M/S. Malathy Constructions vs Bridge And Roof Co. India Ltd on 8 May, 2026

    0
    29
    ADVERTISEMENT

    Calcutta High Court

    M/S. Malathy Constructions vs Bridge And Roof Co. India Ltd on 8 May, 2026

                         IN THE HIGH COURT AT CALCUTTA
                              COMMERCIAL DIVISION
                                 ORIGINAL SIDE
                              RESERVED ON: 22.04.2026
                              DELIVERED ON: 08.05.2026
                                   PRESENT:
                    THE HON'BLE MR. JUSTICE GAURANG KANTH
                                   AP-COM 61 OF 2025
                            M/S. MALATHY CONSTRUCTIONS
                                      VERSUS
                            BRIDGE AND ROOF CO. INDIA LTD.
    Appearance:
    
    Mr. Anubhav Sinha, Adv.
    Mr. Shirsho Banerjee, Adv.
                                                                  ..... for the petitioner
    
    Mr. Sanjib Dawn, Adv.
                                                                ..... for the respondent
    
                                        JUDGMENT
    

    Gaurang Kanth, J.:-

    1. The Petitioner has preferred the present petition under Section 11 of the

    Arbitration and Conciliation Act, 1996, seeking appointment of a sole

    arbitrator to adjudicate the disputes arising between the parties.

    2. The facts leading to the present Petition are as follows:

    3. The Respondent is a multi-disciplinary engineering company primarily

    engaged in infrastructure projects. The Petitioner is a partnership firm

    engaged in civil works and has provided services to various construction

    companies in connection with civil projects.

    4. The Respondent floated a tender, pursuant whereto the Petitioner emerged

    as the successful bidder. Accordingly, the Respondent awarded a

    subcontract to the Petitioner vide tender document bearing No.

    B&R/51108/ARIYALUR/TD/PCC, RCC, FORM WORK dated 16.12.2017,

    for execution of PCC, RCC, and shuttering works on a subcontract basis in
    2

    connection with the execution and handing over of civil works yard and

    buildings (excluding gravel spreading and compound wall) of the 756/400

    KV Substation at Ariyalur, Tamil Nadu.

    5. In furtherance of the said subcontract, the Petitioner carried out

    excavation, disposal, and refilling works under the following work orders

    issued by the Respondent: (i) Work Order No.

    B&R/51108/ARIYALUR/LOI/Earthwork Excavation dated 08.01.2018; (ii)

    Work Order No. B&R/51108/ARIYALUR/LOI/PCC, RCC & Shuttering/01

    dated 08.01.2018; (iii) Work Order No. B&R/51108/ARIYALUR/LOI/Open

    and Covered Stores dated 30.01.2018; (iv) Work Order No.

    B&R/51108/ARIYALUR/LOI/PCC, RCC & Shuttering/01/C dated

    11.05.2018.

    6. The Respondent issued a certificate of completion dated 06.08.2019

    certifying completion of part works in respect of the aforesaid work orders.

    7. The Petitioner contends that the Respondent, while making payments

    against the executed works, withheld 5% of the payment amounts as

    security deposit under the aforesaid letters of intent and work orders. The

    Petitioner further contends that the Respondent’s officials directed the

    Petitioner to excavate foundations beyond a depth of 2 metres, whereas

    excavation up to 2 metres only was within the Petitioner’s contractual

    scope. The Petitioner contends that the Respondent’s officials assured that

    payment for such additional excavation work would be released as and

    when the principal employer released the corresponding payment. However,

    the invoices raised by the Petitioner in respect of such additional work were

    not paid by the Respondent. The Petitioner further contends that, on

    account of disputes between the Respondent and the principal employer,
    3

    certain portions of the work executed by the Petitioner were not certified by

    the principal employer. As a consequence, thereof, the Petitioner was

    required to retain manpower and machinery at the site for an extended

    period, resulting in additional expenditure being incurred by the Petitioner.

    8. The Petitioner raised its last invoice on 12.03.2019 for an amount of Rs.

    37,94,998/-. Against the said invoice, the Respondent released a sum of

    SPONSORED

    Rs. 5,13,965/- on 11.04.2019, leaving a substantial amount outstanding

    and unpaid.

    9. The Petitioner addressed emails to the Respondent on 07.10.2019,

    02.01.2020, and 21.03.2020 calling upon the Respondent to release the

    outstanding dues. However, the Respondent failed to make the payment of

    the said amount.

