M/S. Shinde And Sons, Through It S … vs Godawari Marathwada Irrigation … on 15 April, 2026

    0
    42
    ADVERTISEMENT

    Bombay High Court

    M/S. Shinde And Sons, Through It S … vs Godawari Marathwada Irrigation … on 15 April, 2026

    2026:BHC-AUG:15917-DB
    
                                                           Comm. Arb. Appeal 1 of 2019 ssc.odt
    
                             IN THE HIGH COURT OF JUDICATURE AT BOMBAY
                                        BENCH AT AURANGABAD
    
                             COMMERCIAL ARBITRATION APPEAL NO. 1 OF 2019
    
                       M/s. Shinde & Sons,
                       Through Its Partner
                       Mr. Satish S/o Budhajirao Shinde,
                       Age : 52 Years, Occu : Business,
                       R/o Opp. Bhairavnath Patsanstha,
                       Nagar-Pune Road, Kedgaon Devi,
                       Ahmednagar.                                      ... APPELLANT
    
                                    ...VERSUS...
    
                 1.    Godawari Marathwada
                       Irrigation Development
                       Corporation, Through Its
                       Executive Engineer,
                       Majalgaon Canal Division,
                       Gangakhed, Dist. Parbhani.
    
                 2.    Mr. B. B. Jadhav,
                       Wanshri Elegance
                       Survey No. 80/2, Plot No. 14,
                       Baner Road, Aundh, Pune.                         ... RESPONDENTS
    
    
    
                 _______________________________________________________________
                     Mr. G. K. Naik Thigle, Advocate for the Petitioner
                     Mr. P. R. Katneshwarkar, Senior Advocate i/b. Mr. S. G. Bhalerao,
                      Advocate for Respondent No. 1
                 _______________________________________________________________
    
                                    CORAM              : ARUN R. PEDNEKER AND
                                                         VAISHALI PATIL-JADHAV, JJ.
    

    RESERVED ON : 27.02.2026

    PRONOUNCED ON : 15.04.2026

    SPONSORED

    ksk/ 1/36
    Comm. Arb. Appeal 1 of 2019 ssc.odt

    J U D G M E N T [Per Vaishali Patil-Jadhav, J.] :

    1. Rule. Rule made returnable forthwith and heard finally with the

    consent of the learned counsel for the parties.

    2. By the present Commercial Arbitration Appeal, filed under

    Section 37 of the Arbitration and Conciliation Act, 1996, the appellant-

    contractor has challenged the Judgment and Order dated 11.09.2018

    passed by the learned District Judge-1, Beed, in Miscellaneous Civil

    Application (ARB) No. 242 of 2015, whereby the application filed by

    respondent no. 1 – GMIDC under Section 34 of the Arbitration and

    Conciliation Act,1996 came to be allowed and the arbitral award dated

    27.01.2015 passed by the sole arbitrator was set aside.

    3. The facts of the appeal, in brief, are as follows:

    Pursuant to tender notice No. JPC/LCB/53 of 1990-91, tenders

    were invited by the Government of Maharashtra, Irrigation Department

    for the work of construction of Earth Work, Structures, Lining and

    Selective Lining of Kothala Branch Canal, KM No. 7 to 9, Distributory D-

    12 and D-13 of Kothala Branch Canal on Majalgaon Right Bank Canal.

    The estimated cost of the work was Rs. 1,15,98,000/-. The appellant,

    being the successful tenderer, was allotted the work accordingly. An

    ksk/ 2/36
    Comm. Arb. Appeal 1 of 2019 ssc.odt

    agreement came to be executed between the parties. As per the terms of

    the contract, the stipulated period for completion of work was 30

    Calendar months from the date of issuance of notice to proceed with the

    work.

    4. The work was required to be completed on or before 13.08.1993.

    It is the case of the appellant that due to non-fulfilment of reciprocal

    obligations by the respondent no. 1 and various extensions granted

    from time to time, the scope of the work underwent a sea change both

    in terms of quantity and financial implications. The work came to be

    completed on 21.06.2006 and the final bill was drawn thereafter on

    11.07.2006.

    5. Being aggrieved by the imposition of penalty and termination of

    contract, the appellant instituted RCS No. 258 of 1994 seeking an

    injunction restraining the respondent no. 1 from assigning the

    remaining work to a third agency. The respondent no. 1 also instituted

    proceedings being RCS No. 221 of 1995 seeking a declaration that the

    unilateral appointment of Sole Arbitrator by the appellant as illegal and

    for an injunction restraining the arbitrator from acting as a Sole

    Arbitrator. Both the suits were subsequently compromised. The

    appellant waived the right regarding revision of rates and it was agreed

    that the parties will not resort to arbitration. The termination order was

    revoked and the contract was revived.

    ksk/ 3/36

    Comm. Arb. Appeal 1 of 2019 ssc.odt

    6. The work was completed on 21.06.2006 and the final bill was

    drawn/paid on 11.07.2006. It is the case of appellant that due to

    abnormal increase in the quantity of work and various breaches of the

    contract that occurred during execution of the work, the appellant had

    raised various claims. As the claims raised were not settled and disputes

    arose between the parties, notice under Clause 52 of the General

    Conditions of Contract for settlement of disputes was issued, in the

    meantime, by the appellant on 11.05.2006. On 29.07.2006, the

    respondent no. 1 gave option for the appointment of an Arbitrator

    which was exercised by the appellant on 05.08.2006.

    7. Initially, one Mr. S.D.Chate was appointed as Sole Arbitrator on

    14.08.2006, who later showed his inability to work as an arbitrator and

    withdrew from the proceedings. Thereafter, Mr. E.B.Jogdand was

    appointed as Sole Arbitrator, who also, showed his inability to work and

    withdrew from the proceedings in 2012. Subsequently, by

    communication dated 14.02.2014, the appellant requested the Chief

    Engineer for appointment of an Arbitrator. The respondent no. 1, by

    communication dated 13.03.2014, suggested a list of names of Mr.

    A.R.Kamble, Mr. V.D.Nemade and Mr. B.B.Jadhav for appointment as

    Arbitrator. Vide letter dated 15.03.2014, appellant selected the name of

    Mr. B.B.Jadhav for appointment as a Sole Arbitrator. However, it is the

    case of respondent that Mr. A.R. Kamble was appointed as the sole
    ksk/ 4/36
    Comm. Arb. Appeal 1 of 2019 ssc.odt

    Arbitrator in exercise of powers conferred under clause 52 of the

    contract by the Chief Engineer.

