Indian Newspapaer Society vs Mumbai Metropolitan Region … on 8 April, 2026

    0
    32
    ADVERTISEMENT

    Bombay High Court

    Indian Newspapaer Society vs Mumbai Metropolitan Region … on 8 April, 2026

    2026:BHC-OS:8910-DB
                                                                 Indian-Newspaper-oswp-864-2018-J-R.doc
    
    
    
    
                                                                                                    Shephali
    
    
    
    
                                   IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                                       ORDINARY ORIGINAL CIVIL JURISDICTION
                                           WRIT PETITION NO. 864 OF 2018
    
    
                         Indian Newspaper Society,
                         A company registered under Section 25 of
                         the companies Act, 1956, having its
                         registered office at INS Building,
                         Rafi Marg, New Delhi 110 001.                                    ...Petitioner
    
                                  ~ versus ~
    
                         1.     Mumbai Metropolitan Region
                                Development Authority,
                                a Body Corporate having its Head
                                Office at MMRDA Office Building,
    SHEPHALI                    Plot Nos. C-14 & C-15, 'E' Block,
    SANJAY
    MORMARE                     Bandra Kurla Complex, Bandra (East),
     Digitally signed           Mumbai 400 051.
     by SHEPHALI
     SANJAY
     MORMARE
     Date: 2026.04.09
                         2.     The Metropolitan Commissioner,
     15:15:50 +0530
                                being the Chief Executive Officer of
                                the Mumbai Metropolitan Region
                                Development Authority, having his
                                office at MMRDA Office Building,
                                Plot Nos. C-14 & C-15, 'E' Block,
                                Bandra Kurla Complex, Bandra (East),
                                Mumbai 400 051.                                     ...Respondents
    
                         A PPEARANCES
                         For the Petitioner              Mr. Ankit Lohia, with Mr. Firoz
                                                         Patel,   Mr.   Prashant   Ghelani,
                                                         Ms. Namrata Vashist & Mr. Darshil
                                                         Desai, i/b Markand Gandhi & Co.
                         For Respondents-MMRDA           Dr. Birendra Saraf, Senior Advocate,
                                                         with Mr. Nishant Chotani, Mr. Nivit
                                                         Srivastava, Ms. Sneha Patil, Ms.
                                                         Aditi Sinha, Mr. Hrishikesh Joshi &
    
    
                                                       Page 1 of 50
    
    
                        ::: Uploaded on - 09/04/2026                    ::: Downloaded on - 09/04/2026 21:36:07 :::
                                               Indian-Newspaper-oswp-864-2018-J-R.doc
    
    
    
    
                                       Ms. Isha Vyas, i/b Maniar Srivastava
                                       Associates.
    
    
    
                           CORAM   :    SHREE CHANDRASHEKHAR, CJ &
                                        SUMAN SHYAM, J.
               RESERVED ON         :    22nd JANUARY 2026.
            PRONOUNCED ON          :    8th APRIL 2026.
    
     JUDGMENT (Per Suman Shyam, J):

    1. Rule. Rule is made returnable forthwith.

    SPONSORED

    2. By consent of the parties, the matter is taken up for final

    hearing.

    3. Assailing the demand notice dated 12th September 2017

    (Exhibit-N) the Writ Petitioner has approached this Court inter alia

    contending that the demand for penalty/additional premium on

    account of late completion of the construction, raised by the

    Respondent No. 1, i.e., Mumbai Metropolitan Region Development

    Authority (“MMRDA”), is contrary to the terms and conditions of

    the Lease Agreement and, therefore, arbitrary and illegal. The

    facts and circumstances, giving rise to the filing of the Writ

    Petition, shorn of unnecessary details, are as hereunder.

    Page 2 of 50

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:07 :::

    Indian-Newspaper-oswp-864-2018-J-R.doc

    4. The Writ Petitioner is a registered company having its office

    at INS Building, Rafi Marg, New Delhi 110 001. The Petitioner is a

    non-profit organization and plays a central role in protecting and

    promoting the interest of the Press in India. The Respondent No. 1

    (MMRDA), is an authority set up under a statute viz. the Mumbai

    Metropolitan Regional Development Authority Act, 1974

    (hereinafter referred to as “MMRDA Act”) and the Respondent No.

    2 is its Chief Executive Officer.

    5. Based on an application made by the Petitioner-Company,

    the Respondent No. 1 had allotted the Plot No. C-63 in ‘G’ Block at

    Bandra-Kurla Complex (BKC) vide authority of approval granted

    in its 120th meeting held on 24th December 2007.

    6. On 17th November 2005, the Respondent No. 1 had allotted

    the aforesaid plot admeasuring 10,450 sq. mtrs. to the Writ

    Petitioner, on a long term lease of 80 years, for construction of

    office complex, on payment of lease premium of

    Rs.88,52,75,000/- (Rupees Eighty Eight crores Fifty Two lakhs and

    Seventy Five thousand), calculated at the rate of Rs.42,500/- per

    sq. mtr.

    Page 3 of 50

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:07 :::

    Indian-Newspaper-oswp-864-2018-J-R.doc

    7. On 1st December 2005, the Respondent No. 1 permitted the

    Petitioner to transfer 40% of the built up area to third party

    subject to the condition that the same shall be used only for office

    purpose. Consequently, on 14th February 2008, the Petitioner had

    entered into a Development Agreement with M/s. Orbit Enterprise

    (“Developer”) for development of the said plot.

    8. On 18th February 2008, the Petitioner paid the entire lease

    premium of Rs.88,52,75,000/- (Rupees Eighty Eight Crores Fifty

    Two Lakhs and Seventy Five Thousand) to the Respondent No. 1,

    pursuant whereto, Lease Deed dated 9th April 2008, leasing out

    the area of 10415 sq. mtrs of land, for a period of 80 years, was

    executed by and between the Petitioner and the Respondent No. 1.

    As per the Lease Agreement, the permissible built-up area was

    20,830 sq. mtrs.

    9. Article 2(c) of the Lease Deed dated 9th April 2008 stipulates

    that no work shall commence till the plan is approved by the

    authority; Article 2(d) lays down that the construction will be

    completed within a period of four years from the date of execution

    of the Lease Deed; Article 2(e) stipulates that failure to comply

    with Article 2(d) would require extension of time that may be

    Page 4 of 50

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:07 :::
    Indian-Newspaper-oswp-864-2018-J-R.doc

    permitted by the Metropolitan Commissioner on payment of

    additional premium, which would be 25% of the premium up to

    one year; 35% of the premium between one and two years; and

    40% of the premium between two and three years.

    10. Pursuant to the execution of the Lease Deed dated 9 th April

    2008, possession of the plot of land was handed over to the Writ

    Petitioner on 10th April 2008. It would be pertinent to note herein

    that when the Lease Deed dated 9th April 2008 was executed, 2.00

    Floor Space Index (FSI) was available at Bandra-Kurla Complex

    and, therefore, the permissible built-up area on the said plot of

    land was 20,830 sq. mtrs only. Accordingly, proposal for

    construction of commercial office building with two wings, viz., ‘A’

    and ‘B’ wings with two level basement, constituting Ground+3

    floors at ‘A’ wing (8,006 sq. mtrs.) and Ground+11 floors in ‘B’

    wing (13,650 sq.mtrs) was drawn up by the Petitioner.

    11. On 20th April 2008, the construction plan, along with

    application for shore-piling and excavation, was submitted by the

    Petitioner before the Respondent No. 1. On 30 th May 2008, the

    Respondent No. 1 granted permission for excavation and shore-

    piling.

    Page 5 of 50

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:07 :::

    Indian-Newspaper-oswp-864-2018-J-R.doc

    12. On 3rd November 2008, the drawings of the construction

    was submitted by the Petitioner before the Respondent No. 1 for

    approval. On 8th December 2008, the Respondent No. 1 had issued

    deficiency letter asking the Petitioner to obtain ‘NOC’ for the

    Environment Impact Assessment (EIA), which was obtained and

    submitted by the Petitioner on 8th October 2009. Thereafter, the

    plan upto the plinth level was approved.

