The arbitration procedure in India runs from a written arbitration agreement under Section 7 of the Arbitration and Conciliation Act, 1996, through reference to arbitration, appointment of the tribunal, pleadings, hearings and the award, to enforcement of that award as a decree of the court. What the bare text of the Act does not show is that almost every one of those stages is now governed by judicial gloss rather than statutory language, and the Supreme Court has reversed its own position on stamping, seat, unilateral appointment and the power to modify awards since 2023 alone. A procedure that looks settled on paper has moved substantially in the last three years. This article sets out each stage of the arbitration procedure in India alongside the judgment that currently controls it.
This article sets out the arbitration procedure in India stage by stage, and the judgment that governs each stage.
The Arbitration and Conciliation Act, 1996 was built on the UNCITRAL Model Law and has been amended three times since, in 2015, 2019 and 2021. Each amendment tried to pull the courts further back from the arbitral process. Each was followed by a run of judgments that redrew the line again, sometimes in the opposite direction.
A note on what is not law, because it is widely misreported. The Arbitration and Conciliation (Amendment) Bill, 2024 was released by the Department of Legal Affairs on 18 October 2024 as a consultation draft, with comments invited until 3 November 2024, following an expert committee report submitted in February 2024. As of July 2026 it has not been introduced in Parliament. The operative statute remains the 1996 Act as amended in 2015, 2019 and 2021, and proposals in that draft, including the much-discussed Section 9A on emergency arbitrators, have no legal force.
If you want the definitional groundwork first, our explainer on what arbitration is, its types and its process covers the basics. This piece assumes them and goes to the case law.
Where arbitration procedure in India goes wrong
The arbitration procedure in India goes wrong most expensively at the two ends: at appointment, where a defective clause can void the tribunal, and at the award stage, where a tribunal’s failure to engage with the contract can undo years of work. The clearest illustration involves the same dispute, the same court, and two opposite results three years apart.
In September 2021, in Delhi Airport Metro Express Pvt. Ltd. v. Delhi Metro Rail Corporation Ltd., (2022) 1 SCC 131 (SC, 9 September 2021), the Supreme Court set aside a Division Bench of the Delhi High Court and restored an arbitral award. The reasoning was a lecture on restraint. Grounds under Section 34 of the Arbitration and Conciliation Act, 1996 are to be construed narrowly, the Court held, and judges must not appreciate or re-appreciate facts or law. It read like the end of the argument.
Then came the curative petition.
In April 2024, in Delhi Metro Rail Corporation Ltd. v. Delhi Airport Metro Express Pvt. Ltd., 2024 INSC 292 (SC, 10 April 2024), the Supreme Court set aside the very award it had restored. The sum involved was approximately Rs. 8,000 crore. The Court held that the tribunal had failed to explain what constituted an “effective step” to cure the breach, and had simply ignored a contractual term that spoke of curing a breach “or taking effective steps for curing such breach”. The award was perverse and patently illegal. It is widely regarded as the first arbitral award set aside at the curative stage, which is the fifth level of scrutiny available in Indian law.
Read those two together and the practical lesson isn’t about finality doctrine. It’s that a tribunal which glides past the words of the contract is writing an award with a fault line running through it, and that fault line can open a decade later. The 2021 judgment did not protect the award. The contract’s own language destroyed it.
The cost data points the same way. In a dispute between three Rajasthan state power distribution companies and a technology supplier, a three-member tribunal, one former Supreme Court judge and two former High Court judges, had been paid approximately Rs. 13 crore in fees seven years in, with the proceedings still not concluded. On timelines, extension applications under Section 29A are in practice almost always allowed by the courts, which makes the twelve-month clock Parliament installed in 2015 closer to a diary entry than a deadline.
Some institutional users have simply left. The Delhi Public Works Department deleted the arbitration clause, Clause 25, from the General Conditions of Contract for all future contracts by a notification dated 21 April 2025, regardless of contract value, routing disputes to Delhi courts instead. The Ministry of Finance had already limited arbitration in government contracts to disputes up to Rs. 10 crore in 2024. The PWD went further and removed it outright.
The bench has said as much. Speaking at the Indian Council of Arbitration’s fourth international conference in London in June 2026, Chief Justice of India Surya Kant observed that arbitration “was built to be the answer to the pathologies of formal litigation, and it is seemingly acquiring each of those very failings”, adding that “the remedy has come to resemble the disease it was designed to cure”. He was addressing international arbitration generally rather than India alone. But the diagnosis travels.
So is the procedure broken, or is it being used badly? Mostly the latter, and the distinction matters. Nearly every failure below traces to a party treating a procedural requirement as a formality: an unstamped agreement, a clause letting one side pick the arbitrator, a venue named without thinking about the seat, an extension application filed in the wrong court. None of those are hard problems. They’re just ones people don’t look at until the award is under challenge.
