was of the opinion that since overheads are built into item
    rates and accrue only upon actual execution of works, awarding of any
    amount to the Respondent was unjustified. He therefore opined that the
    entire claim of the Respondent should have been rejected.

    17. This Court is of the opinion that the primary reason given by the
    majority of the learned Arbitral Tribunal was on the basis of their
    observation that hindrances were caused by the Respondent on the Project
    Site, especially after the scope of work was changed from LHS widening to
    concentric widening. It can be noted from a reading of the impugned Award
    that the learned Arbitral Tribunal has observed delay on both sides and
    carefully awarded the amount only for the actual works carried out by the
    Respondent under Phase-I. For this reason, this Court finds itself in
    agreement with the award of amount under Claim No.4 in favour of the
    Respondent.

    18. The last claim challenged by the Petitioner is Claim No.5 under which
    the learned Arbitral Tribunal has awarded Rs.4.10 lakhs in favour of the
    Respondent.

    19. Material on record indicates that the basis of Claim No.5 was the cost
    of deployment of additional resources for execution of additional works
    from January, 2003 onwards. In support of its claim, the Respondent had
    argued before the learned Arbitral Tribunal that it was at the instance of the
    Petitioner that additional resources had to be deployed to ensure completion
    of the Project by 30.10.2003. The Respondent‟s case was that the
    Petitioner‟s decision to suspend the service road works constituted a breach
    of the Contract leaving these additional resources idle at the Project Site.

    20. Against Claim No.5, the Petitioner argued that the Respondent‟s case
    Signature Not Verified
    Signed By:PRATEEK O.M.P. (COMM) 341/2020 Page 28 of 29
    Signing Date:24.03.2026
    15:59:10
    was not supported by any evidence, stating that there were no log books or
    any other document produced to prove the loss as claimed by the
    Respondent. The Petitioner also argued that 90% of the resources which the
    Respondent labels to be additional were actually necessary for the
    Respondent to catch up on the slow progress of works being carried out by
    it.

    21. This Court is of the opinion that considering the findings returned by
    the learned Arbitral Tribunal on other claims as discussed above, the Award
    of Rs.4.10 lakhs under Claim No.5 to meet the ends of justice does not
    warrant any interference.

    22. From the discussion above, it is evident that the learned Arbitral
    Tribunal meticulously evaluated the material presented before it and
    thoroughly examined the documents filed by the parties. Each claim was
    addressed with due regard to the terms of the Contract between the parties as
    well as the applicable legal principles.

    23. This Court believes that the findings of the learned Arbitral Tribunal
    demonstrate that a careful balance between the contractual provisions, the
    conduct of the parties, and the principles of fairness were maintained.

    24. In view of the above, this Court does not find any merit in the instant
    Petition and the challenge laid by the Petitioner against the Impugned
    Award.

    25. Resultantly, the Petition is dismissed along with pending
    application(s), if any.

    SUBRAMONIUM PRASAD, J
    MARCH 24, 2026
    hsk/ap
    Signature Not Verified
    Signed By:PRATEEK O.M.P. (COMM) 341/2020 Page 29 of 29
    Signing Date:24.03.2026
    15:59:10



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here