    13. The FSI in the Bandra-Kurla Complex area was

    subsequently, enhanced to 4.00. As such, the Respondent No. 1

    had offered additional built-up area upto 4.00 FSI to the existing

    Lessees. In view of the enhancement in the FSI, the Petitioner, vide

    letter dated 22nd September 2009, requested the Respondent No. 1

    to allot additional built-up area of 20,830 sq. mtrs. on the same

    plot. Acting on such request made by the Petitioner, on 10 th

    September 2009, the Respondent No. 1 had allotted additional

    built-up area of 20,830 sq. mtrs to the Petitioner against payment

    of Rs.204,02,98,500/- (Rupees Two Hundred Four Crores Two

    Lakhs Ninety Eight Thousand Five Hundred only), which was

    payable in five installments. Liberty was also granted to the

    Petitioner to transfer the entire additional built-up area, subject to

    Page 6 of 50

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:07 :::
    Indian-Newspaper-oswp-864-2018-J-R.doc

    the provision of the Lease Deed. In view of the allotment of the

    additional built-up area, the total built-up area allotted to the

    Petitioner stood increased to 41,660 sq. mtrs.

    14. On 22nd April 2013, a Supplementary Lease Deed was

    executed by and between the Petitioner and the Respondent No. 1.

    Article 2(c) of the Supplementary Lease Deed clearly stipulated

    that there shall be no time-limit, as stipulated in Article 2(d) of

    the Lease Deed dated 9th April 2008, for completion of the

    construction of the building by using the additional built-up area.

    It was further provided that the incremental premises would be

    deemed to be the integral part of the demised premise as defined

    in the Lease Deed dated 9th April 2008.

    15. In the wake of the allotment of additional built-up area

    (BUA), as aforesaid, the Petitioner was required to submit revised

    building plan so as to consume the new built-up area within the

    same plot and the same building. According to the revised plan,

    both the wings, namely, ‘A’ and ‘B’ wings would now have G+14

    floors. Accordingly, on 29th March 2010, the Petitioner had

    submitted amended plan which was approved by Respondent No.

    1 on 26th August 2011. Thereafter, on 2nd January 2012, the

    Page 7 of 50

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:07 :::
    Indian-Newspaper-oswp-864-2018-J-R.doc

    Respondent No. 1 had issued Commencement Certificate (“CC”)

    for the 4th to 6th floor in Wing ‘A’ for the built-up area of 5,730.64

    sq. mtrs.

    16. As per the projection made in the Writ Petition, the

    Petitioner had completed construction of the two basements as

    well as Ground+9 floors in wing ‘B’ and Ground+6 floors in ‘A’

    Wing in the month of April, 2012, thus, substantially consuming

    the original built-up area of 20,830 sq. mtrs.

    17. In view of the allotment of the additional built-up area, the

    height of the building had to also be raised. Therefore, the

    Petitioner had applied for height clearance which was granted by

    the Airports Authority of India by NoC dated 2nd August 2012.

    18. On 18th January 2013, the Respondent No. 1 had issued

    Commencement Certificate (“CC”) for ‘A’ Wing (7 th to 12th floors)

    and ‘B’ Wing (10th to 12th floors) and, thereafter, on 14th November

    2013, the Respondent No. 1 had issued Commencement

    Certificate for the plinth level basements as well as G+14 floors of

    ‘A’ and ‘B’ wings. Thus, the CC for completing the construction of

    the entire building, including the basement as well as G+14 floors

    Page 8 of 50

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:07 :::
    Indian-Newspaper-oswp-864-2018-J-R.doc

    in both the wings, was eventually granted by the Respondent No.

    1 only on 14th November 2013.

    19. Although there was no written demand for any additional

    premium/penalty for extension of time, yet, in view of Article 2(c)

    of the Lease Deed dated 9 th April 2008 stipulating outer limit of

    four years for completion of the construction, which period had

    already expired, on 6th June, 2012, the Petitioner wrote a letter

    to the Chief Town Planner of Respondent No. 1 seeking extension

    of time for two years as the height clearance was yet to be

    received from the Civil Aviation Authorities, New Delhi. The letter

    dated 6th June 2012 was followed by another letter dated 10 th

    December 2012 renewing the request for extension of time by two

    years by citing the reasons for the delay. Thereafter, on 10 th

    January 2013, the Petitioner had addressed another letter to the

    Deputy Metropolitan Commissioner, Land & Estate Department of

    the Respondent No. 1 stating that the completion of the building

    would take almost six years due to various reasons and problems.

    20. In view of the above request for extension of time made by

    the Petitioner, the Respondent No.1 i.e. the MMRDA had proposed

    Page 9 of 50

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:07 :::
    Indian-Newspaper-oswp-864-2018-J-R.doc

    to levy penalty upon the Petitioner due to the delay in completion

    of the construction beyond the time-limit of four years.

    21. Although, the Petitioner did not agree with the said decision

    and had clarified that the decision would be appealed against, yet,

    in the interest of the project, some more time as well as facility of

    payment of additional premium under protest, in four quarterly

    installments, was made by the Petitioner. By the letter dated 10 th

    January 2013, the Petitioner had also assured the Respondent

    No.1 that the first installment would be paid on or before 31 st

    March 2013 as the project did not have any provision for this

    additional burden.

    22. On 30th September 2013, the Deputy Metropolitan

    Commissioner of the Respondent No. 1 Authority had issued a

    letter to the President of the Petitioner-company, granting the

    request for extension of time for completing the construction of

    the building on Plot No. C-63 in ‘G’ Block of Bandra-Kurla

    Complex (BKC) under Lease Deed dated 9th April 2008 for a

    period of one year from 9th April 2012 to 8th April 2013, by

    charging additional premium at the rate of 10% of the lease

    premium payable in advance. In the said letter, it was also

    Page 10 of 50

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:07 :::
    Indian-Newspaper-oswp-864-2018-J-R.doc

    mentioned that the additional premium payable by the Petitioner,

    as on that date, works out to Rs.8,85,27,500/- along with interest

    payable for delayed payment, calculated at the rate of 14% per

    annum. It was also conveyed that as requested by the Petitioner ,

    the Respondent No. 1 was agreeable to the proposal for payment

    of the additional premium in four equal quarterly installments

    along with interest due thereon, at the rate of 14%, of which, the

    first installment would be due on 31 st March 2013. The Petitioner

    was, therefore, asked to pay the outstanding dues immediately

    along with interest applicable thereon.

    23. Thereafter, on 31st October 2013, the Deputy Town Planner

    TN & CP Division of Respondent No. 1, had addressed a letter to

    the representative of the Petitioner calling upon him to deposit the

    amount of Rs.10,05,449/- as scrutiny fee in respect of the

    development on Plot No. C-63 in ‘G’ Block at Bandra-Kurla

    Complex for “Indian Newspaper Society”.

    24. Thereafter, on 22nd August 2014, the Respondents issued a

    notice to the Petitioner to pay up the outstanding dues, failing

    which, the CC will be revoked and the ‘Lease’ would also be

    determined. In the said notice, although reference has been made

    Page 11 of 50

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:07 :::
    Indian-Newspaper-oswp-864-2018-J-R.doc

    to breach of the terms and conditions of the Lease Deed dated 9 th

    April, 2008 as well as the Supplementary Deed of Lease deed

    dated 22nd April 2013, in so far as completion of the construction

    as “fit for occupation” was concerned, yet, there is no mention of

    any specific amount falling due and payable by the Petitioner on

    account of the alleged breach of the terms of the Lease

    Agreements nor was any particulars furnished as regards the

    nature and extent of the breach, so alleged.

    25. On 19th September 2014, the Petitioner submitted its reply

    to the notice dated 22nd August 2014 as well as the letter dated

    31st October 2013, forwarding a Pay Order for an amount of

    Rs.73,78,07,466/- as payment of installment for the additional

    built-up area. That apart, a separate pay order for an amount of

    Rs.13,78,59,150/- was also forwarded towards payment of

    penalty/additional premium for granting extension of time for

    completion of the construction.

    26. The above communication was followed by the letter 22 nd

    September 2014 issued by the Petitioner to the Respondent No. 1

    inter- alia stating that the payment of premium for the additional

    built-up area due to delay in completing the construction has been

    Page 12 of 50

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:07 :::
    Indian-Newspaper-oswp-864-2018-J-R.doc

    made under protest. It has further been mentioned therein that at

    the time of executing the Supplementary Lease Deed allotting the

    additional built-up area, it was assured that due to the increase in

    additional built-up area the period of completion of construction

    would be increased by the MMRDA from four years to six years.

