Jaiswal Iron And Steel Company And Ors vs Board Of Trustees For Syama Prasad on 6 April, 2026

    0
    30
    ADVERTISEMENT

    Calcutta High Court

    Jaiswal Iron And Steel Company And Ors vs Board Of Trustees For Syama Prasad on 6 April, 2026

    O-1
                                    ORDER SHEET
    
                        IN THE HIGH COURT AT CALCUTTA
                       CONSTITUTIONAL WRIT JURISDICTION
                                 ORIGINAL SIDE
    
                                    WPO/157/2026
    
                   JAISWAL IRON AND STEEL COMPANY AND ORS.
                                      VS
                     BOARD OF TRUSTEES FOR SYAMA PRASAD
                     MOOKERJEE PORT OF KOLKATA AND ORS.
    
    
      BEFORE:
      The Hon'ble JUSTICE KRISHNA RAO
      Date : 6th April, 2026.
    
                                                                                Appearance:
                                                                     Mr. Chayan Gupta, Adv.
                                                          Mr. Pourush Bandhyopadhyay, Adv.
                                                                    Mr. Uttam Sharma, Adv.
                                                                     Mr. Vrinda Kediua, Adv.
                                                                         ...for the petitioners
    
                                                                     Mr. Dhiraj, Trivadi, Adv.
                                                                Mr. Ashok Kumar Jena, Adv.
                                                               ...for the respondent no. 1 to 7

    1. Affidavit of service filed by the petitioners be kept with the records.

    2. The petitioner has filed the present writ petition challenging the

    SPONSORED

    impugned order dated 19th August, 2025 wherein the respondent

    authorities have forfeited the entire sale value deposited by the petitioner

    without any refund against the undelivered portion of the sold lot and

    the petitioner’s firm is debarred from participating any future tenders,

    auctions or tender-cum-auctions conducted by the Syama Prasad

    Mookerjee Port, Kolkata (SMPA) for a period of two years effecting from
    2

    the date of receipt of letter. In the said letter the petitioner was also

    refrained from engaging in any further dealings with the Port during the

    debarment period.

    3. The respondent no. 8 had floated a tender wherein e-auction process was

    held for sale of one number of condemned Pontoon lying at Takta Ghat

    and two members of condemned Pontoons lying at Outram Jetty-2 on

    29.11.2023. The petitioner no. 1 had participated in the said tender and

    the bid submitted by the petitioner no. 1 was found to be the highest and

    was declared as successful bidder. The petitioner no. l deposited entire

    sale consideration alongwith applicable taxes. On receipt of payment, the

    Office of the respondent no. 5 issued daily gate pass/Block gate pass on

    11.1.2024.

    4. Mr. Chayan Gupta, learned Advocate representing the petitioner submits

    that in the gate pass dated 11.1.2024 it is mentioned that the same must

    be treated as Block gate pass and not to be treated as daily gate pass,

    the petitioner has made several requests for issuance of daily gate pass

    but the same was not provided to the petitioners.

    5. Mr. Gupta submits that the petitioners have mobilized the labourers for

    transportation of pontoons as per Block gate pass and oral permissions

    as the daily gate pass has not been issued inspite of several oral request

    made by the petitioners. He submits that Pontoons were already afloat on

    the river water surface. He submits that the authorities permitted the
    3

    petitioners to proceed with cutting operations without insisting upon fire

    clearance.

    6. Mr. Gupta submits that on 6th February, 2024, the Assistant Mooring

    Master stopped the work without any notice. The petitioners on the same

    date made an application requesting for waiver of Clause -2 of the

    delivery note dated 11.1.2024 but the respondents have not considered

    the request of the petitioners and again on 8.2.2024 a request was made

    to the respondent no. 3 for waiver of Clause -2. On 8.2.2024, the

    petitioners have also filed a complaint making allegation of Prevention of

    Corruption Act.

    7. The petitioners have withdrawn the allegation of Prevention of Corruption

    Act. The respondents have issued show cause notice to the petitioners on

    6th March, 2024.

