Arb.A./18/2019 on 20 April, 2026

    0
    32
    ADVERTISEMENT

    Gauhati High Court

    Arb.A./18/2019 on 20 April, 2026

                                                                            1
    
    
    GAHC010092912019
    
    
    
    
                                                             2026:GAU-AS:5380
    
    
    
                              IN THE GAUHATI HIGH COURT
            HIGH COURT OF ASSAM, NAGALAND, MIZORAM & ARUNACHAL PRADESH)
    
                               Arb.A./18/2019
    
                          1.   Indian Oil Corporation
                               (Bongaigaon Refinery),
                               A Government of India Company, P.O.
                               Dhaligaon, District - Chirang,
                               Assam, Pin- 783385.
    
                                                                      ......Appellant
                                         -Versus-
    
                          1.   M/S Esteem Projects Private Limited,
                               B-39, Sector- 67, Noida (UP)- 201301.
    
                                                                 ......Respondent
    
      For Appellant       :    Mr. R. Choudhury, Advocate
    
      For Respondent      :    Mr. G. N. Sahewalla, Senior Advocate
                               Mr. H. K. Sharma, Advocate
    
      Date of Hearing     :    06.01.2026
      Date of Judgment    :    20.04.2026
    
    
    
    
    Arb.A./18/2019                                                      Page 1
                                                                                    2
    
    
    
    
                               BEFORE
              HON'BLE MR. JUSTICE MRIDUL KUMAR KALITA
    
                                   JUDGMENT
    

    1. Heard Mr. R. Choudhury, the learned counsel for the
    appellant. Also heard Mr. G. N. Sahewalla, the learned senior
    counsel assisted by Mr. H. K. Sharma, the learned counsel for
    the respondent.

    2. This appeal under Section 37 (1) (c) of the Arbitration and
    Conciliation Act, 1996 has been filed by the appellant, namely,
    Indian Oil Corporation (Bongaigaon Refinery), impugning the
    judgment and order dated 26.02.2019 passed by the Court of
    the learned District Judge, Chirang, Kajalgaon, in Misc.
    (Arbitration) Case No.18/2016, whereby the application filed
    by the appellant under Section 34 of the Arbitration and
    Conciliation Act, 1996 for setting aside the arbitral award
    dated 28.04.2016 was dismissed.

    SPONSORED

    3. The facts relevant for consideration of the instant appeal, in
    brief, are that the respondent herein was found as the
    successful bidder in a tender floated by the appellant for the
    work of “Heater package for the DHDT (Diesel Hydro-
    Treater) project”, Dhaligaon, Assam. The Letter of Intent
    (LOI) in respect of the work order No.2007/PC-1234 was
    issued in favor of the respondent on 16.08.2007. The letter of
    acceptance (LOA) was issued on 29.07.2007. The lump sum
    contract value of the work to be carried out by the respondent
    was USD 17,80,000/- (USD Seventeen Lakh Eighty Thousand

    Arb.A./18/2019 Page 2
    3

    Only) plus Rs. 18,72,20,000/- (Rupees Eighteen Crore
    Seventy-Two Lakh Twenty Thousand Only). The
    commencement date of the said contract was 16.08.2007 and
    the date of completion was 13 months from the date of LOI
    i.e., on 15.09.2008. However, the work was completed by the
    respondent on 10.08.2011, after a delay of 1059 days in
    completing the contract work.

    4. The respondent, after completion of the work, by letter dated
    07.12.2011, sought extension of time for completion of work
    up to 10.08.2011. The appellant by its letter dated
    20.08.2014, informed the respondent of the approval of
    competent authority regarding allowing extension of time up
    to 10.08.2011 to complete the work in question with
    imposition of Liquidated Damages (LD) amounting to 10% of
    the total contract value as per Clause 4.4.0.0 of the General
    Conditions of Contract (GCC). The LD amount was estimated
    at Rs. 2,59,57,700/- (Rupees Two Crore Fifty Nine Lakh Fifty
    Seven Thousand Seven Hundred only).

    5. It is pertinent to mention herein that the respondent
    submitted the final running account bill on 19.04.2012 for an
    amount of Rs. 23,27,946/- (Rupees Twenty Three Lakh
    Twenty Seven Thousand Nine Hundred Forty Six only).

