Cipior Organics Pvt. Ltd vs M/S. Bhavanam Estate Pvt. Ltd on 7 July, 2026

    0
    5
    ADVERTISEMENT

    Telangana High Court

    Cipior Organics Pvt. Ltd vs M/S. Bhavanam Estate Pvt. Ltd on 7 July, 2026

           THE HIGH COURT FOR THE STATE OF TELANGANA AT
                                   HYDERABAD
    
                THE HON'BLE JUSTICE B.R.MADHUSUDHAN RAO
                            CCCA.NO.96 OF 2019
                                    AND
               I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019
    
                                Dated: 07.07.2026
    
    CCCA.No.96 of 2019 and CCCA.No.116 of 2019:
    
    Between:
    Cipior Organics Private Limited,
    A Company registered under Companies Act,
    Represented by its Authorised representative,
    Sri N.N.Devarajan S/o. Late Sri N.S.Natarajam,
    Aged 50 years, R/o C/o.6-3-348,
    Mid Town Complex, B-Block, Road No.1,
    Banjara Hills, Hyderabad 500034.               ... Appellant - Plaintiff
                                        And
    1.M/s.Bhavanam Estate Private Limited,
      A Company incorporated under companies Act,
      Plot No.15, Harita Apartments,
      Kantisikhara Building Road,
      Somajiguda, Hyderabad,
      Represented by its M.D. B.Govind Reddy
    2. Mr.Ravendra Thaper (since Died per Lr's) and three others.
                                                 ... Respondents - Defendants
    [Respondent Nos.3 to 5 - defendant Nos.3 to 5 are brought on record as LRs of
    respondent No.2 - defendant No.2 as per orders in I.A.No.443 of 2016, dated
    20.09.2016.]
                                          2/63
                                                                         CCCA.NO.96 OF 2019
                                                                                       AND
                                                I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019
    
    
    
                               COMMON JUDGMENT
    
    

    1.1 These memorandum of appeals are filed under Section 96 r/w

    Order XLI Rule 1 r/w Section 151 of Civil Procedure Code (for short

    SPONSORED

    CPC‘) assailing the judgment and decree and the counter claim passed

    by the learned V Senior Civil Judge, City Civil Court, Hyderabad, in

    O.S.No.1736 of 2006 dated 17.12.2018.

    1.2 Notice got issued to respondent No.1 in both the appeals is served

    but none appeared.

    CCCA.No.96 of 2019:

    2.1 This appeal is filed by the appellant – plaintiff aggrieved in

    allowing the counter claim filed by the respondent Nos.3 to 5 –

    defendant Nos.3 to 5, wherein they were declared as owners of the

    counter claim schedule property and that the appellant – plaintiff was

    directed to vacate and handover the vacant possession of the counter

    claim schedule property to them within three months from the date of

    decree [17.12.2018].

    CCCA.No.116 of 2019:

    2.2 This appeal is filed by the appellant – plaintiff aggrieved by the

    judgment and decree in O.S.No.1736 of 2006 dated 17.12.2018 passed

    by the learned V Senior Civil Judge, City Civil Court, Hyderabad,

    wherein the suit filed by the appellant – plaintiff is dismissed without

    costs.

    3/63

    CCCA.NO.96 OF 2019
    AND
    I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019

    3. For the sake of convenience, the parties will be hereinafter

    referred to as plaintiff and defendants as arrayed in O.S.No.1736 of

    2006.

    4.1 Plaintiff has filed suit for declaration and permanent injunction

    under Order VII Rule 1 r/w Section 26 of CPC initially against defendant

    Nos.1 and 2.

    4.2 The prayer in the suit is:

    (i) A decree of declaration be passed in favour of the plaintiff and against

    defendant Nos.1 and 2 declaring that the plaintiff is the absolute owner

    of the suit schedule property bearing flat No.103, ground floor, Riviera

    Apartments, in premises No.6-3-347/9, Dwarkapuri Colony, Panjagutta,

    Hyderabad admeasuring 1650 sq.ft of plinth area along with

    proportionate undivided share in the land admeasuring 50 sq.yds

    equivalent to 41.80 sq.mts,

    (ii) permanent injunction be granted in favour of the plaintiff and against

    the defendant Nos.1 and 2 restraining them, their agents, servants,

    henchmen etc., from interfering in the peaceful possession of the

    plaintiff in respect of the suit schedule property in any manner.
    4/63

    CCCA.NO.96 OF 2019
    AND
    I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019

    Suit Schedule Property:

    5. Flat No.103, ground floor, Riviera Apartments, in premises No.6-

    3-347/9, Dwarkapuri Colony, Panjagutta, Hyderabad admeasuring

    1650 sq.fts of plinth area along with proportionate undivided share in

    the land admeasuring 50 sq.yds equivalent to 41.80 sq.mts are bounded

    by North: open area facing 40′ wide road, South: Open area, East: Flat

    No.104 and West: Flat No.102.

    6. It is stated in the plaint that defendant No.1 is the developer of the

    property bearing premises No.6-3-347/9 situated at Panjagutta,

    Hyderabad, wherein Riviera Apartments has been constructed. As per

    the practice prevailing in 1994 – 1995, defendant No.1 has executed

    registered sale deeds in respect of the undivided share of land

    commensurate to the flat area in favour of the purchasers of the various

    flats in the complex. Plaintiff originally agreed to purchase the flat in the

    proposed construction of Riviera Apartments in February, 1994. A

    registered sale deed was executed in favour of the plaintiff

    on 23.07.1994 by the defendant No.1 for a valid sale consideration for

    undivided 1/40th share in 2000 sq.yds of land i.e., 50 sq.yds equivalent

    to 41.80 sq.mts within the premises No.6-3-347/9. Plaintiff has also

    obtained an agreement for construction dated 18.02.1994 from

    defendant No.1 as it is already agreed to purchase the flat in the
    5/63
    CCCA.NO.96 OF 2019
    AND
    I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019

    proposed complex. Plaintiff has paid the total consideration on different

    dates to defendant No.1 and he issued various receipts to that effect.

    Defendant No.1 did not complete the construction as agreed. Originally

    in the construction agreement flat No.002 was mentioned, but later on it

    was confirmed that it is flat No.103 [suit schedule flat]. Defendant No.1

    and its directors were trying to bring third parties to the property,

    having aggrieved plaintiff was constrained to file suit in O.S.No.2288 of

    2005 against defendant No.1 and its directors on the file of II Senior

    Civil Judge, City Civil Court, Hyderabad. After filing the said suit there

    were discussions and deliberations and defendant No.1 and its directors

    confirmed that they shall not interfere further with the possession of the

    plaintiff over the suit flat. After the construction is completed plaintiff

    has let out the flat to M/s. Consortium Management Services Private

    Limited in the month of June, 2006. Plaintiff surprised to know about

    the issuance of notice by defendant No.2 on 07.10.2006 directly to the

    tenant of the plaintiff. Plaintiff has issued reply on 12.10.2006 directly

    to defendant No.2 and prayed to decree the suit as prayed for.

    7. Defendant No.1 remained ex-parte before the Trial Court.

    8. Defendant No.2 filed written statement on 08.12.2006 and

    contended that he has purchased the suit schedule flat under a

    registered sale deed bearing document No.1282 of 2002 dated
    6/63
    CCCA.NO.96 OF 2019
    AND
    I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019

    08.07.2002, from defendant No.1. Defendant No.1 company has issued

    delivery of possession letter dated 08.07.2002 confirming the delivery of

    possession of the said flat to him. After taking possession of the said

    flat, he locked the said premises and left to Mumbai. In the first week of

    August 2006, he came to Hyderabad and was surprised that the suit

    schedule flat was in occupation of M/s.Consortium Management

    Services Private Limited, he made his best efforts to get in touch with

    defendant No.1 to know as to who has inducted the said company into

    the suit schedule flat and thereafter he got issued legal notice on

    07.10.2006 to the said company demanding to vacate and handover the

    possession of the flat. Plaintiff is nothing to do with the suit schedule

    flat and the documents filed by them do not relate to the said flat and

    they filed the suit only to grab his flat and prayed to dismiss the same.

    9. The learned Trial Court basing on the pleadings of the parties has

    framed the following issues:

    1. Whether plaintiff is entitled for decree of declaration as prayed

    for?

    2. Whether plaintiff is entitled for injunction as prayed for?

    3. To what relief?

    10. Chief executive officer of the plaintiff has filed his chief evidence

    affidavit on 15.04.2010 and Exs.A1 to A38 were marked on 10.08.2010.
    7/63

    CCCA.NO.96 OF 2019
    AND
    I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019

    When the suit was coming up for cross examination of PW1, learned

    counsel for defendant No.2 before the Trial Court has filed a memo on

    18.02.2016 stating that defendant No.2 died on 03.06.2012. Defendant

    Nos.3 to 5 came on record as LRs of defendant No.2. Plaintiff has filed

    his amended plaint on 03.11.2016. On 09.11.2016 defendant No.5 has

    filed adoption memo before the learned Trial Court adopting the written

    statement filed by defendant No.2. On 07.12.2016 defendant No.3 filed

    adoption memo adopting the written statement of defendant No.2. On

    22.12.2016 defendant No.4 filed adoption memo adopting the written

    statement of defendant No.2.

    11. Thereafter the suit was posted for cross examination of PW1

    through commissioner. Plaintiff was cross examined by the learned

    counsel for defendant Nos.3 to 5 on 22.02.2017 and 28.02.2017,

    thereafter the advocate commissioner has filed his report on

    01.03.2017. PW2 was examined on 29.06.2017, through him Exs.A39 to

    A104 are marked and an advocate commissioner is appointed to record

    the cross examination of PW2 by learned counsel for defendant Nos.3 to

    5. PW2 was cross examined on 04.08.2017. On 08.08.2017, advocate

    commissioner has filed his report, on which date the evidence of the

    plaintiff is closed and the suit is posted for defendants’ evidence on

    02.08.2017 and 30.08.2017. On 30.08.02017, defendant Nos.3 to 5
    8/63
    CCCA.NO.96 OF 2019
    AND
    I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019

    have filed an application to amend the written statement. The

    application filed by defendant Nos.3 to 5 seeking leave of the Court to

    file additional written statement and counter claim was returned and

    thereafter it is resubmitted, which is numbered as I.A.No.912 of

    2017. On 29.01.2018, I.A.No.912 of 2017 came to be allowed permitting

    defendant Nos.3 to 5 to file additional written statement with counter

    claim.

    12. Defendant Nos.3 to 5 have filed their additional written statement

    separately along with counter claim. In the additional written statement

    defendant Nos.3 to 5 stated that defendant No.2 died on 03.06.2012 and

    their mother Urmila Thapar also died on 04.06.2011, leaving behind

    defendant Nos.3 to 5 as successors and legal heirs of suit schedule flat

    and they were brought on record as LRs of defendant No.2 vide orders in

    I.A.No.443 of 2016 dated 20.09.2016. It is further stated in the

    additional written statement and counter claim of defendant Nos.3 to 5

    that they succeeded to the suit schedule property and sought to declare

    them as absolute owners of flat No.103, ground floor of Riviera

    apartments admeasuring 1800 sq.fts in premises No.6-3-347/9,

    situated at Punjagutta, Hyderabad and consequently prayed for an order

    of delivery of the property to defendant Nos.3 to 5 by the plaintiff and to

    prevent the multiplicity of cases on the same subject matter. In the
    9/63
    CCCA.NO.96 OF 2019
    AND
    I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019

    cause of action paragraph they have shown the dates as 03.06.2012

    when defendant No.2 died, 04.06.2011 when their mother Urmila

    Thapar died, on 20.09.2016 when the orders in I.A.No.443 of 2016 were

    passed and on 24.10.2016 when the plaintiff has filed amended fair

    copy of the plaint.