    8. Appellant, by letter dated 15.07.2014 requested the Arbitrator

    Mr. B.B. Jadhav to commence the arbitration proceedings. The learned

    Arbitrator accordingly, communicated the parties about the preliminary

    meeting scheduled on 03.08.2014. However, in the meantime,

    respondent no. 1, vide letter dated 01.08.2014, informed Mr.

    B.B.Jadhav that in view of their objection regarding the appointment of

    Mr. B.B.Jadhav as sole arbitrator, and in view of the order dated

    14.07.2014 passed by the Assistant Chief Administrator, GMIDC,

    Mr.A.R.Kamble is appointed as a sole arbitrator for settlement of

    disputes and claims regarding the work and as such, it is not advisable

    for him to attend the meeting scheduled on 03.08.2014. The respondent

    no. 1 also had approached this Court by way of Arbitration Application

    No. 12 of 2014 seeking cancellation of appointment of Mr.B.B.Jadhav as

    a Sole Arbitrator on the ground that he is not eligible for being

    appointed as he was a retired officer and was not holding charge of the

    post of Superintending Engineer and by relying on Clause 53 of the

    General Conditions of Contract, it is submitted that Mr. B.B. Jadhav was

    incompetent to act as an arbitrator. The said application came to be

    dismissed by this Court by order dated 18.11.2014, with liberty to raise

    ksk/ 5/36
    Comm. Arb. Appeal 1 of 2019 ssc.odt

    objections before the arbitrator in accordance with law within a period

    of 45 days.

    9. Thereafter, against the judgment and order dated 18.11.2014 of

    this Court, the respondent no. 1 approached the Hon’ble Supreme Court

    by filing SLP No. 5274 of 2015.

    10. During the pendency of the proceedings filed before this Court

    and the Hon’ble Supreme Court, the learned Arbitrator proceeded with

    the matter. In all, seven meetings were conducted from 03.08.2014 to

    30.11.2014 including a site inspection on 29.11.2014. However, the

    respondent no. 1 never caused appearance before the learned

    Arbitrator. Ex-parte award was passed by the learned Arbitrator on

    27.01.2015, directing payment of an amount of Rs. 1,02,45,34,130/-

    with interest at the rate of 18% per annum.

    11. Thereafter, the SLP No. 5274/2015 was disposed of by the

    Hon’ble Supreme Court by order dated 09.03.2015, granting liberty to

    the respondent no. 1 to put forth its challenges as permissible in law,

    while assailing the validity of the award.

    12. The respondent no. 1 challenged the said award dated

    27.01.2025 by filing an application under Section 34 of the Arbitration

    and Conciliation Act, 1966. The learned District Court allowed the

    ksk/ 6/36
    Comm. Arb. Appeal 1 of 2019 ssc.odt

    application and set aside the arbitral award dated 27.01.2025. Hence,

    the present appeal is filed under Section 37 of the Arbitration and

    Conciliation Act, 1996.

    13. The learned counsel Mr. Girish Thigle for the appellant would

    submit that the impugned judgment and order passed by the learned

    District Judge suffers from jurisdictional error. He would submit that the

    well-reasoned arbitral award is set aside mainly on the ground that it is

    an ex-parte award, without referring to or considering any of the

    clauses under Section 34 of the Arbitration & Conciliation Act, 1996.

    14. Mr. Thigle would further submit that the learned District Judge

    has, in paragraph 26 of the impugned order, considered the issue

    regarding the appointment and qualification of the learned Arbitrator,

    though no such objection was raised before the arbitral tribunal as

    required under Section 13 of the Arbitration and Conciliation Act, 1996.

    It is contended that, in the absence of any such challenge at the

    appropriate stage, the said objection could not have been entertained

    while exercising jurisdiction under Section 34 of the Act.

    15. He would further submit that the impugned judgment and order

    is passed without jurisdiction. He placed reliance on the decision of the

    Hon’ble Supreme Court in Indus Mobile Development Pvt. Ltd. Vs.

    Datawind Innovations Pvt. Ltd. reported in (2017) 7 SCC 618 to
    ksk/ 7/36
    Comm. Arb. Appeal 1 of 2019 ssc.odt

    contend the same. He would submit that application under Section 34

    could only have been filed in a Court where the arbitral proceedings

    were held. It was submitted that the learned arbitrator conducted the

    proceedings/sittings at Pune and Aurangabad and no sittings were

    conducted at Beed. Therefore, the Commercial Court at Beed had no

    territorial jurisdiction to entertain the application.

    16. By placing reliance on the decision of the Hon’ble Supreme Court

    in Gayatri Balasamy vs. Novosoft, the learned counsel would submit

    that, setting aside an award has serious consequences and every

    attempt should be made to save an award. He would also submit that

    the award could not be set aside unless it was contrary to the

    substantive provision of law, any provision of the Arbitration and

    Conciliation Act, 1996, or the terms of the agreement.

    It was lastly submitted that the impugned order is unsustainable

    and liable to be set aside, and the arbitral award dated 27.01.2015

    deserves to be restored.

    In support of his submissions, learned counsel for the appellant

    relied on Quippo Construction Equipment Limited Vs. Janardan

    Nirman Private Limited; [(2020) 18 Supreme Court Cases 277], Gayatri

    Balasamy Vs. ISG Novasoft Technologies Limited; [(2025) 7 SCC 1],

    UHL Power Company Limited Vs. State of Himachal Pradesh; [(2022) 4

    ksk/ 8/36
    Comm. Arb. Appeal 1 of 2019 ssc.odt

    SCC 116], Eminent Colonizers Private Limited Vs. Rajasthan Housing

    Board and Others; [2026 SCC OnLine SC 148], Jan De Nul Dredging

    India Pvt. Ltd. Vs. Tuticorn Port Trust; [2026 SCC OnLine SC 33], Indus

    Mobile Distribution Private Limited Vs. Datawind Innovations Private

    Limited and Others; [(2017) 7 SCC 678], BBR (India) Private Limited

    Vs. S.P.Singla Constructions Private Limited; [(2023) 1 SCC 693], Atul

    R. Shah Vs. M/S V. Vrijlal Lalloobhai and Co. and another; [1999 (1)

    Mh.L.J. 629], and Reliance Infrastructure Limited Vs. State of Goa;

    [(2024) 1 SCC 479].

