Debashis Ghosh vs Union Of India on 2 April, 2026

    0
    14
    ADVERTISEMENT

    Calcutta High Court (Appellete Side)

    Debashis Ghosh vs Union Of India on 2 April, 2026

                                                                       2026:CHC-AS:540
    
    
    
    
                      IN THE HIGH COURT AT CALCUTTA
                    CRIMINAL REVISIONAL JURISDICTION
                               APPELLATE SIDE
    
    
         Present:
    
         The Hon'ble Justice Ajay Kumar Gupta
    
                              C.R.R. 426 of 2022
    
                               Debashis Ghosh
                                      Versus
                                Union of India
    
    
    
    
         For the Petitioner       :      Mr. Syed Shahid Imam, Adv.
                                         Mr. Md. Khairul, Adv.
    
         For the C.B.I.           :      Mr. Amajit Dey, Adv.
                                         Mr. Sukanta Chakraborty,     Adv.
    
    
    
         Heard on                 :      06.02.2026
    
         Judgment on              :      02.04.2026
    
    
         Ajay Kumar Gupta, J.:-
    
    1.   The instant Criminal Revisional application under Section 401 read
    
         with Section 482 of the Code of Criminal Procedure, 1973 (in short
    
         'Cr.P.C.') has been preferred by the petitioner challenging the
    
         correctness, legality and propriety of an order dated 24.09.2021
                                        2
    
                                                                            2026:CHC-AS:540
    
    
    
    
         passed by the Learned Special Judge, (CBI) Court No. 1, Bichar
    
         Bhawan Kolkata in SPL Case No. 04 of 2016 arising out of RC.
    
         0102013A0008      of   2013    dated      30.03.2013   under   Sections
    
         120B/420/468/471 of the Indian Penal Code, 1860 (in short 'IPC')
    
         and under Sections 13(2)/13(1)(d) of the Prevention of Corruption
    
         Act, 1988. By the order impugned, the Trial Court rejected the prayer
    
         for discharge from the case involved.
    
         FACTS OF THE CASE: -

    2. The essential facts, leading to the filing of this instant Criminal

    Revisional application, are as under: –

    SPONSORED

    a. The CBI/SPE/ACB/Kolkata registered an F.I.R., being No. RC

    0102013A0008 of 2013 on 30.03.2013 on the basis of source

    information alleging therein that Abhijit Gupta, the then Section

    Engineer, S. E. Rly, Kharagpur and others have given undue

    favour to the accused Private Firms M/S Efftronics Systems Pvt.

    Ltd, M/S Aster Electrosoft Pvt. Ltd and M/S Ambitious

    Enterprises, by allowing these firms to install Electronic Train

    Indicator Boards (ETIBs) at the Andul-Baruia-Deulti stations,

    Sankrail-Nalpur-Jakpur stations, and Tamluk-Belda-Jhargram-

    Digha stations, all under the Kharagpur division.

    b. Even without the integration of ETIBs with the Existing Public

    Address systems and the incomplete work, the said officials of S.E.
    3

    2026:CHC-AS:540

    Railway released the full payment along with security deposit and

    performance guarantee to the accused contractors, thereby

    committing offences U/S 120B r/w 420, 468 and 471 of IPC and

    Sections 13(2) r/w 13(1) (d) of the Prevention of Corruption Act . As

    a result, the S.E. Railway suffered a pecuniary loss of Rs.

    12,44,762.34/-.

    c. After completion of the investigation, a charge sheet, CS No.