1
Arbitration agreement (s.7)
In Re: Interplay
2023
7 judges
Unstamped is curable, not void
2
Reference (ss.8, 11)
Vidya Drolia; Krish Spinning
2020; 2024
3 judges
Prima facie existence only
3
Appointment (s.11, s.12(5))
TRF; Perkins; CORE II
2017; 2019; 2024
5 judges (CORE II)
No unilateral appointment
4
Seat (s.20)
BALCO; BGS SGS Soma
2012; 2019
5 judges (BALCO)
Venue is the seat, absent contrary indicia
5
Interim relief (ss.9, 17)
Amazon v. Future Retail
2021
2 judges
Emergency award enforceable if India-seated
6
Award and clock (ss.29A, 31)
Rohan Builders
2024
2 judges
Extension maintainable after expiry
7
Setting aside (s.34)
Ssangyong; Gayatri Balasamy
2019; 2025
5 judges (Balasamy)
No merits review; limited modification
8
Enforcement (s.36)
Hindustan Construction
2019
3 judges
No automatic stay; s.87 struck down
Constitution Bench or larger (5 or 7 judges)
Smaller bench (2 or 3 judges)
iPleaders · blog.ipleaders.in
The judgments that redrew arbitration procedure in India
The judgments that redrew the arbitration procedure in India cluster into a short list of reversals, and reading them as a group is more useful than reading any one of them alone. The pattern is consistent: the Court expands its own supervisory reach, Parliament legislates to cut it back, and the Court then works out how far the legislation actually went.
Here is the arc.
| The old position | Changed by | What it means now |
|---|---|---|
| Part I applies to foreign-seated arbitrations (Bhatia International v. Bulk Trading S.A., (2002) 4 SCC 105) | Bharat Aluminium Co. v. Kaiser Aluminium Technical Services Inc., (2012) 9 SCC 552 (5 judges) | Territoriality governs. Prospective: binds agreements executed on or after 6 September 2012 |
| Expansive “public policy” review (ONGC Ltd. v. Saw Pipes Ltd., (2003) 5 SCC 705) | The 2015 Amendment, given effect by Ssangyong Engineering & Construction Co. Ltd. v. NHAI, AIR 2019 SC 5041 | Merits review “done away with”. Patent illegality is domestic-only |
| Tenancy disputes are not arbitrable (Himangni Enterprises v. Kamaljeet Singh Ahluwalia, (2017) 10 SCC 706) | Vidya Drolia v. Durga Trading Corporation, (2021) 2 SCC 1 (3 judges) | Arbitrable. Four-fold test for non-arbitrability |
| A named venue is not the seat (Union of India v. Hardy Exploration and Production (India) Inc., (2019) 13 SCC 472) | BGS SGS Soma JV v. NHPC Ltd., (2020) 4 SCC 234 (3 judges) | Declared bad law. Venue is the seat absent contrary indicia |
| Filing a Section 34 petition automatically stays enforcement | BCCI v. Kochi Cricket Pvt. Ltd., AIR 2018 SC 1549, then Hindustan Construction Company Ltd. v. Union of India, AIR 2020 SC 122 | No automatic stay. Section 87 struck down under Article 14 |
| An unstamped arbitration agreement is void (N.N. Global Mercantile (P) Ltd. v. Indo Unique Flame Ltd., (2023) 7 SCC 1, April 2023) | In Re: Interplay, 2023 INSC 1066 (December 2023, 7 judges) | Inadmissible and curable, not void. Reversed in eight months |
| Non-signatories bound via “claiming through or under” (Chloro Controls India Pvt. Ltd. v. Severn Trent Water Purification Inc., (2013) 1 SCC 641) | Cox and Kings Ltd. v. SAP India Pvt. Ltd., 2023 INSC 1051 (5 judges) | Doctrine retained, re-anchored on consent and mutual intention |
| Curated arbitrator panels are permissible (Central Organisation for Railway Electrification v. ECI-SPIC-SMO-MCML (JV), (2020) 14 SCC 712) | Central Organisation for Railway Electrification v. ECI-SPIC-SMO-MCML (JV), 2024 INSC 857 (5 judges) | Unilateral appointment impermissible. Article 14 engaged |
| Courts cannot modify an award | Gayatri Balasamy v. M/s ISG Novasoft Technologies Ltd., 2025 INSC 605 (Constitution Bench) | Limited modification power in four situations |
Three of these deserve more than a table row.
The stamping saga is the sharpest. In April 2023, a five-judge bench in N.N. Global held by a 3:2 majority that an unstamped instrument containing an arbitration agreement was void and could not be acted upon. Eight months later, a seven-judge bench in In Re: Interplay held that it was nothing of the sort. An unstamped instrument is inadmissible in evidence under Section 35 of the Indian Stamp Act, 1899, not void, and the defect is curable. Stamping is not examined at the referral stage at all; it goes to the tribunal. The 2023 bench also held that SMS Tea Estates Pvt. Ltd. v. Chandmari Tea Co. Pvt. Ltd., (2011) 14 SCC 66 and Garware Wall Ropes Ltd. v. Coastal Marine Constructions and Engineering Ltd., (2019) 9 SCC 209 had been wrongly decided.