    17. Per contra, learned senior counsel Mr. P.R. Katneshwarkar i/b

    Mr.S.G. Bhalerao for respondent no. 1, supported the impugned

    judgment and order and would submit that the same is passed after due

    consideration of the material on record and does not warrant any

    interference in the present appeal. He would submit that, at the outset,

    the very foundation of the appellant’s case is misconceived and contrary

    to the terms of the contract. The appellant had accepted the tender with

    specific terms and conditions in which, time was the essence of the

    contract. However, he failed to complete the work within the stipulated

    period i.e., on or before 13.08.1993, despite repeated extensions

    granted by the respondent no. 1. The delay being solely attributable to

    the appellant, penalty under the relevant clauses of the agreement was

    ksk/ 9/36
    Comm. Arb. Appeal 1 of 2019 ssc.odt

    rightly imposed and the contract was terminated in accordance with

    law.

    18. It is the case of the respondent no. 1 that as the work was not

    completed within the stipulated period, the appellant committed a

    breach of the contract and therefore, a penalty of Rs. 5,800/- per day

    was imposed by the Executive Engineer, by communication dated

    21.12.1993. Thereafter, an order of termination of contract was issued

    on 31.01.1994.

    19. The learned senior counsel would submit that the appellant had

    committed various breaches of the terms and conditions of the contract.

    The civil proceedings between the parties were admittedly

    compromised. The appellant had given specific undertaking including

    waiver of claims relating to revision of rates, and agreed not to pursue

    disputes further. In view of such binding undertakings, no subsisting

    dispute survived between the parties and the invocation of arbitration is

    untenable. It is further submitted that the arbitration proceedings

    themselves were not maintainable as there was no “live claim” in

    existence.

    20. He would submit that despite specific objections raised by the

    respondent to the appointment of the arbitrator, the same were not

    ksk/ 10/36
    Comm. Arb. Appeal 1 of 2019 ssc.odt

    taken into consideration and the arbitrator proceeded with undue haste.

    The respondent had, in fact, appointed a competent arbitrator in terms

    of the contract, namely Shri A. R. Kamble; however, the appellant

    deliberately proceeded with an ineligible arbitrator Mr. B.B. Jadhav and

    conducted proceedings unilaterally.

    21. The learned senior counsel would further submit that the ex-parte

    award is passed in violation of principles of natural justice. The

    arbitrator proceeded with the matter despite being aware of the

    pending challenge to his appointment before the Hon’ble High Court

    and thereafter before the Hon’ble Supreme Court. The undue haste in

    proceeding with the matter and passing an ex-parte award

    demonstrates bias and procedural impropriety.

    22. It is submitted that the award is perverse and contrary to public

    policy. The claims allowed by the arbitrator are not supported by any

    cogent evidence and are based on assumptions, conjectures and

    surmises. The amounts awarded are excessive, fictitious and beyond the

    scope of the contract, thereby rendering the award liable to be set aside.

    23. Learned senior counsel would submit that the learned District

    Judge has rightly exercised jurisdiction under Section 34 of the Act. The

    findings recorded are within the permissible scope of interference,

    particularly in view of the illegality in the constitution of the arbitral
    ksk/ 11/36
    Comm. Arb. Appeal 1 of 2019 ssc.odt

    tribunal, absence of a live claim, bar of limitation and violation of

    principles of natural justice.

    It is lastly submitted that the learned District Judge has rightly set

    aside the arbitral award. The present appeal, being devoid of merits,

    deserves to be dismissed with costs.

    In support of his submissions, learned counsel for the respondent

    relied on Kotak Mahindra Bank Ltd. Vs. Narendra Kumar Prajapat;

    [2023 SCC OnLine Del 3148], Bharat Broadband Network Limited Vs.

    United Telecoms Limited; [(2019) 5 SCC 755], S.P. Singla Constructions

    Private Limited Vs. State of Himachal Pradesh and Another; [(2019) 2

    SCC 488], Kinnari Mullick and Another Vs. Ghanshyam Das Damani;

    [(2018) 11 SCC 328], Atul R. Shah Vs. M/s. V. Vrijlal Lalloobhai and

    Co. and another; [AIR 1999 Bombay 67] and The Godavari

    Marathwada Irrigation Development Corporation, Aurangabad Vs. M/s.

    R.B. Kurhade and Company and other; [Arbitration Appeal No.

    20/2018 with connected matter].

    24. Heard Mr. Girish K. Naik-Thigale, learned counsel for the

    Appellants and Mr. P. R. Katneshwarkar, learned senior counsel for

    Respondent No.1. Perused the impugned judgment and order and

    relevant documents.

    ksk/ 12/36

    Comm. Arb. Appeal 1 of 2019 ssc.odt

    25. The facts which are not in dispute, as emerging from the

    record are that, pursuant to Tender Notice, the work of construction of

    earthwork, structures, lining and selective lining of Kothala Branch

    Canal, having an estimated cost of Rs. 1,15,98,000/-, came to be

    allotted to the appellant, and an agreement was accordingly executed

    between the parties. The stipulated period for completion of the said

    work was 30 calendar months, i.e., on or before 13.08.1993; however,

    the work ultimately came to be completed on 21.06.2006, after grant of

    extensions from time to time. In the interregnum, disputes arose

    between the parties, leading to institution of civil suits, being RCS No.

    258 of 1994 and RCS No. 221 of 1995, which were subsequently

    compromised, resulting in revival of the contract. Thereafter, upon

    completion of the work, the final bill came to be drawn on 11.07.2006.

    As, disputes with regard to claims persisted, the arbitration clause was

    invoked, followed by further correspondence resulting in initiation of

    arbitral proceedings. Initially, Mr. S.D. Chate was appointed as the Sole

    Arbitrator on 14.08.2006, who withdrew, followed by appointment of

    Mr. E.B. Jogdand, who also withdrew, and subsequently, Mr. B.B. Jadhav

    came to be appointed as the Sole Arbitrator pursuant to communication

    dated 15.03.2014. The arbitral proceedings were thereafter conducted,

    and an ex parte arbitral award of Rs. 1,02,45,34,130/- with interest was

    passed on 27.01.2015.

    ksk/ 13/36

    Comm. Arb. Appeal 1 of 2019 ssc.odt

    26. From the submissions and the facts noted above, following

    questions arise for our consideration.

