Ali Mohammad Dar vs National Highways Authority Of India on 7 May, 2026

    0
    21
    ADVERTISEMENT

    Jammu & Kashmir High Court – Srinagar Bench

    Ali Mohammad Dar vs National Highways Authority Of India on 7 May, 2026

           IN THE HIGH COURT OF JAMMU & KASHMIR AND LADAKH
                             AT SRINAGAR
    
    
                                        CM(M) No. 149/2026
                                         CM No. 2585/2026
    
                                                                  Reserved on: 05.05.2026
                                                               Pronounced on: 07 .05.2026
                                                                 Uploaded on: 08 .05.2026
                                                         Whether the operative part or full
                                                           judgment is pronounced: Full
    
     Ali Mohammad Dar                                      ...Petitioner(s)/Appellant(s).
     S/O Ghulam Nabi Dar
     R/O Sangam District Anantnag
     Aged 52 years
    
       Through:     Mr. S. N Ratanpuri , Advocate
                                           Vs.
    1. National Highways Authority of India                             ...Respondent(s).
       through Project Director, NHAI, PIU,
       Srinagar.
    2. Collector Land Acquisition, Anantnag
    
       Through:     Mr. Ilyas Nazir Laway, GA
    
    
       CORAM: HON'BLE MR. JUSTICE WASIM SADIQ NARGAL, JUDGE
                                       JUDGEMENT
    

    07.05.2026

    BRIEF FACTS

    SPONSORED

    1. The Petitioner in the instant petition is aggrieved of Order dated 04.02.2026

    passed in an application under Section 151 of the Code of Civil Procedure

    read with Section 17-B of the J&K Land Acquisition Act, as also Order

    dated 27.04.2026 passed in an application seeking review of Order dated

    04.02.2026, by the Court of learned Principal District Judge, Anantnag. The

    impugned orders as per the petitioner being contrary to law, facts, and settled

    1 | Page CM(M) No. 149/2026
    principles of procedure, are liable to be set aside and are accordingly

    challenged by way of the present petition under Article 227 of the

    Constitution of India.

    ARGUMENTS ON BEHALF OF THE PETITIONER

    2. Learned counsel submits that land measuring 6 kanals and 2 marlas, along

    with structures existing thereon, belonging to the Petitioner, came to be

    acquired for the purpose of four-laning of the Srinagar-Jammu National

    Highway at Village Sangam, Bijbehara, District Anantnag.

    3. It is submitted that the acquisition proceedings were conducted strictly in

    accordance with law and an award came to be passed. Being dissatisfied with

    the quantum of compensation, the Petitioner sought reference, which initially

    came to be declined.

    4. It is submitted that upon intervention of this Court, the Collector was

    directed to consider the claim of the Petitioner under Section 18 of the J&K

    Land Acquisition Act, pursuant to which the matter was referred to the

    learned Principal District Judge, Anantnag. The Reference Court, after

    framing issues and recording evidence, passed a detailed award dated

    15.07.2014, whereby, the petitioner was held entitled to the following

    compensation:

    i. “Compensation of land measuring 6 kanals 2 marlas falling
    under survey No.271,272 and 273 situated at Sangam,
    Bijbehara, @ Rs.30 lac per kanal;

    2 | Page CM(M) No. 149/2026
    ii. Compensation for Shane Kashmir Passenger Oriented wayside
    amenities project as per EXPW-1/1 amounting to Rs. 155.96
    lacs;

    iii. Compensation for construction of proposed single storey
    dormatry for Shane Kashmir, amounting to Rs. 11.27 lacs;
    iv. Compensation for reinstallation of the petrol out let @
    Rs.66.70,600/-; and
    v. Compensation for loss of earnings from the date of notification
    till completion of the petrol out let Rs.24.00 lacs.”

    5. It is further submitted that the Reference Court clearly directed deduction of

    the amount already received from the total compensation.

    6. Learned counsel lays particular emphasis on the fact that an amount of

    ₹1,02,54,693/- was paid towards cost of demolition of structures and was not

    part of compensation, which is explicitly recorded in the award itself.

