Jpc Infrastrucrure And Constructions … vs Alstom Transport India Limited on 6 July, 2026

    0
    5
    ADVERTISEMENT

    Delhi High Court

    Jpc Infrastrucrure And Constructions … vs Alstom Transport India Limited on 6 July, 2026

                              $~
                              *      IN THE HIGH COURT OF DELHI AT NEW DELHI
                              %                                Judgment reserved on: 12.05.2026
                                                            Judgment pronounced on: 06.07.2026
                              +      O.M.P. (COMM) 124/2024 & I.A. 5694/2024 (Stay)
                                     JPC  INFRASTRUCTURE     AND     CONSTRUCTIONS
                                     PRIVATE LIMITED                        .....Petitioner
                                                   Through: Ms. Manini Brar and Ms.
                                                            Muskaan Chawla, Advocates.
    
                                                       versus
    
                                     ALSTOM TRANSPORT INDIA LIMITED      .....Respondent
                                                 Through: Mr. Dinesh Pardasani, Mr.
                                                          Aishwary Kumar Tiwari, Mr.
                                                          Siddharth Chechani and Mr.
                                                          Amrit Singh, Advocates.
    
                                     CORAM:
                                     HON'BLE MR. JUSTICE HARISH VAIDYANATHAN
                                     SHANKAR
                                                 JUDGMENT
    

    HARISH VAIDYANATHAN SHANKAR, J.

    1. The present Petition, filed by JPC Infrastructure and
    Constructions Private Limited1 under Section 34 of the Arbitration
    and Conciliation Act, 19962, seeks setting aside of the Arbitral
    Award dated 15.11.20233, passed in favour of Alstom Transport
    India Ltd.4 by a Three-member Arbitral Tribunal, comprising
    Justice D.K. Jain (Retd.) as the Presiding Arbitrator, Justice

    SPONSORED

    1
    Petitioner
    2
    A&C Act
    3
    Impugned Award
    4
    Respondent
    Signature Not Verified
    Digitally Signed
    By:HARVINDER KAUR
    BHATIA O.M.P.(COMM.) 124/2024 Page 1 of 38
    Signing Date:08.07.2026
    10:58:01
    Dipak Misra (Retd.) and Justice J.D. Kapoor (Retd.)5, in the matter
    titled “JPC Infrastructure & Constructions Pvt. Ltd. And Alstom
    Transport India Ltd. (Formerly known as Alstom Systems India Pvt.
    Ltd.)”.

    2. During the course of hearing before this Court, learned counsel
    appearing on behalf of the Petitioner expressly confined the challenge
    to the findings returned by the learned Tribunal in respect of Claim
    Nos. 2, 3, 13 and 16. The findings returned by the learned Tribunal on
    all other claims and counterclaims were not assailed and have
    accordingly attained finality.

    FACTUAL MATRIX:

    3. The present dispute traces its origin to the Eastern Dedicated
    Freight Corridor Project being executed by the Dedicated Freight
    Corridor Corporation of India Limited6, a Government of India
    undertaking, for development of freight railway infrastructure between
    Bhaupur and Khurja.

    4. Pursuant to a Letter of Acceptance dated 21.07.2015, DFCCIL
    awarded to the Respondent the principal contract for design,
    construction, supply, installation, testing and commissioning of 2 x 25
    KV AC electrification, signalling, telecommunication and allied works
    forming part of the said project. The works under the principal
    contract were divided into various segments or “Slices”, one of which
    was Slice-103.

    5. Even prior to the award of the principal contract, the
    Respondent had invited quotations from prospective subcontractors

    5
    learned Tribunal
    6
    DFCCIL
    Signature Not Verified
    Digitally Signed
    By:HARVINDER KAUR
    BHATIA O.M.P.(COMM.) 124/2024 Page 2 of 38
    Signing Date:08.07.2026
    10:58:01
    for execution of portions of the works contemplated under Slice-103.
    The Petitioner submitted its commercial proposal on 31.03.2015,
    which was subsequently revised on 26.11.2015. The said proposal was
    accepted by the Respondent and culminated in the issuance of a Letter
    of Acceptance dated 04.12.2015 in favour of the Petitioner.
    Thereafter, the parties executed a Back-to-Back Sub-Contract
    Agreement dated 15.12.20157.

    6. Under the Contract, the Petitioner was entrusted with the
    execution of civil, electrical and associated works relating to fifty-five
    structures situated at Daudkhan, Hathras and Khurja. The scope of
    work broadly included preparation of designs and drawings,
    geotechnical investigations, topographical surveys, construction of
    buildings and structures, electrical works and maintenance obligations.

    7. The Contract was executed on a lump-sum basis for a
    consideration of Rs. 34,09,58,091/- and contemplated completion of
    the works within 675 days reckoned from 03.08.2015, being the
    commencement date under the principal contract.

    8. The Petitioner’s case throughout has been that the execution of
    the Contract was dependent upon the Respondent first making
    available unhindered and encumbrance-free access to the project sites,
    furnishing finalized project particulars, identifying locations of
    structures and enabling the Petitioner to undertake the preliminary
    investigations and surveys required for preparation of designs.
    According to the Petitioner, these foundational requirements were not
    fulfilled in a timely manner, thereby preventing it from effectively
    carrying out geotechnical investigations, topographical surveys and

    7
    Contract
    Signature Not Verified
    Digitally Signed
    By:HARVINDER KAUR
    BHATIA O.M.P.(COMM.) 124/2024 Page 3 of 38
    Signing Date:08.07.2026
    10:58:01
    design activities contemplated under the Contract.

    9. The Respondent, on the other hand, maintained that all
    necessary information and access required for performance of the
    Contract were duly made available and that the delays and
    deficiencies in execution were attributable solely to the Petitioner.

    10. As the project progressed, disputes arose between the parties
    regarding responsibility for delays, progress of the works, availability
    of sites, preparation and approval of drawings, execution of surveys
    and investigations, entitlement to payments, and the consequences of
    the Petitioner’s alleged non-performance. Extensive correspondence
    was exchanged between the parties, each attributing responsibility for
    the delay and disruption of the project to the other.

    11. The relationship between the parties deteriorated further when
    portions of the work originally entrusted to the Petitioner came to be
    descoped and the Contract ultimately stood terminated by the
    Respondent.

    12. While the Petitioner asserted that the termination and descoping
    were wrongful and were themselves a consequence of the
    Respondent’s inability to fulfil its reciprocal obligations under the
    Contract, the Respondent maintained that the same were necessitated
    by the Petitioner’s continuing defaults and inability to execute the
    works entrusted to it.

    13. The disputes between the parties eventually culminated in
    arbitral proceedings being commenced under Clause 29.3 of the
    Contract. In accordance with the arbitration agreement, the disputes
    were referred to arbitration under the ICC Rules of Arbitration,

    Signature Not Verified
    Digitally Signed
    By:HARVINDER KAUR
    BHATIA O.M.P.(COMM.) 124/2024 Page 4 of 38
    Signing Date:08.07.2026
    10:58:01
    20218 before a three-member Arbitral Tribunal.

    14. Before the learned Tribunal, the Petitioner preferred several
    claims aggregating substantial amounts under diverse heads, including
    reimbursement of expenditure allegedly incurred towards geotechnical
    investigations, topographical surveys, consultancy charges, overhead
    costs, loss of profit and other contractual entitlements. The
    Respondent contested the claims and, in turn, raised multiple
    counterclaims arising out of the alleged breaches committed by the
    Petitioner.

    15. In support of its case, the Petitioner relied, inter alia, upon a
    Letter dated 07.06.2017 addressed by the Respondent to
    DFCCIL9. The Petitioner contended that the said communication
    contained admissions by the Respondent itself acknowledging that
    geotechnical investigations, topographical surveys and other
    preliminary activities could not commence in the absence of
    encumbrance-free access to the sites and availability of necessary
    project particulars.

    16. According to the Petitioner, the contents of the Rejected Letter
    substantiated its defence that the delays and non-performance alleged
    against it were attributable to circumstances for which the Respondent
    was responsible.

    17. The Respondent objected to the reliance placed upon the said
    communication on the ground that it formed part of disputes and
    arbitral proceedings between the Respondent and DFCCIL arising out
    of the principal contract. It was contended that the document was
    confidential in nature and could neither be relied upon nor introduced
    8
    ICC Rules
    9
    Rejected Letter
    Signature Not Verified
    Digitally Signed
    By:HARVINDER KAUR
    BHATIA O.M.P.(COMM.) 124/2024 Page 5 of 38
    Signing Date:08.07.2026
    10:58:01
    in evidence in the arbitration between the present parties.

    18. The learned Tribunal considered the rival contentions
    concerning the admissibility of the aforesaid communication and, by
    its findings contained in Paragraphs 16.1 to 16.12 of the Impugned
    Award, concluded that the document could not be relied upon while
    adjudicating the disputes between the parties. Proceeding on that
    basis, the learned Tribunal evaluated the claims on the material
    otherwise available on record.

    19. Upon consideration of the pleadings, documentary evidence,
    oral testimony and submissions advanced by the parties, the learned
    Tribunal rendered the Impugned Award dated 15.11.2023. While
    certain claims of the Petitioner were allowed in part and all
    counterclaims of the Respondent came to be rejected, the learned
    Tribunal rejected, inter alia, Claim Nos. 2, 3, 13 and 16 relating
    respectively to geotechnical investigations, topographical surveys,
    overhead costs and loss of profit. Insofar as Claim Nos. 13 and 16 are
    concerned, Justice J.D. Kapoor (Retd.) rendered a separate dissenting
    opinion.