    40/2014 on 31.12.1014 was filed against (i) Abhijit Gupta, the

    then SSE/Tele/Wireless KGP, S.E. Railways, (ii) Sri Salil Ghosh,

    partner of M/s Ambitious Enterprise Pvt. Ltd., (iii) Sri Subrata

    Mukherjee, constituted Attorney of M/s Ambitious Enterprises

    Pvt. Ltd., and (iv) Debashis Ghosh, the then DSTE, KGP, S.E. Rly,

    alleging the commission of offences u/s 120B/420 IPC and

    Section 13(1)(d) of the Prevention of Corruption Act.

    d. The allegations against the petitioner in the instant case are that

    he abused his official position and recorded inflated

    measurements in the MB (Measurements Book), and further

    certified the same. On the basis of the false measurements, the

    contractor, M/s Ambitious Enterprises Pvt. Ltd., received inflated

    payments for his bills, resulting in wrongful loss to the Railways.

    e. It was also alleged that the Railway had issued a work order to

    M/s Ambitious Enterprises at substantially higher rates compared
    4

    2026:CHC-AS:540

    to Tata Nagar of CKP division. An excess amount was paid to the

    firm (Contractor) due to wrong measurement of trenching,

    subsequently correlated with data cable, power cable, HDPE pipe,

    etc.

    f. The tender was opened on 24.07.2009, and members had put their

    initials on the tender offers. Thereafter, on 28.07.2009, a

    summary was prepared and all offers/tenders, along with the

    summary, were sent to the tender section at Kharagpur for the

    preparation of a comparative statement and briefing note. A brief

    note and comparative statements were prepared on 10.08.2009

    and sent to the Finance Department for vetting on the same date.

    g. The detailed estimate was technically sanctioned on 10.08.2009,

    which was before the issuance of LOA (Letter of Acceptance) dated

    01.12.2009, in favour of M/s. Ambitious Enterprises Pvt. Ltd.

    h. The tender Committee recommended acceptance of the offer of M/s

    Ambitious Pvt. Ltd. for supply, installation, and commissioning of

    ETIB at the aforesaid stations, and the same was accepted by the

    Tender Accepting Authority. Accordingly, an LOA and Work Order

    were issued for the aforesaid work in question and given to M/s

    Aster Electrosoft Pvt. Ltd. Thereafter, a contract/agreement was

    signed between the S. E. Railways and the contractors for

    executing the aforesaid work.

    5

    2026:CHC-AS:540

    i. It is the contention of the petitioner that he had no role to play in

    the initial planning, tendering and receipt of material and payment

    thereof. He joined as a Divisional Signal & Telecom Engineer/Tele-

    maintenance (DSTE), Kharagpur on 6th January, 2010. He did not

    know such facts and circumstances of work orders.

    j. The allegation against the Petitioner was that the cost of single-line

    double-face (Trilingual) train Arrival/Departure Display Boards as

    per RDSO specification no. RDSO/SPN/TC/61/2007 (Revision

    2.0) was quoted Rs. 2,80,000/- at Chakradharpur Division of

    South Eastern Railway, whereas for the same item, a rate of Rs.

    5,05,000/- was quoted at Kharagpur Division.

    k. In the above premise, the petitioner finds it necessary to mention

    that while making their recommendation, it is the responsibility of

    the Tender Committee to examine all relevant factors, such as the

    existing workload on the lowest two or three tenders, their

    capacities to execute further work and also whether the rates

    quoted are reasonable and workable.

    l. The petitioner was not present while dealing with the tender or

    completion of work orders and had no role to play in the initial

    planning, tendering, receipt and material and payment thereof. In

    view of the aforesaid facts and circumstances, the petitioners
    6

    2026:CHC-AS:540

    stated that the instant proceeding is an abuse of the process of

    law. Hence, this application.

    SUBMISSION ON BEHALF OF THE PETITIONER: –

    3. Learned counsel appearing on behalf of the petitioner submitted that

    the petitioner was a DSTE. His work does not extend to setting up,

    commissioning, supervising, or maintaining ETIBs. The Petitioner is

    under the technical Control of Sr. DSTE and works on the

    instructions of the Senior DSTE. Nearly 90 per cent of the payments

    had already been made in respect of the said schedule work before

    the Petitioner joined.

    4. It was submitted that the final bill, which came up during the

    Petitioner’s tenure, is the subject matter of this case, which

    establishes that the petitioner had no role in the initial planning,

    tendering & receipt of material and payment thereof.

    5. The contention of the Petitioner is that the case was initiated solely

    on the allegation that the Railways had issued a work order to M/s.