Eight months. A five-judge bench, then a seven-judge bench, opposite conclusions. Contracts drafted in that window were negotiated against a rule that no longer exists.
The public policy story runs longer and matters more. Saw Pipes in 2003 invented “patent illegality” as a ground inside “public policy of India”, which handed Section 34 courts a merits review they were never meant to have. Associate Builders v. Delhi Development Authority, (2015) 3 SCC 49, decided in late 2014, systematised it. The Law Commission’s 246th Report, submitted in August 2014, called this out and recommended that patent illegality be construed far more narrowly than Saw Pipes allowed. Parliament rewrote Section 34 in 2015, and Section 34(2A) made patent illegality a standalone ground for domestic awards only, with an express proviso barring its use for erroneous application of law or re-appreciation of evidence. In Ssangyong, the Court confirmed the reset in plain terms: the expansive approaches of Saw Pipes and Western Geco “have been done away with”.
And then there is prospectivity, which is where practitioners actually lose money. BALCO binds only agreements executed on or after 6 September 2012, so the overruled Bhatia position still governs older agreements. CORE II’s conclusions on three-member tribunals apply only to appointments made after 8 November 2024. Getting the date wrong means arguing the wrong law.
The arbitration agreement and reference to arbitration
The arbitration agreement is the foundation of the entire procedure, and Section 7 of the Arbitration and Conciliation Act, 1996 requires only that it be in writing and record an intention to submit defined disputes to arbitration. The litigation isn’t usually about whether an agreement exists. It’s about what a court may examine before sending the parties to a tribunal.
The answer, after In Re: Interplay, is: very little.
Stamping is the clearest example. An insufficiently stamped instrument no longer stops a reference. The objection survives, but it belongs to the tribunal, and the instrument stays inadmissible until it’s impounded and cured. The mistake we see most often runs in both directions: parties either concede at the Section 11 stage because the agreement was unstamped, or they decide stamping stopped mattering altogether (it didn’t, it just moved). Neither is right.
On arbitrability, Vidya Drolia set the four-fold test. A dispute is not arbitrable in any of these situations:
- It involves an action in rem that doesn’t pertain to subordinate rights in personam arising from rights in rem.
- It affects third-party rights, has erga omnes effect, or requires centralised adjudication.
- It relates to inalienable sovereign and public-interest functions of the State.
- A statute expressly or by necessary implication makes it non-arbitrable.
That same ruling overruled Himangni Enterprises and confirmed that landlord-tenant disputes under the Transfer of Property Act, 1882 are arbitrable. Our detailed treatment of the Vidya Drolia four-fold test works through each limb.
The scope of Section 11 scrutiny has narrowed further since. In SBI General Insurance Co. Ltd. v. Krish Spinning, 2024 INSC 532 (SC, 18 July 2024), a three-judge bench held that the inquiry is confined to the prima facie existence of the arbitration agreement and nothing else. A plea of accord and satisfaction, meaning a claim that the parties have already settled, is for the tribunal. Deciding it at the referral stage usurps the tribunal’s power. Limitation goes the same way, as Uttarakhand Purv Sainik Kalyan Nigam Ltd. v. Northern Coal Field Ltd., (2020) 2 SCC 455 had already held: it’s a jurisdictional issue under Section 16, not a Section 11 question.
The practical reality is that arguing limitation or full-and-final settlement at Section 11 is now close to a guaranteed loss, and it costs months of listing time to find that out.
Non-signatories are the other live issue. In Cox and Kings, a five-judge bench retained the group of companies doctrine but re-anchored it. The doctrine sits in Section 7(4)(b) and the definition of “parties” in Section 2(1)(h), and it’s consent-based: the non-signatory must belong to the same group and there must be a mutual intention of all parties to bind it. Common shareholding won’t do it. Nor will a shared group name. You need evidence of involvement in negotiation, performance and the transaction itself (which is a documentary burden, not an argument).
Since the arbitration clause lives inside a commercial contract rather than standing on its own, drafting quality upstream decides how much of this you ever face. For the commercial-drafting side of that, Skill Arbitrage’s piece on contract drafting for foreign clients treats dispute resolution as one of the clauses that does the real risk-allocating work.
Appointment of the arbitral tribunal
Appointment is the stage with the cleanest doctrinal arc in Indian arbitration, and it runs in one direction: away from letting one party choose who decides. Section 12(5) of the Arbitration and Conciliation Act, 1996, read with the Seventh Schedule, makes certain relationships an automatic disqualification. And the case law has steadily widened what that disqualification reaches.