    20. In the present proceedings under Section 34 of the A&C Act,
    the challenge initially laid to several portions of the Impugned Award
    stands substantially narrowed. As noted earlier, during the course of
    hearing, learned counsel for the Petitioner confined the challenge
    exclusively to the findings returned in respect of Claim Nos. 2, 3, 13
    and 16 and, more particularly, to the learned Tribunal’s decision
    declining to admit and rely upon the Rejected Letter.

    21. According to the Petitioner, the exclusion of the said document
    vitiated the adjudication of the aforesaid claims. The Respondent,

    Signature Not Verified
    Digitally Signed
    By:HARVINDER KAUR
    BHATIA O.M.P.(COMM.) 124/2024 Page 6 of 38
    Signing Date:08.07.2026
    10:58:01
    however, supports the reasoning and conclusions contained in the
    Impugned Award and submits that no ground for interference within
    the limited scope of Section 34 of the A&C Act is made out.

    22. It is in the aforesaid factual backdrop that the rival submissions
    fall for consideration.

    CONTENTIONS ON BEHALF OF THE PETITIONER:

    23. Learned counsel appearing on behalf of the Petitioner would, at
    the outset, fairly submit that the present challenge is confined to the
    findings returned by the learned Tribunal in relation to Claim Nos. 2,
    3, 13 and 16. According to the learned counsel, the rejection of the
    aforesaid claims is fundamentally traceable to the learned Tribunal’s
    decision to exclude from consideration a communication dated
    07.06.2017, i.e., the Rejected Letter, addressed by the Respondent to
    DFCCIL.

    24. Learned counsel would submit that the Petitioner’s case before
    the learned Tribunal was that various contractual activities, including
    Geotechnical Investigations and Topographical Surveys, could not be
    effectively undertaken owing to the non-availability of unhindered and
    encumbrance-free access to the project site. In support of the said
    case, reliance would be placed upon the Rejected Letter, wherein the
    Respondent itself allegedly acknowledged before DFCCIL that the
    requisite surveys could not commence until free access to the site was
    made available and that certain essential project particulars had not
    been furnished.

    25. According to the learned counsel for the Petitioner, the contents
    of the Rejected Letter constituted admissions directly supporting the
    Petitioner’s case that the delays and deficiencies attributed to it were
    Signature Not Verified
    Digitally Signed
    By:HARVINDER KAUR
    BHATIA O.M.P.(COMM.) 124/2024 Page 7 of 38
    Signing Date:08.07.2026
    10:58:01
    occasioned by prevailing site conditions and circumstances beyond its
    control. It would therefore be contended that the document went to the
    root of the controversy concerning responsibility for delay,
    performance of contractual obligations and the consequent rejection of
    the claims in question.

    26. Learned counsel would submit that notwithstanding the
    materiality of the said document, the learned Tribunal declined to
    admit or rely upon the same on the ground that it formed part of
    arbitral proceedings between the Respondent and DFCCIL and was
    therefore protected by the confidentiality obligation embodied in
    Section 42A of the A&C Act.

    27. Assailing the aforesaid approach, learned counsel for the
    Petitioner would submit that the learned Tribunal committed a
    manifest error in treating the Rejected Letter as confidential and
    consequently inadmissible. It would be contended that the document
    had already formed part of proceedings before this Court and had
    thereby entered the public domain. According to the learned counsel,
    once a document ceases to retain its confidential character, the
    protection contemplated under Section 42A of the A&C Act cannot
    continue to operate in respect thereof.

    28. Learned counsel would submit that the confidentiality
    contemplated under Section 42A of the A&C Act operates only in
    relation to material which continues to retain the character of
    confidentiality. The learned Tribunal, according to the learned
    counsel, failed to examine whether confidentiality in fact subsisted in
    relation to the Rejected Letter and instead proceeded on the
    assumption that confidentiality attached to the document merely

    Signature Not Verified
    Digitally Signed
    By:HARVINDER KAUR
    BHATIA O.M.P.(COMM.) 124/2024 Page 8 of 38
    Signing Date:08.07.2026
    10:58:01
    because it originated from another arbitral proceeding.

    29. Learned counsel would further contend that the arbitration
    between the parties was conducted under the ICC Rules of
    Arbitration, 202110 and that the learned Tribunal failed to appreciate
    the contractual framework governing confidentiality between the
    parties. Particular reliance would be placed upon Article 22(3) of the
    ICC Rules, which merely empowers an arbitral tribunal, upon request,
    to issue appropriate directions concerning confidentiality and
    protection of confidential information.

    30. Learned counsel for the Petitioner would contend that Article
    22(3)
    does not impose an absolute prohibition against the use or
    consideration of documents emanating from arbitral proceedings. The
    confidentiality regime contemplated under the ICC Rules is
    discretionary and procedural in nature and cannot be construed as
    creating a blanket embargo against consideration of otherwise relevant
    and material evidence.

    31. Learned counsel would therefore submit that neither the ICC
    Rules nor the factual circumstances of the present case justified the
    learned Tribunal in excluding the Rejected Letter altogether. At the
    highest, the learned Tribunal could have adopted appropriate
    safeguards while considering the document. The learned Tribunal,
    however, erroneously proceeded on the footing that confidentiality
    itself rendered the document incapable of consideration.

    32. Proceeding further, learned counsel would submit that even
    assuming that the Rejected Letter remained subject to confidentiality
    obligations, Section 42A of the A&C Act merely imposes an

    10
    ICC Rules
    Signature Not Verified
    Digitally Signed
    By:HARVINDER KAUR
    BHATIA O.M.P.(COMM.) 124/2024 Page 9 of 38
    Signing Date:08.07.2026
    10:58:01
    obligation of confidentiality and does not prescribe inadmissibility as
    a consequence of any alleged breach thereof. It would be contended
    that the provision does not create an exclusionary rule of evidence.

    33. Learned counsel would submit that the learned Tribunal
    effectively read into Section 42A of the A&C Act a consequence
    which the legislature has consciously not enacted. Learned counsel for
    the Petitioner would submit that a document otherwise relevant and
    material does not become inadmissible merely because a
    confidentiality obligation is asserted in respect thereof.

    34. In support of the aforesaid submission, learned counsel would
    place reliance upon the decision of the Bombay High Court in Global
    Aviation Services Private Limited v. Airport Authority of India11
    to
    contend that where a statute imposes an obligation but does not
    prescribe any consequence for non-compliance, a Court or Tribunal
    cannot create a disqualification or disability not contemplated by the
    legislative scheme. Particular reliance would be placed upon
    Paragraph Nos. 115, 118 and 121 thereof.

    35. Learned counsel would further place reliance upon paragraphs
    84 to 86 of the Constitution Bench decision in Interplay Between
    Arbitration Agreements under Arbitration Act, 1996 and Stamp Act,
    1899
    , In re12. It would be submitted that the Supreme Court has held
    that the operation of a non-obstante clause must be confined to the
    legislative purpose underlying the provision in which it appears and
    cannot be extended beyond the field intended by Parliament.

    36. According to the learned counsel, the non-obstante clause
    contained in Section 42A of the A&C Act is intended only to secure
    11
    2018 SCC OnLine Bom 233
    12
    (2024) 6 SCC 1
    Signature Not Verified
    Digitally Signed
    By:HARVINDER KAUR
    BHATIA O.M.P.(COMM.) 124/2024 Page 10 of 38
    Signing Date:08.07.2026
    10:58:01
    confidentiality in arbitral proceedings. The provision cannot be
    expanded so as to create a substantive rule rendering documents
    inadmissible in evidence when the statute itself contains no such
    stipulation.

    37. Learned counsel would additionally submit that the learned
    Tribunal erred in extending the operation of Section 42A of the A&C
    Act to legal counsels and in concluding that the manner in which the
    document came into the possession of the Petitioner justified its
    exclusion from consideration. According to the learned counsel, such
    consequences do not flow from the text of Section 42A of the A&C
    Act.

    38. Proceeding on the aforesaid basis, learned counsel would
    submit that the exclusion of the Rejected Letter materially affected the
    adjudication of Claim Nos. 2 and 3 relating to Geotechnical
    Investigations and Topographical Surveys. It would be contended that
    had the contents of the said communication been considered, the
    learned Tribunal could not have attributed responsibility for failure to
    undertake the said activities to the Petitioner.

    39. Learned counsel would further submit that the findings recorded
    in relation to Claim Nos. 13 and 16 concerning overhead costs and
    loss of profit are likewise vitiated. According to the learned counsel,
    those findings are substantially founded upon conclusions regarding
    the Petitioner’s alleged defaults and breaches, which stand materially
    undermined by the contents of the Rejected Letter.

    40. It would accordingly be contended that exclusion of the
    Rejected Letter resulted in the learned Tribunal disregarding material
    evidence having a direct bearing on the disputes between the parties.

    Signature Not Verified
    Digitally Signed
    By:HARVINDER KAUR
    BHATIA O.M.P.(COMM.) 124/2024 Page 11 of 38
    Signing Date:08.07.2026
    10:58:01

    The Award, according to the learned counsel, therefore suffers from
    patent illegality appearing on the face of the Award and is further
    liable to be interfered with under Section 34 (2A) of the A&C Act.