    7. It is submitted that this crucial aspect has been completely ignored by the

    Court below while passing the impugned orders.

    8. It is submitted that the award dated 15.07.2014 was challenged by

    respondent No.1 before this Hon’ble Court in CFA No. 190/2014, which

    came to be dismissed on 25.08.2022 both on maintainability and also on

    merits.

    9. Thereafter, the order passed by this Court in the above appeal came to be

    challenged before the Hon’ble Supreme Court by way of Special Leave

    Petition, SLP No. 21543/2022, which also came to be dismissed on

    20.02.2024, thereby rendering the award final and binding.

    3 | Page CM(M) No. 149/2026

    10.Learned counsel submits that after finality of the award, respondent No.1

    filed an application dated 06.08.2024 before the learned Principal District

    Judge, Anantnag, alleging excess payment.

    11.It is contended that the said application was wholly vague, frivolous, and

    unsupported by any cogent calculation or legal basis, and was nothing but an

    attempt to reopen settled issues which had attained finality up to the Hon’ble

    Supreme Court.

    12.It is submitted that despite detailed objections filed by the Petitioner

    demonstrating that all payments were made strictly in terms of the award, the

    learned Court below, without proper appreciation of facts and law, allowed

    the application vide order dated 04.02.2026 and directed recovery of

    ₹2,61,34,972/- (two crore, sixty one lakh, thirty four thousand and nine

    hundred seventy two rupees) along with interest @ 6%, from the date of

    receipt of the same.

    13.The learned counsel for the petitioner further submits that review application

    filed by the Petitioner was also dismissed vide order dated 27.04.2026

    without due consideration.

    14.It is submitted that the learned Court below has gravely erred in treating the

    amount of ₹1,02,54,693/- paid towards demolition as part of compensation,

    despite a categorical finding in the award to the contrary.

    4 | Page CM(M) No. 149/2026

    15.It is further submitted that the Court below has wrongly calculated Jabirana

    @ 15% only on land compensation, whereas settled law mandates that the

    same is payable on the entire compensation including value of assets

    attached to the land.

    16.Learned counsel submits that the adverse observations made by the Court

    below imputing fraud upon the Petitioner are wholly unwarranted, baseless

    and beyond jurisdiction, particularly when the Petitioner had no role in the

    computation or disbursement of the compensation.

    17.It is contended that the direction to pay interest on the alleged excess amount

    is unjustified, inasmuch as any alleged excess payment, if at all, resulted

    from official calculations and not from any act or omission attributable to the

    Petitioner.

    18.Per contra, learned counsel for the respondents submitted that the impugned

    order does not alter or modify the award but merely corrects an inadvertent

    mistake resulting in double payment and prevents unjust enrichment of the

    petitioner at the cost of public exchequer.

    LEGAL ANALYSIS

    19.Heard learned counsel for the parties at length and perused the material on

    record.

    5 | Page CM(M) No. 149/2026

    20.At the outset, this Court is conscious of the limited scope of jurisdiction

    under Article 227 of the Constitution of India. The supervisory jurisdiction is

    neither appellate nor revisional in nature and is to be exercised sparingly,

    only to keep subordinate courts within the bounds of their authority and to

    correct jurisdictional errors or manifest perversity.

    21.The Hon’ble Supreme Court in P.Suresh Vs. D.Kalaivani & Ors. reported

    as 2026 SCC OnLine SC 143 has held that:

    “The scope, ambit, amplitude and nature of the powers of a High
    Court under Article 227 of the Constitution are discussed and
    delineated by this Court in catena of decisions. Article 227 is
    perceived to be a custodian of justice, which is in the nature of
    extraordinary supervisory powers, discretionary in nature. In
    Shalini Shyam Shetty vs. Rajendra Shankar Patil1 , this Court
    cautioned that an improper and frequent exercise of this power
    will be counterproductive and would divest this extraordinary
    power of its strength and vitality. It was observed that this
    discretionary power has to be exercised very sparingly”

    22.The supervisory jurisdiction is meant to correct only jurisdictional errors,

    patent perversity, or grave injustice. It is not intended to interfere with

    findings of fact which have attained finality, nor to re-appreciate the

    evidence nor to sit in appeal over the findings of the Court below,

    particularly when the conclusions drawn are borne out from the record and

    are in consonance with settled principles of law.

