Jindal Steel And Power Ltd vs Chhattisgarh State Electricity … on 30 March, 2026

    0
    51
    ADVERTISEMENT

    Chattisgarh High Court

    Jindal Steel And Power Ltd vs Chhattisgarh State Electricity … on 30 March, 2026

                                                                  1
    
    
    
    
                                                                                        2026:CGHC:14839
    
                                                                                                        AFR
    
                                      HIGH COURT OF CHHATTISGARH AT BILASPUR
    
                                                     WPC No. 1927 of 2016
                                                Order reserved on 19/12/2025
                                                Order delivered on 30/03/2026
    
                          1 - Jindal Steel And Power Ltd. S/o A Company Registered Under The
                          Provisions Of Companies Act, 1956, Having Its Corporate Office At Jindal
                          Centre, 12 Bhikaji Cama Place, New Delhi- 110066, Through Mr. Rajesh
                          Agrawal, Associate- Vice- President., Delhi
    
    
                          2 - Mr. Rajesh Agrawal, S/o Shri B.K. Agrawal Aged About 45 Years
                          Shareholder Of Petitioner No.1, A V P- Electrical Power System, Jindal
                          Steel And Power Ltd., R/o Hill View Colony, J S P L, Raigarh, Chhattisgarh,
                          District : Raigarh, Chhattisgarh
                                                                                              ... Petitioners
                                                              versus
    
                          1 - Chhattisgarh State Electricity Regulatory Commission Irrigation Colony,
                          Shanti Nagar, Raipur, Chhattisgarh 492001, Chhattisgarh
    
    
                          2 - Chhattisgarh State Power Distribution Company Ltd., A Successor
                          Company Of C S E B, 4th Floor, Vidyut Sewa Bhavan, Daganiya, Raipur,
                          Chhattisgarh 492013, District : Raipur, Chhattisgarh
    
    
                          3 - Chhattisgarh State Power Transmission Company Ltd., A Successor
                          Company Of C S E B, Energy Info Tech Centre, Danganiya, Raipur,
    VED                   Chhattisgarh 492013, District : Raipur, Chhattisgarh
    PRAKASH
    DEWANGAN                                                                              ... Respondents

    Digitally signed by

    VED PRAKASH (Cause title taken from Case Information System)
    DEWANGAN
    Date: 2026.04.04
    19:30:11 +0530
    2

    SPONSORED

    For Petitioners : Mr. Abhimanyu Bhandari, Senior
    Advocate (through virtual mode) along
    with Mr. Bhaskar Payasi, Mr. Jai
    Dhanani, Ms. Divya Chaturvedi, Mr.
    Saransh Shaw, Mr. Pranav Sood and Mr.
    Pankhuri Gupta, Advocates

    For Respondent No.1 : Mr. Adhiraj Surana, Advocate

    For Respondents No. 2 & 3 : Mr. Rajkumar Mehta, Advocate (through
    virtual mode) with Mr. Varun Sharma,
    Advocate

    Hon’ble Shri Justice Ravindra Kumar Agrawal

    C.A.V. Order

    1. For the sake of convenience, the following terms shall hereinafter be

    referred to as under:

    Power Purchase Agreement – “PPA”

    Chhattisgarh State Power Distribution Co. Ltd. – “CSPDCL”

    Chhattisgarh State Power Transmission Co. Ltd. – “CSPTCL”

    Short Term Open Access – “STOA”

    Indian Electricity Grid Code – “IEGC”

    Inter State Generating Station – “ISGS”

    Availability Based Tariff – “ABT”

    State Load dispatch Centre – “SLDC”

    Electricity Power Survey – “EPS”

    Inter State Generation Station – “ISGS”

    Load Factor – “LF”

    National Electricity Policy – “NEP”

    2. The petitioners have filed the present writ petition challenging the

    judgment dated 26-05-2016 (Annexure P-1) passed by the Appellate
    3

    Tribunal for Electricity, in Appeal Nos. 41 and 67 of 2015, and also

    against the demand notice dated 07-07-2016 (Annexure P-2) issued

    by the Respondent No. 2, letter dated 21-07-2016 (Annexure P-3),

    letter dated 25-07-2016 (Annexure P-4), to issue No Objection

    Certificate to allow the petitioner to open access from the

    Respondent No. 3, and also to declare that the petitioner No. 1 is not

    liable to refund of amount of Rs. 153.55 Crore to the Respondent No.

    2, and prayed for the following reliefs:-

    “It is therefore most respectfully prayed that this

    Hon’ble Court may be pleased to:

    10.1. Admit the Petition and set aside the Impugned

    Judgment dated 26.05.2016 (marked as Annexure P-

    1) passed by the Appellate Tribunal for Electricity in

    Appeal Nos. 41 & 67 of 2015 : CSPDLC vs. CSERC;

    10.2. Quash the Impugned Demand Notice dated

    07.07.2016 (marked as Annexure P-2) passed by the

    Chhattisgarh State Power Distribution Company Ltd.;

    10.3. Quash the Impugned Letter dated 21.07.2016

    (marked as Annexure P-3) passed by the Chhattisgarh

    State Power Distribution Company Ltd.;

    10.4. Quash the Impugned Rejection Letter dated

    25.07.2016 (marked as Annexure P-4) passed by the

    Chhattisgarh State Power Distribution Company Ltd.;

    10.5. Direct the Chhattisgarh State Power Distribution

    Company Ltd. to issue No Objection Certificate to
    4

    allow the Petitioner No.1 to avail Open Access from

    the Chhattisgarh State Power Transmission Co. Ltd;

    10.6. Direct the Chhattisgarh State Power

    Transmission Company Ltd. to grant open access to

    the Petitioner No.1 to supply power;

    10.7. Declare that Petitioner is not liable to refund

    Rs.153.55 Crore to the Chhattisgarh State Power

    Distribution Company Ltd. in relation to the power

    supplied to it in the FY 2011-12 and FY 2012-13; and

    10.8. Pass any such other Order or Orders as this

    Hon’ble Court may deem fit and proper in facts of the

    present case.”

    3. Petitioner No.1 is a company incorporated under the Companies Act,

    1956 and is engaged inter-alia in the business of manufacturing

    sponge iron and steel, as well as the generation of power. The

    Petitioner No.1 has established Captive Power Plants (CPPs) at

    Village Patrapali, District Raigarh, and is a “generating company”

    within the meaning of Section 2(28) of the Electricity Act, 2003. The

    installed capacity of its captive power plant was initially 265.7 MW,

    which was subsequently enhanced to 325.7 MW. Mr. Rajesh Agarwal

    has been authorized to prosecute the petition on behalf of Petitioner

    No.1 by virtue of a Board Resolution dated 26.07.2016.

    4. On 02-11-2011, a PPA was executed between the Petitioner No. 1

    and the Respondent No. 2, CSPDCL, for the supply of Electricity.

    The initial PPA provided for the sale of 150 MW power for the period
    5

    01.11.2011 to 30.06.2012 and incorporated specific provisions

    regarding load factor calculation, scheduled power, and tariff

    determination based on formulae adopted from the State

    Commission’s Suo Motu Order. The agreement permitted injection of

    power up to 110% during off-peak hours and 120% during peak

    hours, with excess supply beyond these limits compensated at Rs. 1

    per unit. The tariff was linked to the load factor, with a minimum

    effective rate of Rs. 1.50 per unit.

    5. Subsequently, supplementary PPAs were executed on 12.07.2012,

    13.08.2012, and 24.01.2013 covering different periods up to

    30.06.2013, including variation in contracted capacity (150 MW and

    later 75 MW). The Petitioner supplied power in terms of these

    agreements during Financial Years 2011-12 and 2012-13 and

    raised invoices, including load factor-based billing and concessional

    rates for excess injection. Respondent No.2 accepted the supplies

    and made payments without any protest, at average rates of Rs. 2.42

    per kWh and Rs. 2.66 per kWh, respectively.

    6. In 2014, Respondent No.2 filed Tariff Petition No. 07/2014 before the

    State Commission seeking true-up and tariff determination. By order

    dated 12.06.2014, the State Commission approved a minimum base

    rate of Rs. 1.50 per kWh for power procured from the Petitioner,

    treating such power as “non-firm”. It is the case of the petitioners that

    this classification was not contemplated under the agreements

    between the parties. A Review Petition was filed by Respondent No.2
    6

    before the State Commission, which was dismissed on 08.12.2014,

    affirming the earlier findings.

    7. The Respondent No.2 thereafter challenged the tariff and review

    orders before the Appellate Tribunal for Electricity in Appeals Nos. 41

    and 67 of 2015. By judgment dated 26.05.2016, the Appellate

    Tribunal upheld the orders of the State Commission. Following the

    Tribunal’s judgment, Respondent No.2 issued a demand notice dated

    07.07.2016 claiming a refund of Rs. 153.55 crore along with interest,

    alleging overcharging by the Petitioner for power supplied during FYs

    2011-12 and 2012-13. The Petitioner disputes this demand as

    arbitrary and contrary to the binding contractual terms, emphasizing

    that all invoices were raised strictly in accordance with the PPAs and

    duly honoured without objection at the relevant time.

    8. The Petitioner sought Short Term Open Access (STOA) in July 2016

    for the supply of power through power exchanges. However,

    Respondent No.2 refused to grant a No Objection Certificate (NOC),

    citing the alleged outstanding dues arising from the impugned

    demand. Consequently, Respondent No.3 (CSPTCL) also rejected

    the Petitioner’s application for open access on 25.07.2016 on the

    same ground, thereby preventing the Petitioner from participating in

    power exchange transactions.

    9. It is also the case of the petitioner that the Petitioner No.1 duly

    supplied power to Respondent No.2/CSPDCL during FYs 2011-12

    and 2012-13 and raised invoices in accordance with the terms of the

    PPAs, computing tariff on the basis of load factor during peak and
    7

    off-peak hours and charging only Re. 1.00 per kWh for power

    injected beyond 110% (off-peak) and 120% (peak) limits, with load

    factor calculated on a weekly basis. Respondent No.2 accepted such

    supplies and made payments at average rates of Rs. 2.42 per kWh in

    FY 2011-12 and Rs. 2.66 per kWh in FY 2012-13 without any

    objection, and at no point prior to the impugned demand did it allege

    that the power supplied was non-firm or that the Petitioner had

    overcharged. The PPAs, being binding contracts, cannot be

    unilaterally disregarded by Respondent No.2 after a lapse of several

    years to seek refund of amounts already paid. It is further apparent

    that the said PPAs were neither placed before the State Commission

    under Section 62 of the Electricity Act, 2003 nor adequately

    explained during tariff proceedings, thereby depriving the

    Commission of the opportunity to examine their terms. Significantly,

    Respondent No.2 itself admitted in the Review Order that the PPAs

    were in consonance with the State Commission’s orders, that

    payments were made in accordance with their terms, and that no

    retrospective alteration of such concluded transactions is

    permissible.

    10. The Petitioners also challenged the demand notice and denial of

    NOC through representations dated 22.07.2016 and 23.07.2016,

    asserting that no direction had been issued by the State Commission

    or the Appellate Tribunal requiring refund, and that liability could not

    be imposed without affording the Petitioner an opportunity of hearing.

    The Petitioner further contended that the PPAs were binding and
    8

    could not be retrospectively altered, particularly after full performance

    and settlement of payments.

    11. Aggrieved by the demand of Rs. 153.55 crore, denial of open access,

    and reliance on orders passed in proceedings to which it was not a

    party, the Petitioner has filed the present petition seeking quashing of

    the Appellate Tribunal’s judgment dated 26.05.2016, the demand

    notice, and related communications. The Petitioner also seeks

    directions restraining Respondent No.2 from recovering the said

    amount and for the grant of NOC and open access facilities.

    12. The Respondent No. 1, Chhattisgarh State Electricity Regulatory

    Commission, contested the claim of the petitioner and filed its return

    with the preliminary objection that the present petition is not

    maintainable and is liable to be dismissed in limine on account of the

    availability of efficacious alternative remedies under the provisions of

    the Electricity Act, 2003. It is submitted that the Petitioner has a

    statutory remedy under Section 125 of the Act of 2003 to assail the

    order dated 26.05.2016 passed by the Appellate Tribunal before the

    Hon’ble Supreme Court. Further, the Petitioner could have availed

    the remedy of review under Section 120(2)(f) of the Act before the

    Appellate Tribunal, particularly on the ground of alleged denial of

    opportunity of hearing. It is also pleaded that the Petitioner has an

    alternative remedy under Section 86(1)(f) of the Act to approach the

    State Commission for adjudication of disputes, which remedy has not

    been exhausted. The consequential proceedings, including the

    demand notice dated 07.07.2016, emanate from the order of the
    9

    Appellate Tribunal, and therefore, unless the said order is set aside

    by the competent forum, no interference with the consequential

    actions is warranted.

    13. The Respondent No. 1 also pleaded that the demand raised against

    the Petitioner is justified and in consonance with the Tariff Orders

    dated 12.06.2014 and 08.12.2014 passed by the State Commission

    in exercise of its statutory powers. The Commission, while

    undertaking the true-up exercise for FYs 2011-12 and 2012-13,

    examined the nature of power supplied by the Petitioner and found

    the same to be non-firm and unstable, based on load curve analysis

    and findings recorded in earlier appellate proceedings. The

    Commission accordingly approved only a minimum base rate of Rs.

    1.50 per kWh for such power, observing that the burden of procuring

    non-firm power at higher rates cannot be passed on to consumers. It

    is further pleaded that the PPAs themselves contained a stipulation

    making them subject to directions and guidelines issued by the

    Commission, thereby rendering the tariff orders binding upon the

    parties.

    14. It is also the reply of the Respondent No. 1 that due process was

    followed by the State Commission as well as the Appellate Tribunal,

    including issuance of public notices and affording opportunity of

    hearing to stakeholders. The notices of tariff and review proceedings

    were published in newspapers, and that a representative of the

    Petitioner had participated in the review proceedings, thereby

    negating the plea of lack of opportunity of hearing or knowledge of
    10

    the proceeding. Similarly, the Appellate Tribunal also issued public

    notices prior to deciding the appeals. Therefore, the Petitioner cannot

    now claim ignorance of the proceedings or violation of principles of

    natural justice.

    15. The Respondent No. 2/CSPDCL have filed their return and have

    raised a preliminary objection as to the maintainability of the present

    writ petition on the ground that the petitioners had an effective and

    statutory alternative remedy. It is submitted that the order dated

    12.06.2014 passed by the State Commission in Petition Nos. 05 to

    08 of 2014 (T), including Petition No. 07/2014 filed by respondent No.