    6. Against the decision of the appellant regarding the deduction
    of the LD, the respondent initiated arbitration proceedings by
    filing statement of claims dated 10.09.2014 before the Indian
    Council of Arbitration (ICA) with following claims –

    Arb.A./18/2019                                                              Page 3
                                                                                       4
    
    
                     (i)    Amount due under RA Bill No. 24 dated 19.04.2012 of
                            Rs. 23,27,946/-;
    

    (ii) Reimbursement of legal fees for opinion on procedure
    for post facto clearance and job work for imported
    material for Rs. 22,000/-;

    (iii) Reimbursement of demurrage/cost incurred on imported
    dues for Rs. 22,80,109/-;

    (iv) Additional cost incurred towards air freight on imported
    tubes;

    (v) Fluctuation in exchange rate for Rs. 1,00,21,890/-;

    (vi) Reimbursement of excise duty in terms of other than
    steel for Rs. 33,03,818/-;

    (vii) Reimbursement of excise duty in terms of other than
    steel for Rs. 42,42,410/-;

    (viii) Bank charges paid for extension of performance bank
    guarantee for Rs. 8,40,134/-;

    (ix) Charges for pre dry out of refractory for Rs. 10,00,000/-

    ;

    (x) Compensation for extended stay for Rs. 58,50,000/-;

    (xi) Reimbursement of Liquidated Damages for Rs.

    2,59,57,700/-;

    (xii) Loss of opportunity for Rs. 2,59,57,700/-;

    (xiii) Interest of Rs. 2,58,63,045/-;

    (xiv) Cost of arbitration.

    7. On receipt of the aforesaid statement of claims in the
    arbitration proceeding, the appellant submitted its
    reply/statement of defence on 18.12.2014. The appellant also

    Arb.A./18/2019 Page 4
    5

    submitted an application under Section 16 of the Arbitration
    and Conciliation Act, 1996 before the Arbitral Tribunal on
    18.12.2014 stating therein that the Arbitral Tribunal does not
    have jurisdiction to entertain the claims raised by the claimant
    as the same are beyond the scope and purview of the
    arbitration in terms of the agreement between the parties.

    8. The main defence taken by the present appellant in their
    statement of defence is that the Arbitral Tribunal lacks
    jurisdiction to entertain the claims raised by the respondent in
    as much as in terms of clause 9.1.0.0 of the GCC, only a
    dispute arising out of notified claims of the contractor included
    in the final bill in accordance with the provisions of Clause
    6.6.1.0 of the GCC can be the subject matter of the
    arbitration. It was contended that none of the claims raised by
    the respondent are notified claims in terms of GCC neither the
    same were included in the final bill dated 19.04.2012.

    9. However, the Arbitral Tribunal, after hearing the parties
    passed the arbitral award, on 28.04.2016, whereby, the Claim
    No. 2 to 10 and Claim No. 12 raised by the respondent were
    rejected by the Arbitral Tribunal as the same were not notified
    claims. However, it allowed the Claim No. 1, i.e., payment of
    Rs. 23,27,946/- against RA Bill No. 24 dated 19.12.2012. It
    also held in respect of Claim No. 11 that the appellant was not
    justified in levying the Liquidated Damages. Accordingly, the
    present appellant was directed to refund the amount of
    Liquidated Damage, namely, Rs. 2,59,57,700/- to the claimant
    (the present respondent). Against Claim No. 13, the Arbitral

    Arb.A./18/2019 Page 5
    6

    Tribunal allowed interest at the rate of 12% per annum from
    the date of reference i.e., 08.08.2015 on the Liquidated
    Damages of Rs. 2,59,57,700/- as well as on the amount under
    RA Bill No. 24 i.e., Rs. 23,27,946/-. In respect of Claim No. 14,
    the Tribunal directed that the claimant would be entitled to a
    sum of Rs. 25,00,000/- towards the cost of the arbitral
    proceeding.

    10. Being aggrieved and dissatisfied with the award dated
    28.04.2016, the appellant preferred an application under
    Section 34 of the Arbitration and Conciliation Act, 1996,
    before the Court of the learned District Judge, Chirang. The
    said application was registered as Misc. (Arbitration) Case
    No.18/2016.

    11. During the pendency of the aforesaid arbitration case, the
    respondent filed an application under Section 34 (5) of the
    Arbitration and Conciliation Act, 1996, alleging that the
    petition under Section 34 of the Arbitration and Conciliation
    Act, 1996, filed by the present appellant was not maintainable
    on the ground of non-compliance of the statutory provision of
    serving prior notice on the respondent before filing the
    aforesaid petition, as contained in Section 34 (5) of the
    Arbitration and Conciliation Act, 1996.