    13. The counter claim schedule property is flat No.103, ground floor of

    Riviera apartments admeasuring 1800 sq.fts carpet area excluding

    common area and balconies along with 1/40th or 50 sq. yds, whichever

    is high in 2000 sq.yds, equivalent to 50 sq.yds in premises municipal

    bearing No.6-3-347/9 situated at Punjagutta, Hyderabad, bounded

    by North: open facing to 40 ft wide road, South: open and corridor, East:

    flat No.104 and West: flat No. 102.

    14. Plaintiff has filed his written statement to the counter claim filed

    by defendant Nos.3 to 5 denying the allegations and further contended

    that the counter claim filed by them is barred by limitation.

    15. Basing on the additional pleadings, the learned Trial Court has

    framed three additional issues, which are as under:

    1. Whether defendant Nos.3 to 5 are entitled for a declaration that

    they are the owners of the suit/counter claim schedule

    property?

    10/63

    CCCA.NO.96 OF 2019
    AND
    I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019

    2. Whether defendant Nos.3 to 5 are entitled for possession of the

    suit/counter claim schedule property?

    3. Whether the counter claim of defendant Nos.3 to 5 is within

    limitation?

    16. The learned Trial Court after framing the additional issues on

    12.06.2018 has observed in the proceeding sheet as under:

    After closure of the evidence of the plaintiff and at the stage the defendant evidence, D3
    to D5 have come up with counter claim. Hence, it is necessary to give an opportunity to
    the plaintiff to produce further evidence, if any, touching the counter claim of D3 to D5.
    Therefore, for further evidence of the plaintiff if any, call on 18.06.2018.

    17. On 18.06.2018 learned counsel for the plaintiff before the trial

    Court has filed a memo reserving the right of the plaintiff to lead

    rebuttal evidence after the evidence of defendant Nos.3 to 5 which was

    granted by the learned Trial Court.

    18. Defendant No.4 is examined as DW1 on 13.07.2018, through her

    Exs.B1 to B8 were marked, on the same day she was cross examined by

    the learned counsel for the plaintiff before the Trial Court. On

    20.07.2018 further evidence of the defendant Nos.3 to 5 was closed and

    it was posted for the rebuttal evidence of the plaintiff. On 07.08.2018

    learned counsel for the plaintiff before the Trial Court has reported no

    rebuttal evidence and thereafter the suit came to be posted for

    arguments of the parties on 14.08.2018. Plaintiff has filed an
    11/63
    CCCA.NO.96 OF 2019
    AND
    I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019

    application to recall PW2 for marking of documents, the same was

    allowed and Exs.A105 to A107 were marked overruling the objections

    raised by learned counsel for defendant Nos.3 to 5 for marking the

    deposition of DW1 in O.S.No.2288 of 2005.

    19. The learned Trial Court after hearing both the counsels on record

    has dismissed the suit of the plaintiff and allowed the counter claim

    filed by defendant Nos.3 to 5 in toto by directing the plaintiff to hand

    over the vacant possession of the counter claim schedule property to

    defendant Nos.3 to 5 within three months from the date of judgment

    [17.12.2018].

    20.1 Learned Senior counsel for the appellant – plaintiff submits that

    the learned Trial Court erred in disbelieving the contention of the

    plaintiff that during 1994 -1995 there was a practice of executing the

    sale deed for undivided share of land and a separate agreement for

    construction of the flat which the purchaser intended to purchase. The

    total sale consideration will be divided into two parts i.e., for the sale of

    undivided share of land and for the construction of the flat. In the case

    of the appellant – plaintiff they have entered into agreement of sale for

    undivided share of land and agreement for construction of flat No.002

    on the first floor/ground floor [floor above the stilt] on 18.02.1994. On

    23.07.1994 sale deed was executed and registered in favour of the
    12/63
    CCCA.NO.96 OF 2019
    AND
    I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019

    appellant – plaintiff for undivided share of land, later flat No.2 was

    renumbered as flat No.103. Payments made by the appellant – plaintiff

    after registration of the sale deed are evidenced by receipts issued by the

    builder which are towards completion of construction of the flat, parking

    place etc. Exs.A27, A34, A36 and A39 were issued in the year 1994 by

    mentioning flat number as 103, ground floor together with Ex.A29 – sale

    deed, Ex.A37-agreement of construction dated 18.02.1994 and Ex.A2

    possession letter clearly shows that the plaintiff is the owner of flat

    No.103 of the ground floor.

    20.2 The learned Trial Court erred in holding that the appellant –

    plaintiff has failed to prove its ownership over the suit schedule flat on

    the erroneous premise that the payment receipts are issued by the

    developer after the registration of the sale deed [for undivided share of

    land] on 23.07.1994 are not true, even though those receipts were

    marked and admitted as evidence by a competent Civil Court in the

    earlier proceedings relates to flat No.103 towards payment for

    construction of the flat, car parking charges etc. It is not the case of

    respondent No.2 – defendant No.2 that appellant – plaintiff has not

    purchased any flat in Riviera apartments as respondent No.2 –

    defendant No.2 stated in his written statement that payments made by

    appellant – plaintiff could be towards some other flat. The learned Trial
    13/63
    CCCA.NO.96 OF 2019
    AND
    I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019

    Court erred in holding that since respondent No.2 – defendant No.2 is

    not a party in O.S.No.2288 of 2005 and he is not bound by the evidence

    adduced and the judgment rendered in the suit. In fact, appellant –

    plaintiff and respondent No.2 – defendant No.2 claim to have purchased

    the suit schedule flat from respondent No.1 – defendant No.1, who is the

    party to O.S.No.2288 of 2005. The Managing Director of respondent

    No.1 – defendant No.1 Mr.B.Govinda Reddy was examined as DW1 in

    the above said suit and his deposition is marked as Ex.A107. The

    judgment in O.S.No.2288 of 2005 is marked as Ex.A105 which is

    binding on the respondent Nos.2 to 5 – defendant Nos.2 to 5 since they

    claim their alleged title through respondent No.1 – defendant No.1. The

    learned Trial Court misdirected itself in holding that Exs.A37 agreement

    for construction could not have been prior to Ex.A29 sale deed for

    undivided share of land. The learned Trial Court ought to have taken

    into consideration various clauses in Exs.A29 and A37 which clearly

    shows that there was an agreement of sale dated 18.02.1994 prior to

    Ex.A29 and that the agreement of sale for undivided share of land

    (which is not filed) and agreement for construction both are part of same

    package deal. Appellant – plaintiff did not find it necessary to file the

    earlier agreement of sale dated 18.02.1994 since Ex.A29 is already filed.
    14/63

    CCCA.NO.96 OF 2019
    AND
    I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019

    20.3 The learned Trial Court has unnecessary raised a doubt in

    paragraph No.15 of the judgment as to whether the said agreement of

    sale is earlier or subsequent to the sale deed under Ex.A29. Clause IV

    of the recitals of the agreement of construction dated 18.02.1994 clearly

    states that there is a separate agreement of sale dated 18.02.1994. The

    learned Trial Court erred in holding that appellant – plaintiff has failed

    to file any proof that he is in possession of flat No.103 and ought to have

    taken into consideration Exs.A27, A34, A36, A39 issued by respondent

    No.1 – defendant No.1 showing flat No.103, electricity bills relating to

    flat No.103, municipal tax receipts. Respondent No.1 – defendant No.1

    admitted the possession of the appellant – plaintiff and decree has been

    passed in pursuance of the said admission in O.S.No.2288 of 2005

    [Exs.A105 and A106]. The learned Trial Court erred in holding that

    appellant – plaintiff failed to prove as to when they were put in

    possession of the property in March 2001 when the last payment was

    made to respondent No.1 – defendant No.1 [Ex.A34]. Appellant – plaintiff

    as PW1 stated in his evidence that they were put in possession of

    the subject flat in the month of March, 2001 which was in semi-finished

    condition and after obtaining possession they completed the

    construction, let it out to M/s.Consortium Management Services Private

    Limited in June, 2006.

    15/63

    CCCA.NO.96 OF 2019
    AND
    I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019

    20.4 The learned Trial Court erred in holding that respondent No.2 –

    defendant No.2 obtained possession of the suit schedule flat on

    08.07.2002 and that respondent Nos.3 to 5 – defendant Nos.3 to 5 are

    the owners of the flat being the legal heirs of the deceased respondent

    No.2 – defendant No.2, when appellant – plaintiff failed to prove Ex.A29

    sale deed.

    20.5 The learned Trial Court failed to take into consideration that

    respondent Nos.3 to 5 – defendant Nos.3 to 5 miserably failed to prove

    their possession over the suit schedule flat at any point of time and

    dispossession by the appellant – plaintiff. Merely by saying that on

    08.07.2002, respondent No.2 – defendant No.2 was put in possession of

    the flat and thereafter locked it and went to Mumbai and came back in

    the first week of August 2006 and found M/s.Consortium Management

    Services Private Limited in possession of the schedule flat. It cannot be

    said that respondent Nos.3 to 5 – defendant Nos.3 to 5 have discharged

    the burden placed on them. Respondent No.2 – defendant No.2 also

    miserably failed to file any evidence to prove that the appellant – plaintiff

    had broke open the lock and entered into flat No.103. Respondent No.2

    – defendant No.2 did not make any counter-claim, however respondent

    Nos.3 to 5 – defendant Nos.3 to 5 came on record as LRs of respondent

    No.2 – defendant No.2 in the year 2016, filed their counter-claim along
    16/63
    CCCA.NO.96 OF 2019
    AND
    I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019

    with additional written statement on 19.09.2017 and the learned Trial

    Court erred in holding that respondent Nos.3 to 5 – defendant Nos.3 to 5

    have proved that they are the owners of the suit schedule flat.

    20.6 The learned Trial Court ought to have upheld the title of the

    appellant – plaintiff on the basis of Exs.A29 and A37 and various

    receipts issued by the builders showing flat No.103, electricity bills,

    municipal tax payment receipts, possession letter (Ex.A2). The sale deed

    of respondent No.2 – defendant No.2 being much later cannot be

    accepted, more so when Managing Director of respondent No.1 –

    defendant No.1 has admitted the sale of the subject flat in favor of

    appellant – plaintiff. Thereafter judgment and decree came to be passed

    under Exs. A105 and A106. Respondent No.1 – defendant No.1

    conveniently remained ex-parte in the suit which goes to show that

    respondents-defendants in collusion with each other have created the

    sale deed in favor of respondent No.2 – defendant No.2 when admittedly

    respondent No.1 – defendant No.1 did not have any subsisting right

    relating to the suit schedule property. The learned Trial Court failed to

    take into consideration Exs.A30 and A31 whereunder the subject

    property was given as collateral security for the loan obtained by the

    appellant – plaintiff from Vijaya Bank in July 2006.
    17/63

    CCCA.NO.96 OF 2019
    AND
    I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019

    20.7 Learned senior counsel to substantiate his contentions has relied

    on the decisions in the cases of: (i)T.K.Mohammed Abubucker (dead)

    though LRs and others vs. P.S.M. Ahamed Abdul Khader and others 1,

    (ii) Ashok Kumar Kalra vs. Wing CDR. Surendra Agnihotri and others 2;

    (iii) Ashok Kumar Kalra vs. Wing CDR. Surendra Agnihotri and others 3,

    (iv) Duraiswami Reddi vs. Angappa Reddi and another 4 ; (v) Gopaldas

    and Company, Mazgaon, Mumbai and others vs. Gopaldas Corporation,

    Mumbai and others 5 and prayed to allow the appeals.