    2, was subjected to challenge before the Appellate Tribunal for

    Electricity (APTEL) by way of Appeal Nos. 41 and 67. The said

    appeals, directed against both the original order and the review order

    dated 08.12.2014, were dismissed by APTEL by a common judgment

    dated 26.05.2016. The petitioners have not preferred any appeal

    before the Hon’ble Supreme Court under Section 125 of the

    Electricity Act, 2003. Therefore, the judgment of APTEL has attained

    finality and is binding on the petitioners, thereby precluding the

    petitioners from re-agitating the same issues in the present writ

    proceedings.

    16. It is further pleaded that the petitioner company had entered into

    Power Purchase Agreements offering 150 MW of firm power on a

    round-the-clock basis, with a permissible reduction up to 20% and a

    guaranteed minimum supply of 120 MW, subject to the provisions of

    the Electricity Act, 2003 and regulatory guidelines issued by the State
    11

    Commission from time to time. Respondent No. 2, being a

    distribution licensee under Section 14 of the Act, procured power on

    a short-term basis in accordance with tariff orders and regulatory

    framework evolved by the State Commission through various suo

    motu proceedings since 2009, wherein ceiling tariffs and

    procurement conditions were determined after due public

    consultation and stakeholder participation, including that of the

    petitioners. In continuation thereof, the State Commission, while

    determining tariff in Petition Nos. 05 to 08 of 2014 (T), examined the

    short-term power purchases made by respondent No. 2 from the

    petitioner and, on analysis of the load curve and injection pattern,

    concluded that the power supplied was intermittent and non-firm in

    nature, causing grid disturbances, and accordingly restricted the tariff

    to a lower rate treating it akin to infirm power. Though respondent

    No. 2 initially contested these findings, its challenge failed, as the

    review petition was partly allowed and the subsequent appeals

    preferred before APTEL against the orders dated 12.06.2014 and

    08.12.2014 were dismissed by a common judgment dated

    26.05.2016, affirming that unstable and fluctuating power supply

    cannot be equated with firm power and must be compensated at a

    lower tariff.

    17. It is further pleaded that the proceedings before the State

    Commission were conducted in accordance with the Chhattisgarh

    State Electricity Regulatory Commission (Conduct of Business)

    Regulations, 2009. Under the said Regulations, individual notices to

    stakeholders are not mandatory; rather, the procedure contemplates
    12

    issuance of public notice to ensure wider participation. In the present

    case, the petitions were uploaded on the Commission’s website,

    copies were made available at the offices of the petitioners, and a

    public notice along with the gist of the petitions was published in

    newspapers inviting objections and suggestions. Public hearing was

    conducted at Raipur on 21.05.2014, followed by a separate

    interaction on 22.05.2014 with representatives of industries, HT

    consumers, and industrial associations. Additionally, consultations

    were held with members of the State Advisory Committee. The

    Commission, after considering all objections and performing due

    diligence, finalized its findings. A further public notice dated

    26.04.2014 was also issued. Thus, the petitioners were duly notified

    and had full opportunity to participate.

    18. The respondent No. 2 had filed Review Petition No. 35 of 2014 on

    31.07.2014 before the State Commission. During the course of

    hearing on 28.10.2014, the authorized representative of petitioner

    No. 1, namely N.K. Chandiramani (DGM, JSPL), was present, as

    reflected in the order sheet. The review petition was ultimately

    disposed of on 08.12.2014. Despite having knowledge of and

    participating in the proceedings, the petitioners failed to effectively

    pursue their remedies or challenge the outcome at the appropriate

    stage. Even thereafter, when APTEL dismissed the appeals on

    26.05.2016, the petitioners did not avail the statutory remedy of

    appeal before the Hon’ble Supreme Court. The respondents submit

    that such conduct demonstrates negligence and attracts the doctrine

    of acquiescence.

    13

    19. It is also pleaded that the dispute pertains to highly technical issues

    involving tariff determination, nature of power supply, and grid

    stability. The State Commission, exercising powers under Sections

    62 and 86 of the Electricity Act, examined the power purchase

    agreements, load curves, and injection patterns, and concluded that

    the power supplied by the petitioner was non-firm in nature due to its

    fluctuating and unstable characteristics. Consequently, the tariff was

    restricted in line with the treatment of infirm power. This finding was

    specifically affirmed by APTEL, which observed that such unstable

    injection patterns create commercial complications and disturb the

    demand-supply balance. The respondents contend that such

    findings, based on technical data and expert analysis, are not

    amenable to judicial review under Article 226, particularly where

    disputed questions of fact are involved.

    20. The respondent No. 2 further pleaded that the present petition suffers

    from non-joinder of necessary and proper parties. Several

    stakeholders, including industries and associations, who participated

    in the proceedings before the State Commission and opposed the

    claims, have not been impleaded in the present writ petition.

    Additionally, the petitioners have not challenged the foundational

    order dated 12.06.2014 or the applicability of the 2009 Regulations,

    which governed the entire process. In the absence of such challenge,

    the relief sought becomes untenable. It is also pleaded that the

    petitioners had knowledge of the APTEL judgment at least by

    07.07.2016 through the demand notice issued by respondent No. 2,

    yet failed to take any appropriate remedial steps.
    14

    21. On the issue of recovery, the respondent No. 2 pleaded that the

    demand raised is in accordance with Section 62(6) of the Electricity

    Act, 2003, which mandates that any excess tariff recovered by a

    generating company shall be refundable along with interest at the

    bank rate. The demand of Rs. 153.55 crore has been raised pursuant

    to the findings of the State Commission and APTEL, and is

    supported by audited accounts and financial records considered

    during tariff determination. It is also pleaded that permitting the

    petitioners to retain such excess amount would result in unjust

    enrichment and would be contrary to public interest, particularly as

    respondent No. 2 is a public utility accountable to consumers.

    22. Respondent No. 3 has also filed its return separately and in

    preliminary submissions, have pleaded the statutory framework of

    the Electricity Act, 2003, to justify their actions. It is pleaded that

    under Section 31 of the Act, the State Load Dispatch Centre (SLDC)

    has been constituted as the apex body for integrated operation of the

    power system within the State, and is operated by the State

    Transmission Utility in terms of Section 39. The SLDC is statutorily

    prohibited from engaging in the trading of electricity and is entrusted

    with critical operational responsibilities relating to grid management,

    scheduling, and dispatch. Further, under Section 86(1) of the Act, the

    State Regulatory Commission is vested with wide powers, including

    the determination of tariff, the regulation of procurement of electricity

    by distribution licensees, facilitation of intra-State transmission,

    adjudication of disputes, and specification of the State Grid Code,

    while ensuring transparency and adherence to national policies. In
    15

    furtherance of its statutory functions, the State Commission has

    notified the Chhattisgarh State Electricity Grid Code, 2011, and the

    SLDC discharges its functions under Section 32 of the Act, which

    include ensuring optimum scheduling and dispatch of electricity,

    monitoring grid operations, maintaining quality of electricity,

    supervising intra-State transmission, and carrying out real-time grid

    control for secure and economic operation. Additionally, under

    Section 33, the SLDC is empowered to issue binding directions to

    generating companies and licensees to maintain grid discipline, and

    such directions are mandatorily required to be complied with, failing

    which penal consequences may follow. The SLDC is also obligated

    to act in coordination with higher load dispatch centres and to ensure

    safe and stable grid operations.

    23. The Respondent No. 3 further pleaded that the petitioner No. 1 has

    consistently injected fluctuating and non-firm power into the State

    grid over a prolonged period of time, including during the subsistence

    of the Power Purchase Agreements executed with respondent No. 2.

    The SLDC had repeatedly issued communications and directions to

    the petitioners, calling upon them to adhere to scheduled injection

    and grid discipline. The petitioner not only failed to comply but also

    admitted its inability to supply firm power on account of fluctuating

    internal consumption patterns. The SLDC, in multiple letters dated

    between 2014 and 2016, highlighted substantial deviations in

    injection ranging from zero to excessive levels, violation of open

    access regulations, and potential threat to grid security, even warning

    of disconnection in case of continued non-compliance.
    16

    Simultaneously, the SLDC also apprised the State Commission of

    the persistent issues arising from such fluctuating power supply and

    sought appropriate guidelines for the identification and treatment of

    “non-firm” or “poor quality” power. Several communications

    addressed to the Commission between 2014 and 2016 emphasized

    the operational difficulties faced in maintaining grid discipline,

    including warnings received from higher load dispatch centres. The

    SLDC specifically requested clarity on the criteria for non-firm power,

    permissible actions against defaulting generators, and the

    permissibility of granting open access in such cases. These

    communications were made in discharge of statutory obligations,

    including under Section 33(4) of the Act.

    24. It is further pleaded that the State Commission, while passing the

    tariff order dated 12.06.2014 in Petition No. 07 of 2014 (T), examined

    the load curve and injection pattern of the petitioner and recorded a

    categorical finding that the power supplied was highly fluctuating,

    unstable, and non-firm in nature. It was observed that such erratic

    supply adversely impacted grid stability and compelled the

    distribution licensee to resort to overdrawal or underdrawal from the

    grid, attracting penalties. Consequently, the Commission held that

    such power could not be treated at par with firm power and restricted

    the tariff to a base rate of Rs. 1.50 per unit, further issuing specific

    directions to discourage procurement and injection of such non-firm

    power and mandating the SLDC to monitor and regulate the same.
    17

    25. The review petition filed by respondent No. 2 was disposed of on

    08.12.2014, wherein the Commission reaffirmed its earlier findings,

    noting that no new material or error apparent on record had been

    brought forth. The Commission also relied on independent studies

    and consistent observations of the SLDC regarding the fluctuating

    injection pattern of the petitioner. The directives issued in the original

    order, including those relating to grid discipline and monitoring of

    non-firm power, thus attained finality at the regulatory level.

    Aggrieved thereby, respondent No. 2 preferred appeals before the

    Appellate Tribunal for Electricity (APTEL), which, by its judgment

    dated 26.05.2016, upheld the findings of the State Commission in

    entirety. The Tribunal took note of the petitioner’s own admissions in

    earlier proceedings regarding the fluctuating nature of surplus power

    and inability to supply consistent power due to variable industrial

    demand. It was categorically held that such an unstable power

    supply has commercial as well as operational implications, disturbs

    demand-supply balance, and cannot be equated with firm power. The

    Tribunal affirmed that such power must be treated as akin to infirm

    power and compensated at a significantly lower rate.

    26. It is further pleaded that the petitioners have neither challenged the

    tariff order dated 12.06.2014 nor the directives issued therein, nor the

    judgment of APTEL. In compliance with the said binding decisions

    and statutory mandate, the SLDC has continued to regulate and

    restrict open access to the petitioner in view of its non-compliance

    with grid discipline and continued injection of non-firm power. The

    rejection of short-term open access applications made by the
    18

    petitioners in July-August 2016 was thus based on statutory

    obligations, regulatory directives, and binding judicial findings, and

    not merely on account of any monetary dispute as alleged. The

    answering respondent has acted strictly within the framework of the

    Electricity Act, 2003, the State Grid Code, and the binding directions

    of the State Commission and APTEL. The continued conduct of the

    petitioner in injecting fluctuating power, coupled with its admitted

    inability to maintain firm supply, justified regulatory intervention and

    denial of open access in the interest of grid security, discipline, and

    public interest.

    27. Learned counsel for the petitioners would submit that the present writ

    petition has been filed by the Petitioner, Jindal Steel & Power Limited

    (JSPL), assailing the demand notice dated 07.07.2016 issued by the

    Respondent No. 2, Chhattisgarh State Power Distribution Company

    Limited (CSPDCL), seeking recovery of Rs. 153.55 crores, along with

    the consequential denial of open access and the underlying judgment

    dated 26.05.2016 passed by the Appellate Tribunal for Electricity

    (APTEL). The core challenge of the Petitioner is that the impugned

    demand is wholly without jurisdiction, contrary to the settled

    principles of law, and has been raised in complete violation of

    principles of natural justice.

    28. The undisputed fact that the Petitioner was never impleaded as a

    party in the proceedings before the State Commission or before

    APTEL. The true-up proceedings initiated by CSPDCL, the

    subsequent review proceedings, and the appeals before APTEL
    19

    were all conducted without issuing any notice to the Petitioner,

    despite the fact that the entire dispute pertained to power supplied by

    the Petitioner under duly executed Power Purchase Agreements.

    The Petitioner was thus denied any opportunity to place its case,

    clarify the nature of supply, or defend the contractual arrangement. It

    is a settled proposition of law that no adverse order can be passed

    against a party without affording it a reasonable opportunity of

    hearing, and any action taken in breach thereof stands vitiated. The

    impugned demand is ex facie illegal, as it seeks to impose a financial

    liability upon the Petitioner on the basis of proceedings to which it

    was not a party and in which no findings have been recorded against

    it. A perusal of the true-up order, review order, and the appellate

    judgment would reveal that the findings, if any, are against CSPDCL

    alone, particularly attributing negligence to it in procuring power.

    There is not even a whisper in the said orders directing recovery from

    the Petitioner or holding that the Petitioner is liable to refund any

    amount. In such circumstances, the unilateral issuance of the

    demand notice is nothing but an afterthought and is wholly

    unsustainable.

    29. Learned counsel for the petitioners further submits that it had no

    occasion to challenge the orders passed by the State Commission or

    APTEL, as it was neither a party to those proceedings nor was any

    liability fastened upon it therein. The cause of action for the Petitioner

    arose only upon issuance of the impugned demand notice dated

    07.07.2016. Therefore, the contention of CSPDCL that the Petitioner

    ought to have availed alternative remedies is misconceived. It is well
    20

    settled that where a party has not been heard and suffers civil

    consequences, the writ jurisdiction of this Hon’ble Court can be

    directly invoked. The Petitioner was a necessary party to the

    proceedings before the State Commission and APTEL, as the

    adjudication directly concerned the nature of power supplied by it and

    the payments made under the PPAs. In the absence of the

    Petitioner, no effective or binding determination could have been

    made on issues that ultimately form the basis of the impugned

    demand. The failure of CSPDCL to implead the Petitioner, despite

    having full knowledge of the contractual relationship and

    transactions, renders the entire exercise procedurally flawed. Such

    omission cannot now be used to prejudice the Petitioner by fastening

    liability upon it without due process.

    30. It is further argued that the petitioner had supplied electricity strictly in

    terms of the Power Purchase Agreements executed with CSPDCL,

    which were based on the Suo-Motu Order passed by the State

    Commission. The contractual framework specifically recognized the

    nature of supply from captive generating plants, including permissible

    variations and the mechanism for computation of tariff through load

    factor and eligible units. The invoices raised by the Petitioner were in

    accordance with these agreed terms and were duly verified and paid

    by CSPDCL without any demur. It is an admitted position that

    CSPDCL accepted the power supplied by the Petitioner, utilized the

    same for distribution to consumers, and recovered the corresponding

    tariff. Payments were made over the relevant period in full

    satisfaction of contractual obligations, and at no stage during the
    21

    subsistence of the PPAs did CSPDCL raise any dispute regarding

    the nature or quality of power supplied. In such circumstances, the

    attempt to retrospectively reclassify the supply as “non-firm” and

    seek recovery of amounts already paid is impermissible in law and

    contrary to the doctrine of finality of concluded transactions.