    6 | Page CM(M) No. 149/2026

    23.The Hon’ble Supreme Court, in a catena of decisions, has consistently held

    that interference under Article 227 is warranted only in cases where there is

    patent lack of jurisdiction, manifest perversity, or gross miscarriage of

    justice. Mere possibility of a different view, or minor errors in appreciation

    of facts, do not justify invocation of such extraordinary jurisdiction.

    24.In the present case, the record reveals that the learned Principal District

    Judge, Anantnag, has exercised jurisdiction under Section 151 CPC for a

    limited and well-defined purpose, namely, to correct an arithmetical or

    clerical error resulting in disbursement of an amount in excess of what was

    lawfully due under the award. Such exercise in the opinion of this Court falls

    squarely within the inherent powers of the Court to ensure that its process is

    not abused and that its orders are not rendered instruments of injustice.

    25.It is also pertinent to note that the impugned orders do not involve any re-

    adjudication of rights, nor do they alter, modify, or review the award which

    has already attained finality up to the Hon’ble Supreme Court. The exercise

    undertaken by the Court below is confined to giving effect to the award in its

    true spirit by preventing duplication of payment and ensuring lawful

    adjustment.

    26.This Court finds that the conclusions arrived at by the learned Court below

    are borne out from the record, supported by objective material, and based on

    7 | Page CM(M) No. 149/2026
    a rational appreciation of facts. No perversity, arbitrariness, or non-

    application of mind is discernible. On the contrary, the impugned orders

    reflect a careful exercise of jurisdiction aimed at preventing unjust

    enrichment and safeguarding public funds.

    27.Accordingly, this Court holds that the impugned orders do not suffer from

    any jurisdictional infirmity, patent illegality, or perversity so as to warrant

    interference under Article 227 of the Constitution of India, and the same

    merit affirmation.

    28.The principal contention of the Petitioner is that once the award dated

    15.07.2014 attained finality, the Court below had become functus officio and

    could not have entertained an application under Section 151 CPC read with

    section 17-B of Jammu and Kashmir land Acquisition Act

    29.It is well settled that the exercise of inherent powers under Section 151 CPC

    is not barred merely because the main proceedings have culminated,

    provided such exercise is aimed at preventing abuse of process or securing

    the ends of justice. The present case does not involve reopening or re-

    adjudication of the award; rather, it concerns correction of an inadvertent

    error leading to excess payment.

    8 | Page CM(M) No. 149/2026

    30.The Hon’ble Supreme Court in case titled My Palace Mutually Aided

    Cooperative Society vs B. Mahesh reported as (2022) 19 SCC 806 held

    that:

    “In view of the above, the law on this issue stands crystallised
    to the effect that the inherent powers enshrined under Section
    151
    CPC can be exercised only where no remedy has been
    provided for in any other provision of CPC. In the event that a
    party has obtained a decree or order by playing a fraud upon
    the court, or where an order has been passed by a mistake of
    the court, the court may be justified in rectifying such mistake,
    either by recalling the said order, or by passing any other
    appropriate order. However, inherent powers cannot be used in
    conflict of any other existing provision, or in case a remedy has
    been provided for by any other provision of CPC.”

    31.Section 151 Code of Civil Procedure (CPC) preserves the inherent powers of

    the Court to do real and substantial justice. The inherent powers of the Court

    are not exhausted upon the conclusion of proceedings rather they continue to

    subsist to prevent abuse of its process and to ensure that its orders do not

    occasion injustice.