    41. Learned counsel would therefore pray that the impugned Award
    be set aside insofar as it rejects Claim Nos. 2, 3, 13 and 16.

    SUBMISSIONS ON BEHALF OF THE RESPONDENT:

    42. Per contra, learned counsel appearing on behalf of the
    Respondent would submit that the present Petition is entirely
    misconceived and seeks to challenge a reasoned arbitral award by
    inviting this Court to undertake a re-appreciation of matters which
    were fully considered and adjudicated upon by the learned Tribunal.

    43. Learned counsel would submit that the challenge raised by the
    Petitioner proceeds upon an incorrect premise that the learned
    Tribunal ignored or refused to consider the Rejected Letter. According
    to the learned counsel, the Award itself demonstrates that the learned
    Tribunal specifically examined the said document, considered the rival
    submissions advanced by the parties regarding its provenance,
    admissibility and confidentiality, and thereafter rendered a reasoned
    determination declining to rely upon the same.

    44. It would therefore be contended that this is not a case where
    material evidence was overlooked or excluded without consideration.
    On the contrary, the issue formed the subject matter of detailed
    adjudication and the learned Tribunal consciously concluded that the
    document ought not to be relied upon while deciding the disputes
    between the parties.

    45. Learned counsel would further submit that the Rejected Letter
    admittedly originated from arbitral proceedings between the
    Signature Not Verified
    Digitally Signed
    By:HARVINDER KAUR
    BHATIA O.M.P.(COMM.) 124/2024 Page 12 of 38
    Signing Date:08.07.2026
    10:58:01
    Respondent and DFCCIL. The learned Tribunal examined the
    circumstances in which the document came into the possession of the
    Petitioner and ultimately concluded that the same formed part of
    confidential arbitral proceedings governed by the confidentiality
    obligations applicable thereto.

    46. According to the learned counsel, the finding returned by the
    learned Tribunal on the issue of confidentiality is a finding rendered
    within its jurisdiction after appreciation of the material placed before
    it. Merely because another view may also be possible would not
    furnish a ground for interference under Section 34 of the A&C Act.

    47. Learned counsel would further submit that the Petitioner cannot
    derive any assistance from the fact that the arbitration between the
    parties was conducted under the ICC Rules. It would be contended
    that Article 22(3) of the ICC Rules merely enables the arbitral tribunal
    to adopt measures concerning confidentiality and protection of
    confidential information. The said provision cannot dilute or override
    a statutory mandate contained in the A&C Act.

    48. According to the learned counsel, once Parliament has enacted
    Section 42A in the A&C Act and imposed a statutory obligation of
    confidentiality in relation to arbitral proceedings, the same cannot be
    curtailed or diluted by reference to institutional rules. It would be
    contended that institutional rules operate within the framework of the
    governing statute and cannot prevail over an express legislative
    command.

    49. Responding to the contention that the Rejected Letter had
    entered the public domain, learned counsel would submit that the
    learned Tribunal considered and rejected the said contention. It would

    Signature Not Verified
    Digitally Signed
    By:HARVINDER KAUR
    BHATIA O.M.P.(COMM.) 124/2024 Page 13 of 38
    Signing Date:08.07.2026
    10:58:01
    be contended that mere production of a document in separate judicial
    proceedings does not automatically establish loss of confidentiality,
    particularly when the document originates from arbitral proceedings
    protected by statutory confidentiality obligations.

    50. Learned counsel would further submit that the Petitioner is
    effectively inviting this Court to re-examine the correctness of the
    factual conclusions drawn by the learned Tribunal regarding
    confidentiality, provenance and admissibility of the document. Such
    an exercise, according to the learned counsel, lies wholly beyond the
    limited scope of jurisdiction under Section 34 of the A&C Act.

    51. Without prejudice to the aforesaid submissions, learned counsel
    would contend that the entire challenge raised by the Petitioner
    proceeds on an erroneous assumption that rejection of the Rejected
    Letter automatically vitiates the findings returned in relation to Claim
    Nos. 2, 3, 13 and 16.

    52. It would be submitted that the learned Tribunal rejected the
    aforesaid claims on the basis of detailed and independent findings
    arising from the evidence on record. The Award records separate
    reasons in relation to each of the claims and does not rest solely upon
    the exclusion of the Rejected Letter.

    53. Learned counsel would submit that significantly, the Petitioner
    has not assailed the independent findings recorded by the learned
    Tribunal while rejecting Claim Nos. 2, 3, 13 and 16. No challenge has
    been mounted to the Tribunal’s appreciation of the documentary
    evidence, findings on proof of expenditure, findings regarding
    performance of work, findings concerning entitlement to overheads or
    findings relating to loss of profit.

    Signature Not Verified
    Digitally Signed
    By:HARVINDER KAUR
    BHATIA O.M.P.(COMM.) 124/2024 Page 14 of 38
    Signing Date:08.07.2026
    10:58:01

    54. According to the learned counsel, the Petition proceeds entirely
    on the footing that once the Rejected Letter is taken into account, the
    conclusions reached by the learned Tribunal must necessarily fail.
    Such a contention, it would be submitted, overlooks the fact that the
    Award contains several independent and self-sustaining reasons
    supporting rejection of the claims.

    55. It would therefore be contended that even assuming, without
    admitting, that the learned Tribunal could have adopted a different
    view regarding the Rejected Letter, the Petitioner has failed to
    demonstrate how the independent findings recorded against Claim
    Nos. 2, 3, 13 and 16 are liable to be interfered with under Section 34
    of the A&C Act.

    56. Learned counsel would submit that the Petition discloses no
    patent illegality or violation of the public policy of India. At its
    highest, the Petitioner seeks substitution of the Tribunal’s view with
    another possible view on a matter squarely falling within the
    Tribunal’s domain. Learned counsel would accordingly pray that the
    present Petition be dismissed.

    ANALYSIS:

    57. This Court has heard the learned counsel for the parties at
    length and, with their able assistance, perused the material available
    on record and the Judicial precedents relied upon.

    58. At the outset, it is apposite to note that this Court is conscious
    of the limited scope of its jurisdiction while examining an objection
    petition under Section 34 of the A&C Act. The contours of judicial
    intervention in such proceedings have been authoritatively delineated
    and settled by a consistent and evolving line of precedents of the
    Signature Not Verified
    Digitally Signed
    By:HARVINDER KAUR
    BHATIA O.M.P.(COMM.) 124/2024 Page 15 of 38
    Signing Date:08.07.2026
    10:58:01
    Hon’ble Supreme Court.

    59. In this regard, a three-Judge Bench of the Hon’ble Supreme
    Court, after an exhaustive consideration of a catena of earlier
    decisions, in OPG Power Generation (P) Ltd. v. Enexio Power
    Cooling Solutions (India) (P) Ltd.13
    , while dealing with the grounds
    of conflict with the public policy of India and patent illegality,
    grounds which have also been urged in the present case, made certain
    pertinent observations, which are reproduced hereunder:

    “Relevant legal principles governing a challenge to an arbitral
    award

    30. Before we delve into the issue/sub-issues culled out above, it
    would be useful to have a look at the relevant legal principles
    governing a challenge to an arbitral award. Recourse to a court
    against an arbitral award may be made through an application
    for setting aside such award in accordance with sub-sections (2),
    (2-A) and (3) of Section 34 of the 1996 Act. Sub-section (2) of
    Section 34 has two clauses, (a) and (b). Clause (a) has five sub-
    clauses which are not relevant to the issues raised before us.
    Insofar as clause (b) is concerned, it has two sub-clauses,
    namely, (i) and (ii). Sub-clause (i) of clause (b) is not relevant to
    the controversy in hand. Sub-clause (ii) of clause (b) provides
    that if the Court finds that the arbitral award is in conflict with
    the public policy of India, it may set aside the award.
    Public policy

    31. “Public policy” is a concept not statutorily defined, though it
    has been used in statutes, rules, notification, etc. since long, and
    is also a part of common law. Section 23 of the Contract Act,
    1872 uses the expression by stating that the consideration or
    object of an agreement is lawful, unless, inter alia, opposed to
    public policy. That is, a contract which is opposed to public
    policy is void.

    *****

    35. In Renusagar Power Co. Ltd. v. General Electric Co., 1994
    Supp (1) SCC 644, a three-Judge Bench of this Court observed
    that the doctrine of public policy is somewhat open–textured
    and flexible. By citing earlier decisions, it was observed that
    there are two conflicting positions which are referred to as the
    “narrow view” and the “broad view”. According to the narrow
    view, courts cannot create new heads of public policy whereas

    13
    (2025) 2 SCC 417
    Signature Not Verified
    Digitally Signed
    By:HARVINDER KAUR
    BHATIA O.M.P.(COMM.) 124/2024 Page 16 of 38
    Signing Date:08.07.2026
    10:58:01
    the broad view countenances judicial law making in these areas.

    In the field of private international law, it was pointed out,
    courts refuse to apply a rule of foreign law or recognise a
    foreign judgment or a foreign arbitral award if it is found that
    the same is contrary to the public policy of the country in which
    it is sought to be invoked or enforced. However, it was clarified,
    a distinction is to be drawn while applying the rule of public
    policy between a matter governed by domestic law and a matter
    involving conflict of laws. It was observed that the application
    of the doctrine of public policy in the field of conflict of laws is
    more limited than that in the domestic law and the courts are
    slower to invoke public policy in cases involving a foreign
    element than when a purely municipal legal issue is involved. It
    was held that contravention of law alone will not attract the bar
    of public policy, and something more than contravention of law
    is required.

