M/S Galore Infotech Pvt. Ltd vs M/S Sew Krishnagar Bahrampore Highways … on 2 April, 2026

    0
    38
    ADVERTISEMENT

    Telangana High Court

    M/S Galore Infotech Pvt. Ltd vs M/S Sew Krishnagar Bahrampore Highways … on 2 April, 2026

    Author: K. Lakshman

    Bench: K. Lakshman

    IN THE HIGH COURT FOR THE STATE OF TELANGANA
                   AT: HYDERABAD
    
               HON'BLE SRI JUSTICE K. LAKSHMAN
    
          ARBITRATION APPLICATION No. 161 OF 2025
    
                            Date: 02 -04-2026
    
    Between in ARB APPL .No.161 of 2025:
    
    M/S Galore Infotech Pvt.Ltd                          ...Applicant
    
                                     And
    
    M/s SEW Krishnagar Bahrampore
    Highways Ltd                                       .....Respondent
    
    This Court passed the following:-
    
                                  ORDER
    

    Heard Mr. M. Govind Reddy, learned counsel representing

    Mr. E. Varun Kumar, learned counsel for the Applicant on the

    SPONSORED

    maintainability of the present application filed under section 14

    read with sections 15 and 11 of the Arbitration and Conciliation

    Act, 1996 ( for short, ‘the Act, 1996’).

    2. The present Arbitration Application arises out of disputes

    between the Applicant, M/s. Galore Infratech Private Limited, and

    the Respondent, M/s. SEW Krishnagar Bahrampore Highways

    Limited, in relation to a work order-cum-agreement dated
    2
    KL,J
    AA_161_2025

    26.09.2012 executed for the supply of aggregates in connection

    with a national highway project.

    3. The genesis of the dispute traces back to June 2012, when

    a group company of the Applicant, namely M/s. Balajee Infratech

    & Constructions Pvt. Ltd., received an enquiry from SEW

    Infrastructure Limited for participation in the project concerning

    the four-laning of the Krishnagar-Baharampore section of NH-34

    in the State of West Bengal under the NHDP Phase-III on DBFOT

    (Annuity) basis. Pursuant to negotiations, a Letter of Intent (LOI)

    dated 13.07.2012 was issued, initially in favour of the said group

    company. Subsequently, upon mutual understanding, the work was

    transferred to the Applicant company, and a fresh offer was

    submitted on 07.09.2012, followed by issuance of a Work Order

    dated 26.09.2012 in favour of the Applicant.

    4. Under the terms of the Work Order, the Applicant was

    obligated to install two crushing plants of 200 TPH capacity and to

    supply approximately 11,00,000 metric tons of crushed stone

    within a stipulated period of one year. In compliance, the Applicant

    mobilized substantial resources, installed the required machinery,
    3
    KL,J
    AA_161_2025

    obtained necessary governmental permissions, and commenced

    production from September/October 2012.

    5. It is the case of the Applicant that despite fulfilling its

    contractual obligations, the Respondent failed to lift the aggregates

    produced, resulting in accumulation of stock at the site, disruption

    of production, and incurring of additional costs such as re-handling

    charges. The Applicant further alleges that the Respondent

    defaulted in making timely payments of monthly bills, leading to

    substantial outstanding dues. The situation allegedly compelled the

    Applicant to demobilize its machinery and discontinue operations,

    thereby suffering significant financial losses.

    6. Subsequently, disputes arose between the parties

    regarding non-payment of dues and damages for breach of

    contract. The Applicant quantified its claim at approximately

    Rs.12.21 crores towards losses suffered. Legal notices were issued

    demanding payment; however, the Respondent failed to comply.

    7. Invoking the arbitration clause contained in the Work

    Order-cum-Agreement, the Applicant initially nominated a sole

    arbitrator. The Respondent, however, disputed the same and
    4
    KL,J
    AA_161_2025

    unilaterally appointed another arbitrator Sri V.V. Raghavan, a

    retired District & Sessions Judge was appointed, according to the

    terms of the contractual clause vesting such power in its Managing

    Director. The Applicant raised objections regarding the

    independence and impartiality of the appointed arbitrator under

    Section 12 of the Act, 1996. The said arbitrator eventually recused

    himself, and thereafter, Respondent has appointed Sri Dasari

    Sambaiah, as a substitute Arbitrator.