    8. On receipt of the said notice, the petitioners have submitted a reply

    requesting 12 days time to submit comprehensive reply and

    subsequently the petitioners have made detailed representation to the

    authority on 3rd of June, 2024. The respondent authorities have issued

    the impugned order on 19th August, 2025. Now the petitioners have filed

    the present writ application mainly on the ground that the respondent

    authorities have issued a fresh tender for the similar materials without

    considering the fact that on the earlier tender process, the petitioners

    have paid the total tender amount to the authorities with respect to the

    said materials. Now the authorities by way of the fresh tender process
    4

    intend to re-sale the said materials and the last date of the auction is of

    7th April, 2026.

    9. Mr. Gupta, learned Advocate appearing for the petitioners submitted that

    by the impugned order dated 19 th August, 2025, the respondents have

    blacklisted the petitioners without issuing any show cause notice and

    without affording any opportunity of hearing. He further submitted that

    the respondent authorities while issuing the impugned order failed to

    appreciate that the petitioners have already paid the total tender amount

    with respect to the materials in question but the authorities have

    cancelled the said tender, work order and proceeded for a new tender

    process for the same work for which the petitioners are suffering severe

    financial loss.

    10. The petitioners further submit that as per the tender condition, in

    case of any default in lifting of the materials by the petitioners within the

    specified date, the outstanding materials may be lifted on payment of the

    rate at 1% per week or part thereof of the total material value for such

    default period beyond the specified delivery period as stipulated in the

    delivery order at the sole discretion of the SMP, Kolkata. He submitted

    that the respondent authorities without considering the said clause have

    cancelled the delivery order of the petitioners and issued fresh tender for

    the same materials.

    5

    11. Learned Counsel for the petitioners submitted that if an interim

    order is not passed and the respondents are allowed to continue with the

    tender process, the petitioners will suffer severe financial loss.

    12. Per contra, learned advocate appearing for the respondent

    authorities submits that the petitioners have suppressed the document

    while filing the present application.

    13. The learned Advocate appearing for the respondents has handed

    over the auction catalogue report and submits that in the said catalogue

    it is categorically mentioned that “For scrap material to be delivered in

    weight, no cutting will be allowed unless certified by the concerned

    custodian. For equipment, cutting may be allowed for facilitating

    transportation of the same on receipt of the application by the purchaser

    and such permission may be granted at the discretion of KOPT for which

    clearance is to be obtained from the Port Fire Service and payment of

    requisite charges is to be made by the buyer on compliance of related

    formalities as might be necessary as well.”

    14. He submits that in the present case, the petitioners have not

    followed the said condition and have not obtained any permission from

    the concerned authority in terms of the Conditions of the Contract. He

    further submits that as per the Contract condition, there is a clause of

    forfeiture and as per the said clause in case the whole or any part of the

    goods sold remain uncleared, even after the authorized period stated in

    the delivery schedule, the purchaser shall have no claim whatsoever on
    6

    the goods remaining uncleared and the amount paid towards EMD shall

    stand forfeited at the expiry of the said period. He further submits that in

    the present case the petitioners have failed to clear the sold materials

    even after receipt of the show cause notice and under such

    circumstances the respondent authorities have invoked the provisions of

    Clause 8.1 of the Tender Conditions.

    15. Learned Counsel appearing for the respondent authorities has

    further brought to the notice of this Court that the tender documents

    provides an arbitration clause but the petitioners instead of invoking the

    provisions of arbitration, have filed the present writ application which is

    not maintainable. He further submits that the impugned order is issued

    on 19th August, 2025 but the petitioners have not challenged the said

    order till the filing of the instant writ application. Only after issuance of

    the tender notice by the respondent authorities and at the fag end when

    the last date of the tender is on 7th April, 2026, the petitioners have filed

    the present writ application only with the intention to stall the tender

    process.

    16. Learned Counsel for the respondents submits that the writ petition

    is not maintainable and the same is liable to be dismissed.

    17. Heard the Learned Counsel for the respective parties. Perused the

    materials on record.

    18. Admittedly, the petitioners have not removed the materials within

    the delivery period. The ground taken by the petitioners for not taking
    7

    out the materials within the delivery period is that the respondent

    authorities have not provided a gate pass. The authorities have issued

    the show cause notice to the petitioners on 6 th March, 2024, wherein it is

    alleged that the petitioners had commenced the subject work without

    following the prescribed procedure and documentation as mentioned in

    the subject delivery order. It is also the allegation that the petitioners

    have not taken any permission from the Port Fire Services for cutting the

    auctioned materials. It is also the allegation that the petitioners have

    commenced taking away SMPK’s materials without any daily gate pass.