    21. Learned senior counsel for the respondent Nos.3 to 5 – defendant

    Nos.3 to 5 submits that the learned Trial Court has properly appreciated

    the facts of the case in right perspective by taking into consideration the

    evidence adduced by the parties with that of the documents marked

    thereon. Appellant – plaintiff has failed to prove that he is entitled for

    declaration and that the respondent Nos.3 to 5 – defendant Nos.3 to 5

    have filed their additional written statement with counterclaim with the

    leave of the Court and they have proved that they are entitled for

    declaration and recovery of possession, the learned Trial Court has

    rightly dismissed the suit filed by the appellant – plaintiff and allowed

    the counterclaim filed by respondent Nos.3 to 5 – defendant Nos.3 to 5.

    1 (2009) 14 SCC 224
    2 2020 (2) SCC 394
    3 Special Leave to Appeal (Civil) No.23599 of 2018 dated 08.01.2020, of the Hon’ble Supreme Court of India
    4 MANU/TN/0085/1945
    5 AIR Online 2020 Bom 3075
    18/63
    CCCA.NO.96 OF 2019
    AND
    I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019

    Counsel to substantiate his contentions has relied on the decisions in

    the cases of (i) Jagdish Chander Chatterjee and others vs Shri Sri

    Kishan and others 6 , (ii) Bal Kishan and others vs Om Parkash and

    another 7, (iii) Saroop Singh vs Banto and others 8 (iv) Prem Singh and

    others vs Birbal and others 9, (v) Sumtibai and others vs. Paras Finance

    Co. registered Partnership Firm Beawer (raj.) Through Mankanwar (SMT)

    w/o. Parasmal Chordia (Dead) and Others 10 , (vi) Suraj Lamp and

    Industries Private Limited through Director vs State of Haryana and

    another 11 , (vii) Union of India vs. Vasavi Cooperative Housing Society

    Limited and others 12, (viii) Vinod Infra Developers Limited vs Mahaveer

    Lunia and others 13, (ix) Hemalatha (D) by LRs. vs Tukaram (D) by LRs

    and others 14 , (x) Bayyarapu Narayan Raidu vs Smt. Pagadala

    Varalaxmi 15 , (xi) Saved Sirajul Hasan vs. Syed Murtaza Ali Khan

    Bahadur and others 16 and prayed to dismiss both the appeals.

    22. Learned senior counsel for the appellant – plaintiff has filed his

    synopsis. Learned senior counsel for respondent Nos.3 to 5 – defendant

    Nos.3 to 5 has filed his written arguments in support of his contentions.

    6 (1972) 2 SCC 461
    7 (1986) 4 SCC 155
    8 (2005) 8 SCC 330
    9 (2006) 5 SCC 353
    10 (2007) 10 SCC 82
    11 (2012) 1 SCC 656
    12 AIR 2014 SC 937
    13 2025 SCC OnLine 1208
    14 2026 INSC 82
    15 2013 SCC OnLine AP 267
    16 MANU/DE/0315/1991
    19/63
    CCCA.NO.96 OF 2019
    AND
    I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019

    23. Heard both sides, perused the material on record.

    24. Now, the points for consideration are:

    (i) Whether the appellant – plaintiff could able to prove that he

    is entitled for declaration of the suit schedule property? If

    so,

    (ii) Whether he is entitled for permanent injunction restraining

    the respondents – defendants, their agents, servants,

    henchmen from interfering with his peaceful possession and

    enjoyment of the suit schedule flat?

    (iii) Whether respondent Nos.3 to 5 – defendant Nos.3 to 5 have

    proved that they are entitled for declaration of the

    counterclaim schedule property? If so,

    (iv) Whether respondent Nos.3 to 5 – defendant Nos.3 to 5 are

    entitled to recover the counterclaim schedule property from

    the appellant – plaintiff?

    (v) Whether the counterclaim filed by the respondent Nos.3 to 5

    – defendant Nos.3 to 5 is barred by law?

    (vi) Whether the judgment and decree passed by the learned

    Trial Court in O.S.No.1736 of 2006 suffers from any

    perversity or illegality? If so, does it require interference of

    this Court?

    20/63

    CCCA.NO.96 OF 2019
    AND
    I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019

    (vii) Whether the learned Trial Court was justified in allowing the

    counterclaim filed by the respondent Nos.3 to 5 – defendant

    Nos.3 to 5, if so, does it require interference of this court?

    25. Plaintiff has filed I.A.No.1 of 2025 in CCCA.NO.116 of 2019 under

    Order XLI Rule 27 CPC r/w. Section 151 of CPC seeking leave of the

    Court to receive the original agreement of sale dated 18.02.1994

    executed by defendant No.1 in favour of plaintiff for purchase of 1/40th

    undivided share in the subject land as additional evidence and the same

    be marked as Ex.A108.

    26. It is stated in the affidavit that the learned Trial Court has

    erroneously dismissed the suit while raising a doubt because of non-

    filing of the original agreement of sale dated 18.02.1994. In fact the

    plaintiff felt that as registered sale deed dated 23.07.1994 under

    document No.2667 of 1994 was already on record as Ex.A29, which

    refers to the execution of earlier agreement of sale, it was not necessary

    to file the original agreement at that stage. Construction agreement

    dated 18.02.1994 also refers to the agreement of sale dated 18.02.1994.

    It is in these circumstances plaintiff has not felt it necessary to file the

    original agreement dated 18.02.1994 during the course of trial. The

    learned Trial Court unnecessarily confused itself by making certain

    adverse remarks raising doubts about the existence of agreement of sale
    21/63
    CCCA.NO.96 OF 2019
    AND
    I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019

    dated 18.02.1994. As an abundant caution and solely with an intention

    to assist the court to effectively decide the subject controversy, the

    original agreement of sale dated 18.02.1994 has been filed herewith with

    an application seeking leave to produce the same as additional evidence.

    It would be in the interest of justice that appropriate leave be granted by

    receiving the document as additional evidence in the appeal and prayed

    to allow the same.

    27. Defendants filed counter to I.A.No.1 of 2025 and contended that

    the petition is not maintainable at this stage and the plaintiff has not

    made out any grounds in the affidavit and prayed to dismiss the same.

    28. On reading of Order XLI Rule 27 of CPC which states about

    production of additional evidence in Appellate Court (i) the parties to an

    appeal shall not be entitled to produce additional evidence, whether oral

    or documentary, in the Appellate Court. But if –

    a) ….

    aa) the party seeking to produce additional evidence establishes that

    notwithstanding the exercise of due diligence, such evidence was

    not within his knowledge or could not, after the exercise of due

    diligence, be produced by him at the time when the decree

    appealed against was passed; or
    22/63
    CCCA.NO.96 OF 2019
    AND
    I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019

    b) the Appellate Court requires any document to be produced or any

    witnesses to be examined to enable it to pronounce judgment, or

    for any other substantial cause.

    The appellate Court may allow such evidence or document to be

    produced or witnesses to be examined.

    29. Plaintiff was in custody of the agreement of sale dated 18.02.1994.

    His contention in the affidavit is that the recitals of the agreement of

    sale dated 18.02.1994 is referred in Ex.A29 sale deed, so also in the

    construction agreement [Ex.A37]. It is the grievance of the plaintiff that

    the learned Trial Court raised a doubt of non-filing of the original

    agreement of sale dated 18.02.1994.

    30. Affidavit is silent with regard to the plaintiff’s due diligence in not

    filing the agreement of sale dated 18.02.1994 and the affidavit is bereft

    of material particulars. There is no whisper in the affidavit what made

    the plaintiff to not to file the same. Furthermore I.A.No.1 of 2025 came

    to be filed basing on the observations made by the learned Trial Court in

    the judgment and decree. Since the affidavit states that agreement of

    sale dated 18.02.1994 is already referred in Exs.A29 and A37, the same

    will be looked into. There are no merits in the application and the same

    is liable to be dismissed and is accordingly dismissed.
    23/63

    CCCA.NO.96 OF 2019
    AND
    I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019

    POINT NOs.i and iv:

    31. Plaintiff is claiming flat No.103, ground floor, Riviera Apartments

    in premises No.6-3-347/9, Dwarakapuri Colony, Punjagutta,

    Hyderabad, admeasuring 1650 square feets, along with proportional

    undivided share in the land admeasuring 50 square yards equivalent to

    41.80 square meters.

    32. Defendant Nos.3 to 5 are also claiming flat No.103, ground floor of

    Riviera Apartments admeasuring 1800 square feets carpet area

    including common area and balconies, along with 1/40th or 50 square

    yards whichever is high in 2000 square yards equivalent to 50 square

    yards in premises M.No.6-3-347/9, situated at Punjagutta, Hyderabad.

    33. Plaintiff and defendant Nos.3 to 5 are claiming flat No.103. The

    extent claimed by the plaintiff is 1650 square feets whereas the extent

    claimed by the defendant Nos.3 to 5 is 1800 square feets. The

    boundaries shown in the plaint schedule and the boundary shown in

    the counter claim schedule are one and the same.

    34. Defendant No.2 has got issued a legal notice on 07.10.2006

    through his counsel to M/s.Consortium Management Services Private

    Limited referring to flat No.103 [Ex.A3]. Ex.A3 notice goes to show that

    defendant No.2 was delivered possession by possession letter dated
    24/63
    CCCA.NO.96 OF 2019
    AND
    I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019

    08.07.2002, on the same day registered sale deed came to be executed

    by M/s.Bhavanam Estates Private Limited. The notice states that

    defendant No.2 is permanent resident of Mumbai and kept the property

    locked and vacant. Paragraph No.4 of the notice states that in or about

    the first week of August 2006, defendant No.2 visited the property at

    Hyderabad and was shocked to find that M/s.Consortium Management

    Services Private Limited is in occupation. Notice further states that on

    inquiries made with Mr.Prabhu, defendant No.2 was informed that

    Consortium Management Services Private Limited is in occupation of the

    property since 15.06.2006 under a lease and license agreement with one

    Ms. Girija Reddy and called upon Consortium Management Services

    Private Limited to vacate the property and hand over the possession to

    defendant No.2 .

    35.1 Ex.A1 is the office copy of plaint in O.S.No.2288 of 2005, plaintiff

    therein is the appellant herein, which is filed against (i) respondent No.1

    – defendant No.1- M/s. Bhavanam Estates Private Limited, represented

    by its Managing Director Mr. Bhavanam Govinda Reddy (ii) Mr.Govinda

    Reddy, Managing Director of M/s. Bhavanam Estates Private Limited,

    (iii) Mrs. Bhavanam Shakeela Reddy, wife of Mr.Bhavanam Govinda

    Reddy, Executive Director of M/s. Bhavanam Estates Private Limited.
    25/63

    CCCA.NO.96 OF 2019
    AND
    I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019

    35.2 It is stated in Ex.A1 that the plaintiff is the sole and absolute

    owner and possessor of Flat No.103, Riviera Apartments, admeasuring

    1650 square feets. At the time of inception of the project it is numbered

    as flat No.2 on the ground floor and subsequently assigned flat No.103.