It started with TRF Ltd. v. Energo Engineering Projects Ltd., (2017) 8 SCC 377 in 2017. A person statutorily ineligible under Section 12(5) cannot nominate someone else as arbitrator. The Court applied qui facit per alium facit per se, meaning what you cannot do yourself you cannot do through another. Disqualification became derivative.
Perkins Eastman Architects DPC v. HSCC (India) Ltd., AIR 2020 SC 59 (SC, 26 November 2019) extended it in 2019. It isn’t only the ineligible person who is barred; a party, its official, or anyone with an interest in the outcome cannot unilaterally appoint a sole arbitrator. The logic is straightforward. If your interest disqualifies you from deciding, it disqualifies you from choosing the decider (which is the whole doctrine, in one line).
Then came the big one. In CORE II, decided on 8 November 2024, a five-judge bench held that party autonomy is subject to the mandatory requirements of Section 18 (equal treatment) and Section 12(5), and that equal treatment applies at the appointment stage, not just during the hearing. Two things follow. A clause requiring one party to unilaterally appoint a sole arbitrator is impermissible. And for a three-member tribunal, a clause forcing the other side to pick its nominee from a panel curated by one party is equally impermissible. Public sector undertakings may propose a panel. They cannot compel selection from it. In public-private contracts, unilateral appointment clauses violate Article 14 of the Constitution.
Fair warning on how CORE II is reported: the bench divided, and different issues carried different majorities. The majority was authored by the Chief Justice of India for himself and two others, with separate partly dissenting opinions from the remaining two judges. You’ll see the split described as 3:2 in some places and 4:1 in others, because both are true of different questions. Don’t rely on a single figure.
The trap is prospectivity. Invoking Article 142, the Court made its conclusions on three-member tribunals apply prospectively, to appointments made after 8 November 2024. Existing tribunals constituted before that date aren’t automatically vulnerable on this ground. We’d recommend checking the appointment date before building a challenge on CORE II, because a good number of them collapse right there.
Waiver is the second trap, and it tightened in 2026. In Bhadra International (India) Pvt. Ltd. v. Airports Authority of India, 2026 INSC 6 (SC, 5 January 2026), the Supreme Court held that waiver of Section 12(5) ineligibility must be by express agreement in writing, made after the disputes have arisen. It cannot be inferred from conduct, from participation in the proceedings, or from a recorded “no objection”. The absence of a prescribed format doesn’t open the door to implied waiver.
Read that alongside CORE II and a common assumption dies. Parties who participated in an arbitration without objecting often believe they’re now estopped from raising Section 12(5). But they aren’t.
This isn’t an abstract problem. On Indian legal forums, the recurring complaint from consumers reads like this one: “I have received a notice from a sole arbitrator appointed by bank.” The same poster adds that there is no amount due and no dispute over any such amount.
And the courts have noticed. In April 2026, the Bombay High Court flagged a rising trend of non-banking financial companies routing unilateral appointments through an institution or “algorithm-based selection”, in the hope, as the court put it, that “the inherent illegality in unilateral-appointment is magically cleansed”. The court identified only two lawful routes to appointment: party consent, or an appointment by a court under Section 11. Those were observations made while disposing of the petitions rather than a merits ruling, since the lender withdrew, but the court directed that the judgment be placed before the company’s board and audit committee.
So does an algorithm cure the defect? Not if one party controls the algorithm.
Seat, interim relief and the conduct of proceedings
The seat determines which court supervises the arbitration, and it’s the single most consequential drafting choice parties make without thinking about it. The Act doesn’t help: Section 20 of the Arbitration and Conciliation Act, 1996 speaks only of “place”, and defines neither seat nor venue. Everything here is judicial construction.
BALCO laid the foundation in 2012. A five-judge bench held that Part I of the Act doesn’t apply to foreign-seated arbitrations, adopting the territoriality principle of the Model Law and overruling Bhatia International. The catch is the date: BALCO applies only to arbitration agreements executed on or after 6 September 2012.
BGS SGS Soma did the harder work in 2019. Applying the Shashoua principle, the Court held that where a place is designated as the venue for the arbitration proceedings, rather than merely for hearings, and there’s no contrary indicia, that venue is the seat. It declared Hardy Exploration bad law. And Indus Mobile Distribution (P) Ltd. v. Datawind Innovations (P) Ltd., (2017) 7 SCC 678 had already established that a designated seat operates like an exclusive jurisdiction clause, vesting supervisory jurisdiction in the courts of the seat even where no part of the cause of action arose there.
One honest caveat. BGS Soma is a three-judge bench declaring an earlier three-judge bench bad law, which is a coordinate bench doing something coordinate benches ordinarily can’t. The point is unsettled at the doctrinal margin, and we found no larger bench resolving it. High Courts continue to diverge. Our fuller treatment of seat, venue and place works through the divergence.
