Mahanagar Telephone Nigam Ltd vs M/S Rukma Decor And Construction Co on 16 July, 2026

    0
    8
    ADVERTISEMENT

    Delhi High Court

    Mahanagar Telephone Nigam Ltd vs M/S Rukma Decor And Construction Co on 16 July, 2026

                      $~
                      *  IN THE HIGH COURT OF DELHI AT NEW DELHI
                      %                                Judgment reserved on: 22.04.2026
                                                    Judgment pronounced on: 16.07.2026
                                                        Judgment uploaded on:16.07.2026
                      +       FAO (COMM) 190/2024 & CM APPL. 55443/2024
                              MAHANAGAR TELEPHONE NIGAM LTD       .....Appellant
                                         Through: Mr. Chandan Kumar & Mr.
                                                  Vikram Sharma, Advs.
    
                                               versus
                              M/S RUKMA DECOR AND CONSTRUCTION CO
                                                                    .....Respondent
                                           Through: Mr. O.P. Gupta, Adv.
    
                              CORAM:
                              HON'BLE MR. JUSTICE ANIL KSHETARPAL
                              HON'BLE MR. JUSTICE AMIT MAHAJAN
                                               JUDGMENT
    

    ANIL KSHETARPAL, J.:

    INTRODUCTION:

    1. The present appeal under Section 37 of the Arbitration and
    Conciliation Act, 1996 has been preferred by the Appellant –

    Mahanagar Telephone Nigam Limited (MTNL), assailing the
    judgment dated 06.08.2024 passed by the learned District Judge
    (Commercial Court-06), Central District, Tis Hazari Courts, Delhi in
    ARB. A. (Comm.) No. 20/2019, whereby the petition filed by the
    Appellant under Section 34 of the Arbitration and Conciliation Act
    seeking setting aside of the arbitral award dated 27.11.2018 came to
    be dismissed. By the said arbitral award, the learned Sole Arbitrator
    partly allowed the claims raised by the Respondent-M/s Rukma Decor
    &
    Signature Not Verified Construction Co. arising out of Agreement No. EE(P)C-
    Signed By:JAI
    NARAYAN
    Signing Date:16.07.2026
    FAO(COMM) 190/2024 Page 1 of 29
    16:14:38
    I/MTNL/2010-11 pertaining to balance and left-out construction work
    relating to 240 Type-III quarters at GH-17, Paschim Vihar, New
    Delhi.

    SPONSORED

    2. The principal controversy raised in the present Appeal pertains
    to the validity and enforceability of Clause 53 of the agreement, which
    prescribed a period of 90 days for invocation of arbitration from the
    date of intimation regarding readiness of the final bill and stipulated
    extinguishment of claims upon expiry of the said period. The
    appellant contends that the claims of the Respondent stood
    contractually barred and extinguished owing to delayed invocation of
    arbitration, whereas the Respondent asserts that such a stipulation is
    void and unenforceable in view of Section 28 of the Indian Contract
    Act, 1872 as amended with effect from 08.01.1997. The dispute also
    involves examination of the findings rendered by the learned
    Arbitrator on attribution of delay, levy of compensation under Clause
    15 of the contract, and award of various monetary claims in favour of
    the Respondent.

    3. Before adverting to the rival submissions and the issues arising
    for determination, it would be apposite to briefly notice the factual
    background giving rise to the present proceedings.

    FACTUAL MATRIX:

    4. The Petitioner, Mahanagar Telephone Nigam Ltd., through its
    Executive Engineer, invited a tender for the balance and left out work
    in relation to the construction of 240 numbers of Type III Quarters at
    GH-17, Paschim Vihar, New Delhi in the year 2010 for an amount of
    Rs. 19,82,392. It is to be noted that this was not a fresh construction
    Signature Not Verified
    Signed By:JAI
    NARAYAN
    Signing Date:16.07.2026
    FAO(COMM) 190/2024 Page 2 of 29
    16:14:38
    project but was balance work left out from a rescinded earlier contract
    bearing Agreement No. 02/EE(P)C-I/MTNL/05-06.

    5. The Respondent, M/s Rukma Decor and Construction Company
    through its proprietor Shanti Prakash Goenka, participated in the bid
    and was awarded the tender vide letter dated 15.11.2010 for a value of
    Rs. 40,55,046. The stipulated date of start of work was 25.11.2010
    and the time allowed for completion was four months, making the
    stipulated date of completion 24.03.2011.

    6. The work could not be completed within the stipulated period.
    The Petitioner granted provisional extensions of time from time to
    time, with the last provisional extension granted up to 15.05.2012. The
    work was actually completed on 03.05.2012, resulting in a delay of
    406 days from the original stipulated date of completion.

    7. The Petitioner’s case was that this delay was entirely
    attributable to the Respondent on account of its casual approach, slow
    progress, failure to mobilise sufficient men, material, T&P and
    machinery, and failure to submit a bar chart or work program despite
    being directed vide letter dated 13.12.2010.

    8. The Respondent’s case, on the other hand, was that the delay
    was caused entirely due to hindrances and breaches on the part of the
    Petitioner, including non-taking of measurements of work executed by
    the earlier agency, non-decision on removal of malba and building
    rubbish left by the earlier agency, non-decision on the existing
    G.L./C.I. pipe work which was choked and incomplete, delay in
    sanction of deviated quantities of concerned items, delay in decision
    on substitute items of stainless steel cramps, and most significantly,
    Signature Not Verified
    Signed By:JAI
    NARAYAN
    Signing Date:16.07.2026
    FAO(COMM) 190/2024 Page 3 of 29
    16:14:38
    the failure of the electrical agency deployed by the Petitioner to
    complete the alignment of lift opening gates till 31.10.2011, which
    held up the cladding, grinding and fitting work at the lift lobby area.

    9. After completion of the work, the Petitioner called upon the
    Respondent to submit the Extension of Time proforma in July 2012,
    November 2012 and finally in January 2013, informing the
    Respondent that in case the Extension of Time proforma was not
    submitted, the final bill would be sent for payment and the Extension
    of Time case would be settled ex-parte.