    31. The impugned demand, in effect, seeks to compel the Petitioner to

    refund monies for electricity that has already been generated,

    supplied, consumed, and paid for. Such a course of action is not only

    inequitable but also legally untenable, as there exists no provision in

    the PPAs or under any statutory framework permitting such recovery.

    In the absence of any contractual stipulation or regulatory direction

    requiring refund, CSPDCL cannot unilaterally impose a financial

    burden upon the Petitioner. Further, the findings of the State

    Commission, as affirmed by APTEL, clearly attribute negligence to

    CSPDCL in procuring power without due prudence. The regulatory

    authorities have held that the consequences of such negligence

    cannot be passed on to consumers. However, CSPDCL now seeks

    to shift this very burden onto the Petitioner, who was not even heard

    in the proceedings. This attempt to transfer liability is contrary to the

    findings of the regulatory authorities themselves and is legally

    impermissible.

    32. It is further argued that the objection raised by CSPDCL regarding

    the availability of an alternative remedy under Section 125 of

    the Electricity Act, 2003 is wholly misconceived and untenable in the

    facts of the present case. The remedy of appeal to the Hon’ble
    22

    Supreme Court under Section 125 is available only to a “person

    aggrieved” by an order passed by the Appellate Tribunal for

    Electricity (APTEL). In the present case, the Petitioner was neither a

    party to the proceedings before the State Commission nor before

    APTEL, and no adverse findings or directions have been issued

    against it in the impugned judgment. Consequently, the Petitioner

    cannot be said to be an “aggrieved person” within the meaning of

    Section 125 so as to avail the said appellate remedy. The cause of

    action for the Petitioner arose only upon issuance of the impugned

    demand notice dated 07.07.2016, whereby, for the first time, a

    liability has been sought to be imposed upon it without any

    adjudication or hearing. It is a settled principle of law that the

    existence of an alternative remedy does not bar the exercise of writ

    jurisdiction under Article 226 of the Constitution of India, particularly

    where the impugned action is wholly without jurisdiction, violative of

    principles of natural justice, or results in manifest injustice. In the

    present case, the Petitioner has been fastened with a substantial

    financial liability without being heard and without any legal basis, and

    therefore, the writ petition is not only maintainable but constitutes the

    only efficacious remedy available to the Petitioner.

    33. The action of CSPDCL is also hit by the principles of estoppel,

    approbation and reprobation. Having accepted the contractual terms,

    acted upon them, and derived benefit from the Petitioner’s

    performance, CSPDCL cannot now take a contradictory stand to the

    detriment of the Petitioner. The law does not permit a party to accept

    benefits under a contract and subsequently challenge its validity or
    23

    seek restitution without any legal basis. The impugned demand

    notice is vitiated by violation of principles of natural justice, absence

    of jurisdictional foundation, lack of contractual or statutory basis, and

    arbitrariness. The Petitioner, having neither been heard nor held

    liable in any adjudicatory proceedings, cannot be subjected to

    recovery of amounts already paid for duly supplied electricity.

    Accordingly, the impugned demand and all consequential actions

    deserve to be quashed, and the Petitioner is entitled to appropriate

    reliefs from this Hon’ble Court.

    34. In support of his submission, he would rely upon the judgments of

    Ramesh Hiranand Kundanmal v. Municipal Corporation of

    Greater Bombay” 1992 (2) SCC 524, “Whirlpool Corporation v.

    Registrar of Trade Marks” 1998 (8) SCC 1, “State of Himachal

    Pradesh v. Gujarat Ambuja Cement Ltd.” 2005 (6) SCC 499,

    “Harbans Lal Sahnia v. Indian Oil Corporation Ltd.” 2003 (2) SCC

    107, “Dhampur Sugar Mills Ltd. v. State of U.P. and Others” 2007

    (8) SCC 338, “Har Shankar and Others v. Dy. Excise and

    Taxation Commissioner and Others” 1975 (1) SCC 737, “State

    Bank of Haryana and Others v. Jage Ram and Others” 1980 (3)

    SCC 599, “Mumbai International Airport (P) Ltd. v. Golden

    Chariot Airport” 2010 (10) SCC 422, “Hari Bans Lal v. Sahodar

    Prasad Mahto” 2010 (9) SCC 655, “Mohindar Singh Gill v. Chief

    Election Commissioner, New Delhi” 1978 (1) SCC 405, “Sharda

    Singh v. State of U.P.” 2009 (11) SCC 683, “Chandi Prasad v.

    Jagdish Prasad” 2004 (8) SCC 724, “Pimpri Chinchwad New

    Town Development Authority v. State of Maharashtra” 2005 (4)
    24

    Mh.L.J. 941, “Haryana Power Purchase Centre v. Sasan Power

    Ltd. and Others” 2023 SCC OnLine SC 577, “Karnataka Power

    Corporation Limited v. EMTA Coal Limited and Another”, order

    dated 20-05-2022, by Hon’ble Supreme Court in Civil Appeals Nos.

    5401-5404 of 2017, “Gujarat Urja Vikas Nigam Limited v. Solar

    Semiconductor Power Company (India) Private Limited and

    Another” 2017 (16) SCC 498.

    35. Per contra, learned counsel appearing for the Respondent Nos. 2

    and 3, at the outset, raises a preliminary objection regarding the

    maintainability of the present writ petition on the ground of the

    availability of efficacious statutory remedies under the Electricity Act,

    2003. It is submitted that the petitioners had the remedy of filing an

    appeal before the Hon’ble Supreme Court under Section 125 against

    the judgment dated 26.05.2016 passed by the Appellate Tribunal for

    Electricity (APTEL), which has not been availed. The said judgment

    has thus attained finality and is binding upon the parties. The

    petitioners, by invoking writ jurisdiction, are impermissibly seeking to

    reopen issues already adjudicated by expert statutory forums, which

    is contrary to settled principles governing the exercise of jurisdiction

    under Article 226 of the Constitution of India.

    36. It is further submitted that the dispute in question arises out of tariff

    determination and true-up proceedings undertaken by the State

    Commission in exercise of its statutory powers under Sections 62

    and 86 of the Electricity Act, 2003. The State Commission, after

    detailed examination of load curves, injection patterns, and
    25

    operational data, recorded a categorical finding that the power

    supplied by the petitioner was non-firm, intermittent, and unstable in

    nature. Such findings, based on technical expertise and regulatory

    analysis, were affirmed by APTEL. The respondents submit that

    these concurrent findings of fact are not amenable to judicial review

    in writ jurisdiction, particularly when they involve highly technical and

    disputed questions requiring specialized adjudication.

    37. It is further submitted that the Power Purchase Agreements (PPAs)

    relied upon by the petitioners were expressly subject to the

    provisions of the Electricity Act, 2003 and regulatory directions

    issued by the State Commission from time to time. Therefore, tariff

    determination by the Commission overrides contractual stipulations

    to the extent of inconsistency. The Commission, in its tariff order

    dated 12.06.2014, lawfully restricted the tariff for non-firm power to a

    base rate of Rs. 1.50 per kWh, in order to safeguard consumer

    interest and prevent undue financial burden on the distribution

    licensee. The petitioners cannot rely on contractual terms to defeat

    statutory tariff orders having an overriding effect. The demand of Rs.

    153.55 crore has been raised strictly in accordance with Section

    62(6) of the Electricity Act, 2003, which mandates the refund of

    excess tariff recovered by a generating company along with

    applicable interest. The excess amount was computed on the basis

    of audited financial data and in line with the findings recorded in the

    tariff and appellate proceedings. Retention of such an excess amount

    by the petitioner would result in unjust enrichment at the cost of

    public funds and electricity consumers, which is impermissible in law.
    26

    38. Learned counsel for Respondents Nos. 2 and 3 further submits that

    the petitioners were not denied an opportunity of hearing, as alleged.

    The proceedings before the State Commission were conducted in

    accordance with the applicable Conduct of Business Regulations,

    which provide for the issuance of public notices rather than individual

    notices. The tariff petitions were widely publicised through

    newspapers and the official website, and public hearings were

    conducted wherein stakeholders, including industry representatives,

    were given an opportunity to participate. In fact, the authorized

    representative of the petitioner was present during the review

    proceedings, demonstrating knowledge and participation in the

    process. Similarly, APTEL also issued public notices before deciding

    the appeals. It is also submitted that the petitioners, despite having

    knowledge of the proceedings and their outcome, failed to avail

    appropriate remedies at the relevant stages, including review before

    APTEL or appeal before the Hon’ble Supreme Court. Such inaction

    and acquiescence disentitle the petitioners from seeking

    discretionary relief under Article 226. The writ petition is thus liable to

    be dismissed on the ground of delay, laches, and waiver, apart from

    being an attempt to bypass statutory remedies.

    39. It is further submitted that under Sections 31, 32, and 33 of the

    Electricity Act, 2003, the State Load Dispatch Centre (SLDC) is

    entrusted with the responsibility of maintaining grid discipline,

    ensuring secure and economic operation of the power system, and

    issuing binding directions to generating companies. The petitioner,

    however, has consistently violated grid discipline by injecting highly
    27

    fluctuating and non-firm power, thereby jeopardizing grid stability.

    Repeated communications and directions were issued by the SLDC

    to the petitioner between 2014 and 2016, calling upon it to adhere to

    scheduled generation and maintain consistency in power supply. The

    petitioner not only failed to comply but also admitted its inability to

    supply firm power due to fluctuating internal consumption. Such

    erratic injection patterns caused operational difficulties, including

    overdrawal and underdrawal situations, attracting penalties and

    affecting overall grid management. The State Commission, taking

    note of these issues, issued directions to regulate and discourage

    such non-firm power. Denial of No Objection Certificate (NOC) and

    rejection of Short Term Open Access (STOA) applications were not

    arbitrary but were based on statutory obligations, regulatory

    directives, and the petitioner’s continued non-compliance with grid

    discipline. Grant of open access to an entity injecting unstable power

    would pose a serious threat to grid security and reliability. The

    impugned actions were therefore taken in the interest of maintaining

    stability of the power system and in compliance with binding

    directions of the State Commission and APTEL.

    40. Lastly, it is also submitted that the present writ petition suffers from

    non-joinder of necessary parties, including stakeholders who

    participated in the tariff proceedings and whose interests are affected

    by the outcome. The petitioners have also failed to challenge the

    foundational tariff orders and regulatory framework, which form the

    basis of the impugned actions. In the absence of such a challenge,

    the reliefs sought are untenable. The respondents thus pray for
    28

    dismissal of the writ petition as being devoid of merit, not

    maintainable, and contrary to the statutory scheme of the Electricity

    Act, 2003.

    41. He would rely upon the judgment of “Power Grid Corporation of

    India Limited v. Madhya Pradesh Power Transmission Company

    Limited and Others” 2025 (8) SCC 705, “State of Himachal

    Pradesh and Another v. JSW Hydro Energy Limited and Others”

    2025 SCC OnLine SC 1460, “Jaipur Vidyut Vitran Nigam Limited

    and another v. MB Power (Madhya Pradesh) and Others” 2024

    (8) SCC 513, “Educanti Kistamma (Dead) through L.Rs. v. S.

    Venkatareddy (Dead) through L.Rs. and Others” 2010 (1) SCC

    756, “Uttar Haryana Bijli Vitran Nigam Limited and Another v.

    Adani Power (Mundra) Limited and Others” 2023 (14) SCC 736,

    “Maharashtra State Electricity Distribution Company Limited v.

    Adani Power Maharashtra Limited and Others” 2023 (7) SCC 401,

    “GMR Warora Energy Ldt. V. CERC” 2023 (10) SCC 401, “R.

    Muthukumar and Others v. Chairman and managing Director

    TANGEDCO and Others” 2022 SCC OnLine SC 151.

    42. Learned Counsel appearing for the Respondent No. 1 would submit

    that the present writ petition under Article 226 of the Constitution of

    India is not maintainable. The petitioners have a complete and

    efficacious statutory remedy under Section 125 of the Electricity Act,

    2003, to challenge the judgment dated 26.05.2016 of the Appellate

    Tribunal for Electricity (APTEL) before the Hon’ble Supreme Court. In

    addition, Section 120(2)(f) provides a remedy of review before
    29

    APTEL. The petitioners’ failure to exhaust these statutory remedies

    precludes interference under writ jurisdiction as held in “Union of

    India v. Satyawati Sharma“, (1965) 1 SCR 363, writ jurisdiction is

    discretionary and cannot be exercised where an alternative statutory

    remedy exists. By adopting the submissions made by learned

    counsel for the Respondents Nos. 2 and 3, he would submit that

    functions under the Electricity Act, 2003, with statutory powers

    defined under Sections 61, 62, and 86. Section 61 empowers the

    Commission to specify the principles for the determination of tariffs.

    Section 62 empowers the Commission to determine the tariff for the

    supply of electricity by a generating company to a distribution

    licensee. Section 86(1)(b) and (f) authorise the Commission to

    adjudicate disputes between licensees and generating companies,

    and to ensure compliance with the Act. All actions of the

    Commission, including the tariff orders dated 12.06.2014 and review

    dated 08.12.2014, were taken within the statutory framework,

    following due process. The Commission, in Petition No. 07/2014,

    undertook the true-up exercise for FYs 2011-12 and 2012-13 and

    determined the minimum base tariff at Rs. 1.50 per unit for non-firm

    power. Section 62(3) and 62(6) mandate that only the tariff

    determined under the Act is payable, and any excess collection must

    be refunded with interest. The petitioner’s claim to receive a higher

    tariff or to avoid refund is contrary to statutory provisions and the

    principle that regulatory tariffs prevail over contractual agreements in

    matters of public utility and consumer interest.
    30

    43. He would further submit that principles of natural justice were fully

    complied with. Regulation 10 of the CSERC (Conduct of Business)

    Regulations, 2009, provides that public notices are sufficient to afford

    hearing to stakeholders. Notices were published in newspapers,

    petitions were uploaded on the Commission’s website, and public

    hearings were conducted at Raipur on 21-22.05.2014.

    Representatives of the petitioner, including DGM N.K. Chandiramani,

    were present and participated in the review proceedings. Thus, the

    claim of denial of opportunity of hearing is wholly misconceived. The

    tariff orders passed by the Commission and affirmed by APTEL are

    binding on the parties under Section 62(6) and Section 111. The

    petitioners cannot seek collateral review through a writ petition to

    avoid statutory obligations. It is well-settled that once an order of a

    specialised tribunal attains finality, collateral attack under writ

    jurisdiction is impermissible (NTPC Ltd. v. CERC & Ors., 2006 11

    SCC 154). Any attempt to circumvent these orders undermines the

    statutory framework.

