District Manager, Food Corporation Of … vs B M Samani on 1 May, 2026

    0
    28
    ADVERTISEMENT

    Gujarat High Court

    District Manager, Food Corporation Of … vs B M Samani on 1 May, 2026

                                                                                                                     NEUTRAL CITATION
    
    
    
    
                                C/FA/7110/1998                                   CAV JUDGMENT DATED: 01/05/2026
    
                                                                                                                     undefined
    
    
    
    
                                                                                        Reserved On     :-
                                                                                Pronounced On : 01/05/2026
    
                                          IN THE HIGH COURT OF GUJARAT AT AHMEDABAD
    
                                                    R/FIRST APPEAL NO. 7110 of 1998
    
    
                           FOR APPROVAL AND SIGNATURE:
    
    
                           HONOURABLE MR. JUSTICE J. C. DOSHI
    
                           ==========================================================
    
                                         Approved for Reporting                   Yes            No
    
                           ==========================================================
                                    DISTRICT MANAGER, FOOD CORPORATION OF INDIA & ANR.
                                                          Versus
                                                    B M SAMANI . & ANR.
                           ==========================================================
                           Appearance:
                           MR NIRAD D BUCH(4000) for the Appellants
                           MR MITUL SHELAT, SR. ADVOCATE with MR PRERAK P OZA(8279) for the
                           Respondent No.1
                           ==========================================================
    
                             CORAM:HONOURABLE MR. JUSTICE J. C. DOSHI
    
    
                                                               CAV JUDGMENT
    

    1. The present appeal is preferred under Section 39 of the
    Arbitration Act, 1940 (in short “the Act”), calling in question
    the legality and validity of the common judgment and order
    dated 5.12.1992 passed in CMA No. 69 of 1991 and CMA No.
    132 of 1991, whereby CMA No. 132 of 1991 filed by the
    appellant – Food Corporation of India was dismissed, and CMA
    No. 69 of 1991 filed by the contractor was allowed, directing
    the award dated 18.3.1991 passed by the learned Arbitrator

    Page 1 of 34

    SPONSORED

    Uploaded by SHEKHAR P. BARVE(HC00200) on Fri May 01 2026 Downloaded on : Sat May 02 05:40:51 IST 2026
    NEUTRAL CITATION

    C/FA/7110/1998 CAV JUDGMENT DATED: 01/05/2026

    undefined

    to be made as rule of the court and registered as a decree
    with interest at the rate of 18% per annum from the date of
    the award till realisation, along with costs. Thereby, the
    application filed under Sections 30 and 33 of the Act was
    rejected and the award dated 18.3.1991 was upheld.

    2. Brief facts leading to filing of present First Appeal are as
    under:-

    2.1 The appellant, Food Corporation of India, had awarded
    stevedoring, clearing, handling and transport contract to the
    respondent contractor M/s B.M. Samani for a period of two
    years between 25.8.1980 and 24.8.1982. Disputes having
    arisen between the parties, the FCI filed an application under
    Section 20 of the Act for appointment of an Arbitrator, being
    CMA No. 170 of 1984, which was allowed vide order dated
    13.7.1989 by the learned Civil Judge, (SD), Jamnagar. The
    learned trial court directed that the Managing Director of the
    FCI shall appoint an Arbitrator within four months from the
    date of the order, and that the Arbitrator so appointed shall
    proceed in accordance with the terms and conditions of the
    agreement and resolve the dispute as per clause 20 of the
    agreement. Pursuant to the said order, the Managing Director
    of the FCI appointed Mr. R.K. Gupta as Arbitrator to resolve
    the disputes between the parties.

    2.2 Since Mr. R.K. Gupta could not publish the award within
    the stipulated time i.e. within two months from the date of the
    award, the FCI filed CMA No. 127 of 1990 under Section 20 of

    Page 2 of 34

    Uploaded by SHEKHAR P. BARVE(HC00200) on Fri May 01 2026 Downloaded on : Sat May 02 05:40:51 IST 2026
    NEUTRAL CITATION

    C/FA/7110/1998 CAV JUDGMENT DATED: 01/05/2026

    undefined

    the Act seeking extension of time for the arbitration
    proceedings. Simultaneously, contractor M/s B.M. Samani
    preferred CMA No. 111 of 1990 under Sections 5 and 12 of
    the Act seeking revocation of the authority of the Arbitrator.

    Subsequently, Mr. R.K. Gupta resigned from his position as
    Arbitrator, and the FCI thereafter appointed Mr. Shiv
    Prakash, Additional Legal Advisor, Ministry of Law, New
    Delhi, as Arbitrator for resolution of the dispute. After
    conducting the arbitration proceedings and issuing notice
    under Section 14(1) of the Act, Arbitrator Mr. Shiv Prakash
    published the award of 18.3.1991.

    2.3 Thereafter, contractor M/s B.M. Samani filed CMA No.
    69 of 1991 directing the FCI to file the original award along
    with depositions so as to make the award as rule of the court.
    As against the said application, the FCI filed CMA No. 132 of
    1991 seeking to set aside the award published by the
    Arbitrator. The impugned order records dismissal of the FCI’s
    application and allowance of the contractor’s CMA, being
    aggrieved by which the FCI has preferred the present first
    appeal.

    2.4 Before the learned Arbitrator, contractor M/s B.M.
    Samani had filed following claims:-

    “I. Claim of Rs 44,015.93 towards amount illegally
    withheld/deducted from the bills.

    II. Claim of Rs 15,78,681.68 towards dispatch money
    earned on account of early release of 11 vessels
    during the contract period.

    Page 3 of 34

    Uploaded by SHEKHAR P. BARVE(HC00200) on Fri May 01 2026 Downloaded on : Sat May 02 05:40:51 IST 2026

    NEUTRAL CITATION

    C/FA/7110/1998 CAV JUDGMENT DATED: 01/05/2026

    undefined

    III. Claim for release of Bank Guarantee of Rs
    45,000/- furnished as security deposit

    IV. Claim for interest at the rate of 18% on claimed
    amount.

    V. Claim for legal expenses of Rs 2000/-.”

    2.5 Against the aforesaid claims, the FCI had filed following
    counter claims:-

    “I. Counter Claim No.1 for Rs 64,931.25 as per para 7
    of the CC

    II. Counter Claim No.2 for Rs 1,92,413.86 toward
    destination shortages

    III. Counter Claim No.3 for adjustment of Rs.45,000
    bank guarantee against the above two claims

    IV. Counter Claim No.4 towards interest.”

    2.6 The Arbitrator allowed Claim No. 1 of the contractor
    pertaining to illegal deduction of Rs.44,015.93; Claim No. 2 to
    the extent of granting benefit of dispatch money amounting to
    Rs. 13,65,352.52, and Claims No. 3 and 5 were also allowed,
    however, interest was disallowed.

    2.7 As regards the counter claims of the FCI, Counter Claim
    No. 1 was allowed to the extent of Rs. 6,40,931.35, Counter
    Claim No. 2 to the extent of Rs. 1,92,413.86, and an
    adjustment of Rs. 45000/- was granted in favour of the
    claimant against encashment of counter claims No. 1 and 2
    and disallowed counter claim No.4 towards interest.

    Page 4 of 34

    Uploaded by SHEKHAR P. BARVE(HC00200) on Fri May 01 2026 Downloaded on : Sat May 02 05:40:51 IST 2026

    NEUTRAL CITATION

    C/FA/7110/1998 CAV JUDGMENT DATED: 01/05/2026

    undefined

    2.8 It is in aforesaid background that the FCI, being
    aggrieved by the allowance of the contractor’s claims by the
    Arbitrator, has preferred the present first appeal.

    3. Learned Advocate Mr. Nirad Buch appearing for the FCI
    and learned Senior Counsel Mr. Mitul Shelat appearing for
    the contractor have filed their respective written submissions,
    both of which are taken on record.