    10. The Respondent submitted the Extension of Time format only
    on 05.03.2013. The Respondent signed the final bill on 15.03.2013
    without any protest. The final bill was intimated as ready on
    21.11.2012. Payment as per the final bill was made to the Respondent
    on 30.05.2013, which was accepted by the respondent without any
    protest as to there being any arbitrary deductions, short or part
    payments.

    11. In June 2013, the Petitioner issued a show cause notice under
    Clause 15 of the General Conditions of Contract for delay in
    completion of the work beyond the stipulated time. Since the same
    was not replied to, second show cause notice was issued on
    11.03.2015. Even in reply thereto, the Respondent did not raise any
    issue of arbitrary deduction or short payments. It was only on
    04.04.2015 that the Respondent raised certain claims with the
    Executive Engineer, which were denied by the Petitioner.

    12. The Respondent thereupon invoked the arbitration clause vide
    its letter dated 26.09.2015, requesting the Chief Engineer, MTNL,
    Signature Not Verified
    Signed By:JAI
    NARAYAN
    Signing Date:16.07.2026
    FAO(COMM) 190/2024 Page 4 of 29
    16:14:38
    New Delhi to appoint an arbitrator in terms of Clause 53 of the
    agreement. The Petitioner denied appointment by means of its
    communication dated 29.10.2015, treating the claims as barred by
    Clause 53. On 05.11.2015, the Petitioner imposed a compensation
    amount of Rs. 92,942 towards delay in terms of Clause 15 of the
    GCC, which the Respondent protested vide letter dated 13.11.2015.

    PROCEEDINGS BEFORE ARBITRAL TRIBUNAL:

    13. The Petitioner, MTNL, refused to appoint an arbitrator due to
    which the Respondent preferred a petition under Section 11 of the
    Arbitration and Conciliation Act, 1996 before the Delhi High Court
    for appointment of an arbitrator. The Delhi High Court appointed S.R.
    Pandey, Retired Additional Director General (CPWD) as Sole
    Arbitrator vide its order dated 20.09.2016, to conduct proceedings
    under the rules of the Delhi International Arbitration Centre, and the
    case was registered as DAC Case No.1306/09-16.

    14. The claimant filed 13 claims. There was no counter-claim by
    the Petitioner. However, the Petitioner raised a preliminary objection
    before the arbitrator that all the claims are time barred under Clause
    53 of the agreement, which provided that if the contractor does not
    make any demand for arbitration in respect of any claim in writing
    within 90 days of receiving the intimation from MTNL that the final
    bill is ready for payment, the claim of the contractor will be deemed to
    have been waived and absolutely barred and MTNL shall be
    discharged and released of all liabilities under the contract in respect
    of these claims.

    Signature Not Verified
    Signed By:JAI
    NARAYAN
    Signing Date:16.07.2026
    FAO(COMM) 190/2024 Page 5 of 29
    16:14:38

    15. The Petitioner contended that the claimant did not invoke
    arbitration within 90 days of receiving intimation regarding the final
    bill on 21.11.2012, not even within 90 days of payment of the final
    bill on 30.05.2013, and that the claimant invoked arbitration only on
    26.09.2015 after an unexplained delay of more than two years .

    16. The claimant rebutted this contention and stated that the
    stipulation of 90 days in Clause 53 is void in terms of Section 28 of
    the Indian Contract Act 1872 as amended on 08.01.1997, and that
    even reckoning limitation from 30.05.2013, the arbitration was
    invoked on 26.09.2015 which was within the three-year limitation
    period.

    17. The arbitrator held the 90-day stipulation in Clause 53 as void
    under the amended Section 28, held the arbitration to be within the
    three-year limitation period under Article 137 of the Limitation Act
    reckoned from 21.11.2012, and rejected all preliminary objections,
    admitting all claims for adjudication on merits.

    18. On the question of delay, the arbitrator found from the
    Hindrance Register maintained by MTNL itself that from the very
    beginning the claimant suffered numerous hindrances solely
    attributable to the Respondent which continued up to 27.09.2011,
    nearly seven months beyond the stipulated date of completion. The
    most significant hindrance recorded was that the work of granite tile
    veneering and stone work in lift lobby and lift jamb remained held up
    from 01.12.2010 to 07.09.2011, for more than nine months due to
    non-completion of alignment and level of lift doors by the electrical
    wing, as against a stipulated completion period of just four months.

    Signature Not Verified
    Signed By:JAI
    NARAYAN
    Signing Date:16.07.2026
    FAO(COMM) 190/2024 Page 6 of 29
    16:14:38

    19. The arbitrator held that the Respondent fell far short of
    performing its reciprocal promise as obligated under Section 46 of the
    Contract Act, and that the delay in performance of the fundamental
    reciprocal promise by the Respondent was the governing delay in
    terms of Sections 51 and 52 of the Contract Act. The Respondent was
    accordingly held in breach and responsible for the entire delay in
    completion of the work. As a direct consequence, the levy of
    compensation of Rs. 92,942/- under Clause 15 was held wrongful and
    illegal both on merits and on the ground of limitation, since the cause
    of action for levy of compensation arose on 03.05.2012 and the levy
    was communicated only on 05.11.2015, beyond three years.

    20. The arbitrator proceeded to adjudicate the individual claims. On
    Claim No. 1 for balance payment, a sum of Rs. 3,88,484/- was
    awarded based on the Local Commissioner’s verified measurements.
    On Claim No. 2 for refund of the withheld amount of Rs. 4,05,505/-,
    the full amount was awarded since the levy of compensation was held
    wrongful and the set-off of Rs. 3,12,563/- under Clause 52.2 against
    another contract was held wrongful as that claim had not been
    adjudicated.

    21. On Claims No. 4 and 6 for insurance charges, Rs. 41,537 was
    awarded since no show cause notice was issued before making the
    recovery and the basis of quantification was not on record. Claims No.
    5 and 7 on service tax were rejected as the deduction under the
    Reverse Charge Mechanism was contractually justified. Claim No. 3
    resulted in a declaratory award.