    *****

    37. What is clear from above is that for an award to be against
    public policy of India a mere infraction of the municipal laws of
    India is not enough. There must be, inter alia, infraction of
    fundamental policy of Indian law including a law meant to serve
    public interest or public good.

    *****

    40. In ONGC Ltd. v. Western Geco International Ltd., (2014) 9
    SCC 263, paras 35, 38 & 39, which also related to the period
    prior to the 2015 Amendment of Section 34(2)(b)(ii), a three-
    Judge Bench of this Court, after considering the decision
    inONGC Ltd. v. Saw Pipes Ltd., (2003) 5 SCC 705, without
    exhaustively enumerating the purport of the expression
    “fundamental policy of Indian law”, observed that it would
    include all such fundamental principles as providing a basis for
    administration of justice and enforcement of law in this country.
    The Court thereafter illustratively referred to three fundamental
    juristic principles, namely:

    (a) that in every determination that affects the rights of a citizen
    or leads to any civil consequences, the court or authority or
    quasi-judicial body must adopt a judicial approach, that is, it
    must act bona fide and deal with the subject in a fair, reasonable
    and objective manner and not actuated by any extraneous
    consideration;

    (b) that while determining the rights and obligations of parties
    the court or Tribunal or authority must act in accordance with
    the principles of natural justice and must apply its mind to the
    attendant facts and circumstances while taking a view one way
    or the other; and

    (c) that its decision must not be perverse or so irrational that no
    reasonable person would have arrived at the same.

    Signature Not Verified
    Digitally Signed
    By:HARVINDER KAUR
    BHATIA O.M.P.(COMM.) 124/2024 Page 17 of 38
    Signing Date:08.07.2026
    10:58:01

    41. In Associate Builders v. DDA, (2015) 3 SCC 49, a two-

    Judge Bench of this Court, held
    that audialterampartem principle is undoubtedly a fundamental
    juristic principle in Indian law and is enshrined in Sections 18
    and 34(2)(a)(iii) of the 1996 Act. In addition to the earlier
    recognised principles forming fundamental policy of Indian law,
    it was held that disregarding:

    (a) orders of superior courts in India; and

    (b) the binding effect of the judgment of a superior court would
    also be regarded as being contrary to the fundamental policy of
    Indian law.

    Further, elaborating upon the third juristic principle (i.e. qua
    perversity), as laid down in ONGC Ltd. v. Western Geco
    International Ltd.
    , (2014) 9 SCC 263, it was observed that
    where:

    (i) a finding is based on no evidence; or

    (ii) an Arbitral Tribunal takes into account something irrelevant
    to the decision which it arrives at; or

    (iii) ignores vital evidence in arriving at its decision, such
    decision would necessarily be perverse [Associate Builders
    case, (2015) 3 SCC 49, para 31].

    To this a caveat was added by observing that when a court
    applies the “public policy test” to an arbitration award, it does
    not act as a court of appeal and, consequently, errors of fact
    cannot be corrected; and a possible view by the arbitrator on
    facts has necessarily to pass muster as the arbitrator is the
    ultimate master of the quantity and quality of evidence to be
    relied upon when he delivers his arbitral award. It was also
    observed that an award based on little evidence or on evidence
    which does not measure up in quality to a trained legal mind
    would not be held to be invalid on that score. Thus, once it is
    found that the arbitrator’s approach is not arbitrary or capricious,
    it is to be taken as the last word on facts.

    The 2015 Amendment in Sections 34 and 48

    42. The aforementioned judicial pronouncements were all prior
    to the 2015 Amendment. Notably, prior to the 2015 Amendment
    the expression “in contravention with the fundamental policy of
    Indian law” was not used by the legislature in either Section
    34(2)(b)(ii)
    or Section 48(2)(b). The pre-amended Section
    34(2)(b)(ii)
    and its Explanation read:

    *****

    44. By the 2015 Amendment, in place of the old Explanation to
    Section 34(2)(b)(ii), Explanations 1 and 2 were added to remove
    any doubt as to when an arbitral award is in conflict with the
    public policy of India.

    45. At this stage, it would be pertinent to note that we are
    dealing with a case where the application under Section 34 of

    Signature Not Verified
    Digitally Signed
    By:HARVINDER KAUR
    BHATIA O.M.P.(COMM.) 124/2024 Page 18 of 38
    Signing Date:08.07.2026
    10:58:01
    the 1996 Act was filed after the 2015 Amendment, therefore the
    newly substituted/added Explanations would apply
    [SsangyongEngg. & Construction Co. Ltd. v. NHAI, (2019) 15
    SCC 131].

    46. The 2015 Amendment adds two Explanations to each of the
    two sections, namely, Section 34(2)(b)(ii) and Section 48(2)(b),
    in place of the earlier Explanation. The significance of the newly
    inserted Explanation 1 in both the sections is two-fold. First, it
    does away with the use of words : (a) “without prejudice to the
    generality of sub-clause (ii)” in the opening part of the pre-

    amended Explanation to Section 34(2)(b)(ii); and (b) “without
    prejudice to the generality of clause (b) of this section” in the
    opening part of the pre-amended Explanation to Section
    48(2)(b)
    ; secondly, it limits the expanse of public policy of India
    to the three specified categories by using the words “only if”.
    Whereas, Explanation 2 lays down the standard for adjudging
    whether there is a contravention with the fundamental policy of
    Indian law by providing that a review on merits of the dispute
    shall not be done. This limits the scope of the enquiry on an
    application under either Section 34(2)(b)(ii) or Section 48(2)(b)
    of the 1996 Act.

    47. The 2015 Amendment by inserting sub-section (2-A) in
    Section 34, carves out an additional ground for annulment of an
    arbitral award arising out of arbitrations other than international
    commercial arbitrations. Sub-section (2-A) provides that the
    Court may also set aside an award if that is vitiated by patent
    illegality appearing on the face of the award. This power of the
    Court is, however, circumscribed by the proviso, which states
    that an award shall not be set aside merely on the ground of an
    erroneous application of the law or by reappreciation of
    evidence.

    48. Explanation 1 to Section 34(2)(b)(ii), specifies that an
    arbitral award is in conflict with the public policy of India, only
    if:

    (i) the making of the award was induced or affected by fraud or
    corruption or was in violation of Section 75 or Section 81; or

    (ii) it is in contravention with the fundamental policy of Indian
    law; or

    (iii) it is in conflict with the most basic notions of morality or
    justice.

    49. In the instant case, there is no allegation that the making of
    the award was induced or affected by fraud or corruption, or was
    in violation of Section 75 or Section 81. Therefore, we shall
    confine our exercise in assessing as to whether the arbitral award
    is in contravention with the fundamental policy of Indian law,
    and/or whether it conflicts with the most basic notions of
    morality or justice. Additionally, in the light of the provisions of

    Signature Not Verified
    Digitally Signed
    By:HARVINDER KAUR
    BHATIA O.M.P.(COMM.) 124/2024 Page 19 of 38
    Signing Date:08.07.2026
    10:58:01
    sub-section (2-A) of Section 34, we shall examine whether there
    is any patent illegality on the face of the award.

    50. Before undertaking the aforesaid exercise, it would be
    apposite to consider as to how the expressions:

    (a) “in contravention with the fundamental policy of Indian
    law”;

    (b) “in conflict with the most basic notions of morality or
    justice”; and

    (c) “patent illegality” have been construed.

    In contravention with the fundamental policy of Indian law

    51. As discussed above, till the 2015 Amendment the expression
    “in contravention with the fundamental policy of Indian law”

    was not found in the 1996 Act. Yet, in Renusagar Power Co.
    Ltd. v. General Electric Co.
    , 1994 Supp (1) SCC 644, in the
    context of enforcement of a foreign award, while construing the
    phrase “contrary to the public policy”, this Court held that for a
    foreign award to be contrary to public policy mere contravention
    of law would not be enough rather it should be contrary to:

    (a) the fundamental policy of Indian law; and/or

    (b) the interest of India; and/or

    (c) justice or morality.

    *****

    55. The legal position which emerges from the aforesaid
    discussion is that after “the 2015 Amendments” in Section
    34(2)(b)(ii)
    and Section 48(2)(b) of the 1996 Act, the phrase “in
    conflict with the public policy of India” must be accorded a
    restricted meaning in terms of Explanation 1. The expression “in
    contravention with the fundamental policy of Indian law” by use
    of the word “fundamental” before the phrase “policy of Indian
    law” makes the expression narrower in its application than the
    phrase “in contravention with the policy of Indian law”, which
    means mere contravention of law is not enough to make an
    award vulnerable. To bring the contravention within the fold of
    fundamental policy of Indian law, the award must contravene all
    or any of such fundamental principles that provide a basis for
    administration of justice and enforcement of law in this country.

    56. Without intending to exhaustively enumerate instances of
    such contravention, by way of illustration, it could be said that:

    (a) violation of the principles of natural justice;

    (b) disregarding orders of superior courts in India or the binding
    effect of the judgment of a superior court; and

    (c) violating law of India linked to public good or public
    interest, are considered contravention of the fundamental policy
    of Indian law.

