Bollu Sammi Reddy vs The State Of Telangana on 7 April, 2026

    0
    55
    ADVERTISEMENT

    Telangana High Court

    Bollu Sammi Reddy vs The State Of Telangana on 7 April, 2026

    Author: Nagesh Bheemapaka

    Bench: Nagesh Bheemapaka

                                            1
                                                                        wp_26406_2025
                                                                                NBK, J
    
    
        IN THE HIGH COURT FOR THE STATE OF TELANGANA
                        AT HYDERABAD
    
    
          THE HON'BLE SRI JUSTICE NAGESH BHEEMAPAKA
    
    
                      WRIT PETITION No. 26406 of 2025
    
    
                                  07thApril, 2026
    Between:
    1. Bollu Sammi Reddy, and others
                                                                    ... Petitioners
                                        AND
    1. The State of Telangana, and others
                                                                  ... Respondents
    ORDER:

    The case of the petitioners, precisely as per the writ affidavit, is that
    they are small and marginal farmers whose primary livelihood comes from
    cultivating their agricultural lands in Oorugonda village. The subject lands
    are also highly valuable due to their proximity to developing urban
    infrastructure such as the Warangal outer ring road and existing highways.
    A preliminary acquisition notification was issued under Section 3A of the
    National Highways Act through Gazette Notification No. 1102(E) dated
    10.03.2021, which was published in newspapers on 25.03.2021. This
    notification proposed acquisition of lands in approximately ten villages
    across the Parkal, Shayampet, and Damera mandals for constructing a
    four-lane greenfield highway forming part of the NH-163G project,
    covering the stretch from Km 88.418 to Km 111.762 within the then
    2
    wp_26406_2025
    NBK, J

    Warangal (Rural) District, later renamed Hanumakonda District. The
    petitioner states that the notification failed to provide landowner-wise
    details and instead merely listed survey numbers and extents without
    adequate descriptions, maps, or plans. As a result, affected landowners
    lacked the information necessary to determine the precise extent of
    acquisition affecting their individual holdings and were thereby prevented
    from filing meaningful objections. The petitioner further claims that the
    authorities did not make maps available at the office of the competent
    authority as indicated in the notification, nor did they conduct any Gram
    Sabha meetings or other local consultations to inform affected residents.
    Despite this lack of information, some affected landowners–including
    some of the petitioners–submitted common objections to the authorities.

    SPONSORED

    1.1. During the same period, an environmental impact assessment
    process was undertaken, and a public hearing was held in which many
    affected villagers recorded objections to the project. After that hearing, the
    petitioner states that the landowners received no further communication for
    nearly a year. They subsequently became aware of a public notice dated
    04.02.2023, published in newspapers on 15.02.2023, issued under Section
    3G
    of the National Highways Act, requiring them to appear before the
    competent authority on various dates between 23.02.2023 and 09.03.2023
    to present their compensation claims. According to the petitioners, it was
    only through this notice that they learned of the issuance of a declaration
    under Section 3D via Gazette Notification No. 1017 dated 08.03.2022,
    confirming the acquisition of their lands. The petitioners asserts that this
    declaration had never been properly published in local newspapers or
    circulated within the affected locality, and that affected landowners
    therefore lacked timely knowledge of the acquisition proceedings.

    3

    wp_26406_2025
    NBK, J

    Following this discovery, the landowners submitted representations to the
    authorities demanding that the process be halted and pointing out alleged
    procedural irregularities.

    1.2. In response to these developments, certain affected persons
    from several villages in Damera Mandal–including residents of
    Oorugonda–approached this Court by filing W.P. No. 5187 of 2023,
    challenging the validity of the Section 3D declaration and the
    compensation inquiry notice under Section 3G. Their challenge was based
    on the allegation that these steps had been taken before obtaining
    environmental clearance for the project, which they argued was contrary to
    the law laid down by the Hon’ble Supreme Court. This Court initially
    granted a stay on further proceedings for more than six months. However,
    during the pendency of that writ petition, environmental clearance for the
    highway project was eventually obtained, and this Court consequently
    dismissed the petition in October 2023. It is stated that the affected
    landowners subsequently filed Writ Appeal No. 1190 of 2023, which
    remains pending. After dismissal of the writ petition, the authorities
    resumed the acquisition process and proceeded to issue compensation
    notices and awards.

    1.3. It is stated that further complications arose when authorities
    began issuing notices under Section 3E demanding that landowners
    surrender possession of their lands even before providing copies of the
    compensation awards. In April 2024, some landowners from Oorugonda
    village filed W.P. No. 9909 of 2024, contesting multiple acquisition
    notifications–including Section 3A notifications S.O. No. 1102 dated
    10.03.2021 and S.O. No. 1905 dated April 21, 2022, Section 3D
    notifications No. 1017 dated 08.03.2022 and No. 3526 dated 29.07.2022,
    4
    wp_26406_2025
    NBK, J

    the Section 3G public notice dated 04.02.2023, and an unnumbered notice
    dated 13.01.2024 relating to the same lands. In that proceeding, this Court
    issued interim protection against dispossession through an order dated
    03.05.2024, and those orders have reportedly been extended from time to
    time and remain in force. Because the lands involved in that litigation are
    adjacent to the petitioners’ lands and arise from the same acquisition
    notifications, the petitioner believed that the authorities would not attempt
    to dispossess them until the legal issues were finally resolved. Meanwhile,
    the petitioner asserts that despite repeated requests, copies of the
    compensation awards were not provided until February 2025, after several
    written representations were submitted.

    1.4. It is alleged that even after receiving the awards, the
    authorities failed to address the concerns raised in those representations.
    Beginning around June-July 2025, workmen accompanied by police
    personnel allegedly entered the petitioners’ lands and warned them not to
    cultivate the land during the current agricultural season. The petitioners
    claim that officials also imposed deadlines on landowners to accept
    compensation by the end of the month, warning that if payment was not
    accepted the money would be deposited in court and possession of the land
    would nevertheless be taken. It is stated that the authorities never
    communicated the decision on those objections. Only after obtaining the
    full case records, including the counter-affidavits filed by the authorities in
    earlier litigation, did the petitioners obtain a copy of the disposal order in
    Proceedings No. B/85/2021 dated 20.11.2021. According to the petitioners,
    a review of that order demonstrates that the competent authority failed to
    independently examine the objections and instead issued a non-reasoned
    decision without proper application of mind. The petitioner also alleges
    5
    wp_26406_2025
    NBK, J

    that the government issued multiple Section 3A notifications–dated
    10.03.2021 and 08.05.2022–with incomplete or inconsistent information,
    without clarifying whether the later notification represented an additional
    acquisition or a change in alignment. It is stated that these notifications
    were published only in the newspapers “Mana Telangana” and “The
    Hindu,” which allegedly have limited circulation in the affected villages,
    and that the authorities did not publish the substance of the notifications
    locally or conduct any Gram Sabha meetings as is customary under land
    acquisition procedures.