    Therefore, the additional premium/penalty was paid without

    prejudice to the right of the Petitioner to claim refund of the entire

    amount, in case, the period of construction is increased from four

    years to six years. Accordingly, a request was made to re-validate

    the NoC etc.

    27. On 23rd December 2014, the Respondent No. 1 extended the

    date of completion of construction of the building to 8 th April 2015

    and demanded additional penalty of Rs. 8.85 Crores for the year

    2014-2015. On such basis, the Respondent No. 1 claimed that an

    amount of Rs.15,44,36,039/- along with interest for delayed

    payment, as on 31st October 2014, was due and payable.

    28. Eventually, on 12th September 2017, the Respondent No. 1

    had issued the impugned Demand Notice calling upon the

    Petitioner to pay the outstanding dues, failing which, action under

    Articles 5 and 6 of the Deed of Lease would be initiated for breach

    Page 13 of 50

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:07 :::
    Indian-Newspaper-oswp-864-2018-J-R.doc

    of the Agreement. The said Demand Notice is under challenge in

    the present proceeding.

    29. In the Reply filed on behalf of the Respondents, the

    maintainability of the Writ Petition has been assailed inter-alia on

    the ground that the same raises several disputed questions of facts

    which cannot be adjudicated in a Writ Petition. By referring to

    Section 44 of the MMRDA Act, 1974 read with Rule 5 of the

    MMRDA Rules,1976, it has been alleged that alternative remedy,

    in the form of an Appeal under Section 44 was available to the

    Petitioner. Therefore, the Writ Petition ought to be dismissed on

    such ground alone.

    30. The Respondents have also alleged that the Writ Petitioner

    has approached this Court by suppressing material facts and

    particulars; that in the Writ Petition, challenge has been made to

    the policy decision of the State without challenging the relevant

    provisions of the statute which permits such action; that the Writ

    Petition is hit by delay and laches and the same is also barred by

    the law of limitation.

    Page 14 of 50

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:07 :::

    Indian-Newspaper-oswp-864-2018-J-R.doc

    31. The Respondents have further alleged that by failing to

    produce the full ‘CC’ dated 14th November 2013, the Petitioner has

    suppressed material facts. Since the Petitioner has approached this

    Court with unclean hands and, hence, the Writ Petition is liable to

    be dismissed on such count alone.

    32. While denying and disputing the assertions made by the

    Petitioner that the construction of the built-up area as per the

    initial allotment of 20,830 sq. mtrs. was completed in the month

    of April 2012, i.e., within the stipulated period of four years, it

    was contended that such disputed questions of facts cannot be

    gone into in a Writ Petition.

    33. This Writ Petition was analogously heard along with three

    other Writ Petitions being Writ Petition No. 2377 of 2018, Writ

    Petition No. 242 of 2018 and Writ Petition No. 3209 of 2017,

    involving similar issues whereby, identical reliefs were sought by

    the Writ Petitioner(s).

    34. Mr. Ankit Lohia Learned Counsel for the Petitioner has

    adopted the arguments advanced by Mr Nakani Learned Senior

    Counsel for the Writ Petitioners in the connected Writ Petitions.

    Page 15 of 50

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:07 :::

    Indian-Newspaper-oswp-864-2018-J-R.doc

    Like wise Dr. Saraf, learned Senior Counsel for the Respondents

    has also advanced common arguments in this Writ Petition as well

    in Writ Petition No 242 of 2018, supporting the statements made

    in the Reply Affidavit.

    35. We have considered the pleadings brought on record and

    have also gone through the documents annexed therein.

    36. At the very outset, it deserves to be mentioned herein that

    although the maintainability of the Writ Petition has been assailed

    on the ground that several disputed questions of facts are involved

    there-in, yet, after examining the record, we find that save and

    except the claim of the Petitioner as regards the date of

    completion of the first phase of initial built-up area of 20,830 sq.

    mtrs., all other assertions made in the Writ Petition are based on

    documents annexed thereto, which are admitted documents.

    Having regard to the core controversy involved in this proceeding

    and considering the fact that the issues involved in this Writ

    Petition would call for determination based on interpretation of

    the relevant clauses of the Lease Agreement(s) as well as the

    documents exchanged by and between the parties, we are of the

    considered opinion that the date of completion of the first phase

    Page 16 of 50

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:07 :::
    Indian-Newspaper-oswp-864-2018-J-R.doc

    of the initial built up area would not have much of a material

    bearing in the out come of the Writ Petition.

    37. In the case of Joshi Technologies International IBC vs. U.O.I.

    & Ors.,1 the Hon’ble Supreme Court has observed that there is no

    absolute bar to the maintainability of a Writ Petition, even in

    contractual matters or where there are disputed questions of fact

    or even when monetory claim is raised, provided, the Court is

    called upon to examine the issue which has a public law character

    attached to it. Having regard to the core controversy involved in

    this proceeding and considering the fact that the issues involved in

    this Writ Petition would call for determination by this Court based

    on interpretation of the relevant Articles of the Lease Agreement

    as well as the documents exchanged by and between the parties so

    as to ascertain fairness in the action of the Respondent No 1, we

    are unable to agree with the stand of the Respondents that the

    Writ Petition ought to be dismissed on the ground that it raises

    disputed questions of facts.

    38. Likewise, in Banda Development Authority, Banda vs.

    Motilal Agarwal & Ors.2 the Hon’ble Supreme Court has observed

    1 (2015) 7 SCC 728.

    2 (2011) 5 SCC 394.

    Page 17 of 50

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:07 :::

    Indian-Newspaper-oswp-864-2018-J-R.doc

    that no limitation has been prescribed for filing a Writ Petition

    under Article 226 of the Constitution of India. However, the High

    Court will treat the delay in filing the Writ Petition as

    unreasonable, if the same is filed beyond the period of limitation

    prescribed for filing a Civil Suit for a similar cause. From the

    above, it would be apparent that although un-explained delay in

    instituting a Writ Petition could be a valid ground to decline relief

    to the Petitioner, yet, the law of Limitation would not have strict

    application in a Writ Petition.

    39. There is no dispute in this case about the fact that the

    Respondent No. 1 is an instrumentality of the State and, therefore,

    would be an “other authority” within the meaning of Article 12 of

    the Constitution of India.

    40. Law is well settled that arbitrariness in the decision making

    process of the State or its instrumentality is a facet of Article 14 of

    the Constitution of India. In E.P..Royappa v State of Tamil Nadu,3 it

    was pointed out that Article 14 would strike at arbitrariness in

    State action and ensure fairness and equality of treatment.

    3 (1974) 4 SCC 3.

    Page 18 of 50

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::

    Indian-Newspaper-oswp-864-2018-J-R.doc

    41. The present is not a proceeding simpliciter for enforcing a

    money claim but raises significant questions pertaining to the

    validity and fairness in the impugned action of the Respondent No

    1, which are required to be adjudicated on the touch stone of

    Article 14. As such, we are of the considered opinion that such

    plea cannot be brushed aside merely on the ground of delay and

    laches, more so, since such delay has evidently not given rise to

    any parallel right of a third party.

    42. In so far as the plea of availability of alternative remedy is

    concerned, from a reading of Section 44 of the MMRDA, Act 1974,

    we find that the provision for Appeal provided thereunder, is

    pertaining to disputes regarding recovery of money due to the

    authority as arrears of land revenue. Since the challenge made to

    the impugned demand notice is on the ground that the same is

    contrary to the terms of the Supplementary Lease Deed and hence,

    illegal and arbitrary, we are of the opinion that the said

    controversy cannot be effectively adjudicated in an Appeal filed

    under Section 44. Therefore, we reject the contention of the

    Respondents that the Petitioner has an effective and efficacious

    alternative remedy.

    Page 19 of 50

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::

    Indian-Newspaper-oswp-864-2018-J-R.doc

    43. We also find that all material facts have been stated in the

    Writ Petition. Therefore, the Writ Petition cannot also be dismissed

    on account of suppression of facts.

    44. In view of the above discussions, we hold that the Writ

    Petition is maintainable in law as well as in the facts and

    circumstances of the case.