    4. Submissions of learned advocate Mr.Nirad Buch in short
    are as under:-

     That an Arbitrator or umpire has misconducted himself or
    the proceedings;

     That an award has been made after the issue of an order
    by the Court superseding the arbitration or after
    arbitration proceedings have become invalid under
    section 35;

     That an award has been improperly procured or is
    otherwise invalid.

     That the learned Arbitrator has transgressed the
    jurisdiction and the agreement.

     That the learned Arbitrator has committed a material
    impropriety and a legal misconduct and grievous favor to
    the contractor.

     That no clause in the agreement entitles the contractor to
    get dispatch money. P. 26 of the Agreement (Clause I,
    Part XX-I, Part I).

    Page 5 of 34

    Uploaded by SHEKHAR P. BARVE(HC00200) on Fri May 01 2026 Downloaded on : Sat May 02 05:40:51 IST 2026

    NEUTRAL CITATION

    C/FA/7110/1998 CAV JUDGMENT DATED: 01/05/2026

    undefined

     That even as per the custom, practice and rules of
    business, the contractor was not entitled, for claim of
    dispatch money.

     That dispatch money stems from Charter Party agreement
    between the FCI and the charterer, in which the
    Contractor is not a party and thus, cannot validly claim
    the dispatch money.

     That dispatch money was in fact Rs. 12,99,923.62, but
    calculated at Rs. 15,78,681.68.

     That the claim was Rs. 15,78,681.68; The learned
    Arbitrator awarded Rs. 13,65,352.52 and although the
    Contractor did not challenge it, the learned court
    increased it to Rs. 15,78,681.68.The learned Arbitrator
    refused to award interest to the Contractor, and the court
    allowed it without challenge by the contractor.
     That the learned Arbitrator passed the award in
    ignorance of material evidence and decides the matter
    not in accordance with the terms of the contract and has
    construed the contract in unreasonable manner.
     That it is well-settled that Arbitrator is the creature of
    contract executed between the parties and thereby, the
    Arbitrator cannot ignore the terms of the contract.
    Consistent view is prevailing that if the learned Arbitrator
    does not adhere to or disregard the terms of the contract,
    it would amount to a jurisdictional error and the Court
    can therefore, interfere with the award.
     That it was incumbent upon the learned civil court to
    examine as to whether the Arbitrator had acted in excess
    of his jurisdiction, by disregarding the terms of reference

    Page 6 of 34

    Uploaded by SHEKHAR P. BARVE(HC00200) on Fri May 01 2026 Downloaded on : Sat May 02 05:40:51 IST 2026
    NEUTRAL CITATION

    C/FA/7110/1998 CAV JUDGMENT DATED: 01/05/2026

    undefined

    or the arbitration agreement or the terms of contract,
    which would indeed be a jurisdictional error in rendering
    the award.

     That a deliberate departure or conscious disregard of the
    contract would have resulted in not only manifesting the
    disregarding of his authority by the Arbitrator or
    misconduct on his part, but also tantamount to mala fide
    action/patent illegality. The Arbitrator could not have
    acted arbitrarily, irrationally, independently or
    capriciously of the contract even under the old regime of
    Arbitration Act. In a case where the Arbitrator acted
    beyond his jurisdiction, interference by the Court in
    setting aside the award was permissible.

    4.1 Mainly upon above submissions, learned advocate Mr.
    Buch seeks to allow this appeal and to quash and set aside the
    impugned award.

    4.2 In support of his submission, learned advocate Mr. Buch
    has relied upon following authorities:-

    1. P. C. Snehal Construction Co. Versus Municipal
    Corporation of Ahmedabad – First Appeal No. 617 of
    2005 (Para 37)

    2. S.D.Shinde Tr. Partner Versus Govt. Of Maharashtra
    2023 (0) AIR(SC) 4174 (Para 24)

    3. Rajasthan State Mines & Minerals Ltd. (1999) 9 SCC
    283 [para 25-29 & 31 to 44]

    4. National Buildings Construction Corporation Limited

    Page 7 of 34

    Uploaded by SHEKHAR P. BARVE(HC00200) on Fri May 01 2026 Downloaded on : Sat May 02 05:40:51 IST 2026
    NEUTRAL CITATION

    C/FA/7110/1998 CAV JUDGMENT DATED: 01/05/2026

    undefined

    Versus U.P. State Bridge Corporation Ltd
    (FA/2359/2010) – Para 57 to 71.

    5. Amratlal B. Tank vs. Surat Municipal Corporation (2012
    (2) GLH 15)

    6. M/s. Cochin Shipyard Ltd. (2015) 10 SCR 994 (Para 10,
    12, 16, 18)

    5. Learned senior Counsel Mr. Mitul Shelat assisted by
    learned advocate Mr. Prerak Oza for the respondent No.1, as
    against the aforesaid submissions, would mainly submit that
    scope of review under Section 39 is extremely circumspect
    and it does not permit a re-appreciation of evidence or
    substitution of the Arbitrator’s findings on merits.
    Interference is only for patent misconduct. He would further
    submit that in the case on hand, the Arbitrator is appointed
    by the Appellant. He would further submit that in the present
    case, the appellant has firstly appointed Mr.RK Gupta and
    then Mr. Shiv Prakash, Additional Legal Advisor, Ministry of
    Law, New Delhi as Arbitrator. He would further submit that
    considering the impugned order, whereby the learned
    Arbitrator allowed the claim as well as counterclaim leaves no
    room for alleging any bias or misconduct on the proceedings.
    He would further submit that this impugned award
    demonstrates that while passing the award, the learned
    Arbitrator has applied his mind. He would further submit
    that the learned civil Court while making the award as as rule
    of the court confirmed the findings of the learned Arbitrator
    which infers that there is no misconduct of the proceedings.
    He would further submit that the appellant failed to establish

    Page 8 of 34

    Uploaded by SHEKHAR P. BARVE(HC00200) on Fri May 01 2026 Downloaded on : Sat May 02 05:40:51 IST 2026
    NEUTRAL CITATION

    C/FA/7110/1998 CAV JUDGMENT DATED: 01/05/2026

    undefined

    any ground, which would warrant interference with the
    impugned award.

    5.1 In support of his submission, learned Senior Counsel Mr.
    Shelat has relied upon following authorities.

    1. State of Gujarat, Executive Engineer vs. Nitin
    Construction & Co., First Appeal No.692 of 1990

    2. BB Yadav through legal heirs and others Vs. Food
    Corporation of India and another
    , 2025 SCC Online Guj

    2085

    3. Food Corporation of India Vs. Harish Transport
    Corporation
    , 2007 AIJEL Hon’ble Court 219527

    5.2 In addition to above arguments, learned senior Counsel
    Mr. Shelat would submit that the main dispute between the
    parties about passing of dispatched money received by the
    FCI under the chartered agreement to the contractor. He
    would further submit that the learned Arbitrator recorded the
    finding on fact that since the liability of demurrage arising
    under the chartered agreement is passed upon the contractor
    in converse benefit of receiving of dispatched money for doing
    the work earlier than the stipulated time period has to be
    passed to the contractor. This is prevailing commercial
    practice, which has been rightly observed by the learned
    Arbitrator and confirmed by the learned civil Court.
    Therefore, he would submit that the reasoning demonstrates
    that the Arbitrator’s view was not only plausible but also
    aligned with equity and fairness. He would further submit

    Page 9 of 34

    Uploaded by SHEKHAR P. BARVE(HC00200) on Fri May 01 2026 Downloaded on : Sat May 02 05:40:51 IST 2026
    NEUTRAL CITATION

    C/FA/7110/1998 CAV JUDGMENT DATED: 01/05/2026

    undefined

    that the tone and tenor of the award passed by the learned
    Arbitrator, whereby he has allowed the claim and
    counterclaim and disallowed the appellant’s claim and
    counterclaim, demonstrate that the learned Arbitrator has not
    misconducted himself or misconducted the proceedings, as
    impugned award suffers from any legal flow. He would
    further submit that looking to this aspect, it cannot be said
    that the award passed by the learned Arbitrator is contrary
    and the decision confirming the same passed by the learned
    civil Court is erroneously illegal. He would further submit
    that application of mind of the learned Arbitrator would be
    seen as he has noted minor discrepancies and miscalculation
    in the claim and thereby, he has acted in the best interest of
    both the parties. Such award being on fact, full of reasons
    and application of mind cannot be said to be non-speaking
    award.