    44. It is further argued that petitioners supplied fluctuating, non-firm

    power, which was duly examined in tariff proceedings. Sections 32

    and 33 empower the SLDC and the Commission to monitor grid

    operations and issue binding directions for maintaining system

    stability. The petitioner’s continued injection of unstable power

    created operational and commercial risks, which the Commission

    duly considered while limiting tariff. The denial of open access by the

    licensee (Respondent No. 2) was in conformity with the

    Commission’s directives. The petitioners had full knowledge of the
    31

    tariff orders, review proceedings, and APTEL judgment. Their failure

    to challenge the orders before the Supreme Court demonstrates

    acquiescence. The orders under challenge are in furtherance of

    public interest and consumer protection, as mandated under Section

    61(g) and 86(1)(b) of the Electricity Act, 2003. Allowing the

    petitioners to retain amounts already paid in excess of the statutory

    tariff would result in unjust enrichment and adversely affect

    consumers. The Commission’s regulatory mandate cannot be

    undermined by private contractual claims. In view of the foregoing,

    he also prays that the writ petition be dismissed on the grounds of (i)

    non-maintainability due to existence of alternative statutory remedies,

    (ii) compliance with principles of natural justice and due process, (iii)

    binding nature of tariff orders and APTEL judgment, (iv) technical and

    regulatory basis of the orders, and (v) protection of public interest.

    The petitioners’ claims are wholly unsustainable in law.

    45. I have heard learned counsel for the respective parties and gone

    through the pleadings and documents annexed thereto.

    46. The present writ petition consists of the challenge to the demand

    notice dated 07.07.2016 issued by Respondent No. 2 (CSPDCL), the

    consequential denial of Short Term Open Access (STOA) and No

    Objection Certificate (NOC), and the extent to which the judgment

    dated 26.05.2016 passed by the Appellate Tribunal for Electricity

    (APTEL) can be relied upon to fasten liability upon the petitioner. The

    foundational question which arises is whether the petitioner No. 1,

    admittedly not impleaded in the tariff proceedings before the State
    32

    Commission or in the appellate proceedings before APTEL, can be

    subjected to adverse civil and pecuniary consequences on the

    strength of findings recorded in such proceedings, and whether such

    action satisfies the mandate of the Electricity Act, 2003 and the

    settled principles of natural justice.

    47. Before adverting to the merits of the controversy, it is necessary to

    deal with the preliminary objection raised by the respondents with

    regard to the maintainability of the present writ petition. The objection

    proceeds on the footing that the petitioner had efficacious alternative

    remedies under Sections 120(2)(f), 125, and 86(1)(f) of the Electricity

    Act, 2003, and having failed to avail the said remedies, the present

    writ petition ought not to be entertained. This Court is unable to

    accept the said contention for more than one reason.

    48. It is trite that the rule of alternative remedy is a rule of self-imposed

    restraint and not a jurisdictional bar. The power of judicial review

    under Article 226 of the Constitution of India is plenary in nature and

    cannot be curtailed by statutory provisions. The Hon’ble Supreme

    Court in “Whirlpool Corporation v. Registrar of Trade Marks“,

    (1998) 8 SCC 1, has authoritatively held that in at least three

    contingencies, namely, where the writ petition seeks enforcement of

    fundamental rights, where there is violation of principles of natural

    justice, and where the impugned orders are wholly without

    jurisdiction, the existence of an alternative remedy would not operate

    as a bar. This principle has been consistently reiterated

    in “Harbanslal Sahnia v. Indian Oil Corporation Ltd.“, (2003) 2
    33

    SCC 107, wherein it has been held that the rule of exclusion of writ

    jurisdiction in view of the availability of an alternative remedy is a rule

    of discretion and not one of compulsion.

    49. In the case of “Whirlpool Corporation” (supra), the Hon’ble

    Supreme Court has held that:-

    “15. Under Article 226 of the Constitution, the High

    Court, having regard to the facts of the case, has a

    discretion to entertain or not to entertain a writ petition.

    But the High Court has imposed upon itself certain

    restrictions one of which is that if an effective and

    efficacious remedy is available, the High Court would

    not normally exercise its jurisdiction. But the alternative

    remedy has been consistently held by this Court not to

    operate as a bar in at least three contingencies, namely,

    where the writ petition has been filed for the

    enforcement of any of the Fundamental Rights or where

    there has been a violation of the principle of natural

    justice or where the order or proceedings are wholly

    without jurisdiction or the vires of an Act is challenged.

    There is a plethora of case-law on this point but to cut

    down this circle of forensic whirlpool, we would rely on

    some old decisions of the evolutionary era of the

    constitutional law as they still hold the field.”

    50. In the case of “Harbanslal Sahnia” (supra), it has been held by their

    lordships of the Hon’ble Supreme Court that:-

    34

    “7. So far as the view taken by the High Court that the

    remedy by way of recourse to arbitration clause was

    available to the appellants and therefore the writ petition

    filed by the appellants was liable to be dismissed is

    concerned. suffice it to observe that the rule of

    exclusion of writ jurisdiction by availability of an

    alternative remedy is a rule of discretion and not one of

    compulsion. In an appropriate case, in spite of

    availability of the alternative remedy, the High Court

    may still exercise its writ jurisdiction in at least three

    contingencies: (i) where the writ petition seeks

    enforcement of any of the fundamental rights; (ii) where

    there is failure of principles of natural justice: or (n)

    where the orders or proceedings are wholly without

    jurisdiction or the vires of an Act is challenged. (See

    Whirlpool Corpn. v. Registrar of Trade Marks The

    present case attracts applicability of the first two

    contingencies. Moreover, as noted, the petitioners

    dealership, which is their bread and butter, came to be

    terminated for an irrelevant and non-existent cause. In

    such circumstances, we feel that the appellants should

    have been allowed relief by the High Court itself instead

    of driving them to the need of initiating 9 arbitration

    proceedings.”

    51. In the case of “Gujarat Ambuja Cement Ltd.” (supra), it has been

    held that:-

    35

    “18. The Constitution Benches of this Court in K.S.

    Rashid and Son v. Income Tax Investigation

    Commission, AIR 1954 SC 207; Sangram Singh v.

    Election Tribunal, Kotah, AIR 1955 SC 425; Union of

    India v. T.R. Varma, AIR 1957 SC 882; State of U.P. v.

    Mohd. Nooh, AIR 1958 SC 86 and K.S. Venkataraman

    and Co. (P) Ltd. v. State of Madras, AIR 1966 SC 1089

    held that Article 226 of the Constitution confers on all

    the High Courts a very wide power in the matter of

    issuing writs. However, the remedy of writ is an

    absolutely discretionary remedy and the High Court has

    always the discretion to refuse to grant any writ if it is

    satisfied that the aggrieved party can have an adequate

    or suitable relief elsewhere. The Court, in extraordinary

    circumstances, may exercise the power if it comes to

    the conclusion that there has been a breach of

    principles of natural justice or procedure required for

    decision has not been adopted.

    19. Another Constitution Bench of this Court in State of

    M.P. v. Bhailal Bhai, AIR 1964 SC 1006 held that the

    remedy provided in a writ jurisdiction is not intended to

    supersede completely the modes of obtaining relief by

    an action in a civil court or to deny defence legitimately

    open in such actions. The power to give relief under

    Article 226 of the Constitution is a discretionary power.

    Similar view has been reiterated in N.T. Veluswami
    36

    Thevar v. G. Raja Nainar, AIR 1959 SC 422; Municipal

    Council, Khurai v. Kamal Kumar, AIR 1965 SC 1321;

    Siliguri Municipality v. Amalendu Das, (1984) 2 SCC

    436; S.T. Muthusami v. K. Natarajan, (1988) 1 SCC

    572; Rajasthan SRTC v. Krishna Kant, 1995) 5 SCC 75;

    Kerala SEB v. Kurien E. Kalathil, (2000) 6 SCC 293; A.

    Venkatasubbaiah Naidu v. S. Chellappan, (2000) 7

    SCC 695; L.L. Sudhakar Reddy v. State of A.P., (2001)

    6 SCC 634; Shri Sant Sadguru Janardan Swami

    (Moingiri Maharaj) Sahakari Dugdha Utpadak Sanstha

    v. State of Maharashtra, (2001) 8 SCC 509; Pratap

    Singh v. State of Haryana, (2002) 7 SCC 484 and GKN

    Driveshafts (India) Ltd. v. ITO, (2003) 1 SCC 72.

    20. In Harbanslal Sahnia v. Indian Oil Corpn. Ltd.,

    (2003) 2 SCC 107, this Court held that the rule of

    exclusion of writ jurisdiction by availability of alternative

    remedy is a rule of discretion and not one of compulsion

    and the Court must consider the pros and cons of the

    case and then may interfere if it comes to the

    conclusion that the petitioner seeks enforcement of any

    of the fundamental rights; where there is failure of

    principles of natural justice or where the orders or

    proceedings are wholly without jurisdiction or the vires

    of an Act is challenged.

    37

    21. In G. Veerappa Pillai v. Raman & Raman Ltd., AIR

    1952 SC 192; CCE v. Dunlop India Ltd., (1985) 1 SCC

    260; Ramendra Kishore Biswas v. State of Tripura,

    (1999) 1 SCC 472; Shivgonda Anna Patil v. State of

    Maharashtra, (1999) 3 SCC 5; C.A. Abraham v. ITO,

    AIR 1961 SC 609; Titaghur Paper Mills Co. Ltd. v. State

    of Orissa, (1983) 2 SCC 433; H.B. Gandhi v. Gopi Nath

    and Sons, 1992 Supp (2) SCC 312; Whirlpool Corpn. v.

    Registrar of Trade Marks, (1998) 8 SCC 1; Tin Plate

    Co. of India Ltd. v. State of Bihar, (1998) 8 SCC 272;

    Sheela Devi v. Jaspal Singh, (1999) 1 SCC 209 and

    Punjab National Bank v. O.C. Krishnan, (2001) 6 SCC

    569, this Court held that where hierarchy of appeals is

    provided by the statute, party must exhaust the

    statutory remedies before resorting to writ jurisdiction.

    22. If, as was noted in Ram and Shyam Co. v. State of

    Haryana, (1985) 3 SCC 267 the appeal is from “Caesar

    to Caesar’s wife” the existence of alternative remedy

    would be a mirage and an exercise in futility. In the

    instant case the writ petitioners had indicated the

    reasons as to why they thought that the alternative

    remedy would not be efficacious. Though the High

    Court did not go into that plea relating to bias in detail,

    yet it felt that alternative remedy would not be a bar to

    entertain the writ petition. Since the High Court has

    elaborately dealt with the question as to why the
    38

    statutory remedy available was not efficacious, it would

    not be proper for this Court to consider the question

    again. When the High Court had entertained a writ

    petition notwithstanding existence of an alternative

    remedy this Court while dealing with the matter in an

    appeal should not permit the question to be raised

    unless the High Court’s reasoning for entertaining the

    writ petition is found to be palpably unsound and

    irrational. Similar view was expressed by this Court in

    First ITO v. Short Bros. (P) Ltd., AIR 1967 SC 81 and

    State of U.P. v. Indian Hume Pipe Co. Ltd., (1977) 2

    SCC 724 That being the position, we do not consider

    the High Court’s judgment to be vulnerable on the

    ground that alternative remedy was not availed. There

    are two well-recognised exceptions to the doctrine of

    exhaustion of statutory remedies. First is when the

    proceedings are taken before the forum under a

    provision of law which is ultra vires, it is open to a party

    aggrieved thereby to move the High Court for quashing

    the proceedings on the ground that they are

    incompetent without a party being obliged to wait until

    those proceedings run their full course. Secondly, the

    doctrine has no application when the impugned order

    has been made in violation of the principles of natural

    justice. We may add that where the proceedings itself

    are an abuse of process of law the High Court in an

    appropriate case can entertain a writ petition.”
    39

    52. Tested on the anvil of the aforesaid principles, the facts of the

    present case clearly bring it within the well-recognized exceptions.

    The petitioner was neither impleaded nor afforded any effective

    opportunity of hearing in the proceedings before the State

    Commission or before APTEL, despite the fact that the entire subject

    matter of those proceedings pertained to power supplied by the

    petitioner under duly executed Power Purchase Agreements.

    53. The contention of the respondents that the petitioner ought to have

    availed the appellate remedy under Section 125 of the Electricity Act,

    2003 also does not merit acceptance. The said provision enables an

    appeal to the Hon’ble Supreme Court by a “person aggrieved” by an

    order of APTEL. In the present case, the petitioner was not a party to

    the proceedings before APTEL, nor does the impugned judgment

    record any finding or direction against it. In the absence of any lis

    involving the petitioner or any adjudication affecting its rights, it

    cannot be said that the petitioner was a “person aggrieved” so as to

    invoke Section 125. A remedy which is illusory or not efficacious in

    the given factual matrix cannot be pressed into service to non-suit

    the petitioner. It is necessary here to notice Section 125 of the

    Electricity Act, 2003, which reads as under:-

    Section 125. (Appeal to Supreme Court):

    Any person aggrieved by any decision or order of the

    Appellate Tribunal, may, file an appeal to the Supreme

    Court within sixty days from the date of

    communication of the decision or order of the
    40

    Appellate Tribunal, to him, on any one or more of the

    grounds specified in section 100 of the Code of Civil

    Procedure,1908:

    Provided that the Supreme Court may, if it is satisfied

    that the appellant was prevented by sufficient cause

    from filing the appeal within the said period, allow it to

    be filed within a further period not exceeding sixty

    days.”

    54. Similarly, the remedy of review under Section 120(2)(f) before

    APTEL cannot be said to be efficacious, as the petitioner was not on

    record in the appellate proceedings and could not have sought

    review of an order passed in a matter to which it was not a party. The

    suggestion that the petitioner could approach the State Commission

    under Section 86(1)(f) for adjudication of disputes is equally

    misconceived, inasmuch as the impugned demand has already been

    raised unilaterally on the basis of concluded proceedings, and the

    petitioner cannot be relegated to initiate fresh adjudicatory

    proceedings merely to contest an action of recovery of Rs. 153.55

    crores.

    55. It is also significant to note that the cause of action for the petitioner

    arose only upon issuance of the demand notice dated 07.07.2016,

    whereby, for the first time, a concrete and enforceable liability was

    sought to be imposed. Prior to this, there was neither any

    adjudication against the petitioner nor any indication that the

    amounts received under the PPAs were liable to be refunded.
    41

    Therefore, the petitioner cannot be faulted for not challenging the

    tariff order or the APTEL judgment, as no prejudice had been caused

    to it at that stage.