    Defendant No.2 therein is the Managing Director and defendant No.3

    therein is the Executive Director of defendant No.1. Defendant No.1

    therein represented by defendant No.2 executed agreement of sale dated

    18.02.1994 and agreed to sell 1/40th share of the land comprising 2000

    square yards equivalent to 1672.32 square meters. Subsequently

    registered sale deed came to be executed in favor of the plaintiff on

    23.07.1994, vide registered document No.2667 of 1994 in respect of

    1/40th share. Original agreement of construction is also executed on

    18.02.1994. Defendants therein have handed over the flat without

    completing the same as per the agreed specifications, without agreed

    facilities, amenities and special features in the last week of April 2005.

    The defendants therein trespassed into the same and committed other

    illegal acts, thereby plaintiff has lodged a complaint before Police

    Station, Banjara Hills, Hyderabad.

    35.3 The prayer in O.S.No.2288 of 2005 – Ex.A1 is to grant perpetual,

    injunction restraining the defendants therein, their employees, agents,
    26/63
    CCCA.NO.96 OF 2019
    AND
    I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019

    servants, or any other person acting or claiming through or under them

    and also claimed amounts for pending works.

    35.4 Ex.A2 is the letter of delivery of possession issued by defendant

    No.1, which reads as under:

    BHAVANAM ESTATES PRIVATE LIMITED
    Plot No. 134, 6-3-347/9, Dwarakapuri Colony, Punjagutta, Hyderabad.

    Tele. No. 55525558.

    __________________________________________________________________________
    DELIVERY OF POSSESSION
    This is to confirm the delivery of possession of Flat No 103 (1st Floor) in
    RIVIERA APARTMENTS, in fully finished condition and to the satisfaction
    of Smt. C.Girija Reddy and K.Amarender Reddy. All the obligations /
    liabilities of the Builder / Developer, and all the right of the apartment
    owner, arising out of all or any previous agreements whether oral or in
    writing shall stand cancelled with this letter. The matters have been
    comprised and there shall be no claims in future by M/s. Bhavanam
    Estates Pvt. Ltd. And M/s. Cipior Organics Pvt. Ltd.

    Sd/-

    OWNER/ALLOTTEE M/S Bhavanam Estates Pvt. Ltd.

    Sd/-

    (B. Govinda Reddy)
    Managing Director.

    Ex.A5 is the original electricity bill dated 11.06.2006. Ex.A13 is the

    original electricity bill dated 06.10.2006. Ex.A94 is the original

    electricity bill dated 02.04.2015. Ex.A96 is the certified copy of

    electricity bill dated 05.05.2015. Ex.A98 is the certified copy of
    27/63
    CCCA.NO.96 OF 2019
    AND
    I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019

    electricity bill dated 03.06.2015. Ex.A100 is the certified copy of

    electricity bill dated 02.10.2015. Ex.A102 is the certified copy of

    electricity bill dated 02.12.2015. All the above said bills shows the

    name of the plaintiff for flat No.103. Exs.A95, A97, A99, A101 and A103

    are the corresponding receipts for Exs. A94, A96, A98, A100 and

    A102.

    35.5 Exs.A6 and A7 are the original receipts dated 04.07.2006, Ex.A8

    is the original receipt dated 08.08.2006 and Ex.A9 is the original receipt

    dated 07.09.2006 issued by Riviera Apartment Owner’s Welfare

    Association, in favor of Consortium Management Services for the month

    of June, July, August and September 2006, showing the flat number as

    103.

    35.6 Exs.A40 to A84 are the receipts issued by Riviera Apartments

    Owner’s Welfare Association in the name of the plaintiff showing the flat

    No.103, towards maintenance charges for different months.

    35.7 Exs.A11 and A38 are the same documents which is the extract of

    minutes of meeting dated 12.01.2005 authorizing Sri K.Amarendra

    Reddy, director hereby authorized to lodge civil, criminal complaints on

    behalf of the company. Ex.A12 is the true copy of certificate of

    incorporation and MOA of the plaintiff.

    28/63

    CCCA.NO.96 OF 2019
    AND
    I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019

    35.8 Ex.A14 is the written statement filed by M/s.Bhavanam Estates

    Private Limited represented by its Managing Director, Mr.Bhavanam

    Govinda Reddy in O.S.No.2288 of 2005 on 17.09.2007. It is stated

    therein that the defendants delivered vacant possession of flat No.103 to

    the plaintiff in full finished condition and to the satisfaction of the

    plaintiff and with specific understanding that all previous agreements

    whether oral or in writing shall stand cancelled.

    35.9 Exs.A15 to A27 are the payment receipts dated 21.02.1994;

    27.02.1994; 10.03.1994; 04.03.1994; 16.04.1994; 31.02.1994;

    23.07.1994; 23.07.1994; 26.07.1994; 20.10.1994; 14.11.1994;

    27.05.1995 and 18.10.1994 issued by defendant No.1 in favour of the

    plaintiff for purchasing a flat in Riviera Apartments. Ex.A27 receipt

    shows that defendant No.1 has received amount of Rs.50,000/- from the

    plaintiff towards the full payment of car parking for flat No.103 at

    Riviera Apartments, Dwarakapuri Colony, Hyderabad.

    35.10 Ex.A28 is the letter addressed by the plaintiff to the

    Managing Director of defendant No.1 dated 27.05.1995. The letter

    subject states that release of payment against our flat. The letter further

    states that as per the agreement, the flat has to be ready by 31.12.1994

    for possession. The completion of work has been delayed by nearly five

    months and the investment was totally blocked, there was loss of
    29/63
    CCCA.NO.96 OF 2019
    AND
    I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019

    interest on their investment. There is lot to be done in the flat including

    sanitary fittings, electricity and water connections, telephone

    connection, windows and doors. Letter further states that they are

    releasing the payment of Rs.50,000/- by way of cheque assuming that

    the flat will be ready within fortnight with all the amenities for

    possession.

    35.11 Exs.A32, A33 and A35 are the part payment receipts dated

    23.02.2001 and 22.03.1994 issued by defendant No.1 in favor of

    plaintiff for purchase of flat at Riviera Apartments. Ex.A34 is part

    payment receipt issued by B.Govinda Reddy for flat No.103 of Riveira

    Apartments in favour of the plaintiff.

    35.12 Ex.A36 is the letter dated 19.10.1994 issued by defendant

    No.1 signed by its executive director in favor of the plaintiff. The letter

    states that ‘with reference to your agreement dated 18.02.1994, they

    have completed the brick work of flat bearing No.103 and sought for

    payment of fifth installment amount of Rs.65,000/-.’

    35.13 Ex.A29 is the certified copy of registered sale deed dated

    23.07.1994 executed by defendant No.1 through its Managing Director,

    Sri Bhavanam Govinda Reddy in favor of the plaintiff. The schedule of

    the property is undivided 1/40th share in 2000 square yards equivalent

    to 50 square yards or 41.806 square meters be it a little more or less
    30/63
    CCCA.NO.96 OF 2019
    AND
    I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019

    and the boundaries thereon with old building almost fully demolished

    bearing MCH.No.6-3-347/9, Panjagutta, Hyderabad. The boundaries

    are North: 30 feet wide public road, Panjagutta to Banjara

    Hills, South: neighbors property, East: neighbors property and West:

    land of Nizam’s Institute of Medical Sciences/Specialities. It is

    mentioned in paragraph No.d at internal page No.4 that whereas the

    vendee approach the vendor for sale of 1/40th undivided portion of

    schedule property and the vendors have agreed on mutually acceptable

    terms and conditions set out herein and the vendee paid full

    consideration to the vendors as per the agreement of sale and agreement

    of construction between the parties.

    35.14 Ex.A30 is the copy of Form 8 whereunder plaintiff has

    deposited his title deeds for equitable mortgage with letter of gaurantee.

    Ex.A31 is the certified copy of certificate of registration of mortgage

    under Section 132 of Companies Act 1956.

    35.15 Ex.A37 is the agreement of construction dated 18.02.1994

    executed by defendant No.1 by its Managing Director Sri Bavanam

    Govinda Reddy in favor of the plaintiff. Clause 1, 2, 3, 5, 6, 8, 9 and 11

    are important, which reads as under:

    1. The purchaser having agreed to purchase under separate
    agreement of sale the 1/40th undivided share of the land comprising the
    31/63
    CCCA.NO.96 OF 2019
    AND
    I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019

    schedule A property has, as part of same package deal, agreed that the
    developer shall construct for him flat No.2 on the first floor with a super
    built up area of 1650 sq.ft and the schedule B property as part of the
    complex to be named “RIVIERA” on land comprising the schedule A
    property.

    2. The total consideration that the purchaser has agreed to pay to
    the developer for the construction is Rs.6,24,250/-(Rupees Six lakhs
    twenty four thousand two hundred and fifty only) payable as per the
    schedule of payments vide I hereof.

    3. Flat No.2 in the ground floor is intended for commercial use as
    described in the schedule B shall be as per the specifications set out in
    annexure I hereto.

    5. The developer shall construct the building in accordance with the
    plans which have been shown to the purchaser and the developer reserves
    the right to make such modifications as may be necessary at its sole
    discretion so long as the total super built up area deliverable to the
    purchaser is not diminished. The developer also reserves the right to
    construct two penthouses over the terrace of the sixth floor (either ground
    or cellar being reserved parking) and to earmark for the exclusive use of all
    owners of the flats proposed, one half of the terrace over the topmost floor,
    computed as below, with the remaining half being earmarked for the
    exclusive use of the two penthouses to be constructed as above, the
    terraces over the penthouses to belong exclusively to the owners of the
    respective penthouses. For computation of the half area of the terrace, area
    of each penthouse built ог to be built shall be excluded.

    I. Whereas the Developer has duly purchased an undivided 29/40th
    or 72.5% share in the property described in the schedule “A” below by and
    under a sale deed dated 27th November 1992 registered as document no:

    3110 of 1992 in Book I volume 1954 at pages 89 to 194 at the office of the
    Sub-Registrar, Hyderabad and has done so with the objective of
    development of the said property for construction of a complex of
    apartments, penthouses and commercial units. (11/40th or 27.5%
    undivided share in the schedule “A” property has been simultaneously
    purchased by registered sale deeds by other persons from the owners, as
    32/63
    CCCA.NO.96 OF 2019
    AND
    I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019

    part of the same composite transaction, for the purpose of having
    apartments in the complex to be constructed by the developer therein.)

    II. WHEREAS the purchaser is an individual, desirous of owing an
    apartment/commercial unit in the complex to be developed and named
    “RIVIERA”.

    III. WHEREAS pursuant to the sale by the owners of the schedule A
    property in favour of the developer herein, the developer has entered into a
    separate agreement of sale with the purchaser herein for sale to the
    purchaser, of an undivided 1/40th or 2.5% share of the total land
    comprising the schedule A property (which share of the total land
    comprises 1/29th or 3.4483% undivided share of the extent purchased by
    the developer) and is now entering into this agreement of construction,
    both together forming parts of one package deal.

    IV. WHEREAS the purchaser has approached the developer for sale to
    him/her of 1/40th undivided share in the schedule “A” property and the
    same has been agreed to between developer and the purchaser under a
    separate agreement sale dated 18.2.1994, and also for construction of the
    property described in the schedule j below and hereinafter for brevity
    referred to as the schedule “B” property comprising residential
    apartment/commercial unit, in the complex proposed, with the
    understanding that neither of the two agreements shall be capable of
    cancellation without simultaneous automatic cancellation of the other
    inasmuch as, a stated above, both constitute parts of one package deal a
    transaction.

    v. WHEREAS the developer has shown to the purchaser and the
    purchaser has scrutinized, all documents and papers in possession of
    developer, pertaining to the schedule A property and the rights of the
    developer to develop the same, enter into this agreement and the ancilliary
    agreement of sale in favour of the purchaser, etc.
    33/63
    CCCA.NO.96 OF 2019
    AND
    I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019

    6. The purchaser agrees that he will have an undivided 1/40th share
    in the land comprising the schedule A property and will not have or claim
    any exclusive rights in respect of any specified area of the land.