    10. The Petitioner thereafter issued a legal notice dated 29.05.2020 demanding

    release of the total outstanding sum of Rs. 1,72,62,327/-. The Respondent,

    by electronic mail dated 01.06.2020, denied all claims of the Petitioner and

    indicated that any disputes between the parties would be resolved through

    arbitration.

    11. The Petitioner subsequently invoked the arbitration clause, being Clause 26

    of Annexure II to the General Conditions of the tender document dated

    16.12.2017, vide letter dated 30.06.2022. The Respondent neither

    responded to the said invocation notice nor took any steps for constitution

    of the arbitral tribunal.

    12. In the aforesaid circumstances, the Petitioner has preferred the present

    petition under Section 11 of the Arbitration and Conciliation Act, 1996,

    seeking appointment of an independent arbitrator to adjudicate the

    disputes between the parties.

    4

    Submission on behalf of the Petitioner

    13. Mr. Anubhav Sinha, learned counsel for the Petitioner submits that a valid

    and binding arbitration agreement exists between the parties in the form of

    Clause 26 of Annexure II to the General Conditions of the tender document

    dated 16.12.2017 and that all disputes arising out of non-payment of

    contractual dues, retention of security deposit, non-certification of extra

    work, and losses incurred on account of prolonged site presence fall

    squarely within the scope of that clause. Upon the Petitioner’s invocation

    of the arbitration clause vide letter dated 30.06.2022, the Respondent failed

    and neglected to respond or to participate in the appointment process. In

    this precise situation, the Delhi High Court in ABB ABL Ltd. v. Cement

    Corporation of India reported as [1999 (49) DRJ 131] held that where a

    party fails to appoint an arbitrator despite notices and requests and shows

    no inclination to cooperate in constituting the tribunal, the Court’s

    jurisdiction under Section 11(6) of the Arbitration and Conciliation Act,

    1996 is properly and necessarily invoked, as the only recourse available to

    the aggrieved party in such circumstances is to approach the Court for

    appointment. The present petition is therefore fully maintainable.

    14. On the question relating to the scope of inquiry at this stage, the Petitioner

    relies upon the judgment of the Hon’ble Supreme Court in Schlumberger

    Asia Services Ltd. v. Oil and Natural Gas Corporation Ltd. reported as

    [2013 (7) SCC 562], wherein it was categorically held that while the Court

    or the designated authority under Section 11 may decide whether a claim is

    patently dead or long time barred by limitation, it is not imperative to do so

    at the threshold. It is further held that where disputed questions arise,

    whether as to limitation, receipt of notices, or the validity of claims, such
    5

    issues are matters of evidence and are therefore required to be left to the

    Arbitral Tribunal. Similarly, the Division Bench of the Delhi High Court in

    Oval Investment Pvt. Ltd. v. Indiabulls Financial Services Pvt. Ltd.

    reported as [2009 (113) DRJ (504) (DB)] affirmed that the statutory scheme

    of the Arbitration and Conciliation Act, 1996 is a self-contained code, and

    any challenge relating to the existence or invocation of an arbitration

    agreement must be addressed within that framework. It is further held that

    it is not open to a party to circumvent or frustrate the arbitral process by

    inaction or by raising disputes outside the Act’s framework. The Bombay

    High Court in Singhai & Brothers v. MTNL reported as [(2005) 3 Mh.L.J.

    951] further reinforced this position by holding that where the parties have

    continued to correspond and the cause of action is of a continuing nature,

    delay in approaching the Court for appointment of an arbitrator under

    Section 11 does not extinguish the arbitrable claims, and any contention as

    to limitation remains a matter exclusively within the domain of the Arbitral

    Tribunal to determine on evidence.

    15. In light of the foregoing, it is the submission of the learned counsel for the

    Petitioner that at this stage, this Court is not called upon to examine the

    merits of the Petitioner’s claims or any objections which the Respondent

    may seek to raise, all of which fall within the exclusive adjudicatory domain

    of the Arbitral Tribunal. The Court’s task is confined to satisfying itself of

    the existence of a valid arbitration agreement, which is undisputed and the

    breakdown of the appointment mechanism which is evident from the

    Respondent’s failure to respond to the invocation notice. In view thereof,

    the Petitioner prays for the appointment of a sole independent arbitrator to
    6

    adjudicate the disputes between the parties, in terms of Section 11 of the

    Arbitration and Conciliation Act, 1996.