    Signature Not Verified
    Signed By:JAI
    NARAYAN
    Signing Date:16.07.2026
    FAO(COMM) 190/2024 Page 7 of 29
    16:14:38

    22. Claim No. 8 on minus extra items was rejected since the
    contractor had accepted the deductions without protest. On Claim No.
    9 for overheads during the extended period, Rs. 3,86,767/- was
    awarded computed using CPWD guidelines on 3.75% overhead factor
    applied to an effective prolongation of 13 months with 10% deduction
    for mitigation.

    23. On Claim No. 10 for price escalation, Rs. 4,25,445/- was
    awarded computed using the CPWD Clause 10 CC formula. On Claim
    No. 11 for delayed release of security deposit, Rs. 12,831/- was
    awarded. Pre-award interest at 10% per annum simple interest
    amounting to Rs. 7,22,656/- was awarded under Claim No. 12 under
    Section 31(7)(a) of the Act. Rs. 90,000/- was awarded as arbitration
    costs under Claim No. 13 and Rs. 50,000/- was awarded under Section
    38(2)
    towards MTNL’s share of the Local Commissioner’s fee paid by
    the claimant.

    24. The total award was Rs. 25,23,225/- with future interest at 12%
    per annum from 28.11.2018 till the date of payment, with no future
    interest payable if the award amount was paid within three months of
    the date of award.

    PROCEEDINGS BEFORE THE DISTRICT COURT:

    25. The Petitioner filed the petition under Section 34 of the
    Arbitration and Conciliation Act, 1996 before the District Judge,
    Commercial Court-06, Central District, Tis Hazari, Delhi on
    27.02.2019, challenging the award dated 27.11.2018. The Petitioner
    initially challenged all claims so allowed by the arbitrator but, during
    the arguments, restricted the scope of its challenge to the grounds and
    Signature Not Verified
    Signed By:JAI
    NARAYAN
    Signing Date:16.07.2026
    FAO(COMM) 190/2024 Page 8 of 29
    16:14:38
    contentions recorded in the written submissions dated 31.10.2023.
    Final arguments were heard on 03.08.2024 and the order was
    pronounced on 06.08.2024.

    26. The petitioner further contended that Section 43(3) of the
    Arbitration and Conciliation Act itself carves out an exception to the
    general law of limitation and validates contractual time limit clauses
    for initiation of arbitration, and hence the arbitrator’s interpretation
    nullifying Clause 53 runs foul of Section 43(3).

    27. The Petitioner relied upon the Supreme Court judgments in
    Wildlife Institute of India v. Vijay Kumar Garg1 and P. Manohar
    Reddy v. Maharashtra Krishna Valley Dev
    . Corp2. in support of its
    contention that clauses providing limitation so as to enable a party to
    lodge a claim are not invalid. The Respondent contended that the view
    taken by the arbitrator is a plausible legal view which cannot be
    interfered with under Section 34, and that Clause 53 is void under the
    amended Section 28 of the Contract Act.

    28. The District Court held that after the 1997 amendment to
    Section 28 of the Indian Contract Act, the distinction previously
    carved out by the Supreme Court between clauses merely limiting the
    period to sue and clauses providing for forfeiture or waiver of rights
    no longer survives. The court held that the 1997 amendment
    introduced Clause (b) to Section 28 which additionally renders void
    any agreement that extinguishes the rights of any party or discharges
    any party from liability on the expiry of a specified period.

    
    
    
                    1
                        (1997) 10 SCC 528
    Signature Not Verified
                    2
    Signed By:JAI         (2009) 2 SCC 494
    NARAYAN
    Signing Date:16.07.2026
                        FAO(COMM) 190/2024                                      Page 9 of 29
    16:14:38
    

    29. The court relied upon the consistent line of Delhi High Court
    judgments in Punj Lloyd v. NHAI3, Chander Kant v. DDA4, Union of
    India v. Pt. Munshi Ram & Associates Pvt. Ltd.5
    , Silicon Graphics
    Systems (India) Pvt. Ltd. v. Sterling and Wilson Electricals Pvt. Ltd6
    ,
    and B.L. Kashyap AP & Sons Ltd. v. Airport Authority of India7, all
    of which had held identical 90-day clauses void after the 1997
    amendment, and noted that the Supreme Court judgments in Wildlife
    Institute (supra) and P. Manohar Reddy (supra) were distinguished
    by the Delhi High Court on the ground that those judgments were
    rendered in the context of the unamended Section 28 and the cause of
    action in those cases had arisen before the amendment.

    30. On the Section 43(3) argument, the court held that this had
    already been addressed by the Delhi High Court in Punj Lloyd’s case
    (supra) and the amended Section 28 of the Contract Act prevails
    notwithstanding Section 43(3). The court accordingly held that the
    arbitrator committed no error of jurisdiction in holding Clause 53 void
    and no patent illegality was made out. The petition under Section 34
    was dismissed and parties were directed to bear their own costs.

    APPELANT’S CONTENTIONS:

    31. The principal contentions advanced by the Appellant are
    summarised as follows:

    i. The Arbitral Tribunal committed a jurisdictional error in excess
    of jurisdiction by entertaining and deciding upon claims of the

    3
    MANU/DE/1321/2009
    4
    2025:DHC:7654-DB
    5
    (2006) 4 SCC 538
    6
    2015 SCC OnLine Del 9741
    Signature Not Verified
    7
    Signed By:JAI 2016 SCC OnLine Del 5258
    NARAYAN
    Signing Date:16.07.2026
    FAO(COMM) 190/2024 Page 10 of 29
    16:14:38
    Respondent-Contractor which had stood barred and were deemed to
    have been waived, consequent to the Contractor having failed to
    invoke arbitration within 90 days of receiving intimation from MTNL
    that the final bill was ready for payment, in terms of Clause 53 of the
    GCC. Since the claims were waived and extinguished by operation of
    the contractual clause, the Arbitrator had no jurisdiction to entertain
    the same.

    ii. Clause 53 of the GCC, being a material condition of the
    contract, was binding and decisive as to limitation and remedy. The
    Arbitrator, being a creature of the Agreement and deriving authority
    solely therefrom, could neither traverse beyond its terms nor re-write
    the Agreement. By ignoring Clause 53, the Arbitrator exceeded his
    jurisdiction and committed a patent illegality.

    iii. The cut-off date of 90 days constituted a material condition
    which went to the very right to arbitrate, and the Respondent’s failure
    to invoke arbitration within the said period had the direct consequence
    of waiving the claims, as unambiguously stated in the clause itself.
    Clause 53 should therefore be construed not merely as a limitation
    clause, but as an antecedent condition precedent to invoking
    arbitration.

    iv. The Arbitrator proceeded erroneously to calculate the limitation
    period of 90 days from the date of actual payment (30.05.2013) rather
    than from the date of intimation that the final bill was ready
    (21.11.2012). This constituted a patent illegality and an error of
    jurisdiction.