    45. Having held as above, it would be pertinent to mention

    herein that our attention has been invited to an earlier decision

    rendered by a co-ordinate Bench of this Court (Coram: Ranjeet

    More & Bharati Dangre, JJ) dated 20 th November 2019 passed in

    Raghuleela Builders Pvt. Limited and Anr. vs. The Mumbai

    Metropolitan Regional Development Authority & Ors. 4 wherein

    issues of similar nature were involved. In that case also the Writ

    Petitioners had challenged a similar Demand Notice dated 12 th

    September 2017 issued by the Respondent No.1 by invoking

    identical Articles in the Lease Deed as well as the Supplementary

    Lease Deed, thus demanding payment of a sum of Rs. 432 Crores

    as penalty for the delay in completion of construction of the

    building. In that case also, the initial built up area was 30550 sq.

    4 (2020) (1) ABR 397: 2019 SCC OnLine Bom 4529.

    Page 20 of 50

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::

    Indian-Newspaper-oswp-864-2018-J-R.doc

    meters, which was to be consumed by constructing 9 floors in the

    building, yet, subsequently, due to the increase in the FSI, the

    Respondent No.1 had allotted additional built up area of 67000

    sq. meters to the Petitioner resulting into construction of 11

    additional floors in the same building. Due to addition in the built

    up area, the construction of the building could not be completed

    within four years, as a result of which, Demand Notice dated 12 th

    September, 2017 was served on the Lessees for recovery of

    penalty/additional premium along with interest calculated

    thereon.

    46. By the Judgment and Order dated 20th November 2019,

    rendered in Raghuleela Builders Pvt. Ltd. & Anr . (Supra), a

    Division Bench of this Court had set aside the impugned Demand

    Notice dated 12th September 2017 by holding that such a demand

    was not maintainable in the eyes of law. That apart, it was also

    observed that in view of the change in policy of the MMRDA

    increasing the time for completion of the building “Fit for

    occupation”, from four years to six years, the demand for

    penalty/additional premium for delay in completion of

    Page 21 of 50

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::
    Indian-Newspaper-oswp-864-2018-J-R.doc

    construction within four years was ex-facie unreasonable,

    unjustified and discriminatory.

    47. The Special Leave Petition (C) No. 6411 of 2020 preferred

    by the Respondent No.1 assailing the Judgment and Order dated

    20th November 2019 was dismissed by the Hon’ble Supreme Court

    by the order dated 27th July 2020 by taking note of the findings

    recorded in paragraphs No. 39 and 41 of the Judgment and Order

    dated 20th November 2019. However, it was clarified that since the

    judgment of the Division Bench of Bombay High Court in

    Raghuleela Builders Pvt. Ltd. & Anr. (Supra) was rendered in the

    facts of that case, hence, it cannot influence any other matter in

    this behalf. With the above observation the Special Leave Petition

    was dismissed by the following order:-

    “We are not inclined to exercise our jurisdiction under Article
    136
    of the Constitution of India in the given facts of the case and
    more so as reflected from paragraphs 38 and 40 of the
    impugned judgment.

    Mr. K. K. Venugopal, learned Attorney General for India
    expresses some apprehension on account of there being other
    matters pending.

    We clarify that the present matter is in the given facts of
    the case as stated aforesaid and thus, cannot be said to influence
    any other matter in this behalf.

    The special leave petition is dismissed in terms aforesaid.
    Pending applications shall also stand disposed of.”

    Page 22 of 50

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::

    Indian-Newspaper-oswp-864-2018-J-R.doc

    48. It appears that the Respondent No. 1 had filed a Review

    Petition seeking review of the order dated 27 th July 2020, which

    was also dismissed by the Hon’ble Supreme Court vide order

    dated 29th September 2020 passed in Review Petition (Civil) No.

    1764 of 2020 arising out of SLP (C) No. 6411 of 2020.

    49. From the plain reading of order dated 27th July 2020, what

    transpires is that the Hon’ble Supreme Court had observed that

    the decision in Raghuleela Builders Pvt. Ltd. & Anr . (Supra) was

    passed in the facts of that case. However, in our considered

    opinion, we can take note of the legal principles, if any, emanating

    from the said decision. In that view of the matter we are unable to

    agree with the submission of learned Counsel for the Respondent

    that the decision in the case of Raghuleela Builders Pvt. Ltd. &

    Anr. (Supra) cannot be looked into by this Court even for the

    purpose of deciding the question of maintainability of the Writ

    Petition.

    50. The question of maintainability of a Writ Petition is mixed

    question of law and facts. Therefore, such question has to be

    answered by taking note of the facts and circumstances of each

    case. Having regard to the peculiar facts and circumstances of this

    Page 23 of 50

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::
    Indian-Newspaper-oswp-864-2018-J-R.doc

    case and also considering the fact that a similar Writ Petition,

    raising similar issues, in Raghuleela Builders Pvt. Ltd. & Anr .

    (Supra) had earlier been entertained by this court, we are not

    inclined to non-suit the Petitioner merely on the plea of

    maintainability raised by the Respondents.

    On Merit :-

    51. By referring to the materials available on record the

    learned Counsel for the Petitioner has argued that after the

    allotment of the additional built-up area of 20,830 sq. meters,

    which was required to be used on the same plot and the same

    building, it was impossible to segregate the construction and

    complete the construction of initial built-up area of 20,830 sq.

    meters “fit for occupation”, inasmuch as, various services, such as,

    cooling tower, air cool chillers, exhaust fans for toilet exhaust, DG

    exhaust, pipes, fresh air fans for AHU, pressurization fans for

    staircase, etc. were common facilities for the entire building and

    therefore, were required to be located on top of 14 th floor of the

    building, which would not be possible until the entire construction

    is completed. As a result of the same, the Building cannot be

    completed “fit for occupation” without such facilities. Likewise,

    Page 24 of 50

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::
    Indian-Newspaper-oswp-864-2018-J-R.doc

    submits the learned counsel, it would not be possible to obtain fire

    NOC, storm-water drainage completion certificate, service lift /

    fire lift approval, etc. from the Statutory Authorities until the

    construction of the entire building was completed. It is also the

    submission of learned Counsel for the Petitioner that the demand

    for penalty for delay in construction was unsustainable in law, as

    the ‘No Time Limit’ clause would be applicable to the entire

    building after the additional built-up area was allotted.

    52. By referring to the subsequent decision of the MMRDA to

    grant six years time for completion of construction of the buildings

    but keeping it confined only to those leases which were granted

    after 25th August 2015, the learned counsel has argued that such

    differentia is wholly arbitrary, illegal, discriminatory and devoid of

    any rational basis. The learned counsel for the Petitioner further

    submits that the Respondent No.1 has not disclosed any

    reasonable basis for making a distinction between pre-August

    2015 and post-August 2015 lease agreement for granting

    additional period of time for completion of construction without

    levying any penalty, notwithstanding the fact that the lessees of

    both the categories were similarly situated and were facing similar

    Page 25 of 50

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::
    Indian-Newspaper-oswp-864-2018-J-R.doc

    nature of challenges in completing the construction, which facts

    were well within the knowledge and understanding of the

    Respondent No.1. Therefore, he submits that the impugned

    Demand Notice is illegal and hence, liable to be set aside by this

    court.

    53. Dr. Birendra Saraf, learned Senior Counsel appearing for the

    Respondents, on the other hand, has submitted that the

    Petitioners, having executed a Lease Deed which contains a

    specific stipulation in the form of Article 2(c) permitting levy of

    penalty due to delay in completion of construction beyond four

    years, cannot now turn back and question such decision of the

    authority. It is also his submission that the Petitioner cannot be

    permitted to question the policy decision of the Respondent No.1,

    which has the backing of a statute. On such count, the learned

    senior counsel has submitted that the Writ Petition deserves to be

    dismissed with cost.

    54. At the very out set it must be noted here-in that as per

    Article 2(d) the lessee is required to complete the construction

    within four years from the date of execution of the lease deed.

    However, Article 2 (c) of the Lease Deed makes it clear that no

    Page 26 of 50

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::
    Indian-Newspaper-oswp-864-2018-J-R.doc

    work shall commence or be carried out contrary to the

    Development Control Regulations and the Building Regulations

    applicable to the plot of land and until the plans, elevations,

    sections, specifications and details shall have been approved.