    However, while assessing whether there has been a
    contravention of the fundamental policy of Indian law, the

    Signature Not Verified
    Digitally Signed
    By:HARVINDER KAUR
    BHATIA O.M.P.(COMM.) 124/2024 Page 20 of 38
    Signing Date:08.07.2026
    10:58:01
    extent of judicial scrutiny must not exceed the limit as set out
    in Explanation 2 to Section 34(2)(b)(ii).

    *****
    Patent illegality

    65. Sub-section (2-A) of Section 34 of the 1996 Act, which was
    inserted by the 2015 Amendment, provides that an arbitral
    award not arising out of international commercial arbitrations,
    may also be set aside by the Court, if the Court finds that the
    award is visited by patent illegality appearing on the face of the
    award. The proviso to sub-section (2-A) states that an award
    shall not be set aside merely on the ground of an erroneous
    application of the law or by reappreciation of evidence.

    66. In ONGC Ltd. v. Saw Pipes Ltd., (2003) 5 SCC 705, while
    dealing with the phrase “public policy of India” as used in
    Section 34, this Court took the view that the concept of public
    policy connotes some matter which concerns public good and
    public interest. If the award, on the face of it, patently violates
    statutory provisions, it cannot be said to be in public interest.
    Thus, an award could also be set aside if it is patently illegal. It
    was, however, clarified that illegality must go to the root of the
    matter and if the illegality is of trivial nature, it cannot be held
    that award is against public policy.

    67. In Associate Builders v. DDA, (2015) 3 SCC 49, this Court
    held that an award would be patently illegal, if it is contrary to:

    (a) substantive provisions of law of India;

    (b) provisions of the 1996 Act; and

    (c) terms of the contract [See also three-Judge Bench decision of
    this Court in State of Chhattisgarh v. SAL Udyog (P) Ltd.,
    (2022) 2 SCC 275].

    The Court clarified that if an award is contrary to the substantive
    provisions of law of India, in effect, it is in contravention of
    Section 28(1)(a) of the 1996 Act. Similarly, violating terms of
    the contract, in effect, is in contravention of Section 28(3) of the
    1996 Act.

    68. In SsangyongEngg. & Construction Co. Ltd. v. NHAI,
    (2019) 15 SCC 131 this Court specifically dealt with the 2015
    Amendment which inserted sub-section (2-A) in Section 34 of
    the 1996 Act. It was held that “patent illegality appearing on the
    face of the award” refers to such illegality as goes to the root of
    matter, but which does not amount to mere erroneous
    application of law. It was also clarified that what is not
    subsumed within “the fundamental policy of Indian law”,
    namely, the contravention of a statute not linked to “public
    policy” or “public interest”, cannot be brought in by the
    backdoor when it comes to setting aside an award on the ground
    of patent illegality [See SsangyongEngg.
    & Construction Co.
    Ltd. v. NHAI
    , (2019) 15 SCC 131]. Further, it was observed,

    Signature Not Verified
    Digitally Signed
    By:HARVINDER KAUR
    BHATIA O.M.P.(COMM.) 124/2024 Page 21 of 38
    Signing Date:08.07.2026
    10:58:01
    reappreciation of evidence is not permissible under this category
    of challenge to an arbitral award [See SsangyongEngg. &
    Construction Co. Ltd. v. NHAI, (2019) 15 SCC 131].
    Perversity as a ground of challenge

    69. Perversity as a ground for setting aside an arbitral award was
    recognised inONGC Ltd. v. Western Geco International Ltd.,
    (2014) 9 SCC 263. Therein it was observed that an arbitral
    decision must not be perverse or so irrational that no reasonable
    person would have arrived at the same. It was observed that if an
    award is perverse, it would be against the public policy of India.

    70. In Associate Builders v. DDA, (2015) 3 SCC 49 certain tests
    were laid down to determine whether a decision of an Arbitral
    Tribunal could be considered perverse. In this context, it was
    observed that where:

    (i) a finding is based on no evidence; or

    (ii) an Arbitral Tribunal takes into account something irrelevant
    to the decision which it arrives at; or

    (iii) ignores vital evidence in arriving at its decision, such
    decision would necessarily be perverse.

    However, by way of a note of caution, it was observed that when
    a court applies these tests it does not act as a court of appeal and,
    consequently, errors of fact cannot be corrected. Though, a
    possible view by the arbitrator on facts has necessarily to pass
    muster as the arbitrator is the ultimate master of the quantity and
    quality of evidence to be relied upon. It was also observed that
    an award based on little evidence or on evidence which does not
    measure up in quality to a trained legal mind would not be held
    to be invalid on that score.

    71. In SsangyongEngg. & Construction Co. Ltd. v. NHAI,
    (2019) 15 SCC 131, which dealt with the legal position post the
    2015 Amendment in Section 34 of the 1996 Act, it was observed
    that a decision which is perverse, while no longer being a
    ground for challenge under “public policy of India”, would
    certainly amount to a patent illegality appearing on the face of
    the award. It was pointed out that an award based on no
    evidence, or which ignores vital evidence, would be perverse
    and thus patently illegal. It was also observed that a finding
    based on documents taken behind the back of the parties by the
    arbitrator would also qualify as a decision based on no evidence
    inasmuch as such decision is not based on evidence led by the
    parties, and therefore, would also have to be characterised as
    perverse [See SsangyongEngg.
    & Construction Co.
    Ltd. v. NHAI
    , (2019) 15 SCC 131].

    72. The tests laid down in Associate Builders v. DDA, (2015) 3
    SCC 49 to determine perversity were followed
    in SsangyongEngg.
    & Construction Co. Ltd. v. NHAI, (2019)
    15 SCC 131 and later approved by a three-Judge Bench of this

    Signature Not Verified
    Digitally Signed
    By:HARVINDER KAUR
    BHATIA O.M.P.(COMM.) 124/2024 Page 22 of 38
    Signing Date:08.07.2026
    10:58:01
    Court in Patel Engg. Ltd. v. North Eastern Electric Power
    Corpn. Ltd.
    , (2020) 7 SCC 167.

    73. In a recent three-Judge Bench decision of this Court in
    DMRC Ltd. v. Delhi Airport Metro Express (P) Ltd., (2024) 6
    SCC 357, the ground of patent illegality/perversity was
    delineated in the following terms: (SCC p. 376, para 39)
    “39. In essence, the ground of patent illegality is available
    for setting aside a domestic award, if the decision of the
    arbitrator is found to be perverse, or so irrational that no
    reasonable person would have arrived at it; or the
    construction of the contract is such that no fair or
    reasonable person would take; or, that the view of the
    arbitrator is not even a possible view. A finding based on
    no evidence at all or an award which ignores vital
    evidence in arriving at its decision would be perverse and
    liable to be set aside under the head of “patent illegality”.
    An award without reasons would suffer from patent
    illegality. The arbitrator commits a patent illegality by
    deciding a matter not within its jurisdiction or violating a
    fundamental principle of natural justice.”

    Scope of interference with an arbitral award

    74. The aforesaid judicial precedents make it clear that while
    exercising power under Section 34 of the 1996 Act the Court
    does not sit in appeal over the arbitral award. Interference with
    an arbitral award is only on limited grounds as set out in Section
    34
    of the 1996 Act. A possible view by the arbitrator on facts is
    to be respected as the arbitrator is the ultimate master of the
    quantity and quality of evidence to be relied upon. It is only
    when an arbitral award could be categorised as perverse, that on
    an error of fact an arbitral award may be set aside. Further, a
    mere erroneous application of the law or wrong appreciation of
    evidence by itself is not a ground to set aside an award as is
    clear from the provisions of sub-section (2-A) of Section 34 of
    the 1996 Act.

    75. In Dyna Technologies (P) Ltd. v. Crompton Greaves Ltd.,
    (2019) 20 SCC 1, paras 27-43, a three-Judge Bench of this
    Court held that courts need to be cognizant of the fact that
    arbitral awards are not to be interfered with in a casual and
    cavalier manner, unless the court concludes that the perversity of
    the award goes to the root of the matter and there is no
    possibility of an alternative interpretation that may sustain the
    arbitral award. It was observed that jurisdiction under Section 34
    cannot be equated with the normal appellate jurisdiction. Rather,
    the approach ought to be to respect the finality of the arbitral
    award as well as party’s autonomy to get their dispute
    adjudicated by an alternative forum as provided under the law.

    *****

    Signature Not Verified
    Digitally Signed
    By:HARVINDER KAUR
    BHATIA O.M.P.(COMM.) 124/2024 Page 23 of 38
    Signing Date:08.07.2026
    10:58:01
    Scope of interference with the interpretation/construction of a
    contract accorded in an arbitral award

    84. An Arbitral Tribunal must decide in accordance with the
    terms of the contract. In a case where an Arbitral Tribunal
    passes an award against the terms of the contract, the award
    would be patently illegal. However, an Arbitral Tribunal has
    jurisdiction to interpret a contract having regard to terms and
    conditions of the contract, conduct of the parties including
    correspondences exchanged, circumstances of the case and
    pleadings of the parties. If the conclusion of the arbitrator is
    based on a possible view of the matter, the Court should not
    interfere [See: SAIL v. Gupta Brother Steel Tubes Ltd., (2009)
    10 SCC 63; Pure Helium India (P) Ltd. v. ONGC, (2003) 8
    SCC 593; McDermott International Inc. v. Burn Standard Co.
    Ltd.
    , (2006) 11 SCC 181; MMTC Ltd. v. Vedanta Ltd., (2019)
    4 SCC 163].
    But where, on a full reading of the contract, the
    view of the Arbitral Tribunal on the terms of a contract is not a
    possible view, the award would be considered perverse and as
    such amenable to interference [South East Asia Marine Engg.
    & Constructions Ltd. v. Oil India Ltd.
    , (2020) 5 SCC 164].
    Whether unexpressed term can be read into a contract as an
    implied condition

    85. Ordinarily, terms of the contract are to be understood in the
    way the parties wanted and intended them to be. In agreements
    of arbitration, where party autonomy is the grund norm, how the
    parties worked out the agreement, is one of the indicators to
    decipher the intention, apart from the plain or grammatical
    meaning of the expressions used [BALCO v. Kaiser Aluminium
    Technical Services Inc., (2016) 4 SCC 126].