    Signature Not Verified
    Signed By:JAI
    NARAYAN
    Signing Date:16.07.2026
    FAO(COMM) 190/2024 Page 11 of 29
    16:14:38

    v. Exception 1 to Section 28 of the Indian Contract Act, 1872 (‘the
    Contract Act‘), as it stood before the 1997 amendment, expressly
    saved clauses restricting parties to pursuing remedies within a
    contracted time. Even after the 1997 amendment, Exception 1
    continues to survive, and therefore clauses providing for limitation for
    the purposes of lodging a claim remain valid. The Appellant relied
    upon the Supreme Court’s judgments in M/s P. Manohar Reddy
    (supra) and Wildlife Institute of India, Dehradun (supra).

    vi. Section 43(3) of the Act itself carves out a specific exception
    which expressly recognises and validates contractual time limit
    provisions for initiating arbitration proceedings. It empowers courts to
    extend time only in cases of undue hardship, thereby presupposing the
    validity of such clauses. On this basis, it was contended that the
    Arbitrator’s interpretation nullifying Clause 53 runs foul of the express
    mandate of Section 43(3) and cannot be sustained.

    vii. The Appellant further relied upon the judgment of the Supreme
    Court in the matter of Interplay Between Arbitration Agreements
    under A&C Act, 1996 & Stamp Act, 1899, In re, [(2024) 6 SCC 1],
    wherein the Seven-Judge Bench affirmed that the Arbitration Act,
    being a special legislation, enjoys primacy over the Contract Act
    which is a general law, in accordance with the principle of
    generaliaspecialibus non derogant. On this basis, the Appellant urged
    that Section 43(3) of the Act, as a provision of the special law, should
    prevail over Section 28 of the Contract Act.

    viii. The levy of compensation amounting to Rs. 92,942/- under
    Clause 15 of the GCC was a matter exclusively within the competence
    of the
    Signature Not Verified competent authority under the contract, namely the Chief
    Signed By:JAI
    NARAYAN
    Signing Date:16.07.2026
    FAO(COMM) 190/2024 Page 12 of 29
    16:14:38
    Engineer (CEBW), MTNL, whose decision in writing was final and
    binding in terms of the contract. The Arbitrator, by proceeding to
    examine and set aside this levy, exceeded his jurisdiction and acted in
    excess of the terms of the reference.

    RESPONDENT’S CONTENTIONS:

    32. The Respondent has opposed the appeal and sought dismissal
    thereof on the following grounds:

    i. The view taken by the learned Arbitrator on the validity of
    Clause 53 is a plausible legal view based on a well-reasoned analysis
    of the applicable legal provisions. Under the limited scope of Section
    34
    of the Act, the Court cannot sit in appeal over the Arbitrator’s
    findings on merits or on questions of legal interpretation. So long as
    the interpretation adopted is a possible view, the Award cannot be
    interfered with.

    ii. The Award contains adequate reasoning for all decisions taken
    by the learned Arbitrator, including on the threshold question of
    limitation. The Arbitrator has independently and correctly applied
    Section 28 of the Indian Contract Act as amended by the Amendment
    Act 1 of 1997, and has reached a well-founded conclusion that the 90-
    day stipulation in Clause 53 is void.

    iii. The learned Arbitrator was correct in holding that the claims are
    within limitation, being within three years from the date of cause of
    action, i.e., the date of payment of the final bill on 30.05.2013, having
    regard to the established position that the period of limitation under
    Article 137 of the Limitation Act, 1963 is three years. The Respondent
    also contended that the so-called final bill dated 30.05.2013 could not
    Signature Not Verified
    Signed By:JAI
    NARAYAN
    Signing Date:16.07.2026
    FAO(COMM) 190/2024 Page 13 of 29
    16:14:38
    be treated as the final bill since certain amounts were withheld and
    deductions were made unilaterally; thus, the cause of action was
    continuing.

    iv. Clause 53 is void under the law as has been clearly discussed by
    the learned Arbitrator. The 1997 amendment to Section 28 of the
    Contract Act is sweeping in its effect. Post-amendment, not only are
    clauses merely curtailing the time to bring a suit void, but also clauses
    which extinguish the rights of any party or discharge any party from
    liability on the expiry of a specified period are void. Clause 53, in
    providing that upon non-invocation within 90 days the claims ‘will be
    deemed to have been waived and absolutely barred and the MTNL
    shall be discharged and released of all liabilities under the contract’, is
    squarely hit by the amended Section 28(b) of the Contract Act.

    v. The Respondent relied upon the judgment of the Supreme Court
    in Bharat Sanchar Nigam Limited v. M/s Nortel Networks India
    Limited (Civil Appeal Nos. 843 and 844 of 2021 decided on
    10.03.2021) to contend that the limitation for initiating arbitration
    must be in accordance with Article 137 of the Schedule to the
    Limitation Act, 1963
    and the request for appointment of an arbitrator
    made within three years cannot be treated as barred.

    vi. The consistent line of judgments of the Delhi High Court-in
    Punj Lloyd Ltd. (supra), Chander Kant & Co. (supra), Union of
    India
    (supra), Silicon Graphics Systems (India) P. Ltd. (supra), and
    B.L. Kashyap AP & Sons Ltd. (supra)-have uniformly held that
    contractual clauses identical to Clause 53 are void after the 1997
    amendment to Section 28 of the Contract Act, and have also
    distinguished the Supreme Court judgments in
    Signature Not Verified Wildlife Institute of
    Signed By:JAI
    NARAYAN
    Signing Date:16.07.2026
    FAO(COMM) 190/2024 Page 14 of 29
    16:14:38
    India (supra) and P. Manohar Reddy (supra) on the ground that those
    were rendered in the context of the unamended Section 28.