    Therefore, in view of Article 2(c), the construction cannot

    commence until all statutory approvals including the approval of

    building plan etc is received by the Lessee. Article 2(a) of the

    Lease Deed mentions that the lessee shall within three months

    submit plans etc. for approval. However, there is no condition in

    the Lease Deed laying down any time line for granting of such

    approval by the authority.

    55. In a construction of this nature, permission of multiple

    statutory authorities including the Municipal Corporation, Fire

    department, Environment clearance, height clearance etc. will be

    necessary, without which also the Commencement Certificate

    cannot be issued. Unless the Commencement Certificate is issued

    by the Authority, the construction work cannot commence. These

    statutory authorities are not bound by the terms and conditions of

    the Lease Agreement. Notwithstanding the same, the Lease

    Agreement is completely silent as to who will be responsible in

    Page 27 of 50

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::
    Indian-Newspaper-oswp-864-2018-J-R.doc

    case of delay in granting approval by these statutory authorities

    coming in the way of early commencement and completion of the

    construction.

    56. Not only that, the Lease Deed is also silent as to what would

    be the effect on the time line of four years for completion of the

    construction as laid down in Article 2(d) in case, there is delay in

    granting of statutory approvals. Therefore, if there is delay in

    granting permissions/ approval by the statutory authorities for any

    reason whatsoever, leading to delay in commencement of

    construction, then even in that event, the Lessee will be left with

    no option but to complete the construction within the stipulated

    time for no fault on its part. Yet, as per Article 2(d), as interpreted

    by the Respondent No 1, the lessee would still be liable to pay

    penalty for the delay in completing the construction beyond the

    period of four years from the date of execution of the Lease Deed.

    Viewed from that perspective, Article 2(d) of the lease deed

    appears to be ex-facie unfair, unreasonable and hence,

    unconscionable. However, since the Articles of the Lease Deed are

    not under challenge, hence, the said aspect of the matter need not

    detain this Court.

    Page 28 of 50

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::

    Indian-Newspaper-oswp-864-2018-J-R.doc

    57. From a plain reading of the documents brought on record,

    more particularly, the Deed of Lease dated 9 th April 2008, it is

    apparent that in view of the applicability of 2.00 FSI, the

    Respondent No.1 had initially granted built-up area 20,830 sq.

    mtrs only to the Petitioner by realizing the agreed premium.

    However, subsequently, after the FSI was increased for the Bandra-

    Kurla Complex area to 4.00, additional built-up area of 20,830 sq.

    meters was allotted to the Petitioner. Consequently, a

    supplementary Lease Deed dated 22 nd April 2013, was executed.

    In Article 2(c) of the Supplementary Agreement, the time

    restriction for completion of the building within four years was,

    however, dispensed with and in its place, the time period for

    completing the construction was made unlimited. Since the entire

    controversy in this proceeding revolves around the pertinent

    clauses of the two Lease Deeds, hence , we deem it appropriate to

    reproduce the relevant clauses of the lease deeds as hereunder :-

    58. Article 2 of the Lease Deed Dated 9 th April 2008 reads as

    follows:-

    “2. The Lessee hereby agrees to observe and perform the
    following conditions that is to say:

    Page 29 of 50

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::

    Indian-Newspaper-oswp-864-2018-J-R.doc

    (c) No work to begin until plans are approved: No work
    shall be commenced or carried on which infringes any of the
    Development Control Regulations and Building Regulations set
    out in the THIRD SCHEDULE hereto as also Municipal or any
    other Regulations so far as the same are applicable to the said
    land or to the use to which the said land and/or building there
    upon is going to be put to, being the subject of these presents,
    or until the said plans, elevations, sections, specifications and
    details shall have been to approved as aforesaid and thereafter
    shall not make any alterations or additions there to unless
    such alternations and additions shall have been previously, in
    like manner, approved.

    (d) Time limits for commencement and completion of
    construction work: That the Lessee shall within three months
    from the receipt of approval of his plans and specifications of
    building or buildings intended to be erected on the land,
    commence and within a period of four years from the date of
    this lease at his own expense and in a substantial and
    workman-like manner and with the sound materials and in
    compliance with the said Development Control Regulations
    and Building Regulations and all Municipal Rules, bye-laws
    and Regulations applicable hereto and in strict accordance
    with the approved plans, elevations, sections, specifications
    and details, to the satisfactions of the Metropolitan
    Commissioner and confirming to the building lines marked on
    the plan hereto annexed, and the Development Control
    Regulations and Building Regulations, build and completely
    finish, fit for occupation a building to be used as building with
    all requisite drains and other proper convenience thereto.

    (e) Extension of time stipulated for construction of
    building or development of land:

    (i) If the Lessee shall not perform and observe the
    limitations of the time mentioned in clause 2(d) above for
    construction of the intended building or otherwise
    development of land leased to him for reasons beyond his
    control, the Metropolitan Commissioner may permit extension
    of such time on payment of additional premium at the
    following rates:

    Up to 1 year ______ 25 percent of the premium
    Between 1 and 2 years ______ 35 percent of the premium
    Between 2 and 3 years ______ 40 percent of the premium

    (ii) If the Metropolitan Commissioner shall refuse to permit
    such extension of time or shall find the Lessee of having
    committed breach of any condition or covenant during

    Page 30 of 50

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::
    Indian-Newspaper-oswp-864-2018-J-R.doc

    limitation of time mentioned in clause 2(d) hereinbefore, the
    Metropolitan Commissioner may forfeit and determine the
    Lease; provided that in the event of such determination of
    lease 25 percent of the premium paid by the Lessee to the
    Lessor shall stand forfeited and the remaining 75 percent of
    such premium shall be refunded to him; provided further that
    the power to so determine the Lease shall not be exercised
    unless and until the Metropolitan Commissioner shall have
    given to the Lessee or left on some part of the demised
    premises a notice in writing of his intention to do so and of
    specific breach of the covenant or condition in respect of
    which forfeiture is intended and default shall have been made
    by the Lessee in remedying such breach within three months
    from the service of a notice on him on the notice being left on
    the demised premises.”

    59. Thereafter, a Supplementary Lease Agreement was entered

    by and between the parties on 22 nd April 2013 covering the

    additional built up area. Articles 2(c), 2(d) and 2(e) of the

    Supplementary Lease Deed are reproduced as hereunder:-

    “2. It is hereby agreed and declared by and between the
    parties hereto that–

    (b) The Lessee shall use the said additional build up area
    on the plot allotted to them and shall be at liberty to assign
    the said constructed build up area subject to the terms &
    conditions and covenants as setout in the said Lease Deed.

    (c) All the conditions and covenants including the terms
    of the lease and except the condition in Article 2(d) as
    contained in the said Deed of Lease shall be deemed to be
    incorporated herein and shall regulate the lease hereby
    granted. It is further agreed and declared by the parties
    hereto that the incremental premises hereby permitted to be
    constructed and to be leased by the Lesor to the Lessee shall
    be deemed to be the integral part of demised premises as
    defined in the said Deed of Lease dated 9 th April 2008,
    annexed hereto as ANNEXURE-I. There shall be no time limit
    as contained in the Article 2(d) of the said Deed of Lease for
    completion of construction of the building by using the said
    additional built up area.

    Page 31 of 50

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::

    Indian-Newspaper-oswp-864-2018-J-R.doc

    (d) The Lessee shall not apply and Lessor shall not grant
    Occupation Certificate in respect of the premises
    constructed by using the said additional built up area as
    required under the Development Control Regulations and
    Building Regulations as also Municipal or any other
    regulations so far as the same are applicable to the said plot
    of land or to the use for which the said plot of land and/or
    building there upon is going to be put to, unless Lessee pays
    to the Lessor the balance lease premium of the said additional
    built up area with interest due thereon or any other amount
    due to the Lessor.”

    60. The use of expressions such as “the incremental premises”

    which shall be deemed to be “integral part of the demised

    premises as defined in Deed of Lease dated 9th April 2008,” used in

    Article 2(c) of the Supplementary Lease Deed makes it abundantly

    clear that it was a case of composite construction meant to be

    carried out over the same plot of land and in the same building.

