B V Ahuja vs Neeraj Mohan Chief Engineer Project on 6 July, 2026

    0
    10
    ADVERTISEMENT

    Jammu & Kashmir High Court

    B V Ahuja vs Neeraj Mohan Chief Engineer Project on 6 July, 2026

     HIGH COURT OF JAMMU & KASHMIR AND                                   Serial No. 30
                  LADAKH
                      AT JAMMU
    CCP(S) No. 163/2024 in
    CFA No. 18/2014 c/w
    CCP(S) No. 167/2024
    B V Ahuja                                          .....Appellant(s)/Petitioner(s)
    
    
                           Through: Mr. Ateet Spolia, Advocate
    
                     vs
    Neeraj Mohan Chief Engineer Project                           ..... Respondent(s)
    Sampark Union of India C/O 56, APO
                  Through: Mr. Vishal Sharma, (Sr. Adv.) DSGI with
                            Mr. Sumant Sudan, Advocate
    CORAM: HON'BLE MR. JUSTICE SANJAY PARIHAR, JUDGE
                            ORDER
    

    06.07.2026

    1. Heard learned counsel for the parties and perused the record.

    SPONSORED

    2. At the relevant time, the petitioner was appointed as the Arbitrator in

    respect of an arbitral dispute between the parties. The arbitral award

    subsequently became the subject matter of CFA No. 18/2014, filed

    under Section 39 of the Jammu and Kashmir Arbitration Act, 2002

    (1945 A.D.) (hereinafter referred to as “the Act”), challenging the

    judgment dated 11.01.2014 passed by the learned Principal District

    Judge, Jammu.

    3. The award rendered by the petitioner was assailed by the Union of

    India. This Court, vide judgment dated 09.05.2022, set aside the arbitral

    award passed in favour of M/s D. Khosla and Company and remitted

    the matter to the petitioner for fresh adjudication of the claims in

    accordance with law.

    2 CCP(S) No. 163/2024 in

    CFA No. 18/2014 c/w
    CCP(S) No. 167/2024

    4. While disposing of CFA No. 18/2014, the Coordinate Bench of this

    Court observed as follows:

    For determination of claims of the contractor i.e.
    claim Nos. (1), (2), (4), (8), (13), (15), (16) & (17), the
    matter is remitted back to the arbitrator. However, if
    for any reason whatsoever, the learned Arbitrator,
    who has passed the award, is not available or is
    otherwise incapable to conduct further proceedings;
    matter shall be referred to Sh. Vinod Sharma, Retired
    Chief Engineer, Resident of H.No. 42, Sector-1-A,
    Trikuta Nagar, Jammu, Mobile No. 9419180988, who
    shall enter the reference and decide the claims of the
    contractor aforesaid within a period of four months.
    The arbitrator is left free to determine his fee having
    regard to the 4th Schedule of the Arbitration and
    Conciliation Act, 1996
    .

    5. The petitioner submits that, after the matter was remitted to him, he

    rendered a fresh arbitral award and placed the same before this Court to

    be taken on record. In addition, thereto, he sought payment of arbitral

    fees from the Union of India in the sum of ₹19,75,000/-.

    6. Mr. Vishal Sharma, learned DSGI, contended that the fresh award

    rendered by the petitioner-arbitrator has itself been assailed by the

    respondent under Sections 30 and 33 of the Jammu and Kashmir

    Arbitration Act, 2002 (1945 A.D.) by way of a separate petition before

    this Court. He submitted that the petitioner has misconstrued the

    directions contained in the judgment dated 09.05.2022 and that the

    present contempt petition is wholly misconceived and not maintainable.

    He further argued that, having already submitted the award before this

    Court on 30.09.2022 and simultaneously sought payment of arbitral
    3 CCP(S) No. 163/2024 in
    CFA No. 18/2014 c/w
    CCP(S) No. 167/2024

    fees, and since the award is presently under challenge in independent

    proceedings, the petitioner cannot invoke the contempt jurisdiction of

    this Court for enforcement of his claim.

    7. Per contra, learned counsel for the petitioner, placing reliance upon the

    judgment dated 09.05.2022, submitted that the Court had expressly left

    it open to the arbitrator to determine his fee and had also directed that

    the same be disbursed. It was contended that the contractor-firm has

    already paid its share of the arbitral fee and that the balance amount of

    ₹19,75,000/-, payable by the Union of India, remains outstanding.