    1.5. It is contended that the authorities incorrectly relied on
    Section 3G of the National Highways Act, 1956 to determine
    compensation, despite the fact that the Removal of Difficulties Order dated
    28.08.2015 under the Right to Fair Compensation and Transparency in
    Land Acquisition, Rehabilitation and Resettlement Act, 2013
    extends the
    compensation and rehabilitation provisions of that Act to acquisitions
    carried out under other enactments listed in its Fourth Schedule, including
    the National Highways Act. According to the petitioners, this legal
    framework requires that compensation be determined in accordance with
    Sections 21 to 30 of the 2013 Act and that rehabilitation and resettlement
    benefits be determined under Sections 16 to 18, 23, and 31, along with the
    First, Second, and Third Schedules of that Act. It is stated that the
    competent authority failed to follow these procedures and did not conduct
    the required award enquiry or prepare a rehabilitation and resettlement
    scheme. Additionally, the District Collector did not revise the market value
    of the lands under Section 26 prior to issuing the acquisition notification,
    and that land valuation rates had not been revised since 2013. The
    petitioner further alleges that two different compensation rates were
    6
    wp_26406_2025
    NBK, J

    applied to awards issued in January 2024 merely because the relevant
    Section 3A notifications were issued one year apart, resulting in
    discriminatory treatment among landowners within the same village for the
    same highway project.

    1.6. It is stated that the awards themselves are incomplete because
    they fail to determine compensation for trees, structures, and other assets
    located on the acquired lands. The authorities neither conducted a proper
    enumeration of trees and structures nor issued notices to the landowners
    regarding their valuation. It is contended that, under the applicable legal
    framework, possession of land cannot be taken until full compensation–
    including compensation for structures and trees as well as any applicable
    rehabilitation entitlements–has been determined and offered to affected
    landowners. Nevertheless, the officials and contractors have continued to
    enter the fields to mark and clear land, asserting that the petitioners’ lands
    are not covered by the interim orders previously granted by this Court. The
    petitioners therefore seek to declare the impugned notifications and awards
    illegal, and restrain the authorities from taking possession of the
    petitioners’ lands until lawful procedures for acquisition, compensation
    determination, and rehabilitation are properly followed.

    2. A counter-affidavit is filed by the 3rd respondent-Revenue Divisional
    Officer (RDO), Parkal, Hanumakonda District, essentially contending that
    the acquisition of lands in Oorugonda Village, Damera Mandal,
    Hanumakonda District for the construction of National Highway-163G
    was conducted strictly in accordance with the National Highways Act,
    1956
    and the applicable provisions of the Right to Fair Compensation and
    Transparency in Land Acquisition, Rehabilitation and Resettlement Act,
    7
    wp_26406_2025
    NBK, J

    2013. The compensation award issued in Proceedings No. B/85/2021-10-
    NH-163G dated 16.01.2024, the notice issued under Section 3G dated
    04.02.2023, and the subsequent steps toward taking possession under
    Section 3E are lawful actions undertaken after following the full statutory
    procedure.

    2.1. The respondent explains that the highway project forms part
    of a major economic corridor linking several states. Specifically, the
    Nagpur-Vijayawada Greenfield alignment was proposed as a component
    of the economic corridor under the National Highways programme,
    connecting the states of Maharashtra, Telangana, and Andhra Pradesh. This
    alignment decision was taken during a Land Acquisition Committee
    meeting of the headquarters of the concerned highway authority on
    03.09.2020, after technical evaluation of site conditions and engineering
    parameters, and once such an alignment is approved by the competent
    authority of the project proponent, it cannot be arbitrarily altered.

    2.2. The respondent further states that the Revenue Divisional
    Officer, Parkal, was formally designated as the Competent Authority for
    Land Acquisition within the jurisdiction of the Parkal Revenue Division
    through Gazette Notification No. 3099 dated 27.08.2019. Following the
    requisition submitted by the project authorities, a preliminary notification
    under Section 3A of the National Highways Act was issued through
    Gazette Notification No. 1102(E) dated 10.03.2021, proposing the
    acquisition of lands in ten villages, including Oorugonda, for the
    construction of the four-lane access-controlled greenfield highway from
    Km 88.418 to Km 111.762. The respondent asserts that the statutory
    requirements for publication were fulfilled because the substance of the
    notification was published on 25.03.2021 in the newspapers “Mana
    8
    wp_26406_2025
    NBK, J

    Telangana” (Telugu) and “The Hindu” (English), which meet the legal
    requirement that acquisition notices be published in two newspapers,
    including one in a vernacular language.

    2.3. The notification invited objections from landowners and
    interested persons within 21 days as required under Section 3A(3) of the
    Act. In response, a few persons, including the 5thpetitioner, filed objections
    under Section 3C within the prescribed period. It is stated that these
    objections were duly examined. Notices were issued to the objectors,
    hearings were conducted, and the petitioners were given an opportunity to
    present their concerns. After considering those objections, the Competent
    Authority rejected them through Proceedings No. B/85/2021 dated
    20.11.2021 under Section 3C(2) of the Act. Subsequently, the Central
    Government issued the declaration of acquisition under Section 3D
    through Gazette Notification S.O. No. 1017(E) dated 08.03.2022, thereby
    confirming that the land stood acquired for the project.

    2.4. Certain landowners filed W.P. No. 5187 of 2023, alleging that
    acquisition steps had been taken without obtaining environmental
    clearance. This Court initially granted an interim stay on 26.02.2023.
    However, the Ministry of Environment, Forest and Climate Change
    granted environmental clearance on 05.07.2023. After the environmental
    clearance was issued, this Court dismissed the writ petition on 26.09.2023.
    Although the petitioners subsequently filed Writ Appeal No. 1190 of 2023,
    no interim stay has been granted in that appeal.

    2.5. It is stated that while preparing subdivision records prior to
    issuing the final declaration under Section 3D, officials discovered that
    certain extents of land lying within the approved alignment had been
    inadvertently omitted from the original Section 3A notification dated
    9
    wp_26406_2025
    NBK, J

    10.03.2021. To rectify this omission, an additional Section 3A notification
    was issued through S.O. No. 1905(E) dated 21.04.2022, covering only the
    previously omitted land without overlapping the earlier acquisition. After
    following the same procedure for objections under Section 3C, further
    notifications were issued under Section 3D through S.O. No. 3526(E)
    dated 29.07.2022, and the public notice for determination of compensation
    under Section 3G was issued through Rc. No. B/85/2021 dated 09.01.2024,
    which was published in newspapers on 13.01.2024. The issuance of
    additional notifications was a technical correction to include missing
    extents within the approved alignment and does not constitute any legal
    irregularity.

    2.6. Regarding compensation, it is stated that the Competent
    Authority passed the main award on 16.01.2024, through Proceedings No.
    B/85/2021-10-NH-163G, determining compensation in accordance with
    the National Highways Act and the applicable provisions of the 2013 land
    acquisition law. The respondent emphasizes that compensation calculations
    included statutory benefits such as 100% solatium, 12% additional market
    value from the date of the Section 3A notification until the date of the
    award, and a multiplication factor of 1.5 applied to the land value, as
    required under Sections 26 to 30 of the 2013 Act. It is stated that if any
    landowner is dissatisfied with the compensation amount, the aggrieved
    party may approach the Arbitrator under Section 3G(5) of the National
    Highways Act, and thereafter challenge the arbitral decision before the
    competent District Court under Section 34 of the Arbitration and
    Conciliation Act, 1996. It is stated that Arbitrator-cum-District Collector of
    Hanumakonda reviewed the compensation rates fixed by the Competent
    Authority and enhanced the market value for lands in all ten affected
    10
    wp_26406_2025
    NBK, J

    villages, including Oorugonda village, through Appeal No. G/1371/2024-1
    dated 17.10.2025. The enhanced compensation amounts have already been
    disbursed to landowners who accepted payment. The respondent explains
    that differences in compensation rates arose because the original Section
    3A
    notification was issued on 10.03.2021, while the additional Section 3A
    notification was issued on 21.04.2022. Since the law requires that market
    value be calculated on the basis of sale transactions occurring within three
    years preceding the respective notification, different notification dates
    inevitably produced different valuation benchmarks. The respondent
    argues that such differential rates are legally justified and do not constitute
    discrimination.