    Ambitious Enterprises Pvt. Ltd. at rates substantially higher than

    those quoted at Tatanagar, under the Chakradharpur (CKP) Division.

    However, upon investigation, the Investigating Authority recorded in

    the charge sheet as follows:

    “The cost of single line double face (Trilingual) train
    arrival/departure display board as per RDSO Specification
    No.RDSO/SPN/TC/61/2007 (Revision 2.0) was quoted
    7

    2026:CHC-AS:540

    Rs.2,80,000/-at Chakradharpur Division of South Eastern
    Railway whereas for the same item rate of Rs.5,05,000/- was
    quoted at Kharagpur Division. But investigation also remarked
    that in Kharagpur there was a condition in the Notice Inviting
    Tender that the times has to be procured from RDSO approved
    source, which is also one of the reasons for the variation in price
    of Chakradharpur Division and Kharagpur Division.”

    6. It is, therefore, evident that the very basis on which the FIR was

    lodged stood explained during investigation. The Investigating Agency

    itself found that the variation in price was attributable to the tender

    condition mandating procurement from RDSO-approved sources, and

    consequently failed to substantiate the allegations against the

    petitioner. The foundational premise of the case thus stood

    demolished.

    7. Despite such clarification, which goes to the root of the matter, the

    Investigating Agency proceeded with the investigation and ultimately

    filed a charge sheet against the petitioner. This action, in the absence

    of any incriminating material, appears to be arbitrary and amounts to

    an abuse of process, giving rise to a case of wrongful and malicious

    prosecution instituted without good faith.

    8. Finally, it was submitted that the Petitioner was not a named accused

    in the FIR; he has been falsely implicated in the present case, though

    he had no role to play in any physical checking, testing and
    8

    2026:CHC-AS:540

    measuring of the cable. All measuring, testing and checking were

    executed before he joined as DSTE.

    9. Therefore, the proceeding against the present petitioner is an abuse

    of the process of law. To secure the ends of justice, it requires him to

    be discharged by quashing of the proceedings in so far as the

    petitioner is concerned; otherwise, the petitioner would greatly suffer

    and be prejudiced.

    SUBMISSION ON BEHALF OF THE OPPOSITE PARTY/CBI: –

    10. Learned counsel Mr. Dey, representing the CBI, vehemently opposed

    the prayer of the petitioner and further submitted that the Petitioner

    had played a role in the offence as alleged. During the investigation, it

    was revealed that after finding the inflated payment with less work on

    the ground, the S. E. Rly. recovered an amount of Rs. 10,12,194.67/-

    from M/S Ambitious Enterprises Pvt. Ltd. for 2 work orders vide

    contract Agreement dated 20.03.2010, in pursuance of Para 51 (2) of

    General Conditions of Contract Vol-2-2001, which deals with post-

    payment audit. The Petitioner had certified the completion of the

    aforesaid work. Rs. 2,32,567.67/-, along with the pending bills of the

    aforesaid contractor is yet to be recovered.

    11. It was further submitted that the petitioner was responsible for

    conducting a test check of the work. He has also certified the

    Measurement books. The bill was submitted on 03.02.2010. The final
    9

    2026:CHC-AS:540

    bill was released on 04.08.2010 during his tenure; as such, the

    petitioner was involved in the offence punishable under section U/S

    120B read with 420, 468 and 471 of IPC and Sections 13(2) r/w 13(1)

    (d) of the Prevention of Corruption Act.

    12. It was further submitted that during the course of fresh

    measurements, it was revealed that the measurements, as recorded

    in the MB, were false and inflated. These inflated measurements were

    recorded in the MB by accused Shri Abhijit Gupta (A-1), which was

    certified to be correct by accused Shri Debasish Ghosh and

    countersigned by Sh. M. Santosh Kumar, representative of M/S Aster

    Electrosoft Pvt Ltd, had claimed bills against these inflated

    measurements in the MB; as such, the petitioner is required to face

    trial to unearth the truth. Therefore, the present application is liable

    to be dismissed.