    12. The Court of the learned District Judge, Chirang, allowed the
    aforesaid application by its order dated 06.07.2017 and held
    that the application under Section 34 of the Arbitration and
    Conciliation Act, 1996 filed by the present appellant is hit by
    Section 34 (5) of the Arbitration and Conciliation Act, 1996,

    Arb.A./18/2019 Page 6
    7

    and as such, the said application under Section 34 of the said
    Act is not maintainable.

    13. On being aggrieved by the aforesaid order dated 06.07.2017,
    passed by the Court of the learned District Judge, Chirang,
    the appellant approached this Court by filing an arbitration
    appeal, i.e., Arbitration Appeal No.19/2017. Later on, this
    Court, by its order dated 09.08.2018, passed in Arbitration
    Appeal No. 19/2017 had set aside the order dated 06.07.2017,
    passed by the Court of the learned District Judge, Chirang,
    petition under Section 34 (5) of the Arbitration and
    Conciliation Act, 1996 filed by the present respondent.

    14. The matter was remanded to the Court of learned District
    Judge, Chirang for deciding the petition under Section 34 as
    well as Section 16 of the Arbitration and Conciliation Act 1996,
    which were filed by the present appellant, afresh.

    15. Ultimately, by its judgment dated 20.06.2019, which has been
    impugned in the instant appeal, the Court of the learned
    District Judge, Chirang held that the Arbitral Tribunal has the
    jurisdiction to decide the disputes raised by the respondent
    regarding liquidated damages deducted from the final bill of
    the respondent by the appellant and as such by the aforesaid
    judgment, the petition under Section 34 of the Arbitration and
    Conciliation Act, 1996, filed by the present appellant, was
    dismissed.

    16. Mr. R. Choudhury, the learned counsel for the appellant
    submits that the Court of the learned District Judge, Chirang,
    while passing the impugned judgment dated 26.02.2019,

    Arb.A./18/2019 Page 7
    8

    erred and failed to take into consideration the aspect that the
    arbitral award dated 28.04.2016, passed by the Arbitral
    Tribunal, is liable to be set aside under Section 34 (2) (a) (iv)
    of the Arbitration and Conciliation Act, 1996. He submits that
    the Court of the learned District Judge, Chirang, erred in not
    considering the fact that the Claim No.11 of the present
    respondent before the Arbitral Tribunal, regarding the
    reimbursement of the Liquidated Damages, was not notified in
    terms of the Clause 6.6.1.0 the GCC. As such, the same could
    not have been the subject matter of the arbitration, in terms
    of the Clause 9.1.0.0 of the GCC, before the Arbitral Tribunal.
    He submits that the Arbitral Tribunal failed to take into
    consideration that only those disputes arising out of the
    notified claim of the contractor included in the final bill, in
    accordance with the provision of clause 9.1.0.0, are referrable
    to arbitration. However, as the dispute regarding deduction of
    Liquidated Damages by the appellant was not notified in
    terms of the aforementioned clauses of the contract, the
    Arbitral Tribunal lacks jurisdiction to entertain any reference
    for arbitration.

    17. The learned counsel for the appellant submits that as per
    Clause 6.6.1.0 of the GCC, if the contractor had any dispute
    regarding deduction of Liquidated Damages by the appellant
    from the final bill, he ought to have given notice in writing to
    the Engineer-in-Charge and the Site Engineer within 10 days
    from the date of issuance of order. He submits that any of the
    claims of contractor notified in accordance with the provision

    Arb.A./18/2019 Page 8
    9

    of Clause 6.6.1.0 remain at the time of preparation of final bill
    by the contractor, same shall have to be separately included in
    the final bill prepared by the contractor in form of a statement
    of claim attached thereto in terms of the Clause 6.6.3.0 of the
    GCC. He further submits that as per Clause 6.6.3.1, any
    notified claim not separately reflected and included in the final
    bill in accordance with the provisions of Clause 6.6.3.0 shall
    be deemed to have been waived by the contractor. He further
    submits that as per Clause 9.1.0.0, only notified claim of the
    contractor included in the final bill in accordance with the
    provision of Clause 6.6.3.0 may be referred to arbitration as
    per Clauses 9.1.1.0 and 9.1.2.0 of the GCC. However, in the
    instant case, the claim regarding reimbursement of deduction
    of liquidated damages by the appellant was not notified by the
    respondent in pursuant to the provisions contained in Clause
    6.6.1.0, therefore, the Arbitral Tribunal does not have
    jurisdiction to entertain any reference of such dispute to
    arbitration under Clause 9.1.0.0 of the GCC. In support of his
    submission, the learned counsel for the appellant has cited a
    ruling of the Apex Court in the case of “Indian Oil Corporation
    Limited Versus NCC Limited” reported in 2023 (2) SCC 539.