    56. The objection of the respondents, if accepted, would lead to a

    situation where a party is saddled with serious civil consequences

    without being heard, and is then denied access to judicial review on

    the ground that it failed to challenge proceedings to which it was not

    even a party. Such an interpretation would be wholly unjust and

    contrary to the basic tenets of fairness embedded in Article 14 of the

    Constitution.

    57. In view of the foregoing discussion, this Court is of the considered

    opinion that the present case falls squarely within the recognized

    exceptions to the rule of alternative remedy, namely, violation of

    principles of natural justice. The remedies suggested by the

    respondents are neither efficacious nor available in the true sense to

    the petitioner in the peculiar facts of the case. Accordingly, the

    preliminary objection regarding maintainability is rejected, and the

    writ petition is held to be maintainable for adjudication on merits.

    58. The factual matrix, as borne out from the record, indicates that the

    petitioner had entered into multiple Power Purchase Agreements

    (PPAs) with CSPDCL during the period between 2011 and 2013 for

    the supply of electricity, which were acted upon by both parties. The

    petitioner supplied electricity and raised invoices in terms of the

    agreed contractual mechanism, including a load factor-based tariff. It

    is also not in dispute that CSPDCL accepted such supply and
    42

    effected payments during the relevant financial years. However, the

    mere fact that payments were made at a particular point in time, or

    that the transactions were not immediately disputed, cannot be

    construed to mean that such transactions attained irrevocable finality

    so as to be insulated from subsequent statutory scrutiny. It is

    necessary to notice here the initial PPA dated 02-11-2011, which is

    as under:-

    POWER PURCHASE AGREEMENT

    ******* THIS AGREEMENT made on this 2nd day of

    November 2011 between the Chhattisgarh state

    Power Distribution Co. Ltd. (A Government of

    Chhattisgarh undertaking, a successor company of

    Chhattisgarh State Electricity Licensee, hereinafter

    referred to as “Licensee”) which expression shall

    where the context so admits shall include its

    successors in office and assigns of the one part and

    M/s Jindal Steel & Power Limited (hereinafter referred

    as Company) a company incorporated under the

    companies Act 1956 having it’s registered office at

    O.P. Jindal Marg, Hisar – 125005, Haryana which

    expression shall where the context so admits includes

    its successors in business executors administrators,

    legal representatives, and assigns of the other parts.

    ******* AND WHEREAS the company has set up the

    Captive Generating Plant at Dongamahua, District

    Raigarh and whereas the company has offered to sell
    43

    power on firm basis to the Licensee based on

    anticipated availability, which has been accepted by

    the Licensee vide letter No.02-02/ACE-I/2124 dt.

    21.10.2011.

    ******* NOW This agreement witnesses and the

    parties hereto have agreed as below:-

    (1) (a) The Company has offered 150 MW firm power

    on Round the Clock basis i.e. 00.00 hrs to 24.00 hrs,

    hereinafter referred to as maximum contracted

    quantum of power. The Company may reduce the

    quantum of power supply to the extent of 20% of

    maximum contracted power due to the reason which is

    not under the control of company to supply maximum

    contracted power. The minimum contracted power

    shall be 120 MW, which is not less than 80% of

    maximum contracted power. Load factor of company

    having minimum contracted power less than 10 MW

    will be calculated on monthly basis and having

    minimum contracted power of 10 MW and above will

    be calculated on weekly basis, during the term of this

    agreement the Licensee has agreed to purchase

    power generated by the company as per contracted

    capacity subject to the provisions contained in the

    Electricity Act, 2003 (herein after referred as ‘the Act’)

    and rules made there under as per Chhattisgarh State

    Electricity Regulatory Commission (CSERC) guideline
    44

    for power purchase and procurement and the terms

    and conditions of power purchase by Licensee as

    approved by CSERC from time to time.

    (1) (b) The billing and scheduling modalities are as

    under:-

    (i) Agreed rate:- Rs.3.00 (Rs.Three) per kWh for RTC

    power.

    (ii) Merit order purchase:-

    ******* The power from the company will be purchased

    in accordance to merit order purchase principle under

    Section 32(2) of the Act. The State Load Despatch

    Centre (SLDC) will carry out real time operation for

    grid control and dispatch of electricity within the state

    through secured and economic operation of the grid.

    Both parties of this agreement shall abide themselves

    by the instructions issued by the SLDC for maintaining

    grid discipline. The SLDC may restrict power supply

    from the company by backing down of the generation /

    reduction in injection, if required, for secured and

    economic operation of the State grid. In case of clear

    instruction from SLDC, if, the company do not back

    down their generation / reduce their injection to the

    quantum as required by the SLDC, the company shall

    be liable for the payment at the rate which may be

    imposed on the licensee due to congestion in grid, or
    45

    panel UI charges or any other penalty in any form due

    to over injection in the grid.

    ******* In case, supply of power by the company is

    restricted by SLDC due to backing down of the

    generation / reduction in injection, then that backing

    down period of supply shall be considered as deemed

    generation with respect to the scheduled quantum of

    power and this deemed generation shall be taken into

    account for calculation of load factor, subject to

    certification of deemed generation from SLDC. The

    quantum of deemed generation will be considered for

    purpose of calculation of load factor only. Payment for

    purchase of power shall be done on the basis of actual

    energy injection.

    (3) Scheduling:-

    ******* Company shall give a monthly schedule of

    quantum of power intended to be supplied to the

    Licensee for the ensuing month by 23rd of the month.

    The scheduled quantum of power shall be either

    maximum / minimum contracted power or between

    minimum and maximum contracted power. In case the

    monthly schedule for month is not submitted by the

    company upto prescribed date, to SLDC under

    intimation to the Licensee then the running schedule

    shall be considered as schedule for ensuing month

    also.

    46

    (4) Limit of Power Injection:-

    (a) During off peak hour (00.00 to 18.00 hrs & 23.00

    hrs to 24.00 hrs)

    The company shall be permitted to inject up to 110%

    of scheduled power for off peak hours i.e. 00.00 hrs to

    18.00 hrs & 23.00 hours to 24.00 hours subject to the

    technical limitation of equipment / line rating at

    sending and receiving ends. However, payment @

    Rs.1.00 (Rs.One only) per unit shall be made for the

    energy injected over & above 110% of schedule

    subject to condition that technical limitation to be

    observed by Supplier. Units supplied upto permitted

    injection rate of 110% will be taken as eligible units for

    calculation of load factor and payment. Eligible units

    shall mean the units (energy) supplied upto permitted

    injection rate of 110% of schedule (schedule energy in

    time block) during off peak hours.

    (b) During peak hours (18.00 hrs to 23.00 hrs)

    The company shall be permitted to inject upto 120% of

    schedule for peak hours i.e. 18.00 hrs to 23.00 hrs

    subject to the technical limitation of equipment / line

    rating at sending and receiving ends. However,

    payment @ Rs.1.00 (Rs.One only) per unit shall be

    made for the energy injected over & above 120% of

    schedule subject to condition that technical limitation

    to be observed by supplier. Units supplied upto
    47

    permitted injection rate of 120% will be taken as

    eligible units for calculation of load factor and

    payment. Eligible units shall mean the units (energy)

    supplied upto permitted injection rate of 120% of

    schedule (schedule energy in time block) during peak

    hours.

    (5) Load Factor:-

    (a) For the power supplied the load factor will be

    calculated as below:-

    LF = Number of eligible units supplied during a month /week
    Monthly schedule quantum of power×24 hrs.×No. of days in a month/week

    Effective Rate in Rs. = 3.00×Actual LF % (monthly / weekly)
    80%

    In addition to the above, the following modalities for

    accounting & calculation of LF shall be taken into

    account :-

    (i) Schedule power means quantum of power declared

    by generator for the month which is equal to maximum

    / minimum contracted power or in between maximum

    contracted power and minimum contracted power as

    per clause 1(a).

    (ii) Load Factor shall be calculated on monthly /

    weekly basis as per clause 1(a).

    (iii) The payment will be done on monthly basis.

    (iv) The minimum effective rate shall be Rs.1.50 per

    unit.

    48

    (6) Rate of Infirm power:-

    Power supplied by the company after synchronization

    with licensee’s grid and before the COD (date of

    commercial operation) of their power plant shall be

    treated as infirm power and shall be paid @ Re.1/- per

    unit. This rate of infirm power is applicable to the

    power plant who enters PPA with licensee.

    (7) The company having power purchase agreement

    with licensee only for peak hours, the injected

    between 17.30 hrs to 18.00 hrs and 23.00 hrs to 23.30

    hrs shall be paid at a fixed rate of Rs 1.00 (Rs one

    only) per unit. No payment will be made for any

    injection prior to 17.30 hrs and after 23.30 hrs.

    However, if the company is having contract /

    agreement with other than licensee to supply of power

    during off peak hours i.e. between 23.00 hrs to 18.00

    hrs, next day, no payment will be made for the power

    injected between 17.30 hrs to 18.00 hrs and 23.00 hrs

    to 23.30 hrs.

    (8) Notwithstanding to the above in case the CSERC

    issues any other guidelines or specifies / modifies

    terms and conditions of power purchase by the

    licensee, the same shall be acceptable and binding on

    both the parties.

    (9) Company shall abide by the grid discipline as per

    the provisions of State Electricity Grid Code and shall
    49

    maintain technical parameters regarding voltage,

    frequency, power factor, within the limit as per prudent

    utility practices, subject to the technical plant limits

    and in Line with prudent utility practices, the company

    shall operate and maintain the plant in such a manner,

    so as not to have an adverse effect on the operation of

    Licensee’s Grid System. In case arry violation is noted

    in abiding by Grid Discipline, the Licensee/SLDC may

    isolate company’s power supply from its grid system,

    will out any liability on the licensee when system

    security aspect of the State grid is involved, taking into

    consideration the provision of State Grid Code.

    (10) For power supplied to Licensee, joint

    monthly/weekly reading or any other mechanism

    (AMR) as approved by CSERC. in respect of power

    exported to Licensee shall be laken by the authorized

    representative of company and Licensee. Company

    shall submit monthly invoice of energy sold to

    Licensee, to Superintending Engineer (O&M)

    CSPDCL at Raigarh under intimation to Chief

    Engineer (Comm.) of Licensee. Reinur after each

    monthly / weekly metar reading duly supported by the

    documents.

    (11) PAYMENT

    Normally, licensee shall make the payment within 30

    days from the date of receipt of bill in the office of the
    50

    Superintending Engineer(O&M) CSPDCL at Raigarh

    under intimation to Chief Engineer(Comml) (licensee)

    Raipur. However, in case the company desires

    payment within fifteen days from the date of

    presentation of bill, they shall allow 2% (Two percent)

    rebate on the billed amount for supply of power

    Further, in case payment is made after 30 days, a

    delayed payment surcharge of 1.00% (one percent)

    per month shall be paid by licensee. This delayed

    payment surcharge shall be calculated on simple

    interest basis on the number of days outstanding after

    the said period. In the event of 15/30th day being a

    holiday, the next working day shall be the due date for

    the payment for this purpose.

    (12) METERING

    12.1 The metering point for power purchese arid billing

    purpose for generating plants which are connected to

    gnd shall be at point of injection at Licensee /

    Chhattisgarh State Power Transmission Co. Ltd.

    (herein after referred as CSPTCL) sub-station. The

    provision related to metering shall be governed by the

    Central Electricity Authority (Installation and Operation

    of Meters) Regulation, 2006 as amended from time to

    time.

    12.2 The energy loss for dedicated lines, ie. from the

    power plant to the point of injection at the sub-station
    51

    is to be borne by the company. The energy. loss from

    the point of Injection onwards has to be acrne by the

    licensee. In case billing and check meter installed at

    metering point l.e. at sul station end becomes

    defective, then the billing shall be done on the basis of

    injection recorded at generating station end meter if

    found functioning properly. However, in this case the

    company shall have to bear line loss as approved by

    CSERC.

    12.3 Export/Import meters capable of recording active

    as well as reactive power shall be installed at the

    interconnection point. Reactive energy billing shall be

    as per the orders of CSERC issued from time to time:

    In case the CSERC approves reactive power billing on

    the basis of ABT meter then the rates and other

    modalities shall be as per CSERC’s order.

    12.4 The specifications of the Special Energy Meters

    shall be as approved by The Licensee/CSPTCL.

    12.5 The meter shall be jointly tested and inspected

    and sealed on behalf of both the parties and shall not

    be interfered by either party except in the presence of

    the other party or its representatives.

    12.6 Billing meters and the check meters (wherever

    provided) shall be tested for accuracy once in a year

    in presence of both the parties.

    52

    12.7 The meters shall be deemed to have working

    satisfactorily if the errors as determined in the tests

    are within the permissible limits as allowed in the

    relevant IS specifications or I.E. rules, 1958 applicable

    to high precision energy meters.

    12.8 If during the periodical testing the billing meter is

    found to have errors, beyond permissible limits but the

    check meters (wherever provided) are found to have

    error within the permissible limit, billing shall be

    revised on the basis of generation / injection recorded

    by the check meter. However, billing meter shall be

    attended / replaced immediately and biling thereafter

    shall be as per generation / injection recorded by new

    tested biling meter.

    12.8 If during the periodical testing both billing & check

    meters (wherever provided) are found to have error

    peyond permissible limits, the bill shall te revised by

    applying correction factor to the injection registered by

    the billing meter. The correction factor shall mean the

    percentage of error between the R.S.S. meter & billing

    meters.

    12.10 If both the meters i.e. the billing meter and the

    check meter (wherever provided) fall to record or if

    any of the PT fuse is blown out, then the energy

    accounting shall be done as per clause 12(2) or on a

    mutually agreeable basis between licensee and the
    53

    company, in case the generator end meter also found

    defective.

    12.11 All the tests on the billing and check meters

    (wherever provided) shall be conducted by the meter

    relay testing staff of the Licensee/CSPTCL jointly with

    the staff of company.

    12.12 The licensee / CSPTCL will have access to the

    meters and metering equipments at any point of time

    for which company woule provide entry to the

    Licensee/CSPTCL staff authorized “or this purpose.

    12.13 All the data transfer facilities shall be provided

    by the Company for monitoring, billing and other

    accounting purpose.

    (13) Dispute Resolution: in the event of any dispute

    arising between the Company and the licensee as

    regards to the interpretation of this agreement or any

    other matter arising out of or in connection with this

    agreement, such dispute or difference shall be

    referred to the CSERC for settlement of the dispute.

    (14) FORCE-MAJEURE AND OUTAGE:

    14.1 Force Majeure: Any event which is beyond the

    control of the agencies involved which they could not

    foresee or with a reasonable amount of diligence

    could not have foreseen or which could not be

    prevented and which substantially affect the
    54

    performance by either of the agency such as but not

    limited to:

    (a) Acts of God, natural phenomena, including but not

    limited to floods, droughts, earthquakes and

    epidemics.