    II. ANALYSIS:

    SCOPE AND AMBIT OF APPELLATE REVIEW:

    33. Before entering into the merits of the contest, it is necessary to
    briefly delineate the parameters within which this Court exercises
    jurisdiction under Section 37(1)(b) of the Act. Section 37 confers a
    right of appeal only against orders under Section 34 allowing or
    refusing to set aside an arbitral award. The jurisdiction of the Court
    under Section 34 is itself tightly circumscribed by the grounds
    enumerated in sub-sections (2) and (2A). The legislature’s design
    reflects a conscious policy choice in favour of minimal curial
    interference with arbitral awards, so as to preserve the efficacy of
    arbitration as an alternative dispute resolution mechanism.

    34. The Supreme Court has, through an unbroken line of
    authorities, repeatedly affirmed that courts exercising jurisdiction
    under Section 34 and Section 37 do not sit as courts of appeal on the
    merits of the award and cannot re-appreciate evidence or substitute
    their own view for that of the Arbitrator. The permissible grounds of
    challenge-public policy of India including the sub-ground of patent
    illegality under Section 34(2A), and jurisdictional excess-must be
    examined with this framework firmly in view. The test is whether the
    Arbitrator has acted within jurisdiction and within the four corners of
    the agreement, and not whether the court would have reached a
    different conclusion.

    Signature Not Verified
    Signed By:JAI
    NARAYAN
    Signing Date:16.07.2026
    FAO(COMM) 190/2024 Page 15 of 29
    16:14:38

    35. The challenge pressed before this Court by the Appellant is not
    a re-appreciation of factual findings but raises a pure and important
    question of law regarding the interplay of Clause 53 of the GCC,
    Section 28 of the Indian Contract Act as amended in 1997, and
    Section 43(3) of the Act. This question goes to the root of the
    Arbitrator’s jurisdiction and is therefore amenable to examination.

    NATURE AND EFFECT OF CLAUSE 53 OF GCC:

    36. Clause 53 of the General Conditions of Contract executed
    between the parties stipulates, in relevant part, that if the contractor
    does not make any demand for arbitration in respect of any claim in
    writing within 90 days of receiving the intimation from MTNL that
    the bill is ready for payment, the claim of the contractor will be
    deemed to have been waived and absolutely barred, and MTNL shall
    be discharged and released of all liabilities under the contract in
    respect of those claims.

    37. The central question is whether this clause constitutes a valid
    and enforceable contractual term that was binding upon the learned
    Arbitrator, or whether it is rendered void by the operation of Section
    28
    of the Indian Contract Act, 1872. The proper characterisation of the
    clause is therefore essential.

    38. The clause operates in two distinct ways: first, it circumscribes
    the period within which a demand for arbitration must be made;

    second, and more significantly, it attaches a draconian consequence to
    non-compliance-the contractor’s claims are deemed to have been
    ‘waived and absolutely barred’ and MTNL is ‘discharged and released
    of all liabilities under the contract’. It is this second limb-the
    Signature Not Verified
    Signed By:JAI
    NARAYAN
    Signing Date:16.07.2026
    FAO(COMM) 190/2024 Page 16 of 29
    16:14:38
    extinguishment of the Respondent’s contractual rights and the
    discharge of the Appellant from all liability-that is legally decisive.
    The clause does not merely restrict the time to approach a forum; it
    extinguishes the very right of the contractor to claim. It is squarely a
    clause of the kind contemplated by Section 28(b) of the Contract Act
    as amended.

    1997 AMENDMENT AND ITS EFFECT:

    39. Section 28 of the Indian Contract Act, 1872 was substantially
    amended by Act 1 of 1997 with effect from 08.01.1997. The pre-

    amendment Section 28 rendered void every agreement by which any
    party was restricted absolutely from enforcing his rights under or in
    respect of any contract by the usual legal proceedings in the ordinary
    tribunals. Exception 1 to the unamended Section 28 saved from this
    prohibition clauses which merely limited the time within which a
    party could enforce his rights (as opposed to absolute restrictions on
    enforcement).

    40. The 1997 amendment significantly expanded the scope of
    Section 28 by adding clause (b), which additionally renders void every
    agreement by which any party thereto is restricted from enforcing his
    rights under or in respect of any contract, whether by extinguishing
    the rights of any party thereto or by discharging any party from any
    liability under or in respect of any contract on the expiry of a specified
    period so as to restrict any party from enforcing his rights. The section
    before and after the amendment has been reproduced as under:-

    Section 28 of the Indian Contract Act, 1872

    1. Pre-1997 (Original, Unamended) Text
    Signature Not Verified
    “Every agreement, by which any party thereto is restricted absolutely
    Signed By:JAI
    NARAYAN
    Signing Date:16.07.2026
    FAO(COMM) 190/2024 Page 17 of 29
    16:14:38
    from enforcing his rights under or in respect of any contract, by the
    usual legal proceedings in the ordinary tribunals, or which limits the
    time within which he may thus enforce his rights, is void to that extent.

    Exception 1. This section shall not render illegal a contract, by which
    two or more persons agree that any dispute which may arise between
    them in respect of any subject or class of subjects shall be referred to
    arbitration, and that only the amount awarded in such arbitration
    shall be recoverable in respect of the dispute so referred.”

    2. Post-1997 (As Amended by the Indian Contract (Amendment) Act,
    1996 / Act 1 of 1997, in force from 8 January 1997)

    “Every agreement

    (a) by which any party thereto is restricted absolutely from enforcing
    his rights under or in respect of any contract, by the usual legal
    proceedings in the ordinary tribunals, or which limits the time within
    which he may thus enforce his rights; or

    (b) which extinguishes the rights of any party thereto, or discharges
    any party thereto from any liability, under or in respect of any
    contract on the expiry of a specified period so as to restrict any party
    from enforcing his rights, is void to that extent.

    Exception 1. Saving of contract to refer to arbitration dispute that
    may arise. This section shall not render illegal a contract, by which
    two or more persons agree that any dispute which may arise between
    them in respect of any subject or class of subjects shall be referred to
    arbitration, and that only the amount awarded in such arbitration
    shall be recoverable in respect of the dispute so referred.