    Article 2(c) of the Supplementary Lease Deed dated 22 nd April

    2013, also makes it amply clear that there shall be “no time limit”

    for completion of construction of the building by using the

    additional built-up area. It is, therefore, evident that after the

    signing of the Supplementary Lease Deed dated 22 nd April 2013, in

    view of Article 2(c), time was no longer the essence of the

    contract for development of the land.

    61. The unambiguous expressions used in Article 2(c) of the

    Supplementary Lease Deed had clearly displaced the time

    Page 32 of 50

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::
    Indian-Newspaper-oswp-864-2018-J-R.doc

    restriction imposed under Article 2(d) of the Lease Deed dated 9 th

    April, 2008 for completing the construction as long as the

    construction is carried out by using the additional BUA. Had it

    been the intention of the parties to still continue with time

    restriction clause, as envisaged in Article 2 (d) of Lease Deed

    even after allotment of the additional Built up Area and signing of

    the Supplementary Lease Deed, then in that event, the said aspect

    of the matter would have been clarified in the subsequent

    agreement. However, the same was not done. If that be so, the

    irresistible conclusion that would follow is that in view of Article

    2(c) of the Supplementary Lease Deed dated 22 nd April 2013,

    Article 2(d) of the original Lease Deed dated 9 th April 2008

    imposing the time restriction for completing the construction was

    no longer enforceable. We are, therefore, of the unhesitant

    opinion that, in view of Article 2(c) of the Supplementary Lease

    Deed, the Respondent No.1 did not have any right under the Lease

    Agreement to insist on the time restriction clause of four years for

    completing the construction by using the additional built up area.

    62. It would be further pertinent to note herein that even

    assuming that Article 2(d) of the Lease Deed dated 9 th April 2008,

    Page 33 of 50

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::
    Indian-Newspaper-oswp-864-2018-J-R.doc

    had any relevance after the allotment of the additional built-up

    area, even then, it is apparent after the expiry of the four years

    time from the Date of execution of the Lease Deed, although the

    construction of the building was still incomplete, no default notice

    was served upon the Petitioner. As a matter of fact, until 22 nd

    August 2014, the Respondent No.1 had never raised any demand

    seeking penalty nor did it threaten to determine the lease for any

    reason whatsoever. The demand for payment of additional

    payment/ penalty was also raised, under the circumstances noted

    above, without calling for any explanation from the Petitioner as

    to why such demand should not be raised, thus acting in clear

    violation of the principles of the natural justice and administrative

    fair play.

    63. Although, there is no written communication from the

    Respondent No. 1 available on record intimating the Petitioner

    regarding expiry of the time limit for completing the construction,

    yet, it appears that the Petitioner had, on its own volition, issued

    communications dated 6th June 2012 (Exh.F) seeking extension of

    time, which was followed up by the subsequent communications

    dated 10th December 2012 (Exh.G) and 10th January 2013

    Page 34 of 50

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::
    Indian-Newspaper-oswp-864-2018-J-R.doc

    (Exh.H), whereby, it had deposited the amount of penalty for

    delay but under protest. In all probability, such demand was made

    by the Petitioner on the projection made by the Respondent No.1

    threatening to determine the lease, thus, jeopardizing the entire

    construction. However, since the payment was made under protest

    and by reserving the right of the Petitioner to seek refund and

    considering the fact that such demand was in conflict with Article

    2(c) of the Supplementary Lease Deed dated 22 nd April 2013,

    hence, we are of the view that the mere fact that the amount had

    been deposited by the Petitioner would not be prejudicial to its

    interest in any manner.

    64. We also note herein that in the Demand Notice dated 22 nd

    August 2014, although a threat was held out to determine the

    lease until the outstanding dues were cleared by the Petitioner, the

    Respondent No.1 did not specify any amount nor referred to the

    specific articles of the Lease Deed which had allegedly been

    violated by the Petitioner. Even in the subsequent Notice dated

    12th September 2017, there is no mention as to in what manner,

    the Petitioner had acted in violation of any specific Article of the

    Lease Deed or for that matter, the exact amount which was found

    Page 35 of 50

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::
    Indian-Newspaper-oswp-864-2018-J-R.doc

    to be due and recoverable from the Petitioner. Considering the

    nature of controversy involved in this Writ Petition, we deem it

    appropriate to reproduce the Demand Notice dated 12 th

    September 2017, as hereinunder:-

    EXHIBIT = ‘N’
    MUMBAI METROPOLITAN REGION DEVELOPMENT AUTHORITY
    eqacbZ egkuxj izns’k fodkl izkf/kdj.k
    _________________________________________________________
    No.LEC/BKC (G)/INS(C-63)/1792/2017 Date: 12th September 2017
    NOTICE
    WHEREAS the Mumbai Metropolitan Region Development
    Authority issued a Show Cause Notice dated 22/08/2014 for
    non-payment of requisite dues and non-performance of the Lease
    Deed conditions as stated therein.

    WHEREAS you have submitted your say along with
    explanation vide your letter dated 19/09/2014 & 22/09/2014.

    WHEREAS your representation/explanation is examined
    thoroughly and no merit was found in the submission/
    explanation given by you.

    AND WHEREAS the explanation submitted vide your
    letter 19/09/2014 & 22/09/2014 dated with reference to the
    Show Cause Notice is unsatisfactory and hence was summarily
    rejected vide our letter dated 23/12/2014.

    WHEREAS you were instructed to pay the outstanding
    dues as stated in the Notice under reference within a period of 30
    days. However, till date you did not pay the requisite dues to
    MMRDA and thus failed to comply with your obligations.

    AND WHEREAS the amount due to the Authority along
    with the interest due thereon is as shown in the statement
    annexed hereto as Annexure- A & B. An amount due to Authority
    is un-paid till date & thus you have therefore committed breach
    of the terms and conditions of the said Deed of Lease and
    therefore, the Authority has power to recover the said due
    amount as stated hereinbefore as arrears of land revenue and
    also resume the said land as per the Article 5 and 6 of the said
    Deed of Lease.

    NOW THEREFORE, in exercise of the powers conferred by
    Articles 5 and 6 of the said Deed of Lease, I, the Dy. Metropolitan
    Commissioner for and on behalf of the Metropolitan

    Page 36 of 50

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::
    Indian-Newspaper-oswp-864-2018-J-R.doc

    Commissioner of the Authority hereby call upon you to remedy or
    cause to be remedied within 30 days from the date of this notice.
    Please take further notice that in the event of the default to
    comply with this requisition, the Authority will have the right to
    determine the Lease and enter upon the premises and proceed
    further to recover the due amount stated hereinbefore as arrears
    of land revenue.”

    Sd/-

    (A.R. Wankhade)
    Dy. Metropolitan Commissioner,
    M.M.R.D.A.
    To,
    The President,
    Indian Newspaper Society,
    INS Building,
    Rafi Marg, New Delhi -110 001.

    65. From a plain reading of the impugned Demand Notice, it is

    clear that the same is devoid of any specific particulars as to the

    head on which the amount was sought to be recovered. Rather, it

    appears to be a completely vague and unsubstantiated notice

    which did not refer to violation of any specific article of the Lease

    Deed. Moreover, although the demand was admittedly a penal

    action, no prior Show Cause was served upon the Petitioner

    calling for any explanation. As such, impugned demand notice, in

    the opinion of this Court, is liable to be declared illegal on the

    ground of violation of the principles of natural justice alone.

    66. There is no controversy in this case about the fact that the

    Lease Deed(s) are contract agreements within the meaning of

    Page 37 of 50

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::
    Indian-Newspaper-oswp-864-2018-J-R.doc

    Section 10 of the India Contract Act,1872. Law is well settled that

    while constructing the terms of a contract, the documents must be

    read as a whole so as to ascertain the true intent of the parties.

    67. In the case of Bank of India & Anr. Vs K. Mohandas, 5 the

    Hon’ble Supreme Court has held that it is well recognized

    principle of construction of contract that it must be read as a

    whole in order to ascertain the true meaning of its several clauses

    and the words of each clause should be interpreted so as to bring

    them into harmony with the other provisions if that interpretation

    does no violence to the meaning of which they are entirely

    susceptible to. The observations made in paragraph 28 would be

    relevant in the present case and, therefore, are being reproduced

    herein-below for ready reference:-

    “28. The true construction of a contract must depend upon the
    import of the words used and not upon what the parties choose
    to say afterwards. Nor does subsequent conduct of the parties in
    the performance of the contract affect the true effect of the clear
    and unambiguous words used in the contract. The intention of
    the parties must be ascertained from the language they have
    used, considered in the light of the surrounding circumstances
    and the object of the contract. The nature and purpose of the
    contract is an important guide in ascertaining the intention of the
    parties.”