    Submission on behalf of the Respondent

    16. Mr. Sanjib Dawn, learned counsel for the Respondent submits that while

    the subcontract work was indeed allotted to the Petitioner, the Petitioner

    consistently failed to perform its obligations under the contract. The

    progress of work remained unsatisfactory throughout, and the Petitioner

    failed to effectively dispose of hard rock generated from blasting and

    surplus soil, leading to an accumulation of debris at the site, which

    impeded the execution of the project. On account of the Petitioner’s failure

    to perform, the principal employer BHEL was constrained to engage

    another agency to carry out the very work allotted to the Petitioner, at the

    risk and cost of the Petitioner. The Respondent has specifically denied the

    Petitioner’s contention that its men and machinery were required to be

    stationed at site at the Respondent’s behest. The Respondent never directed

    the Petitioner to retain men or machinery at site. It was the Petitioner who,

    of its own volition and in anticipation of future work that never

    materialised, refused to demobilise from the site. The discontinuation of

    work was entirely attributable to vendor related issues on the part of the

    Petitioner, and not due to any act or omission of the Respondent. The last

    payment made to the Petitioner was on 19.06.2019, and after that date, the

    Petitioner took no effective steps within the period of limitation to pursue

    its claims through the contractually prescribed mechanism.

    17. The Respondent further submits that the present petition is liable to be

    dismissed on several independent and compelling legal grounds. First, the

    petition is hopelessly barred by limitation. The last payment by the
    7

    Respondent was made on 19.06.2019, and the cause of action, if any,

    crystallised on or around the said date. The alleged arbitration invocation

    notice was issued only on 30.06.2022, well beyond three years from the

    date on which the Petitioner’s cause of action alleged to have arisen. The

    Petitioner’s intermittent emails in 2019 and 2020 do not constitute any

    acknowledgment of liability by the Respondent and cannot operate to

    extend or refresh the period of limitation. Second, no valid notice under

    Section 21 of the Arbitration and Conciliation Act, 1996 was ever received

    by the Respondent. The only communication received by the Respondent

    from the Petitioner was in the nature of a notice under Section 80 of the

    Code of Civil Procedure, 1908, which is a precursor to civil litigation and

    cannot be treated as a request for reference of disputes to arbitration

    within the meaning of Section 21 of the Act. In the absence of receipt of a

    valid Section 21 notice, the arbitration proceedings cannot be deemed to

    have commenced and the present petition is premature and misconceived

    in law. Third, the Petitioner has not placed on record the agreement

    forming part of the transaction sought to be referred to arbitration. The

    work orders relied upon by the Petitioner do not form part of the tender

    document bearing No. B&R/51108/ARIYALUR/TD/PCC, RCC, FORM

    WORK dated 16.12.2017, the very document in which the arbitration

    clause is embedded. In the absence of any demonstrated nexus between the

    work orders and the said tender document, the disputes alleged to have

    arisen from those work orders cannot be said to be covered by or referable

    to the arbitration clause contained therein.

    18. Learned Counsel for the Respondent accordingly submits that the present

    petition suffers from a confluence of fatal infirmities: the claims are time
    8

    barred and arise from long standing inaction on the part of the Petitioner;

    that no valid Section 21 notice has ever been received by the Respondent so

    as to constitute the commencement of arbitration proceedings that the

    foundational agreement containing the arbitration clause has not been

    placed on record; and the work orders sought to be agitated have not been

    shown to form part of the tender document containing the arbitration

    clause. Each of these grounds, individually and collectively, disentitles the

    Petitioner from obtaining the reliefs claimed. The present petition under

    Section 11 of the Arbitration and Conciliation Act, 1996 is therefore liable

    to be dismissed with costs.

    Legal Analysis

    19. This Court has carefully considered the submissions advanced by the

    learned counsel for both parties, examined the documents placed on

    record, and perused the judgments cited at the Bar.

    20. The present petition has been filed under Section 11 of the Arbitration and

    Conciliation Act, 1996, seeking appointment of a sole arbitrator. The

    Petitioner has invoked arbitration under Clause 26 of Annexure II to the

    General Conditions of Contract forming part of the tender document

    bearing No. B&R/51108/ARIYALUR/TD/PCC, RCC, FORM WORK dated

    16.12.2017.