    8. The disputes between the parties were earlier subject

    matter of Arbitration Application No.110 of 2016 filed by the

    Applicant herein under Section 11(6) of the Act, 1996, wherein the

    Applicant sought appointment of an independent Arbitrator. The

    said application was dismissed by this Court by order dated

    09.06.2020, upholding the appointment made in terms of the

    contractual clause and holding that the arbitration was governed by

    the pre-Amendment Act, 2015 regime.

    9. The said order was carried in Special Leave Petition (C)

    No.13500 of 2020 before the Hon’ble Supreme Court, which came

    to be dismissed by order dated 15.03.2024, thereby affirming the
    5
    KL,J
    AA_161_2025

    judgment of this Court and rendering the issue final between the

    parties.

    10. Aggrieved by the unilateral appointment mechanism and

    the continuation of arbitral proceedings, the Applicant approached

    this Court by filing the present arbitration under Section 14, read

    with Sections 15 and 11 of the Act, 1996, seeking appropriate

    reliefs including termination of the mandate of the arbitrator and

    appointment of an independent arbitrator.

    11. The present Arbitration Application, therefore, arises in

    the backdrop of the said proceedings, centering around the validity

    of the arbitral process, the legality of unilateral appointment of the

    arbitrator, and the consequential rights of the parties under the

    Arbitration and Conciliation Act, 1996.

    12. CONTENTIONS OF THE APPLICANT

    i) The Applicant assails the impugned proceedings primarily

    on the ground that the arbitral process initiated by the Respondent

    is vitiated in law and contrary to the mandate of the Act, 1996.

    ii) At the outset, it is contended that the Respondent has

    exercised unilateral control over the constitution of the Arbitral
    6
    KL,J
    AA_161_2025

    Tribunal by invoking the contractual clause empowering its

    Managing Director to appoint sole arbitrator. According to the

    Applicant, such unilateral appointment strikes at the root of the

    principles of neutrality, independence, and impartiality of the

    arbitral process, which are foundational to arbitration law. The

    Applicant submits that once disputes had arisen between the

    parties, the Respondent, being an interested party, could not have

    retained exclusive authority to appoint the arbitrator.

    iii) It is further contended that the initial appointment made

    by the Respondent was itself legally unsustainable, and although

    the said arbitrator subsequently recused, the Respondent again

    proceeded to appoint a substitute arbitrator unilaterally. The

    Applicant submits that such successive appointments by one party

    demonstrate a continued dominance over the arbitral process and

    render the proceedings inherently biased and contrary to Sections

    12 and 18 of the Act.

    iv) The Applicant also asserts that it had raised specific

    objections under Section 12(3) of the Act, 1996 regarding

    justifiable doubts as to the independence and impartiality of the
    7
    KL,J
    AA_161_2025

    arbitrator. These objections, according to the Applicant, were not

    adequately addressed, thereby necessitating judicial intervention

    under Sections 14 and 15 of the Act, for termination of the

    arbitrator’s mandate.

    v) Another principal contention advanced is that once the

    originally appointed arbitrator recused, the Respondent forfeited its

    contractual right, if any, to appoint a substitute arbitrator,

    particularly in light of the disputes having crystallized and the

    Applicant having expressed lack of confidence in such unilateral

    mechanism. It is argued that, in such circumstances, the

    appointment ought to have been made through the intervention of

    the Court under Section 11 of the Act, to ensure fairness and

    neutrality.

    vi) The Applicant further submits that the Respondent has

    acted in breach of the statutory scheme introduced by the Act,

    2015, which emphasizes independence and impartiality of

    arbitrators and restricts party autonomy where it conflicts with

    these principles. The unilateral appointment procedure, it is
    8
    KL,J
    AA_161_2025

    contended, is hit by the ineligibility provisions and the broader

    doctrine against bias.

    vii) In addition, the Applicant contends that the arbitral

    proceedings themselves are liable to be set aside or stayed, as they

    are being conducted pursuant to an invalid constitution of the

    Tribunal. It is argued that continuation of such proceedings would

    cause grave prejudice to the Applicant and defeat the very purpose

    of a fair adjudicatory mechanism.

    viii) Lastly, the Applicant submits that the Court, while

    exercising jurisdiction in the present proceedings, ought to ensure

    that the arbitral tribunal is constituted in a manner consistent with

    the principles of natural justice, equality of parties, and statutory

    safeguards, and accordingly seeks termination of the mandate of

    the unilaterally appointed arbitrator and appointment of an

    independent arbitrator through the Court.