    5.3 In light of the aforesaid argument, learned senior
    Counsel Mr. Shelat would submit that this Court u/s 39 of the
    Act should not examine sufficiency of the correctness of the
    fact and reasoning nor can it attempt to reconstruct the
    reasoning process of the Arbitrator.

    5.4 In support of his submission, learned senior Counsel Mr.
    Shelat has referred to and relied upon the judgment in case of
    Atlanta Limited through its Managing Director vs.
    Union of India
    represented by Chief Engineer, Military
    Engineering Service, (2022) 3 SCC 739 and in case of
    Nitin Construction (supra) and in case of Administrator

    Page 10 of 34

    Uploaded by SHEKHAR P. BARVE(HC00200) on Fri May 01 2026 Downloaded on : Sat May 02 05:40:51 IST 2026
    NEUTRAL CITATION

    C/FA/7110/1998 CAV JUDGMENT DATED: 01/05/2026

    undefined

    of the Specified Undertaking of the Unit Trust of India
    and another Vs. Garware Polyester Ltd.
    , 2005(10) SCC
    682.

    5.5 With the aforesaid submissions, learned senior Counsel
    Mr. Shelat prays to dismiss the petition.

    6. Having heard the learned advocates for both parties and
    having gone through the facts, circumstances, record and
    proceedings of the case, as well as the authorities cited at bar,
    this Court proceeds to decide the matter. Before adverting to
    the rival submissions of the contesting parties, worthy
    reference is taken from the Division Bench judgment of this
    Court in the case of Nitin Construction (supra), wherein
    the Division Bench analysed the scope of interference in an
    arbitral award in the context of the prevailing position of law.
    The relevant paragraphs 13, 14, 15, 16 and 17 of the said
    judgment are reproduced as under:-

    “13. Analysis :-

    [As regards the award of an arbitrator under
    the Act, the law is well settled that the
    Arbitrator’s adjudication is generally considered
    binding between the parties for he is a Tribunal
    selected by the parties and the power of the
    Court to set aside the award is restricted to
    cases set out in Sec. 30 of the Act, viz. (a) if the
    Arbitrator has misconducted himself or the
    proceedings; or (b) when the award has been
    made after the issue of an order by the Court
    superseding the arbitration or after arbitration
    proceedings have become invalid under Sec. 35;
    or (c) when the award has been improperly

    Page 11 of 34

    Uploaded by SHEKHAR P. BARVE(HC00200) on Fri May 01 2026 Downloaded on : Sat May 02 05:40:51 IST 2026
    NEUTRAL CITATION

    C/FA/7110/1998 CAV JUDGMENT DATED: 01/05/2026

    undefined

    produced or is otherwise invalid.]

    14. Under clause (c) of Sec. 30, the Court can set
    aside the award which suffers from an error on the
    face of the award. It is, however, not open to the
    Court to speculate, where no reasons are given by
    the Arbitrator, as to what impelled the Arbitrator to
    arrive at his conclusion. The jurisdiction of the
    Arbitrator is limited by the reference and if the
    Arbitrator has assumed jurisdiction not possessed by
    him, the award to the extent to which it is beyond the
    Arbitrator’s jurisdiction, would be invalid and liable
    to be set aside. This position of law has been well
    settled by the Constitution Bench of the Supreme
    Court in Raipur Development Authority V/s.

    Chokhamal Contractors and ors., reported in 1989
    (2) SCC 721. In Raipur Development Authority
    (supra) it has been held that an Arbitrator or umpire
    is under no obligation to give reasons in support of
    the decision reached by him unless under the
    arbitration agreement or the deed of submission he
    is required to give such reasons, and if the Arbitrator
    or umpire chooses to give reasons in support of his
    decision it is open to the Court to set aside the award
    if it finds that an error of law has been committed by
    the arbitrator or umpire on the face of the record on
    going through such reasons, and an award can
    neither be remitted nor set aside merely on the
    ground that it does not contain reasons in support of
    the conclusion or decisions reached in it except
    where the arbitral agreement or the deed by
    submission requires him to give reasons.

    15. The position of law as aforesaid answers one of
    the main contentions of the appellant that the
    Arbitrator has failed to assign reasons while passing
    the award. As a matter of fact, on perusal of the
    award we find that the arbitrator in his own way has
    assigned reasons and we are convinced by the
    reasons assigned by the Arbitrator.

    16. The scope and extent of examination by the
    Court of an award made by the Arbitrator has been
    laid down in various decisions. We may profitably
    quote decision of the Supreme Court in the case of

    Page 12 of 34

    Uploaded by SHEKHAR P. BARVE(HC00200) on Fri May 01 2026 Downloaded on : Sat May 02 05:40:51 IST 2026
    NEUTRAL CITATION

    C/FA/7110/1998 CAV JUDGMENT DATED: 01/05/2026

    undefined

    Guj. Water Supply & Sewerage Board V/s. Unique
    Erectors (Gujarat) (P) Ltd., reported in AIR 1989 SC
    972, wherein the Bench held in para 9 as under :-

    [“It has to be noted that there is a trend in
    modern times that reasons should be stated in
    the award though the question whether the
    reasons are necessary in ordinary arbitration
    awards between the parties is pending
    adjudication by the Constitution bench of this
    Court. Even,however, if it be held that it is
    obligatory for the arbitratorto state reasons, it
    is not obligatory to give any detailed judgment.
    An award of an arbitrator should be read
    reasonably as a whole to find out the
    implication and the meaning thereof Short
    intelligible indications of the grounds should be
    discernible to find out the mind of the arbitrator
    for his action even if it be enjoined that in all
    cases of award by any arbitrator reasons have
    to be stated. The reasons should not only be
    intelligible but should also deal either expressly
    or impliedly with the substantial points that
    have been raised. Even in a case where the
    arbitrator has to state reasons, the sufficiency
    of the reasons depends upon the facts and the
    circumstances of the case. The Court, however,
    does not sit in appeal over the award and
    review the reasons. The Court can set aside the
    award only if it is apparent from the award that
    there is no evidence to support the conclusion
    or if the award is based upon any legal
    proposition which is erroneous. See the
    observations of this Court in Indian Oil
    Corporation Ltd. V/s. Indian Carbon Ltd.[1988]
    3 SCC 36.]
    [In M.CD. V/s. M/s. JaganNath Ashok Kumar,
    reported in (1987) 4 SCC 497, the Supreme
    Court observed thus :-]
    [“In this case, there was no violation of any
    principles of natural justice. It is not a case
    where the arbitrator has refused cogent and
    material factors to be taken into consideration.

    Page 13 of 34

    Uploaded by SHEKHAR P. BARVE(HC00200) on Fri May 01 2026 Downloaded on : Sat May 02 05:40:51 IST 2026

    NEUTRAL CITATION

    C/FA/7110/1998 CAV JUDGMENT DATED: 01/05/2026

    undefined

    The award cannot be said to be vitiated by non-
    reception of material or non-consideration of
    the relevant aspects of the matter.