    18. The learned counsel for the appellant submits that since as
    per Clause 9.1.0.0, only disputes arising out of notified claim
    are referrable to arbitration and since in the instant case, the
    dispute regarding deduction of the liquidated damages by the
    appellant was not notified in terms of Clause 6.6.1.0 of the
    GCC, the same is a non-arbitrable dispute and it would not be

    Arb.A./18/2019 Page 9
    10

    open for the Arbitral Tribunal to arbitrate over such a dispute,
    since it would be beyond its jurisdiction. He further submits
    that this aspect was not taken into consideration by the Court
    of the learned District Judge, Chirang while passing the
    impugned judgment under Section 34 of the Arbitration and
    Conciliation Act, 1996.

    19. The learned counsel for the appellant submits that that such a
    dispute, which is not notified in terms of the aforesaid clauses
    of the GCC, may be treated as those kind of dispute which are
    specifically excluded from the purview of arbitration clause
    and as such, the same would not be referrable to arbitration,
    therefore, the Court of the learned District Judge, Chirang as
    well as the Arbitral Tribunal failed to consider this aspect while
    assuming jurisdiction to arbitral dispute referred to it. In
    support of his submission, the learned counsel for the
    appellant has cited a ruling of a Coordinate Bench of this
    Court in the case of “Bongaigaon Refinery Versus Buildworth
    Private Limited”, reported in 2019 SCC online GAU 2820.

    20. The learned counsel for the appellant has also submitted that
    since the delay in execution of the work is apparent in this
    case and the same is attributable to the contractor, the
    appellant has rightly invoked the provision of Clause 4.4.2.0 of
    the GCC and levied 10% of the total contract value as
    liquidated damages on the respondent to compensate the loss
    suffered to the appellant due to breach of contract by the
    respondent in completing the contract work beyond the
    stipulated time as provided in the contract. He submits that

    Arb.A./18/2019 Page 10
    11

    same is in terms with the spirit of law as contained in Section
    73
    of the Contract Act, 1872.

    21. The learned counsel for the appellant also submits that the
    Court of the learned District Judge, Chirang, while considering
    the application under Section 34 of the Arbitration and
    Conciliation Act, 1996 filed by the present appellant also failed
    to take into consideration the fact that though the Arbitral
    Tribunal rejected the Claim No. 2 to 10 and 12 of the
    respondent, as the same were not notified claims in terms of
    Clause 6.1.0.0, whereas, the claim in respect of liquidated
    damages was dealt with by adopting a different reasoning by
    the Tribunal, which is blatantly illegal. He submits that the
    Arbitral Tribunal erred in arbitrating over a non-arbitrable
    dispute as per the agreement between the parties. He also
    submits that the arbitral award is also liable to be set aside
    under Section 34 (2) (b) (i) as well as (ii) of the Arbitration
    and Conciliation Act, 1996
    .

    22. On the other hand, Mr. G. N. Sahewalla, the learned senior
    counsel for the respondent has submitted that the Court of
    the learned District Judge, Chirang has rightly dismissed the
    application under Section 34 of the Arbitration and
    Conciliation Act, 1996, filed by the present appellant
    challenging the arbitral award passed by the Arbitral Tribunal
    on 28.04.2016. He submits that in page No.13 of the arbitral
    award, the Arbitral Tribunal has observed that the objection as
    to deduction of liquidated damages by the appellant may not
    be regarded as a claim and hence, the notification of the said

    Arb.A./18/2019 Page 11
    12

    objection under Clause 6.6.1.0 of the GCC is not necessary for
    referring any dispute arising out of such deduction to
    arbitration in terms of Clause 9.1.0.0 of the GCC.