    Exception 2. Saving of contract to refer questions that have already
    arisen. Nor shall this section render illegal any contract in writing, by
    which two or more persons agree to refer to arbitration any question
    between them which has already arisen, or affect any provision of any
    law in force for the time being as to references to arbitration.”

    41. The post-amendment position of law, as authoritatively and
    consistently stated by the High Court of Delhi in a series of
    judgments, may be thus summarised: whereas the pre-1997 Section 28
    merely rendered void agreements that were absolute restrictions on the
    right to sue, the post-1997 amendment additionally renders void
    clauses which, upon the expiry of a specified period, extinguish the
    contractual rights of any party or discharge any party from liability.

    Signature Not Verified
    Signed By:JAI
    NARAYAN
    Signing Date:16.07.2026
    FAO(COMM) 190/2024 Page 18 of 29
    16:14:38

    This is the precise function performed by the offending limb of Clause

    53. By deeming the claims ‘waived and absolutely barred’ and by
    discharging MTNL from ‘all liabilities under the contract’, Clause 53
    goes well beyond a mere procedural time-bar; it extinguishes
    substantive contractual rights and is therefore clearly and
    unambiguously struck down by the amended Section 28(b).

    42. The consistent judicial consensus on this question – expressed in
    Hindustan Construction Company v. DDA8, Kalyan Chand Goyal v.
    DDA9
    , Explore Computers Pvt. Ltd. v. Cals Ltd10, Punj Lloyd Ltd.
    (supra), M/s Chander Kant & Co. (supra), Union of India (supra),
    Silicon Graphics Systems (India) P. Ltd. (supra), and B.L. Kashyap
    & Sons Ltd.
    (supra) – is that clauses identical or analogous to Clause
    53 are void by reason of the amended Section 28(b) of the Contract
    Act.

    43. The Appellant has placed reliance upon the judgments of the
    Supreme Court in Wildlife Institute of India, Dehradun (supra) and
    P. Manohar Reddy & Bros. (supra), wherein contractual limitation
    clauses were upheld. This reliance is misplaced. Both judgments have
    been authoritatively distinguished by the Delhi High Court on the
    ground that the cause of action in those cases arose before the 1997
    amendment to Section 28 came into force, and the courts accordingly
    considered the question in the light of the pre-amendment provision.
    As the High Court observed in M/s Chander Kant & Co. (supra), in P.
    Manohar Reddy
    ‘s case, the Supreme Court had no occasion to
    consider the effect of the insertion of Clause (b) in Section 28 by the

    8
    77 (1999) DLT 165
    9
    1998 47 DRJ 772
    Signature Not Verified
    10
    Signed By:JAI 131 (2006) DLT 477
    NARAYAN
    Signing Date:16.07.2026
    FAO(COMM) 190/2024 Page 19 of 29
    16:14:38
    Amending Act of 1997. The distinction is not a matter of mere
    technicality; it is legally substantive. The law in force at the relevant
    time governs, and since all material events in the present case-the final
    bill, the payment, the claims and the invocation of arbitration-occurred
    after 08.01.1997, the amended provision of Section 28 is fully
    applicable.

    ARGUMENT ON CLAUSE 43(3) ARBITRATION ACT:

    44. The Appellant’s more adventurous submission is that Section
    43(3)
    of the Act itself provides an independent source of validity for
    contractual time-bar clauses like Clause 53, and that the Arbitrator’s
    nullification of Clause 53 therefore violates the statutory mandate of
    Section 43(3). This argument, though ingeniously framed, does not
    withstand scrutiny. Section 43(3) provides that where an arbitration
    agreement to submit future disputes to arbitration provides that any
    claim to which the agreement applies shall be barred unless some step
    to commence arbitral proceedings is taken within a time fixed by the
    agreement, and a dispute arises to which the agreement applies, the
    Court, if it is of opinion that in the circumstances of the case undue
    hardship would otherwise be caused, and notwithstanding that the
    time so fixed has expired, may on such terms, if any, as the justice of
    the case may require, extend the time for such period as it thinks
    proper.

    45. The Appellant urges that this provision presupposes the validity
    of contractual time-bar clauses for initiation of arbitration, and that the
    legislature, by enacting Section 43(3), has expressly recognised their
    enforceability. On this basis, it is contended that the Arbitration Act,
    Signature Not Verified
    being a special law, must prevail over the general law of the Contract
    Signed By:JAI
    NARAYAN
    Signing Date:16.07.2026
    FAO(COMM) 190/2024 Page 20 of 29
    16:14:38
    Act by virtue of the doctrine of generaliaspecialibus non derogant, as
    recognised by the Seven-Judge Bench of the Supreme Court in the
    Interplay case11.

    46. This argument proceeds on a fundamental misreading of
    Section 43(3). The provision does not validate or positively enact the
    enforceability of contractual time-bar clauses. It addresses only the
    limited question of whether a court may grant an extension of time in
    cases of undue hardship where the contractual time limit has expired.

    The precondition for the exercise of this power is that there exists a
    valid time-bar clause; Section 43(3) does not, by its own force, render
    otherwise void clauses valid. Whether a particular clause is void under
    Section 28 of the Contract Act-a question antecedent to and
    independent of Section 43(3) – falls to be determined by the Contract
    Act
    itself.

    47. As the learned District Court has correctly noted, relying upon
    the reasoning in Punj Lloyd (supra), Section 43(3) of the Act and the
    amended Section 28 of the Contract Act operate in different fields and
    are not in genuine conflict. Section 43(3) addresses the power of the
    court to extend time in cases of undue hardship. It does not address-
    and cannot override-the statutory mandate of Section 28(b) of the
    Contract Act which renders void certain classes of clauses as a matter
    of substantive contract law.