    DISCUSSIONS, ANALYSIS AND CONCLUSION OF THIS COURT: –

    13. Having heard the learned counsels appearing on behalf of the

    respective parties and upon perusal of the records, especially the

    complaint and charge sheet submitted in RC0102013A0008 dated

    30/03/2013 against Shri Abhijit Gupta, the then Senior Section

    Engineer/Tele/Wireless, Kharagpur Division, South Eastern Railway,

    Kharagpur and others under sections 120B/420 of the IPC and

    Section 13(2) r/w 13(1) (d) of PC Act, 1988, this court finds that the
    10

    2026:CHC-AS:540

    allegations primarily relate to issuance of work orders for the supply

    and installation of ETIBs at various stations under Howrah-

    Kharagpur-Digha section, at substantially higher rates than those

    prevailing in a comparable project executed shortly prior in the

    Chakradharpur Division, S.E. Railway. It appears from the record

    that M/s Ambitious Enterprises, had executed similar work at

    Tatanagar, Rourkela and Jharsuguda stations at an accepted rate of

    Rs. 71, 17, 349/-, whereas the estimate prepared by Pradip Kumar

    Prasad and the present accused Abhijit Gupta for the Howrah-

    Kharagpur-Digha section was Rs. 92,01,836/-, thereby giving rise to

    the allegation of inflated estimation and possible financial

    irregularity.

    14. During the investigation, it has been revealed that the petitioner was

    also very much involved in the measurement process, and the

    measurements recorded in the MB were false and inflated. He should

    have raised objection before final payment if there was false and

    inflated measurement recorded in the MB. The said inflated

    measurements were recorded by accused Shri Abhijit Gupta (A-1)

    which were subsequently certified as correct by the present

    petitioner, Shri Debasish Ghosh, on the basis of which, bills were

    raised and payments claimed.

    11

    2026:CHC-AS:540

    15. The principal contention of the petitioner is twofold: first, that he had

    no role in the foundational aspects of the contract such as tendering,

    rate fixation, or execution; and secondly, that the very basis of the

    FIR, namely the alleged disparity in rates between Kharagpur

    Division and Chakradharpur Division, stood satisfactorily explained

    during the investigation itself. In this regard, it is significant that the

    charge sheet records that the variation in price was attributable to a

    specific tender condition requiring procurement from RDSO-approved

    sources. This clarification materially weakens the foundational

    allegation of undue favour or arbitrary rate fixation.

    16. However, the scope of the present proceeding cannot be confined

    merely to the validity of the initial tender process. The prosecution

    has specifically attributed an active role to the petitioner in certifying

    measurements and facilitating the release of the final bill. The CBI

    has specifically alleged that the measurements recorded were false

    and inflated, and that the petitioner certified those measurements.

    Based on these certified measurements, payments were made to the

    contractor.

    17. This Court notes that certifying measurements is an important

    responsibility. It is not just a routine task, because such certification

    directly affects how much money is paid. If the measurements were

    indeed inflated and were wrongly certified, it may amount to an
    12

    2026:CHC-AS:540

    offence. During investigation, it established prima facie case against

    the Petitioner.

    18. In such circumstances, this Court is not persuaded to hold that the

    continuation of the proceedings amounts to an abuse of the process

    of law. Involvement of the accused in the allegations requires him to

    face trial to unearth the truth after recording evidence. Therefore, the

    application found to be devoid of merit and requires dismissal.

    19. Accordingly, CRR 426 of 2022 is, thus, dismissed. Connected

    applications, if any, are also, thus, disposed of.

    20. Let a copy of this Judgment and Order be sent to the Learned Court

    below for information.

    21. Interim order, if any, stands vacated.

    22. All parties will act on the server copies of this Judgment and Order

    uploaded on the official website of this Hon’ble High Court.

    23. Urgent photostat certified copy of this Judgment and Order, if applied

    for, is to be given as expeditiously to the parties on compliance of all

    legal and necessary formalities.

    (Ajay Kumar Gupta, J)

    P. Adak (P.A.)



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here