The drafting error this produces is predictable and expensive: a contract that says the venue shall be Mumbai and separately that courts at Delhi have exclusive jurisdiction. After BGS Soma, naming Mumbai for the arbitration probably makes it the seat, and the Delhi clause is likely overridden. Two years of jurisdictional litigation before anyone reaches the merits.
On interim relief, Sections 9 and 17 run in parallel, with Section 9 before a court and Section 17 before the tribunal. In Amazon.com NV Investment Holdings LLC v. Future Retail Ltd., Civil Appeal Nos. 4492-4493 of 2021 (SC, 6 August 2021), decided on 6 August 2021, the Supreme Court held that an Emergency Arbitrator’s award in an institutional arbitration seated in India is an order under Section 17(1) and is enforceable under Section 17(2). An order enforcing it isn’t appealable under Section 37.
But read that holding narrowly, because its limit is where people get hurt. Amazon concerns India-seated institutional arbitration. Emergency arbitrator relief from a Singapore-seated or Paris-seated arbitration remains not directly enforceable in India. The draft 2024 Bill’s proposed Section 9A was aimed squarely at this gap, and since that Bill was never introduced, the gap is still open. Anyone advising that an SIAC emergency award from a Singapore seat now enforces in India is reading a proposal as if it were a statute. LawSikho’s longer treatment of when courts grant interim relief under Section 9 and how Section 17 orders are enforced goes deeper into the enforcement mechanics than there is room for here.
Section 16 carries the kompetenz-kompetenz principle: the tribunal rules on its own jurisdiction, including on the existence and validity of the arbitration agreement. In Re: Interplay strengthened it considerably by routing stamping objections there.
But Section 16 has an asymmetry that catches people. If the tribunal accepts a jurisdictional plea, that’s appealable under Section 37(2)(a). If it rejects the plea, there is no appeal. You wait for the final award and take the point under Section 34. Rushing to a writ petition under Article 226 or 227 instead is routinely dismissed, and a 2026 ruling confirmed that such a challenge must show it cannot await the final award.
The award and the section 29A clock
Section 29A of the Arbitration and Conciliation Act, 1996 sets the timetable, and it’s the reform that best illustrates the gap between statutory design and practice. The tribunal must make its award within twelve months from the completion of pleadings. Parties can extend by six months by consent. Anything beyond that needs a court.
International commercial arbitrations sit outside the twelve-month limit entirely (a carve-out that surprises a lot of counsel mid-arbitration). That exemption comes from the statute itself, inserted by the 2019 amendment, which requires only that such awards be made “as expeditiously as possible”. The Supreme Court confirmed the reading in Tata Sons Pvt. Ltd. v. Siva Industries and Holdings Ltd. (SC, 5 January 2023) in January 2023. Attributing the carve-out to the judgment rather than the section inverts the source of law, and it’s a common slip.
The judicial treatment has been consistently permissive. In Rohan Builders (India) Pvt. Ltd. v. Berger Paints India Ltd., 2024 INSC 686 (SC, 12 September 2024), decided on 12 September 2024, the Supreme Court held that an extension application under Section 29A(4) read with Section 29A(5) is maintainable even after the period has expired. The statutory words, “either prior to or after the expiry of the period so specified”, are unambiguous. The Court added that extensions aren’t to be granted mechanically, and reversed the Calcutta High Court’s contrary view.
A 2026 ruling went further, holding that an extension application is maintainable even after the award has been rendered. The time-barred award is ineffective, but the court’s power to extend survives, and courts retain a toolkit of fee reduction, costs, conditions and even substitution of the arbitrator.
Now set that against practice. Extension applications are almost always allowed. The twelve-month clock was Parliament’s answer to arbitration taking as long as litigation, and a limit that is routinely extended after it has already expired, and now even after the award has been made, is doing something other than limiting. But whether that’s judicial pragmatism or the quiet death of a reform depends on which side of the extension you’re sitting.
There’s a jurisdictional trap here that costs real months. A January 2026 ruling (2026 INSC 92) held that Section 29A extension applications lie before the “Court” as defined in Section 2(1)(e), meaning the commercial or civil court of original jurisdiction. Not the High Court. Not the Supreme Court. And this holds even where that superior court made the Section 11 appointment, because the appointing authority becomes functus officio once the tribunal is constituted.
So where do most people file? The High Court that appointed the tribunal, because it feels natural. That’s a jurisdictional dead end.
On the award itself, Section 31 governs form and content, and Section 31(7)(b) covers post-award interest. A February 2026 ruling held that an express contractual bar on pre-award interest binds the arbitrator, while post-award interest under Section 31(7)(b) is statutory and can’t be contracted out of, though courts may modify an excessive rate.