    (1) Whether the arbitrator Mr. B.B. Jadhav is

    appointed in terms of clause 52 and 53 of the agreement

    between the parties ?

    (2) Whether the application under section 34 of the

    Arbitration and Conciliation Act is filed before the

    appropriate court having jurisdiction to entertain the

    same ?

    (3) Whether the award by the arbitrator is patently

    illegal and is amenable for interference under section 34

    of the Arbitration and Conciliation Act.

    CONSIDERATION

    27. As regards the issue, whether the arbitrator is appointed in terms

    of clause 52 and 53 of the agreement is concerned, The relevant clauses

    52 and 53 of the agreement, which govern the arbitration mechanism

    between the parties read as under :

    “52. SETTLEMENT OF DISPUTES:

    If the contractor considers any work demanded of him to
    be outside the requirements of the contract, or considers any
    drawings record of ruling of the Engineer-in-charge on any
    matter in connection with or arising out of the contract or the
    carrying out of work to be unacceptable, he shall promptly ask
    the Engineer-in-charge in writing for written instructions or

    ksk/ 14/36
    Comm. Arb. Appeal 1 of 2019 ssc.odt

    decision. Thereupon the Engineer-in-charge shall give his written
    instructions or decision within a period of twenty days of such
    request.

    Upon receipt of the written instructions or decision the
    contractor shall promptly proceed without delay to comply with
    such instructions or decision.

    If the Engineer-in-charge fails to give his instructions or
    decision in writing within a period of twenty days after being
    requested, or if the contractor is dissatisfied with the instructions
    or decision of the Engineer-in-charge, the contractor may within
    twenty days after receiving the instructions or decision appeal to
    be Superintending Engineer, who shall afford an opportunity to
    the contractor to be heard and to offer evidence in support of his
    appeal, to the requirement of department. The Superintending
    Engineer shall give a decision within a period of twenty days
    after the contractor has given the said evidence in support of his
    appeal.

    If the contractor is dissatisfied with the decision of the
    Superintending Engineer the contractor may within twenty days
    after receiving the decision, appeal to the Chief Engineer, who
    shall afford an opportunity to the contractor to be heard and to
    offer evidence in support of his appeal. The Chief Engineer shall
    give decision within a period of twenty days after the contractor
    has given evidence in support of his appeal.

    If the contractor is dissatisfied with this decision, the
    contractor within a period of twenty days from receipt of decision
    shall indicate his intention to refer the dispute to Arbitration,
    failing which the said decision shall be final and conclusive.

    53. ARBITRATION :

    All dispute of differences in respect of which the decision is
    not final and conclusive, shall be referred for arbitration to a sole
    arbitrator appointed as follows.

    ksk/ 15/36

    Comm. Arb. Appeal 1 of 2019 ssc.odt

    Within thirty days of receipt of notice from the contractor
    of his intention to refer the dispute to arbitration the Chief
    Engineer shall send to the contractor a list three offers of the rank
    of Superintending Engineer or higher, who have not been
    connected with the work under this contract. The contractor shall
    within fifteen days of receipt of this list selected and
    communicate to the Chief Engineer the name of one officer from
    the list who shall then be appointed as the Sole arbitrator. If
    contractor fails to communicate his selection of name, within the
    stipulated period, the Chief Engineer shall without delay select
    one officer from the list and appoint him as the sole arbitrator. If
    the Chief Engineer fails to send such a list within thirty days as
    stipulated the contractor shall send a similar list to the Chief
    Engineer within fifteen days; the Chief Engineer shall then select
    one officer from the lit of appoint him as a sole arbitrator within
    fifteen days. If the Chief Engineer fails to do so the contractor
    shall communicate to the Chief Engineer the name of one officer
    from the list, who shall then be the sole arbitrator.

    The arbitrator shall be conducted in accordance within the
    provisions of the Indian Arbitration Act, 1940, or any statutory
    modification thereof. The decision of the sole arbitrator shall not
    final and binding on the parties thereto. The arbitrator shall
    determine the amount of costs of arbitration to be awarded to
    either parties.

    Performance under the contract shall continue during the
    arbitration proceedings and payment due to the contractor by the
    Department shall not be withheld, unless they are the subject
    matter of the arbitration proceedings.

    All awards shall be in writing and in case of awards amounting to
    Rs. 1.00 lakhs & above, such awards shall state reasons for the
    amounts awarded.

    Neither party is entitled to bring claim to arbitration if the
    Arbitrator has not been appointed before the expiration of thirty
    days after defect liability period.

    ksk/ 16/36

    Comm. Arb. Appeal 1 of 2019 ssc.odt

    28. Clause 53 of the contract provides that within thirty days of

    receipt of notice from the contractor, of his intention to refer the

    dispute to arbitration the Chief Engineer shall send to the contractor a

    list of three officers of the rank of Superintending Engineer or higher

    who have not been connected with the work under this contract. The

    contractor shall within fifteen days of receipt of this list select and

    communicate to the Chief Engineer the name of one officer from the

    list, who shall then be appointed as the sole arbitrator, within stipulated

    time then the Chief Engineer shall select, the officer from the list and

    appoint him as sole arbitrator.

    29. In the instant case, on receipt of notice from the contractor to

    refer the dispute to the arbitrator, three names were suggested by the

    Chief Engineer from which one person was selected by the appellant.

    Accordingly, in terms of clause 53 of the agreement, the arbitrator was

    appointed. The appointment of arbitrator is in terms of clause 53 of the

    contract. The District Court while deciding the application under section

    34 has rightly observed that the arbitrator was correctly appointed and

    the objection raised that only a serving officer has to be appointed, has

    been rejected. No error can be found with the impugned order of the

    District Court on the issue of appointment of arbitrator is concerned.

    30. Coming to the next question, whether the application under

    section 34 of the Arbitration and Conciliation Act is filed before the
    ksk/ 17/36
    Comm. Arb. Appeal 1 of 2019 ssc.odt

    appropriate court having jurisdiction to entertain the same, we need to

    see section 34 of the Arbitration and Conciliation Act, which is as

    under :-

    “34. Application for setting aside arbitral award.–(1)
    Recourse to a Court against an arbitral award may be
    made only by an application for setting aside such award
    in accordance with sub-section (2) and sub-section (3).