    32.In the present case, the jurisdiction exercised by the learned trial Court,

    while entertaining the application under Section 151 of the Code of Civil

    Procedure read with section 17-B of Jammu and Kashmir land Acquisition

    Act, was not for the purpose of reopening or re-adjudicating the award. The

    exercise was confined to ensuring that the award is executed in its true letter

    and spirit and that no party is permitted to derive an undue benefit at the cost

    9 | Page CM(M) No. 149/2026
    of the public exchequer. The recovery of an amount, which stands

    inadvertently paid in excess by no stretch of imagination can be construed as

    modification or alteration of the award.

    33.It is well settled that the doctrine of restitution, embedded in Indian

    jurisprudence, mandates that no person can be permitted to retain a benefit to

    which he is not legally entitled. The Court, in exercise of its inherent

    powers, is duty-bound to correct its own mistake and to restore the parties to

    the position which they would have occupied .

    34.The Hon’ble Supreme Court in the case titled Odisha Forest Development

    Corporation Ltd. v. M/s Anupam Traders reported as (2022) 19 SCC806

    has reiterated the well-settled principle that no party should suffer on account

    of an act of the Court. It was observed that:

    “The Court will have to bear in mind the maxim actus curiae
    neminem gravabit, namely, no party shall suffer due to the act
    of the Court.”

    35.The learned Court below has merely exercised its inherent jurisdiction under

    Section 151 CPC read with 17B Of Land Acquisition Act, to rectify a

    manifest error in disbursement and to prevent unjust enrichment. Such an

    exercise squarely falls within the ambit of its powers.

    10 | P a g e CM(M) No. 149/2026

    36.Accordingly, this Court is of the considered view that the application under

    Section 151 CPC read with 17B Of Land Acquisition Act was maintainable

    in law, and the learned trial Court cannot be said to have acted without

    jurisdiction in entertaining and allowing the same.

    37.The Petitioner has vehemently contended that an amount of ₹1,02,54,693/-

    was paid towards demolition of structures and did not form part of the

    compensation awarded under the judgment dated 15.07.2014, and therefore,

    could not have been taken into account for the purpose of adjustment.

    38.At the outset, it requires to be noted that it is a well-settled principle of law

    that compensation under the land acquisition is not confined merely to the

    value of the land acquired, but extends to all interests therein, including

    structures and assets attached to such land.

    39.The said payment was inextricably linked with the process of acquisition and

    constituted recompense for the structures standing upon the acquired land,

    being an integral component of the overall acquisition process.

    40.Once while determining compensation in the award dated 15.07.2014, it has

    categorically being directed that the amount already received by the

    Petitioner shall be deducted from the total compensation so awarded, the said

    11 | P a g e CM(M) No. 149/2026
    direction necessarily encompassed all payments made to the Petitioner in

    relation to the acquired land and the assets appurtenant thereto.

    41.Viewed thus, once the learned Reference Court, while determining

    compensation in the award dated 15.07.2014, had categorically directed that

    the amount already received by the Petitioner shall be deducted from the

    total compensation so awarded, the said direction necessarily encompassed

    all payments made to the Petitioner in relation to the acquired land and the

    assets appurtenant thereto.

    42.Accordingly, this Court is of the considered view that the contention raised

    by the Petitioner, that the aforesaid amount i.e., Rs. 2,61,34,972/-, (two

    crore, sixty one lakh, thirty four thousand and nine hundred seventy two

    rupees) as wholly independent and immune from adjustment, is

    misconceived, devoid of merit, and liable to be rejected.