    21. Before proceeding to consider the appointment of an arbitrator, it is

    necessary for this Court to examine two threshold questions that go to the

    root of the maintainability of this present petition: first, whether the

    disputes alleged by the Petitioner arise out of and are referable to the

    arbitration clause relied upon; and second, whether a valid notice under

    Section 21 of the Act was issued and received by the Respondent so as to
    9

    constitute a valid commencement of arbitration proceedings. It is well

    settled that these two requirements are jurisdictional in nature and must

    be satisfied before this Court can exercise its power of appointment under

    Section 11 of the Act.

    22. On the first threshold question, this Court is called upon to determine

    whether the work orders under which the Petitioner claims its alleged dues

    arise out of the tender document bearing No.

    B&R/51108/ARIYALUR/TD/PCC, RCC, FORM WORK dated 16.12.2017, or

    whether they arise out of an altogether different document, namely tender

    document bearing No. B&R/51108/ARIYALUR/TD/Form Work dated

    08.01.2018. The answer to this question is decisive, for it is only if the work

    orders are traceable to the tender document dated 16.12.2017 that the

    arbitration clause embedded in Clause 26 of Annexure II thereto can be

    invoked in respect of disputes arising out of such work orders.

    23. An examination of the record reveals a fundamental and material

    inconsistency in the Petitioner’s own case. In the present petition, the

    Petitioner contends that the work orders were issued in pursuance of the

    tender document dated 16.12.2017, and on that basis invokes Clause 26 of

    Annexure II to the General Conditions of Contract forming part of that

    document. However, the notice dated 30.06.2022, whereby the Petitioner

    purported to invoke arbitration, projects a materially different and

    contradictory case. In that notice, the Petitioner categorically states that it

    had participated in a tender process initiated by the Respondent vide

    tender document bearing No. B&R/51108/ARIYALUR/TD/Form Work

    dated 08.01.2018, for execution of earthworks on a subcontract basis in

    connection with the execution and handing over of Civil Works Yard and
    10

    Buildings at the TNEB Ariyalur Project, and that upon being the successful

    bidder, the subcontract work relating to excavation, disposal, and refilling

    works was allotted to it thereunder. The petition and the arbitration

    invocation notice thus project inconsistent and irreconcilable cases as to

    the very tender document out of which the work orders and the consequent

    disputes are stated to arise. It is a well-established principle that a party

    cannot be permitted to approbate and reprobate simultaneously, that is to

    say, a party cannot blow hot and cold by adopting one position when it

    suits its purpose and an inconsistent position when that suits better. A

    party is bound by the position adopted in its own documents and cannot be

    permitted to resile therefrom while relying upon the same documents before

    a Court. In the present case, the Petitioner’s invocation notice dated

    30.06.2022 is the Petitioner’s own document and the Petitioner cannot

    distance itself from the case projected therein while simultaneously relying

    upon that very notice as the foundation of the present petition. The

    Petitioner’s inconsistency in this regard is not a peripheral irregularity, it

    strikes at the foundational premise of the present petition.

    24. The Respondent has strenuously contended that the work orders relied

    upon by the Petitioner do not arise out of the tender document dated

    16.12.2017 and that, therefore, the disputes alleged to have arisen from

    those work orders are neither referable to nor covered by Clause 26 of

    Annexure II to that document. This contention has not been rebutted by

    the Petitioner by placing any cogent documentary material on record.

    25. This Court finds that the inconsistency between the case projected in the

    petition and the case projected in the arbitration invocation notice is not a

    mere procedural irregularity, it strikes at the foundation of the invocation
    11

    itself. Where the Petitioner is unable to project a consistent and

    unambiguous case as to which tender document governs the work orders

    in question, there can be no clarity as to which arbitration clause is

    applicable, and consequently, no valid invocation of arbitration can be said

    to have been made in respect of the disputes alleged.