    2.7. It is stated that after obtaining evaluations from various
    technical departments–including the Executive Engineer of the MB Intra
    Division, Hanumakonda, the District Horticulture and Sericulture Officer,
    the District Roads and Buildings Officer, and the District Forest Officer–
    the Competent Authority issued a supplementary award on 28.05.2025,
    through Proceedings No. B/85/2021-10-NH-163G-Structure, specifically
    determining compensation for trees and structures located on the acquired
    lands. The respondent therefore denies the allegation that the award was
    incomplete. The Removal of Difficulties Order dated 28.08.2015, issued
    under the 2013 land acquisition law does not render Section 3G of the
    National Highways Act obsolete. Instead, it merely makes certain
    provisions of the 2013 Act–particularly those relating to the calculation of
    compensation under Sections 26 to 30 and certain limited rehabilitation
    benefits–applicable to acquisitions under the National Highways Act. The
    respondent argues that the petitioners are deliberately misinterpreting the
    law by claiming that the entire procedural framework of the 2013 Act,
    11
    wp_26406_2025
    NBK, J

    including provisions relating to social impact assessments and
    rehabilitation schemes under Sections 16 to 18, 21, and 23, must be applied
    to highway acquisitions. It is contended that those provisions are not
    applicable because highway projects are linear infrastructure projects in
    which land acquisition is confined to a narrow Right of Way, typically
    causing minimal displacement of affected families. Therefore, large-scale
    resettlement and rehabilitation schemes are generally unnecessary.

    2.8. It is contended that once a declaration under Section 3D of the
    National Highways Act is published in the Gazette, the land vests
    absolutely in the Central Government free from all encumbrances. In the
    present case, final declarations were published on 08.03.2022, 29.07.2022,
    and 23.08.2023, and that under Section 3D(4)such declarations cannot be
    challenged before any court or authority. The respondent further points out
    that out of 1,035 total awardees affected by the acquisition, 859
    landowners have already accepted the compensation and received
    payment, while only the petitioners and a few others have refused to do so.
    The respondent therefore alleges that the present writ petition has been
    filed with the intention of obstructing or delaying the land acquisition
    process rather than addressing any genuine legal grievance, and therefore
    the writ petition as devoid of merit.

    3. A counter-affidavit is filed by the Project Director of the Project
    Implementation Unit, Warangal, on behalf of Respondent Nos. 6 and 7
    essentially contending that the NHAI initiated a project to construct a four-
    lane greenfield national highway between Mancherial and Warangal,
    covering the stretch from Km 88.418 to Km 111.762, including lands
    situated in Oorugonda Village of Damera Mandal in Hanumakonda
    12
    wp_26406_2025
    NBK, J

    District. The project was conceived as a greenfield corridor because it
    would shorten travel distance, reduce vehicle operating costs, decrease
    travel time, and stimulate economic development in the adjoining regions.
    In furtherance of the project, the NHAI submitted a requisition for
    acquisition of land under Section 3A(1) of the National Highways Act.
    Acting on that requisition, the competent authority issued a preliminary
    acquisition notification through S.O. No. 1102(E) dated 10.03.2021,
    proposing acquisition of lands including those belonging to the petitioners.
    The substance of this notification was published in the newspapers Mana
    Telangana (Telugu) and The Hindu (English) on 25.03.2021, thereby
    inviting objections from landowners within the statutory period of 21
    days.The respondent asserts that no objections were received within the
    stipulated period under Section 3C following publication of the
    notification. Consequently, the Central Government issued the declaration
    of acquisition under Section 3D through S.O. No. 1017(E) dated
    08.03.2022, which legally vested the land in the Central Government free
    from all encumbrances. Once a declaration under Section 3D is published,
    the land automatically vests in the government and cannot be encumbered
    by private claims. Subsequently, environmental clearance for the project
    was granted by the Ministry of Environment, Forest and Climate Change
    on 05.07.2023, thereby removing any regulatory impediment to the
    project’s execution.

    3.1. As required under Section 3G(3) of the National Highways
    Act, a public notice dated 15.02.2023 was published in the newspapers
    Mana Telangana and The Hindu, calling upon interested persons to appear
    before the Revenue Divisional Officer acting as the Competent Authority
    for Land Acquisition and to submit documentary evidence of their claims.

    13

    wp_26406_2025
    NBK, J

    The notice required landowners to appear before the authority on
    06.03.2023 during office hoursfor the purpose of establishing title and
    claiming compensation. After conducting the statutory award enquiry, the
    Competent Authority passed the compensation award through Proceedings
    No. B/85/2021-10-NH-163G dated 16.01.2024.

    3.2. The compensation determined in the award was calculated
    strictly in accordance with the statutory framework. The award
    incorporated benefits mandated by the RFCTLARR Act, including 100%
    solatium, 12% additional market value calculated from the date of
    publication of the Section 3A notification until the date of the award, and a
    1.5 multiplication factor applied to the land value. The respondent further
    states that the compensation amount determined under the award has
    already been deposited by the NHAI with the competent authority as
    required under Section 3H of the National Highways Act. The respondent
    also indicates that a supplementary award would be passed for valuation of
    structures such as trees and borewells after completion of the necessary
    departmental assessments. It is stated that additional Section 3A
    notification was issued only to cover missing extents of land that were
    inadvertently left out of the earlier notification and did not overlap with
    previously notified land. The respondent further rejects the allegation that
    the newspapers used for publication lacked sufficient circulation, stating
    that publication in two newspapers–one vernacular and one English–
    fully satisfies the statutory requirement under the National Highways Act.

    3.3. The respondent also denies the petitioners’ allegation that the
    Section 3D notification dated 08.03.2022 was based on an invalid report or
    that objections were not properly considered. The respondent disputes the
    petitioners’ argument that Section 3G of the National Highways Act has
    14
    wp_26406_2025
    NBK, J

    ceased to operate due to the Removal of Difficulties Order dated
    28.08.2015 issued under the 2013 land acquisition law. The respondent
    asserts that only certain compensation-related provisions of the
    RFCTLARR Act–specifically Sections 26 to 30 relating to calculation of
    compensation and the schedules relating to rehabilitation in limited
    circumstances–are applicable to acquisitions under the National
    Highways Act
    .

    3.4. With regard to rehabilitation and resettlement benefits under
    the Second and Third Schedules of the RFCTLARR Act, it is contended
    that such benefits apply only where land acquisition results in
    displacement or relocation of affected families. In the present case, the
    respondent asserts that the acquisition involves only a limited strip of land
    within the Right of Way (RoW) required for a highway project, as highway
    projects are linear infrastructure projects, where the RoW typically ranges
    between 15 meters for a two-lane highway and up to about 100 meters for
    an expressway, while for four-lane, six-lane, or eight-lane highways the
    RoW generally varies between 45 meters and 70 meters. Because such
    acquisitions usually involve only small portions of land rather than entire
    properties, the respondent contends that displacement and resettlement of
    families rarely occurs. In the present case, the respondent asserts that the
    petitioners have neither been relocated nor resettled and therefore do not
    fall within the statutory definition of a displaced familyunder Section 3(k)
    of the RFCTLARR Act, 2013. Consequently, they are not entitled to the
    rehabilitation and resettlement benefits claimed in the writ petition. It is
    contended that the interim orders granted in other writ petitions–
    particularly W.P. No. 9909 of 2024–cannot automatically extend to the
    present petitioners. The respondent also denies allegations that officials or
    15
    wp_26406_2025
    NBK, J

    police threatened the petitioners or interfered with their cultivation,
    asserting that these claims are unsupported by evidence.