    Appraisement of evidence by the arbitrator is
    ordinarily never a matter which the Court
    questions and considers. The parties have
    selected their own forum and the deciding
    forum must be conceded the power of
    appraisement of the evidence. In the instant
    case, there was no evidence of violation of any
    principle of natural justice.]
    [The arbitrator in our opinion is the sole judge
    of the quality as well as quantity of evidence
    and it will not be for this Court to take upon
    itself the task of being a judge of the evidence
    before the arbitrator. It may be possible that on
    the same evidence the Court might have arrived
    at a different conclusion than the one arrived at
    by the arbitrator but that by itself is no ground
    in our view for setting aside the award of an
    arbitrator.”]
    [The Supreme Court further concluded:-]
    [“After all an arbitrator as a judge in the words
    of Benjamin N. Cardozo, has to exercise a
    discretion informed by tradition, methodized by
    analogy, disciplined by system, and
    subordinated to “the primordial necessity of
    order in the social life”.]
    [In P. M. Paul V/s. Union of India, reported in
    (1989) Supp 1 SCC 368, the Supreme Court
    held as under :-]
    [“It was submitted that if the contract work was
    not completed within the stipulated time which
    it appears was not done then the contractor has
    got a right to ask for extension of time, and he
    could claim difference in price. This is precisely
    what he has done and has obtained a portion of
    the claim in the award. It was submitted on
    behalf of the Union of India that failure to
    complete the contract was not the case. Hence,
    there was no substance in the objections raised.

    Page 14 of 34

    Uploaded by SHEKHAR P. BARVE(HC00200) on Fri May 01 2026 Downloaded on : Sat May 02 05:40:51 IST 2026

    NEUTRAL CITATION

    C/FA/7110/1998 CAV JUDGMENT DATED: 01/05/2026

    undefined

    Furthermore, in the objections raised, it must
    be within the time provided for the application
    under Sec. 30 i.e., 30 days during which the
    objection was not specifically taken, we are of
    the opinion that there is no substance in this
    objection sought to be raised in opposition to
    the award. Once it was found that the arbitrator
    had jurisdiction to find that there was delay in
    execution of the contract due to the conduct of
    the respondent, the respondent was liable for
    the consequences of the delay, namely, increase
    in prices. Therefore, the arbitrator had
    jurisdiction to go into this question. He has
    gone into that question and has awarded as he
    did.”]
    [In one of the recent pronouncements of the
    Supreme Court in the case of Ravindra Kumar
    Gupta and Company v. Union of India
    , reported
    in (2010) 1 SCC 409, the Supreme Court has
    considered the law with regard to the scope and
    ambit of the jurisdiction of the Courts to
    interfere with an arbitration award after taking
    note of catena of judgments. The relevant
    paragraphs are quoted below :-]
    [9. The law with regard to scope and ambit of
    the jurisdiction of the Courts to interfere with
    an arbitration award has been settled in a
    catena of judgments of this Court. We may
    make a reference here only to some of the
    judgments. In the case of State of Rajasthan
    V/s. Puri Construction Company Ltd. 1994 (6)
    SCC 485 : (1994 AIR SCW 5061), this Court
    observed as follows :-]
    [“The arbitrator is the final arbiter for the
    dispute between the parties and it is not open
    to challenge the award on the ground that the
    arbitrator has drawn his own conclusion or has
    failed to appreciate the facts. In Sudarsan
    Trading Co. V/s. Govt. of Kerala, 1989 Ind law
    SC 463 : (AIR 1989 SC 890) it has been held by
    this Court that there is a distinction between
    disputes as to the jurisdiction of the arbitrator

    Page 15 of 34

    Uploaded by SHEKHAR P. BARVE(HC00200) on Fri May 01 2026 Downloaded on : Sat May 02 05:40:51 IST 2026
    NEUTRAL CITATION

    C/FA/7110/1998 CAV JUDGMENT DATED: 01/05/2026

    undefined

    and the disputes as to in what way that
    jurisdiction should be exercised. There may be
    a conflict as to the power of the arbitrator to
    grant a particular remedy. One has to
    determine the distinction between an error
    within the jurisdiction and an error in excess of
    the jurisdiction. Court cannot substitute its own
    evaluation of the conclusion of law or fact to
    come to the conclusion that the arbitrator had
    acted contrary to the bargain between the
    parties. Whether a particular amount was liable
    to be paid is a decision within the competency
    of the arbitrator. By purporting to construe the
    contract the Court cannot take upon itself the
    burden of saying that this was contrary to the
    contract and as such beyond jurisdiction. If on a
    view taken of a contract, the decision of the
    arbitrator on certain amounts awarded is a
    possible view though perhaps not the only
    correct view, the award cannot be examined by
    the Court. Where the reasons have been given
    by the arbitrator in making the award the Court
    cannot examine the reasonableness of the
    reasons. If the parties have selected their awn
    forum, the deciding forum must be conceded
    the power of appraisement of evidence. The
    arbitrator is the sole judge of the quality as well
    as the quantity of evidence and it will not be for
    the Court to take upon itself the task of being a
    judge on the evidence before the arbitrator.]
    [In the case of Municipal Corpn. of Delhi v.
    Jagan Nath Ashok Kumar
    , 1987 (4) SCC 497 :

    (AIR 1987 SC 2316), it has been held by this
    Court that appraisement of evidence by the
    arbitrator is ordinarily never a matter which the
    Court questions and considers. It may be
    possible that on the same evidence the Court
    may arrive at a different conclusion than the
    one arrived at by the arbitrator but that by
    itself is no ground for setting aside the award.
    It has also been held in the said decision that it
    is difficult to give an exact definition of the
    word ‘reasonable’. Reason varies in its

    Page 16 of 34

    Uploaded by SHEKHAR P. BARVE(HC00200) on Fri May 01 2026 Downloaded on : Sat May 02 05:40:51 IST 2026
    NEUTRAL CITATION

    C/FA/7110/1998 CAV JUDGMENT DATED: 01/05/2026

    undefined

    conclusions according to the idiosyncrasies of
    the individual and the time and circumstances
    in which thinks. In cases not covered by
    Authority, the verdict of a jury or the decision of
    a judge sitting as a jury usually determines
    what is ‘reasonable’ in each particular case is
    The word reasonable has in law prima facie
    meaning of reasonable in regard to those
    circumstances of which the actor, called on to
    act reasonably knows or ought to know. An
    arbitrator acting as a judge has to exercise a
    discretion informed by tradition, methodized by
    analogy disciplined by system and subordinated
    to the primordial necessity or order in the social
    life. Therefore, where reasons germane and
    relevant for the arbitrator to hold in the manner
    he did, have been indicated, it cannot be said
    that the reasons are unreasonable.”]
    [10. In the case of Arosan Enterprises Ltd. v.
    Union of India
    , 1999 (9) SCC 449 : (1999 AIR
    SCW 3872), this Court upon analysis of
    numerous earlier 35 decisions, held as
    follows :-]
    [“36. Be it noted that by reasons of a long
    catena of cases, it is now a well-settled
    principle of law that reappraisal of evidence by
    the Court is not permissible and as a matter of
    fact exercise of power by the Court to
    reappraise the evidence is unknown to
    proceedings under Sec. 30 of the Arbitration
    Act. In the event of there being no reasons in
    the award, question of interference of the Court
    would not arise at all. In the event, however,
    there are reasons, the interference would still
    be, not available within the jurisdiction of the
    Court unless of course, there exist a total
    perversity in the award or the judgment is
    based on a wrong proposition of law. In the
    event however two views are possible on a
    question of law as well, the Court would not be
    justified in interfering with the award.]
    [37. The common phraseology “error apparent

    Page 17 of 34

    Uploaded by SHEKHAR P. BARVE(HC00200) on Fri May 01 2026 Downloaded on : Sat May 02 05:40:51 IST 2026
    NEUTRAL CITATION