    26. It is a well settled principle of arbitration law that the jurisdiction of an

    arbitral tribunal is derived from and is co-extensive with the arbitration

    agreement between the parties. An arbitration clause contained in one

    document does not automatically extend to disputes arising from

    independent instruments unless it is clearly established that such

    instruments were issued in pursuance of, or expressly incorporate by

    reference, the terms of the parent document containing the arbitration

    clause. In the present case, the Petitioner has failed to place on record any

    cogent material, whether by way of clauses of incorporation in the work

    orders themselves, cross references to the tender document dated

    16.12.2017, any covering communication linking the work orders to that

    tender document, or any other contemporaneous documentary evidence,

    that establishes the requisite nexus. The Respondent’s denial of this

    connection has not been rebutted. In the absence of any demonstrated

    nexus between the work orders and the tender document dated

    16.12.2017, this Court is unable to conclude that the disputes arising out

    of the said work orders are governed by or referable to Clause 26 of

    Annexure II to that document. The burden of establishing this nexus lay

    squarely upon the Petitioner, and that burden has not been discharged. In

    this regard, this Court also notes that the judgments relied upon by the

    Petitioner, including Schlumberger Asia Services Ltd. (supra), Oval
    12

    Investment Pvt. Ltd. (supra), Singhai & Brothers (supra), and ABB ABL

    Ltd. (supra) all proceed on the premise that a valid and identifiable

    arbitration agreement exists between the parties and that the disputes

    sought to be referred to arbitration fall within the scope of that agreement.

    None of these judgments assist the Petitioner at the threshold stage where

    the very agreement governing the work orders and the applicable

    arbitration clause remain unestablished on the record. These judgments

    would become relevant only once the foundational jurisdictional

    requirements are duly satisfied.

    27. The second threshold issue concerns the validity of the notice purportedly

    issued under Section 21 of the Arbitration and Conciliation Act, 1996.

    Section 21 of the Act provides that, unless otherwise agreed by the parties,

    arbitral proceedings in respect of a particular dispute shall be deemed to

    have commenced on the date on which a request for the dispute to be

    referred to arbitration is received by the Respondent. The Section 21 notice

    is not a mere procedural formality, rather it is a jurisdictional prerequisite

    that marks the very commencement of arbitration proceedings. For a notice

    to constitute a valid Section 21 notice, it must satisfy the following

    essential requirements: it must clearly communicate the claimant’s

    intention to invoke arbitration in respect of the specific disputes between

    the parties; it must identify the agreement or contract under which

    arbitration is sought to be invoked and, in particular, the arbitration clause

    being relied upon; it must contain or reasonably indicate the nature and

    particulars of the disputes sought to be referred to arbitration; and it must

    be addressed to and actually received by the other party. A notice that is

    vague, ambiguous, or fails to identify the arbitration agreement or clause
    13

    sought to be invoked, or a notice that does not clearly indicate that

    arbitration is being invoked as the dispute resolution mechanism under the

    Act, does not satisfy the requirements of Section 21 and cannot be treated

    as constituting a valid commencement of arbitration proceedings.

    28. Examining the facts of the present case against the requirements set out

    above, this Court finds that the Respondent’s objection to the validity of the

    Section 21 notice of the Act must be upheld on two independent and self-

    sufficient grounds, either of which is sufficient to vitiate the invocation. The

    first ground is non-receipt of the notice. The Respondent has categorically

    denied receipt of the notice dated 30.06.2022, and the Petitioner has not

    placed on record any postal acknowledgment, courier proof of delivery, or

    any other evidence of actual receipt of the said notice by the Respondent.

    Since Section 21 of the Act makes receipt of the notice by the Respondent

    the operative event for commencement of arbitration, the absence of proof

    of receipt is itself a fatal deficiency. The second and independent ground

    relates to the defective contents of the notice. Even proceeding on the

    assumption that the said notice was sent, an examination of its contents

    reveals multiple infirmities: it does not expressly state that it is issued

    under or in terms of Section 21 of the Arbitration and Conciliation Act,

    1996; further, it does not clearly identify the specific arbitration clause

    under which arbitration is sought to be invoked. The particulars of the

    claims sought to be referred to arbitration are also not set out with any

    clarity or specificity. Moreover, as noted above, the notice refers to a

    different tender document altogether, tender document No.

    B&R/51108/ARIYALUR/TD/Form Work dated 08.01.2018, rather than the

    tender document dated 16.12.2017 under which Clause 26 is sought to be
    14

    invoked in the petition. This further compounds the infirmity, as the

    invocation notice and the petition are themselves inconsistent with each

    other on the foundational question as to which document governs the

    disputes. Both grounds are independent of each other, and the finding

    regarding invalidity of the Section 21 notice rests on each of them

    separately and on both of them cumulatively.