    68. In the present case, if the intent of the parties was to

    continue with the original time restriction clause as per Article

    5 (2009) 5 SCC 313.

    Page 38 of 50

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::

    Indian-Newspaper-oswp-864-2018-J-R.doc

    2(d) of the Lease Deed dated 9th April 2008 notwithstanding the

    allotment of the additional built up area, then in that event, there

    was nothing preventing the Respondent No 1 to clarify the same in

    the Supplementary Leased Deed. The same was, however, not

    done. On the contrary, as has been noted above, a specific

    stipulation in the form of Article 2(c), completely dispensing with

    the time restriction, was inserted in the Supplementary Lease

    Deed, thus signifying a clear policy shift as regards the time

    restriction for completing the construction.

    68. Law is well settled that the onus to remove ambiguity in a

    contract would always be on the party drafting the contract.

    Therefore, if there is any ambiguity in the contract, the benefit of

    the same must be resolved in favour of the party which is not

    responsible for creating the ambiguity.

    69. The legal maxim “Contra Proferentum” means, ambiguity to

    be resolved against the party which had drafted the contract.

    While dealing with the maxim “Contra Proferentum”, the Hon’ble

    Supreme Court, in case of Industrial Promotion and Investments

    Page 39 of 50

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::
    Indian-Newspaper-oswp-864-2018-J-R.doc

    Corporation of Orissa Ltd., vs New India Assurance Co. Ltd. &

    Anr.,6 has made the following observations:-

    “We proceed to deal with the submission made by the counsel
    for the appellant regarding the rule of contra proferentem. The
    Common Law rule of construction “verba chartarum fortius
    accipiuntur contra proferentem” means that ambiguity in the
    wording of the policy is to be resolved against the party who
    prepared it. MacGillivray on Insurance Law deals with the rule
    of contra proferentem as follows:

    “The contra proferentem rule of construction
    arises only where there is a wording employed by those
    drafting the clause which leaves the court unable to
    decide by ordinary principles of interpretation which of
    two meanings is the right one. ‘One must not use the
    rule to create the ambiguity — one must find the
    ambiguity first.’ The words should receive their
    ordinary and natural meaning unless that is displaced
    by a real ambiguity either appearing on the face of the
    policy or, possibly, by extrinsic evidence of surrounding
    circumstances.”

    70. From a careful analysis of Articles 2(d) of the Lease Deed

    dated 9th April,2008 and Article 2(c) of the Supplementary Lease

    Deed dated 22nd April,2013, we are of the opinion that both the

    Articles cannot be simultaneously enforced in the respect of the

    same construction since the construction is composite in nature.

    We, therefore, find force in the submission of the learned counsel

    for the Petitioner that it would be impossible to implement Articles

    2(d) of the Lease Deed and 2(c) of the Supplementary Lease Deed

    referred to above, on the same construction and at the same time.

    6 (2016) 15 SCC 315

    Page 40 of 50

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::
    Indian-Newspaper-oswp-864-2018-J-R.doc

    71. We have taken note of the stand of the Respondents that

    Clause 2(d) of the Lease Deed dated 9 th April 2008 puts in place a

    policy decision of the authority and, therefore, the same is not

    amenable to challenge by one of the contracting parties by

    invoking the writ jurisdiction of the Writ Court under Article 226

    of the Constitution of India. However, we are of the view that such

    arguments of the Respondents cannot be countenance in view of

    the law laid down in the case of Industrial Promotion and

    Investments Corporation of Orissa Ltd., vs New India Assurance

    Co. Ltd. & Anr. (Supra), which categorically lays down that the

    principle of “Contra Proferentum” would apply even in a case

    where there is ambiguity in the wording of the policy.

    72. It would be apparent from the observations made above

    that the Petitioner did not deposit the amount of Penalty

    voluntarily but the same was done under pressure and on the face

    of the threat issued by the Respondent No. 1 to terminate the

    Lease and also cancel the CC. Therefore, it is apparent that the

    amount of penalty deposited by the Petitioner was obtained under

    duress and / or coercion.

    Page 41 of 50

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::

    Indian-Newspaper-oswp-864-2018-J-R.doc

    73. Section 72 of the Indian Contract Act provides that a person

    who receives payment made by the payee under coercion must

    repay or return the same.

    74. In Fatima Khatoon Chowdrain vs. Mahmoed Jan

    Chowdhury,7 the Privy Council has held that payment made not

    voluntarily but under species of compulsion would be liable to be

    returned.

    75. In Valpy vs Manley,8 the Court of England & Wales has held

    that money paid under the constraint of threats to interfere with

    the legal right is sufficient to make it recoverable.

    76. In Ram Kishen Singh vs. Dooli Chand9 before the Privy

    Council, it was held that if a person pays money to save his

    property which has been wrongly attached in execution, he is

    entitled to recover it.

    77. Relying upon the case of Ram Kishen Singh (Supra), the

    Privy Council in the case of Kanhaya Lal vs The National Bank of

    India Limited10 has held that if a payment is made under protest
    7 (1868) 12 Moo Ind App 65.

    8 (1845) 1 CP 594.

    9 (1881) 8 IA 93.

    10 1913 SCC Online PC 4.

    Page 42 of 50

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::

    Indian-Newspaper-oswp-864-2018-J-R.doc

    and involuntarily, under coercion, the party making such payment

    would be entitled to claim refund of the same.

    78. In view of the discussions in the foregoing paragraphs, we

    are of the considered opinion that the demand for additional

    premium/penalty raised by the Respondent No. 1 on account of

    delay in completing the construction was dehors the terms of the

    Lease Deed and hence, was not authorized under the law. The

    Respondents have acted in a highly arbitrary and high handed

    manner by realizing such amount from the Petitioner under duress

    and coercion.

    79. It is to be noted here that in a matter of this nature, where

    the Authority is seeking to recover penalty for default on grounds

    which are not admitted, the recovery cannot be based on mere

    ipse dixit, but upon proper resolution of the controversy in

    accordance with law, more so, when such claim arises out of a

    contract wherein the Authority itself is a party.

    80. Having held as above, we deem it appropriate to record

    here-in that although the learned Counsel for the Petitioner has

    argued that this case is squarely covered by the decision rendered

    Page 43 of 50

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::
    Indian-Newspaper-oswp-864-2018-J-R.doc

    in Raghuleela Builders Pvt. Ltd. & Anr . (Supra),yet, the said

    assertion has been strongly contested by the Respondent’s Counsel

    by submitting that in view of the observations made by the

    Hon’ble Supreme Court in the order dated 27 th July 2020, no

    reliance can be placed on the said judgment on any count for the

    purpose of deciding the present Writ Petition. On a careful

    examination of the decision in Raghuleela Builders Pvt. Ltd. &

    Anr. (Supra) we also find that the said decision was rendered in

    the facts of that case. However, it is important to note here-in that

    one of the question raised in the said proceedings was pertaining

    to the question as to whether, the decision of the MMRDA to apply

    the extension of time from 4 years to 6 years for completing the

    construction only to the post August 2015 was valid in the eyes of

    law, is also a question raised in the present proceeding. While

    answering the said question, it was held in Raghuleela Builders

    Pvt. Ltd. & Anr. (Supra), as follows:-

    “38. The MMRDA constituted a single member committee of
    retired Judge of the Supreme Court to decide whether the
    MMRDA should give concession in recovery of premium
    considering the time required for plot owner to obtain
    permissions from various authorities for construction of building
    thereon. It is contended that one member committee has
    concluded that the charging of premium for extension of time
    for completing construction in Bandra-Kurla Complex area,
    specifically in case where additional built up area has been
    allotted by the MMRDA, was illegal. In its 138th meeting held

    Page 44 of 50

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::
    Indian-Newspaper-oswp-864-2018-J-R.doc

    on 26th August 2015, the MMRDA had acknowledged the
    difficulties faced by the lessees and that the condition of
    completion of construction within 4 years of the execution of the
    lease was adversely affecting the tendering process. The
    MMRDA had appointed an expert one man committee of retired
    Supreme Court Judge in that regard. The single member
    committee has advised that the period of 6 to 7 years be granted
    for completion of construction.