    C/FA/7110/1998 CAV JUDGMENT DATED: 01/05/2026

    undefined

    on the face of the record” does not itself,
    however, mean and imply closer scrutiny of the
    merits of documents and materials on record.
    The Court as a matter of fact cannot substitute
    its evaluation and come to the conclusion that
    the arbitrator had acted contrary to the bargain
    between the parties. If the view of the,
    arbitrator is a possible view the award or the
    reasoning contained therein cannot be
    examined.”]
    [11. This view has been reiterated by this Court
    in the case of Oil and Natural Gas Corporation
    Ltd. V/s. SAW Pipes Ltd. 2003 AIR SCW 3041 :-]
    [“53. In the light of the aforesaid decisions, in
    our view, there is much force in the contention
    raised by the learned Counsel for the appellant.
    However, the learned senior Counsel Mr. Dave
    submitted that even if the award passed by the
    arbitral Tribunal is erroneous, it is settled law
    that when two views are possible with regard to
    interpretation of statutory provisions and or
    facts, the Court would refuse to interfere with
    such award.]
    [54. It is true that if the arbitral Tribunal has
    committed mere error of fact law in reaching its
    conclusion on the disputed question submitted
    to it for adjudication then the Court would have
    no jurisdiction to interfere with the award. But,
    this would depend upon reference made to the
    arbitrator : (a) if there is a general reference for
    deciding the contractual dispute between the
    parties and if the award is based on erroneous
    legal proposition, the Court could interfere; (b)
    It is also settled law that in a case of reasoned
    award, the Court can set aside the same if it is,
    on the face of it, erroneous on the provision of
    law or its application; (c) If a specific question
    of law is submitted to the arbitrator, erroneous
    decision in point of law does not make the
    award bad, so as to permit of its being set
    aside, unless the Court is satisfied that the
    arbitrator had proceeded illegally.”]

    Page 18 of 34

    Uploaded by SHEKHAR P. BARVE(HC00200) on Fri May 01 2026 Downloaded on : Sat May 02 05:40:51 IST 2026
    NEUTRAL CITATION

    C/FA/7110/1998 CAV JUDGMENT DATED: 01/05/2026

    undefined

    [12. In the M/s. Kwality Manufacturing
    Corporation V/s. Central Warehousing
    Corporation it was held :-]
    [“10. At the outset, it should be noted that the
    scope of interference by Courts in regard to
    arbitral awards is limited. A Court considering
    an application under Sec. 30 or 33 of the Act,
    does not sit in appeal over the findings and
    decision of the arbitrator. Nor can it re-assess
    or re-appreciate evidence or examine the
    sufficiency or otherwise of the evidence. The
    award of the arbitrator is final and the only
    grounds on which it can be challenged are
    those mentioned in Secs. 30 and 33 of the Act.
    Therefore, on the contentions urged, the only
    question that arose for consideration before the
    High Court was, whether there was any error
    apparent on the face of the award and whether
    the arbitrator misconducted himself or the
    proceedings.”]
    [13. Again it is reiterated in the judgment of
    Madhya Pradesh Housing Board v. Progressive
    Writers and Publishers
    (2009) 5 SCC 678 :

    (2009 AIR SCW 2484) as follows :-]
    [“28. The finding arrived at by the arbitrator in
    this regard is not even challenged by the Board
    in the proceedings initiated by it under Sec. 30
    of the Act. It is fairly well settled and needs no
    restatement that the award of the arbitrator is
    ordinarily final and the Courts hearing
    applications under Sec. 30 of the Act do not
    exercise any appellate jurisdiction. Reappraisal
    of evidence by the Court is impermissible.”]
    [14. In this case, the Supreme Court notice the
    earlier judgment in the case of Ispat
    Engineering and Foundry Works, B.S. City,
    Bokaro V/s. Steel Authority of India, B.S. City,
    Bokaro [(2001) 6 SCC 3471 : (2007 AIR SCW
    2723) wherein it was held as follows :-]
    [“4. Needless to record that there exists a long
    catena of cases through which the law seems to

    Page 19 of 34

    Uploaded by SHEKHAR P. BARVE(HC00200) on Fri May 01 2026 Downloaded on : Sat May 02 05:40:51 IST 2026
    NEUTRAL CITATION

    C/FA/7110/1998 CAV JUDGMENT DATED: 01/05/2026

    undefined

    be rather well settled that the reappraisal of
    evidence by the Court is not permissible. This
    Court in one of its latest decisions [Arosan
    Enterprises Ltd. V/s. Union of India (1999) 9
    SCC 449 : (W99 AIR SCW 3872)] upon
    consideration of decisions in Champsey Bhara
    and Co. v. Jivraj Balloo Spg. and Wvg. Co. Ltd
    .

    [AIR 1923 PC 66], Union of India v.. Bungo
    Steel Furniture (P) Ltd. [(1967) 1 SCR 324] :

    (AIR 1967 SC 1032) N.Chellappan V/s. Secy.,
    Kerala SEB [(1975) 1 SCC 289] : (AIR 1975 SC

    230), Sudarshan Trading Co. V/s. Govt.of Kerala
    [(1989) 2 SCC 38], State of Rajasthan v. Puri
    Construction Co.Ltd. [(1994) 6 SCC 485] :

    (1994 AIR SCW 5061) as also in Olympus
    Superstructures (P) Ltd. V/s. Meena Vijay
    Khetan [(1999) 5 SCC 651]: (1999 AIR SCW
    1831) has stated that reappraisal of evidence by
    the Court is not permissible and as a matter of
    fact, exercise of power to reappraise the
    evidence is unknown to a proceeding under
    Sec. 30 of the Arbitration Act, 1940 . This Court
    in Arosan Enterprises. categorically stated that
    in the event of there being no reason in the
    award, question of interference of the Court
    would not arise at all. In the event, however,
    there are reasons, interference would still be
    not available unless of course, there exist a
    total perversity in the award or the judgment is
    based on a wrong proposition of law. This Court
    went on to record that in the event, however,
    two views are possible on a question of law, the
    Court would not be justified in interfering with
    the award of the arbitrator if the view taken
    recourse to is a possible view. The observations
    of Lord Dunedin in Champsey Bhara stand
    accepted and adopted by this Court in Bungo
    Steel Furniture to the effect that the Court had
    no jurisdiction to investigate into the merits of
    the case or to examine the documentary and
    oral evidence in the record for the purposes of
    finding out whether or not the arbitrator has
    committed an error of law. The Court as a

    Page 20 of 34

    Uploaded by SHEKHAR P. BARVE(HC00200) on Fri May 01 2026 Downloaded on : Sat May 02 05:40:51 IST 2026
    NEUTRAL CITATION

    C/FA/7110/1998 CAV JUDGMENT DATED: 01/05/2026

    undefined

    matter of fact, cannot substitute its own
    evaluation and come to the conclusion that the
    arbitrator had acted contrary to the bargain
    between the parties.”]

    17. From the various decisions referred to above, it
    could safely be stated that :-

    [(a) In the award, the arbitrator is not required
    to give reasons in detail.]
    [(b) The award can be set aside only on the
    ground of error of law on the face of it, i.e. to
    say, if the award is based upon any legal
    proposition which is erroneous.]
    [(c) The Civil Court has no jurisdiction to sit in
    appeal over the award and review the reasons
    assigned by the arbitrator and the award
    cannot be set aside merely because by process
    of inference and arguments it could be
    demonstrated that the arbitrator has committed
    some mistake in arriving at his conclusion.]
    [(d) The award cannot be interfered with even
    in the case where on an interpretation of any
    contract or documents, two views are plausible
    and the arbitrator accepts one view while the
    other view is more appealing to the Court.]
    [(e) The award can be set aside by the Civil
    Court if the arbitrator has misconducted
    himself or the arbitrator has acted contrary to
    or gone beyond the terms of the reference.]”