    86. However, reading an unexpressed term in an agreement
    would be justified on the basis that such a term was always and
    obviously intended by the parties thereto. An unexpressed term
    can be implied if, and only if, the court finds that the parties
    must have intended that term to form part of their contract. It is
    not enough for the court to find that such a term would have
    been adopted by the parties as reasonable men if it had been
    suggested to them. Rather, it must have been a term that went
    without saying, a term necessary to give business efficacy to the
    contract, a term which, although tacit, forms part of the contract
    [Adani Power (Mundra) Ltd. v. Gujarat ERC, (2019) 19 SCC
    9].

    87. But before an implied condition, not expressly found in the
    contract, is read into a contract, by invoking the business
    efficacy doctrine, it must satisfy the following five conditions:

    (a) it must be reasonable and equitable;

    Signature Not Verified
    Digitally Signed
    By:HARVINDER KAUR
    BHATIA O.M.P.(COMM.) 124/2024 Page 24 of 38
    Signing Date:08.07.2026
    10:58:01

    (b) it must be necessary to give business efficacy to the contract,
    that is, a term will not be implied if the contract is effective
    without it;

    (c) it must be obvious that “it goes without saying”;

    (d) it must be capable of clear expression;

    (e) it must not contradict any terms of the contract [Nabha
    Power Ltd. v. Punjab SPCL, (2018) 11 SCC 508, followed
    in Adani Power case, (2019) 19 SCC 9].

    (emphasis supplied)

    60. In the present case, learned counsel for the Petitioner has
    expressly confined the challenge to Claim Nos. 2, 3, 13 and 16. A
    careful reading of the pleadings, written submissions and oral
    arguments advanced before this Court demonstrates that the challenge
    to all four claims ultimately rests upon a single foundational
    grievance, namely, that the learned Tribunal erred in declining to rely
    upon the Rejected Letter addressed by the Respondent to DFCCIL and
    that such exclusion materially affected the adjudication of the
    aforesaid claims.

    61. The first aspect which this Court deems apposite to note is that
    this is not a case where the learned Tribunal overlooked, ignored or
    failed to notice the said communication. On the contrary, the
    Impugned Award contains a separate and detailed discussion
    regarding the provenance, admissibility and permissible use of the
    said document. The issue was specifically raised before the learned
    Tribunal and was adjudicated upon after considering the rival
    submissions advanced by the parties.

    62. The Impugned Award records that the learned Tribunal
    examined the competing explanations regarding the manner in which
    the Petitioner came into possession of the document and also
    considered the implications of Section 42A of the A&C Act.

    Signature Not Verified
    Digitally Signed
    By:HARVINDER KAUR
    BHATIA O.M.P.(COMM.) 124/2024 Page 25 of 38
    Signing Date:08.07.2026
    10:58:01

    63. The learned Tribunal, after an exhaustive discussion and
    analysis, ultimately concluded that the communication formed part of
    arbitral proceedings between DFCCIL and the Respondent and that
    the circumstances indicated that the document had come into the
    hands of the Petitioner through access obtained in relation to those
    proceedings. The learned Tribunal therefore held that admitting and
    relying upon the said communication would be inconsistent with the
    confidentiality obligations governing the arbitral process under
    Section 42A of the A&C Act.

    64. The relevant findings and discussion of the learned Tribunal,
    with regard to the aforesaid discussion, may be reproduced for the
    sake of clarity. The same reads as follows:

    “16.7. In the light of the said statutory provision, the Tribunal has
    no hesitation in holding that the letter dated 07.06.2017 which was
    produced by the Respondent in arbitration with the Employer
    cannot be introduced in these proceedings in breach of
    confidentiality of the proceedings in that arbitration.
    16.8. Now comes the question as to whether the Claimant got the
    copy of letter dated 7.6.2017 from officials of the Respondent and
    not from its Counsel and, if so, whether the provisions of Section
    42-A
    of the 1996 Act are not attracted.

    16.9. It needs to be appreciated that while denying that the letter
    was made available by the Counsel, the Claimant came up with
    specific plea that it was provided to it by the employees of the
    Respondent in one of the meetings. However, neither in pleadings
    nor in evidence there was reference as to when that meeting was
    held and what was the context. In the absence of these details the
    bald plea of the Claimant cannot be accepted. Even otherwise it is a
    matter of fact that the Sub-Contract was terminated on 28.01.2017.
    The Jetter in question was written on 07.06.2017. There is nothing
    on record to show that after 28.4.2017, specifically after 7.6.2017
    any meeting between the Claimant and the Respondent was held.
    Therefore, the Tribunal is not convinced that the letter was
    provided to the Claimant by the employees of the Respondent.
    16.10. The plea of the Respondent, on the other hand, viz. that the
    Claimant got access to the letter through the office of the Counself
    highly probable. Isis a matter of fact that in the dispute between the
    Respondent and the Employer, [in (OMP) (COMM) 375/2017)],

    Signature Not Verified
    Digitally Signed
    By:HARVINDER KAUR
    BHATIA O.M.P.(COMM.) 124/2024 Page 26 of 38
    Signing Date:08.07.2026
    10:58:01
    the same Counsel who is representing the Claimant in these
    proceedings, had appeared before the Hon’ble High Court of Delhi
    for the Employer. There is no denial that the same Counsel was
    representing the Employer in the Arbitration proceedings. In that
    capacity he/his office must have had access to the letter which, in
    all likelihood, was made available to the Claimant. This being so,
    breach of confidentiality occurred Admitting the letter in evidence
    in such a situation will not be legal and proper.
    16.11. While holding so, the Tribunal is conscious of the fact that
    Section 42A of the 1996 Act takes in its fold the arbitrator, the
    arbitration institute and the parties. This, however, does not mean
    that the Counsel and their office are immune. There is no
    gainsaying that the lawyer is an agent of the party and hence what a
    party is prohibited from, cannot be done through the Counsel.
    Therefore, even if the Counsel are not specifically mentioned in
    Section 42A of the 1996 Act, they being agents of the parties are
    equally bound to follow the mandate of law in the same manner as
    the parties are.

    16.12. As a consequence of the foregoing discussion, the objection
    as to admission of the letter dated 07.06.2017 is sustained.”

    65. The controversy before this Court therefore narrows down to a
    singular question as to whether the learned Tribunal committed any
    jurisdictional, legal or patent error in declining to rely upon the
    Rejected Letter.

    66. The Petitioner has contended that Section 42A merely imposes
    a duty of confidentiality and does not prescribe exclusion of evidence
    as a consequence of breach. This Court is unable to accept the
    aforesaid submission.

    67. Before adverting to the discussion on this aspect, this Court
    deems it apposite to take note of Section 42A of the A&C Act, which
    reads as follows:

    “42A. Confidentiality of information. – Notwithstanding anything
    contained by any other law for the time being in force, the
    arbitrator, the arbitral institution and the parties to the arbitration
    agreement shall maintain confidentiality of all arbitral proceedings
    except award where its disclosure is necessary for the purpose of
    implementation and enforcement of award.”

    Signature Not Verified
    Digitally Signed
    By:HARVINDER KAUR
    BHATIA O.M.P.(COMM.) 124/2024 Page 27 of 38
    Signing Date:08.07.2026
    10:58:01

    68. On a bare perusal of Section 42A of the A&C Act, it may be
    noted that it begins with a non-obstante clause and provides that
    “notwithstanding anything contained in any other law for the time
    being in force,……”. Therefore, the legislative object underlying the
    provision is manifest. Confidentiality constitutes one of the
    fundamental features of the arbitral process and the provision seeks to
    preserve the integrity of that process by ensuring that materials
    forming part of arbitral proceedings are not freely disseminated or
    utilised outside the proceedings for which they were produced.

    69. In the considered opinion of this Court, the submission
    advanced on behalf of the Petitioner proceeds on an unduly narrow
    construction of Section 42A of the A&C Act. It is true that the
    provision does not expressly employ the expression “inadmissibility”.
    However, the provision cannot be interpreted in a manner that renders
    the statutory protection of confidentiality illusory. The interpretation
    of a statutory provision must further the object sought to be achieved
    by the legislature and not defeat it.

    70. Section 42A of the A&C Act was introduced to statutorily
    recognise and preserve one of the defining attributes of arbitration,
    namely, confidentiality. The legislative intent is to ensure that
    pleadings, documents, evidence and materials forming part of arbitral
    proceedings are not freely disseminated or utilised outside the arbitral
    process except to the limited extent contemplated by law. If the
    interpretation canvassed by the Petitioner were to be accepted, a party
    would be free to procure documents originating from a separate
    arbitration and deploy them in collateral proceedings on the ground
    that Section 42A of the A&C Act merely creates an obligation but

    Signature Not Verified
    Digitally Signed
    By:HARVINDER KAUR
    BHATIA O.M.P.(COMM.) 124/2024 Page 28 of 38
    Signing Date:08.07.2026
    10:58:01
    carries no practical consequence. Such a construction would
    substantially erode the protection intended by Parliament and reduce
    the statutory mandate to a mere formality devoid of effective content.