    23. The learned senior counsel for the respondent has submitted
    that the Arbitral Tribunal has correctly held that since the
    deduction against liquidated damages were made after 2.5
    years of the submission of final RA bill as well as after expiry
    of defect liability period on 09.08.2012, the objection
    regarding deduction of liquidated damages could not have
    been raised in the final bill by the respondent and as such, the
    same could not have been notified in terms of the provision
    contained in Section 6.6.1.0 of the GCC. He submits that the
    view taken by the Arbitral Tribunal regarding its jurisdiction to
    entertain the reference cannot be regarded as perverse.
    Hence, the Court of the learned District Judge, Chirang was
    right in not interfering in the view taken by the Arbitral
    Tribunal as in a proceeding under Section 34 of the Arbitration
    and Conciliation Act, 1996, it cannot sit as the Court of appeal
    over the findings of the Arbitral Tribunal.

    24. He further submits that the interpretation of the terms of
    contract is primarily for an arbitrator to decide, and unless the
    arbitrator construes the contract in such a way that it could
    not be said to be something that no fair-minded or reasonable
    person could do, same cannot be faulted with. He submits
    that the Court should not interfere with an award merely
    because an alternative view on facts and interpretation of
    contract exists. He submits that the court needs to be

    Arb.A./18/2019 Page 12
    13

    cautious and should defer to the view taken by the Arbitral
    Tribunal even if the reasoning provided in the award is implied
    unless such award portrays perversity unpardonable under
    Section 34 of the Arbitration and Conciliation Act, 1996. He
    submits that the Court of the learned District Judge, Chirang
    is, therefore, right in not interfering with the interpretation
    given by the Arbitral Tribunal while discarding the objection
    regarding its jurisdiction to entertain the reference of the
    dispute to the arbitration.

    25. The learned senior counsel for the respondent submits that
    the final RA bill was submitted by the respondent in the year
    2012 itself, whereas, the decision to deduct liquidated
    damages was made by the appellant in the year 2014 as such,
    the said claim could not have been included in the final bill,
    which was submitted two years prior to imposition of LD by
    the appellant. The learned senior counsel for the respondent
    submits that this aspect was also taken into consideration in
    Page No. 79 of the impugned judgment by the Court of the
    learned District Judge, Chirang.

    26. He also submits that the reasoning given by the Court of the
    learned District Judge, Chirang for agreeing with the finding of
    the Arbitral Tribunal that the dispute regarding deduction of
    liquidated damages by the appellant could not have been
    included in the final bill, should not be regarded as perverse
    so as to justify any interference by this Court in the
    impugned order passed by the learned District Judge, Chirang

    Arb.A./18/2019 Page 13
    14

    in exercise of its powers under Section 34 of the Arbitration
    and Conciliation Act, 1996.

    27. The learned senior counsel for the respondent submits that
    when it comes to the scope of an appeal under Section 37 of
    the Arbitration and Conciliation Act, 1996, the jurisdiction of
    an Appellate Court in examining the order refusing to set
    aside an award is all the more circumscribed. He submits that
    if the view taken by the Arbitral Tribunal in the interpretation
    of contract is a possible and plausible view, merely because
    another view can be taken may hardly be ground for
    interference with the arbitral award.

    28. The learned senior counsel for the respondent has also
    submitted that since the contract work has already been
    completed in the year 2011 and since the final RA bill was
    also submitted in the year 2012, there may not be any
    Engineer-in-Charge or Site Engineer after two and a half years
    of completion of the said work. Hence, the question of
    notifying them does not arise. He also submits that this Court
    while exercising its jurisdiction under Section 37 of the
    Arbitration and Conciliation Act, 1996 cannot travel beyond
    the restrictions laid down under Section 34 of the said Act. He
    submits that this Court cannot undertake an independent
    assessment of the merit of the award and must only ascertain
    that the court of learned District Judge, while exercising the
    powers under Section 34 of the Arbitration and Conciliation
    Act, 1996 has not exceeded the scope of the provisions. He
    submits that it is evident that in the case where an arbitral

    Arb.A./18/2019 Page 14
    15

    award has been confirmed by the Court under Section 34 of
    the Arbitration and Conciliation Act, 1996, this Court should be
    very cautious in interfering with such a finding of the Court.
    He submits that the Court of the learned District Judge,
    Chirang has rightly dismissed the application under Section 34
    of the Arbitration and Conciliation Act, 1996 filed by the
    present appellant and has rightly refused to interfere with the
    arbitral award passed by the learned Arbitral Tribunal,
    therefore, he submits that this appeal does not have any merit
    and is liable to be dismissed.