    7. In the case of Atlanta Limited (supra), the Hon’ble
    Apex Court held that once an Arbitrator has interpreted the
    clauses of a contract by taking a possible view and has gone
    to great lengths to analyze several reasons offered by the
    appellant-claimant to justify its plea for extension of time to
    execute the contract, the High Court, exercising jurisdiction
    under Section 39 of the Act, ought not to have sat over the

    Page 21 of 34

    Uploaded by SHEKHAR P. BARVE(HC00200) on Fri May 01 2026 Downloaded on : Sat May 02 05:40:51 IST 2026
    NEUTRAL CITATION

    C/FA/7110/1998 CAV JUDGMENT DATED: 01/05/2026

    undefined

    said decision as an appellate court seeking to substitute its
    own view for that of the Arbitrator. The relevant paragraphs
    are 19 to 22 of the said judgment, which read as under:-

    “19. It is also a well-settled principle of law that
    challenge cannot be laid to the Award only on the
    ground that the Arbitrator has drawn his own
    conclusion or failed to appreciate the relevant facts.
    Nor can the Court substitute its own view on the
    conclusion of law or facts as against those drawn by
    the Arbitrator, as if it is sitting in appeal. This aspect
    has been highlighted in State of Rajasthan v. Puri
    Construction Co. Ltd. And Another
    , (1994) 6 SCC 485
    where it has been observed thus:

    “26. The arbitrator is the final arbiter for the
    dispute between the parties and it is not open to
    challenge the award on the ground that the
    arbitrator has drawn his own conclusion or has
    failed to appreciate the facts. In Sudarsan
    Trading Co. v. State of Kerala [Sudarsan Trading
    Co. v. State of Kerala, (1989) 2 SCC 38] it has
    been held by this Court that there is a distinction
    between disputes as to the jurisdiction of the
    arbitrator and the disputes as to in what way
    that jurisdiction should be exercised. There may
    be a conflict as to the power of the arbitrator to
    grant a particular remedy. One has to determine
    the distinction between an error within the
    jurisdiction and an error in excess of the
    jurisdiction. Court cannot substitute its own
    evaluation of the conclusion of law or fact to
    come to the conclusion that the arbitrator had
    acted contrary to the bargain between the
    parties. Whether a particular amount was liable
    to be paid is a decision within the competency of
    the arbitrator. By purporting to construe the
    contract the court cannot take upon itself the
    burden of saying that this was contrary to the
    contract and as such beyond jurisdiction. If on a
    view taken of a contract, the decision of the
    arbitrator on certain amounts awarded is a

    Page 22 of 34

    Uploaded by SHEKHAR P. BARVE(HC00200) on Fri May 01 2026 Downloaded on : Sat May 02 05:40:51 IST 2026
    NEUTRAL CITATION

    C/FA/7110/1998 CAV JUDGMENT DATED: 01/05/2026

    undefined

    possible view though perhaps not the only
    correct view, the award cannot be examined by
    the court. Where the reasons have been given by
    the arbitrator in making the award the court
    cannot examine the reasonableness of the
    reasons. If the parties have selected their own
    forum, the deciding forum must be conceded the
    power of appraisement of evidence. The
    arbitrator is the sole judge of the quality as well
    as the quantity of evidence and it will not be for
    the court to take upon itself the task of being a
    Judge on the evidence before the arbitrator.”

    [emphasis added]

    20. As long as the Arbitrator has taken a possible
    view, which may be a plausible view, simply because a
    different view from that taken in the Award, is
    possible based on the same evidence, would also not
    be a ground to interfere in the Award. In Arosan
    Enterprises Ltd. v. Union of India and Another
    , (1999)
    9 SCC 449 this Court has held as follows:

    “36. Be it noted that by reason of a long catena
    of cases, it is now a well-settled principle of law
    that reappraisal of evidence by the court is not
    permissible and as a matter of fact exercise of
    power by the court to reappraise the evidence is
    unknown to proceedings under Section 30 of the
    Arbitration Act. In the event of there being no
    reasons in the award, question of interference of
    the court would not arise at all. In the event,
    however, there are reasons, the interference
    would still be not available within the
    jurisdiction of the court unless of course, there
    exist a total perversity in the award or the
    judgment is based on a wrong proposition of law.
    In the event however two views are possible on a
    question of law as well, the court would not be
    justified in interfering with the award.”

    (Also refer Municipal Corporation of Delhi v. Jagan
    Nath Ashok Kumar and Another
    , (1987) 4 SCC 497)

    21. In Rajasthan State Mines & Minerals Ltd. (supra),
    relied on by the respondent – Union of India, on a

    Page 23 of 34

    Uploaded by SHEKHAR P. BARVE(HC00200) on Fri May 01 2026 Downloaded on : Sat May 02 05:40:51 IST 2026
    NEUTRAL CITATION

    C/FA/7110/1998 CAV JUDGMENT DATED: 01/05/2026

    undefined

    conspectus of the case law relating to an Award made
    under the Arbitration Act, 1940 and the scope of
    interference by courts in such an arbitral Award, the
    legal position was summarized by the court in the
    following words :

    “44. From the resume of the aforesaid decisions,
    it can be stated that:

    (a) it is not open to the court to speculate, where
    no reasons are given by the arbitrator, as to
    what impelled arbitrator to arrive at his
    conclusion.

    (b) It is not open to the court to admit to probe
    the mental process by which the arbitrator has
    reached his conclusion where it is not disclosed
    by the terms of the Award.

    (c) If the arbitrator has committed a mere error
    of fact or law in reaching his conclusion on the
    disputed question submitted for his adjudication
    then the Court cannot interfere.

    (d) If no specific question of law is referred, the
    decision of the arbitrator on that question is not
    final, however much it may be within his
    jurisdiction and indeed essential for him to
    decide the question incidentally. In a case where
    specific question of law touching upon the
    jurisdiction of the arbitrator was referred for the
    decision of the arbitrator by the parties, then the
    finding of the arbitrator on the said question
    between the parties may be binding.

    (e) In a case of non-speaking Award, the
    jurisdiction of the court is limited. The Award
    can be set aside if the arbitrator acts beyond his
    jurisdiction.

    (f) To find out whether the arbitrator has
    travelled beyond his jurisdiction, it would be
    necessary to consider the agreement between
    the parties containing the arbitration clause. The
    arbitrator acting beyond his jurisdiction is a
    different ground from the error apparent on the
    face of the Award.

    Page 24 of 34

    Uploaded by SHEKHAR P. BARVE(HC00200) on Fri May 01 2026 Downloaded on : Sat May 02 05:40:51 IST 2026

    NEUTRAL CITATION

    C/FA/7110/1998 CAV JUDGMENT DATED: 01/05/2026

    undefined

    (g) In order to determine whether arbitrator has
    acted in excess of his jurisdiction what has to be
    seen is whether the claimant could raise a
    particular claim before the arbitrator. If there is
    a specific term in the contract or the law which
    does not permit or give the arbitrator the power
    to decide the dispute raised by the claimant or
    there is a specific bar in the contract to the
    raising of the particular claim then the Award
    passed by the arbitrator in respect thereof would
    be in excess of jurisdiction.

    (h) The Award made by the Arbitrator
    disregarding the terms of the reference or the
    arbitration agreement or the terms of the
    contract would be a jurisdictional error which
    requires ultimately to be decided by the Court.
    He cannot Award an amount which is ruled out
    or prohibited by the terms of the agreement.
    Because of specific bar stipulated by the parties
    in the agreement, that claim could not be raised.
    Even if it is raised and referred to arbitration
    because of wider arbitration clause such claim
    amount cannot be awarded as agreement is
    binding between the parties and the arbitrator
    has to adjudicate as per the agreement…..

    (i) The arbitrator could not act arbitrarily,
    irrationally, capriciously or independently of the
    contract. A deliberate departure or conscious
    disregard of the contract not only manifests the
    disregard of his authority or misconduct on his
    part but it may tantamount to mala fide action.

    (j) The arbitrator is not a conciliator and cannot
    ignore the law or misapply it in order to do what
    he thinks just and reasonable; the arbitrator is a
    tribunal selected by the parties to decide the
    disputes according to law.”