    8. The purchaser shall have no rights of possession in respect of the
    schedule B property or any part thereof until full payment is made to the
    Developer of all dues under this agreement as well as under the agreement
    of sale.

    9. The developer agrees that the construction shall be completed in all
    aspects as per the specification and the said flat no.2 on the ground floor
    and parking delivered on or before 31.12.2024 to the purchaser. In the
    event of delay thereafter, for any reasons attributable to default on the part
    of the developer, being factors within its control, the developer agrees to
    pay to the purchaser compensation for the delay at the rate of Rs.2/-

    (Rupees two only) per month per sq.ft. of carpet area of the schedule B
    property till such time as the schedule B property is ready for delivery, the
    payments for the concerned month’s delay being made on or before the
    expiry of the fifth day of the succeeding month.

    11. The purchaser agrees and undertakes that the purchaser shall not be
    entitled to object to any inconvenience that will be caused on account of
    any other construction being carried out in the schedule A property on any
    part thereof at any time including the gathering of men and materials,
    erecting of scaffolding, etc., laying of electric supply lines, etc., drainage
    and other pipes, conduits, cable T.V. cables, telephone and other cables,
    construction of sumps, overhead tanks, and other building activity, and/or
    due to dust, noise and the like.

    Schedule A and B are mentioned in the agreement of construction but

    they do not find place in the document.

    34/63

    CCCA.NO.96 OF 2019
    AND
    I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019

    35.16 Exs.A85, A88, A89 and A92 are the property tax demand

    notices dated 22.06.2009, 31.07.2010, 13.05.2011 for door No.6-3-

    347/9/103. Exs.A86, A87, A90 and A91 are the provisional receipt for

    cheque showing the name of the plaintiff with house No.6-3-347/9/103.

    Ex.A93 is the acknowledgment card of Southern Power Distribution

    Company of Telangana Limited in the name of the plaintiff for service

    connection No. A5018942.

    35.17 Ex.A105 is the certified copy of judgment in O.S.No.2288 of

    2005 dated 31.03.2009 wherein the suit filed by the plaintiff in

    O.S.No.2288 of 2005, was decreed in part granting the relief of

    permanent injunction restraining the defendants therein, their

    employees, agents from interfering with the peaceful possession and

    enjoyment of the suit schedule property.

    36. Ex.106 is the decree in O.S.No.2288 of 2005 dated 31.03.2009.

    The schedule property is flat No.103 on the ground floor of Riviera

    Apartments municipal bearing No.6-3-347/9 admeasuring 1650 sq.fts.

    Ex.A107 is the certified copy of deposition of B.Govinda Reddy,

    Managing Director of defendant No.1. The relevant portion of the

    deposition is as under:

    ‘I received amount under receipts [Exs.A2 to A15, A17 to A20 marked in
    O.S.No.2288 of 2005]. It is true that the amount covered under the said
    35/63
    CCCA.NO.96 OF 2019
    AND
    I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019

    receipts pertains to construction of flat No.103 in Rivirea Apartment. By
    2001 construction was completed and possession of the schedule flat was
    delivered to the plaintiff.’

    37.1 Chief Executive Officer of the plaintiff is examined as PW1 – C.

    Sanjay Reddy. His evidence is the same with that of the original plaint

    averments. Witness was cross-examined on 22.02.2017 by the learned

    counsel for defendant Nos.3 to 5. He stated that Ex.A1 does not contain

    the signature of the plaintiff or the counsel for the plaintiff. Ex.A2 does

    not contain the date of delivery of possession. Ex.A10 does not reflect

    flat number. Suit is filed for flat No.103 ground floor. Witness adds that

    the ground floor is above the parking lot on the stilt and it is taken as

    first floor. The possession of the suit schedule property was given in the

    month of March 2001 to the plaintiff. Ex.A38 does not specifically

    authorize him to give evidence in the present suit. Witness adds that

    Ex.A38 is a general authorization. The schedule of property mentioned

    in the plaint and its boundaries with that of Ex.A29 sale deed are

    different. Witness adds that Ex.A29 is executed in the year 1994. He do

    not remember whether he has filed any document to show that the

    construction of the flat subsequent to Ex.A29. In Ex.A30 – Form 8,

    property mentioned as flat No.103 in first floor and whereas in the plaint

    schedule property mentioned as flat No.103 ground floor. Witness adds

    that the ground floor is located on the stilt above the parking lot, hence
    36/63
    CCCA.NO.96 OF 2019
    AND
    I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019

    it is designated as first floor. Ex.A37 agreement of construction was

    executed prior to Ex.A29 sale deed. Ex.A37 is not a registered

    document. As per Ex.A37, flat number given for construction is flat

    No.2 on the first floor. Witness adds that flat No.103 was assigned after

    building approval. He has not filed agreement of sale executed between

    the developer and the plaintiff as referred in Ex.A37. There is document

    subsequent to Ex.A37 executed between the developer and the plaintiff,

    i.e., Ex.A29. There is no other agreement executed between the

    developer and the plaintiff after Ex.A37.

    37.2 Witness further stated in his cross-examination that Govinda

    Reddy was the Managing Director of defendant No.1 and he executed

    Ex.A20. Ex.A20 does not disclose the mode of payment, i.e, by way of

    cash or cheque. Ex.A20 does not reflect the suit schedule flat No.103.

    Plaintiff has not filed any document to show that Mr.Govinda Reddy was

    the Managing Director of defendant No.1 company. Witness adds he has

    filed Ex.A20. Plaintiff’s name is not mentioned in Exs. A15 to A19 and

    A21 to A25. Witness adds that it is mentioned as M/s.Cipior Organics.

    All the payments under Exs.A15 to A19 and A21 to A26 are by way of

    cheques and flat No.103 is not mentioned therein. Plaintiff paid total

    amount of Rs.7,31,750/- towards agreement of sale and agreement of

    construction to defendant No.1. Ex.A27 does not disclose the amount
    37/63
    CCCA.NO.96 OF 2019
    AND
    I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019

    paid by way of cash or cheque. Format of Exs.A20, A27, A32, A33, A34

    and A35 are different from that of Exs.A15 to A19 and A21 to A26.

    Signatures on Exs.A26 and A27 are different. Ex.A28 does not contain

    the suit schedule flat No.103. Ex.A34 does not contain the name of

    defendant No.1. Ex.A35 does not show the registration charges are

    towards flat No.103. Witness adds that they are towards registration of

    the suit property. He is not a witness to Ex.A36. It is not mentioned in

    Exs.A6 to A9 as to whether flat No.103 is situated in ground floor or first

    floor. Exs.A32, A33 and A35 does not mention the flat No.103.

    37.3 PW1 was further cross-examined on 28.02.2017 wherein he stated

    that Exs.A29 and A37 do not mention the flat No.103 and the plaintiff

    has filed criminal case against defendant No.1. Plan annexure to the

    plaint is not marked. Parties to the documents and description of the

    documents are not mentioned in the list of plaint documents at serial

    Nos.4 to 19 of the amended fair copy of the plaint. Consortium

    Management Services Private Limited were the tenants of the plaintiff

    from 2006 for a period of 4 to 5 years. He do not remember the exact

    year when they have vacated the property. He has not filed rental deed

    or rental receipts to show that Consortium Management Services Private

    Limited are the tenants of the plaintiff. Witness adds that he has filed

    Exs.A6 to A9 which are the maintenance receipts issued by the
    38/63
    CCCA.NO.96 OF 2019
    AND
    I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019

    association showing the payment of maintenance charges by the tenant.

    He do not recollect what was the rent paid by the tenant initially and

    they used to pay by way of cheque and sometimes by way of cash. At

    present there is no tenant in the suit schedule property. PW1 denied the

    suggestion that tenant is not in possession of the suit schedule property

    as on the date of filing of the suit. He also denied the suggestion that

    defendant No.2 has purchased the suit schedule property from

    defendant No.1 through registered sale deed bearing document No.1282

    of 2002 dated 08.07.2002 and that the possession was delivered vide

    letter of delivery of possession dated 08.07.2002 confirming the delivery

    of possession. He also denied the suggestion that suit schedule property

    was not sold to the plaintiff and no such construction was made by

    them, that is the reason why he did not file any documents as proof of

    the said construction. He denied the suggestion that plaintiff has filed

    the suit in collusion with defendant No.1.

    38.1 PW2 – N.N.Devarajan is the Assistant Manager (Legal) of the

    plaintiff, his evidence is that plaintiff is in possession of the flat No.103

    and they were paying maintenance charges maintained by Riviera

    Apartments Owners Welfare Association and they were also paying

    municipal taxes, electricity bills. Plaintiff is in possession of the suit

    schedule property since 2001 and continued to be in possession of the
    39/63
    CCCA.NO.96 OF 2019
    AND
    I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019

    same. Defendant No.2 was never in possession of the suit schedule

    property and possession was never delivered to him by defendant No.1.

    Learned VI Senior Civil Judge, City Civil Court, has decreed the suit in

    O.S.No.2288 of 2005 vide judgment and decree dated 31.03.2009

    restraining the defendant No.1 and its directors from interfering with the

    peaceful possession of the plaintiff over the suit schedule property,

    specifically held that the plaintiff is in possession of the suit schedule

    property.

    38.2 PW2 was cross-examined by learned counsel for defendant Nos.3

    to 5 on 04.08.2017. He stated that he has not filed the original of

    Ex.A39 in the case and it does not bear any date. Plaintiff has not filed

    the bank statement evidencing that the cheque Ex.A39 has been

    encashed. Exs.A70 and A71 signatures are different from each other.

    Witness adds that they have been signed by different persons. Ex.A70 is

    signed by Mr.Chandy and Ex.A71 is signed by G.Sreemannarayana as

    secretary of the welfare association. Ex.A71 is signed by

    G.Sreemannarayana for secretary. Receipts under Exs.A42 to A84 do

    not bear the revenue stamps and there is no official seal of welfare

    association on the said receipts. In Ex.A65 there is a note by the

    association for enhancement of maintenance from Rs.1,200/- per month

    to Rs.1,500/- per month with effect from July 2012. Plaintiff has not
    40/63
    CCCA.NO.96 OF 2019
    AND
    I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019

    filed any bank statements to show encashment of the cheques. All the

    payments of maintenance made to the welfare association were through

    cheques only. Exs.A40 to A84 are prescribed as receipts but not as pre-

    receipts. Plaintiff is in occupation of the suit schedule property and they

    are storing the records. O.S.No.4162 of 2009 on the file of XII Junior

    Civil Judge, City Civil Court, Hyderabad is filed by T. Srinivas Yadav

    seeking injunction and it is at the stage of arguments. The suit was

    originally filed against the owner of flat No.104 and they got impleaded

    in the said suit.

    38.3 PW2 was recalled as per the orders in I.A.No.528 of 2018 dated

    07.09.2018 for marking of documents i.e., Exs.A105 to A107.

