M/S Fortuna Constructions India Pvt Ltd vs Smt. Shamalamma on 20 July, 2026

    0
    3
    ADVERTISEMENT

    Karnataka High Court

    M/S Fortuna Constructions India Pvt Ltd vs Smt. Shamalamma on 20 July, 2026

                                             -1-
                                                       COMAP No. 137 of 2024
                                                   C/W COMAP No. 190 of 2024
    
    
                                                                    ND
                                                       RESERVED ON 22    APRIL 2026
    
                        IN THE HIGH COURT OF KARNATAKA AT BENGALURU
    
                             DATED THIS THE 20TH DAY OF JULY, 2026
    
                                           PRESENT
                          THE HON'BLE MR. VIBHU BAKHRU, CHIEF JUSTICE
                                             AND
                            THE HON'BLE MR. JUSTICE C.M. POONACHA
                              COMMERCIAL APPEAL NO. 137 OF 2024
                                             C/W
                              COMMERCIAL APPEAL NO. 190 OF 2024
    
    
                   IN COMAP No.137/2024
    
                   BETWEEN:
    
                   1.   M/S FORTUNA CONSTRUCTIONS (INDIA) PVT LTD
                        HAVING OFFICE AT
                        NO.184, FORTUNA HOUSE
                        OUTER RING ROAD, OPP. NCERT BSK
                        3RD STAGE, BANASHANKARI
                        BANGALORE - 560 085
    Digitally
    signed by           REPRESENTED BY ITS MANAGING DIRECTOR
    SRIDEVI S
                        MR. PADMAIAH VUPPU
    Location:
    High Court                                              ...APPELLANT
    of Karnataka
                   (BY SRI DHYAN CHINNAPPA, SENIOR ADVOCATE FOR
                   SRI AJIT P.B., ADVOCATE &
                   SRI THONTADHARYA R.K, ADVOCATE)
    
                   AND:
    
                   1.     SMT. SHAMALAMMA
                          W/O LATE A.N. KRISHNA MURTHY
                          AGED ABOUT 78 YEARS
                               -2-
                                        COMAP No. 137 of 2024
                                    C/W COMAP No. 190 of 2024
    
    
    
    
    2.     SRI K. NATARAJ
           S/O LATE A.N. KRISHNA MURTHY
           AGED BOUT 54 YEARS
    
    3.     MASTER N AKHILESH
           S/O K NATARAJ
           AGED ABOUT 18 YEARS,
    
    4.     MASTER N ANIL
           S/O K NATARAJ
           AGED ABOUT 15 YEARS
           MINOR
           REPRESENTED BY HIS
           FATHER AND NATURAL GUARDIAN
           MR K. NATARAJ
    
    5.     SRI K GOPALA GOWDA
           S/O LATE A N KRISHNA MURTHY
           AGED ABOUT 44 YEARS
           SINCE DECEASED BY LRS
    
    5(a)   SMT KAVITHA G
           W/O LATE K GOPALA GOWDA
           AGED ABOUT 38 YEARS
    
    5(b). MASTER ARAYAN A.G.
          S/O LATE K GOPALA GOWDA
          AGED ABOUT 3 YEARS
    
    6.     MASTER ASHWIN G.A
           S/O K. GOPALA GOWDA
           AGED ABOUT 13 YEARS
    
           BOTH 5(b) & 6
           MINOR REPRESENTED BY
                               -3-
                                        COMAP No. 137 of 2024
                                    C/W COMAP No. 190 of 2024
    
    
         THEIR MOTHER AND
         NATURAL GUARDIAN
         SMT. KAVITHA K.
         RESPONDENT No.5(a)

    7. SMT. JAYALAKSHMAMMA
    D/O LATE A.N. KRISHNAMURTHY
    AGED ABOUT 59 YEARS

    8. SMT. AMMAJAMMA
    D/O LATE A.N. KRISHNA MURTHY
    AGED ABOUT 57 YEARS

    SPONSORED

    9. SMT. HEMALATHA
    D/O LATE A.N. KRISHNAMURTHY
    AGED ABOUT 49 YEARS

    ALL ARE RESIDING AT
    AVALAHALLI VILLAGE
    SINGANAYAKANAHALLI POST
    YELAHANKA HOBLI
    BANGALORE NORTH TALUK
    BANGALORE DISTRICT – 560 064
    …RESPONDENTS

    (BY SRI VIVEK REDDY, SENIOR ADVOCATE ALONG WITH
    SRI T.M. VENKATA REDDY, ADVOCATE
    FOR C/RESPONDENT)

    THIS COMMERCIAL APPEAL IS FILED UNDER SECTION
    13(1-A) OF COMMERCIAL COURTS ACT, READ WITH ORDER 37
    (1) (C) OF ARBITRATION & CONCILIATION ACT PRAYING TO
    CALL FOR RECORDS OF THE PROCEEDINGS IN COM.
    A.P.NO.98/2023 ON THE FILE OF THE LEARNED LXXXIX
    ADDITIONAL CITY CIVIL & SESSIONS JUDGE, BENGALURU,
    (COMMERCIAL COURT) (CCH 90) AND SET ASIDE THE
    -4-
    COMAP No. 137 of 2024
    C/W COMAP No. 190 of 2024

    JUDGMENT DATED 30/01/2024, PASSED IN
    COM.A.P.NO.98/2023 ON THE FILE OF THE LEARNED LXXXIX
    ADDITIONAL CITY CIVIL & SESSIONS JUDGE, BENGALURU,
    (COMMERCIAL COURT) (CCH 90) (ANNEXURE A) & ETC.

    IN COMAP NO. 190/2024

    BETWEEN:

    1. SMT. SHAMALAMMA
    W/O LATE A.N. KRISHNA MURTHY
    AGED ABOUT 79 YEARS

    2. SRI K. NATARAJ
    S/O LATE A.N. KRISHNA MURTHY
    AGED ABOUT 56 YEARS

    3. MASTER N. AKHILESH
    S/O K. NATARAJ
    AGED ABOUT 23 YEARS

    4. MASTER N ANIL
    S/O K. NATARAJ
    AGED ABOUT 17 YEARS
    MINOR REP. BY HIS FATHER AND
    NATURAL GUARDIAN
    MR K. NATARAJ

    5. SMT. KAVITHA G
    W/O LATE K GOPALA GOWDA
    AGED ABOUT 37 YEARS

    6. MASTER ARYAN A.G.
    S/O LATE K. GOPALA GOWDA
    AGED ABOUT 3 YEARS
    -5-
    COMAP No. 137 of 2024
    C/W COMAP No. 190 of 2024

    7. MASTER ASHWIN G.A.
    S/O K GOPALA GOWDA
    AGED ABOUT 15 YEARS
    MINOR REPRESENTED BY HIS MOTHER
    AND NATURAL GUARDIAN
    SMT. KAVITHA G

