M/S Manish Taxi Service & Another vs The Airports Authority Of India on 29 July, 2026

    0
    3
    ADVERTISEMENT

    Uttarakhand High Court

    M/S Manish Taxi Service & Another vs The Airports Authority Of India on 29 July, 2026

                                                   UKHC010110302026
    
    
    
                                                             2026:UHC:6546-DB
    
    
         IN THE HIGH COURT OF UTTARAKHAND
                      AT NAINITAL
    
             HON'BLE THE CHIEF JUSTICE SRI MANOJ KUMAR GUPTA
                                     AND
                  HON'BLE SRI JUSTICE SUBHASH UPADHYAY
    
    
                   APPEAL FROM ORDER NO. 229 OF 2026
    
    
    
    
                                 29TH JULY, 2026
    
    
    M/s Manish Taxi Service & another                       ......     Appellants
    
    
    Versus
    
    
    The Airports Authority of India                         ......    Respondent
    
    
    Counsel for the appellants       :       Mr. Jitendra    Chaudhary,   learned
                                             counsel
    
    Counsel for the respondent       :       Mr. Digvijay Rai, Ms. Abhilasha
                                             Tomar and Mr. Y.S. Chaudhary,
                                             learned counsel
    
    
    
    The Court made the following:
    
    
    JUDGMENT:

    (per Sri Manoj Kumar Gupta, C.J.)

    1) The present appeal is directed against the order

    SPONSORED

    of Commercial Court dated 23.05.2026, whereby the

    application filed by the appellants under Section 9 of the

    Arbitration and Conciliation Act, 1996 has been rejected.

    In the said application, the appellants had prayed for an

    order restraining the Airports Authority of India (AAI),

    1
    UKHC010110302026

    2026:UHC:6546-DB
    Dehradun from encashing the bank guarantees furnished

    by the appellants by way of security for execution of the

    contract between the appellants and AAI. During the

    pendency of the proceedings before the Commercial

    Court, the appellants by means of another application

    (paper No. 17C), sought an ad-interim injunction against

    AAI for restoring back the status of bank guarantee as on

    02.05.2025 and, vide yet another application (paper No.

    22C), the appellants prayed for staying the effect of a

    letter dated 15.05.2025, by which AAI intimated the

    appellants that it had adjusted the outstanding dues

    against the Security Deposit available with it as bank

    guarantee and after adjustment, the Security Deposit has

    got reduced. The appellants were accordingly required to

    recoup the same within fifteen days of issuance of the

    notice failing which the license would be terminated.

    2) The facts of the case have been noted by the

    Commercial Court in paragraph Nos. 2, 3 and 4 of its

    order and, the same are as follows :

    2(i). Brief facts of the case are that, earlier the present
    petition was filed by the petitioners before this Court on dated
    02.05.2025 for restraining the respondent from encashing the
    Bank Guarantees as mentioned in the relief clause of the
    petition. On dated 28.05.2025, after hearing both the sides,
    the Application under Section 9 of the Act, was rejected by

    2
    UKHC010110302026

    2026:UHC:6546-DB
    this Court holding that the petition was premature and not
    maintainable without exhausting the remedy of mediation
    provided under the Agreement between the parties. The
    petitioners challenged the aforesaid order of this Court by
    filing A.O. No. 168 of 2025.

    (ii). On dated 09.06.2025, Hon’ble High Court of
    Uttarakhand held that for the reason that the bank guarantees
    have already been invoked, the remedy, provided under
    Section 9 of the Act, cannot be rendered nugatory, allowed
    the Appeal and remitted the mater back to this Court for
    deciding the same on merits.

    (iii). In compliance of the order passed by the Hon’ble
    High Court of Uttarakhand in the aforesaid appeal, the present
    matter has been heard on merit.

    3(i). The contentions of the petitioner are that on
    25.01.2023, the respondent issued an e-tender notice inviting
    request for proposal for Concession to Design, Fit out, finance,
    develop, market, operate, maintain and manage the Food and
    Beverage outlets at Dehradun Airport for a period of seven
    years. A total area 429.61 square meters was earmarked for
    the said purpose by the respondent. The petitioner firm was
    declared L-1, as it quoted highest price at the rate of Rs.51.70
    per passenger.

    (ii). On 24.05.2023, a letter of intent (LOI) was issued
    by the respondent in favour of the petitioner firm. The
    petitioners deposited the Bank Guarantee amount in three
    parts, (a) BG of Rs.1 crore issued by HDFC Bank Dehradun
    dated 03.07.2023 (b) BG of Rs. 6 crores issued by HDFC Bank
    Dehradun dated 09.10.2023 and (c) BG of Rs.46.68 lakhs
    issued by HDFC Bank Dehradun dated 07.11.2023.

    (iii). Thereafter, on 07.11.2023, Concession Agreement
    was executed between the parties. It is stated by the
    petitioner that the respondent was obliged to hand-over the
    entire area measuring 429.61 square meters and only then,

    3
    UKHC010110302026

    2026:UHC:6546-DB
    liability to make payment would accrue, but the respondent
    delivered possession in phases starting from 29.11.2023 till
    September 2024. The respondent issued Show Cause Notices
    on various dates, however, it is contended by the petitioner
    that the demands made by the respondent were not genuine
    and the petitioner disputed the demands and did not make the
    payment to the respondent.