    3.5. It is contended that if the petitioners are dissatisfied with the
    compensation awarded on 16.01.2024, they may approach the designated
    arbitrator under Section 3G(5) of the National Highways Act. If still
    aggrieved by the arbitrator’s decision, they may pursue further relief before
    the jurisdictional District Court under Section 34 of the Arbitration and
    Conciliation Act, 1996. The respondent therefore argues that the writ
    petition is inappropriate because the petitioners have bypassed the
    specialized remedy provided under the statute. It is contended that
    continued delay of project will increase expenditure on labor and materials
    and may also expose the NHAI to contractual penalties. Since the project
    serves a national infrastructure objective and benefits the general public,
    the respondent argues that the balance of convenience lies strongly in favor
    of allowing the project to proceed.

    4. A reply affidavit is filed by the petitioners denying the respondent’s
    claim that the compensation award dated 16.01.2024 was passed strictly in
    accordance with the National Highways Act, 1956. They contend that the
    award itself demonstrates procedural violations because it did not include
    valuation or compensation for structures and trees, nor did it include
    rehabilitation and resettlement entitlements. The petitioners further point
    out that the Arbitrator-cum-District Collector of Hanumakonda
    subsequently enhanced the market value of the land to nearly double the
    amount determined by the Competent Authority, which they argue proves
    that the original compensation determination was arbitrary and inconsistent
    with the statutory framework.

    16

    wp_26406_2025
    NBK, J

    4.1. The petitioners also challenge the respondent’s assertion that
    the highway alignment, once approved by the National Highways
    Authority of India, cannot be altered. They argue that accepting such a
    proposition would render meaningless the statutory right under Section 3C
    of the National Highways Act that allows landowners to file objections and
    be heard regarding the use of their land.

    4.2. With respect to the enquiry conducted on objections filed by
    affected landowners, the petitioners contend that the process violated the
    principles of natural justice. They state that the disposal order passed by
    the authority indicates a pre-determined and biased approach, lacking
    impartial application of mind. Moreover, the petitioners claim that copies
    of the disposal order were never communicated to them either before or
    after issuance of the Section 3D declaration, thereby depriving them of a
    fair opportunity to challenge the decision.

    4.3. The petitioners contend that respondents themselves admitted
    that the mandatory environmental clearance had not been obtained prior to
    the issuance of the Section 3D declaration, which formally vests the land in
    the Central Government. The petitioners state that this issue is presently
    pending consideration before a Division Bench of this Court, thus the
    legality of the acquisition declaration itself remains under judicial scrutiny.

    4.4. The petitioners also argue that the respondents’ own
    admissions reveal that the initial Section 3A notification dated 10.03.2021
    did not cover all lands falling within the proposed alignment, and this
    indicates lack of due diligence and failure to follow the prescribed
    guidelines. They further state that the subsequent Section 3A
    notificationissued to cover missing extents of land was not properly
    communicated to the affected landowners. In particular, the authorities
    17
    wp_26406_2025
    NBK, J

    allegedly failed to provide local-level notice–such as publication at the
    Gram Panchayator through personal notices–relying solely on newspaper
    publication. The petitioners maintain that such limited publication deprived
    many affected persons of meaningful opportunity to raise objections.
    Further, Section 3E possession notices were issued in 2023, even though
    the award for structures and trees was passed only in 2025, and the
    rehabilitation award has not yet been issued. According to them, initiating
    possession proceedings before completing the full award process violates
    the statutory scheme. They emphasize that the supplementary award
    passed in May 2025 for structures further demonstrates that the original
    award dated 16.01.2024was incomplete and therefore invalid.

    4.5. The petitioners contend that the Removal of Difficulties
    Order, 2015 dated 28.08.2015 requires application of certain provisions
    relating to rehabilitation and resettlement, and the respondents have failed
    to provide any legal justification for excluding provisions such as Sections
    16, 17, 18, 21, and 23, which deal with identification of affected families
    and preparation of rehabilitation schemes. The petitioners further argue
    that the authorities failed to correctly determine the market value of the
    land in accordance with Section 26 of the 2013 Act. They point out that the
    Competent Authority relied on market values prevailing as on 10.03.2021,
    taken from the Sub-Registrar’s market value register. However, the
    petitioners contend that these values were not revised in the State from
    2013 until 30.06.2021, thereby the values used in the award did not reflect
    the true prevailing market rates. They also highlight that for awards issued
    during the same month under a later notification, entirely different market
    values–more than double the earlier figures–were applied. According to
    18
    wp_26406_2025
    NBK, J

    the petitioners, this inconsistency demonstrates arbitrariness and renders
    the award legally unsustainable.

    4.6. The petitioners state that entitlements under the Second
    Schedule of the 2013 Act are applicable to affected families. The fact that a
    supplementary award for structures was issued more than a year after the
    main awardfurther reinforces their contention that the acquisition process
    was incomplete and flawed.

    5. Heard Mr. Ch. Ravi Kumar, learned counsel for the petitioners;
    learned Standing Counsel for NHAI, learned Standing Counsel for
    CALA,and Mr. B. Narasimha Sarma, learned Additional Solicitor General
    of India. Perused the record.

    6. Learned counsel for the petitioners contends that the acquisition
    proceedings were earlier challenged in WP No.5187 of 2023 on the ground
    that environmental clearance was not obtained prior to issuance of the
    declaration under Section 3D of the NH Act, 1956, and though interim
    orders were initially granted, the writ petition was later dismissed and Writ
    Appeal No.1190 of 2023 is pending without interim relief; that some
    adjoining landowners have separately challenged the Section 3A and 3D
    notifications in WP No.10431 of 2024 and obtained interim protection,
    leading the petitioners to reasonably believe that the authorities would not
    interfere with their possession until final adjudication; that the petitioners
    received copies of the Award proceedings only in February 2025; that
    multiple notifications under Sections 3A and 3D were issued without
    specifying survey numbers, landowner-wise extents, plans, or maps, and
    the order under Section 3C dated 20.11.2021 was not communicated to the
    19
    wp_26406_2025
    NBK, J

    petitioners; that the petitioners came to know about the multiple
    notifications only through the NHAI website and were unaware of the
    environmental clearance for nearly a year until public notices appeared in
    newspapers; that Section 3G of the NH Act, 1956, relating to determination
    of compensation, is no longer operative in view of the RFCTLARR
    (Removal of Difficulties) Order, 2015 issued under Section 105(3) of the
    RFCTLARR Act, 2013, and therefore the provisions of the 2013 Act apply
    to acquisitions under the National Highways Act; that consequently,
    compensation and rehabilitation benefits ought to have been determined in
    accordance with Sections 16 to 18, 21 to 30, 23 and 31 of the RFCTLARR
    Act, 2013 and not under Section 3G of the National Highways Act; that the
    competent authority failed to revise or update the market value of the
    acquired land as required under Section 26 of the RFCTLARR Act prior to
    issuance of the Section 3A notification; that two different rates were
    adopted while passing the award in January 2024; that the expressions
    “amount” and “compensation” used in Sections 3G and 3H of the National
    Highways Act include compensation for land, structures, and rehabilitation
    entitlements to affected families; that though the petitioners may not be
    displaced, they remain an affected family entitled to rehabilitation benefits;
    that possession of the land cannot be taken unless complete compensation
    including valuation of trees and structures and determination of
    rehabilitation entitlements is finalized; that the award proceedings are
    unsustainable as compensation for structures and trees has not been
    determined and therefore the notice under Section 3E of the National
    Highways Act is also liable to be set aside; that the competent authority
    ought to have issued notice under Section 21 of the RFCTLARR Act and
    conducted award enquiry under Section 23 after following the procedure
    under Sections 16 to 18 for identification of eligible persons and
    20
    wp_26406_2025
    NBK, J