    8. SMT. JAYALAKSHMAMMA
    D/O LATE A.N. KRISHNA MURTHY
    AGED ABOUT 58 YEARS

    9. SMT AMMAJAMMA
    D/O. LATE A.N. KRISHNA MURTHY
    AGED ABOUT 58 YEARS

    10. SMT. HEMALATHA
    D/O LATE A.N. KRISHNA MURTHY
    AGED ABOUT 50 YEARS

    ALL ARE RESIDING AT
    AVALAHALLI VILLAGE
    SINGANAYAKANAHALLI POST
    YELAHANKA HOBLI AND TALUK
    BANGALORE DISTRICT – 560 064
    …APPELLANTS

    (BY SRI VIVEK REDDY, SENIOR ADVOCATE A/W
    SRI T.M. VENKATA REDDY, ADVOCATE )

    AND:

    1. M/S FORTUNA CONSTRUCTIONS (INDIA) PVT. LTD.

    HAVING ITS OFFICE AT NO.184
    FORTUNA HOUSE, OUTER RING ROAD
    OPP. NCERT, BSK 3RD STAGE
    BANASHANKARI
    -6-
    COMAP No. 137 of 2024
    C/W COMAP No. 190 of 2024

    BANGALORE – 560 085
    REP. BY ITS MANAGING DIRECTOR
    MR. PADMAIAH VUPPU

    2. MR. PADMAIAH VUPPU
    S/O ANKAIAH VUPPU
    AGED ABOUT 52 YEARS
    NO.184, FORTUNA HOUSE
    OUTER RING ROAD
    OPP: NCERT BSK 3RD STAGE
    BANASHANKARI
    BANGALORE – 560 085
    …RESPONDENTS

    (BY SRI DHYAN CHINNAPPA, SENIOR ADVOCATE FOR
    SRI AJIT P.B., ADVOCATE &
    SRI THONTADHARYA R.K, ADVOCATE)

    THIS COMMERCIAL APPEAL IS FILED UNDER SECTION
    13 OF COMMERCIAL COURTS ACT, READ WITH ORDER 37 (1)
    (C) OF ARBITRATION & CONCILIATION ACT PRAYING TO SET-
    ASIDE THE JUDGMENT DATED: 30/01/2024 IN COM. A.P.
    NO.128/2023 (CCH:90) PASSED BY THE LXXXIX ADDL. CITY
    CIVIL & SESSIONS JUDGE AT BENGALURU, AT ANNEXURE-A &
    ETC.

    THESE COMMERCIAL APPEALS HAVING BEEN HEARD
    AND RESERVED FOR JUDGMENT, COMING ON FOR
    PRONOUNCEMENT THIS DAY, JUDGMENT WAS
    PRONOUNCED AS UNDER:

    CORAM: HON’BLE MR. VIBHU BAKHRU, CHIEF JUSTICE
    and
    HON’BLE MR. JUSTICE C.M. POONACHA
    -7-
    COMAP No. 137 of 2024
    C/W COMAP No. 190 of 2024

    C.A.V. JUDGMENT
    (PER: HON’BLE MR. VIBHU BAKHRU, CHIEF JUSTICE)

    1. These appeals have been preferred under Section 37(1)(c) of

    the Arbitration and Conciliation Act, 1996 [the A&C Act] read with

    Section 13(1A) of the Commercial Courts Act, 2015, assailing a

    common judgment dated 30.01.2024 [‘the Impugned Judgment’]

    passed by the learned LXXXIX Additional City Civil and Sessions

    Judge, Bengaluru [‘the Commercial Court’], in two connected

    petitions under Section 34 of the Act, being COM.A.P No.98/2023

    and COM.A.P No.128/2023. M/s Fortuna Constructions (India) Pvt.

    Ltd. [‘FCIPL’] had filed the petition, COM.A.P No.98/2023, under

    Section 34 of the A&C Act, seeking setting aside of an arbitral

    award dated 12.06.2023 [the Impugned Award] passed by an

    arbitral tribunal comprising of a sole arbitrator [Arbitral Tribunal] in

    arbitration conducted under the aegis of the Arbitration and

    Conciliation Centre (Domestic and International), Bengaluru.

    2. Smt. Shamalamma and her family members, including their

    predecessors in interest [‘the Landowners’], Respondents in

    COMAP No. 137 of 2024 and the Appellants in COMAP No. 190 of

    2024, had filed COM.A.P No.128/2023 before the learned

    Commercial Court, assailing the impugned award to the extent of
    -8-
    COMAP No. 137 of 2024
    C/W COMAP No. 190 of 2024

    the monetary award of `65,00,000/- (Rupees sixty five lakhs only) in

    favour of FCIPL. The learned Commercial Court found no grounds

    to interfere with the impugned award and, accordingly, dismissed

    the appeals by the impugned order.

    PREFATORY FACTS

    3. FCIPL, appellant in COMAP No. 137/2024 and Respondent

    No.1 in COMAP No. 190/2024, is engaged in the business of

    developing real estate. The Landowners (or their predecessors in

    interest) claim to be the absolute owners of the property bearing Sy.

    No. 118, new Sy. No. 118/1, measuring 1 Acre, situated at

    Avalahalli Village, Singanayakanahalli post, Yelahanka Hobli,

    Bangalore North Taluka, Bangalore District [the Subject Property].

    4. On 04.03.2013, the Respondent Nos.2 and 5 in COMAP

    No.137/2024, along with their late father, Mr A.N. Krishnamurthy,

    executed a Memorandum of Understanding [‘the MOU’] with FCIPL,

    agreeing to the development of the subject on a joint-venture basis.

    Acting upon the MOU, FCIPL paid goodwill of `50,00,027/- (Rupees

    fifty lakh and twenty seven only) out of an agreed sum of

    `60,00,036/- (Rupees sixty lakh and thirty six only). FCIPL also

    claims that it paid the balance of `10,00,009/- (Rupees ten lakh and

    nine only) in cash on 26.05.2014; however, the same has not been
    -9-
    COMAP No. 137 of 2024
    C/W COMAP No. 190 of 2024

    accepted by the Arbitral Tribunal. The parties agreed that the

    landowners’ share in the constructed area and the undivided

    interest in the land would be 34% and FCIPL’s share would be 66%.

    5. The Schedule Property was converted from agricultural use to

    non-agricultural residential use under the Conversion Order No.

    ALN(NAY)SR:233/2013 dated 27.03.2014.

    6. In furtherance of the MOU, FCIPL and the Landowners

    entered into a registered Joint Development Agreement dated

    26.05.2014 [the JDA] for the development of the Schedule Property

    into a residential apartment complex. FCIPL paid a refundable

    deposit of `2,00,000/- (Rupees two lakh only) to the Landowners

    and also agreed to complete the construction within 45 months from

    the date of the Sanction Plan. Simultaneously, on the same day, the

    Landowners executed a General Power of Attorney in favour of

    FCIPL [the GPA], constituting FCIPL as their true and lawful

    attorney for the purposes of the project.