    (2) An arbitral award may be set aside by the Court
    only if–

    (a) the party making the application 1 establishes on
    the basis of the record of the arbitral tribunal that —

    (i) a party was under some incapacity, or

    (ii) the arbitration agreement is not valid under the
    law to which the parties have subjected it or, failing any
    indication thereon, under the law for the time being in
    force; or

    (iii) the party making the application was not given
    proper notice of the appointment of an arbitrator or of
    the arbitral proceedings or was otherwise unable to
    present his case; or

    (iv) the arbitral award deals with a dispute not
    contemplated by or not falling within the terms of the
    submission to arbitration, or it contains decisions on
    matters beyond the scope of the submission to
    arbitration:

    Provided that, if the decisions on matters
    submitted to arbitration can be separated from those not
    so submitted, only that part of the arbitral award which
    contains decisions on matters not submitted to
    arbitration may be set aside; or

    (v) the composition of the arbitral tribunal or the
    arbitral procedure was not in accordance with the

    ksk/ 18/36
    Comm. Arb. Appeal 1 of 2019 ssc.odt

    agreement of the parties, unless such agreement was in
    conflict with a provision of this Part from which the
    parties cannot derogate, or, failing such agreement, was
    not in accordance with this Part; or

    (b) the Court finds that–

    (i) the subject-matter of the dispute is not capable of
    settlement by arbitration under the law for the time
    being in force, or

    (ii) the arbitral award is in conflict with the public
    policy of India.

    Explanation 1.–For the avoidance of any doubt, it
    is clarified that an award is in conflict with the public
    policy of India, only if,–

    (i) the making of the award was induced or affected
    by fraud or corruption or was in violation of section 75
    or section 81; or

    (ii) it is in contravention with the fundamental policy
    of Indian law; or

    (iii) it is in conflict with the most basic notions of
    morality or justice.

    Explanation 2.–For the avoidance of doubt, the test as
    to whether there is a contravention with the
    fundamental policy of Indian law shall not entail a
    review on the merits of the dispute.

    (2A) An arbitral award arising out of arbitrations other
    than international commercial arbitrations, may also be
    set aside by the Court, if the Court finds that the award
    is vitiated by patent illegality
    appearing on the face of the award:

    Provided that an award shall not be set aside
    merely on the ground of an erroneous application of the
    law or by reappreciation of evidence.

    ksk/ 19/36

    Comm. Arb. Appeal 1 of 2019 ssc.odt

    (3) An application for setting aside may not be made
    after three months have elapsed from the date on which
    the party making that application had received the
    arbitral award or, if a request had been made under
    section 33, from the date on which that request had been
    disposed of by the arbitral tribunal:

    Provided that if the Court is satisfied that the
    applicant was prevented by sufficient cause from making
    the application within the said period of three months it
    may entertain the application within a further period of
    thirty days, but not thereafter.

    (4) On receipt of an application under sub-section (1),
    the Court may, where it is appropriate and it is so
    requested by a party, adjourn the proceedings for a
    period of time determined by it in order to give the
    arbitral tribunal an opportunity to resume the arbitral
    proceedings or to take such other action as in the
    opinion of arbitral tribunal will eliminate the grounds for
    setting aside the arbitral award.

    (5) An application under this section shall be filed by a
    party only after issuing a prior notice to the other party
    and such application shall be accompanied by an
    affidavit by the applicant endorsing compliance with the
    said requirement.

    (6) An application under this section shall be disposed
    of expeditiously, and in any event, within a period of one
    year from the date on which the notice referred to in
    sub-section (5) is served upon the other party.”

    31. Section 34 uses the words that recourse to a court against an

    arbitral award may be made only by an application for setting aside

    such award in accordance with sub-section (2) and sub-section (3).

    ksk/ 20/36

    Comm. Arb. Appeal 1 of 2019 ssc.odt

    The word ‘Court’ has been defined under section 2(e), as under :-

    “(e) “Court” means–

                          (i)    in the case of an arbitration other than
                          international commercial arbitration, the
                          principal
    

    Civil Court of original jurisdiction in a district,
    and includes the High Court in exercise of its
    ordinary original civil jurisdiction, having
    jurisdiction to decide the questions forming the
    subject-matter of the arbitration if the same
    had been the subject-matter of a suit, but does
    not include any Civil Court of a grade inferior
    to such principal Civil Court, or any Court of
    Small Causes;

    (ii) in the case of international commercial
    arbitration, the High Court in exercise of its
    ordinary original civil jurisdiction, having
    jurisdiction to decide the questions forming the
    subject-matter of the arbitration if the same
    had been the subject-matter of a suit, and in
    other cases, a High Court having jurisdiction to
    hear appeals from decrees of courts
    subordinate to that High Court;”

    32. Section 20 of the Arbitration and Conciliation Act is relevant and

    provides for place of arbitration, which is reproduced below :-

    “20. Place of arbitration.–(1) The parties are free to
    agree on the place of arbitration.

    (2) Failing any agreement referred to in sub-section
    (1), the place of arbitration shall be determined by the
    arbitral tribunal having regard to the circumstances of
    the case, including the convenience of the parties.

    ksk/ 21/36

    Comm. Arb. Appeal 1 of 2019 ssc.odt

    (3) Notwithstanding sub-section (1) or sub-section (2),
    the arbitral tribunal may, unless otherwise agreed by the
    parties, meet at anyplace it considers appropriate for
    consultation among its members, for hearing witnesses,
    experts or the parties, or for inspection of documents,
    goods or other property.”

    33. The Supreme Court in the case of BGS SGS Soma JV Vs. NHPC

    Limited, reported in (2020) 4 SCC 234 has held that where it is found

    on the facts of a particular case that either no ‘seat’ is designated by

    agreement, or has not been so determined by the arbitral tribunal, or

    the so-called ‘seat’ is only a convenient ‘venue’ then there may be

    several courts where a part of the cause of action arises, that may have

    jurisdiction over the arbitration. The relevant portion is as under :-

    “46. This Court in Indus Mobile Distribution Private Limited
    (supra), after referring to Sections 2(1)(e) and 20 of the
    Arbitration Act, 1996, and various judgments distinguishing
    between the “seat” of an arbitral proceeding and “venue” of
    such proceeding, referred to the Law Commission Report,
    2014 and the recommendations made therein as follows:

    “17. In amendments to be made to the Act, the Law
    Commission recommended the following:

    ‘Amendment of Section 20

    12. In Section 20, delete the word “Place” and add the
    words “Seat and Venue” before the words “of arbitration”.

    (i) In Sub-section (1), after the words “agree on the”

    deletethe word “place” and add words “seat and venue”.

    ksk/ 22/36

    Comm. Arb. Appeal 1 of 2019 ssc.odt

    (ii) In Sub-section (3), after the words “meet at any”

    delete the word “place” and add word “venue”. [NOTE:

    The departure from the existing phrase “place” of
    arbitration is proposed to make the wording of the Act
    consistent with the international usage of the concept of
    a “seat” of arbitration, to denote the legal home of the
    arbitration. The amendment further legislatively
    distinguishes between the “[legal] seat” from a “[mere]
    venue” of arbitration.]