    preparation of a Rehabilitation and Resettlement Scheme instead of
    proceeding under Section 3G of the National Highways Act; that despite
    representations expressing unwillingness to part with the land and pointing
    out the illegality in the acquisition and compensation determination, the
    authorities in June-July 2025 attempted to mark the petitioner’s land with
    police assistance and threatened the petitioner not to cultivate the land
    despite the existence of standing crops, thereby compelling the petitioner
    to approach this Court.

    7. Learned counsel for the petitionersrelies on:

    1) Akkala Chandrakala v. The State of Telangana 1;

    2) Kolkata Municipal Corporation v. Bimal Kumar Shah 2;

    3) B.K. Ravichandra v. Union of India3;

    4) Hindustan Petroleum Corpn. Ltd. v. Darius Shapur Chenai 4;

    5) K. Ramachandram v. State of Telangana5;

    6) Madi Satyavati v. State of Telangana6;

    7) Manorama Devi v. National Highways Authority of India7;

    8) Nagpur Improvement Trust v. Vithal Rao 8;

    9) National Highways Authority of India v. P. Nagaraju alias
    Cheluvaiah 9;

    10)Ranivr Singh v. National Highways Authority of India 10;

    11) Union of India v. Shiv Raj 11;

    1

    W.P. No. 11486 of 2024 (Telangana High Court)
    2
    (2024) 10 SCC 533
    3
    (2021) 14 SCC 703
    4
    (2005) 7 SCC 627
    5
    W.P. No. 23939 of 2013 (Telangana High Court)
    6
    W.A. No. 676 of 2023 (Telangana High Court)
    7
    Neutral Citation No. 2023:AHC:240588 – DB (Allahabad High Court)
    8
    (1973) 1 SCC 500
    9
    (2022) 15 SCC 1
    10
    2023 SCC OnLine All 5276
    21
    wp_26406_2025
    NBK, J

    12) State of Uttar Pradesh v. Singhara Singh 12

    7.1. In Akkala Chandrakala (supra), this Courtconsidered a
    dispute over land acquisition for the development of National Highway
    765DG. The petitioners, whose homes were being acquired, sought
    Rehabilitation and Resettlement (R&R) benefits under the Right to Fair
    Compensation and Transparency in Land Acquisition, Rehabilitation and
    Resettlement Act, 2013
    , while government authorities argued that such
    benefits were not applicable to the road-widening project under the
    National Highways Act, 1956. This Court, by interim order dated
    12.11.2024, rejected the authorities’ prayer to vacate an earlier stay order
    and indicated that highway acquisitions remain subject to modern R&R
    protections, and granted status quo until final hearing, while allowing
    authorities to begin the formal process of determining and awarding R&R
    compensation.

    7.2. In Bimal Kumar Shah (supra), the Hon’ble Supreme Court
    broadened the understanding of the constitutional right to property under
    Article 300-A of the Constitution of India by stating that lawful land
    acquisition requires more than just public purpose and compensation. The
    Hon’ble Supreme Court identified seven essential procedural sub-rights–
    including the right to notice, the right to be heard, and the right to a
    reasoned decision–along with requirements for an efficient process and
    fair rehabilitation. Ruling against the Kolkata Municipal Corporation, the
    Supreme Court held that any State action that ignores these safeguards is
    invalid.

    11

    (2014) 6 SCC 564
    12
    1963 SCC OnLine SC 23
    22
    wp_26406_2025
    NBK, J

    7.3. In B.K. Ravichandra (supra), the Hon’ble Supreme Court
    clarified the limits of Government power over private property. The
    Supreme Court held that although the right to property is no longer a
    fundamental right, it remains a constitutional safeguard under Article 300-
    A
    of the Constitution of India, protecting both physical land and intangible
    assets, and the government cannot occupy private land indefinitely without
    proper legal authority, as prolonged possession amounts to unlawful
    deprivation of property. Emphasizing the rule of law, the Court rejected
    any notion that the State can act with “royal prerogative” and insisted that
    all State actions must be backed by clear statutory authority. As a result,
    the Court ordered the return of land that had been held by the government
    for over thirty years and directed that fair compensation be paid to the
    rightful owners.

    7.4. In Darius Shapur Chenai (supra), the Hon’ble Supreme
    Court examined the procedural safeguards required under the Land
    Acquisition Act, 1894
    during the acquisition of private property. The
    Supreme Court focused on whether the State had genuinely considered the
    landowner’s objections as required under Section 5-A of the Land
    Acquisition Act, 1894. It held that the right to object and be heard under
    Section 5-A is a significant safeguard–comparable in importance to a
    fundamental right–and must involve a real and careful consideration by
    the government rather than a mere formality. The Court further ruled that
    when such decisions are challenged, the government must produce its
    records to demonstrate that a fair decision-making process was followed.
    Since the State failed to provide adequate evidence or a proper counter-
    affidavit, the Court upheld the quashing of the acquisition, reinforcing that
    23
    wp_26406_2025
    NBK, J

    laws allowing the taking of private property must be strictly interpreted to
    prevent arbitrary state action.

    7.5. In K. Ramachandram(supra), this Courtexamined whether
    the government had followed the required statutory procedures while
    attempting to acquire the petitioner’s land; and held that although the
    preliminary notification remained valid because it had been properly
    extended, the later declaration was unlawful due to the authorities’ failure
    to prepare and publish mandatory rehabilitation and resettlement schemes
    under the Right to Fair Compensation and Transparency in Land
    Acquisition, Rehabilitation and Resettlement Act, 2013
    . Finding that these
    procedural safeguards are essential to protect the landowner’s rights, the
    declaration was quashed with a direction to the government to strictly
    comply with the Act if it wishes to proceed with the acquisition, while also
    encouraging both parties to pursue an amicable settlement through land
    exchange or fair monetary compensation.

    7.6. In Madi Satyavati v. State of Telangana 13, the Division
    Bench of this Court dealt with a matter pertaining to land acquisition for a
    railway project; and held that not only the mother, but also her three
    daughters, qualify as an affected family under Right to Fair Compensation
    and Transparency in Land Acquisition, Rehabilitation and Resettlement
    Act, 2013
    ; and modified a prior order to ensure that rehabilitation benefits
    are determined for the daughters in addition to the mother’s solatium and
    allowed the appellants to seek a formal reference if they are dissatisfied
    with the final monetary compensation, reinforcing that the rights of all
    affected family members must be recognized in land acquisition cases.