    39. The lease deed entered into by the MMRDA with the
    lessees are as per form D, prescribed under the MMRDA
    (Disposal of Lands) Regulations 1977. Clause 2(a) of the lease
    deed provides that for building plans to be submitted to country
    and town planing division for approval within 3 months from
    the date of lease. Clause 2(c) of the lease deed provides that no
    work is to be carried out until all plans, elevations, specifications
    are approved by the concerned authorities. Clause 2(d) provides
    that within 3 months of the approval of plans, the lessee is to
    commence construction which is to be completed within four
    years of the lease. Clause 2(e) provided for extension of time.
    Clause 2(e) contemplates a situation when the time for
    completion of construction can be extended, parties to the
    contract contemplated that certain uncertainties or situations
    may arise which may require more time for completion of the
    construction. In view of this, time is not essence of the contract
    between the parties and rightly so since construction of any
    building in Bandra Kurla Complex, several permissions are
    required from the various authorities and not only from the
    MMRDA who is planning authority for the Bandra Kurla area,
    namely,
    (1) The environmental clearance under the
    Environmental Impact Notification from the Ministry of
    Environment and Forest.

    (2) Building height clearance from the Ministry of
    Civil Aviation because of the close proximity to Airport.

                    (3)        Clearance from the high rise committee.
                    (4)        Permission from the the MCGM.
                    (5)        Permission from the traffic police.
    

    Each of these authorities is required to be approached
    separately since there is no single window clearance / nodal
    agency which would co-ordinate with the aforesaid authorities
    for granting of all necessary permissions. In view of the delay in
    obtaining permissions which are beyond the control of lessee, no
    work could be carried out as per clause 2(d) of the lease deed.

    Page 45 of 50

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::

    Indian-Newspaper-oswp-864-2018-J-R.doc

    40. The MMRDA had issued a letter of allotment dated 20th
    March 2012 allotting additional 67,000 sq. meters at
    consideration of 984 crore. Part payment of Rs.196 crore was
    received on 20th March 2012. The supplementary lease deed
    was executed for additional built up area of 67,000 sq. meters.
    The letter of allotment dated 20th March 2012, the acceptance
    of part payment of consideration for additional built up area
    allotted, diluted the time period of four years and there was no
    question of application of condition of occupation certificate for
    built up area within 4 years when additional built up area was
    allotted for raising additional 11 floors on the same building.

    41. The resolution passed by MMRDA for extending the time
    period for completing construction from 4 years to 6 years only
    for leases executed after 26th August 2015 also appears to be
    arbitrary, discriminatory, without basis and justification. The
    same set of circumstances are prevailing for the construction
    being carried out under the leases executed prior to 26th August
    2015. Therefore, not extending this benefit of this extension of
    time from 4 years to 6 years to the prior leases in respect of
    other plots in the BKC, is completely arbitrary, discriminatory,
    capricious and violative of Article 14 of the Constitution of
    India. There is no reasonable basis or justification for this
    decision. The classification sought to be made between the
    leases prior and subsequent to 26th August 2015 is not founded
    on intelligible differentia and neither does this differentia has
    any logic, rational, nexus to the object sought to be achieved.
    The MMRDA has sought to treat equals as unequal. The lessees
    of plots are being discriminated on the basis of their date of
    execution of their leases. The lessees who are placed in similar
    circumstances prevailing for construction in Bandra Kurla area
    are entitled to equal treatment guaranteed under Article 14 of
    the Constitution of India.”.

    81. It is not in dispute that the Lease Deed involved in

    Raghuleela Builders Pvt. Ltd. & Anr. (Supra) was also in Form ‘D’

    of the Regulations of 1977 wherein the same Articles 2 (d) and (e)

    were involved. The Writ Petitioner there-in was also a similarly

    situated lessee, from whom, penalty for delay in completing the

    construction beyond the period of 4 years was raised by the

    Respondent No 1. The Petitioner in that case had also raised

    Page 46 of 50

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::
    Indian-Newspaper-oswp-864-2018-J-R.doc

    identical plea as regards the applicability of the time extension

    Clause. The Lease Deed in that case was also executed prior to 26 th

    August, 2015. If that be so there can be no doubt about the fact

    that the legal principles discussed and the findings & observations

    recorded in paragraphs 38 and 41 of Raghuleela Builders, in so

    far as uniform applicability of the 6 years time extension clause is

    concerned, would be applicable to the facts of the present case as

    well. Therefore, we hold that by applying the principles parity, the

    Respondent No. 1 would be duty-bound to extend the same

    benefit of extension of time for completion of construction to six

    years to the present Petitioner as well.

    82. In the facts and circumstances of this case, we are also of

    the opinion that there is no legal justification for the Respondent

    No. 1 to confine the benefit of the time extension clause only to

    those Lease Agreements which were executed after 26 th August

    2015 as such an approach would be highly arbitrary and

    discriminatory in nature. Therefore, having regard to the peculiar

    facts and circumstances of this case, we do not find any justifiable

    ground to take a different view on the aforesaid issue.

    Page 47 of 50

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::

    Indian-Newspaper-oswp-864-2018-J-R.doc

    83. Law is well settled that for maintaining judicial discipline

    and propriety, a decision rendered by a Coordinate Bench on the

    same issue must be respected and followed by a Coordinate

    Bench. In the case of Mary Pushpam vs. Televi Curusumary &

    Ors.11 the Hon’ble Supreme Court has observed that when a

    decision of a Coordinate Bench of the same High Court is brought

    to the notice of the Bench, it is to be respected and would be

    binding, subject to the right of the Bench of such co-equal forum

    to take a different view and refer the question to a larger Bench.

    In other words, any decision of a Coordinate Bench would be

    binding on a Bench of equal strength subject to the condition that

    if a different view is sought to be taken in the matter, then the

    issue would have to be referred to a larger Bench.

    84. The above legal principle has taken a firm footing in the

    Indian Jurisprudence by a long line of judicial pronouncements.

    We do not deem it necessary to burden this judgment by referring

    to all those decisions. However, suffice it to mention here-in that

    unless there are justifiable grounds to take a different view in the

    matter warranting reference to a larger Bench, the previous

    11 (2024) 1 SCR 11.

    Page 48 of 50

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::

    Indian-Newspaper-oswp-864-2018-J-R.doc

    decision of a coordinate Bench would be binding on a Bench of

    equal strength.

    85. For the reasons stated above we hold that the Demand

    Notices dated 22nd August 2014 as well as 12 th September 2017

    are illegal, dehors the terms and conditions of the Lease Deeds as

    well as the authority of law. Therefore, the same are hereby set

    aside.

    86. The Writ Petition stands allowed in terms of prayer clauses

    (A) and (B).

    87. From the statements made in the Writ Petition it appears

    that the Petitioner had deposited an amount of Rs 13,78,59,150/-

    as penalty by the letter dated 19/09/2014 and thereafter, a

    further amount of Rs. 8.85 crores on 23/12/2014, totaling to Rs

    22,63,59,150/-. In view of the determination made above, the

    Respondent No. 1 is directed to verify and refund the entire

    amount paid by the Petitioner on additional premium/penalty,

    within a period of 90 (ninety) days from the date of receipt of a

    Certified Copy of this order, failing which, the amount would carry

    interest at the rate of 14% per annum i.e. the same rate at which,

    Page 49 of 50

    ::: Uploaded on – 09/04/2026 ::: Downloaded on – 09/04/2026 21:36:08 :::
    Indian-Newspaper-oswp-864-2018-J-R.doc

    interest was payable by the Petitioner under the Lease Agreement

    due to delay in payment of outstanding dues, to be calculated

    from the date of this order till the amount is refunded.

    88. With the above observations, Rule is made absolute.

    89. The Writ Petition is disposed of accordingly.

    90. Parties to bear their own costs.

    (SUMAN SHYAM, J)                                              (CHIEF JUSTICE)
    
    
    
    
                                    Page 50 of 50
    
    
    ::: Uploaded on - 09/04/2026                        ::: Downloaded on - 09/04/2026 21:36:08 :::
     



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here