    13.LAW AND ANALYSIS

    i) The principal question that arises for consideration in the

    present proceedings is whether the application filed under Sections
    9
    KL,J
    AA_161_2025

    14 read with Sections 11 and 15 of the Act, 1996 is maintainable in

    the facts and circumstances of the case.

    ii) At the outset, it is necessary to advert to the prior

    litigation between the parties, which has a direct bearing on the

    issue at hand. The Applicant had earlier invoked the jurisdiction of

    this Court by filing an Arbitration Application No.110 of 2016

    under Section 11(6) of the Act, seeking appointment of an

    independent arbitrator in substitution of the arbitrator appointed by

    the Respondent in terms of the Work Order-cum-Agreement dated

    26.09.2012.

    iii) By judgment dated 09.06.2020 in Arbitration

    Application No. 110 of 2016, this Court declined to interfere

    with the appointment so made and upheld the contractual

    mechanism of appointment. This Court, upon a detailed

    consideration of the statutory scheme and the law declared by the

    Hon’ble Supreme Court, held that the arbitration agreement in

    question was governed by the pre-Amendment Act, 2015 regime

    and that the arbitral proceedings had commenced prior to the

    coming into force of the Amendment Act. It was further held that
    10
    KL,J
    AA_161_2025

    the provisions introduced by the Arbitration and Conciliation

    (Amendment) Act, 2015, including Section 12(5), would not apply

    retrospectively so as to invalidate the agreed procedure of

    appointment.

    iv) The said judgment has attained finality. The Special

    Leave Petition vide SLP (C) No.13500 of 2020 preferred by the

    Applicant came to be dismissed by the Hon’ble Supreme Court by

    order dated 15.03.2024, observing that it was not inclined to

    interfere with the impugned judgment and order passed by this

    Court.

    v) Thus, the validity of the unilateral appointment

    mechanism contained in the agreement as also the applicability of

    the pre-amendment regime, stands conclusively determined inter

    partes.

    vii) The Applicant, thereafter, invoked the provisions of

    Sections 12 and 13 of the Act, seeking recusal of the Arbitrator on

    the ground of alleged bias. The said application came to be

    rejected, and the statutory scheme, which contemplates
    11
    KL,J
    AA_161_2025

    continuation of the arbitral proceedings subject to challenge under

    Section 34, was reiterated.

    viii) In the aforesaid backdrop, the present proceedings

    under Sections 14, read with Sections 11 and 15 fall for

    consideration.

    ix) Section 14 of the Act, provides for termination of the

    mandate of an arbitrator where he becomes de jure or de facto

    unable to perform his functions or fails to act without undue delay.

    The scope of the provision is narrow and is confined to situations

    where the arbitrator suffers from a legal or factual incapacity which

    renders continuation of the mandate impossible. The provision

    cannot be invoked as a substitute for challenging the validity of the

    appointment itself.

    ix) Section 15 of the Act, which deals with substitution of an

    arbitrator, is consequential in nature and comes into operation only

    upon termination of the mandate under Section 14 or in

    circumstances expressly contemplated therein. It does not confer an

    independent right to seek reconstitution of the arbitral tribunal.
    12

    KL,J
    AA_161_2025

    x) The contention of the Applicant, though couched in the

    language of Sections 14 and 15, is in substance a challenge to the

    very appointment of the Arbitrator in terms of the agreement. Such

    a challenge, having been raised and negatived in the earlier round

    of litigation, cannot be permitted to be re-agitated under the guise

    of the present proceedings.

    xi) The invocation of Section 11 of the Act, is equally

    misconceived. Once an arbitrator has been appointed in accordance

    with the agreed procedure and such appointment has been upheld

    by this Court, the jurisdiction under Section 11 stands exhausted

    and cannot be invoked repeatedly on the same grounds.