    71. The question before the learned Tribunal was therefore not
    whether Section 42A of the A&C Act expressly creates a rule of
    inadmissibility in every case. The real issue was whether a document
    found to have originated from confidential arbitral proceedings and
    procured in circumstances inconsistent with the confidentiality
    obligation recognised under Section 42A of the A&C Act could
    legitimately be relied upon in a separate arbitration.

    72. In the considered view of this Court, the answer returned by the
    learned Tribunal accords with both the language and the underlying
    purpose of the provision. The learned Tribunal was justified in
    holding that permitting reliance upon such material would undermine
    the very confidentiality regime which Section 42A of the A&C Act
    seeks to protect. To hold otherwise would substantially undermine the
    confidentiality obligation recognised under Section 42A of the A&C
    Act and render the statutory protection susceptible to circumvention.

    73. Even assuming that Section 42A of the A&C Act does not, by
    itself, create a rigid rule of inadmissibility, the learned Tribunal was
    not divested of its authority to regulate the evidentiary record before
    it. The Tribunal was entitled to examine the provenance of the
    document, the circumstances in which it came into the possession of
    the Petitioner and the implications of permitting reliance upon
    material originating from a separate confidential arbitral proceeding.
    The decision to decline reliance on the document was therefore an
    exercise of evidentiary discretion and cannot, in the facts of the

    Signature Not Verified
    Digitally Signed
    By:HARVINDER KAUR
    BHATIA O.M.P.(COMM.) 124/2024 Page 29 of 38
    Signing Date:08.07.2026
    10:58:01
    present case, be characterised as a jurisdictional error, patent illegality
    or perversity.

    74. This Court also finds no merit in the submission that the
    communication dated 07.06.2017 was required to be considered
    merely because it was allegedly material to the Petitioner’s case.
    Relevance of a document and its permissible use are distinct
    considerations. A party cannot claim an unrestricted right to rely upon
    a document solely on the ground that it may support its case,
    irrespective of the circumstances in which such document was
    obtained or the legal obligations governing its disclosure. The learned
    Tribunal was therefore justified in first examining the permissibility of
    reliance upon the document before considering its evidentiary value.

    75. In this regard, learned counsel for the Petitioner has also sought
    to derive support from the decision of the Bombay High Court in
    Global Aviation Services Private Limited (supra), particularly
    Paragraph Nos. 115, 118 and 121 thereof, to contend that where a
    statute does not prescribe any consequence for breach of an obligation,
    a Court or Tribunal ought not to create one by judicial interpretation.
    There can be no quarrel with the said proposition. The aforesaid
    paragraphs, being Paragraph Nos. 115, 118 and 121, are reproduced
    herein below for ready reference:

    “115. The said provision also is silent on the issue i.e. if there are
    office objections raised by the office of this Court and if the
    petitioner is required to make any changes in the petition in the
    format or in the contents of the petition for the purposes of removal
    of such objections raised by the office, whether the petitioner is
    required to issue a fresh notice along with the papers with the
    corrections in the petition or not. Section 34(6) provides that such
    petition has to be disposed of within one year from the date on
    which the notice referred to in sub section 5 of section 34 is served
    upon the other party. If after giving the notice on the first day itself
    upon the receipt of the signed copy of the award from the arbitral
    Signature Not Verified
    Digitally Signed
    By:HARVINDER KAUR
    BHATIA O.M.P.(COMM.) 124/2024 Page 30 of 38
    Signing Date:08.07.2026
    10:58:01
    tribunal, if the petitioner issues such notice as referred to in sub
    section 5 of section 34 and does not file the petition for the next
    three months or even within 30 days after expiry of three months
    and if filed within the time prescribed under section 34(3), the
    petition remains in the office objections for another six months, an
    application filed under section 34(1) obviously cannot be disposed
    of within a period of one year from the date on which a notice
    referred to in sub section 5 of section 34 is served upon the other
    party. No consequence is provided in section 34(6) also if the
    arbitration petition is not disposed of by the Court within one year
    from the date of service of notice under section 34(5) of the
    Amendment Act. For this reason also, I am of the view that the
    provisions of section 34(5) and 34(6) cannot be construed as
    mandatory but has to be construed as directory. In my view, the
    requirement of the notice under section 34(5) of the Amendment
    Act is procedural in nature and not a substantive provision. The
    compliance of such procedural provision without providing any
    consequences in case of defiance thereof thus cannot be construed
    as mandatory and has to be construed as directory. Even if a notice
    is not given prior to the date of filing of the petition, the right of
    challenging an award vested in section 34 of the Arbitration &
    Conciliation Act, 1996 cannot be taken away.

    ***

    118. In my view, Mr. Mehta, learned senior counsel and Mr. Jain,
    learned counsel have rightly contended that issuance of such notice
    under section 34(5) is a requirement however, not mandatory. The
    discretionary power is given to the Courts to look into the facts in
    each case and decide if the same has to be made mandatory or not.
    If the provision of section 34(5) is construed as mandatory, it
    would take away the discretionary powers from the Court. Any
    strict interpretation of such procedural provision will cause
    inconvenience to the parties and would result in lengthening the
    procedure and defeating the entire purpose of the Act itself. High
    Court (Original Side) Rules already provides sufficient protection
    to the other party for issuance of a notice before the matter is heard
    by the Court with a view to obviate any delay in the matter.

    ***

    121. In my view since there is no consequence provided in section
    34(5)
    as well as section 34(6) for non-compliance of the
    requirement mentioned therein, the Court has to balance the
    situation and exercise its discretionary power to permit the
    petitioner to issue notice along with papers and proceedings upon
    the other party even after the petition is filed to avoid any delay in
    disposal of such application. In my view section 34(5) cannot be
    equated with section 80 of the Code of Civil Procedure, 1908. In
    view of the fact that now by virtue of the amendment to section 36,
    merely upon filing of the arbitration application for challenging an

    Signature Not Verified
    Digitally Signed
    By:HARVINDER KAUR
    BHATIA O.M.P.(COMM.) 124/2024 Page 31 of 38
    Signing Date:08.07.2026
    10:58:01
    award under section 34, there is no automatic stay, the petitioner
    who challenges the arbitral award by filing an application under
    section 34 would not wait and would not cause any delay by not
    issuing notice upon the other party to obviate any situation of
    execution of award under the provisions of the Code of Civil
    Procedure
    , 1908. For this reason also, I am of the view that the
    requirement under section 34(5) has to be construed as directory
    and nor mandatory.”

    76. However, the reliance placed upon the aforesaid decision is
    misplaced. The controversy before the Bombay High Court concerned
    the interpretation of Section 34(5) of the A&C Act and whether the
    requirement of prior notice before institution of a petition under
    Section 34 was mandatory or merely directory. The Court was
    therefore examining whether non-compliance with a procedural
    statutory requirement carried the consequence of invalidating the
    proceedings, despite the statute itself being silent in that regard.

    77. The issue before the learned Tribunal in the present case stood
    on an entirely different footing. The Tribunal was not concerned with
    imposing any statutory consequence for breach of Section 42A of the
    A&C Act, nor did it proceed on the basis that Section 42A itself
    creates a rule rendering every document obtained in breach of
    confidentiality inadmissible in evidence. The learned Tribunal merely
    examined the circumstances in which the document dated 07.06.2017
    came into the possession of the Petitioner and, having concluded that
    its disclosure would constitute a breach of confidentiality arising from
    separate arbitral proceedings, declined to place reliance upon it.

    78. The decision, therefore, was rooted in the Tribunal’s assessment
    of the provenance and evidentiary propriety of the document and not
    in the creation of a statutory disqualification not contemplated by
    Section 42A of the A&C Act.

    Signature Not Verified
    Digitally Signed
    By:HARVINDER KAUR
    BHATIA O.M.P.(COMM.) 124/2024 Page 32 of 38
    Signing Date:08.07.2026
    10:58:01

    79. Equally unpersuasive is the reliance placed upon Interplay
    Between Arbitration Agreements under Arbitration Act, 1996 and
    Stamp Act, 1899 (supra). The observations of the said Judgment,
    relied upon by the Petitioner, were rendered in the context of
    determining the legal effect of a non-obstante clause and the extent to
    which one statutory regime excludes or overrides another. The
    controversy therein concerned the interpretive operation of competing
    statutory provisions and not the admissibility of evidence allegedly
    sourced in breach of arbitral confidentiality. The paragraphs relied
    upon, being Paragraph Nos. 84 to 86, are reproduced herein under for
    ready reference:

    “84. Although a non obstante clause must be allowed to operate
    with full vigour, its effect is limited to the extent intended by the
    legislature. In Icici Bank Ltd. v. Sidco Leathers Ltd., (2006) 10
    SCC 452 a two-Judge Bench of this Court held that a non obstante
    clause must be interpreted by confining it to the legislative policy.
    Thus, even if a non obstante clause has wide amplitude, the extent
    of its impact has to be measured in view of the legislative intention
    and legislative policy.
    [JIK Industries Ltd.v. Amarlal V.
    Jumani
    , (2012) 3 SCC 255] In view of this settled legal position,
    the issue that arises for our consideration is the scope of the non
    obstante clause contained in Section 5 of the Arbitration Act.