The assumption
The reality
1
Arguing limitation or accord and satisfaction at Section 11
Referral is confined to prima facie existence. It goes to the tribunal.
Krish Spinning (2024)
2
Treating CORE II as retrospective
The three-member-tribunal conclusions bind appointments after 8 November 2024 only.
CORE II (2024), Article 142
3
Assuming participation waives Section 12(5)
Waiver must be express, in writing, and after the dispute arose.
Bhadra International (2026)
4
Pleading patent illegality against a foreign-seated award
Section 34(2A) is domestic-only. The ground does not exist.
Ssangyong (2019)
5
Filing the Section 29A extension in the appointing High Court
It lies before the Section 2(1)(e) commercial court. The appointing court is functus officio.
2026 INSC 92
6
Assuming a Section 34 petition stays enforcement
It does not. A separate Section 36(3) application is required.
BCCI v. Kochi (2018); HCC (2019)
iPleaders · blog.ipleaders.in
Setting aside, modification and enforcement
Section 34 of the Arbitration and Conciliation Act, 1996 is where arbitration in India either ends or begins again, and the grounds are narrower than the sheer volume of Section 34 litigation suggests. The section has been rewritten once and reinterpreted repeatedly (twenty years ago it meant something close to the opposite of what it means now).
The arc starts with Saw Pipes in 2003, which read “patent illegality” into “public policy of India” and opened awards to merits review. Associate Builders systematised the grounds at the end of 2014. Parliament reset the section in 2015, and Section 34(2A) confined patent illegality to domestic awards with an express proviso that it can’t be invoked for erroneous application of law or re-appreciation of evidence.
Ssangyong gave that reset teeth on 8 May 2019. Post-2015, “public policy” means fraud or corruption, contravention of the fundamental policy of Indian law, or conflict with the most basic notions of morality or justice. No merits review. Patent illegality applies to domestic awards only and must go to the root of the matter. Our breakdown of the grounds for setting aside an award under Section 34 covers each ground in turn.
The mistake we see most often at this stage is pleading patent illegality against a foreign-seated or international commercial award. Section 34(2A) is domestic-only. The ground simply isn’t available, and the petition fails on a threshold point before anyone reads the merits.
Then, in April 2025, the ground shifted again. In Balasamy, a five-judge Constitution Bench held by a 4:1 majority that courts do have a limited power to modify an award under Sections 34 and 37. The Court confined it to four situations:
- Where the award is severable, by severing the invalid portion from the valid portion.
- By correcting clerical, computational or typographical errors apparent on the face of the record.
- By modifying post-award interest, in some circumstances.
- Where Article 142 applies, to be exercised with great care and caution.
The dissenting judge took the view that the power to set aside doesn’t include the power to modify.
Here’s the part that gets misread. Balasamy is not a licence to ask a Section 34 court to fix a bad award. The first two categories are narrow and technical. And the fourth, Article 142, is the Supreme Court’s own constitutional power. It isn’t available to a district judge or a High Court hearing a Section 34 petition, which is exactly where most parties are standing when they cite it. The 2026 rulings are already policing the line, including a May 2026 decision holding that Section 33(1)(a) permits only computational, clerical or typographical corrections, and that changing the mode of interest calculation is a substantive determination that falls outside it. Our analysis of whether courts can modify an arbitral award works through the four categories.
Enforcement under Section 36 has its own reversal story, and it’s the one instance where the Court struck down Parliament’s attempt to undo it.
Before 2015, filing a Section 34 petition automatically stayed enforcement, which made challenge the default tactic. BCCI v. Kochi, decided on 15 March 2018, held that the 2015 amendments applied to Section 36 enforcement even where the related court proceedings had been filed earlier, and warned the Government that the proposed Section 87 would be regressive. Parliament enacted Section 87 anyway in 2019. In Hindustan Construction, decided on 27 November 2019, the Supreme Court struck Section 87 down as manifestly arbitrary and violative of Article 14, and confirmed that the pre-2015 automatic stay reading had been wrong all along.
So the position today: filing a Section 34 petition does not stay enforcement. You need a separate application under Section 36(3), supported by reasons, and the court may impose conditions including security. And advising a client otherwise is how award-debtors discover execution proceedings while they assume they’re protected.
Which court enforces? The confusion on this is genuine and widespread. In one forum thread asking whether an execution petition goes to the court where the arbitration took place or to the court where the judgment-debtor resides, four responders split: three advised filing where the award was passed and then seeking a transfer, while a fourth said the applicant could apply directly to the court where the judgment-debtor resided. An award is a deemed decree under Section 36, and the seat determines supervisory jurisdiction. But the persistence of the question tells you how much of this procedure survives on assumption rather than authority.
Frequently asked questions
What is the arbitration procedure in India, in order?