    29. In support of his submission, the learned senior counsel for
    the respondent has cited the following rulings:

    (i) OPG Power Generation Private Limited Versus M/s ENEXIO
    Power Cooling Solutions (I) Private Limited and others re-

    ported in 2025 (2) SCC 417.

    (ii) UHL Power Company Limited Versus the State of Himachal
    Pradesh, reported in 2022 (4) SCC 116.

    (iii) MMTC Ltd. Versus M/s Vedanta Limited reported in 2019 (4)
    SCC 163.

    (iv) Reliance Infrastructure Ltd. Versus State of Goa reported in
    2024 (1) SCC 479.

    (v) Olympus Superstructures Private Limited Versus Meena Vi-

    jay Khetan and Others reported in 1999 (5) SCC 651.

    (vi) Associate Builders Versus DDA reported in 2015 (3) SCC 49.

    (vii) S V Samudran Versus The State of Karnataka reported in
    2024 (3) SCC 623.

    30. I have considered the submissions made by the learned
    counsel for both sides and have gone through the materials

    Arb.A./18/2019 Page 15
    16

    available on record. I have also perused the rulings cited by
    the learned counsel for both sides in support of their
    respective submissions.

    31. The main contention of the appellant in the instant appeal
    under Section 37 (1) (c) of the Arbitration and Conciliation
    Act, 1996 is that the Court of the learned District Judge,
    Chirang, while considering the application under Section 34 of
    the Arbitration and Conciliation Act, 1996, filed by the present
    appellant, as well as the Arbitral Tribunal itself, did not
    consider the objection raised by the present appellant before
    both the Forums regarding the lack of jurisdiction of the
    Arbitral Tribunal to entertain the arbitration proceedings.

    32. It is contended that the dispute regarding the imposition of
    liquidated damage by the present appellant on the respondent
    was not notified in terms of the Clause 6.6.1.0 of the GCC,
    therefore, said dispute could not have been referred to
    arbitration under Clause 9.1.0.0 of the GCC.

    33. For the sake of convenience Clause 6.6.1.0 of the GCC is
    quoted herein below:

    “6.6.1.0 – Should the contractor consider that he is
    entitled to any extra payment or compensation in
    respect of the works over and above the amounts
    due in term of the contract as specified in Clause
    6.3.1.0 hereof or should the contractor dispute the
    validity of any deductions made or threatened by
    the Owner from any Running Account Bills or any
    payments due to him in term of the contract, the
    contractor shall forthwith give notice in writing of
    his claim in this behalf to the Engineerin-Charge and
    the Site Engineer within 10 (ten) days from the date
    of the issue of orders or instructions relative to any

    Arb.A./18/2019 Page 16
    17

    works for which the contractor claims such
    additional payment or compensation, or on the
    happening of other event upon which the contractor
    bases such claim, and such notice shall give full
    particulars of the nature of such claim, grounds on
    which it is based, and the amount claimed. The
    contractor shall not be entitled to raise any claim, or
    shall the Owner anywise be liable in respect of any
    claim by the contractor unless notice of such claim
    shall have been given by the contractor to the
    Engineer-in-charge and the Site Engineer in the
    manner and within the time aforesaid, and the
    contractor shall be deemed to have waived any or
    all claims and all his rights in respect of any claim
    not notified to the Engineer-in-charge and the Site
    Engineer in the matter and within the time
    aforesaid.”

    34. It appears that the objection regarding jurisdiction of the
    Arbitral Tribunal for want of notifying the dispute regarding
    deduction of liquidated damages from the final bill of the
    respondent was raised before the Arbitral Tribunal also. The
    Arbitral Tribunal rejected the said objection mainly on the
    ground that according to it, the respondent is not asking for
    any additional payment from the appellant and in that sense,
    it was not regarded as a claim, it only objected to the
    deduction of liquidated damages after more than two and a
    half years after submission of final RA bill, much after the
    lapse of defect liability period which expired on 09.09.2012.
    The Arbitral Tribunal also held that since the objection to the
    deduction made by the appellant as liquidated damages was
    not any additional claim by the respondent. There is no
    question of including the same in the final RA bill submitted

    Arb.A./18/2019 Page 17
    18

    by the respondent and accordingly, it held that it does have
    jurisdiction to entertain the arbitral proceedings.