    85. In Morgan Securities & Credit (P) Ltd. v. Modi Rubber
    Ltd.
    , (2006) 12 SCC 642, the issue before the two-Judge Bench
    was whether the provisions of the Arbitration Act would prevail
    over the provisions of the Sick Industrial Companies (Special
    Provisions) Act, 1985
    (SICA). While noting the non obstante
    clause contained in Section 5 of the Arbitration Act, this Court held
    that the non obstante clause has “limited application aiming at the
    extent of judicial intervention”. It was held that the Arbitration Act
    would not prevail over SICA since the latter enactment seeks to
    “achieve a higher goal”. In other words, the scope of the non
    obstante clause is limited to prohibiting the intervention of judicial
    authorities, unless it has been expressly provided for under Part I of
    the Arbitration Act
    .

    86. Similar to Article 5 of the Model Law, Section 5 uses the
    expression “in matters governed by this Part”. The use of this
    expression circumscribes the scope of judicial intervention to

    Signature Not Verified
    Digitally Signed
    By:HARVINDER KAUR
    BHATIA O.M.P.(COMM.) 124/2024 Page 33 of 38
    Signing Date:08.07.2026
    10:58:01
    matters expressly governed by Part I of the Arbitration Act. The
    matters governed by Part I inter alia include:

    86.1. Section 8 which mandates judicial authorities to refer parties
    to arbitration when prima facie there is a valid arbitration
    agreement;

    86.2. Section 9 which allows Courts to issue interim measures on
    an application made by a party to an arbitration agreement;
    86.3. Section 11 which empowers the Supreme Court or the High
    Courts to appoint arbitrators on an application made by parties to
    an arbitration agreement;

    86.4. Section 27 which allows the Arbitral Tribunal to request the
    Court for assistance in taking evidence; and
    86.5. Section 34 which empowers the Court to set aside an arbitral
    award on the basis of the limited grounds mentioned therein.”

    80. Far from assisting the Petitioner, the observations in Interplay
    Between Arbitration Agreements under Arbitration Act, 1996 and
    Stamp Act, 1899 (supra) reinforce the principle that a non-obstante
    clause must be construed in a manner that advances the legislative
    purpose underlying the provision in which it occurs. As already noted
    hereinabove, the legislative purpose underlying Section 42A of the
    A&C Act is preservation of arbitral confidentiality. The interpretation
    canvassed by the Petitioner would substantially diminish the efficacy
    of that protection. The reliance placed upon the aforesaid Judgment is
    therefore misconceived.

    81. Further, equally unpersuasive is the submission founded upon
    the premise that since the present Arbitral proceeding was governed
    by the ICC Rules, under which the rule of confidentiality is
    discretionary, the strict rules of confidentiality as envisaged under
    Section 42A of the A&C Act shall be inapplicable.

    82. This Court is of the considered view that even though the
    arbitration may have been conducted under the ICC Rules, however
    the seat of arbitration being in India, the arbitral proceedings remained
    subject to the mandatory provisions of the A&C Act. The rules of
    Signature Not Verified
    Digitally Signed
    By:HARVINDER KAUR
    BHATIA O.M.P.(COMM.) 124/2024 Page 34 of 38
    Signing Date:08.07.2026
    10:58:01
    institutionalised arbitral proceedings derive their efficacy from party
    autonomy, but operate subject to the governing law.

    83. A statutory mandate enacted by Parliament therefore cannot be
    diluted, displaced or overridden by institutional rules framed by an
    arbitral institution. Consequently, the learned Tribunal was fully
    justified in treating Section 42A of the A&C Act as controlling and
    binding irrespective of any interpretation sought to be placed upon the
    ICC Rules.

    84. There is yet another reason why the Petitioner cannot succeed.

    85. A substantial part of the challenge now advanced before this
    Court proceeds upon factual assertions regarding the manner in which
    the document allegedly entered the public domain and the legal
    consequences flowing therefrom. The Respondent has specifically
    contended that several of these contentions were never urged before
    the learned Tribunal.

    86. A Section 34 proceeding cannot be converted into a forum for
    reconstructing the arbitral case on an altogether different factual
    foundation. A party which had the opportunity to place a contention
    before the Tribunal but failed to do so cannot be permitted to invite a
    Court exercising jurisdiction under Section 34 to set aside an award on
    the basis of a case never presented before the arbitral forum.

    87. Now adverting to the next submission advanced on behalf of the
    Petitioner that the Rejected Letter had already entered the public
    domain because it formed part of proceedings before this Court. In the
    considered opinion, this submission is equally liable to be rejected.

    88. Merely because a document forms part of judicial proceedings
    does not automatically result in the document losing every attribute of

    Signature Not Verified
    Digitally Signed
    By:HARVINDER KAUR
    BHATIA O.M.P.(COMM.) 124/2024 Page 35 of 38
    Signing Date:08.07.2026
    10:58:01
    confidentiality. Whether a document can be said to have entered the
    public domain is a question dependent upon the circumstances in
    which access thereto is obtained and the legal regime governing such
    access. The learned Tribunal was not presented with any material
    conclusively establishing that the confidentiality attaching to the
    document had ceased to exist. On the contrary, the Tribunal returned a
    factual finding that the explanation furnished by the Petitioner
    regarding the source of the document was not worthy of acceptance
    and accepted the Respondent’s version regarding its provenance.

    89. Such findings are findings of fact based upon appreciation of
    the material before the Tribunal. No perversity has been demonstrated
    in the said findings. This Court therefore finds no reason to interfere
    with the same.

    90. Ultimately, what emerges from the record is that the learned
    Tribunal was alive to the controversy surrounding the Rejected Letter,
    considered the rival submissions advanced by the parties, examined
    the circumstances in which the document came into the possession of
    the Petitioner, analysed the effect of Section 42A of the A&C Act and
    thereafter arrived at a reasoned conclusion that the document ought
    not to be relied upon. The decision was thus neither rendered without
    consideration of the issue nor founded upon an omission to notice
    relevant material.

    91. It is also significant that the Petitioner has not independently
    assailed the merits of the findings returned by the learned Tribunal in
    relation to Claim Nos. 2, 3, 13 and 16. The challenge is founded
    entirely upon the exclusion of the communication dated 07.06.2017.
    Consequently, once this Court finds no infirmity in the learned

    Signature Not Verified
    Digitally Signed
    By:HARVINDER KAUR
    BHATIA O.M.P.(COMM.) 124/2024 Page 36 of 38
    Signing Date:08.07.2026
    10:58:01
    Tribunal’s approach towards the said document, the very foundation
    of the challenge to the rejection of the aforesaid claims necessarily
    falls. In the absence of any independent challenge to the merits of the
    findings recorded on the said claims, this Court is not called upon to
    examine the correctness thereof.

    92. Having considered the scheme, object and purpose of Section
    42A of the A&C Act, this Court is of the considered opinion that the
    interpretation adopted by the learned Tribunal accords with the
    legislative intent underlying the provision. The challenge mounted by
    the Petitioner proceeds upon an interpretation which, if accepted,
    would substantially dilute the statutory protection of confidentiality
    recognised by Parliament. The Court therefore finds no error in the
    legal approach adopted by the learned Tribunal while declining to rely
    upon the said communication.

    93. This Court is also unable to discern any conflict with the public
    policy of India or any contravention of the fundamental policy of
    Indian law within the meaning of Section 34(2)(b)(ii) of the A&C Act.
    The challenge mounted by the Petitioner essentially invites this Court
    to undertake a re-examination of the correctness of the learned
    Tribunal’s evidentiary determination. Such an exercise would fall
    outside the permissible confines of judicial review under Section 34 of
    the A&C Act.

    94. Likewise, no patent illegality appearing on the face of the
    Award within the meaning of Section 34(2A) of the A&C Act has
    been demonstrated. The Impugned Award neither disregards any
    binding statutory provision nor adopts an interpretation contrary to the
    scheme, object or purpose of the A&C Act. The challenge, in

    Signature Not Verified
    Digitally Signed
    By:HARVINDER KAUR
    BHATIA O.M.P.(COMM.) 124/2024 Page 37 of 38
    Signing Date:08.07.2026
    10:58:01
    substance, seeks reconsideration of a reasoned determination rendered
    by the learned Tribunal on the admissibility and use of material arising
    from separate arbitral proceedings, which falls beyond the permissible
    scope of interference under Section 34 of the A&C Act.

    95. In view of the aforesaid discussion, this Court is of the
    considered opinion that the Petitioner has failed to establish any
    ground falling within the limited parameters of interference available
    under Section 34 of the A&C Act. The Impugned Award reflects due
    consideration of the pleadings, evidence and submissions advanced
    before the learned Tribunal and does not suffer from any infirmity
    warranting interference by this Court.

    DECISION:

    96. Accordingly, the present Petition is dismissed, and
    consequently, the Impugned Award shall remain undisturbed.

    97. The present Petition, along with pending Application(s), if any,
    stands disposed of in aforesaid terms.

    98. There shall be no Order as to the costs.

    HARISH VAIDYANATHAN SHANKAR, J.

    JULY 06, 2026|DJ

    Signature Not Verified
    Digitally Signed
    By:HARVINDER KAUR
    BHATIA O.M.P.(COMM.) 124/2024 Page 38 of 38
    Signing Date:08.07.2026
    10:58:01



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here