    xii) In SP Singla Constructions Pvt. Ltd. v. State of

    Himachal Pradesh1, the Hon’ble Supreme Court, while dealing

    with the applicability of the Arbitration and Conciliation

    (Amendment) Act, 2015, held that the amended provisions would

    not apply to arbitral proceedings which had commenced prior to

    the coming into force of the Amendment Act, unless the parties

    otherwise agree. The Court emphasized that the contractual

    mechanism of appointment and the legal regime governing such
    1
    (2019) 2 SCC 488
    13
    KL,J
    AA_161_2025

    proceedings must be tested in accordance with the un-amended Act

    where the arbitration had already commenced.

    xiii) Similarly, in M/s. Shree Vishnu Constructions v. The

    Engineer-in-Chief2, the Hon’ble Supreme Court, following the

    decision in BCCI v. Kochi Cricket Pvt. Ltd 3., elaborated upon

    Section 26 of the Amendment Act and held that the amendment is

    prospective in nature. It was held that while arbitral proceedings

    commenced prior to the Amendment Act would continue to be

    governed by the un-amended provisions, even court proceedings

    “in relation to” such arbitral proceedings must be examined in light

    of the stage at which they are initiated, thereby reaffirming the

    non-retrospective application of the amended provisions.

    xiv) In Central Organization for Railway Electrification

    v. ECI-SPIC-SMO-MCML (JV) 4, the Hon’ble Supreme Court,

    while considering the issue of unilateral appointment of arbitrators,

    reiterated the importance of independence and impartiality in

    arbitral appointments. However, the Court recognized that the legal

    principles evolved under the amended regime operate prospectively

    2
    (2023) 8 SCC 329
    3
    (2018) 6 SCC 287
    4
    (2025) 4 SCC 641
    14
    KL,J
    AA_161_2025

    and would not unsettle arbitral proceedings commenced prior to the

    2015 Amendment. Thus, the decision does not invalidate

    appointments made under pre-amendment agreements where the

    arbitral process had already been set in motion.

    14) To conclude while the post-amendment jurisprudence

    has evolved to strengthen the principles of neutrality and

    independence, the same cannot be applied retrospectively so as to

    invalidate an appointment which has already been upheld and has

    attained finality between the parties. The legal position in this

    regard is no longer res integra.

    15. In the present case, the arbitration agreement is dated

    26.09.2012, the arbitral proceedings had commenced prior to the

    2015 Amendment; the validity of the appointment mechanism has

    already been upheld by this Court in Arbitration Application

    No.110 of 2016; the said finding has attained finality upon

    dismissal of the Special Leave Petition (SLP) by the Supreme

    Court; and the Applicant has already availed the statutory remedy

    under Sections 12 and 13 of the Act.

    15

    KL,J
    AA_161_2025

    16. No material has been placed on record to demonstrate

    that the arbitrator has become de jure or de facto unable to perform

    his functions or has failed to act without undue delay so as to

    attract Section 14 of the Act.

    17. In such circumstances, the present proceedings, in

    substance, constitute an attempt to reopen and re-agitate an issue

    which stands concluded between the parties and to indirectly

    challenge the constitution of the arbitral tribunal. Such an exercise

    is clearly impermissible, both on the principles of finality of

    judicial determinations and under the statutory scheme of the Act,

    which mandates minimal judicial interference in arbitral

    proceedings.

    18. Accordingly, this Court holds that the application filed

    under Section 14 read with Sections 15 and 11 of the Act, 1996 is

    not maintainable in law. The arbitral proceedings shall, therefore,

    continue in accordance with law, leaving it open to the Applicant

    including bias and raise all the grounds and contentions which it

    has raised in the present Application in all the consequential

    proceedings.

    16

    KL,J
    AA_161_2025

    19. In the light of the aforesaid discussion, this Arbitration

    Application dismissed as not maintainable. No order as to costs.

    As a sequel thereto, miscellaneous petitions, if any, pending

    in this arbitration application shall stand closed.

    
    
    
                                           _________________________
                                            JUSTICE K. LAKSHMAN
    Date:     02 .04.2026
    Vvr.
     



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here