    29. In contrast, the only notice admittedly received by the Respondent was the

    legal notice dated 29.05.2020. By its own character, that notice is a

    demand notice and a precursor to civil litigation, and not an invocation of

    arbitration under the Arbitration and Conciliation Act, 1996. A demand

    notice of that nature and a Section 21 notice under the Arbitration Act are

    instruments of entirely different character, purpose, and legal consequence.

    The former is a statutory prerequisite to the filing of a civil suit against

    certain parties; the latter is a jurisdictional act that marks the

    commencement of arbitral proceedings. One cannot be read as or

    substituted for the other. The receipt of a demand notice by the Respondent

    cannot, in law, be equated with the receipt of a request for arbitration so as

    to satisfy the requirement of Section 21 of the Act.

    30. This Court further notes that the Respondent, in its email dated

    01.06.2020, while denying the Petitioner’s claims, made a specific reference

    to Clauses 14 and 15 of Annexure II of the General Conditions of Contract

    as being the relevant clauses governing dispute resolution between the

    parties. The Petitioner, on the other hand, has preferred the present

    petition by invoking arbitration under Clause 26 of the same Annexure II of

    the tender document dated 16.12.2017. This divergence is significant in

    two respects. First, it establishes that both parties acknowledge the
    15

    existence of an arbitration mechanism under the General Conditions of

    Contract, and therefore the arbitrability of the underlying disputes is, in

    principle, not in question. The Respondent is bound by its own

    acknowledgment in the email dated 01.06.2020 to the extent that it

    conceded the arbitral route as the appropriate forum for resolution of

    disputes. Second, and more importantly, the disagreement as to the

    applicable clause and tender document, further reinforces the finding that

    the invocation as made in the notice dated 30.06.2022 lacks the necessary

    clarity and precision that a valid Section 21 notice demands. The Petitioner,

    having been put on notice by the Respondent’s email of 01.06.2020 that

    the Respondent understood the applicable dispute resolution clauses to be

    different from those subsequently invoked, was obliged to address this

    discrepancy and establish the correct applicable clause, either at the stage

    of the invocation notice or in the petition. It has done neither. The complete

    text of Annexure II to the General Conditions of Contract has also not been

    placed before this Court, thereby preventing any examination of whether

    Clause 26 and Clauses 14 and 15 operate independently, in overlap, or in

    conflict with each other.

    31. To summarise, this Court finds that the Petitioner has failed to establish

    two essential jurisdictional prerequisites for the exercise of power under

    Section 11 of the Act. First, the Petitioner has not established that the work

    orders from which the alleged disputes arise form part of or are governed by

    the tender document dated 16.12.2017 containing the arbitration clause

    invoked, and the inconsistency between the petition and the invocation

    notice on this foundational question is irreconcilable on the present record.

    Second, the notice dated 30.06.2022 does not fulfil the requirements of a
    16

    valid Section 21 notice inasmuch as it does not expressly invoke arbitration

    under the Act, does not identify the correct arbitration clause, refers to a

    different tender document from the one relied upon in the petition, and is

    not demonstrated to have been received by the Respondent. The only notice

    admittedly received by the Respondent is a demand notice which is legally

    insufficient to constitute a commencement of arbitration under Section 21

    of the Act. These two threshold infirmities are not isolated, they are

    mutually reinforcing, and together paint a picture of a fundamentally

    defective invocation that cannot sustain the exercise of jurisdiction under

    Section 11 of the Act.

    32. In view of the foregoing, the present petition stands dismissed. However, in

    light of the fact that both parties have, in their respective communications,

    acknowledged that the disputes inter se are liable to be resolved through

    arbitration in terms of the General Conditions of Contract, such dismissal

    shall not preclude the Petitioner from initiating fresh arbitral proceedings in

    accordance with law. It is clarified that, in the event the Petitioner issues a

    notice invoking arbitration under Section 21 of the Act, the question of

    limitation shall be considered and decided independently, in accordance

    with law, at the appropriate stage.

    33. The present petition is accordingly dismissed in the aforesaid terms. All

    pending applications, if any, shall also stand dismissed.

    (GAURANG KANTH, J.)

    SAKIL AMED P.A.



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here