    43.A conjoint and purposive reading of Section 17-B of the Jammu & Kashmir

    Land Acquisition Act makes it abundantly clear that the statute itself

    contemplates the possibility of excess payment at the stage of acquisition and

    provides a definite mechanism for its adjustment and recovery. The

    provision mandates that any amount paid or deposited under Section 17-A

    must be taken into account while determining the final compensation, and if

    such payment exceeds the amount ultimately awarded by the Collector under

    12 | P a g e CM(M) No. 149/2026
    Section 11, the excess amount does not vest in the claimant as a matter of

    right. On the contrary, the statute obligates the recipient to refund the surplus

    amount within the stipulated period, failing which the same becomes

    recoverable as arrears of land revenue. For facility of reference the same is

    reproduced as under:

    “17-B. Determination of compensation and recovery of excess
    amount. The amount paid or diposited under section 17-A,
    shall be taken into account for determining the amount of
    compensation re- quired to be tendered under section 32 and
    where the amount so paid or deposited exceeds the
    compensation awarded by the Collector under section 11, the
    excess amount may unless refunded within three months from
    the date of the Collector’s award be recovered as an arrear of
    land revenue.”

    44.It expressly stipulates that where the amount already paid exceeds the

    compensation awarded by the Collector under Section 11, such excess

    amount is not to be treated as a windfall or vested benefit in favour of the

    claimant. Rather, the statute casts a clear obligation upon the recipient to

    refund the surplus amount within the prescribed period, failing which the

    same is liable to be recovered as arrears of land revenue. The mechanism of

    recovery provided is stringent and summary in nature, underscoring the

    legislative intent that public funds must not be allowed to remain with a

    private party beyond lawful entitlement.

    13 | P a g e CM(M) No. 149/2026

    45.This Court is of the considered view that Section 17-B is a statutory

    embodiment of the doctrine of restitution under section 144 of Code of Civil

    Procedure (CPC). It reinforces the principle that compensation is not a

    matter of bounty but of strict legal entitlement, regulated by the scheme of

    the Act. Any amount paid in excess amount, howsoever occasioned by

    clerical mistake, or otherwise does not confer any indefeasible right upon the

    claimant.

    46.The action of the Court below in directing adjustment/recovery of the excess

    amount is in complete consonance with the statutory mandate. Such direction

    merely ensures that the award is implemented in its true spirit and that the

    disbursement aligns with the compensation actually determined. To hold

    otherwise would tantamount to defeat the express provision of Section 17-B

    and to countenance unjust enrichment at the cost of public revenue, which

    the law does not permit.

    47.The contention advanced on behalf of the Petitioner that Jabirana ought to

    have been computed on the entire compensation, including the value of

    structures and other appurtenant assets, has been carefully considered by the

    Learned Trial Court.

    48.It is well settled that once an award attains finality, it cannot be reopened,

    reinterpreted in collateral proceedings. The proceedings before the learned

    14 | P a g e CM(M) No. 149/2026
    Trial Court under Section 151 Code of Civil Procedure (CPC) were neither

    in the nature of interpretation, modification, nor enhancement of the award.

    The limited scope of the application was confined only to examining, on the

    basis of the award as it stood, whether any excess amount had been paid to

    the Petitioner and whether such excess amount required adjustment or

    recovery in accordance with law.

    49.Viewed thus, the contention of the Petitioner that Jabirana ought to be

    recalculated on the entire compensation is not available at this stage, more so

    when the award has attained finality having been affirmed up to the Hon’ble

    Supreme Court of India, and its terms, including the manner of computation,

    cannot now be reopened or reinterpreted under the guise of fresh calculation.

    50.Accordingly, this Court is of the considered view that the learned Court

    below rightly refrained from entering into any such re-computation, and

    confined itself to the limited exercise of arithmetical adjustment in terms of

    the award. The contention of the Petitioner, therefore, does not merit

    acceptance and is liable to be rejected.

    51.The core question which falls for determination is whether the Petitioner can

    be permitted to retain an amount of ₹2,61,34,972/-, (two crore, sixty one

    lakh, thirty four thousand and nine hundred seventy two rupees) which is

    admitted to have been received twice, as emerged from the record.

    15 | P a g e CM(M) No. 149/2026

    52.This Court is mindful of the settled law that governs the doctrine of

    restitution. The principle is not merely equitable but has been consistently

    recognised as an integral part of Indian civil jurisprudence. The object of

    restitution is to restore the parties to the position which they would have

    occupied but for the erroneous or unjust benefit conferred upon one party.