    7. FCIPL claims that it commenced the work and obtained the

    Katha of the Subject Property in the name of the 2nd Respondent in

    COMAP No.137/2024. It also applied to the Bangalore Development

    Authority [the BDA] for sanction of the building plan on 17.12.2014.

    – 10 –

    COMAP No. 137 of 2024

    C/W COMAP No. 190 of 2024

    8. The National Green Tribunal [the NGT], by an order dated

    07.05.2015, directed that a setback of 15 meters be maintained

    from the edge of Raja Kaluves/ Nalas. FCIPL had sought approval

    for building plans, leaving a 10-meter buffer zone from the centre of

    the nala that runs alongside the Schedule Property. By a letter

    dated 18.07.2016, BDA informed FCIPL to furnish revised plans

    providing for the buffer zone as directed by the learned NGT.

    9. The Landowners state that despite the BDA’s letter dated

    18.07.2016, FCIPL took no steps either to obtain a modified plan or

    to apprise the Landowners of the requirement.

    10. The Landowners issued a legal notice dated 26.03.2018

    alleging delay in execution of the development and terminated the

    JDA. FCIPL responded by a letter dated 03.04.2018 and attributed

    the delay to dispute regarding the buffer zone. The NGT’s order in

    question was assailed before the Supreme Court. Thus, FCIPL

    called upon the Landowners either to await resolution of the said

    proceedings or to accord their consent to a modification of the

    sanctioned plan.

    11. The challenge to the NGT’s order was adjudicated by the

    Supreme Court in its judgment dated 05.03.2019. Thereafter, on

    – 11 –

    COMAP No. 137 of 2024

    C/W COMAP No. 190 of 2024

    14.05.2019, FCIPL addressed a letter to the BDA seeking

    reconsideration of the plan for approval, while the Landowners sent

    a representation requesting the BDA not to accord plan sanction.

    The landowners lodged a complaint against FCIPL for failing to

    rectify the objections. The Landowners also issued legal notices

    dated 23.07.2020 and 07.08.2020, which were not served due to the

    disruption occasioned by the COVID-19 pandemic and FCIPL’s

    shifting of its office.

    12. The Landowners filed an application under Section 11 of the

    A&C Act, C.M.P.No.134/2020 before this Court, which was allowed

    by an order dated 15.01.2021 and a Sole Arbitrator was appointed

    to adjudicate the disputes between the parties.

    13. The Landowners, as Claimants, filed their Statement of Claim

    seeking a declaration that the JDA was invalid and cancelled. They

    also sought an award permitting them to develop the Schedule

    Property, returning the original title documents for the Schedule

    Property, and restraining FCIPL from interfering with, alienating,

    encumbering, or creating any charge over the Schedule Property.

    14. FCIPL, as the Respondent in the arbitral proceedings, filed its

    Statement of Objection along with a Counter-Claim stating that it

    – 12 –

    COMAP No. 137 of 2024

    C/W COMAP No. 190 of 2024

    was willing to perform the obligations of the JDA and that the project

    was held up awaiting the outcome of the matter before the Supreme

    Court arising from the order of the NGT.

    15. FCIPL contended that the Claim Petition is not maintainable

    and that the claims are liable to be dismissed because the

    landowners suppressed several vital and material facts. FCIPL also

    contended that the claim petition was barred by limitation.

    16. During the pendency of the arbitral proceedings, FCIPL filed

    an application dated 09.02.2023 under Order XXVI Rule 9 of the

    Code of Civil Procedure, 1908, seeking appointment of a Court

    Commissioner to conduct a local inspection and submit a report,

    along with a sketch, as to whether a Raja Kaluve existed on either

    side of the Schedule Property, and the category thereof. By the

    order dated 12.03.2023, the learned Sole Arbitrator dismissed the

    said application, holding that it would amount to the collection of

    evidence.

    17. The arbitral proceedings culminated in the impugned award.

    The dispositive part of the Impugned Award is set out below:

    “a) The Claim of the Claimants is partly allowed

    b) The Counter-Claim of the Respondent is partly –

    allowed

    – 13 –

    COMAP No. 137 of 2024

    C/W COMAP No. 190 of 2024

    A. Ex. P1 Joint Development Agreement and
    Ex.R.5 General Power of Attorney stand cancelled
    as prayed for subject to payment of Rs.65,00,000/-
    awarded as counter-claim by the Claimants to the
    Respondent

    B. The Respondent or their agents or anybody
    claiming under or through the Respondent, are
    permanently restrained from interfering with the
    possession and enjoyment of the Schedule
    Property by the Claimants.

    C. The Claimants shall pay Rs.65,00,000/- to the
    Respondent within a period of three months from
    the date of award – failing which, the Respondent
    is at liberty to recover the same in accordance with
    law.

    c) The stamp duty is payable as per Karnataka
    Stamp Act
    .

    d) The award is signed and issued in 3 originals,
    one for record of Arbitration Centre and rest of the
    two to each of the parties”

    18. Following the Impugned Award, an application under Section

    33 of the Act was moved before the learned Sole Arbitrator seeking

    a direction that the Award be transmitted to the sub-registrar for

    registration of the cancellation of the JDA and the GPA, and for

    return of the original documents produced by the parties before the

    Arbitral Tribunal. The said application was allowed by the order

    dated 05.08.2023. Pursuant to the letter dated 10.08.2023

    addressed by the Director, Arbitration Centre, to the Sub-Registrar,

    Gandhinagar, Bengaluru, the JDA and the GPA came to be

    – 14 –

    COMAP No. 137 of 2024

    C/W COMAP No. 190 of 2024

    cancelled by the cancellation deed dated 25.08.2023 and a Nil

    Encumbrance Certificate for the period from 01.04.2023 to

    26.08.2023 was also obtained in respect of the Schedule Property.

    19. Aggrieved by the Impugned Award, FCIPL filed a petition

    under Section 34 of the A&C Act, before the Commercial Court,

    seeking to set aside the Impugned Award. FCIPL’s challenge

    proceeded principally on the grounds that the Impugned Award was

    patently illegal and opposed to the fundamental policy of Indian law

    and public policy as:

    (a) The learned Sole Arbitrator erred in granting the relief of

    cancelling the JDA and GPA dated 26/05/204 as the

    same is violative of the Contract Act and the specific

    terms of the JDA and GPA. Further, the cancellation of

    the GPA is patently illegal as the same was not prayed

    for, hence the same is liable to be set aside.

    (b) The learned Sole Arbitrator ignored vital evidences in

    concluding that the FCIPL is also liable for the breach

    of the JDA.