    (b) Acts of any Government domestic or foreign,

    including but not limited to war declared or

    undeclared, hostilities priorities, quarantines,

    embargoes,

    (c) Riol or Civil Commotion

    (d) Grid’s failure not attributable to agencies involved

    During force majeure period neither party shall be

    entitled for claiming compensation for damages in the

    event of force majeure.

    14.2 Forced Outage: An outage of Generating Unit(s)

    of the compary due to a fault or other reasons which

    has not been planned shall be considered as forced

    outage. The company supplying power to the licensee

    shall be eligible to claim a maximum of 240 hours in a

    year as forced outage period. There shall not be any

    requirement to verify the forced outage of the power

    plant of the company but company will intimate

    licensee and SLDC immediately in writing (by fax)

    regarding breakdown / forced cutage and probable

    time to restore power supply and subsequently inform
    55

    wnen generator comes on the bus. The forced outage

    period of maximum 240 hours in a year shall be

    considered for LF calculation.

    14.3 Planned Outage: The power plant of the

    company shall be eligible for maximum 15 days in a

    year for planned outage. The company shall declare

    about their outage planning to the licensee and SLDC

    well in advance at least 15 days from the date of

    starting of planned outage. The planned outage period

    shall be considered for L.F. calculation maximum to 15

    days in a year.

    14.4 The provision under clause 14.2 i.e. maximum

    240 hours for force outage and urider clause 14.3 i.e.

    maximum 15 days for planned outage in a year shall

    be considered for the purpose of LF calculation only, if

    company executes PPA with licensee for complete

    one year.

    14.5 In case the company falls to supply power to the

    licensee for all the 12 months le. contracted period the

    company will not be entitled to get benefit of

    forced/planned outage for considering load factor

    calculation purpose. In such case the benefit avalled

    by the company in this caspect shall be refundable to

    the licensee.

    (15) DURATION:

    56

    This agreement shall remain operative for a period

    upto 30 June 2012 from the fate of commencement of

    the agreement. The date of commencement of this

    agreement shall be 1″ November 2011 and cease to

    operate automatically without any notice after 30 June

    2012.

    Notwithstanding to the above, this agreement shall be

    terminable during the currency period of the

    agreement by either party by serving one month notice

    or on the specific direction from CSERC.

    (16) IDEMNITY: Company shall indemnify the

    Licensee/CSPTCL from any all damages which may

    occur to the Licensee/CSPTCL personnel duning the

    operation of the interconnection

    (17) INSPECTION BY LICENSEE/ CSPTCL,

    Company shall allow and accord necessary facilities

    for inspection at all times of its generation,

    interconnection equipments and records by personnel

    of the licenseal CSPTCL to ensure their proper

    functioning. Records or such inspections shall be

    signed by the authorized representatives of company

    and licensee/CSPTCL.

    (18) NOTICES- All notices shall be deemed to have

    been served when sent ty registered post at the

    address given below:

    57

    (1) The Managing Director.

    Chhattisgarh State F’ower Distribution Company Ltd.,

    Vidyut Sewa Bhawan, PO: Sunder Nagar

    Danganiya, Raipur-492013.

    (ii) The Executive Director

    M/s. Jindal Steel & Power Ltd.

    Post Box No.16. Kharsia Road

    Raigarh-496001 Chhattisgarh

    (19) LOAD MANAGEMENT: The licensee shall

    endeavor to evacuate all the electricity offered by

    Company as per this agreement. However, licensee/

    CSPTCL may ask the company to temporarily curtait

    or stop its electricity export to grid when necessary on

    account of.

    (a) Inspection/repair/maintenance to its transmission

    network and associated equipments.

    (b) Safety of equipment of the licensee/CSPTCL and

    (c) Force-maieure conditions.

    No compensation, whatsoever shall be paid by the

    licensee / CSPTCL due to non-evacuation of the

    power due to reasons stated above.

    (20) NO WAIVER- No waiver of any of the terms &

    conditions of this agreement shall ce binding or

    effectual for any purpose, unless expressed in writing
    58

    and signed by the party giving the same and any such

    waiver shall be effective only in the specific instance

    and for the purpose given, No failure or delay on the

    part of either party hereto in exercising any right,

    power of privilege hereunder shall operate as a waiver

    thereof.

    (21) The terms and conditions (except rate) as

    mentioned in the CSERC order dated 30.04.2010

    passed in suo motu petition No.05 of 2010 & orrler

    dated 15.07 2011 pessed in suo motu petition No.23

    of 2011 are applicable for this PPA Any change in the

    existing rates and terms and conditions of power

    purchase of licensee, by CSERC will be made

    applicable to this power purchase agreement In that

    case supplementary PPA to incorporate such

    changes! modification shall be executed between

    licensee and company.

    IN WITNESS WHEREOF parties through their

    respective duly authorized Officer/ representative have

    signed this agreement.

    59. Paragraph (1)(a) of the said PPA clearly stipulates that “During the

    term of this agreement, the licensee has agreed to purchase

    power generated by the company as per contracted capacity

    subject to the provisions contained in the Electricity Act, 2003,

    (hereinafter referred as “the Act”) and rules made there under

    as per Chhattisgarh State Electricity Regulatory Commission
    59

    (CSERC) guideline for power purchase and procurement and the

    terms and conditions of power purchase by Licensee as

    approved by CSERC from time to time.” So, the PPA was

    governed under the terms of the Electricity Act, 2003 and guideline

    of CSERC.

    60. The CSERC in its suo motu Petition No. 05 of 2010, decided on 30-

    04-2010, observed the Limits on over-injection that:-

    “7. Limits on over-injection

    ******* The CSPDCL has requested to impose limits

    on over-injection during peak hour supply of power

    also. CSPDCL has submitted that, unrestricted

    injection during peak hours is misutilized by some of

    the generators to avail undue benefit from the market.

    The CSPDCL has proposed to limit injection rate to

    110% throughout the day. Chhattisgarh Vidhyut

    Mandal Abhiyanta Sangh has requested the

    Commission to investigate into the matter and then

    proceed in this case. M/s JPL, M/s BMPL, CII, CUM,

    UIA, BALCO and others had opposed this proposal of

    CSPDCL and suggested to continue the existing

    mechanism. CSPDCL submitted that over-injection by

    the generators resulted into under-drawal by State,

    and the average rate for Ul under-drawal for three

    consecutive months was about Rs 2.50 per unit. This

    position of the State requires attention. Although the
    60

    CSPDCL has not submitted any fact or analysis on

    commercial Implications of such under-drawal, but

    what we understand is that, if the average cost of

    short-term power purchase of CSPDCL is more than

    Rs 2.50 per unit in the respective three months (as

    indicated by CSPDCL) then this would adversely

    affect the commercial aspect of CSPDCL and

    ultimately the end consumers of the State. The tariff

    order 2009-10 emphasized to adopt merit order

    purchase principle during power procurement. The

    previous three tariff orders also directed the licensee

    to adopt merit order purchase principle. A mechanism

    was already in place, to prevent such situation, but

    whether it has been followed or not is not known to us.

    This may be examined in detall during truing up

    exercise of CSPCL’s petition.

    ******* However, the fact submitted by CSPDCL

    cannot be overlooked. The loss on account of such

    power procurement by the CSPDCL will affect the

    consumers of the State. One more aspect needs to be

    seen. The CSPDCL is a Ul pool member (regional

    entity as per IEGC) for regional grid operations. The

    Central commission has passed an order in suo-motu

    petition No. 01/2010 “in the matter of rate of

    congestion charge in real time operation in inter-State
    61

    transmission of electricity”. para 2(5) of this order

    says:

    ******* “It is important to note that at a frequency

    greater than 50 Hz, the congestion would not be

    caused by the overdrawing utility but by the utility

    injecting power into the congested transmission

    corridor and the congestion charge would instead be

    applied on the Injecting utility. The detailed procedure

    for levy of congestion charge is given in the

    Congestion Charge Regulations. For the injecting

    utility, the remedy would be to reduce injection through

    reduction of generation in its control area.

    ******* Further 22 (c) of the referred CERC order says:

    ******* “at frequency below 50 Hz, congestion charge

    would be levied for over-drawal in the importing

    control area and at frequencies above 50 Hz,

    congestion charge would be levied for under-drawal in

    the exporting control area.”

    ******* These two provisions of CERC relating to

    congestion charges requires special attention. As

    mentioned above, CSPDCL is a regional entity and UI

    pool member for inter-State power transactions. The

    power developers connected to the State grid are the

    intra-State entities. Now, at a situation when there is

    under-drawal position by CSPDCL, at frequency
    62

    above 50 Hz, if power injection (supply) is not

    regulated then the CSPDCL is liable to pay congestion

    charge at Rs 5.45 per kwh. This penal clause will

    definitely have an adverse impact. This situation can

    be avoided mainly by two methods. First, by adopting

    merit order purchase principle and second by properly

    controlling and regulating the Injection into the State

    grid. The first method of regulating power supply by

    adopting merit order purchase will be discussed in

    coming paragraphs. So here we will examine the

    second point i.e. injection limit only. There are two

    modes of power purchase by CSPDCL, long-term and

    short-term. Major portion of CSPDCL’s power

    purchase is through long-term route. The rate of

    power purchase through long-term route is generally

    less than short-term power purchase price. For

    Central generating station, the IEGC and UI

    Regulations specifies provisions for controlled

    injection to avoid over-injection, misuse and gaming.

    The CSPGCL supplies its full power to State and also

    the tariff of State generating utility is less than rates of

    short-term power purchase by CSPDCL. So the

    supply from CSPGCL into the grid can not be

    restricted except otherwise under an extreme grid

    emergency conditions and for safety purpose. Hence,

    among the entities which are connected to the State

    grid, the remaining is the suppliers who supply power
    63

    through short-term route. According to the existing

    terms and conditions of short-term power supply, for

    off-peak hours there is an over-injection limit of 110%,

    which may take care of the situation to some extent.

    For off-peak hours supply, there is disincentive, if the

    IPPs/CGPs continue supplying power beyond 110% of

    the contracted quantum. For short-term peak hours

    supply, there is no limit of injection. Of course a power

    plant can supply power only upto its capacity of

    generation, but here in the State, most of the power

    plants who supply power to CSPDCL are CGPs which

    have in house captive load. The supply to the grid can

    vary (upto the capacity of generation), depending

    upon drawal of their captive load. Some IPPs supply

    power to the buyers outside the State, during peak

    hours also. Such IPPs may vary the quantum of power

    injection into the State grid as per their commercial

    interest. If an IPP or CGP understates Its capacity and

    enters into contract for less quantum of power than

    what it can actually supply (for power supply during

    the peak hours) it has no disincentive as it can inject

    power to the extent to attain load factor of 80% and

    get the full rate (price) for supply of power though It

    may cause under-drawal by CSPDCL and congestion

    in the system. The associations and some generators

    have stated that there is TOD tariff for peak hours and

    so there should not be any injection limit. On this
    64

    point, the Commission would like to clarify that TOD is

    the tariff for supply to consumers during peak and

    other hours and here we are concerned with quantum

    of injection and drawal. In the order dated 18.04.09,

    the over-injection limit was kept at 110% for peak

    hours supply also, but on the request of the power

    developers and keeping in view that CSPDCL faces

    shortage of power specially during peak hours, this

    restriction was removed by order dated 23.06.09.

    ******* In the light of above discussions, the

    Commission comes into conclusion that there is a

    need to impose over-injection limit for peak hour short-

    term supply also. Summing up this issue, there are

    three main reasons for imposing injection limit during

    peak hour. First, commercial Implication to the State

    because of congestion charges. Second, to avoid

    possibility of misuse of the existing provisions for

    unlimited injection (for short-term supply) during peak

    hours. The third reason for imposing such limitation

    shall be covered in succeeding paragraphs 9 below.

    ******* Now what shall be the limit of over-injection is

    another important issue. Except a few, most of the

    power plants in the State are of low capacity. So in a

    general context, taking a liberal view the Commission

    fixes an over-injection limit of 120% for peak hours
    65

    supply, however, for off-peak hours the injection limit

    of 110% is maintained.

    ******* The over-injection limit has to be monitored on

    real time basis by SLDC. The real time data may not

    be available to SLDC in some cases. The Commission

    is of the view that apart from monitoring injection

    during real time operations, there should be a

    disincentive if the suppliers continue supplying power

    over the specified limit. For power supply during off-

    peak hours, the rate of power supply beyond the

    specified limits, was fixed at Re 1/- per unit which is

    maintained during 2010-11 also. This provision was

    incorporated with a view to discourage injection

    beyond the permissible limits and the same shall be

    continued for the year 2010-11. This rate of Re.1/- per

    unit shall also be applicable for supply during peak

    hour beyond the permissible limit.”

    61. After having considered all the surrounding circumstances and the

    nature of the transaction and supply of electricity, the Commission

    decided the base rate, effective rate, minimum effective rate during

    the off-peak hours and peak hours, which is as under:-

    “18. In view of the above, the Commission decides

    as follows:

    66

    (1) The maximum base rate for power supply at 80%

    and above load factor of the schedule power shall be

    Rs. 3.10 per kwh, which is 5% more as compare to the

    maximum base rate for the year 2009-10.

    (2) The effective rate for power supply below 80% load

    factor will be calculated as follows:

    Effective Rate in Rs. – Agreed base rate XLFN
    80%
    The agreed base rate is the rate agreed between the

    supplier and CSPDCL, which may be equal to or less

    than the maximum base rate of Rs. 3.10 per kwh.

    (3) The minimum effective rate shall be Rs 1.50 per

    unit.

    (4) The rate for power supply during peak hours i.e.

    18:00 hrs. to 23:00 hrs. shall be 5% more than the

    agreed base rate /effective rate, as the case may be.

    (5) Rate for power supplied beyond over-injection limit:

    Off peak hour supply: The rate for excess supply, i.e.

    for over-injection over and above 110% of scheduled

    energy in time block, Re 1/- per KWh.

    Peak hour supply: The rate for excess supply, l.e. for

    over-injection over and above 120% of scheduled

    energy in time block, Re. 1/- per Kwh.
    67

    (6) The rate of infirm power, i.e. power supplied by any

    CGP/IPP, before the date of COD of their power plant

    shall be Rs. 1/- per unit. This rate of infirm power is

    applicable to the power plants who may enter PPA

    with CSPDCL.”

    62. In the case of “Power Grid Corporation of India Ltd.” (supra), it has

    been considered that:

    “11.4. Further, APTEL had already addressed a similar

    question in Nuclear Power Corpn. of India Ltd. v. CERC

    wherein it was held as under: (SCC OnLine APTEL

    para 10)

    “10. … 10.5. Accordingly, in absence of specific

    provisions in the Sharing Regulations/Tariff

    Regulations, 2014 to deal with the situation under

    question the Central Commission through exercise

    of its regulatory powers has prescribed a principle for

    sharing of transmission charges of the Transmission

    System of Respondent 2 in the impugned order.

