Kynjaimon Amse vs . National Highways Authority on 20 March, 2026

    0
    45
    ADVERTISEMENT

    Meghalaya High Court

    Kynjaimon Amse vs . National Highways Authority on 20 March, 2026

    Author: W. Diengdoh

    Bench: W. Diengdoh

    Serial No. 01
    Supplementary List
    
                         HIGH COURT OF MEGHALAYA
                               AT SHILLONG
    
     PIL No.11/2022
                                              Date of order: 20.03.2026
    
     Kynjaimon Amse           Vs.       National Highways Authority
     (since deceased)                   of India (NHAI) & ors
     Coram:
            Hon'ble Mrs. Justice Revati Mohite Dere, Chief Justice
            Hon'ble Mr. Justice W. Diengdoh, Judge
    
     For the Petitioner     :   Mr. S. Panthi, Amicus Curiae
    
     For the Respondents :      Mr. S. Sengupta, Adv for NHAI

    Mrs. S. Laloo, GA

    On 19th March, 2026, the following order was passed:

    SPONSORED

    “The matter was adjourned by consent on 11th March, 2026 to
    enable the learned Amicus and Mr. Sengupta, learned counsel
    for NHAI to visit the Jowai By-Pass and Ratacherra,
    considering the statement made on affidavit by Shri Anand
    Singh Chauhan, Project Director, NHAI, in paragraph 4 that
    the strengthening and improvement work for the entire Jowai-
    Ratacheera section has been completed by both the
    contractors.

    2. Mr. Panthi, learned Amicus and Mr. Sengupta, learned
    counsel visited the entire stretch to verify the veracity of the
    statement made on affidavit by Mr. Chauhan. Pursuant
    thereto, a report has been submitted by Mr. Panthi. The said
    report dated 19th March, 2026 is taken on record. To the
    report are annexed photographs of the potholes. It appears
    that in the portion of the road at Byndihati, Tonseng before
    the bridge, there are big potholes in the middle of the road,
    Ratacherra near the petrol pump. There are also big potholes
    in Tonseng warranting immediate attention. It is further
    Page 1 of 8
    mentioned in the report that the guard walls, drain erected in
    most the stretches, slabs are either blocked or not in order
    leading to water logging in some of the stretches. Therefore,
    prima facie it appears that the statement made by Mr.
    Chauhan in the additional affidavit dated 23 rd February,
    2026 is incorrect.

    3. This petition is pending since 2022 with respect to the
    repair and restoration work of the road (done by NHAI) on the
    Jowai-Ratacherra road (NH-6). Almost four years have lapsed
    and yet the road is not completely done as stated in the
    affidavit.

    4. Learned Amicus seeks time to place the incorrect
    statements made by the NHAI in their affidavits/report. Time
    granted.

    5. Shri Anand Singh Chauhan, Project Director, NHAI to
    remain present in Court tomorrow i.e. 20th March, 2026.

    6. Stand over to 20th March, 2026″.

    2. Pursuant to the aforesaid order, Shri Anand Singh

    Chauhan, Project Director, NHAI is present in Court, today.

    3. Mr. Panthi, learned Amicus states that the Project Director

    has been filing reports stating therein that the road works

    between Jowai By-Pass and Ratacherra have been completed,

    when infact, the same is not completely done and there are still

    huge craters/potholes in several areas. He submits that the

    affidavits and reports filed by the Project Director, NHAI are

    Page 2 of 8
    nothing but an attempt to hoodwink the Court by annexing

    photographs only of completed areas and indirectly, an attempt to

    mislead the Court. Mr. Panthi submits that when he visited the

    area between Jowai By-Pass and Ratacherra covering an area of

    about 102.225, he found that some of the roads are in an

    extremely poor condition with huge craters/potholes requiring

    vehicles to navigate through the same. Mr. Panthi had tendered a

    report on 19th March, 2026, to that effect. To the report are

    annexed photographs which show that the statement made by the

    Project Director is incorrect and misleading.

    4. Infact, in the report dated 28th October, 2025 submitted

    by the Project Director, NHAI duly signed by him, it is stated that

    the stretch from Lumshnong to Ratacherra of NH-06, which was

    the main concern of PIL No.11 of 2022, has been completely

    constructed. It is further stated that the strengthening and

    improvement work for the Jowai-Ratacherra section is almost

    complete. At the end of the report, under the title “Completion

    status (Jowai-Ratacherra section)”, it is stated as under:

    Page 3 of 8

    “In this regard, it is humbly submitted that the
    overlay/construction work of the main carriageway has
    almost been completed. The remaining works related to road
    furniture, including road marking, are in progress and are
    likely to be completed in all respects by 15.11.2025.”