    (c) The learned Sole Arbitrator erred in refusing to direct

    the Landowners to pay the entire amount spent by the

    – 15 –

    COMAP No. 137 of 2024
    C/W COMAP No. 190 of 2024

    FCIPL and only allowing a sum of Rs.65,00,000/ that

    too without awarding any interest.

    20. The Landowners also filed a petition under Section 34 of the

    Act assailing the Impugned Award only insofar as it allowed FCIPL’s

    Counter-Claim and directed payment of `65,00,000/- (Rupees sixty

    five lakh only) by the Landowners to FCIPL as:

    (a) The learned Sole Arbitrator erred in allowing for

    payment of `65,00,000/- (Rupees sixty five lakh only) to

    FCIPL by the Landowners as it is bad in law, patently

    illegal and against the law on the basis of MOU, JDA,

    the terms of contract and the award itself as it

    contradicts the conditions stipulated therein.

    (b) Once the Arbitrator cancelled the JDA and GPA, the

    question of allowing the counter claim did not arise.

    21. The Commercial Court framed two points for determination,

    namely: (i) whether the parties in their respective petitions had

    made out grounds for interference; and (ii) what order ought to

    follow.

    – 16 –

    COMAP No. 137 of 2024

    C/W COMAP No. 190 of 2024

    22. Applying the well-settled limits and principles on the exercise

    of jurisdiction under Section 34 of the A&C Act, the Commercial

    Court held that neither the prayer of the Landowners to partially set

    aside the Award qua the Counter-Claim, nor the prayer of FCIPL for

    a remand for fresh adjudication of the Counter-Claim was available

    in law.

    23. The Commercial Court held that the learned Sole Arbitrator

    had rightly rejected the Landowners’ contention that the BDA was

    not the competent authority to sanction the plan, and had correctly

    appreciated the Supreme Court’s order dated 05.03.2019 modifying

    the manner of measuring the buffer zone. Further, no interference

    was required with the Arbitral Tribunal’s findings regarding the

    mutual breach by the parties; the failure of the Landowners to

    extend cooperation to FCIPL’s efforts to obtain a modified plan;

    causing hindrances, including by lodging police complaints; and

    failure on the part of FCIPL to prove the delay was wholly beyond its

    control.

    24. The Commercial Court observed that the Arbitral Tribunal had

    rightly concluded that the continuation of the JDA was not warranted

    and that the cancellation of the GPA naturally followed the

    cancellation of the JDA, as it was executed to facilitate the JDA. The

    – 17 –

    COMAP No. 137 of 2024

    C/W COMAP No. 190 of 2024

    Commercial Court further endorsed the direction restoring the

    parties to their pre-contract position by payment of `65,00,000/-

    (Rupees sixty five lakh only) to FCIPL, without interest.

    25. On the Counter-Claim, the Commercial Court held that the

    determination of the Landowners’ liability at `65,00,000/- (Rupees

    sixty five lakh only), as against the larger sum of `1,98,82,036/-

    (Rupees one crore ninety eight lakh eighty two thousand thirty six

    only) originally claimed by FCIPL, was a finding of fact arrived at

    after a meticulous consideration of the exhibits and oral evidence,

    which could not be interfered with. Regarding the question of

    limitation and misjoinder of parties, the Commercial Court held that

    the learned Arbitral Tribunal had correctly analysed the material on

    record and rightly answered both objections.

    26. The Commercial Court held that the learned Sole Arbitrator

    had assigned proper and convincing reasons in partly accepting the

    claim of the Landowners and partly allowing the Counter-Claim of

    FCIPL, and that neither party had made out grounds to set aside the

    impugned award in its entirety, or to modify it, or to remand the

    matter for fresh adjudication. Accordingly, the Commercial Court

    dismissed both Com. A.P.No.98/2023 and Com. A.P.No.128/2023.

    – 18 –

    COMAP No. 137 of 2024

    C/W COMAP No. 190 of 2024

    27. Aggrieved by the Impugned Judgment, the parties have filed

    the present appeals.

    RIVAL CONTENTIONS

    28. Sri. Dhyan Chinnappa, learned senior counsel appearing for

    FCIPL, assailed the impugned award on the solitary ground that the

    conclusion was inconsistent with the findings. He contended that

    although the findings of the Arbitral Tribunal were in favour of

    FCIPL, the Arbitral Tribunal had rendered the impugned award in

    effect acceding to the prayers made by the landowners. He

    submitted that the Arbitral Tribunal had considered that the same

    was in the interest of justice and equity. However, the arbitration

    agreement (arbitration clause in the JDA) did not empower the

    Arbitral Tribunal to act as ex aequo et bono. He referred to

    paragraph no. 77 of the impugned award and pointed out that the

    Arbitral Tribunal had expressly decided the issue regarding

    cancellation of the JDA, “in the interest of justice and equity”. He

    contended that the impugned Arbitral award had acted beyond its

    jurisdiction; therefore the impugned award was liable to be set

    aside.

    – 19 –

    COMAP No. 137 of 2024

    C/W COMAP No. 190 of 2024

    29. Mr. Reddy countered the aforesaid submissions. He referred

    to Paragraph No.58 of the impugned award and submitted that the

    Arbitral Tribunal had also found that FCIPL had defaulted in its

    obligations and thus rightly declined to allow FCIPL’s prayer for

    specific performance. He readily conceded that in view of the

    factual findings, the land owners’ challenge to the award for return

    of the funds to FCIPL would not be sustainable.

    REASONS AND CONCLUSIONS

    30. At the outset, it is relevant to bear in mind that the landowners

    were the claimants before the Arbitral Tribunal. They had filed the

    statement of claim, inter alia, praying as under:

    a) “Declare that the Joint Development
    Agreement dated 26/05/2014 in No. GNR-1-

    00597/2014-15, stored in Book No. 1, CD
    No.GNRD91, registered in the Office of Senior Sub-
    Registrar, Ganganagar (Gandhi Nagara),
    Bangalore is invalid and cancelled and to pass
    award, and consequently permit the Claimants to
    develop the Schedule Property at their will and nil
    encumbrances.

    b) Grant injunction against the respondents,
    restraining the Respondents from interfering,
    alienating or encumbering or creating any charge
    on the Schedule Property in favour of any third
    party either in part or in the form of flats.

    c) Direct the Respondents to return the original
    title documents of the Claimants Schedule Property
    including original JDA dated 26.05.2014.

    – 20 –

    COMAP No. 137 of 2024

    C/W COMAP No. 190 of 2024

    d) Grant such other relief’s as this Hon’ble court
    may deem fit in the facts and circumstances of the
    case along with by awarding the costs of the
    litigation in the interest of justice and equity.”

    31. As is apparent from the above, the landowners sought a

    declaration that the JDA is invalid and cancelled. They sought an

    award permitting development of the subject property at their will

    without any encumbrance. Additionally, they sought a direction

    restraining the FCIPL from interfering with the subject property and

    directing the return of the original documents in its possession.