    Amendment of Section 31

    17. In Section 31

    (i) In Sub-section (4), after the words “its date and
    the” delete the word “place” and add the word “seat”.

    18. The amended Act, does not, however, contain the
    aforesaid amendments, presumably because the BALCO
    judgment in no uncertain terms has referred to “place” as
    “juridical seat” for the purpose of Section 2(2) of the Act.

    It further made it clear that Section 20(1) and 20(2)
    where the word “place” is used, refers to “juridical seat”,
    whereas in Section 20(3), the word “place” is equivalent
    to “venue”. This being the settled law, it was found
    unnecessary to expressly incorporate what the
    Constitution Bench of the Supreme Court has already
    done by way of construction of the Act.

    19. A conspectus of all the aforesaid provisions shows
    that the moment the seat is designated, it is akin to an
    exclusive jurisdiction clause. On the facts of the present
    case, it is clear that the seat of arbitration is Mumbai and
    Clause 19 further makes it clear that jurisdiction
    exclusively vests in the Mumbai courts. Under the Law of
    Arbitration, unlike the Code of Civil Procedure which
    applies to suits filed in courts, a reference to “seat” is a
    concept by which a neutral venue can be chosen by the

    ksk/ 23/36
    Comm. Arb. Appeal 1 of 2019 ssc.odt

    parties to an arbitration clause. The neutral venue may
    not in the classical sense have jurisdiction-that is, no part
    of the cause of action may have arisen at the neutral
    venue and neither would any of the provisions of Section
    16
    to 21 of the Code of Civil Procedure be attracted. In
    arbitration law however, as has been held above, the
    moment “seat” is determined, the fact that the seat is at
    Mumbai would vest Mumbai courts with exclusive
    jurisdiction for purposes of regulating arbitral
    proceedings arising out of the agreement between the
    parties.

    20. It is well settled that where more than one court
    has jurisdiction, it is open for parties to exclude all other
    courts. For an exhaustive analysis of the case law, see
    Swastik Gases Private Limited v. Indian Oil Corporation
    Limited This
    was followed in a recent judgment in B.E.
    Simoese Von Staraburg Niedenthal and Anr. v.

    Chhattisgarh Investment Limited.”

    34. In the present case, neither seat nor venue is mentioned in

    agreement (GCC) between the parties and the arbitrator has chosen

    venue at Pune and Aurangabad at his own convenience. The venue

    chosen is not the exclusive seat of arbitration. Thus, in the present case,

    the part of the cause of action arise within the jurisdiction of District

    Court of Beed, which is the principal civil court of original jurisdiction

    to deal with the application under section 34. Considering the law laid

    down in the case of BGS SGS Soma JV Vs. NHPC Limited, cited supra,

    and considering the provisions of the Arbitration Act, the District Court,

    where the part of cause of action arises and where the subject suit could
    ksk/ 24/36
    Comm. Arb. Appeal 1 of 2019 ssc.odt

    have been filed, has jurisdiction to entertain the application under

    section 34.

    35. Considering the law laid down as above and having considered

    the agreement between the parties and since there is no exclusive seat

    or venue as mentioned in the agreement, the principal civil court of

    original jurisdiction at Beed i.e. the District Court has jurisdiction in the

    matter as part of the cause of action has arisen within the jurisdiction of

    Beed. Interestingly this objection was not taken before the District

    Court.

    36. The next question that arises for our consideration is whether the

    impugned award passed by the arbitrator is patently illegal and is

    amenable for interference under section 34 of the Arbitration and

    Conciliation Act. It is required to be noted that scope of interference in

    the arbitral award is extremely limited.

    37. The power of the ‘Court’ to interfere with arbitral award under

    Section 34 and of this Court under Section 37 of the Arbitration Act

    needs to be noted before considering the above submissions on merits

    of arbitral award. The Supreme Court in the case of PSA Sical Terminals

    Private Limited Vs. Board of Trustees of V.O. Chidambaranar Port Trust

    ksk/ 25/36
    Comm
    . Arb. Appeal 1 of 2019 ssc.odt

    Tuticorn and Anr. reported in (2023) 15 SCC 781 has observed that it is

    a settled legal position, that in an application under Section 34, the

    court is not expected to act as an appellate court and reappreciate the

    evidence. The scope of interference would be limited to grounds

    provided under Section 34 of the Arbitration Act. The interference

    would be so warranted when the award is in violation of “public policy

    of India”, which has been held to mean “the fundamental policy of

    Indian law”. A judicial intervention on account of interfering on the

    merits of the award would not be permissible. However, the principles

    of natural justice as contained in Section 18 and 34(2)(a)(iii) of the

    Arbitration Act would continue to be the grounds of challenge of an

    award. The ground for interference on the basis that the award is in

    conflict with justice or morality is now to be understood as a conflict

    with the “most basic notions of morality or justice”. It is only such

    arbitral awards that shock the conscience of the court, that can be set

    aside on the said ground. An award would be set aside on the ground of

    patent illegality appearing on the face of the award and as such, which

    goes to the roots of the matter. However, an illegality with regard to a

    mere erroneous application of law would not be a ground for

    interference. Equally, re-appreciation of evidence would not be

    permissible on the ground of patent illegality appearing on the face of

    the award.

    ksk/ 26/36

    Comm. Arb. Appeal 1 of 2019 ssc.odt

    38. The Hon’ble Supreme Court in PSA Sical Terminals Private

    Limited (supra) has further observed that a decision which is perverse,

    though would not be a ground for challenge under “public policy of

    India”, would certainly amount to a patent illegality appearing on the

    face of the award. However, a finding based on no evidence at all or an

    award which ignores vital evidence in arriving at its decision would be

    perverse and liable to be set aside on the ground of patent illegality.