    53.In South Eastern Coalfields Ltd. v. State of M.P. (2003) 8 SCC 648, the

    Hon’ble Supreme Court has authoritatively held that

    “In law, the term ‘restitution’ is used in three senses; (i) return
    or restoration of some specific thing to its rightful owner or
    status; (ii) compensation for benefits derived from a wrong
    done to another; (iii) compensation or reparation for the loss
    caused to another. (See Black’s Law Dictionary, Seventh
    Edition, p.1315). The Law of Contracts by John D. Calamari &
    Joseph M. Perillo has been quoted by Black to say that
    ‘restitution’ is an ambiguous term, sometimes referring to the
    disgorging of something which has been taken and at times
    referring to compensation for injury done. “Often, the result in
    either meaning of the term would be the same. ….. Unjust
    impoverishment as well as unjust enrichment is a ground for
    restitution.”

    54.Applying the aforesaid principle to the facts of the present case, this Court

    finds that the retention of the excess amount by the Petitioner, which has

    admittedly resulted from duplication of payment under the same

    compensation stream, would clearly amount to unjust enrichment. Such

    enrichment is not only impermissible in law but is also opposed to public

    interest, particularly when public funds are involved.

    16 | P a g e CM(M) No. 149/2026

    55.This Court is of the considered view that the learned Court below has

    correctly applied the principles of restitution and has rightly directed refund

    of the excess amount along with interest.

    56.The next contention raised on behalf of the Petitioner that no interest can be

    imposed since the excess amount arose out of an computational error, does

    not merit acceptance.

    57.This Court is of the considered view that once it is established that a party

    has retained an amount which, in law, was not due to him, the obligation to

    restitute does not remain confined merely to the principal sum. The principle

    of restitution, as, is not a narrow concept; it is a complete restorative

    mechanism aimed at placing the parties in the position they would have

    occupied but for the wrongful enrichment.

    58.The Hon’ble Supreme Court in the case of Sahakari Khand Udyog Mandal

    Ltd. -Vs.- Commissioner of Central Excise & Customs reported in

    (2005) 3 SCC 738 has held as follows:-

    “31. Simply stated, “unjust enrichment” means retention of a
    benefit by a person that is unjust or inequitable. “Unjust
    enrichment occurs when a person retains money or benefits
    which in justice, equity and good conscience, belong to someone
    else. 32. The doctrine of “unjust enrichment” postulates that no
    person can be allowed to enrich inequitably at the expense of
    another. A right of recovery under the doctrine of “unjust
    enrichment” arises where retention of a benefit is considered
    contrary to justice or against equity. 33. The juristic basis of the

    17 | P a g e CM(M) No. 149/2026
    obligation is not founded upon any contract or tort but upon a
    third category of law, namely, quasi-contract or the doctrine of
    restitution.”

    59. This Court is of the considered view that the doctrine of unjust enrichment

    is founded on the principle that no person can be permitted to retain a

    benefit which, in justice, equity, and good conscience, belongs to another;

    and once it is shown from the record that the Petitioner has retained an

    amount not lawfully due to him, such retention becomes impermissible in

    law, thereby mandating restoration of the excess amount along with interest.

    60.In the present case, the Petitioner admittedly had the benefit of the amount

    for a considerable period. Permitting retention of such benefit without

    compensating the value of its use would defeat the very object of restitution

    and would amount to allowing unjust enrichment indirectly.

    61.Accordingly, this Court finds that the direction to pay interest at the rate of

    6% per annum is just, reasonable, and in consonance with settled principles

    of law. The interest component awarded cannot be said to be excessive or

    arbitrary, but rather a balanced measure to ensure complete restitution

    62.In the present case, a perusal of the review order dated 27.04.2026

    demonstrates that the learned trial has correctly appreciated the limited

    scope of review jurisdiction. The Court has recorded a clear and unequivocal

    18 | P a g e CM(M) No. 149/2026
    finding that the excess amount released in favour of the Petitioner was the

    result of an inadvertent duplication in disbursement, which stood duly

    established from the record. The direction for refund was manifestly justified

    and aimed at ensuring faithful implementation of the award, and not in the

    nature of re-adjudication or modification thereof.