    32. It would be relevant to refer to the averments made in the

    statement of claim setting out the grounds on which the aforesaid

    reliefs were claimed. The landowners stated that, under the JDA,

    FCIPL had given an undertaking to obtain approved plans to build

    apartments as required within 3 months; thereafter, start

    construction within 3 months; and complete the same within 33

    months, with a grace period of 6 months. The landowners

    contended that, as per the JDA, construction was required to be

    completed within a maximum of 45 months, a deadline that expired

    in February, 2017. They claimed that although time was of the

    essence of the contract, FCIPL had not taken steps to obtain the

    approved plan and had failed to start construction. Additionally, they

    – 21 –

    COMAP No. 137 of 2024

    C/W COMAP No. 190 of 2024

    claimed that FCIPL had not paid the goodwill amount and the

    agreed advance, but had paid a meagre `2,00,000/- (Rupees two

    lakh only) towards a refundable advance.

    33. The landowners claimed that they issued a legal notice dated

    26.03.2018 to FCIPL to comply with the conditions of the JDA and

    to cancel the same. However, FCIPL did not respond to the said

    notice. They claimed that FCIPL also failed to comply with the

    demands made in the legal notice dated 26.03.2018. Thereafter, the

    landowners issued another notice dated 23.06.2020 under clause

    26 of the JDA, and called upon the FCIPL to consent to the

    cancellation of the JDA, pay damages, and return the original

    documents. However, the said notice was returned unserved

    because FCIPL had shifted its office. The subsequent notice dated

    07.08.2020 was also returned for the same reason.

    34. The landowners alleged that FCIPL had collected crores of

    rupees from third parties by showing the subject property. But, it did

    not take any steps to raise the construction as it had no intention of

    completing the construction of the residential apartments.

    35. It is also relevant to refer to paragraph 10 of the statement of

    claims, which is set out below:

    – 22 –

    COMAP No. 137 of 2024
    C/W COMAP No. 190 of 2024

    “10. Though the Petitioners are ready and
    willing to perform their part of obligation as per
    the terms and conditions of the Joint
    Development Agreement dated: 26/05/2014,
    and Respondents are not able to do any of the
    work. That inspite of granting sufficient time,
    the Respondents are not performing their part
    of obligation Respondents have not taken any
    initiative action in the matter and thereby
    caused heavy loss to Petitioners for the last 7
    years.”

    36. It is the Landowners’ case that they were ready and willing to

    perform their obligations under the JDA, but FCIPL was unable to

    complete the works. FCIPL disputed the said claim. Thus, the

    principal dispute before the Arbitral Tribunal was (a) whether FCIPL

    had breached the terms of the agreement by not commencing the

    construction within the time stipulated; and b) whether FCIPL’s

    failure to do so was despite the Landowners being ready and willing

    to perform their obligations. The Arbitral Tribunal was also required

    to consider the allegation that FCIPL had failed to pay the amounts

    as contemplated under the JDA.

    37. FCIPL filed the statement of defence, inter alia, praying as

    under :

    “34. The Respondents pray that to dismiss the
    Claim Petition and direct the Claimants to co-
    operate for the developmental of Schedule
    Property as agreed in JOINT DEVELOPMENT

    – 23 –

    COMAP No. 137 of 2024
    C/W COMAP No. 190 of 2024

    AGREEMENT and if at all if this Hon’ble
    Arbitrator comes to the conclusion that the
    Claimants are entitle for the relief of
    cancellation of JOINT DEVELOPMENT
    AGREEMENT and return of Original
    documents and in that event, Claimants may
    be directed to return/ refund the amount
    received by them, with the expenses incurred
    on the project as shown above i.e. in all Rs.
    1,98,82,036/- (Rupees One Crore ninety eight
    Lakhs eighty two thousand thirty six only)
    together with interest at the rate of 18% p.a.
    from the date of JOINT DEVELOPMENT
    AGREEMENT, till its realization. It is submitted
    that, due to the change of usage of lands i.e.
    conversion of lands, the land value is also
    appreciated considerably and apart from
    conversion also the land value has been
    considerably increased from year 2014 and
    the Claimants are also liable to compensate
    for the same to the Respondents. Hence these
    Respondents are entitle to continue with the
    development work and for any reasons if this
    Hon’ble Arbitrator comes to the conclusion
    that the JOINT DEVELOPMENT
    AGREEMENT needs to be cancelled and in
    that event order for payment of Rs.
    1,98,82,036/- (Rupees One Crore ninety eight
    Lakhs eighty two thousand thirty six only) to
    the Respondents.”

    38. On the basis of the rival pleadings, the learned Sole Arbitrator

    framed ten issues for determination, namely:

    “1. Whether the Claimant proves that the
    Respondent has violated the terms and conditions
    of Joint Development agreement dated
    26.05.2014?

    2. Whether the Claimant proves that they are
    entitled for cancellation of Joint Development
    agreement dated 26.05.2014?

    – 24 –

    COMAP No. 137 of 2024
    C/W COMAP No. 190 of 2024

    3. Whether the Claimant proves that they are
    entitled for a declaration that the Joint Development
    agreement dated 26.05.2014 is invalid and entitled
    to develop the Schedule Property?

    4. Whether the Claimant proves that they are
    entitled for injunction, as prayed for?

    5, Whether Respondent proves that it was not able
    to complete the project due to circumstances
    beyond its control?

    6. Whether the respondent proves that the
    Claimant has committed breach of the terms and
    conditions of Joint Development agreement dated
    26.05.2014?

    7. Whether the respondent proves that they are
    entitled for an amount of Rs.1,98,82,036/- claimed
    in counter-claim?

    8. Whether the Respondents prove that the claim of
    the Claimants is barred by time?

    9. Whether the Respondents prove that the claim of
    the Claimants is bad for mis-joinder of parties?

    10. What award/ order?”

    39. The Arbitral Tribunal considered issues Nos.1, 5 and 6

    together, that is, whether the landowners proved that FCIPL had

    violated the terms of the JDA; whether FCIPL proved that it was

    unable to complete the project due to circumstances beyond its

    control; and whether the landowners had committed breach of the

    terms and conditions of the JDA.

    40. As noted above, the landowners’ case is that FCPIL had

    breached the terms and conditions is premised on the ground that

    – 25 –

    COMAP No. 137 of 2024

    C/W COMAP No. 190 of 2024

    FCPIL had failed to complete construction within the outer limit of 45

    months from the date of the JDA. The MoU dated 04.03.2013

    expressly recorded the landowners’ acknowledgement that they had

    received a sum of `50,00,027/- (Rupees fifty lakh and twenty seven

    only) from FCIPL, and that the balance amount of 10,00,009/-

    (Rupees ten lakh and nine only) would be payable at the time of

    registration of the JDA. The JDA was executed and registered on

    26.05.2014.