    39. To appreciate the test of perversity, the Hon’ble Supreme Court in

    PSA Sical Terminals Private Limited (supra) in para 42 has further held

    as under :-

    “42. To understand the test of perversity, it will also be
    appropriate to refer to paragraph 31 and 32 from the judgment
    of this Court in Associate Builders (supra), which read thus:

    31. The third juristic principle is that a decision which is
    perverse or so irrational that no reasonable person would have
    arrived at the same is important and requires some degree of
    explanation. It is settled law that where:

    (i) a finding is based on no evidence, or

    (ii) an Arbitral Tribunal takes into account something
    irrelevant to the decision which it arrives at; or

    (iii) ignores vital evidence in arriving at its decision,
    such decision would necessarily be perverse.

    32. A good working test of perversity is contained in two
    judgments. In Excise and Taxation Officer-cum-Assessing
    Authority v. Gopi Nath & Sons [1992 Supp (2) SCC 312], it was
    held:

    “7. … It is, no doubt, true that if a finding of fact is arrived
    at by ignoring or excluding relevant material or by taking
    into consideration irrelevant material or if the finding so
    outrageously defies logic as to suffer from the vice of
    irrationality incurring the blame of being perverse, then,
    the finding is rendered infirm in law.”

    ksk/ 27/36

    Comm. Arb. Appeal 1 of 2019 ssc.odt

    In Kuldeep Singh v. Commr. of Police (1999) 2 SCC 10, it was
    held:

    “10. A broad distinction has, therefore, to be maintained
    between the decisions which are perverse and those which
    are not. If a decision is arrived at on no evidence or
    evidence which is thoroughly unreliable and no reasonable
    person would act upon it, the order would be perverse. But
    if there is some evidence on record which is acceptable and
    which could be relied upon, howsoever compendious it
    may be, the conclusions would not be treated as perverse
    and the findings would not be interfered with.”

    40. Now, adverting to the facts of the present appeal, letter dated

    21.7.2014 was issued to the parties by the sole arbitrator, Mr. B. B.

    Jadhav, wherein it is stated that he is appointed as a sole arbitrator for

    settlement of claims arising out of the execution of the work by the

    appellant, and he has decided to convene the first preliminary meeting

    in the matter on 03.08.2014 at 11:00 a.m. at Hotel Kohinoor, Pune. It is

    further noted in the letter that the said meeting is scheduled for

    submission of written pleadings such as statement of claims, written

    statement, rejoinder and other documents of both the parties. The said

    letter was addressed to the Executive Engineer and to the appellant

    herein.

    41. On 01.08.2014, a letter was returned by the Executive Engineer

    to Mr. B. B. Jadhav, informing him that Mr. A. R. Kamble,

    Superintending Engineer, Irrigation Circle, Aurangabad, is appointed as

    the sole arbitrator for settlement of disputes and claims relating to the
    ksk/ 28/36
    Comm. Arb. Appeal 1 of 2019 ssc.odt

    work of the claimants, and therefore, it is not advisable to attend the

    meeting scheduled on 03.08.2014. The arbitrator was thus put to notice

    that the respondent-Executive Engineer had appointed Mr. A. R. Kamble

    as the sole arbitrator in terms of the contract.

    42. Thereafter, on 01.09.2014, the Executive Engineer issued another

    letter to the appellant, intimating him to remain present in the chamber

    of the Executive Engineer on 09.09.2014 for a meeting organized in

    respect of the subject matter of the arbitration. In the minutes of the

    meeting held by Mr. A. R. Kamble on 09.09.2014 at Aurangabad it can

    be seen that the Executive Engineer, Deputy Engineer, Junior Engineer

    and Section Engineer were present. The arbitrator waited for half an

    hour and thereafter proceeded with the meeting and directed the

    respondent to submit certain documents. On 01.10.2014, the

    documents were filed before the arbitrator. The Executive Engineer filed

    pleadings before Mr. A. R. Kamble as regards the maintainability of the

    arbitral dispute, raising certain objections. The claimant did not

    participate before the said arbitrator.

    43. It is pertinent to note that, in parallel proceedings, the arbitrator,

    Mr. B. B. Jadhav, on 24.07.2014, issued a letter to the earlier arbitrator,

    Mr. E. B. Jogdand, for handing over the record of the arbitral

    ksk/ 29/36
    Comm. Arb. Appeal 1 of 2019 ssc.odt

    proceedings along with documents submitted before him by both the

    parties.

    44. First Meeting :- On 03.08.2014, the first meeting of the arbitrator,

    Mr. B. B. Jadhav, was held at Hotel Kohinoor, Pune wherein it is

    recorded that the claimants were present, whereas, no representative of

    the GMIDC, Aurangabad, was present. The arbitrator waited for one

    and half hours and thereafter commenced the meeting. Thereafter, on

    11.08.2014, the proceedings before the arbitrator Mr. B. B. Jadhav were

    held and the parties were intimated about the next meeting scheduled

    on 24.08.2014.

    45. Second Meeting :- The second meeting before the arbitrator, Mr.

    B. B. Jadhav, was held on 24.08.2014, wherein it is noted that none

    appeared on behalf of the respondent, while the claimants were

    present. The arbitrator fixed costs, meeting charges and other charges

    and observed that in terms of Section 38(1) and (2) the fees shall be

    payable in equal shares by the parties. The third meeting was scheduled

    on 05.10.2014 at Hotel Kohinoor, Gymkhana, Pune. It is recorded that

    the copies of the proceedings were submitted to both the parties.

    46. Third Meeting :- The third meeting was held on 05.10.2014 by

    Mr. B. B. Jadhav, wherein it was noted that none appeared on behalf of

    either the appellant or the respondent. The sole arbitrator decided to

    ksk/ 30/36
    Comm. Arb. Appeal 1 of 2019 ssc.odt

    hold the next meeting on 19.10.2014 and called upon the parties to

    make payment of fees. The record indicates that the copies of order

    were posted to all the parties.

    47. Fourth Meeting :- The fourth meeting was conducted on 19.10.

    2014 by Mr. B. B. Jadhav. The claimants were present, whereas the

    respondents were not present. It was noted by the arbitrator that

    despite specific notice on 03.08.2014, 24.08.2014, 05.10.2014, the

    respondents had not caused their appearance. The arbitrator, therefore,

    proceeded under Section 25 of the Arbitration and Conciliation Act,

    1996. It is further recorded that the counsel for the claimants invited

    attention to various claims and that the claimant had briefly introduced

    the claim statement.

