04.08.2026
1. Since both the writ petitions have been instituted by the same petitioner
and involve substantially identical questions of fact and law, arising out of
the same set of circumstances, they are being taken up together
adjudication.
WP(C) 1217/2023:
2. By way of the instant petition, the petitioner has prayed for the following
reliefs:
I. Issue a writ in the nature of certiorari, quashing the
impugned bid document bearing No.
GEM/2023/B/3415527 dated 06.05.2023.
II. Issue a writ in the nature of mandamus, directing the
respondents to allow the petitioner to continue and
complete the contract time frame of two years as
envisaged by NIT dated 10.09.2020 from the date of
execution of contract pursuant to letter of allotment
bearing No. SIMS 325 31/2019-822-32 dated 28.04.2022.