    35. It also appears that the Court of the learned District Judge,
    Chirang while considering the application under Section 34 of
    the Arbitration and Conciliation Act, 1996, has held in Page
    No. 79 of the impugned judgment that as demand for
    imposition of liquidated damage as the liquidated damages
    were imposed on the respondent much after submission of
    final RA bill by it, hence, it was not possible for the present
    respondent to have mentioned the claim of reimbursement of
    deduction of liquidated damages in the said bill.

    36. It also appears that the Court of the learned District Judge,
    Chirang has also held in page no. 80 of the impugned
    judgment that Clause 9.1.0.0 of the GCC contemplates about
    two circumstances, under which a dispute may be referred to
    arbitration. Firstly, any dispute arising between parties out of
    any notified claim of the contractor included in the final bill.
    Secondly, any dispute regarding deduction from the final bill
    of the contractor or any amount payable by the owner to the
    contractor in respect of the work. The Court of the learned
    District Judge, Chirang observed that the dispute of illegal
    deduction of liquidated damage which was referred to the
    arbitration is not included in first part of the Clause 9.1.0.0 of
    the GCC, rather, it is included in the second part of the said
    clause which allows any dispute regarding any deduction from
    final bill of the contractor to be referred to the arbitration.
    Hence, the Court of the learned District Judge, Chirang held

    Arb.A./18/2019 Page 18
    19

    that the Arbitral Tribunal was correct in holding that the
    dispute referred to the arbitration by the respondent cannot
    be a notified claim, rather it is a dispute regarding deduction
    of liquidated damages from the final bill which could not have
    been notified in terms of Clause 6.6.1.0 of the GCC.

    37. For the sake of clarity, the Clause 9.1.0.0 of the GCC is quoted
    herein below:

    “9.1.0.0 – Subject to provisions of Clause 6.7.1.0
    and 6.7.2.0 hereof, any dispute or difference
    between the parties hereto arising out of any
    notified claim of the contractor included in the final
    bill in accordance with the provisions of Clause
    6.6.3.0 hereof and/or arising out of any amount
    claimed by the Owner (whether or not the amount
    claimed by the Owner or any part thereof shall
    have been deducted from the final bill of the
    contractor or any amount paid by the Owner to
    the contractor in respect of the work) shall be
    referred to arbitration as hereunder provided in
    Clauses 9.1.1.0 and 9.1.2.0 as applicable.”

    38. The Arbitral Tribunal as well as the Court of the learned
    District Judge, Chirang interpreted the Clause 6.6.1.0 and
    Clause 9.1.0.0 of the GCC in a manner, which does not require
    the dispute regarding deduction of liquidated damages from
    the final bill to be notified under Clause 6.6.1.0 of the GCC.
    Though, this court is of the view that a different interpretation
    of the said clauses may also be made, however, the
    jurisdiction of this Court under Section 37 of the Arbitration
    and Conciliation Act, 1996 is extremely circumscribed to justify
    making of any such attempt.

    Arb.A./18/2019 Page 19
    20

    39. The Apex Court in the case of “UHL Power Company
    Limited Versus the State of Himachal Pradesh” (Supra) has

    observed as follows:

    “20. In Dyna Technologies [Dyna Technologies (P)
    Ltd. v. Crompton Greaves Ltd.
    , (2019) 20 SCC 1],
    the view taken above has been reiterated in the
    following words : (SCC p. 12, para 25)
    “25. Moreover, umpteen number of judgments of
    this Court have categorically held that the courts
    should not interfere with an award merely because
    an alternative view on facts and interpretation of
    contract exists. The courts need to be cautious and
    should defer to the view taken by the Arbitral
    Tribunal even if the reasoning provided in the
    award is implied unless such award portrays
    perversity unpardonable under Section 34 of the
    Arbitration Act.”

    21. An identical line of reasoning has been adopted
    in South East Asia Marine Engg. & Constructions Ltd.
    (SEAMEC Ltd.) v. Oil India Ltd. [South East Asia
    Marine Engg. & Constructions Ltd.

    (SEAMEC Ltd.) v. Oil India Ltd., (2020) 5 SCC 164 :

    (2020) 3 SCC (Civ) 1] and it has been held as
    follows : (SCC p. 172, paras 12-13)
    “12. It is a settled position that a court can set
    aside the award only on the grounds as provided
    in the Arbitration Act as interpreted by the courts.