The arbitration procedure in India runs in eight stages: a written arbitration agreement under Section 7 of the Arbitration and Conciliation Act, 1996; invocation by written notice under Section 21; constitution of the tribunal under Section 11; interim relief where needed under Section 9 or Section 17; pleadings under Section 23; hearings and evidence; the award under Section 31, subject to the Section 29A timeline; and then either challenge under Section 34 or enforcement under Section 36. Court involvement is deliberately front-loaded at appointment and back-loaded at challenge and enforcement.
Is an unstamped arbitration agreement valid after the 2023 Supreme Court ruling?
Yes, in the sense that it no longer blocks a reference to arbitration. A seven-judge bench held in December 2023 that an unstamped or insufficiently stamped instrument is inadmissible in evidence under Section 35 of the Indian Stamp Act, 1899, not void, and that the defect is curable. Stamping isn’t examined at the Section 8 or Section 11 stage; the objection goes to the tribunal. The instrument still needs to be impounded and stamped before it can be admitted in evidence, so stamping hasn’t stopped mattering. It has moved.
Can one party appoint the sole arbitrator?
No. A party, its official, or anyone with an interest in the outcome cannot unilaterally appoint a sole arbitrator, following Perkins Eastman in 2019 and confirmed by a five-judge bench in CORE II in November 2024. CORE II went further: for a three-member tribunal, a clause requiring one side to pick its nominee from a panel curated by the other side is also impermissible. Public sector undertakings may propose a panel, but they cannot compel selection from it, and unilateral appointment clauses in public-private contracts violate Article 14 of the Constitution.
Does CORE II invalidate arbitrator appointments made before November 2024?
No, and this catches people. Invoking Article 142, the Supreme Court made its conclusions on three-member tribunals apply prospectively, to appointments made after the date of the judgment, 8 November 2024. Tribunals constituted before that date aren’t automatically vulnerable on this ground. Check the appointment date before building a challenge around CORE II.
Can a court modify an arbitral award in India?
Only in narrow circumstances. A five-judge Constitution Bench held in April 2025, by a 4:1 majority, that courts have a limited power to modify an award under Sections 34 and 37 in four situations: severing an invalid portion where the award is severable; correcting clerical, computational or typographical errors apparent on the face of the record; modifying post-award interest in some circumstances; and where Article 142 applies. The Article 142 route belongs to the Supreme Court alone. A district court or High Court hearing a Section 34 petition cannot use it, which is the most common misreading of the judgment.
Does filing a Section 34 petition automatically stay enforcement?
No. That was the pre-2015 position, and it ended with the 2015 amendment. Parliament tried to restore it through Section 87 in 2019, and the Supreme Court struck Section 87 down in November 2019 as manifestly arbitrary and violative of Article 14. An award-debtor must file a separate application under Section 36(3) with reasons, and the court may grant a stay subject to conditions, including security.
Is the Arbitration and Conciliation (Amendment) Bill, 2024 now law?
No. It was released by the Department of Legal Affairs on 18 October 2024 as a consultation draft, with comments invited until 3 November 2024, following an expert committee report submitted in February 2024. As of July 2026 it has not been introduced in Parliament, and there has been no Cabinet approval, standing committee reference or assent. The operative statute remains the Arbitration and Conciliation Act, 1996 as amended in 2015, 2019 and 2021. Its proposals, including the Section 9A recognition of emergency arbitrator relief and the renaming of the statute, have no legal force.
References
Case law
- Amazon.com NV Investment Holdings LLC v. Future Retail Ltd., Civil Appeal Nos. 4492-4493 of 2021 (SC, 6 August 2021) (AIR 2021 SC 3723)
- Associate Builders v. Delhi Development Authority, (2015) 3 SCC 49 (AIR 2015 SC 620; decided 25 November 2014)
- BGS SGS Soma JV v. NHPC Ltd., (2020) 4 SCC 234 (SC, 10 December 2019, 3 judges)