    Thus, it is observed that by way of exercising its

    regulatory power by a way of judicial order(s) the

    Central Commission has laid down the principles of

    payment of transmission charges in such an

    eventuality. However, it is felt that the Central

    Commission in the impugned order has abruptly

    concluded the payment liability on the appellant just
    68

    by referring to its earlier orders and not establishing

    the linkage with the present case explicitly. This

    Tribunal would like to clarify the same.”

    Respondent 1 submitted that APTEL had taken a

    peculiar view of the matter. Although CERC exercises

    twin powers of adjudication and regulation, yet the f fact

    remains that the regulatory power cannot be exercised

    by way of a judicial order. Since APTEL took a contrary

    view on the issues at hand, Respondent 1 was of the

    view that no useful purpose would be served by filing an

    appeal under Section 111.

    12. Having heard the parties, the High Court affirmed

    that despite the availability of an alternative remedy, a

    writ petition can be entertained if any of the factors

    mentioned in Whirlpool are satisfied. Since Respondent

    1 had challenged the constitutionality of the orders of

    CERC dated 21-1-2020 and 27-1-2020, respectively, on

    the grounds that the power exercised by CERC was

    beyond the powers vested in it as per the relevant

    regulation and that the relief granted to the appellant

    was beyond the reliefs prayed for, the High Court was

    of the opinion that the principles of natural justice were

    breached. Therefore, despite the availability of an

    alternative remedy, the writ petition deserved to be
    69

    entertained. Having held so, the High Court admitted

    the writ petition for hearing on merits.

    67. In view of the aforesaid exposition of law, we find

    that this Court’s observations in Whirlpool are of no

    avail to Respondent 1 as the present matter falls in

    none of the cases enumerated therein. Therefore, there

    was no occasion for the High Court to admit the writ

    petition of Respondent 1.

    68. For all the foregoing reasons, we have reached the

    conclusion that the High Court committed an egregious

    error in passing the impugned judgment. We are left

    with no other option but to set aside the impugned

    judgment and order dated 25-2-2021 passed by the

    High Court and dismiss both the writ petitions. In the

    result, the appeals succeed and are hereby allowed.”

    63. In a regulated sector such as electricity, all commercial arrangements

    remain subject to statutory tariff determination and regulatory

    oversight under the Electricity Act, 2003. Reliance has been placed

    on the judgment of “Haryana Power Purchase Centre v. Sasan

    Power Ltd. and Others“, 2023 SCC OnLine SC 577, wherein it has

    been held that:-

    “95. We are of the view that what the parties

    contemplated under Article 13.2 was that change in

    law must be viewed through the specific provisions of
    70

    clauses (a) and (b). In other words, a change in law

    may occur during the period of construction. Then it is

    to be treated as falling under Article 13.2 (a). A

    change in law may occur during the period of its

    operation. It would then appear to be dealt with under

    clause (b). If a change in law takes place during the

    period of construction then its impact is to be

    measured with reference to the capital cost of the

    project. The word “capital cost” understandably has

    been defined in PPA. A formula has been engrafted.

    The formula contemplates that for every

    increase/decrease of each Rs 50 crores in the capital

    cost as a result of the change in law, the

    increase/decrease in the non-escalable capacity

    charges is to be 0.267% of the non-escalable capacity

    charges. No doubt, this is if the seller provides to the

    procurers documentary proof of such

    increase/decrease in establishing the impact of such

    change.

    96. In other words, the effect of change in law during

    the construction period is captured by Article 13.2(a).

    We must understand that this is a meticulously

    thought through contract which emerged after a long

    rigorous process. Parties were clear about how the

    change in law had to be compensated and

    methodology has been set out clearly. Therefore, any
    71

    appeal made to the general part in Article 13.2 which

    speaks about the affected party being restored to the

    same economic condition as if such change in law had

    not occurred cannot result in departing from the

    specific formula which has been set in place. This

    meaning is inevitable from the words “to the extent

    contemplated in this Article 13″, which precedes the

    general words.”

    64. The proposition emerging from paragraph 95 of “Haryana Power

    Purchase Centre” (supra), that regulatory authorities cannot

    override contractual terms, is not of universal application and is

    confined to the specific context of tariff discovered through

    competitive bidding under Section 63 of the Electricity Act, 2003. This

    position is qualified by earlier decisions of the Hon’ble Supreme

    Court, which have consistently held that contractual arrangements in

    the electricity sector are subservient to statutory regulation and public

    interest. In All India Power Engineer Federation v. Sasan Power

    Ltd., (2017) 1 SCC 487, the Hon’ble Supreme Court categorically

    held that even contractual waivers or arrangements cannot be

    enforced if they are contrary to public interest or affect tariff

    determination, emphasizing the primacy of Sections 61 to 63 of the

    Act. Further, in “Energy Watchdog v. Central Electricity

    Regulatory Commission“, (2017) 14 SCC 80, the Hon’ble Supreme

    Court has reiterated that tariff fixation is a statutory function of the

    Regulatory Commission and cannot be left to private agreements

    between parties, thereby underscoring that PPAs operate within, and
    72

    are subject to, the regulatory framework particularly in matters

    affecting tariff and public interest. These decisions clearly establish

    that tariff fixation is not a matter of private contract alone but is

    governed by statutory regulation.

    65. In the case of “Adani Power Maharashtra Ltd.” (supra), the Hon’ble

    Supreme Court has observed that:

    “119. In this respect, we may refer to the following

    observations of this Court in Reliance Infrastructure Ltd.

    v. State of Maharashtra18: (SCC pp. 376-77, paras 38-

    39)

    “38. MERC is an expert body which is entrusted with

    the duty and function to frame regulations, including

    the terms and conditions for the determination of

    tariff. The Court, while exercising its power of judicial

    review, can step in where a case of manifest

    unreasonableness or arbitrariness is made out.

    Similarly, where the delegate of the legislature has

    failed to follow statutory procedures or to take into

    account factors which it is mandated by the statute

    to consider or has founded its determination of tariffs

    on extraneous considerations, the Court in the

    exercise of its power of judicial review will ensure

    that the statute is not breached. However, it is no

    part of the function of the Court to substitute its own

    determination for a determination which was made
    73

    by an expert body after due consideration of material

    circumstances.

    39. In Assn. of Industrial Electricity Users v. State of

    A.P.19 a three-Judge Bench of this Court dealt with

    the fixation of tariffs and held thus: (SCC p. 717,

    para 11)

    ’11. We also agree with the High Court20 that the

    judicial review in a matter with regard to fixation

    of tariff has not to be as that of an appellate

    authority in exercise of its jurisdiction under

    Article 226 of the Constitution. All that the High

    Court has to be satisfied with is that the

    Commission has followed the proper procedure

    and unless it can be demonstrated that its

    decision is on the face of it arbitrary or illegal or

    contrary to the Act, the court will not interfere.

    Fixing a tariff and providing for cross-subsidy is

    essentially a matter of policy and normally a court

    would refrain from interfering with a policy

    decision unless the power exercised is arbitrary

    or ex facie bad in law.”

    66. In the case of “Sasan Power Ltd. (2017)” (supra), the Hon’ble

    Supreme Court has held that:-

    74

    “21. Regard being had to the aforesaid decisions, it is

    clear that when waiver is spoken of in the realm of

    contract, Section 63 of the Indian Contract Act, 1872

    governs. But it is important to note that waiver is an

    intentional relinquishment of a known right, and that,

    therefore, unless there is a clear intention to relinquish

    a right that is fully known to a party, a party cannot be

    said to waive it. But the matter does not end here. It is

    also clear that if any element of public interest is

    involved and a waiver takes place by one of the

    parties to an agreement, such waiver will not be given

    effect to if it is contrary to such public interest. This is

    clear from a reading of the following authorities.

    22. In Lachoo Mal v. Radhey Shyam, (1971) 1 SCC

    619, it was held:-

    “The general principle is that everyone has a right to

    waive and to agree to waive the advantage of a law or

    rule made solely for the benefit and protection of the

    individual in his private capacity which may be

    dispensed with without infringing any public right or

    public policy. Thus the maxim which sanctions the

    non-observance of the statutory provision is cuilibet

    licet renuntiare juri pro se introducto. (See Maxwell on

    Interpretation of Statutes, Eleventh Edn., pp. 375 and

    376). If there is any express prohibition against
    75

    contracting out of a statute in it then no question can

    arise of anyone entering into a contract which is so

    prohibited but where there is no such prohibition it will

    have to be seen whether an Act is intended to have a

    more extensive operation as a matter of public policy.”

    23. In Indira Bai v. Nand Kishore, (1990) 4 SCC 668, it

    was held:-

    “The test to determine the nature of interest, namely,

    private or public is whether the right which is

    renunciated is the right of party alone or of the public

    also in the sense that the general welfare of the

    society is involved. If the answer is latter then it may

    be difficult to put estoppel as a defence. But if it is right

    of party alone then it is capable of being abnegated

    either in writing or by conduct.”

    24. In Krishna Bahadur v. Purna Theatre, (2004) 8

    SCC 229, it was held:

    “9. The principle of waiver although is akin to the

    principle of estoppel; the difference between the two,

    however, is that whereas estoppel is not a cause of

    action; it is a rule of evidence; waiver is contractual

    and may constitute a cause of action; it is an

    agreement between the parties and a party fully
    76

    knowing of its rights has agreed not to assert a right

    for a consideration.

    10. A right can be waived by the party for whose

    benefit certain requirements or conditions had been

    provided for by a statute subject to the condition that

    no public interest is involved therein. Whenever waiver

    is pleaded it is for the party pleading the same to show

    that an agreement waiving the right in consideration of

    some compromise came into being. Statutory right,

    however, may also be waived by his conduct.”

    25. It is thus clear that if there is any element of public

    interest involved, the court steps in to thwart any

    waiver which may be contrary to such public interest.

    26. On the facts of this case, it is clear that the

    moment electricity tariff gets affected, the consumer

    interest comes in and public interest gets affected.

    This is in fact statutorily recognized by the Electricity

    Act in Sections 61 to 63 thereof. Under Section 61, the

    appropriate commission, when it specifies terms and

    conditions for determination of tariff, is to be guided

    inter alia by the safeguarding of the consumer interest

    and the recovery of the cost of electricity in a

    reasonable manner. For this purpose, factors that

    encourage competition, efficiency and good

    performance are also to be heeded. Under Section 62
    77

    of the Act, the appropriate commission is to determine

    such tariff in accordance with the principles contained

    in Section 61. The present case, however, is covered

    by Section 63, which begins with a non obstante

    clause stating that notwithstanding anything contained

    in Section 62, the appropriate commission shall adopt

    the tariff if such tariff has been determined through a

    transparent process of bidding in accordance with the

    guidelines issued by the Central Government. The

    guidelines dated 19.1.2005 issued by the Central

    Government under Section 63 make it clear that such

    guidelines are framed with the following objectives in

    mind:

    “These guidelines have been framed under the above

    provisions of section 63 of the Act. The specific

    objectives of these guidelines are as follows:

    1) Promote competitive procurement of electricity by

    distribution licensees;

    2) Facilitate transparency and fairness in procurement

    processes;

    3) Facilitate reduction of information asymmetries for

    various bidders;

    78

    4) Protect consumer interests by facilitating

    competitive conditions in procurement of electricity;

    5) Enhance standardization and reduce ambiguity and

    hence time for materialization of projects;

    6) Provide flexibility to suppliers on internal operations

    while ensuring certainty on availability of power and

    tariffs for buyers.

    Clause 2.3 of the said guidelines reads as follows:

    “2.3. Unless explicitly specified in these guidelines, the

    provisions of these guidelines shall be binding on the

    procurer. The process to be adopted in event of any

    deviation proposed from these guidelines is specified

    later in these guidelines under para 5.16.”

    27. Paragraph 4 of the aforesaid guidelines relates to

    tariff structure and paragraph 4.11 in particular, which

    relates to energy charges, is as follows:-

    “4.11 Where applicable, the energy charges payable

    during the operation of the contract shall be related on

    the base energy charges specified in the bid with

    suitable provision for escalation. In case the bidder

    provides firm energy charge rates for each of the

    years of the contract term, the same shall be permitted

    in the tariffs.”

    79

    28. Para 5.4 then speaks of a model power purchase

    agreement proposed to be entered into with the seller

    of electricity as follows:-

    “(ii) Model PPA proposed to be entered into with the

    seller of electricity. The PPA shall include necessary

    details on:

    (a) Risk allocation between parties;

    (b)   Technical     requirements   on    minimum    load
    
    conditions;
    
    (c) Assured offtake levels;
    
    

    (d) Force majeure clauses as per industry standards;

    (e) Lead times for scheduling of power;

    (f) Default conditions and cure thereof, and penalties;

    (g) Payment security proposed to be offered by the

    procurer.”

    29. Paragraph 5.16 then goes on to state:-

    “Deviation from process defined in the guidelines

    5.16 In case there is any deviation from these

    guidelines, the same shall be with the prior approval of

    the Appropriate Commission. The Appropriate

    Commission shall decide on the modifications to the

    bid documents within a reasonable time not exceeding

    90 days.”

    80

    30. A perusal of the CERC tariff adoption order in the

    present case dated 17.10.2007 makes it clear that the

    tariff is adopted by the Commission only because the

    competitive bidding process which has been

    undertaken is in accordance with the guidelines so

    issued.

    31. All this would make it clear that even if a waiver is

    claimed of some of the provisions of the PPA, such

    waiver, if it affects tariffs that are ultimately payable by

    the consumer, would necessarily affect public interest

    and would have to pass muster of the Commission

    under Sections 61 to 63 of the Electricity Act. This is

    for the reason that what is adopted by the Commission

    under Section 63 is only a tariff obtained by

    competitive bidding in conformity with guidelines

    issued. If at any subsequent point of time such tariff is

    increased, which increase is outside the four corners

    of the PPA, even in cases covered by Section 63, the

    legislative intent and the language of Sections 61 and

    62 make it clear that the Commission alone can

    accept such amended tariff as it would impact

    consumer interest and therefore public interest.”

    67. Thus, the ratio in Sasan Power (2023) cannot be read as excluding

    regulatory intervention altogether; rather, it is confined to situations

    where the statute expressly preserves the sanctity of competitively
    81

    discovered tariff. In cases falling under Section 62, or involving

    issues of grid discipline, public interest, or statutory compliance, the

    regulatory authorities retain full jurisdiction, and contractual terms

    cannot be enforced in derogation of statutory mandate.