    48. Fifth Meeting :- The fifth meeting was held by Mr. B. B. Jadhav on

    26.10.2014, at Pune, wherein documents were produced by the

    claimants and submissions were advanced. The matter was thereafter

    posted for further consideration on 04.11.2014.

    49. Sixth Meeting :- The sixth meeting was held by Mr. B. B. Jadhav

    on 23.11.2014, wherein only the claimants were present and the

    respondents were not present. The counsel for the claimants advanced

    submissions claim-wise, which were taken on record.

    ksk/ 31/36

    Comm. Arb. Appeal 1 of 2019 ssc.odt

    50. Seventh Meeting :- The seventh meeting was held on 29.11.2014.

    The claimants were present, whereas the respondents were absent. The

    arbitrator instructed the claimants, and the claimants continued with

    their submissions. Thereafter, the matter was reserved for passing of the

    final award.

    51. On 27.01.2015 at 12:30 PM, Mr. B. B. Jadhav declared the final

    award. It is noted that though the parties were directed to deposit the

    costs of arbitral proceedings and the same was not deposited by the

    respondents, a copy of the award was not supplied to the parties. The

    parties were informed that they would be entitled to a copy of the

    award upon payment of costs by the respondent.

    52. The above procedure followed by the arbitrator reveals two

    fundamental issues. Firstly, there existed a dispute regarding the

    appointment of Mr. B. B. Jadhav. The respondents had filed an

    application under Section 11 before the High Court for appointment of

    an arbitrator. When the matter was taken up for consideration by this

    Court, this Court by order dated 18.11.2024 granted liberty to the

    respondents to raise within 45 days all grievances before the arbitrator

    under Section 13(2) of the Arbitration Act. The respondents thereafter

    challenged the order of the High Court dated 18.11.2014 before the

    Hon’ble Supreme Court. Despite the arbitrator and the parties having

    ksk/ 32/36
    Comm. Arb. Appeal 1 of 2019 ssc.odt

    knowledge that the respondent had applied before the High Court

    under Section 11 for appointment of arbitrator, the arbitrator Mr. B. B.

    Jadhav proceeded with the arbitration ex-parte and in hasty manner.

    When the matter came up before Supreme Court, it was noted by the

    respondent that the arbitrator, Mr. B. B. Jadhav, had already passed an

    ex-parte award. In the absence of the respondent, the arbitrator had

    proceeded hurriedly with the matter.

    53. Unlike civil suits where the claim can be deemed to be admitted

    in absence of written statement, in arbitration proceedings, the

    arbitrator is expected to decide the claim on merits even though it is an

    ex-parte proceeding. Section 25 particularly deals with this aspect,

    which is noted below :-

    25. DEFAULT OF A PARTY :

    Unless otherwise agreed by the parties, where, without
    showing sufficient cause,–

    (a) the claimant fails to communicate his statement of claim in
    accordance with sub-section (1) of section 23, the arbitral
    tribunal shall terminate the proceedings;

    (b) the respondent fails to communicate his statement of defence
    in accordance with sub-section (1) of section 23, the arbitral
    tribunal shall continue the proceedings without treating that
    failure in itself as an admission of the allegations by the claimant
    3[and shall have the discretion to treat the right of the
    respondent to file such statement of defence as having been
    forfeited].

    ksk/ 33/36

    Comm. Arb. Appeal 1 of 2019 ssc.odt

    (c) a party fails to appear at an oral hearing or to produce
    documentary evidence, the arbitral tribunal may continue the
    proceedings and make the arbitral award on the evidence before
    it.”

    54. It was necessary for the arbitrator to follow the procedure under

    Section 25 of the Arbitration Act. Although reference is made to Section

    25 of the Act in the award, the evidence in support of the claims

    appears to be lacking and the claims cannot be said to be established. A

    perusal of the proceedings before the arbitrator indicates that the

    submission of the claimants are made on two dates and the same is

    accepted by the tribunal. No evidence is laid as regards the expansion of

    work and performance of additional work. It is not known how the R.A.

    bills were submitted to the respondents and for what claims and the

    same were rejected by the respondents on which grounds. No affidavit

    in evidence of technical person is before the tribunal. Work shown to

    the arbitrator at alleged site visit is not known whether the said work

    was executed by the appellant. Lengthy award is passed citing long list

    of case laws, but is completely bereft of evidence and the conduct of the

    arbitrator also appears to be biased. The process, to say the least,

    appears to be biased and against the respondents. The arbitrator’s

    award is thus patently illegal and also shocks the conscience of the

    court and the award is in conflict with basic notions of justice.

    ksk/ 34/36

    Comm. Arb. Appeal 1 of 2019 ssc.odt

    55. The procedure as contemplated under Section 25 of the

    Arbitration Act does not appear to have been properly followed. There

    are various issues those arise for consideration before the arbitrator Mr.

    B. B. Jadhav. Independently, an application under Section 11 was filed.

    In such circumstances, the arbitrator, Mr. B. B. Jadhav ought to have

    waited for some time. However, in absence of the respondent, Mr. B. B.

    Jadhav felt it appropriate to proceed with the matter in a hurried

    manner.

    56. The arbitrator ought to have examined the impact of the decree

    of the Civil Court which has a prima facie bearing on the arbitration

    proceedings, at least to the extent of the compromise recorded before

    the Civil Court. Also, the delay in execution of the work also prima facie

    rested on the claimant, for which suit and arbitral proceedings were

    filed and later compromised. The arbitrator appears to have willingly

    brushed aside the orders of civil court and without considering the

    impact of the decree on the arbitration proceedings.

    57. Thus, the District Court, while exercising jurisdiction under

    Section 34 of the Arbitration and Conciliation Act, 1996, has set aside

    the award passed by the arbitrator. We are in agreement with the order

    passed under Section 34 and find no reason to interfere with the same.

    However, it is clarified that the parties are at liberty to agree upon an

    ksk/ 35/36
    Comm. Arb. Appeal 1 of 2019 ssc.odt

    arbitrator for adjudication of the dispute, failing which the applicant is

    at liberty to approach this court for appointment of arbitrator. If such an

    application is filed all contentions are kept open.

    58. Accordingly, the Commercial Arbitration Appeal stands dismissed.

    [VAISHALI PATIL-JADHAV, J.] [ARUN R. PEDNEKER, J.]

    ksk/ 36/36



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here