    In the show cause notice it is also alleged that the petitioners

    unauthorisedly resorted to stacking gas cylinder after trespassing into

    the port premises, for cutting of pontoon within the Port premises at

    Outram Jetty-II in front of Riverside Officers Club, without any

    permission from the Port authorities.

    19. It is also at the allegation that the petitioners instead of taking out

    the materials in accordance with the work order issued, the petitioners

    have made several allegations against the Port Officers. In the show

    cause notice the petitioners were given an opportunity to regularize the

    irregularities within 10 days from the date of receipt of this

    communication.

    20. The petitioners have submitted their reply to the show cause notice

    on 16.05.2024 but this Court finds that the petitioners have not given

    any justification to the allegations made in the notice dated 6 th March,
    8

    2024. In the reply the petitioners have prayed for 12 days time to file a

    comprehensive representation. On 3 rd of June, 2024 the petitioners have

    made a detailed reply. The respondents have considered the detailed

    reply and passed the impugned order dated 19 th August, 2025.

    21. The petitioners have raised two issues that in the tender document

    in one place the respondents have stated that in Clause 8.1 that in case

    whole or any part of the goods sold remain uncleared or even after the

    period stated in the delivery schedule, the purchaser shall have no claim

    whatsoever on the goods remaining uncleared and the amount paid

    towards the EMD shall stand forfeited.

    22. On the other hand, in Clause 7.2 it is mentioned that the ground

    rent in case of default in lifting of the materials by the petitioner within

    the specified time limit, the outstanding materials may be lifted on

    payment of ground rent at the rate of one (1) percent per week or part

    thereof, of the total material values for such defaulted period, beyond the

    specified delivery period, as stipulated in the delivery order, at the sole

    discretion of the SMP Kolkata.

    23. The authorities have issued the notice to the petitioner on 6 th

    March, 2024. On 16th May, 2024 the first reply was submitted by the

    petitioners, the petitioners have not given any explanations to the

    allegation in the said reply. Subsequently, on 3 rd June, 2024 the

    petitioners have submitted a detailed representation but in the said

    representation also the petitioners have not stated that they are ready to
    9

    pay interest @ 1% per week, or part thereof, of the total material value for

    such defaulted period beyond the specified delivery period as stipulated

    in the delivery order. Thus, the respondent authorities have not

    considered the request of the petitioners.

    24. Considering the above, this Court finds that when the petitioners

    have made a detailed representation, the petitioners should have opted

    clause 7.2 which the petitioners intend to take the benefit of the said

    clause after the period of delivery. The petitioners have also not pleaded

    for the benefit of the said clause in the writ application that the

    petitioners are ready to pay the 1% of per week charge as per the Clause

    7.2 of the Tender conditions, only at the time of hearing the petitioners

    have pointed out the said clause.

    25. As regards the arbitration is concerned, this Court finds that the

    impugned order was passed in the month of August, 2025. The

    petitioners have not challenged the said order till the filing of the writ

    application. Though this writ application was filed only on 1 st April,

    2026, when the last date of auction schedule was 7 th April, 2026, from

    the said act of the petitioners, this Court is of the view that the

    petitioners only to stall the re-tender process of the respondents have

    filed the present writ application actually the petitioners are not

    aggrieved with the impugned notice dated 19.08.2025.

    26. As regards the blacklisting of the petitioners, this Court finds that

    though the respondents have issued the notice on 6 th March, 2024, but
    10

    in the said notice the respondents have not informed the petitioners that

    the respondents are going to blacklist the firm of the petitioners.

    27. Thus, it is settled law unless an until the petitioners are not given

    an opportunity of hearing with regard to the blacklisting of the firm, the

    order of the blacklisting cannot be sustained.

    28. In view of the above, the writ petition is disposed of only by setting

    aside the part of the order wherein the petitioner firm have been

    blacklisted and other portion of the order is not interfered by this Court.

    29. This writ application is disposed of at the stage of motion. Since no

    affidavit is called for, the allegations made in the writ application are

    deemed to have been denied. However, the petitioners are at liberty to

    take appropriate steps for initiation of arbitration proceeding in

    accordance with law.

    (KRISHNA RAO, J.)

    gb



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here