    68. It is equally borne out that CSPDCL initiated tariff and true-up

    proceedings before the State Commission in 2014, wherein the

    Commission, upon detailed examination of load curve data, injection

    patterns, and operational parameters, recorded a categorical finding

    that the power supplied by the petitioner was non-firm, intermittent,

    and unstable in nature. Based on such technical evaluation, the

    Commission determined that such power could not be equated with

    firm power and accordingly restricted the tariff to a minimum base

    rate of Rs. 1.50 per kWh. The said findings were subjected to review

    and thereafter carried in appeal before the Appellate Tribunal for

    Electricity (APTEL), which, by its judgment dated 26.05.2016,

    affirmed the conclusions of the State Commission. These findings,

    having attained finality within the statutory framework, are binding

    and cannot be lightly interfered.

    69. The principal contention advanced by the petitioner is that it was not

    impleaded as a party to the tariff or appellate proceedings and was

    not afforded any opportunity of hearing before imposing liability, and

    therefore, the subsequent demand raised against it is vitiated for

    violation of principles of natural justice. While the doctrine of audi

    alteram partem is indeed a fundamental facet of fair procedure, its

    application must be understood in the context of the nature of the
    82

    proceedings in question. The tariff determination and true-up

    exercise undertaken by the State Commission are legislative or

    quasi-legislative in character, carried out in accordance with the

    Conduct of Business Regulations, which contemplate issuance of

    public notices and stakeholder participation rather than individual

    impleadment of every entity that may be indirectly affected. The

    record reflects that public notices were duly issued, proceedings

    were conducted transparently, and representatives of industry,

    including that of the petitioner, had participated at various stages. In

    such circumstances, it cannot be said that the petitioner was wholly

    unaware of or excluded from the regulatory process.

    70. Moreover, the impugned demand does not arise in isolation but is a

    direct consequence of the tariff determination made by the State

    Commission and affirmed by APTEL. The statutory scheme under

    Sections 61 and 62 of the Electricity Act, 2003, vests exclusive

    authority in the Commission to determine tariffs, and such

    determination overrides any contractual arrangement to the contrary.

    It is well settled that in matters of tariff, the regulatory framework

    prevails over private agreements, as the same is guided by

    considerations of public interest and consumer protection. Therefore,

    even if the PPAs provided for a particular pricing mechanism, the

    same would remain subject to the tariff ultimately determined by the

    Commission.

    71. The submission that the tariff orders did not specifically direct

    recovery from the petitioner does not advance the case of the
    83

    petitioner. Once it is found, in accordance with law, that the tariff

    applicable to the supply in question is lower than what has been paid,

    the consequence of adjustment or recovery necessarily follows under

    Section 62(6) of the Act, which mandates refund of excess tariff

    recovered by a generating company. The absence of an express

    direction against the petitioner in the tariff order does not negate the

    statutory obligation arising therefrom. The demand raised by

    CSPDCL is thus traceable to and supported by the binding tariff

    orders and appellate judgment.

    72. The argument that concluded transactions cannot be reopened is

    also devoid of merit in the present context. The true-up exercise

    undertaken by the Commission precisely envisages the adjustment

    of past transactions based on actual data and a prudence check.

    Such retrospective correction is an integral feature of tariff regulation

    and is intended to balance the interests of utilities and consumers.

    Accepting the petitioner’s contention would defeat the very purpose

    of the statutory mechanism and permit retention of amounts found to

    be in excess of the permissible tariff, thereby resulting in unjust

    enrichment. In this regard, the judgment of Hon’ble Supreme Court in

    the case of “Indian Council for Enviro-Legal Action v. Union of

    India” 2011 (8) SCC 161 is relevant, in which it has been held that:

    “151. Unjust enrichment has been defined as:

    “Unjust enrichment. A benefit obtained from another,

    not intended as a gift and not legally justifiable, for
    84

    which the beneficiary must make restitution or

    recompense.”

    See Black’s Law Dictionary, 8th Edn. (Bryan A. Garner)

    at p. 1573. A claim for unjust enrichment arises where

    there has been an “unjust retention of a benefit to the

    loss of another, or the retention of money or property of

    another against the fundamental principles of justice or

    equity and good conscience”.

    152. “Unjust enrichment” has been defined by the court

    as the unjust retention of a benefit to the loss of

    another, or the retention of money or property of

    another against the fundamental principles of justice or

    equity and good conscience. A person is enriched if he

    has received a benefit, and he is unjustly enriched if

    retention of the benefit would be unjust. Unjust

    enrichment of a person occurs when he has and retains

    money or benefits which in justice and equity belong to

    another.

    153. Unjust enrichment is “the unjust retention of a

    benefit to the loss of another, or the retention of money

    or property of another against the fundamental

    principles of justice or equity and good conscience”. A

    defendant may be liable “even when the defendant

    retaining the benefit is not a wrongdoer” and “even
    85

    though he may have received [it] honestly in the first

    instance”. (Schock v. Nash, A 2d, 232-33.)

    154. Unjust enrichment occurs when the defendant

    wrongfully secures a benefit or passively receives a

    benefit which would be unconscionable to retain. In the

    leading case of Fibrosa Spolka Akcyjna v. Fairbairn

    Lawson Combe Barbour Ltd 62, Lord Wright stated the

    principle thus: (AC p. 61)

    “… [A]ny civilised system of law is bound to provide

    remedies for cases of what has been called unjust

    enrichment or unjust benefit, that is to prevent a man

    from retaining the money of or some benefit derived

    from another which it is against conscience that he

    should keep. Such remedies in English law are

    generically different from remedies in contract or in

    tort, and are now recognised to fall within a third

    category of the common law which has been called

    quasi-contract or restitution.”

    155. Lord Denning also stated in Nelson v. Larholt63 as

    under: (KB p. 343)

    “… It is no longer appropriate, however, to draw a

    distinction between law and equity. Principles have

    now to be stated in the light of their combined effect.

    Nor is it necessary to canvass the niceties of the old
    86

    forms of action. Remedies now depend on the

    substance of the right, not on whether they can be

    fitted into a particular framework. The right here is

    not peculiar to equity or contract or tort, but falls

    naturally within the important category of cases

    where the court orders restitution, if the justice of the

    case so requires.”

    73. Insofar as the reliance placed by the petitioner on principles of

    natural justice is concerned, it must be noted that no prejudice, in the

    legal sense, has been demonstrated. The characterization of the

    power as non-firm is based on objective technical data relating to

    injection patterns, which have been consistently recorded by the

    State Commission and affirmed by APTEL. The petitioner has not

    placed any material before this Court to dislodge these findings or to

    demonstrate that the tariff applied by it was in conformity with the

    statutory determination. In the absence of any substantive challenge

    to the foundational findings, the plea of violation of natural justice

    cannot be invoked as a mere technical ground to invalidate

    consequential action.

    74. The contention that the dispute involves complex technical issues

    further weighs with this Court in declining interference. The

    determination of the nature of power supply, its impact on grid

    stability, and the appropriate tariff are matters falling within the

    domain of expert regulatory bodies. The State Commission and

    APTEL, being specialized forums, have examined these aspects in
    87

    detail. It is not the function of this Court, in exercise of writ

    jurisdiction, to reappreciate such technical findings or sit in appeal

    over the conclusions reached by expert bodies.

    75. The denial of No Objection Certificate (NOC) and the consequent

    rejection of the petitioner’s applications for Short Term Open Access

    (STOA) by Respondent No. 3 also do not warrant interference. A

    scrutiny of the statutory scheme and the material placed on record

    would demonstrate that such action is rooted not merely in the

    existence of alleged outstanding dues, but in the larger and

    paramount consideration of maintaining grid discipline and ensuring

    secure, reliable, and economic operation of the power system within

    the State. Under Section 31 of the Electricity Act, 2003, the State

    Load Dispatch Centre (SLDC) is constituted as the apex body for

    integrated operation of the power system within the State, and under

    Section 32, it is entrusted with critical functions including scheduling

    and dispatch of electricity, monitoring grid operations, keeping

    accounts of electricity transmitted, and exercising supervision and

    control over intra-State transmission. These functions are not merely

    administrative but are technical and operational in nature, requiring

    continuous real-time assessment of grid conditions. Further, Section

    33 confers wide powers upon the SLDC to issue binding directions to

    generating companies, licensees, and other participants in the grid to

    ensure stability and discipline. Compliance with such directions is

    mandatory, and any deviation has the potential to jeopardize the

    entire grid system.

    88

    76. In the present case, the record reveals that the petitioner had a

    consistent history of injecting power in a fluctuating and

    unpredictable manner, with significant variations in generation

    ranging from negligible or zero output to sudden high injections. Such

    erratic patterns of supply have been specifically noted by the SLDC

    in multiple communications issued over a period of time, wherein the

    petitioner was repeatedly called upon to adhere to scheduled

    generation and maintain grid discipline. These deviations were not

    isolated or sporadic but constituted a recurring operational concern,

    affecting load management and requiring compensatory adjustments

    by the system operator. The consequences of such non-firm and

    unstable injection are far-reaching. The grid operates on a delicate

    balance between supply and demand, and any significant deviation

    can result in overdrawal or underdrawal situations, frequency

    fluctuations, and potential grid disturbances. These, in turn, may

    attract penalties under applicable regulations and may even pose

    risks to the stability and integrity of the transmission system. It is in

    this backdrop that the State Commission, in its tariff order, also

    recognized the adverse impact of non-firm power on grid operations

    and issued directions to discourage such practices.

    77. In light of these statutory responsibilities and technical

    considerations, the SLDC is duty-bound to exercise caution while

    granting open access to any entity. The grant of STOA is not a

    matter of right but is subject to the fulfilment of regulatory conditions,

    including adherence to grid discipline, technical feasibility, and

    system security. Where an entity has demonstrated a pattern of non-
    89

    compliance with scheduling norms or has been found to inject power

    in a manner detrimental to grid stability, the SLDC would be justified

    in withholding or regulating access in the larger public interest.

    78. The contention of the petitioner that the denial of NOC was solely on

    account of the alleged outstanding dues does not find full support in

    the record. While the existence of dues may have been one of the

    factors considered, it is evident that the decision was also influenced

    by the petitioner’s past conduct in relation to grid operations and its

    inability to ensure firm and reliable supply. The communications

    issued by Respondent No. 3 reflect concerns regarding operational

    discipline, compliance with scheduling instructions, and the potential

    risk posed to the grid. Therefore, the decision cannot be

    characterized as arbitrary or extraneous.

    79. It is also pertinent to note that the statutory framework casts a

    responsibility upon the SLDC to act in a preventive manner rather

    than a reactive one. The objective is to ensure that grid disturbances

    are avoided, rather than remedied after occurrence. In such a

    scenario, the SLDC is entitled to take into account the past

    performance and operational behaviour of an applicant while

    considering the grant of open access. The petitioner, having been

    repeatedly cautioned and having failed to demonstrate consistent

    compliance, cannot claim an indefeasible right to open access.

    Judicial review in such matters is necessarily limited. The decision to

    grant or deny open access involves technical assessment,

    operational expertise, and real-time considerations, which fall within
    90

    the domain of specialized authorities. Unless the decision is shown to

    be mala fide, perverse, or in clear violation of statutory provisions,

    this Court would be slow to interfere. In the present case, no such

    infirmity has been demonstrated.

    80. The another submission raised by learned counsel for the petitioners

    that with respect to other power generators, who are similarly

    situated, no order has been passed by the respondents. By

    submitting the said contention, the petitioners are claiming negative

    parity, which cannot be claimed, as has been held by the Hon’ble

    Supreme Court in the case of “R. Muthukumar and others” (supra),

    in which in para 28 and 29, it has been held that:

    “28. A principle, axiomatic in this country’s constitutional

    lore is that there is no negative equality. In other words,

    if there has been a benefit or advantage conferred on

    one or a set of people, without legal basis or

    justification, that benefit cannot multiply, or be relied

    upon as a principle of parity or equality. In Basawaraj v.

    Special Land Acquisition Officer, this court ruled that:

    “8. It is a settled legal proposition that Article 14 of

    the Constitution is not meant to perpetuate illegality

    or fraud, even by extending the wrong decisions

    made in other cases. The said provision does not

    envisage negative equality but has only a positive

    aspect. Thus, if some other similarly situated

    persons have been granted some relief/benefit
    91

    inadvertently or by mistake, such an order does not

    confer any legal right on others to get the same

    relief as well. If a wrong is committed in an earlier

    case, it cannot be perpetuated.”

    29. Other decisions have enunciated or applied this

    principle (Ref: Chandigarh Admn. v. Jagjit Singh, Anand

    Buttons Ltd. v. State of Haryana, K.K. Bhalla v. State of

    M.P.17; Fuljit Kaur v. State of Punjab, and Chaman Lal

    v. State of Punjab). Recently, in The State of Odisha v.

    Anup Kumar Senapati this court observed as follows:

    “If an illegality and irregularity has been committed in

    favour of an individual or a group of individuals or a

    wrong order has been passed by a judicial forum,

    others cannot invoke the jurisdiction of the higher or

    superior court for repeating or multiplying the same

    irregularity or illegality or for passing a similarly

    wrong order. A wrong order/decision in favour of any

    particular party does not entitle any other party to

    claim benefits on the basis of the wrong decision.”

    81. Accordingly, this Court is of the considered view that the denial of

    NOC and rejection of STOA applications by Respondent No. 3 is in

    consonance with the statutory mandate under Sections 32 and 33 of

    the Electricity Act, 2003, and is justified on grounds of maintaining

    grid discipline, system security, and public interest. The action,

    therefore, cannot be termed as arbitrary, unreasonable, or without

    authority of law.

    92

    82. The plea based on the doctrine of approbation and reprobation is

    equally untenable. CSPDCL, being a distribution licensee, is bound

    to act in accordance with statutory tariff orders and cannot be

    estopped from enforcing the same merely because payments were

    earlier made under a different understanding. The doctrine of

    estoppel cannot operate against a statute, nor can it be invoked to

    defeat public interest embedded in tariff regulation. The recovery

    sought is not in the nature of repudiation of contract, but in

    furtherance of statutory compliance.

    83. Having regard to the totality of circumstances, this Court is of the

    considered opinion that the demand notice dated 07.07.2016 is not

    without jurisdiction, but is a consequential action flowing from binding

    tariff orders and the judgment of APTEL. The petitioner has failed to

    establish any ground warranting interference under Article 226 of the

    Constitution. The issues raised pertain to matters of tariff

    determination, technical evaluation, and regulatory policy, which

    have already been adjudicated by competent statutory forums.

    84. Accordingly, this Court finds no merit in the writ petition. The same is

    liable to be and is hereby dismissed. No order as to costs.

    85. Interim order granted earlier also stands vacated.

    Sd/-

    (Ravindra Kumar Agrawal)
    Judge
    ved
    93

    HEAD NOTE

    The principle that regulatory authorities cannot

    override contractual terms is not of universal application.

    Tariff fixation is a statutory function of the Regulatory

    Commission and cannot be left to private agreements

    between the parties; it is subject to the regulatory

    framework, particularly in matters affecting tariff and

    public interest.



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here