    13

    W.A. No. 676 of 2023 (Telangana High Court)
    24
    wp_26406_2025
    NBK, J

    7.7. In Manorama Devi (supra), the Allahabad High Court
    adjudicated a petition filed by Manorma Devi against the National
    Highway Authority of India. The Allahabad High Court addressed her
    claim for rehabilitation and resettlement benefits, which she had not
    received despite being compensated for her land. The Court observed that
    her grievance aligned with previous cases under the Right to Fair
    Compensation and Transparency in Land Acquisition, Rehabilitation and
    Resettlement Act, 2013
    , where affected landowners were entitled to
    additional support. It directed the authorities to prepare a formal proposal
    within six months to provide the petitioner with entitlements for housing,
    employment, and relocation as outlined in the Second Schedule of the Act,
    and granted legal relief consistent with earlier, similar judgments.

    7.8. In Nagpur Improvement Trust (supra), the Hon’ble
    Supreme Court examined whether the Nagpur Improvement Trust Act
    violated Article 14 of the Constitution of India by allowing the State to
    acquire property at lower compensation rates than standard national laws.
    The Supreme Court held that the Government cannot justify paying
    different amounts for similar lands based solely on which authority
    conducts the acquisition or the stated public purpose. Emphasizing the
    principle of equal protection, the judgment affirmed that landowners are
    entitled to consistent, market-value compensation regardless of the
    acquiring body, and dismissed the appeal, ruling that discriminatory
    treatment in compensation or statutory bonuses is unconstitutional.

    7.9. In P. Nagaraju alias Cheluvaiah (supra), the Hon’ble
    Supreme Court addressed the determination of fair compensation and
    clarified the role of Courts in reviewing arbitral awards under Section 34
    of the Arbitration and Conciliation Act, 1996. The Supreme Court held that
    25
    wp_26406_2025
    NBK, J

    an arbitrator’s failure to provide adequate and intelligible reasoning for
    compensation constitutes a ground of “patent illegality,” justifying judicial
    intervention. Emphasizing equitable treatment for landowners, including
    solatium and interest, the ruling aligned compensation practices with
    constitutional protections and remanded the matter for recalculation of the
    property’s market value using proper evidence and updated guideline rates.

    7.10. In Ranivr Singh (supra), the Allahabad High Court
    addressed petitions by displaced families who claimed that the National
    Highway Authority of India had failed to provide mandatory rehabilitation
    and resettlement benefits under the Right to Fair Compensation and
    Transparency in Land Acquisition, Rehabilitation and Resettlement Act,
    2013
    . The Court held that the status of affected families must be properly
    assessed, rejecting the authorities’ contention that linear road projects
    cause minimal disruption. It directed the competent authority to conduct a
    thorough inquiry and submit a resettlement proposal to the District
    Collector, ensuring that eligible landowners receive entitlements such as
    housing units, employment opportunities, or relocation allowances as part
    of their compensation.

    7.11. In Shiv Raj (supra), the Hon’ble Supreme Courtconsidered
    the validity of land acquisition proceedings under the Land Acquisition
    Act, 1894
    . The Supreme Court highlighted procedural lapses, including
    violations of natural justice where objections were heard by one official
    but the final report was issued by another without a fresh hearing. It also
    examined the impact of the Right to Fair Compensation and Transparency
    in Land Acquisition, Rehabilitation and Resettlement Act, 2013
    on older
    cases where the government delayed possession or failed to provide
    compensation for over five years.

    26

    wp_26406_2025
    NBK, J

    7.12. InSinghara Singh (supra), the Hon’ble Supreme Court
    addressed the admissibility of oral testimony regarding a defendant’s
    confession, arising from a Second-Class Magistrate’s failure to follow
    procedures under Section 164 of the Code of Criminal Procedure, 1973.

    8. Learned Standing Counsel for NHAI contends that the competent
    authority awarded adequate and lawful compensation to the petitioners in
    accordance with the National Highways Act, 1956 and the RFCTLARR
    Act, 2013
    ; that the Respondent No.4-CALA passed awards dated
    05.01.2024 and 31.01.2024 in Proceedings No. B/85/2021-08-NH-163G
    after considering objections and providing opportunity of hearing to all
    concerned, and the compensation amounts were received by the petitioners
    except petitioner Nos. 4 and 6; that if the petitioners are aggrieved by the
    determination of compensation, they have an efficacious alternative
    remedy under Section 3G(5) of the NH Act by approaching the Arbitration-
    cum-District Collector and any challenge to the arbitral award lies before
    the District Court under Section 34 of the Arbitration and Conciliation Act,
    1996; that the petitioners do not fall within the definition of a displaced
    family under Section 3(k) of the RFCTLARR Act, 2013 as they have
    neither been relocated nor resettled from the affected area; that the
    petitioners have failed to produce any documentary evidence establishing
    displacement or loss of livelihood so as to qualify as an “affected family”

    under Section 3(c) of the RFCTLARR Act, 2013 or to claim benefits under
    the Second and Third Schedules of the said Act; that only a portion of the
    petitioners’ land has been acquired and the remaining land continues to be
    available for their livelihood, thereby negating any claim of deprivation of
    livelihood; that where substantial monetary compensation has been
    awarded, the landowners can utilize such compensation for acquiring
    27
    wp_26406_2025
    NBK, J

    alternative land or assets and therefore cannot insist on rehabilitation or
    resettlement benefits; that even otherwise, the petitioners failed to raise
    specific objections before the competent authority demonstrating that the
    compensation awarded was insufficient to enable rehabilitation or
    resettlement; that any claim for rehabilitation or resettlement requires
    cogent evidence demonstrating that the compensation determined is
    grossly inadequate to secure such rehabilitation; that entitlement to benefits
    under the Second Schedule of the RFCTLARR Act arises only when the
    competent authority certifies that the family has been displaced or
    dislocated, which is not the case here; that preparation of a Social Impact
    Assessment (SIA) report is not mandatory for acquisitions under the
    National Highways Act, 1956; that the provisions of the RFCTLARR Act,
    2013
    , particularly those relating to Social Impact Assessment and
    rehabilitation and resettlement under Chapter II, do not automatically
    apply to acquisitions under the National Highways Act unless specifically
    extended by notification under Section 105 of the Act of 2013, and no such
    notification applies in the present case; that since only part of the
    petitioners’ land has been acquired and they have not been dislocated, there
    is no requirement to frame a rehabilitation and resettlement scheme; that
    injunction against an infrastructure project is barred under Section 20-A of
    the Specific Relief Act, 1963; that the present project is a public
    infrastructure project of national importance and cannot be stalled, and
    therefore the acquisition proceedings cannot be challenged merely on the
    ground of dissatisfaction with the compensation, particularly when an
    effective statutory remedy for enhancement of compensation is available
    under Section 3G(5) of the National Highways Act.