    41. Article 8 of the JDA, which, according to the land owners, had

    been breached by FCIPL is set out below:

    “8. COMMENCEMENT OF CONSTRUCTION
    WORK:

    8.1 The SECOND PARTY/DEVELOPER
    shall commence the construction work on the
    Schedule Property within Three months from
    the date of obtaining sanction of the building
    plan. The quality of construction shall be in
    accordance with the specifications contained
    hereunder or equivalent thereto. The quality of
    material used shall confirm to ISI codes or
    equivalent thereto.

    8.2 The FIRST PARTY/OWNER shall
    extend full co-operation to the SECOND
    PARTY/DEVELOPER in executing the project
    on the Schedule Property and completing
    construction work of the Apartment Complex.

    The FIRST PARTY/OWNER shall not create
    any impediment or obstruction in the way of
    the SECOND PARTY/DEVELOPER in
    developing or constructing the Apartment
    complex. The authorised

    – 26 –

    COMAP No. 137 of 2024

    C/W COMAP No. 190 of 2024

    agents/representatives of the FIRST
    PARTY/OWNER shall be at liberty to visit the
    construction site.

    8.3 The SECOND PARTY/DEVELOPER
    may, agreed to execute additional items of
    work as may be required by the FIRST
    PARTY/OWNER on separately and mutually
    agreed terms/and/or rates or that the FIRST
    PARTY/OWNER shall be at liberty to get any
    additional items of work done by their own
    agency only after possession is handed over
    to them by the SECOND
    PARTY/DEVELOPER.

    8.4 The SECOND PARTY/DEVELOPER
    shall have absolute right over the method,
    manner and design of construction the
    residential complex.”

    42. The Arbitral Tribunal found that FCIPL was required to

    commence construction within 3 months of obtaining sanction for

    the building plans and to complete construction within 39 months

    (including a 6-month grace period). The JDA did not specify the time

    frame within which FCIPL was to apply for and obtain sanction for

    the building plans. In light of this, the Arbitral Tribunal held that

    FCIPL was required to apply for sanction for the building plans

    within a reasonable period. The relevant extract of the impugned

    award is set out below:

    “52… I may also mention here that
    unfortunately, either in Ex.R.1 Memorandum of
    Understanding or Ex.P.1 Joint Development
    Agreement, no time limit is prescribed for
    obtaining sanctioned plan. When no time limit

    – 27 –

    COMAP No. 137 of 2024
    C/W COMAP No. 190 of 2024

    is fixed for doing certain things, the same
    cannot be postponed indefinitely and such an
    obligation has to be performed within a
    ‘reasonable time’.

    43. It is relevant to note that one of the principal assertions on

    which the landowners had premised their claim is that FCIPL had

    not applied for approval of the building plans. The Arbitral Tribunal

    rejected the said contention as the Arbitral Tribunal found sufficient

    evidence on record to establish that FCIPL had applied for the

    sanction of a building plan on 17.12.2014.

    44. The next question that fell for consideration of the Arbitral

    Tribunal was whether there were any further defaults by FCIPL in

    proceeding with the sanction plan. The Arbitral Tribunal found that

    FCIPL’s request for sanction was not processed and the Bangalore

    Development Authority (BDA) had sent a letter dated 18.07.2016

    (Ex.R.17) directing the FCIPL to leave a buffer zone in terms of the

    order passed by the National Green Tribunal [NGT] and resubmit

    the plans for sanctions.

    45. FCIPL stated that there was a Raja Kaluve/Nala at the edge

    of the subject land; therefore, FCIPL had applied for the building

    plans, leaving a buffer area of 10 meters from the centre of the

    – 28 –

    COMAP No. 137 of 2024

    C/W COMAP No. 190 of 2024

    Nala. However, under the NGT’s decision, it was now required to

    maintain a buffer of 15 meters from the edge of the Nala. FCIPL

    claims that this would have substantially reduced the area available

    for construction, and thus it did not proceed with construction as the

    NGT’s order was under challenge before the Supreme Court.

    46. The pleadings and the impugned award indicate that the

    learned NGT’s order was challenged before the Supreme Court in

    Civil Appeal No. 5016/2016, which was disposed of by an order

    dated 05.03.2019.

    47. In the meantime, the landowners sent a legal notice dated

    26.03.2018 (Ex.P2) terminating the JDA and further demanding a

    sum of 60,00,000/- (Rupees sixty thousand only) as well as the

    original title deeds of the said property on account of alleged losses

    suffered by them.

    48. The Arbitral Tribunal was thus required to examine the merits

    of the FCIPL’s defence that it had not resubmitted the plans,

    pending the decision of the order passed by the NGT.

    49. In this regard, the Arbitral Tribunal found that there was Raja

    Kaluve/ Halla / Kharab Kaluve on the subject land. And, if the orders

    – 29 –

    COMAP No. 137 of 2024

    C/W COMAP No. 190 of 2024

    of the NGT and the Hon’ble Supreme Court are taken into

    consideration, the parties were at a disadvantage under the order of

    the NGT. Thus, in effect, the Arbitral Tribunal accepted FCIPL’s

    contention that if the construction was raised while the NGT’s order

    was subsisting, the same would be disadvantageous to the interest

    of the parties.

    50. The Arbitral Tribunal also found that FCIPL had sent a letter

    dated 04.05.2019 to the BDA, informing the BDA of the order dated

    05.03.2019 passed by the Supreme Court setting aside the NGT’s

    order. FCIPL stated that thus the buffer zone as contemplated

    earlier would be applicable and it had prepared a new building plan

    and had also filed an undertaking affidavit. FCIPL requested BDA

    to approve the building plans. However, BDA did not process the

    plans as some of the landowners had given a representation dated

    12.06.2019 not to proceed with the plans.

    51. In his cross-examination, PW1 affirmed that it had given a

    letter to BDA not to sanction building plans as the time period

    stipulated for completion of the project under the JDA had expired in

    the year 2017-2018.

    – 30 –

    COMAP No. 137 of 2024

    C/W COMAP No. 190 of 2024

    52. The landowners had also filed a police complaint with Ulsoor

    Police Station. In the aforesaid backdrop, the Arbitral Tribunal

    concluded that the landowners had obstructed the grant of the

    building plans and had created hindrances in FCIPL proceeding with

    the development of the subject land.

    53. It is relevant to note that the Arbitral Tribunal also took into

    account FCIPL’s letter dated 03.04.2018 (Ex.R14), sent in response

    to the landowners’ legal notice dated 26.03.2018 (Ex.P2). FCIPL

    had denied the allegations in the legal notice dated 26.03.2018, but

    also expressed its willingness to modify the building plans to

    increase the buffer area and thus reduce the buildable area in

    conformity with NGT’s order. The relevant extract of the said letter,

    is reproduced below:

    “Our client states that if your clients are ready
    to take proportionate share in the project as
    per ratio 33% of SBA in the new building plan
    in view of NGT new order, then my client is
    ready and willing to modify the drawings of the
    building Plan as per the NGT order by leaving
    buffer zone as per the NGT order. Then your
    clients will get lesser SBA area and
    proportionately our client is also getting lesser
    area.