    38.4 In his cross-examination he stated that he is not aware that the

    decree under Ex.A106 was passed after compromise between the parties

    to the suit. He has not filed sale deed relating to the suit schedule

    property in O.S.No.2288 of 2005. Witness adds that at that time sale

    deed was pledged with Vijaya Bank, Haridwar Branch. In Ex.A37 clause-

    1, it is mentioned as flat No.2 on the first floor. Witness adds that flat

    No.2 is in the ground floor as mentioned in clause-3. The property in

    respect of Ex.A37 and the property covered by Ex.A105 are one and the

    same. As per Exs.A105 and A106 the schedule property is flat No.103 in

    ground floor. Witness adds that flat No.002 has been changed to flat
    41/63
    CCCA.NO.96 OF 2019
    AND
    I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019

    No.103. He has not filed any document either in O.S.No.2288 of 2005 or

    in O.S.No.1736 of 2006 to show that flat No.002 has been changed to

    flat No.103. Witness adds that the builder tentatively given numbers as

    flat Nos.001, 002 and 003 etc. He has not filed the possession, delivery

    letter in O.S.No.2288 of 2005. Witness adds that the said letter was

    pledged with Vijaya Bank, Haridwar branch. Ex.A2 was given in March

    2001, it does not bear any date. He denied the suggestion that Ex.A2 is

    not a letter of delivery of possession and it is only confirmation of

    delivery of possession. Ex.A2 does not specifically say when possession

    was delivered. PW2 denied the suggestion that after filing the criminal

    case against defendants in O.S.No.2288 of 2005, they have illegally

    occupied the suit schedule property. He do not remember when the

    criminal case was withdrawn. He also denied the suggestion that sale

    deed does not say whether it is flat No.002 or flat No.103, whether it is

    in ground floor or in first floor. Witness adds that the sale deed is in

    respect of undivided share of land. He also denied the suggestion that

    they have colluded with defendant No.1 and filed the suit and they are

    not in possession of the suit schedule property.

    38.5 PW2 was recalled for marking the documents vide orders in

    I.A.No.528 of 2018 dated 07.09.2018 and he was examined further in

    chief on 26.10.2018 by that time additional written statement and
    42/63
    CCCA.NO.96 OF 2019
    AND
    I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019

    counter claim filed by defendant No.3 to 5 were already on record, in

    spite of it there is no suggestion to the witness with regard to the

    pleadings in the counter claim.

    39. Ex.B1 is the certified copy of registered sale deed bearing

    document No.1282 of 2002, dated 08.07.2002 which is executed by

    defendant No.1 by its Managing Director B.Govinda Reddy in favor of

    defendant No.2. In internal page No.6 of Ex.B1 the total sale

    consideration fixed is Rs.7,00,000/- and it is mentioned in paragraph

    No.4 of internal page No.6 that defendant No.2 has paid Rs.2,00,000/-

    by way of cheque No.034751 dated 30.09.1993 and Rs.2,00,000/- by

    way of cheque No.034752 on the same date and an amount of

    Rs.3,00,000/- is paid by way of D.D.No.668687 dated 08.07.2002 i.e, on

    the date of execution of sale deed dated 08.07.2002. The schedule

    property is shown as flat No.103 on ground floor of Riviera Apartment,

    admeasuring 1800 square feets. Ex.B2 is the delivery of possession

    letter dated 08.07.2002 confirming the delivery of flat No.103 to

    defendant No.2.

    40.1 Defendant No.4 is examined as DW1, her evidence is similar to the

    written statement and the counter claim.

    40.2 In her cross examination she stated that except the suit schedule

    flat her father did not buy any other property in Hyderabad. Except
    43/63
    CCCA.NO.96 OF 2019
    AND
    I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019

    Exs.B1 to B3 and B8, she has no other document to show that her

    father has purchased the suit schedule flat and exercised his right over

    the said flat as its owner. She do not know whether her father has

    entered into any agreement of sale with defendant No.1 earlier to the

    alleged purchase of the suit flat under Ex.B1. She do not know whether

    her father has disclosed the transaction under Ex.B1 in his income tax

    returns or before any other government authorities. She do not know

    whether her father has obtained electricity service connection in respect

    of the suit flat. She do not know whether her father has mutated his

    name as owner in the municipal corporation records. She do not know

    whether her father has paid any property tax in respect of the suit

    schedule flat, maintenance charges to the association of the apartment.

    Except Exs.B1 and B2 she has no other document to show that her

    father was given possession of the suit schedule flat on 08.07.2002. She

    do not know that as on 08.07.2002 plaintiff was in possession of the

    suit schedule flat. She do not know that her father was not given

    possession of the suit schedule flat on 08.07.2002. She do not know

    that earlier to 1993 to 1994 there was a practice that the

    developers/owners used to register the sale deeds in respect of

    undivided share in the land and after construction of the building the

    flats were used to be conveyed to the purchaser by the letter of delivery.
    44/63

    CCCA.NO.96 OF 2019
    AND
    I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019

    According to her M/s. Consortium Management Services Private Limited

    is in possession of the suit schedule flat as on date.

    40.3 DW1 further stated in her cross examination that plaintiff was in

    possession of the suit schedule flat as on the date of filing the suit.

    Plaintiff is also in possession of the suit schedule flat as on the date

    [13.07.2018]. She did not verify from her father as to how the plaintiff

    came into possession of the suit schedule flat. It may be true that the

    plaintiff is paying the property tax, maintenance charges, electricity

    consumption chargers to the respective authorities in respect of the suit

    schedule flat. She do not remember whether her father has informed her

    that in first week of August 2006, when he went to Hyderabad, he found

    the suit schedule flat in occupation of M/s. Consortium Management

    Services Private Limited. DW1 denied the suggestion that herself and

    defendant Nos.3 & 5 are not entitled for counter claim properties, on the

    other hand plaintiff is entitled for the relief claimed in the suit.

    41.1 In T.K. Mohammed Abubucker1, Supreme Court held at paragraph

    No.13 which reads as under:

    13. Though title to an immovable property is usually established by tracing
    it for a period of thirty years, many a time, the search and tracing is
    restricted to a minimum period of twelve years, presumably with reference
    to Articles 64 and 65 of the Limitation Act, 1963. Further, where the title is
    traced to a grant or transfer by the Government or a statutory development
    45/63
    CCCA.NO.96 OF 2019
    AND
    I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019

    authority, as contrasted from a transfer from a private person, the search
    is not taken prior to such transfer/grant, even if such transfer/grant is
    within twelve years.

    41.2 In Ashok Kumar Kalra2, a three-judge bench of the Supreme Court

    of India answered a crucial legal reference concerning the interpretation

    of Order VIII Rule 6A of the CPC and observed at paragraph No.20 which

    reads as under:

    20. We sum up our findings, that Order VIII Rule 6A of CPC does not put
    an embargo on filing the counter-claim after filing the written statement,
    rather the restriction is only with respect to the accrual of the cause of
    action. Having said so, this does not give absolute right to the defendant to
    file the counter-claim with substantive delay, even if the limitation period
    prescribed has not elapsed. The court has to take into consideration the
    outer limit for filing the counter-claim, which is pegged till the issues are
    framed. The court in such cases have the discretion to entertain filing of
    the counter-claim, after taking into consideration and evaluating inclusive
    factors provided below which are only illustrative, though not exhaustive:

    i. Period of delay.

    ii. Prescribed limitation period for the cause of action pleaded.
    iii. Reason for the delay.

         iv.    Defendant's assertion of his right.
          v.    Similarity of cause of action between the main suit and the
                counterclaim.
         vi.    Cost of fresh litigation.
         vii.   Injustice and abuse of process.
        viii.   Prejudice to the opposite party.
         ix.    and facts and circumstances of each case.
          x.    In any case, not after framing of the issues.
                                              46/63
                                                                              CCCA.NO.96 OF 2019
                                                                                            AND
                                                     I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019
    
    
    
    

    After the reference is answered the matter is sent back to the

    appropriate bench.

    41.3 The Honorable Supreme Court in Ashok Kumar Kalra3 vide order

    dated 08.01.2020 observed as under:

    A counter-claim was filed after the issues were framed, the said counter-
    claim cannot be filed as per the law laid down by this judgment.
    Consequently, the Special Leave Petition is dismissed. However, it will be
    open for the petitioner to file a fresh suit based on the cause of action in
    the counter – claim if it is otherwise permissible in law.

    41.4 In The Duraiswami Reddi4, High Court of Madras held at

    paragraph No.2, which reads as under:

    The law gives four months’ period for registration and if the document is
    registered within that date, the subsequent transferee cannot be heard to
    say that as he got his document without notice, and during this period
    allowed to the earlier transferee, got his own document registered he must
    be deemed to be a bona fide purchaser for value. Such a plea, if allowed,
    would lead to much fraud. If a later document registered earlier is to prevail
    over an earlier document registered later it would always be easy for the
    vendor and the later purchaser to enter into a transaction within the time
    given for registration of the earlier document and get the new deed
    registered immediately and thus defeat the purchaser under the earlier
    deed. The correct proposition is set down in the following short passage in
    Mulla’s Indian Registration Act under Section 47:

    If there is a competition between registered documents relating to the same
    property, the document executed first in order of time has priority over the
    other, though the former document may not have been registered until
    after the latter.

    47/63

    CCCA.NO.96 OF 2019
    AND
    I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019

    41.5 In Gopaldas and company5, Bombay High Court observed at

    paragraph Nos.19 and 27, which reads as under:

    19. The restriction imposed upon legal heirs, who are required to take
    up a defence limited to their character as legal representatives, under
    Order XXII Rule 4(2) of CPC, would not, for instance, permit the legal
    representative to take up defences inconsistent or independent with the
    original defendant’s defence, if any, and/or file a counter-claim along with
    his written statement, if a counter-claim had not already been filed by the
    original defendant.

    27. It is clear as daylight that a defendant, who is impleaded as legal
    representative of the deceased- defendant, is entitled to take up a defence
    and such pleas and defence can be taken up only by filing a written
    statement. Whether such a written statement is in addition to the written
    statement filed by the original defendant or whether it is a written
    statement sought to be filed by the legal representatives after the suit was
    directed to be heard as an undefended suit, is not material. Even if the
    original defendant had not filed a written statement, as in the present case,
    the legal representatives – defendant nos.5(a) to 5(c) cannot be deprived of
    their right to file a written statement. It is another matter altogether as to
    the contentions that can be taken up by defendant nos.5(a) to 5(c), that will
    be open for consideration at an appropriate time; provided a written
    statement is filed. The plaintiffs’ attempt to thwart the filing of the written
    statement cannot be sustained for those reasons. In this view of the matter,
    I am of the opinion that defendant nos.5(a) to 5(c), in the present case, are
    entitled to file their written statements notwithstanding the order dated
    22nd March 2019, which directs the suit to proceed undefended against
    defendant nos.1, 3, 4 and 5.

    42.1 In Jagdish Chander Chatterjee6, Supreme Court observed at

    paragraph No.10, which reads as under:

    48/63

    CCCA.NO.96 OF 2019
    AND
    I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019

    10. Under sub-clause (ii) of Rule 4 of Order XXII of the Civil Procedure Code
    any person so made a party as a legal representative of the deceased,
    respondent was entitled to make any defence appropriate to his character
    as legal representative of the deceased – respondent. In other words, the
    heirs and the legal representatives could urge all contentions which the
    deceased could have urged except only those which were personal to the
    deceased. Indeed this does not prevent the legal representatives from
    setting up also their own independent title, in which case there could be no
    objection to the court impleading them not merely as the legal
    representatives of the deceased but also in their personal capacity avoiding
    thereby a separate suit for a decision on the independent title.