    28

    wp_26406_2025
    NBK, J

    9. Learned Standing Counsel for the Competent Authority for Land
    Acquisition (CALA) contends that environmental clearance for the project
    was obtained on 05.07.2023 vide File No.10/29/2021-IA-III and the
    additional notification under Section 3A of the NH Act, 1956 was issued
    only for the purpose of covering certain missing structures; that the
    competent authority passed awards dated 05.01.2024 and 31.01.2024
    determining compensation for the acquired lands and subsequently passed
    a supplementary award dated 11.11.2025 determining compensation for
    structures; that several landowners who were aggrieved by the
    compensation approached the Arbitrator-cum-District Collector under
    Section 3G(5) of the NHActand the arbitrator revised the market value and
    enhanced compensation through awards dated 09.05.2025, 23.07.2025,
    04.08.2025 and 23.10.2025; that the provisions of Sections 16 to 18, 21
    and 23 of the RFCTLARR Act, 2013 are not applicable to acquisitions
    under the National Highways Act as the project is a linear infrastructure
    project where the affected area is confined to the right of way and therefore
    identification of eligibility for rehabilitation benefits and preparation of a
    Rehabilitation and Resettlement Scheme is not mandatory; that benefits
    under the Second Schedule of the RFCTLARR Act can be claimed only
    when the competent authority certifies that the petitioner’s family has been
    displaced or dislocated from the area; that objections filed under Section
    3C
    of the National Highways Act were duly received and disposed of and
    additional notifications were issued only to acquire certain missing extents
    of land, following which notification under Section 3D was issued and the
    land vested with the Central Government free from all encumbrances; that
    out of 1035 landowners whose lands were acquired or are in the process of
    acquisition, 859 landowners have already received compensation and only
    the petitioner and a few others have not accepted the amount; that the
    29
    wp_26406_2025
    NBK, J

    petitioner has raised untenable objections and approached this Court with
    the intention of stalling the land acquisition process; that Section 3G of the
    NHAct continues to govern determination of compensation for lands
    acquired under the Act, while only the provisions of the RFCTLARR Act,
    2013
    relating to determination of compensation under the First Schedule
    and Rehabilitation and Resettlement benefits under the Second Schedule
    are applicable to such acquisitions, and therefore the writ petition is liable
    to be dismissed.

    10. Learned Additional Solicitor General relies on several judgments in
    support of his contention that a writ remedy is not maintainable in the
    instant case; particularly on Ramniklal N. Bhutta v. State of
    Maharashtra
    14 and contends that the Courts have to weigh the public
    interest vis-à-vis the private interest while exercising the power and there
    are many ways of affording appropriate relief and redressing a wrong, and
    that quashing of acquisition proceedings is not the only mode of redress.

    10.1. He also relies on Nerajala Nageswara Rao v. Union of
    India15
    , to contend that alternative remedy harsh one should not be
    resorted in public purpose projects and larger public purpose prevails over
    individual interest.
    He also relies on N.G. Projects Ltd. v. Vinod Kumar
    Jain16
    , to contend that construction of road is an infrastructure project and
    keeping in view the intent of the legislature that infrastructure projects
    should not be stayed, the High Court would have been well advised to hold
    its hand to stay the construction of the infrastructure project.

    14

    1997 (1) SCC 134
    15
    2017 SCC Online Hyd 250
    16
    2022 (6) SCC 127
    30
    wp_26406_2025
    NBK, J

    10.2. He also relies on Bluepark Seafoods (P) Ltd v. District
    Collector17 and contends that in case of acquisition for benefit of general
    public, the landowner can stake claim for reasonable compensation and
    nothing beyond that. Relying on NHAI v. Sayedabad Tea Company
    Ltd 18, it is contended that National Highways Act is a special enactment
    and a comprehensive code which provides an inbuilt mechanism for
    initiating acquisition until culmination of the proceedings in determining
    the compensation and its adjudication by arbitrator under Section 3-G(5) of
    the NH Act.

    10.3. He also relies on the judgment of the High Court of
    Karnataka, at Bengaluru, in W.P.No.10103 of 2020 (LA-RES) and
    batch, dated 19.07.2022, and contends that in the said case, the High
    Court of Karnataka has set aside the awards passed by the CALA and
    directed the authority to redetermine the compensation afresh, and if the
    parties are aggrieved by the fresh awards passed by the CALA, the parties
    can approach the arbitrator.

    10.4. He also relies on the judgment of Hon’ble Supreme Court in
    M/s Tirupati Developers v. The Union Territory of Dadra and Nagar
    Haveli19
    , and contends that the Hon’ble Supreme Court directed the
    Collector to give one opportunity to the appellant therein to submit its
    objections, followed by personal hearing and thereafter pass appropriate
    award after holding inquiry under Section 23 of the RTCTLARR Act, and
    therefore similar dispensation attracts in the present writ petition in view of
    similarity of facts.

    17

    2011 SCC OnLine AP 267
    18
    (2020) 15 SCC 161
    19
    Civil Appeal No.4952 of 2023, dated August 7, 2023
    31
    wp_26406_2025
    NBK, J

    11. Having considered the respective contentions and perused the
    record, it may be noted that the grievance of the petitioners essentially is
    that multiple notifications under Sections 3A and 3D of the National
    Highways Act were issued with incomplete information, inadequate
    publication, and without providing proper landowner-wise details, maps, or
    an effective opportunity to file objections with regard to the acquisition of
    their agricultural lands for the proposed four-lane National Highway-163G,
    and that their objections were not properly considered. It is also contended
    that the authorities proceeded with the declaration and award process even
    before obtaining environmental clearance, issued additional notifications
    without informing the affected landowners, and passed incomplete
    compensation awards without determining compensation for structures and
    trees, and without granting rehabilitation and resettlement benefits as
    required under the RFCTLARR Act, 2013 and the Removal of Difficulties
    Order, 2015. They also allege discriminatory and outdated valuation of
    land, denial of statutory entitlements, and attempts by the authorities to
    forcibly take possession of their lands without paying lawful
    compensation, thereby threatening their livelihood as small and marginal
    farmers. It is also their grievance that the compensation cannot be confined
    only to the land on the mere ground that the land is an agricultural extent,
    and that compensation should also be granted for the structures existing on
    the land, and rehabilitation and resettlement benefits should be extended to
    the petitioners.

    11.1. On the contrary, the essential contention of the respondents
    (NHAI and CALA authorities) is that the acquisition of the petitioners’
    land for the construction of the four-lane National Highway-163G
    (Mancherial-Warangal Greenfield Corridor) has been carried out strictly in
    32
    wp_26406_2025
    NBK, J

    accordance with the procedure prescribed under the National Highways
    Act, 1956
    and the applicable provisions of the RFCTLARR Act, 2013, and
    that all statutory steps–issuance of notifications under Sections 3A and
    3D, consideration of objections under Section 3C, conduct of enquiry, and
    passing of compensation awards under Section 3G–were duly followed.
    According to them, adequate opportunity was given to the landowners, and
    compensation has been determined and deposited as per law. It is also their
    contention that the entire village or villages have not been acquired,
    requiring the villagers, along with their houses, cattle, and livelihood, to be
    shifted/relocated to an alternative location, or re-establish the village at
    some other place entirely; but only such extent of land(s) that is under
    alignment would go into the highway project, and only such limited
    extents of land(s) were acquired, and therefore there cannot be any
    contentions of displacement of persons requiring rehabilitation and
    resettlement under the RFCTLARR Act because they are not “displaced
    families”. It is contended that any grievance regarding compensation must
    be pursued through the statutory remedy of arbitration under Section 3G(5)
    of the National Highways Act rather than through a writ petition, and the
    petitioners’ allegations are unfounded. They further contend that the
    interim order restraining the project may be vacated since it delays a
    project of national importance and public interest.

    12. At this juncture, it is to be noted that the project concerns the laying
    of a four-lane National Highway (Mancherial-Warangal Greenfield
    Corridor), and that land acquisition has been undertaken for the said
    highway. In land acquisition for a National Highway of this nature,
    connecting highways across States, the acquisition process or the laying of
    the highway per se cannot be stalled indefinitely by taking recourse to the
    33
    wp_26406_2025
    NBK, J

    extraordinary jurisdiction of this Court. Ultimately, the sole grievance that
    can be agitated by the aggrieved persons is confined to the compensatory
    benefits in lieu of the lands acquired, which is pecuniary in nature.