    22. In a recent ruling in NTPC (supra), decided by a
    three Judge Bench of this Court, drawing strength
    from the decision in Kwality Manufacturing
    Corporation (supra), it has been held thus:

    “13. From the above pronouncements, and from

    Page 25 of 34

    Uploaded by SHEKHAR P. BARVE(HC00200) on Fri May 01 2026 Downloaded on : Sat May 02 05:40:51 IST 2026
    NEUTRAL CITATION

    C/FA/7110/1998 CAV JUDGMENT DATED: 01/05/2026

    undefined

    a catena of other judgments of this Court, it is
    clear that for the objector/appellant in order to
    succeed in their challenge against an arbitral
    award, they must show that the award of the
    arbitrator suffered from perversity or an error of
    law or that the arbitrator has otherwise
    misconducted himself. Merely showing that
    there is another reasonable interpretation or
    possible view on the basis of the material on the
    record is insufficient to allow for the
    interference by the Court [See State of U.P. v.
    Allied Constructions
    , (2003) 7 SCC 396;
    Ravindra Kumar Gupta and Company v. Union of
    India
    , (2010) 1 SCC 409; Oswal Woollen Mills
    Limited v. Oswal Agro Mills Limited
    , (2018) 16
    SCC 219].”

    [emphasis added]”

    8. Keeping in mind the aforesaid parameters, this Court
    proceeds to examine the plea advanced by the learned
    Advocate for the appellant. Learned Advocate Mr. Buch
    mainly argued that, in the absence of terms and conditions of
    passing the dispatch money earned by the FCI to the
    contractor in the contract executed between the parties with
    regard to the stevedoring, clearing, handling and transport
    contract, the learned Arbitrator committed a serious error in
    awarding dispatch money in favour of the contractor. He had
    further submitted that if the learned Arbitrator recorded
    findings beyond the terms and conditions of the contract, the
    award would be rendered as nullity. He had further submitted
    that the learned Arbitrator, in his findings, categorically held
    that there are no terms and conditions executed between the
    parties entitling the contractor to have benefit of dispatch
    money, yet, by taking recourse to the prevailing commercial

    Page 26 of 34

    Uploaded by SHEKHAR P. BARVE(HC00200) on Fri May 01 2026 Downloaded on : Sat May 02 05:40:51 IST 2026
    NEUTRAL CITATION

    C/FA/7110/1998 CAV JUDGMENT DATED: 01/05/2026

    undefined

    practice, the learned Arbitrator proceeded to award dispatch
    money to the contractor.

    9. Explaining the term “dispatch money,” learned Advocate
    Mr. Buch argued that the contract with the contractor is
    subsequent to a charter party agreement executed between
    the owner of the ship/vessel and the appellant, the Food
    Corporation of India (FCI). If the ship/vessel is alighted and
    offloaded within the stipulated time period stated in the
    charter agreement, the owner of the vessel would pay
    dispatch money to the appellant FCI, as these terms and
    conditions remained confined to the agreement between the
    owner of the vessel and the appellant FCI. He contended that,
    in the absence of contractual terms and conditions between
    the contractor and the FCI entitling the contractor to dispatch
    money, the contractor would not be legally entitled to claim
    dispatch money even if the contractor had completed his work
    before the time limit, which in turn enabled the FCI to earn
    dispatch money under the charter party agreement.

    10. In regard to aforesaid submissions of learned Advocate
    Mr. Buch, let refer the order passed in CMA No. 170 of 1984.
    Early offloading of the ship/vessel would permit owner to
    depart from the port, because of which, owner of ship/vessel
    will save port staying charge. To trace root of dispute, by the
    order in CMA No.170 of 1984, the learned Civil Court, in
    exercise of jurisdiction under Section 20 of the Act, directed
    the FCI to appoint an Arbitrator. That order has not been
    challenged. In an unnumbered paragraph at the bottom

    Page 27 of 34

    Uploaded by SHEKHAR P. BARVE(HC00200) on Fri May 01 2026 Downloaded on : Sat May 02 05:40:51 IST 2026
    NEUTRAL CITATION

    C/FA/7110/1998 CAV JUDGMENT DATED: 01/05/2026

    undefined

    portion of paragraph 4 of the said order, the learned Civil
    Court, while directing appointment of an Arbitrator to resolve
    the dispute between the FCI and the contractor, referred to
    the tender agreement and held that, though it does not speak
    about dispatch money earned by the claimant or as to who
    would get the benefit earned out of such dispatch money, if
    the defendant is liable for the demurrage for delayed
    execution of contract, they have an equal right to demand
    dispatch money earned by the other side due to efficiency on
    the part of the defendant. Treating this as a dispute between
    the parties, the learned Civil Court took the cue from the
    terms and conditions of the contract between the FCI and the
    contractor and held that the dispute is covered under the
    purview of the arbitration clause, and consequently ordered
    appointment of an Arbitrator. At the cost of repetition, it has
    to be observed that these findings have not been challenged,
    but rather accepted and as per order, Arbitrator was
    appointed.

    11. Looking to the history of the arbitration proceedings as
    stated hereinabove, this Court does not venture further into
    re-appreciating the same. The real dispute between the
    parties pertains to Claim No. 2, as prepared by the contractor
    and decided by the learned Arbitrator. Claim No. 2 and the
    award thereon reads as under:-

    “Claim No. 2)

    The claimants claim a sum of Rs. 15,78,681/68 on
    account of despatch money earned in early release of

    Page 28 of 34

    Uploaded by SHEKHAR P. BARVE(HC00200) on Fri May 01 2026 Downloaded on : Sat May 02 05:40:51 IST 2026
    NEUTRAL CITATION

    C/FA/7110/1998 CAV JUDGMENT DATED: 01/05/2026

    undefined

    11 Vessels arrived at Beli/Rozi Court during the
    contract period from 25.8.80 to 2418.82.

    Award No. 2)

    The claim is allowed to the extent of Rs. 13,65,352/52
    for the following reasons:-

    It is admitted position that the subject contract does
    not speak asito who will get the benefit earned out of
    despatch money. The Admittedly quantum of Rs.
    15,78,681/68 earned as despatch money against the
    subject contract is also not disputed as the 11 Vessels
    were discharged in a shorter time than the number of
    lay-days provided to the claimants contractor. As per
    the settled commercial practice, if the Charterer
    discharges the Vessels in a shorter time than is
    allowed to him by the lay-days, he may be entitled to
    despatch money. In the instant case the claimants
    contract was responsible for Stevedoring, Clearance,
    Handling and Transport of stores and if the despatch
    money is earned by his efficient efforts by discharing
    the Vessels in a shorter time than is allowed to him
    by the lay-days, the benefit of said despatch money
    earned shall go to the claimants, particularly for the
    reason that the claimants contractor was liable for
    any demurrage or warfage charges that may occur
    for payment by the Corporation to Railways, Court or
    any other party on account of the delay on their part
    in leading or unloading etc. beyond the free time
    allowed to them for the work under the terms of the
    contract. The claim is allowed to the extent of Rs.
    13,65,352/52 against the claim of Rs. 15,78,681/68
    for the reason that the respondents F.C.I. shall also
    be entitled to recover the balance amount of Rs.
    2,13,329/16 against their counter claims as
    mentioned below after adjusting the withheld amount
    of Rs. 44,015/95 as already stated in award against
    Claim No. 1) above.”

    12. It is the aforesaid finding that bothered the FCI. The first
    contention of learned Advocate Mr. Buch, that the reference,

    Page 29 of 34

    Uploaded by SHEKHAR P. BARVE(HC00200) on Fri May 01 2026 Downloaded on : Sat May 02 05:40:51 IST 2026
    NEUTRAL CITATION

    C/FA/7110/1998 CAV JUDGMENT DATED: 01/05/2026

    undefined

    which was made beyond the terms and conditions of the
    agreement, fails to sustain on the ground that the order
    passed by the learned Civil Court in CMA No. 170 of 1984
    directing appointment of an Arbitrator has not been
    challenged at any point of time; rather, it has been accepted
    by the FCI and without hesitation, participated in the arbitral
    proceedings by raising counter claims. FCI having obtained an
    adverse order from the learned Arbitrator, confirmed by the
    learned Civil Court, the FCI cannot now contend that the
    terms and conditions of the agreement did not permit the
    learned Civil Court to appoint an Arbitrator.