    42.2 In Bal Kishan7, Supreme Court observed at paragraph No.3 which

    reads as under:

    Order XXII Rule 4 of the Code of Civil Procedure, 1908 provides that where
    one of two or more defendants dies and the right to sue does not survive
    against the surviving defendant or defendants alone, or a sole defendant or
    sole surviving defendant dies and the right to sue survives, the court, on an
    application made in that behalf, shall cause the legal representative of the
    deceased defendant to be made a party and shall proceed with the suit.
    Since the action in this case related to property, the right to sue did survive
    and the Rent Controller was right in bringing the legal representative of the
    deceased Musadi Lal on record. Sub-rule (2) of Rule 4 Order XXII
    authorises any person who is brought on record as the legal representative
    of a defendant to make any defence appropriate to his character as legal
    representative of the deceased defendant. The said sub-rule authorises the
    legal representative of a deceased defendant or respondent to file an
    additional written statement or statement of objections raising all pleas
    which the deceased tenant had or could have raised except those which
    were personal to the deceased defendant or respondent.

    49/63

    CCCA.NO.96 OF 2019
    AND
    I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019

    42.3 In Saroop Singh8, Supreme Court observed at paragraph No.28 as

    under:

    28. The statutory provisions of the Limitation Act have undergone a
    change when compared to the terms of Articles 142 and 144 of the
    Schedule appended to the Limitation Act, 1908, in terms whereof it was
    imperative upon the plaintiff not only to prove his title but also to prove his
    possession within twelve years, preceding the date of institution of the suit.

    However, a change in legal position has been effected in view of Articles 64
    and 65 of the Limitation Act, 1963. In the instant case, the plaintiff-
    respondents have proved their title and, thus, it was for the first defendant
    to prove acquisition of title by adverse possession. As noticed hereinbefore,
    the first defendant-appellant did not raise any plea of adverse possession.
    In that view of the matter the suit was not barred.

    42.4 In Prem Singh9, Supreme Court observed at paragraph No.27

    which as under:

    27. There is a presumption that a registered document is validly
    executed. A registered document, therefore, prima facie would be valid in
    law. The onus of proof, thus, would be on a person who leads evidence to
    rebut the presumption. In the instant case, Respondent 1 has not been
    able to rebut the said presumption.

    42.5 In Sumtibai10, Supreme Court observed at paragraph No.8, which

    reads as under:

    8. Every party in a case has a right to file a written statement. This is in
    accordance with natural justice. The Civil Procedure Code is really the
    rules of natural justice which are set out in great and elaborate detail. Its
    purpose is to enable both parties to get a hearing. The appellants in the
    50/63
    CCCA.NO.96 OF 2019
    AND
    I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019

    present case have already been made parties in the suit, but it would be
    strange if they are not allowed to take a defence. In our opinion, Order XXII
    Rule 4(2) CPC cannot be construed in the manner suggested by learned
    counsel for the respondent.

    42.6 In Suraj Lamps and Industries Private Limited11, Supreme Court

    observed at paragraph Nos.18, 23 and 24 as under:

    18. It is thus clear that a transfer of immovable property by way of sale can
    only be by a deed of conveyance (sale deed). In the absence of a deed of
    conveyance (duly stamped and registered as required by law), no right, title
    or interest in an immovable property can be transferred.

    23. Therefore, an SA/GPA/will transaction does not convey any title nor
    creates any interest in an immovable property. The observations by the
    Delhi High Court in Asha M. Jain v. Canara Bank [(2001) 94 DLT 841] ,
    that the “concept of power-of-attorney sales has been recognised as a mode
    of transaction” when dealing with transactions by way of SA/GPA/will are
    unwarranted and not justified, unintendedly misleading the general public
    into thinking that SA/GPA/will transactions are some kind of a recognised
    or accepted mode of transfer and that it can be a valid substitute for a sale
    deed. Such decisions to the extent they recognise or accept SA/GPA/will
    transactions as concluded transfers, as contrasted from an agreement to
    transfer, are not good law.

    24. We therefore reiterate that immovable property can be legally and
    lawfully transferred/conveyed only by a registered deed of conveyance.

    Transactions of the nature of “GPA sales” or “SA/GPA/will transfers” do not
    convey title and do not amount to transfer, nor can they be recognised or
    valid mode of transfer of immovable property. The courts will not treat such
    transactions as completed or concluded transfers or as conveyances as
    they neither convey title nor create any interest in an immovable property.
    They cannot be recognised as deeds of title, except to the limited extent of
    Section 53-A of the TP Act. Such transactions cannot be relied upon or
    made the basis for mutations in municipal or revenue records. What is
    stated above will apply not only to deeds of conveyance in regard to
    51/63
    CCCA.NO.96 OF 2019
    AND
    I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019

    freehold property but also to transfer of leasehold property. A lease can be
    validly transferred only under a registered assignment of lease. It is time
    that an end is put to the pernicious practice of SA/GPA/will transactions
    known as GPA sales.

    42.7 In Vasavi Cooperative Housing Society Limited12 Supreme Court

    observed at paragraph No.15 as under:

    The legal position, therefore, is clear that the plaintiff in a suit for
    declaration of title and possession could succeed only on the strength of its
    own title and that could be done only by adducing sufficient evidence to
    discharge the onus on it, irrespective of the question whether the
    defendants have proved their case or not. We are of the view that even if the
    title set up by the defendants is found against, in the absence of
    establishment of plaintiff’s own title, plaintiff must be non-suited.

    42.8 In Vinod Infra Developers Limited13, matter partings to rejection of

    plaint. Hence, the same is not applicable to the case facts.

    42.9 In Hemalatha14, Supreme Court observed at paragraph No.31 as

    under:

    It is a settled position of law that a registered Sale Deed carries with it a
    formidable presumption of validity and genuineness. Registration is not a
    mere procedural formality but a solemn act that imparts high degree of
    sanctity to the document. Consequently, a Court must not lightly or
    casually declare a registered instrument as a “sham”

    42.10 In Bayyarapu Narayan Raidu15, High Court of AP, observed

    at paragraph No.20 as under:

    52/63

    CCCA.NO.96 OF 2019
    AND
    I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019

    20.When it is not necessary as per the provisions of the Limitation Act,
    1963
    twelve years from the date of his dispossession, it is not necessary to
    decide the issue when the plaintiff was dispossessed from the plaint
    schedule property. Therefore, in my opinion, the lower appellate court erred
    in remanding the matter to the trial court to frame and decide the issue
    “when the plaintiff was disposed from the plaint schedule property”. When
    there is no plea of adverse possession raised by the defendant, there is also
    no need to decide the issue whether the suit is barred by limitation.

    42.11 In Saved Sirajul Hasan16, High Court of Delhi, observed that

    “legal representative had the right to make the defense and to file

    written statement.”

    43. It is apt to refer Order VIII Rule 6 (A)(1) and Order VIII Rule 9 of

    CPC, which reads as under:

    6A. Counter-claim by defendant.–(1) A defendant in a suit may, in addition
    to his right of pleading a set-off under rule 6, set up, by way of counter-
    claim against the claim of the plaintiff, any right or claim in respect of a
    cause of action accruing to the defendant against the plaintiff either
    before or after the filing of the suit but before the defendant has delivered
    his defence or before the time limited for delivering his defence has
    expired, whether such counter-claim is in the nature of a claim for
    damages or not:

    Provided that such counter-claim shall not exceed the pecuniary limits of
    the jurisdiction of the court.

    9. Subsequent pleadings.–No pleading subsequent to the written
    statement of a defendant other than by way of defence to set-off or counter-

    claim shall be presented except by the leave of the Court and upon such
    terms as the Court thinks fit; but the Court may at any time require a
    written statement or additional written statement from any of the parties
    and fix a time of not more than thirty days for presenting the same.
    53/63

    CCCA.NO.96 OF 2019
    AND
    I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019

    44. Ex.A37 is the agreement of construction dated 18.02.1994

    executed by and between defendant No.1 and plaintiff. The recitals goes

    to show that developer shall construct flat No.2 on the first floor with a

    super built up area of 1650 sq.fts. Clause – 3 of the agreement states

    that flat No.2 in the ground floor is intended for commercial use as

    described in the schedule – B as per the specifications set out in

    annexure – II. Clause IX of the construction agreement states that the

    construction shall be completed in all aspects as per specifications on

    flat No.2 on the ground floor with parking on or before 31.12.1994.

    Payment schedule is shown in annexure – I. It is to be noted here that in

    clause V sub clause 4 it is mentioned that purchaser has approached

    the developer for sale to him/her i.e., 1/40th undivided share in

    schedule “A” property and the same has been agreed to between the

    developer and the purchaser under a separate agreement of sale dated

    18.02.1994. Agreement of sale is dated 18.02.1994 and agreement of

    construction is on the same day.

    45. Ex.A29 is the sale deed of the plaintiff dated 23.07.1994. In

    internal page No.5 there is a reference to an agreement of sale and

    agreement of construction between the parties.
    54/63

    CCCA.NO.96 OF 2019
    AND
    I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019

    46. Ex.A27 receipt dated 18.10.1994 goes to show that full payment

    for car parking is made for flat No.103. Under Ex.A28 plaintiff addressed

    letter to defendant No.1 through executive director that flat has to be

    ready by 31.12.1994 for possession. Ex.A36 letter dated 19.10.1994 is

    issued by defendant No.1 to plaintiff stating that brick work of flat

    bearing No.103 is completed. Prior to executing Ex.A29 sale deed dated

    23.07.1994 plaintiff has entered into agreement of sale and agreement of

    construction on 18.02.1994 itself which is reflected in Ex.A29 so also in

    Ex.A37 with regard to agreement of sale. As per Ex.A3 – legal notice got

    issued by defendant No.2 to M/s.Consortium Management Services

    Limited wherein he stated that after purchase of the property under

    Ex.B1 he locked the same as he being the permanent resident of

    Mumbai and when he came to Hyderabad in first week of August 2006

    he was shocked to find that M/s.Consortium Management Services

    Limited was in possession. As per Ex.B1 defendant No.2 sale deed is

    dated 08.07.2002, there is no record to show that what has transpired

    between 2002 to August 2006. Defendant Nos.3 to 5 have not filed any

    document except Exs.B1 and B2 to show that possession of flat No.103

    was delivered to defendant No.2 by Riviera apartments.

    47. As stated supra M/s.Consortium Management Services Limited

    was in occupation of flat No.103 and Riviera apartment owners’ welfare
    55/63
    CCCA.NO.96 OF 2019
    AND
    I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019

    association have got issued Exs.A6 to A10 in respect of flat No.103.

    Plaintiff has also paid maintenance charges to Riviera Apartment

    Owners’ welfare association which are evident from Exs.A40 to A84

    showing the name of the plaintiff with flat No.103. Exs.A15 to A27, A32,

    A35 and A39 are of the year 1994 of different dates and different months

    showing the payments made by plaintiff to defendant No.1. Ex.A29 sale

    deed came to be executed in favour of the plaintiff with regard to

    undivided 1/40th share.