    8. It is fairly conceded during the course of hearing that, pursuant to the

    remand of the matter by this Court for fresh consideration, the

    petitioner-arbitrator reheard the parties and rendered a fresh award,

    which has since been challenged by the respondent in separate

    proceedings. In compliance with the directions of this Court, the

    petitioner, after pronouncing the award on 16.09.2022, submitted the

    arbitral record before this Court on 30.09.2022. While doing so, he also

    informed the Court that a sum of ₹19,75,000/- was payable towards his

    arbitral fee and requested that the same be remitted in terms of the

    judgment dated 09.05.2022.

    9. A careful reading of the judgment dated 09.05.2022 reveals that the

    Court merely observed that, since the proceedings were governed by the

    old Act and the original arbitrator, who had earlier rendered the award,

    might not be available or might be incapable of conducting the

    proceedings upon remand, the matter could, in such an eventuality, be

    referred to Shri Vinod Sharma, Retired Chief Engineer, who was

    directed to enter upon the reference and decide the claims of the
    4 CCP(S) No. 163/2024 in
    CFA No. 18/2014 c/w
    CCP(S) No. 167/2024

    contractor within a period of four months. The Court further left it open

    to the said arbitrator to fix his fee in accordance with the Fourth

    Schedule to the Arbitration and Conciliation Act, 1996. The directions

    were thus purely contingent in nature. As a matter of fact, the petitioner,

    being the original arbitrator, neither expressed any unwillingness nor

    was shown to have become incapable of proceeding with the reference.

    On the contrary, he reheard the matter and rendered the fresh award on

    16.09.2022. Significantly, the order dated 09.05.2022 contains no

    direction or mandate requiring either of the parties to pay the arbitral

    fee.

    10. Section 39 of the Jammu and Kashmir Arbitration Act confers upon the

    arbitrator a lien over the arbitral award for the costs of arbitration,

    including the fee claimed by the arbitrator. Sub-section (3) thereof

    authorises any party to apply to the Court for determination of the fee

    demanded by the arbitrator, unless such fee has already been fixed by a

    written agreement between the parties and the arbitral tribunal. In such

    proceedings, the arbitral tribunal is entitled to appear and be heard.

    Further, sub-section (4) empowers the Court to pass such orders as it

    considers appropriate regarding the costs of arbitration where any

    dispute arises concerning such costs and the arbitral award makes no

    adequate provision in that regard. It is not in dispute that, while

    submitting the arbitral record before this Court on 30.09.2022, the

    petitioner also sought a direction for remittance of his arbitral fee.

    11. It has also been brought to the notice of this Court that the award

    rendered by the petitioner is already under challenge in separate

    proceedings pending before this Court. Consequently, any dispute
    5 CCP(S) No. 163/2024 in
    CFA No. 18/2014 c/w
    CCP(S) No. 167/2024

    relating to the payment of arbitral fees properly falls within the scope of

    those proceedings. Moreover, the order dated 09.05.2022 neither

    confers any enforceable right upon the petitioner nor contains any

    mandatory direction requiring the respondent-Union of India to pay the

    arbitral fee. The order merely provided that, in the event the original

    arbitrator was unavailable or incapable of continuing with the

    proceedings, Shri Vinod Sharma could be appointed as arbitrator and

    would be at liberty to determine his fee in accordance with the Fourth

    Schedule. A plain reading of the order leaves no manner of doubt that

    no writ of mandamus or mandatory direction was issued for payment of

    arbitral fees. Since the petitioner has already raised his claim regarding

    arbitral fees in the proceedings wherein the award dated 16.09.2022 is

    under challenge, the said issue can appropriately be adjudicated therein.

    Resort to the contempt jurisdiction of this Court is, therefore, wholly

    misconceived. The present contempt petition is accordingly devoid of

    merit and is dismissed.

    12. The petitioner shall, however, be at liberty to pursue such remedy as

    may be available to him under Section 39 of the Jammu and Kashmir

    Arbitration Act.

    (Sanjay Parihar)
    Judge

    Jammu
    06.07.2026
    Diksha



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here