    63.The grounds urged in the review petition, , do not disclose any error apparent

    on the face of the record, nor do they bring forth any new material

    warranting reconsideration. On the contrary, the attempt of the Petitioner

    was to re-agitate issues already considered and decided, which is clearly

    impermissible within the confines of review jurisdiction.

    64.This Court is of the considered view that the learned Court below has

    exercised its jurisdiction in accordance with law and has returned findings

    which are well-reasoned and borne out from the material on record. No

    perversity, illegality, or jurisdictional infirmity is discernible in the

    impugned order.

    65.Accordingly this court in agreement with the view taken by the learned trial

    court, and finds no ground to interfere with both orders which are subject

    matter of the instant petition.

    19 | P a g e CM(M) No. 149/2026
    CONCLUSION

    66.Thus in the light of what has been discussed hereinabove coupled with the

    settled legal position, this Court is of the considered view that no case for

    interference under Article 227 of the Constitution of India is made out.

    67. Further this Court is of the view that permitting the Petitioner to retain the

    excess amount would result in clear unjust enrichment at the cost of public

    funds, which is impermissible in law. The doctrine of unjust enrichment

    mandates that no person can be allowed to retain a benefit which is not

    legally due to him. Once it stands established from the record that an amount

    has been received in excess of lawful entitlement, the obligation to

    pay/restore the same arises, forthwith. Retaining the said excess amount

    would not only defeat the statutory scheme governing compensation but

    would also undermine the principles of equity, fairness, and public

    accountability.

    68. Accordingly, this court is of the considered view that orders passed by the

    learned Principal District and Sessions Judge, Anantnag dated 04.02.2026

    and 27.04.2026 are well-reasoned, and legally sustainable. The learned trial

    court has meticulously examined the entire record, and has applied settled

    principles of law. The reasoning adopted is neither arbitrary nor perverse;

    20 | P a g e CM(M) No. 149/2026
    rather, it reflects a careful and balanced judicial approach aimed at ensuring

    that no party is permitted to retain public money beyond lawful entitlement.

    69.This Court further observes that the direction issued by the learned trial court

    to the petitioner to deposit the excess amount of Rs.2,61,34972/- (Rupees

    two Cores sixty one lakh thirty four thousand nine hundred ad seventy two

    only) along with 6% interest shall be complied with within a period of one

    month from the date of this order, as the time period to deposit the same in

    terms of the learned trial court order has since expired. It is further made

    clear that in case of failure on part of the petitioner to comply with the

    aforesaid direction within the stipulated period, the same shall be recovered

    as arrears in terms of the Land Revenue Act.

    70.Accordingly, this Court does not find any illegality /infirmity or perversity

    in the impugned orders dated 04.02.2026 and 27.04.2026 passed by the

    learned Principal District Judge, Anantnag and the same are hereby upheld.

    71.Before parting, this court would like to observe that filing of review petition

    by the petitioner after earning dismissal in the application under Section 151

    of the Code of Civil Procedure (CPC) read with Section 17-B of the Land

    Acquisition Act was a tactics to avoid depositing of the excess public money

    and even after dismissal of the review petition, the petitioner has made

    another attempt to file the instant petition by invoking the supervisory

    21 | P a g e CM(M) No. 149/2026
    jurisdiction of this Court under Article 227 of the Constitution on false and

    flimsy grounds in absence of any perversity, jurisdictional infirmity, patent

    illegality and that too urging similar grounds and facts which have been gone

    in detail by the learned trial court by cogent reasons.

    72.The petition, being devoid of any merit, is accordingly dismissed.

    (WASIM SADIQ NARGAL)
    JUDGE

    SRINAGAR:

    07-05-2026
    Mubashir
    i. Whether the judgment is speaking: Yes
    ii. Whether the judgment is reportable: Yes

    22 | P a g e CM(M) No. 149/2026



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here