    12.1 Further, the petitioners’ grievance with regard to entitlement
    to compensation for structures, trees, standing crops, or even alternative
    rehabilitation/resettlement benefits is also justiciable, provided such
    structures are legally permitted, and the CALA has certified that the
    structures/crops, etc., have been affected in the land acquisition process, in
    a way that resettlement and rehabilitation is necessary.

    12.2 Be that as it may, in land acquisition for a public purpose,
    unless there are proven malafides, neither is the acquisition liable to be set
    aside, nor can the opinion of experts–either with regard to the alignment
    of the highway or with regard to the determination of factual aspects such
    as the extent of land acquired and the monetary compensation payable–be
    substituted by exercising extraordinary jurisdiction under Article 226.

    13. At this juncture, it would be relevant to refer to the judgment of the
    Hon’ble Supreme Court in Union of India v. Kushala Shetty 20, wherein it
    was held as follows:

    “24. Here, it will be apposite to mention that NHAI is a
    professionally managed statutory body having expertise in the
    field of development and maintenance of National Highways. The
    projects involving construction of new highways and widening
    and development of the existing highways, which are vital for
    development of infrastructure in the country, are entrusted to
    experts in the field of highways. It comprises of persons having
    vast knowledge and expertise in the field of highway development

    20
    (2011) 12 SCC 69
    34
    wp_26406_2025
    NBK, J

    and maintenance. NHAI prepares and implements projects relating
    to development and maintenance of National Highways after
    thorough study by experts in different fields. Detailed project
    reports are prepared keeping in view the relevant factors including
    intensity of heavy vehicular traffic and larger public interest. The
    Courts are not at all equipped to decide upon the viability and
    feasibility of the particular project and whether the particular
    alignment would subserve the larger public interest. In such
    matters, the scope of judicial review is very limited. The Court can
    nullify the acquisition of land and, in rarest of rare cases, the
    particular project, if it is found to be ex facie contrary to the
    mandate of law or tainted due to mala fides.”

    14. Further, it would be relevant to refer to the judgment of the Hon’ble
    Division Bench of this Court in Writ Appeal No.774 of 2024, dated
    07.08.2024, which is an appeal filed challenging a Notification for laying a
    national highway. The Hon’ble Division Bench, by referring to various
    precedent judgments of the Hon’ble Supreme Court, more particularly
    Kushala Shetty (supra), held as follows:

    “12. In view of aforesaid enunciation of law, it is evident that the
    projects involving construction of new highways and widening
    and development of existing highways are vital for development of
    infrastructure of the country. The projects have been entrusted to
    the experts in the field of highways and it comprises of persons
    having vast knowledge and expertise in the field of highway
    development and maintenance. The NHAI is implementing the
    project relating to development and maintenance after thorough
    study by experts.

    13. It is pertinent to note that in pursuance of the notification
    issued under the Act, award has already been passed on
    10.05.2022 and petitioners No.8 and 11 in W.P.No.24150 of 2021
    have even received the compensation. The project is virtually
    complete except for a small stretch.”

    35

    wp_26406_2025
    NBK, J

    15. In this connection, it is to be noted that under Section 3G of the
    National Highways Act, determination of compensation is entrusted to the
    Competent Authority for Land Acquisition (CALA). Significantly, Section
    3G(5)
    expressly provides that where the amount determined by the
    Competent Authority is not acceptable to either of the parties, the matter
    shall, on application, be referred to the Arbitrator appointed by the Central
    Government–ordinarily the District Collector. Thus, the statute itself
    creates a complete adjudicatory mechanism for redressal of disputes
    relating to compensation.

    16. Further, once the Arbitrator renders an award under Section 3G(5) of
    the National Highways Act, 1956, such award is governed by the
    provisions of the Arbitration and Conciliation Act, 1996; and the persons
    aggrieved by the arbitral award has a further statutory remedy under
    Section 34 of the Arbitration and Conciliation Act before the competent
    Civil Court.

    17. Though the existence of an alternative remedy is not a bar to
    invoking the writ jurisdiction of this Court under Article 226, its invocation
    comes with the rider that there should be exceptional circumstances,
    warranting invocation under Article 226 bypassing the statutory remedy. In
    this context, it is relevant to refer to the judgment of the Hon’ble Supreme
    Court in Whirlpool Corporation v. Registrar of Trademarks 21, wherein
    the Supreme Court held as follows:

    “15. Under Article 226 of the Constitution, the High Court, having
    regard to the facts of the case, has a discretion to entertain or not

    21
    1998 (8) SCC 1
    36
    wp_26406_2025
    NBK, J

    to entertain a writ petition. But the High Court has imposed upon
    itself certain restrictions one of which is that if an effective and
    efficacious remedy is available, the High Court would not normally
    exercise its jurisdiction. But the alternative remedy has been
    consistently held by this Court not to operate as a bar in at least
    three contingencies, namely, where the writ petition has been filed
    for the enforcement of any of the Fundamental Rights or where
    there has been a violation of the principle of natural justice or
    where the order or proceedings are wholly without jurisdiction or
    the vires of an Act is challenged.”

    18. In the instant writ petition, this Court does not find any violation of
    fundamental rights per se, or any violation of the principles of natural
    justice, or any jurisdictional error on the part of the respondent authorities;
    nor does the writ petition challenge the vires of the Act passed by the
    competent authority. Further, it is the specific unrebutted contention of the
    respondents, borne out by the record, that out of 1035 landowners whose
    lands were acquired or in process of acquisition, 859 landowners have
    already received compensation; thereby roughly 83% of persons have
    received the compensation.

    19. The grievance of the petitioners is about (i) determination of
    compensation under the awards dated 05.01.2024 and 31.01.2024, (ii)
    alleged improper calculation of market value, multiplication factor,
    solatium, and other statutory components, and (iii) alleged inadequate
    grant of certain benefits under the RFCTLARR framework as applied to
    acquisitions under the National Highways Act, 1956.

    37

    wp_26406_2025
    NBK, J

    20. Though the petitioners contend that they are entitled to certain
    rehabilitation and resettlement benefits, it cannot be disputed that the
    competent authority should have certified that the affected landowner has
    been displaced. Furthermore, the petitioners have a two-step statutory
    remedy, one under the National Highways Act, 1956 and, if still aggrieved,
    the second under the Arbitration and Conciliation Act, 1996; and therefore
    the petitioners are not remediless.

    21. In the light of the judgment of Hon’ble Supreme Court in Kushala
    Shetty
    (supra), and Whirlpool Corporation (supra), and also the
    judgment of the Hon’ble Division Bench in W.A. No.774 of 2024, dated
    07.08.2024, this Court does not find any exceptional circumstances to
    entertain the writ petition bypassing the statutory arbitration mechanism
    provided under the National Highways Act, 1956 and the Arbitration and
    Conciliation Act, 1996
    .

    22. Accordingly, the writ petition is disposed of, relegating the
    petitioners to avail the statutory remedy under Section 3G(5) of the
    National Highways Act, 1956 and thereafter, if necessary, under Section
    34
    of the Arbitration and Conciliation Act, 1996. No costs. Interim order
    dated 09.09.2025 stand vacated. Miscellaneous petitions pending, if any,
    shall stand closed.

    ________________________________
    JUSTICE NAGESH BHEEMAPAKA
    07thApril, 2026

    ksm



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here