    48. The Interplay judgment (supra) lends no assistance to the
    Appellant’s case on this point. The Seven-Judge Bench was concerned
    with the relationship between the Arbitration Act and the Stamp Act

    Signature Not Verified
    11
    Signed By:JAI [(2024) 6 SCC 1]
    NARAYAN
    Signing Date:16.07.2026
    FAO(COMM) 190/2024 Page 21 of 29
    16:14:38
    in the specific context of arbitration agreements and not with the
    relationship between the Arbitration Act and the Contract Act in the
    context of limitation clauses within contracts. The principle of
    generaliaspecialibus non derogant operates to resolve conflicts
    between a special law and a general law in the specific domain in
    which the special law operates. The question of the validity of a
    contractual provision that extinguishes a party’s substantive rights is
    governed by the Contract Act as the primary legislation on the law of
    contract. This is a different domain from the procedural or institutional
    law of arbitration. To the extent there is any conflict between Section
    43(3)
    of the Arbitration Act and Section 28(b) of the Contract Act, it
    is resolved not by giving blanket primacy to the Arbitration Act over
    the Contract Act but by recognising that Section 28(b) of the Contract
    Act addresses the anterior question of contractual validity, which must
    be answered first, before Section 43(3) can even be invoked.

                      ARBITRATOR'S           JURISDICTION         AND      VALIDITY         OF
                      CLAUSE 53:
    

    49. The Appellant’s submission that the Arbitrator exceeded his
    jurisdiction by entertaining claims barred by Clause 53 is founded on
    the proposition that Clause 53 was valid and binding. This premise has
    been shown above to be legally unsustainable. Once Clause 53-to the
    extent it purports to extinguish the Respondent’s claims-is void by
    operation of Section 28(b) of the Contract Act, the Arbitrator was not
    only entitled but bound to proceed with the claims on their merits.

    50. The principle that an Arbitrator is a creature of the contract and
    cannot traverse beyond its terms is well-established-see M/s Alopi

    Signature Not Verified
    Signed By:JAI
    NARAYAN
    Signing Date:16.07.2026
    FAO(COMM) 190/2024 Page 22 of 29
    16:14:38
    Parshad v. Union of India12
    ; Associate Engineering Company v.
    Govt. of Andhra Pradesh13
    ; PSA Sical Terminals Pvt. Ltd. v. Board
    of Trustees of V.O. Chidambranar Port Trust Tuticorin and
    Others14
    . However, this principle operates within the domain of valid
    contractual terms. The Arbitrator’s jurisdiction does not require him to
    give effect to a contractual clause which is void ab initio under
    statutory law. A void clause is no clause at all in the eyes of the law.
    To hold otherwise would be to give effect to a provision which the
    legislature has expressly declared to be of no force or effect – a result
    that neither the law of contract nor the law of arbitration can sanction.

    51. In the present case, the Arbitrator’s conclusion that the 90-day
    stipulation in Clause 53 was void under the amended Section 28
    reflects precisely the legal position as it has been consistently and
    repeatedly affirmed by the Delhi High Court over a period of more
    than two decades. The Arbitrator, in reaching this conclusion, not only
    exercised his jurisdiction correctly but also applied a coherent and
    well-grounded line of legal authority. There is no error of jurisdiction,
    no excess of jurisdiction, and no patent illegality in this conclusion.

    LIMITATION: RECKONING OF THE PERIOD

    52. Even assuming, for the sake of argument, that Clause 53 was
    not void-which this Court has found not to be the case-the Appellant’s
    submission that the 90-day period commenced from the date of
    intimation that the final bill was ready (21.11.2012) rather than from
    the date of payment (30.05.2013) deserves examination.

    12

    (1960) 2 SCR 793
    13
    (1991) 4 SCC 93
    Signature Not Verified
    14
    Signed By:JAI (Civil Appeal No. 3699-3700 of 2018)
    NARAYAN
    Signing Date:16.07.2026
    FAO(COMM) 190/2024 Page 23 of 29
    16:14:38

    53. The Arbitrator found, on the facts, that the so-called ‘final bill’
    paid on 30.05.2013 could not be treated as the final bill in the true
    sense since certain amounts were withheld in the running bills and
    remained withheld even at the time of payment of the final bill. The
    Arbitrator also found that the Respondent did not sign an unqualified
    certificate of acceptance of the final bill as full and final settlement.
    On this basis, the Arbitrator concluded that the cause of action had not
    crystallised in the manner assumed by the Appellant.

    54. This is a factual finding supported by evidence. Even on the
    question of limitation independent of the void nature of Clause 53, the
    Respondent’s invocation of arbitration on 26.09.2015 falls within three
    years of both the date of intimation of the final bill (21.11.2012) and
    the date of payment of the final bill (30.05.2013), calculated under
    Article 137 of the Limitation Act, 1963. The claims were therefore
    within limitation in any event.

    CHALLENGE TO INDIVIDUAL CLAIMS AND FINDING ON
    MERITS:

    55. It is necessary to note that during the course of arguments
    before the District Court, the Appellant restricted the scope of its
    challenge to the grounds and contentions set out in its written
    submissions dated 31.10.2023, which primarily addressed the
    threshold question of limitation and jurisdiction. The Appellant did
    not, before the District Court, press challenges to each individual
    claim on its merits with the specificity that would be required to make
    out a case of patent illegality, perversity or jurisdictional excess in
    relation to the individual heads of award.

    Signature Not Verified
    Signed By:JAI
    NARAYAN
    Signing Date:16.07.2026
    FAO(COMM) 190/2024 Page 24 of 29
    16:14:38

    56. The learned Arbitrator made detailed and reasoned findings on
    each claim, supported by the Hindrance Register maintained by
    MTNL itself, the report of the Local Commissioner appointed to
    verify measurements, and the contractual provisions governing each
    claim. The finding that the entire delay was attributable to MTNL on
    account of, most significantly, the failure of its electrical wing to
    complete the alignment of lift opening gates-which held up the
    cladding and finishing work in the lift lobby area for over nine
    months, well beyond even the original stipulated period of four
    months-is a factual finding on evidence. It cannot be disturbed under
    Section 34 or Section 37 of the Act unless it rises to the level of
    perversity amounting to no evidence at all, or unless there is a patent
    illegality apparent on the face of the award.