- Bhadra International (India) Pvt. Ltd. v. Airports Authority of India, 2026 INSC 6 (SC, 5 January 2026)
- Bharat Aluminium Co. v. Kaiser Aluminium Technical Services Inc., (2012) 9 SCC 552 (SC, 6 September 2012, 5 judges)
- Bhatia International v. Bulk Trading S.A., (2002) 4 SCC 105 (AIR 2002 SC 1432; SC, 13 March 2002)
- Board of Control for Cricket in India v. Kochi Cricket Pvt. Ltd., AIR 2018 SC 1549 (SC, 15 March 2018)
- Central Organisation for Railway Electrification v. ECI-SPIC-SMO-MCML (JV), (2020) 14 SCC 712 (SC, 17 December 2019: overruled by the 2024 Constitution Bench below)
- Central Organisation for Railway Electrification v. ECI-SPIC-SMO-MCML (JV), 2024 INSC 857 (Constitution Bench, SC, 8 November 2024, 5 judges)
- Chloro Controls India Pvt. Ltd. v. Severn Trent Water Purification Inc., (2013) 1 SCC 641 (SC, 28 September 2012)
- Cox and Kings Ltd. v. SAP India Pvt. Ltd., 2023 INSC 1051 (SC, 6 December 2023, 5 judges)
- Delhi Airport Metro Express Pvt. Ltd. v. Delhi Metro Rail Corporation Ltd., (2022) 1 SCC 131 (SC, 9 September 2021)
- Delhi Metro Rail Corporation Ltd. v. Delhi Airport Metro Express Pvt. Ltd., 2024 INSC 292 (curative petition, SC, 10 April 2024)
- Garware Wall Ropes Ltd. v. Coastal Marine Constructions and Engineering Ltd., (2019) 9 SCC 209 (AIR 2019 SC 2053; SC, 10 April 2019)
- Gayatri Balasamy v. M/s ISG Novasoft Technologies Ltd., 2025 INSC 605 (Constitution Bench, SC, 30 April 2025, 5 judges, 4:1 majority)
- Himangni Enterprises v. Kamaljeet Singh Ahluwalia, (2017) 10 SCC 706 (AIR 2017 SC 5137; SC, 12 October 2017)
- Hindustan Construction Company Ltd. v. Union of India, AIR 2020 SC 122 (SC, 27 November 2019)
- Indus Mobile Distribution (P) Ltd. v. Datawind Innovations (P) Ltd., (2017) 7 SCC 678 (AIR 2017 SC 2105; SC, 19 April 2017)
- In Re: Interplay Between Arbitration Agreements under the Arbitration and Conciliation Act 1996 and the Indian Stamp Act 1899, 2023 INSC 1066 (SC, 13 December 2023, 7 judges)
- N.N. Global Mercantile (P) Ltd. v. Indo Unique Flame Ltd., (2023) 7 SCC 1 (SC, 25 April 2023, 5 judges: overruled by In Re: Interplay above)
- ONGC Ltd. v. Saw Pipes Ltd., (2003) 5 SCC 705 (AIR 2003 SC 2629; SC, 17 April 2003)
- Perkins Eastman Architects DPC v. HSCC (India) Ltd., AIR 2020 SC 59 (2019 SCC OnLine SC 1517; SC, 26 November 2019)
- Rohan Builders (India) Pvt. Ltd. v. Berger Paints India Ltd., 2024 INSC 686 (SC, 12 September 2024)
- SBI General Insurance Co. Ltd. v. Krish Spinning, 2024 INSC 532 (SC, 18 July 2024)
- SMS Tea Estates Pvt. Ltd. v. Chandmari Tea Co. Pvt. Ltd., (2011) 14 SCC 66 (AIR 2011 SC 1972; SC, 20 July 2011)
- Ssangyong Engineering & Construction Co. Ltd. v. NHAI, AIR 2019 SC 5041 ((2019) 8 SCALE 41; SC, 8 May 2019)
- Tata Sons Pvt. Ltd. v. Siva Industries and Holdings Ltd. (SC, 5 January 2023)
- TRF Ltd. v. Energo Engineering Projects Ltd., (2017) 8 SCC 377 (SC, 3 July 2017)
- Union of India v. Hardy Exploration and Production (India) Inc., (2019) 13 SCC 472 (AIR 2018 SC 4871; SC, 25 September 2018)
- Uttarakhand Purv Sainik Kalyan Nigam Ltd. v. Northern Coal Field Ltd., (2020) 2 SCC 455 (AIR 2020 SC 979; SC, 27 November 2019)
- Vidya Drolia v. Durga Trading Corporation, (2021) 2 SCC 1 (SC, 14 December 2020, 3 judges)
Statutes
- Arbitration and Conciliation Act, 1996: sections cited are 7, 8, 9, 11, 12(5), 16, 17, 18, 20, 21, 23, 29A, 31, 33, 34, 36 and 37.
- Indian Stamp Act, 1899: section cited is 35.
Secondary sources
- Supreme Court Observer and SCC Online report of the Chief Justice of India’s address to the Indian Council of Arbitration’s 4th international conference, London, June 2026
- ThePrint on arbitration costs and the Jaipur Vidyut Vitran Nigam tribunal fees
- Bar and Bench on the Bombay High Court’s observations on unilateral arbitrator appointments by non-banking financial companies
- IndiaCorpLaw on the Delhi Public Works Department notification of 21 April 2025 deleting the arbitration clause
- PRS Legislative Research Bills Track (confirming no arbitration Bill after 2021)
- Draft Arbitration and Conciliation (Amendment) Bill, 2024 (consultation text)
This article is for informational and educational purposes only and does not constitute legal advice. Arbitration law in India is moving quickly, and several of the 2026 rulings referred to above are recent. For advice on a specific dispute, consult a qualified advocate.