    5. Learned Amicus states that the little work that remained to

    be done i.e. relating to road furniture, including road marking, as

    per the said report dated 28th October, 2025, was to be completed

    in all respect by 15th November, 2025. It appears that the same

    has also not been done.

    6. Again, in the report submitted by the Project Director dated

    2nd February, 2026 to the Court, it is stated that the

    strengthening and improvement work for the entire Jowai-

    Ratacherra section has been completed, which was the main

    concern of the PIL and the package-wise details were mentioned

    in the said report. Under the column “Completion status (Jowai-

    Ratacherra section)”, the Project Director has stated as under:

    “In this regard, it is most respectfully submitted that the
    overlay/construction work of the main carriageway of the
    subject stretch stands completed. However, in order to
    address the recurring issue of landslides at certain
    vulnerable locations, which during heavy monsoon leads to
    complete stoppage of traffic, a separate an independent

    Page 4 of 8
    contract has been awarded for slope protection and allied
    works at seven (07) vulnerable locations, along the Jowai-
    Ratacherra section, which is presently being executed by
    M/s MFB Geotech Private Limited for a contract period of one
    and a half year. It is submitted that the works at these
    locations are confined to small stretches of approximately 50-
    100 meters each, primarily on the hill side and valley side,
    and are being carried out without disturbing the main the
    carriageway. At present, culvert work at Km 105 is in
    progress, and the road has been kept trafficable.

    It is further submitted that, barring 2-3 scattered stretches of
    limited length (50-100 m each), the entire road stands
    completed in all respect and is operational. Since this stretch
    lies in an area experiencing extreme rainfall conditions,
    among the highest in the world, coupled with heavy
    commercial traffic including overloaded vehicles, activities
    such as pothole repair, slope stabilization and black spot
    rectification are continuous and dynamic in nature and are
    undertaken periodically to improve road safety and
    serviceability; however, the road itself has already been
    reconstructed and completed.”

    7. Infact, it is pertinent to note that in the additional affidavit

    filed by Shri Anand Singh Chauhan on 23rd February, 2026,

    before physical verification was undertaken by the learned

    Amicus and learned Standing Counsel for the NHAI jointly of the

    area, in the said additional affidavit, in paragraph 4, it has been

    stated that “it is pertinent to mention that the strengthening and

    improvement work for the entire Jowai-Ratacherra section has

    Page 5 of 8
    been completed by both the contractors.” In paragraph 8 of the

    said additional affidavit, it is stated as under:

    “8. That it is pertinent to mention that the culvert at Km 105
    which was earlier pending completion has been completed
    and all the vehicles are plying over it without any
    hinderance.”

    Accordingly, in the said report, it is stated that since no

    cause of action survives, the Public Interest Litigation be closed.

    8. Learned Standing Counsel for the NHAI has today tendered

    photographs of the section pointed out by the learned Amicus

    yesterday. He states that yesterday, repair work in the said

    section commenced and that temporary work is being done i.e.

    levelling of the work is being done so as to make it motorable. He

    tenders an unconditional apology on behalf of the Project Director

    for submitting the earlier reports.

    9. Considering the reports filed by the Project Director, NHAI

    with respect to the Jowai-Ratacherra section showing that the

    work is complete, despite the same not being complete, we find

    that the Project Director is attempting to prima facie mislead the

    Page 6 of 8
    Court into closing the petition by stating that the entire work has

    been completed. But, for Mr. Panthi, learned Amicus in pursuing

    the petition, and expressing his willingness to visit the stretch

    and take inspection before the PIL could be closed, we would have

    disposed of the petition, in view of the report filed by the Project

    Director, believing the same to be true and honest.

    10. Consistently, from the report dated 28th October, 2025 till

    the additional affidavit filed by the Project Director as stated

    aforesaid, it appears that an attempt is being made to mislead the

    Court into believing that the entire work section i.e. Jowai-

    Ratacherra section, is complete. The photographs relied upon by

    Mr. Panthi, learned Amicus show not only incomplete road but

    huge craters/potholes on the roads requiring vehicles to navigate

    through the said section.

    11. Considering the aforesaid, we deem it appropriate to issue

    show cause notice to Shri Anand Singh Chauhan, Project

    Director, NHAI, under the Contempt of Courts Act, as to why

    contempt action should not be taken against him, for attempting

    to mislead the Court.

    Page 7 of 8

    12. Accordingly, the Registry to issue show cause notice to Shri

    Anand Singh Chauhan, Project Director, NHAI under Section 12

    of the Contempt of Courts Act, 1971 returnable on 9th April,

    2026.

    13. Stand over to 9th April, 2026.

            (W. Diengdoh)                    (Revati Mohite Dere)
                Judge                           Chief Justice
    
    
    
    
     Meghalaya
    20.03.2026
    "Lam DR-PS"
    
    
    
    
                                                               Page 8 of 8
     



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here