    57. Similarly, the levy of compensation under Clause 15 of the
    GCC was held wrongful on two independent grounds: on merits,
    because the delay was attributable to MTNL, not the Contractor; and
    on limitation, because the cause of action for levy arose on 03.05.2012
    but the levy was communicated only on 05.11.2015, beyond three
    years. These are well-reasoned conclusions supported by the evidence
    on record. The Appellant’s submission that the levy of compensation
    was a matter exclusively within the competence of the Chief Engineer
    (CEBW) and was not amenable to arbitral review does not hold, for it
    is well-settled that the scope of the arbitration clause extends to all
    disputes arising out of or in relation to the contract, including disputes
    about the levy of liquidated damages and compensation.

    58. On the question of the individual claims including overheads
    during the extended period (Claim No. 9), price escalation (Claim No.
    Signature Not Verified
    Signed By:JAI
    NARAYAN
    Signing Date:16.07.2026
    FAO(COMM) 190/2024 Page 25 of 29
    16:14:38

    10), delayed release of security deposit (Claim No. 11), pre-award
    interest (Claim No. 12) and arbitration costs (Claim No. 13), the
    Arbitrator has applied the applicable legal and contractual provisions
    and CPWD guidelines in a detailed and structured manner. No patent
    illegality or perversity is discernible from the face of the award in
    respect of any of these heads.

                    APPLICATION OF              THE      PRINCIPLE        OF     MINIMAL
                    INTERFERENCE:
    

    59. The scheme of the Arbitration and Conciliation Act, 1996
    embodies the principle of minimal curial interference with arbitral
    awards, which is foundational to the pro-arbitration policy of Indian
    law. This legislative intent has been consistently recognised and
    affirmed by the Supreme Court in a series of judgments including
    Associate Builders v. DDA15 and Ssangyong Engineering and
    Construction Co. Ltd. v. NHAI16
    . Under this scheme, an award can be
    set aside only if it falls within the limited categories of challenge
    specified in Section 34, and even within those categories, the power to
    set aside is not a power to correct errors of law or fact which do not
    rise to the specified threshold.

    60. The challenge in the present case, when examined against this
    standard, falls substantially short of the threshold required to set aside
    an award. The core question of law-whether Clause 53 of the GCC is
    void under Section 28(b) of the Contract Act as amended in 1997-has
    been answered by the Arbitrator in a manner which is consistent with
    a long, unbroken and authoritative line of judicial decisions. The
    conclusion is not merely plausible; it is correct. The Arbitrator has

    15
    (2015) 3 SCC 49
    Signature Not Verified
    16
    Signed By:JAI (2019) 15 SCC 131
    NARAYAN
    Signing Date:16.07.2026
    FAO(COMM) 190/2024 Page 26 of 29
    16:14:38
    exercised jurisdiction properly, has remained within the four corners
    of the legal framework applicable to the dispute, and has rendered an
    award that is grounded in a sound appreciation of the law and of the
    evidence.

    61. The Appellant’s invocation of the Interplay judgment (supra) as
    a new ground of challenge at the appellate stage does not advance its
    case for the reasons set out above. The Interplay judgment, which was
    rendered on 17.12.2023 and is therefore subsequent to the Award
    dated 27.11.2018, was cited before the District Court as forming the
    basis of a new legal argument. The District Court, while taking note of
    the submission, correctly concluded that the amended Section 28 of
    the Contract Act prevails in the present context. This Court affirms
    that conclusion.

    CONCLUSION:

    62. For the foregoing reasons, this Court is of the opinion that:

    i. Clause 53 of the GCC, to the extent it provides for the
    extinguishment of the Respondent-Contractor’s claims upon non-
    invocation of arbitration within 90 days and discharges MTNL from
    all liability thereunder, is void under Section 28(b) of the Indian
    Contract Act, 1872 as amended by Act 1 of 1997 with effect from
    08.01.1997.

    ii. The learned Arbitrator committed no error of jurisdiction in
    holding Clause 53 void and in proceeding to adjudicate the claims of
    the Respondent on their merits. The Arbitrator correctly applied the
    settled post-amendment legal position as affirmed by a consistent line
    Signature Not Verified
    of Delhi High Court judgments.

    Signed By:JAI
    NARAYAN
    Signing Date:16.07.2026
    FAO(COMM) 190/2024 Page 27 of 29

    16:14:38
    iii. The argument based on Section 43(3) of the Arbitration and
    Conciliation Act, 1996 is legally untenable. Section 43(3) does not
    override the statutory mandate of Section 28(b) of the Contract Act
    and does not lend independent validity to a clause that is otherwise
    void under the Contract Act.

    iv. The reliance placed upon the judgments in Wildlife Institute of
    India (supra) and P. Manohar Reddy (supra) is misplaced, as those
    judgments were rendered in the context of the pre-amendment Section
    28
    of the Contract Act and are not applicable to the facts of the present
    case where all material events occurred post-amendment.

    v. The invocation of the principle of lex specialison the basis of
    the Interplay judgment does not assist the Appellant. The Arbitration
    Act
    ‘s primacy over the Stamp Act in respect of arbitration agreements,
    as affirmed in Interplay, has no bearing on the validity of a contractual
    term under the Contract Act.

    vi. No patent illegality, perversity, or jurisdictional excess is made
    out in relation to the individual claims adjudicated by the Arbitrator.
    The factual findings are supported by evidence and are insulated from
    challenge under Section 34 and Section 37 of the Act.

    vii. The learned District Court was correct in dismissing the petition
    under Section 34 of the Act. The impugned order dated 06.08.2024
    calls for no interference.

    63. Accordingly, the present Appeal is dismissed. The award dated
    27.11.2018 is affirmed in full. The order of the learned District Judge
    (Commercial Court-06) dated 06.08.2024 is upheld.

    Signature Not Verified
    Signed By:JAI
    NARAYAN
    Signing Date:16.07.2026
    FAO(COMM) 190/2024 Page 28 of 29
    16:14:38

    64. The pending application stand closed.

    ANIL KSHETARPAL, J.

    AMIT MAHAJAN, J.

    JULY16, 2026
    sp/kb

    Signature Not Verified
    Signed By:JAI
    NARAYAN
    Signing Date:16.07.2026
    FAO(COMM) 190/2024 Page 29 of 29
    16:14:38



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here