    48. Ex.A2 confirms the delivery of possession of flat No.103 to the

    plaintiff. Though date is not mentioned in Ex.A2 but possession of the

    flat No.103 is given to the plaintiff by defendant No.1, in pursuance of

    which plaintiff and his tenant have paid Riviera apartment owners’

    welfare association maintenance charges

    49. Ex.A107 is the deposition of B.Govinda Reddy managing director

    of defendant No.1. In his cross examination in O.S.No.2288 of 2005 he

    stated that amount covered under the receipts pertains to construction

    of flat No.103 in Riviera apartments. In 2001 construction was

    completed and possession of the schedule flat was delivered to the

    plaintiff. Though learned counsel for defendant Nos.3 to 5 has raised

    objection with regard to marking of Ex.A107 the learned Trial Court has

    rejected the same and got marked the deposition.
    56/63

    CCCA.NO.96 OF 2019
    AND
    I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019

    50. Learned senior counsel has also raised similar objection in the

    appeal in his written arguments contending that it is barred under

    Section 33 of the Indian Evidence Act. The learned Trial Court has

    already decided the said issue.

    51.1 As per Ex.B1 the property claimed by defendant No.2 is flat

    No.103 admeasuring 1800 sq.fts. Delivery of possession was given on

    08.07.2002. There is no explanation from defendant Nos.3 to 5 why the

    property was kept locked right from 08.07.2002 to 07.10.2006 [date of

    issuing legal notice] when defendant No.2 came down to Hyderabad in

    the month of August, 2006. DW1 admitted in her cross examination

    that she has not filed any document except Exs.B1 and B2.

    51.2 Learned senior counsel for defendant Nos.3 to 5 submits that

    Ex.A14 – written statement is filed by defendant No.1 in O.S.No.2288 of

    2005 after the execution of Ex.B1- sale deed dated 08.07.2002 in favour

    of defendant No.2. Ex.B1 is neither challenged by defendant No.1 and

    the plaintiff. It is to be noted here that Ex.A27 receipt dated 18.10.1994,

    Ex.A34 – receipt dated 01.03.2001 and Ex.A36 – letter dated 19.10.1994

    shows the flat No.103, which receipts were issued by defendant No.1 in

    favour of the plaintiff. The above said receipts are in the year 1994 and

    2001 much prior to Ex.B1. Hence the contention of the senior counsel is

    negatived.

    57/63

    CCCA.NO.96 OF 2019
    AND
    I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019

    52. Defendant Nos.3 to 5 have filed their counter claim with the leave

    of the Court with additional written statement, which permission is

    accorded by the learned Trial Court in I.A.No.912 of 2017 dated

    29.01.2018 by which time PW1 and PW2 were cross examined. After

    filing of the counter claim by defendant Nos.3 to 5, they have not

    recalled PW1 and PW2 to put forth their defence that they are entitled

    for declaration and recovery of possession. PW1 and PW2 were not cross

    examined by learned counsel for defendant Nos.3 to 5 in respect of the

    counter claim schedule property except the evidence of DW1. Though

    PW2 was recalled for marking Exs.A105 to A107, even then defendant

    Nos.3 to 5 failed to put any questions with regard to the defence taken

    by them in their additional written statement and counter claim.

    53. The learned Trial Court has misread the evidence of the parties

    and drawn an adverse inference against the plaintiff for not filing the

    agreement of sale dated 18.02.1994.

    54. The admissions made by the managing director of defendant No.1

    in O.S.No.2288 of 2005 under Ex.A107 is sufficient to come to a

    conclusion that flat No.103 was delivered to the plaintiff which is

    supported with Riviera apartment owner’s welfare association receipts

    towards maintenance (Exs.A6 to A9, A40 to A84) with that of the

    property tax and electricity bills (Exs.A5, A13, A94, A96, A98, A100 and
    58/63
    CCCA.NO.96 OF 2019
    AND
    I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019

    A102) Furthermore the suit filed by the plaintiff in O.S.No.2288 of 2005

    in respect of Falt No.103 came to be decreed under Exs.A105 and A106.

    Though defendant No.2 is not a party to the said suit in view of the

    admission made by the managing director of the defendant No.1, when

    the property is delivered to the plaintiff in the year 2001 with regard to

    flat No.103, it is the defendant Nos.3 to 5, to explain how Ex.B1 came

    into existence. Though there is a discrepancy with regard to mentioning

    of flat numbers in Ex.A37, the receipts filed by the plaintiff shows that

    flat No.103 is delivered to him by the defendant No.1 in the ground floor.

    55.1 T.K.Mohammed Abubucker1 is not applicable to the case on hand

    as the facts are distinguishable from the facts of the present case.

    55.2 The decision in Duraiswami Reddi4 is not applicable to the case on

    hand in view of the fact that Ex.A29 sale deed dated 23.07.1994 is in

    respect of undivided 1/40th share in 2000 sq.yds equivalent to 50 sq.yds

    or 41.806 sq.mts in MCH.No.6-3-347/9. Ex.B1 sale deed dated

    08.07.2002 is in respect of Flat No.103.

    56.1 Since plaintiff is holding registered documents in his favour under

    Ex.A29 for undivided 1/40th share in 2000 sq.yds in H.No.6-3-347/9

    and defendant Nos.3 to 5 are holding Ex.B1-sale deed in respect of Flat

    NO.103. Both the above said documents are registered sale deeds, hence
    59/63
    CCCA.NO.96 OF 2019
    AND
    I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019

    the decisions in Prem Singh9 and Hemalatha14 are not applicable to the

    case on hand as the facts are distinguishable.

    56.2 Suraj Lamp and Industries Private Limited11 is not applicable to

    the case on hand as the facts are distinguishable.

    57. Plaintiff and defendant Nos.3 to 5 are claiming their title through

    defendant NO.1. Plaintiff could able to prove title over the suit schedule

    property with the evidence of PW1, PW2, Exs.A27, A29, A34, A36, A105

    – A107 and other documents i.e., Exs.A6-A9, A40 to A84 with that of

    electricity bills i.e., Exs.A5, A13, A94, A96, A98, A100 and A102.

    Defendant Nos.3 to 5 failed to prove their title, hence Vasavi Co-

    operative Housing Society Limited12 goes against defendant Nos.3 to 5

    case.

    58. This Court is of the view that the learned Trial Court has misread

    the evidence of PW1, PW2 with that of the documents marked thereon.

    The learned Trial Court has not appreciated the evidence in proper

    perspective by taking into consideration the documents marked on

    behalf of the plaintiff with that of the admissions made by the managing

    director of the defendant No.1 under Ex.A107 and erroneously came to a

    conclusion that the plaintiff failed to prove his case and that he is not
    60/63
    CCCA.NO.96 OF 2019
    AND
    I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019

    entitled for declaration and allowed the counter claim filed by defendant

    Nos.3 to 5.

    59. As stated supra, no suggestion is put by learned counsel for

    defendant Nos.3 to 5 before the learned Trial Court to PW1 and PW2

    about the counter claim schedule property and they have not cross

    examined PW1 and PW2 on the said aspect. Taking into consideration

    the totality of the circumstances, this Court is of the view that the

    judgment and decree passed by the learned Trial Court and in allowing

    the counter claim filed by defendant Nos.3 to 5 suffers from perversity

    and illegality and the same are liable to be set aside and are accordingly

    set aside. Hence points are answered accordingly.

    Point No.v:

    60. The learned Trial Court in paragraph No.28 of its judgment

    observed that counter claim filed by defendant Nos.3 to 5 is within time

    as per Article 65 of the Limitation Act and the learned Trial Court

    further observed that the plaintiff company did not specify as to how the

    counter claim of defendant Nos.3 to 5 is barred by limitation, the period

    of limitation to file suit for recovery of possession of the property is 12

    years and therefore, the counter claim filed by defendant Nos.3 to 5 on

    19.09.2017 is within the prescribed period of limitation from the date

    when the defendant No.2 noticed that M/s. Consortium Management
    61/63
    CCCA.NO.96 OF 2019
    AND
    I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019

    Services Private Limited is in occupation of the schedule flat in the first

    week of August, 2006.

    61. At the cost of repetition, defendant No.5 has filed adoption memo

    on 09.11.2016, defendant No.3 has filed adoption memo on 07.12.2016

    and defendant No.4 has filed adoption memo on 22.12.2016 adopting

    the written statement filed by defendant No.2.

    62. The learned Trial Court has returned the additional written

    statement and counter claim filed by defendant No.3 on 30.11.2017

    raising office objection as:

    1. —-

    2. State how the counter claim is maintainable after the issues are settled
    and after trial is commenced.

    63. Counter claim came to be received by the learned Trial Court on

    29.01.2018 by allowing I.A.No.912 of 2017. On close reading of Order

    VIII Rule 6(a) of CPC it states that a defendant in a suit may in addition

    to his right of pleading a set-off, under Rule 6, set up, by way of

    counter-claim against the claim of the plaintiff, any right or claim in

    respect of cause of action accruing to the defendant against the plaintiff

    either before or after the filing of the suit but before the defendant has

    delivered his defence or before the time limited for delivering his defence

    has expired, whether such counter claim is in the nature of a claim for

    damages or not.

    62/63

    CCCA.NO.96 OF 2019
    AND
    I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019

    64. Written statement of defendant No.2 is filed on 08.12.2006, issues

    came to be framed on the same day.

    65. In Ashok Kumar Karla2 [Three Judge Bench of the Supreme Court

    on reference] has held that the restriction is only with respect to the

    approval of cause of action, it does not give absolute right to the

    defendant to file counter claim with substantive delay, even if the

    limitation period prescribed has not elapsed. The Court has to take into

    consideration the outer limit for filing counter claim which is pegged till

    the issues are framed.

    66. In Ashok Kumar Karla3 the Supreme Court held that counter

    claim cannot be filed after issues are framed. The above said judgment

    is squarely applicable to the case on hand. The decision in Gopaldas

    and company5 is not applicable to the facts of the case as facts differ.

    67. The decision in Jagdish Chander Chatterjee6, Bal Kishan7, Saroop

    Singh8, Sumtibai10, Bayyarapu Narayan Raidu15 and Saved Sirajul

    Hasan16 are distinguishable from the facts of the present case and they

    are not applicable to the case on hand.

    68. Counter claim filed by defendant Nos.3 to 5 is with a substantive

    delay. The learned Trial Court failed to look into the outer limit for filing
    63/63
    CCCA.NO.96 OF 2019
    AND
    I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019

    counter claim which has to be pegged till the issues are framed. Hence

    point is answered accordingly.

    Point Nos.vi & vii:

    69. In view of the reasons in point Nos. i to iv the judgment and

    decree passed by the learned Trial Court in dismissing the suit filed by

    the plaintiff and allowing the counter claim filed by defendant Nos.3 to 5

    in O.S.No.1736 of 2006 dated 17.12.2018 suffers from perversity and

    illegality, the same are liable to be set aside and are accordingly set

    aside. Hence points are answered accordingly.

    70. In the result CCCA.No.96 of 2019 and CCCA.No.116 of 2019 are

    allowed and the judgment and decree passed by the learned V Senior

    Civil Judge, City Civil Court, Hyderabad, in O.S.No.1736 of 2006 dated

    17.12.2018 and in allowing the counter claim filed by defendant Nos.3

    to 5, are set aside. Consequently the suit filed by the plaintiff is decreed

    as prayed for and the counter claim filed by defendant Nos.3 to 5 is

    dismissed.

    71. I.A.No.1 of 2025 is also dismissed without costs.

    Interim orders if any stands vacated. Miscellaneous petition/s if

    any stands closed.

    64/63

    CCCA.NO.96 OF 2019
    AND
    I.A.NO.1 OF 2025 IN/AND CCCA.NO.116 OF 2019

    _______________________________________
    JUSTICE B.R.MADHUSUDHAN RAO
    07.07.2026
    Dua



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here