M/S. Lord Shiva Enterprises & Anr vs The Union Of India & Ors on 3 July, 2026

    0
    9
    ADVERTISEMENT

    Calcutta High Court (Appellete Side)

    M/S. Lord Shiva Enterprises & Anr vs The Union Of India & Ors on 3 July, 2026

    Author: Shampa Sarkar

    Bench: Shampa Sarkar

    03.07.2026
    Court No. 12
     Item No. 05
      Sandip
                             IN THE HIGH COURT AT CALCUTTA
                              CIVIL APPELLATE JURISDICTION
                                    APPELLATE SIDE
    
                                   M.A.T. 919 of 2026
                                 IA No : CAN 1 of 2026
    
                        M/s. Lord Shiva Enterprises & Anr.
                                     -Versus-
                                 The Union of India & Ors.
    
                        Mr. Sirsanya Bandopadhyay,
                        Ms. Utsa Podder,
                        Ms. Sneha Sarkar
                                             .....for the appellants.
                        Mr. Biswanath Chatterjee,
                        Ms. Sayonee Boral,
                        Mr. Sobhan Kr. Poithak
                               ....for the respondent nos. 2 & 3.

    1) The appeal arises out of an order dated
    May 14, 2026, passed in W.P.A. 11099 of 2026.

    2) By the order impugned, the learned Court
    found that balance of convenience and
    inconvenience, did not tilt in favour of the
    appellants, so as to warrant an interim
    protection.

    SPONSORED

    3) His Lordship was of the, prima facie, view
    that, in the absence of any illegality or
    arbitrariness in the action of the tendering
    authority, the interim protection sought for in
    the writ petition could not be granted.

    4) The writ petition was preferred by the
    appellants, being aggrieved by a decision dated
    April 15, 2026, by which the contract of the
    appellants with the respondent no. 2 had been
    terminated on the ground that the change of
    names/registrations of the tank trucks had not
    been obtained within 120 days from the date of
    the receipt of the LOA by the appellants.

    2

    Further, a sum of Rs. 2 toward EMD was also
    forfeited.

    5) The contract was entered into between the
    appellants and the respondent no. 2 (HPCL).
    The letter of acceptance was issued on August
    21, 2025. The vehicles/tank truck which were
    involved, were not owned by the appellants.
    HPCL permitted the appellants to participate in
    the tender process, under the ATS framework.
    The clause provided that a person who had an
    agreement for sale with a truck owner, could
    participate in the tender process. If the bid was
    accepted by the tendering authority, the
    transfer of the vehicles ought to be effected
    within four months from the issuance of letter
    of acceptance. The appellants had time till
    December 19, 2025 to complete the formalities
    with regard to registration and transfer of the
    tank truck in the name of the appellants. This
    requirement was a part of the tender condition
    and had been provided under Clause 5 of the
    corrigendum 3. The same is quoted below:-

    “Clause 5 of the Corrigendum No. 3

    published on April 4, 2025. The clause is
    quoted below:-

    “In case the bidder fails to submit the
    required documents with change of
    name, etc. within 4 months of issue of
    LOI, suitable penal action shall be
    taken, which may include EMD
    forfeiture, caution money forfeiture,
    termination of order of such TTs and
    blacklisting of such TTs. Under no
    circumstances will the
    abovementioned timeline be extended.
    In such cases, the contracting
    Corporation reserves the right and
    shall be at liberty to induct TTs as per
    the methodology mentioned in the
    tender to fulfil the shortfall arising
    thereof.”

    3

    6) A show cause notice was issued to the
    appellants on February 23, 2026. The tank
    truck was not put to use thereafter. When the
    authority did not proceed with the show cause
    notice, a writ petition was filed. While disposing
    of the writ petition, another learned single
    Judge directed HPCL to decide the matter on
    the basis of the reply filed by the appellants. At
    that juncture, the appellants were not
    protected by any interim order. Subsequently,
    the order of termination of the contract was
    passed and the writ petition was filed, the EMD
    was forfeited. His Lordship was of the view that,
    the actions of the authorities, prima facie, did
    not indicate any arbitrariness and mala fide
    intent.

    7) Upon taking note of the sequence of
    events and the submissions made by the
    respective parties, His Lordship was of the view
    that a speaking order had been passed by the
    authority. The principles of natural justice were
    followed. Adequate opportunity was granted to
    the appellants to put forward their case. Thus,
    His Lordship held that, the question whether
    the termination was illegal or contrary to the
    terms and conditions of the contract, or
    whether HPCL’s use of the tank truck beyond,
    120 days, would amount to waiver of clause 5
    of corrigendum 3, would be decided at the final
    hearing of the writ petition.

    8) Mr. Sirsanya Bandopadhyay, learned
    advocate for the appellants relies on a decision
    of the Division Bench presided by one of us
    (Shampa Sarkar, J.), in support of the
    contention that, an interim protection should
    4

    be given to the appellants to continue with the
    contract, with a further direction upon HPCL to
    allow the tank trucks of the appellants to
    continue operation.

    9) We are of the view that, the facts which
    led to the order on May 21, 2026 in MAT 878 of
    2026, do not squarely apply here. In that
    matter, IOCL had continued to utilize the tank
    trucks even during the pendency of the show
    cause notice and the writ court also allowed the
    trucks to continue their operation. Thus, the
    Division Bench, upon balancing the
    convenience and inconvenience of the parties
    held that, the appellants therein were entitled
    to an interim protection for four weeks, so that
    the business would not suffer.

    10) The Bench held that, in the event IOCL
    was permitted to stop utilization of the tank
    trucks of the appellants, IOCL would have to
    induct other bidders to complete the work.
    Whereas, if the appellants were allowed to
    continue the work and be granted a month’s
    time to approach the appropriate forum for a
    protective order, in view of the agreed forum of
    an arbitral tribunal, IOCL would not suffer any
    loss.

    11) In this case, HPCL stopped utilizing the
    vehicle from February 2023. Four months have
    elapsed since then. Directing HPCL to use the
    tank truck of the appellants, would amount to
    putting the clock back. This cannot be
    permitted, because HPCL must have made an
    interim arrangement to procure tank trucks
    from third parties.

    12) Under such circumstances, the prayer
    made by Mr. Bandopadhyay that the appellants
    5

    may be allowed to continue with their business
    for a period of four weeks, is not accepted by
    us. Moreover, with regard to the prayer before
    the learned writ Court for stay of the
    termination, we are of the view that, the
    termination order had taken effect, and as
    such, the validity of the decision of the
    authority in terminating the contract, must be
    decided by the writ Court upon exchange of
    affidavits.

    13) Time to file the opposition is extended by a
    period of three weeks. Reply within one week
    thereafter. Liberty to mention for urgent
    hearing of the matter.

    14) Accordingly, the appeal and the connected
    application are disposed of.

    15) The disposal of the appeal without any
    interference, will not prevent the appellants
    from raising all the questions which have been
    raised in this appeal. All points are left open to
    be decided by the writ Court.

    16) Urgent photostat certified copy of the
    order, if applied for, be given to the parties,
    upon usual undertakings.

    (Shampa Sarkar, J.)

    (Smita Das De, J.)



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here