    Recently, this Court in Dyna Technologies (P)
    Ltd. v. Crompton Greaves Ltd. [Dyna Technologies
    (P) Ltd.
    v. Crompton Greaves Ltd., (2019) 20 SCC
    1] laid down the scope of such interference. This
    Court observed as follows : (SCC p. 12, para 24)
    „24. There is no dispute that Section 34 of the
    Arbitration Act limits a challenge to an award only
    on the grounds provided therein or as interpreted
    by various Courts. We need to be cognizant of the

    Arb.A./18/2019 Page 20
    21

    fact that arbitral awards should not be interfered
    with in a casual and cavalier manner, unless the
    Court comes to a conclusion that the perversity of
    the award goes to the root of the matter without
    there being a possibility of alternative
    interpretation which may sustain the arbitral
    award. Section 34 is different in its approach and
    cannot be equated with a normal appellate
    jurisdiction. The mandate under Section 34 is to
    respect the finality of the arbitral award and the
    party autonomy to get their dispute adjudicated by
    an alternative forum as provided under the law. If
    the Courts were to interfere with the arbitral award
    in the usual course on factual aspects, then the
    commercial wisdom behind opting for alternate
    dispute resolution would stand frustrated.‟

    13. It is also settled law that where two views are
    possible, the Court cannot interfere in the plausible
    view taken by the arbitrator supported by
    reasoning. This Court in Dyna Technologies [Dyna
    Technologies (P) Ltd. v. Crompton Greaves Ltd.
    ,
    (2019) 20 SCC 1] observed as under : (SCC p. 12,
    para 25)
    „25. Moreover, umpteen number of judgments of
    this Court have categorically held that the Court
    should not interfere with an award merely because
    an alternative view on facts and interpretation of
    contract exists. The Courts need to be cautious
    and should defer to the view taken by the Arbitral
    Tribunal even if the reasoning provided in the
    award is implied unless such award portrays
    perversity unpardonable under Section 34 of the
    Arbitration Act.‟ “

    40. If we go through the Clause 9.1.0.0 of the GCC as quoted
    herein above, it appears that under the facts and
    circumstances of this case where the liquidated damages were

    Arb.A./18/2019 Page 21
    22

    imposed after two and a half years of submitting final RA bill,
    the interpretation of the aforesaid Clause (Clause 9.1.0.0)
    given by the Arbitral Tribunal as well as by the Court of the
    learned District Judge, Chirang, while dealing with the
    application under Section 34 of the Arbitration and
    Conciliation Act, 1996, cannot be regarded as irrational
    interpretation. Though, an alternative interpretation is also
    possible, however, merely because an alternative view on
    facts and interpretation of contract exists, this Court in
    exercise of its powers under Section 37 of the Arbitration and
    Conciliation Act, 1996 would not interfere in the arbitral award
    as well as in the judgment of the Court of the learned District
    Judge, Chirang rendered under Section 34 of the Arbitration
    and Conciliation Act, 1996, wherein it has declined to set
    aside the arbitral award.

    41. This Court is of the considered opinion that in the facts and
    circumstances, which are peculiar to this case, the
    interpretation of the relevant clauses of the GCC as given by
    the learned Arbitral Tribunal as well as by the Court of the
    learned District Judge, Chirang under Section 34 of the
    Arbitration and Conciliation Act, 1996 are both possible and
    plausible. As such, any interference with the impugned
    judgment of the Court of the learned District Judge, Chirang,
    whereby it refused to set aside the arbitral award, is not
    warranted.

    42. In view of the discussions made in the foregoing paragraphs
    as well as the reasons stated therein, this Court is of

    Arb.A./18/2019 Page 22
    23

    considered opinion that the present appeal lacks merit and
    any interference with the finding of the Court of the learned
    District Judge, Chirang in the impugned judgment as well as
    any interference in the arbitral award passed by the learned
    Arbitral Tribunal is not warranted under the facts and
    circumstances of the case.

    43. Accordingly, this appeal is hereby dismissed.

    44. The stay on the execution of the impugned judgment and
    order of the learned District Judge, Chirang granted by this
    court on 08/11/2019 in IA(C)3412/2019 shall stands vacated.
    The respondent shall be entitled to the pendente lite interest
    on the awarded amount in terms of the arbitral award.

    
    
    
    
                                                                 JUDGE
    
         Comparing Assistant
    
    
    
    
                                Digitally signed
               Munm             by Munmun
                                Boruah
               un               Date:
                                2026.04.20
               Boruah           16:10:04
                                +05'30'
    
    
    
    
    Arb.A./18/2019                                                           Page 23
     

    [ad_1]

    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here