    Therefore, our client states that your clients
    can’t forfeit the amount as mentioned in the
    notice and also they are not liable to terminate
    the JDA as he is performing his obligations as
    agreed up on without delay, hence, he is not at

    – 31 –

    COMAP No. 137 of 2024
    C/W COMAP No. 190 of 2024

    all liable to pay any amount towards losses to
    your clients.

    Therefore, kindly advise your clients to co-
    operate with our client to resolve buffer zone
    issue and to get building license, approval of
    building Plan, NOC, required approvals from
    concerned departments to fulfil the obligations
    as agreed up on in the JDA Dtd.26.05.2014.”

    54. However, the impugned award does not render any specific

    finding on the aforesaid defence. The Arbitral Tribunal’s findings

    are summarised as under:

    54.1 That there was no time limit to apply for the

    sanction plan, and therefore FCIPL was to apply for

    the same within a reasonable period.

    54.2 FCIPL had, in fact, applied for the sanction

    plan on 17.12.2014, therefore, there was no default

    on the part of FCIPL in this regard.

    54.3 There was a Raja Kaluve / Nala / Kharab

    Kaluve beside the subject property which required

    FCIPL to provide for a setback from the edge of the

    said Raja Kaluve / Nala / Kharab Kaluve.

    – 32 –

    COMAP No. 137 of 2024

    C/W COMAP No. 190 of 2024

    54.4 NGT had passed an order increasing the

    buffer zone by directing the same to extend to 15

    meters from the edge of the Rakja Kulawe/Nala,

    instead of 10 meters from its centre.

    54.5 The said order was disadvantageous to the

    parties as it would reduce the area that could be

    constructed and the floor area that could be built.

    54.6 The NGT’s order was the subject matter of

    challenge before the Supreme Court in Civil Appeal

    No.5016/2016 (Mantri Tech Zone Private Limited

    v. Forward Foundation and others1) and the

    Supreme Court had passed an order dated

    05.03.2019 setting aside the learned NGT’s order.

    Consequently, the extent of the buffer zone was

    restored to as it was prior to the NGT’s order.

    54.6 FCIPL had approached the BDA seeking

    approval of the new building plan immediately after

    the Supreme Court’s order.

    1
    (2019) 18 SCC 494

    – 33 –

    COMAP No. 137 of 2024

    C/W COMAP No. 190 of 2024

    54.7 Some of the land owners had sent a letter

    objecting to the same and had also filed a police

    complaint to the Ulsoor Police Station and had thus

    created hindrances for FCIPL to perform its

    obligations.

    55. In addition to the above finding, the Arbitral Tribunal faulted

    the landowners’ conduct. The Arbitral Tribunal observed that the

    landowners were not truthful or straightforward and their conduct

    was not above board. Further, the Arbitral Tribunal observed that

    under the JDA it was the duty of the landowners to co-operate with

    FCIPL in getting the approval of the sanction plan and other related

    matters.

    56. Although the principal findings are adverse to the landowners,

    the Arbitral Tribunal also found that FCIPL was also responsible for

    non-completion of the apartment complex and held that FCIPL had

    also defaulted in performing its obligations. Paragraph 58 of the

    impugned award which records the Arbitral Tribunal’s conclusion in

    regard to issues 1 to 3 is as under:

    “58. At the same time, I may also mention
    here that after receiving Letter, seeking the
    clarification, from the Bangalore Development
    Authority as mentioned above, the

    – 34 –

    COMAP No. 137 of 2024
    C/W COMAP No. 190 of 2024

    Respondent has also not taken effective steps
    in the matter. If the overall evidence on
    records is taken into consideration, in my
    opinion, both the Claimants and the
    Respondent are responsible for non-
    completion of the construction of Apartment
    Complex and also in performing the duty and
    obligation against each other. Hence, I hold
    that both the Claimants and the Respondents
    are able to prove against each other that they
    have committed violation of terms and
    conditions of Ex.R.1 Memorandum of
    Understanding and Ex.P.1 Joint Development
    Agreement. Hence, I hold that the Respondent
    has failed to prove that it was not able to
    complete the project due to the circumstances
    beyond its control.”

    57. The Arbitral Tribunal considered the landowner’s prayer in

    light of the aforesaid findings. As noted above, the landowners had

    prayed for a declaration that the JDA is invalid and cancelled. The

    landowners had terminated the JDA by a letter dated 26.03.2018

    (Ex P2) sent through their advocate. Paragraph 8 of the said letter

    read as under:

    “8. Our Client instructs to state that in view of
    above, our client is constrained to terminate
    the JDA dated 26.05.2014 and deal with the
    said property by themselves and/or through
    their nominees/agents/ Legal Heirs.
    Furthermore, the Advance amounts paid
    under the said JDA dated 26.05.2014 is
    forfeited for the losses suffered by our clients
    and breaches committed by yourself, further
    you are liable to pay a sum of Rs.60,00,000/-
    (Rupees Sixty Lakhs Only) as the losses
    suffered by our clients for the loss of
    opportunity and the undue delay caused by

    – 35 –

    COMAP No. 137 of 2024
    C/W COMAP No. 190 of 2024

    you and other incidental losses suffered by our
    clients, which you ought to pay within 15 days
    from the date of receipt of this notice, failing
    which, our clients have instructed us to initiate
    suitable legal proceedings against you for the
    recovery of the same at your expense.”

    58. The Arbitral Tribunal found that although the landowners had

    created hindrances, FCIPL had not taken effective steps for

    performance of its obligations. Indisputably, the said view is a

    plausible one and we are unable to accept that the said conclusion

    vitiates the impugned award by patent illegality. Although there is

    specific finding in regard to FCIPL’s defence to the effect that it had

    refrained from filing revised plans as the challenge to the NGT’s

    order was pending, it is apparent that the Arbitral Tribunal did not

    accept that defence.

    59. Given the aforesaid conclusion, the Arbitral Tribunal’s

    decision to accept that the JDA is terminated, would warrant no

    interference. The refusal to accept the cancellation of the JDA, in

    effect amounts to holding that the JDA subsists and the parties are

    not absolved from performing their obligations under the JDA. In

    effect, the same would amount to allowing the counterclaim for the

    specific performance of the JDA, as sought for by FCIPL. However,

    in view of the finding that FCIPL was in breach of its obligations

    – 36 –

    COMAP No. 137 of 2024

    C/W COMAP No. 190 of 2024

    under the JDA, the impugned award cannot be held to be patently

    illegal for not granting the said relief.