    13. It is an uncontroverted fact that 11 vessels were
    discharged in a shorter time period than the number of lay
    days provided to the contractor, having been stevedored and
    offloaded before the date stipulated by the FCI. Adopting the
    practice prevailing in commercial transactions, the learned
    Arbitrator held that if the stevedore discharged a vessel
    within a shorter time period than the lay days allowed to him,
    the charterer would, under the charter party agreement
    between the owner of the vessel and the charterer, be entitled
    to dispatch money. In the present case, the charterer, i.e., the
    FCI, earned the dispatch money. The contract was in respect
    of stevedoring, clearing, handling and transport of stores, and
    the contractor was responsible for the performance thereof.

    14. If the charterer, i.e., the FCI, was required to adhere to
    the time limit for completion of stevedoring, clearing,
    handling and transport in order to earn dispatch money, the

    Page 30 of 34

    Uploaded by SHEKHAR P. BARVE(HC00200) on Fri May 01 2026 Downloaded on : Sat May 02 05:40:51 IST 2026
    NEUTRAL CITATION

    C/FA/7110/1998 CAV JUDGMENT DATED: 01/05/2026

    undefined

    corollary follows that the contractor who actually performed
    the said work would equally be entitled to earn dispatch
    money if he completed the work within the time limit
    stipulated by the charterer. In other words, if the contractor
    completed the work of stevedoring, clearing, handling and
    transport of the stores within the time limit specified by the
    charterer, the contractor would be entitled to receive dispatch
    money to the extent that the charterer received dispatch
    money. This is just, fair and equitable.

    15. The charter party agreement between the owner of the
    vessel and the FCI, more particularly Clauses 35,37 and 42,
    contemplates earning of dispatch money. If discharge of the
    vessel is completed before the stipulated time, and liability to
    pay demurrage if the discharge of the vessel is not completed
    within the lay days. The agreement between the contractor
    and the FCI does not speak to the payment of dispatch money,
    as has consistently been held by the competent Civil Court
    and the learned Arbitrator. It is evident that while the FCI
    retained the benefit of earning dispatch money arising under
    the charter party agreement, it cast the liability of demurrage
    upon the contractor. Clause 49 of the agreement between the
    FCI and the contractor expressly provides that, in case the
    contractor fails to complete the work within the lay days
    provided by the FCI, the contractor would be liable to pay
    demurrage and other consequential costs. This is unfair
    practice and rules against equity. FCI cannot observe double
    standard The FCI on one hand, retains clause to earn benefit
    of dispatch money, which could only be achieved by the

    Page 31 of 34

    Uploaded by SHEKHAR P. BARVE(HC00200) on Fri May 01 2026 Downloaded on : Sat May 02 05:40:51 IST 2026
    NEUTRAL CITATION

    C/FA/7110/1998 CAV JUDGMENT DATED: 01/05/2026

    undefined

    contractor by offloading ship/vessel before lay days, on the
    other hand, cannot pass liability of demurrage which could be
    occurred due to non-observance of offloading within the lay
    days. The FCI thus, either can retain both; benefit of earning
    of dispatch money and risk of demurrage or can pass both to
    the contractor. As far as passing of the benefit of earning
    dispatch money is concerned, the FCI, by executing contract,
    can retain same share.

    16. The FCI cannot be permitted to blow hot and cold. If the
    FCI earned dispatch money on account of the early discharge
    of the vessel, it is obligated to pass the same or part thereof to
    the contractor. As observed hereinabove, the FCI, instead of
    providing for payment of dispatch money to the contractor,
    retained it for itself by not incorporating any clause in the
    agreement in that regard, while simultaneously incorporating
    a liability clause, i.e., a demurrage clause, upon the contractor
    in case the vessel was not discharged within the lay days. The
    learned Arbitrator rightly recorded the unfairness on the part
    of the FCI and passed the award in favour of the contractor.
    The said award was thereafter subjected to scrutiny before
    the learned Civil Court, which did not find any compelling
    reason to set aside the impugned award and has accordingly
    made the award a decree of the court. This Court, exercising
    jurisdiction under Section 39 of the Act, does not find any
    reason to interfere with the impugned order.

    17. In the case of Parasa Raja Manikyala Rao And Anr vs
    State Of A.P
    reported in AIR 2004 SC 132, the Hon’ble

    Page 32 of 34

    Uploaded by SHEKHAR P. BARVE(HC00200) on Fri May 01 2026 Downloaded on : Sat May 02 05:40:51 IST 2026
    NEUTRAL CITATION

    C/FA/7110/1998 CAV JUDGMENT DATED: 01/05/2026

    undefined

    Supreme Court has observed and held as under:

    “…Each case, more particularly a criminal case
    depends on its own facts and a close similarity
    between one case and another is not enough to
    warrant like treatment because a significant detail
    may alter the entire aspect. In deciding such cases,
    one should avoid the temptation to decide cases (as
    said by Cordozo) by matching the colour of one case
    against the colour of another. To decide therefore on
    which side of the line a case falls, the broad
    resemblance to another case is not at all decisive.”

    17.1 In expose of aforesaid law on binding precedent, the
    authorities relied on by the learned advocate for the appellant
    would not be of any assistance to the case of the appellant, as
    they are on different facts.

    18. Before parting with this judgment, worthy assistance
    may be drawn from the judgment of the Hon’ble Apex Court in
    the case of Himachal Pradesh State Electricity Board
    Versus R.J.Shah And Company , reported in (1999) 4
    SCC 214, wherein the Hon’ble Apex Court, in paragraph 26,
    laid down the relevant position of law, which is adopted and
    applied in the present case.

    “26. The decision in Associated Engineering Co. case
    relied upon by Sh. Maninder Singh does not in any
    way persuade us to take a view different than the
    view arrived at by the High court. At page 103
    Thommen, J. speaking for the court observed as
    follows:

    “The arbitrator cannot act arbitrarily,
    irrationally, capriciously or independently of
    the contract. His sole function is to arbitrate
    in terms of the contract. He has no power

    Page 33 of 34

    Uploaded by SHEKHAR P. BARVE(HC00200) on Fri May 01 2026 Downloaded on : Sat May 02 05:40:51 IST 2026
    NEUTRAL CITATION

    C/FA/7110/1998 CAV JUDGMENT DATED: 01/05/2026

    undefined

    apart from what the parties have given him
    under the contract. If he has travelled outside
    the bounds of the contract, he has acted
    without jurisdiction. But if he has remained
    inside the parameters of the contract and has
    construed the provisions on the contract, his
    award cannot be interfered with unless he has
    given reasons for the award disclosing an
    error apparent on the face of it.”

    Applying the ratio of the present case it is not
    possible to say that the arbitrator in the
    present case travelled outside the bounds of
    the contract. Correspondence exchanged
    between the parties prior to the making of the
    reference shows that the arbitrators were
    called upon to construe the contract in order
    to determine whether the contractor was
    entitled to claim revision of rates and if so
    what should be the revised rates. The
    construction placed on contract by the
    contract by the contractor cannot be said to
    an implausible one. Even if the arbitrators
    construed the terms of the contract
    incorrectly it cannot be said that the award
    was in excess of their jurisdiction. Their
    jurisdiction clearly was to construe the terms
    of the contract and their decision thereon is
    final and binding on the parties.”

    19. For the foregoing reasons, present First Appeal fails and
    stands dismissed. Notice discharged. Interim relief, if any,
    stands vacated forthwith.

    20. Registry is directed to return back the R & P, if any, to
    the concerned Court forthwith.

    (J. C. DOSHI,J)
    SHEKHAR P. BARVE

    Page 34 of 34

    Uploaded by SHEKHAR P. BARVE(HC00200) on Fri May 01 2026 Downloaded on : Sat May 02 05:40:51 IST 2026



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here