    60. In the aforesaid context, the Arbitral Tribunal held as under:

    “77. The Claimants have prayed for
    declaration to declare that Ex.P.1 Joint
    Development Agreement is invalid, they have
    also prayed for cancellation of Ex.P.1 Joint
    Development Agreement and consequential
    relief of injunction.

    Ex.R.1 Memorandum of Understanding is
    dated 4.3.2013. Ex.P.1 Joint Development
    Agreement is dated 26.5.2014. I have already
    held that both the parties are at fault and as a
    result, the project could not be completed. The
    contracts in question are now more than 10
    years old. Though there is nothing to indicate
    that Ex.P.1 Joint Development Agreement is
    invalid, looking to the relationship between the
    Claimants and the Respondent, the conduct of
    each of them and the time that has lapsed
    after execution of the contract, it is in the
    interest of justice and equity that Ex.P.1 Joint
    Development Agreement is cancelled. …”

    61. There is merit in the contention that the Arbitral Tribunal is

    required to decide in accordance with law unless the parties

    expressly agree otherwise. Section 28(2) of the A&C Act expressly

    provides that:

    – 37 –

    COMAP No. 137 of 2024
    C/W COMAP No. 190 of 2024

    “28. Rules applicable to substance of
    dispute.

    ** ** **
    (2) The arbitral tribunal shall decide ex
    aequo et bono or as amiable compositeur
    only if the parties have expressly authorised
    it to do so.”

    62. However, a plain reading of the impugned award shows that

    the Arbitral Tribunal accepted that the cancellation of the JDA for

    the reason that both the parties had defaulted in their obligations.

    63. The construction of the apartment complex was inordinately

    delayed, and indisputably, there have been long periods of inactivity

    on the part of FCIPL. Thus, the Arbitral Tribunal faulted FCIPL for

    the delay and non-performance of the JDA. It is apparent that this is

    the principal reason for the Arbitral Tribunal not acceding to FCIPL’s

    prayer for directing specific performance of the JDA. A party that

    has defaulted in performing the contract may not be entitled to the

    specific performance of the contract, notwithstanding that the other

    party had also breached its obligations.

    64. The observation of the Arbitral Tribunal that it was in the

    interest of justice and equity to cancel the JDA, in effect denying its

    – 38 –

    COMAP No. 137 of 2024

    C/W COMAP No. 190 of 2024

    specific performance, must be read in conjunction with the finding

    that both parties were in default of their obligations.

    65. Whilst the Arbitral Tribunal declined to direct specific

    performance of the JDA, it accepted that FCIPL is entitled to the

    amounts expended on the project. The Arbitral Tribunal had

    examined the evidence and found that FCIPL had failed to establish

    that it had expended a sum of `1,98,82,036/- (Rupees one crore

    ninety eight lakh eighty two thousand and thirty six only) for the

    project as claimed. However, the Arbitral Tribunal found that FCIPL

    had established that it had paid/expended an aggregate amount of

    `64,12,405/- (Rupees sixty four lakh twelve thousand four hundred

    and five only). Accordingly, the Arbitral Tribunal rounded off the said

    amount and awarded an amount of `65,00,000/- (Rupees sixty five

    lakh only).

    66. We also consider it apposite to refer to the following extract

    from the decision of the Supreme Court in Dyna Technologies (P)

    Ltd. v. Crompton Greaves Ltd2:

    ” 34. The mandate under Section 31(3) of the
    Arbitration Act is to have reasoning which is
    intelligible and adequate and, which can in
    appropriate cases be even implied by the

    2
    (2019) 20 SCC 1

    – 39 –

    COMAP No. 137 of 2024
    C/W COMAP No. 190 of 2024

    courts from a fair reading of the award and
    documents referred to thereunder, if the need
    be. The aforesaid provision does not require
    an elaborate judgment to be passed by the
    arbitrators having regard to the speedy
    resolution of dispute.

    35. When we consider the requirement of a
    reasoned order, three characteristics of a
    reasoned order can be fathomed. They are:

    proper, intelligible and adequate. If the
    reasonings in the order are improper, they
    reveal a flaw in the decision-making process.
    If the challenge to an award is based on
    impropriety or perversity in the reasoning, then
    it can be challenged strictly on the grounds
    provided under Section 34 of the Arbitration
    Act. If the challenge to an award is based on
    the ground that the same is unintelligible, the
    same would be equivalent of providing no
    reasons at all. Coming to the last aspect
    concerning the challenge on adequacy of
    reasons, the Court while exercising jurisdiction
    under Section 34 has to adjudicate the validity
    of such an award based on the degree of
    particularity of reasoning required having
    regard to the nature of issues falling for
    consideration. The degree of particularity
    cannot be stated in a precise manner as the
    same would depend on the complexity of the
    issue. Even if the Court comes to a conclusion
    that there were gaps in the reasoning for the
    conclusions reached by the Tribunal, the Court
    needs to have regard to the documents
    submitted by the parties and the contentions
    raised before the Tribunal so that awards with
    inadequate reasons are not set aside in casual
    and cavalier manner. On the other hand,
    ordinarily unintelligible awards are to be set
    aside, subject to party autonomy to do away
    with the reasoned award. Therefore, the
    courts are required to be careful while
    distinguishing between inadequacy of reasons
    in an award and unintelligible awards.

    – 40 –

    COMAP No. 137 of 2024
    C/W COMAP No. 190 of 2024

    67. In the present case, whilst the impugned award records

    elaborate reasons for finding the landowners in default of their

    obligations and for creating hindrances, the reason for finding FCIPL

    in default is very brief; FCIPL had not taken effective steps after

    receiving a letter from BDA to submit fresh plans. There is no

    discussion in the impugned award regarding FCIPL’s contention that

    it was awaiting decision on the challenge to the NGT’s order, as the

    buildable space had been considerably reduced. It is apparent that

    the Arbitral Tribunal has not accepted the said explanation. The

    reasons on which the impugned award is founded are not

    unintelligible. Since the Arbitral Tribunal also found the landowners

    to be in default, it has awarded the amounts deposited and

    expended by FCIPL, in its favour.

    68. The scope of examination under Section 34 of the A&C Act

    does not permit the court to re-evaluate the evidence, re-adjudicate

    the disputes and supplant its opinion in place of that of the Arbitral

    Tribunal. It is well settled that so long as the Arbitral Tribunal’s view

    is a plausible one, no interference would be warranted.

    – 41 –

    COMAP No. 137 of 2024

    C/W COMAP No. 190 of 2024

    69. In the given circumstances, we are unable to accept that the

    impugned award is vitiated by patent illegality or is in conflict with

    the public policy of India.

    70. The appeals are accordingly dismissed.

    Sd/-

    (VIBHU BAKHRU)
    CHIEF JUSTICE

    Sd/-

    (C.M. POONACHA)
    JUDGE
    SD/AHB



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here