    (iv). During pendency of the present petition, on dated
    09.05.2025 the respondents encashed the Bank Guarantees
    and adjusted a sum of Rs.4,78,93,927/- (Rs.3,89,05,633
    towards the principal amount and Rs.89,88,294/- as penal
    interest) against the outstanding dues and therefore, the
    security deposit (BG) got reduced to Rs.2,67,74,093/-.

    (v). Thereafter, the respondent issued notice to the
    petitioner dated 15.05.2025 intimating the petitioners about
    the adjustment made towards the arrears of license fees from
    the security deposit and required the petitioners to recoup the
    security deposit in terms of the license agreement within
    fifteen days of issue of the notice, i.e. 30.05.2025, failing
    which necessary action to terminate the license would be
    initiated without any further reference to the petitioner.

    (vi). In the above mentioned changed circumstances,
    the petitioner filed an application paper no. 17C seeking ad-
    interim injunction, against the respondent to restore back the
    status of bank guarantee as on 02.05.2025 and vide an
    application paper no. 22C the petitioner has prayed to stay
    the effect of the above mentioned letter dated 15.05.2025.

    4(i). The respondent contended that the gestation
    period was 60 days from Access Date of each location (site)
    and not 60 days from the date of issuance of LOI. The
    respondent raised bills on pro-rata basis from access date.
    The petitioners defaulted in payment of the bills. The present
    petition has become infructuous as the bank guarantees have
    already been invoked and Writ Petition (M/B) Nos. 381 and

    4
    UKHC010110302026

    2026:UHC:6546-DB
    383 of 2025 which were filed by the petitioner for seeking
    stay order against the termination of the contract and issuing
    fresh tenders, rejected by the Hon’ble High Court and the
    petitioner has not moved any amendment application, in the
    present petition for any additional prayer before this Court,
    despite the liberty granted to the petitioner by the Hon’ble
    High Court vide order dated 20.03.2026.

    (ii). The operation of F&B locations at the Airport is
    being seriously impacted. The respondent issued a notice
    inviting tender for short-term license for operating a snack bar
    over a small area measuring 15 square meters on the first
    floor at Dehradun Airport on 1st May, 2025 subject to
    termination of the Master Concessionaire in favour of the
    petitioners. In the changed circumstances, the relief sought
    by the petitioner cannot be granted in the present petition
    under Section 9 of the Act. Ld. Counsel for the respondent
    has placed reliance upon the case law M/s Inter Ads Exhibition
    Pvt. Ltd. Vs Busworld Internation Cooperatieve Vennootschap
    Met Beperkte Anassprakelijkheid, O.M.P(I) (Comm
    .) 273/2019
    and submitted that the said contract has already terminated
    by the respondent. The dispute is capable of arbitration, the
    disputes can only be adjudicated in the arbitration
    proceedings.”

    3) The Commercial Court has held that an

    injunction order for restraining a party from encashing

    bank guarantee can only be passed in a case where any

    fraud is established and, since in the present matter,

    there is no such case, therefore, no such injunction can be

    granted. For arriving at the said conclusion, the

    Commercial Court has placed reliance on the judgment of

    the Supreme Court in case of U.P. State Sugar

    5
    UKHC010110302026

    2026:UHC:6546-DB
    Corporation Vs M/s Sumac International Ltd., 1997 (1)

    SCC 568. The relevant observations wherein are as

    follows :

    “….The law relating to invocation of such bank
    guarantees is by now well settled. When in the course
    of commercial dealings an unconditional bank
    guarantee is given or accepted, the beneficiary is
    entitled to realize such a bank guarantee in terms
    thereof irrespective of any pending disputes. The bank
    giving such a guarantee is bound to honour it as per its
    terms irrespective of any dispute raised by its
    customer. The very purpose of giving such a bank
    guarantee would otherwise be defeated. The courts
    should, therefore, be slow in granting an injunction to
    restrain the realization of such a bank guarantee. The
    courts have carved out only two exceptions. A fraud in
    connection with such a bank guarantee would vitiate
    the very foundation of such a bank guarantee. Hence if
    there is such a fraud of which the beneficiary seeks to
    take advantage, he can be restrained from doing so.
    The second exception relates to cases where allowing
    the encashment of an unconditional bank guarantee
    would result in irretrievable harm or injustice to one of
    the parties concerned. Since in most cases payment of
    money under such a bank guarantee would adversely
    affect the bank and its customer at whose instance the
    guarantee is given, the harm or injustice contemplated
    under this head must be of such an exceptional and
    irretrievable nature as would override the terms of the
    guarantee and the adverse effect of such an injunction
    on commercial dealings in the country. The two
    grounds are not necessarily connected, though both
    may co-exist in some cases. In the case of U.P.
    Cooperative Federation Ltd. v. Singh Consultants and

    6
    UKHC010110302026

    2026:UHC:6546-DB
    Engineers (P) Ltd. (988 [1] SCC 174), which was the
    case of works contract where the performance
    guarantee given under the contract was sought to be
    invoked, this Court, after referring extensively to
    English and Indian cases on the subject, said that the
    guarantee must be honoured in accordance with its
    terms. The bank which gives the guarantee is not
    concerned in the least with the relations between the
    supplier and the customer; nor with the question
    whether the suppler has performed his contractual
    obligation or not, nor with the question whether the
    supplier is in default or not. The bank must pay
    according to the tenor of its guarantee on demand
    without proof or condition. There are only two
    exceptions to this rule. The first exception is a case
    when there is a clear fraud of which the bank has
    notice. The fraud must be of an agregious nature such
    as to vitiate the entire underlying
    transaction. Explaining the kind of fraud that may
    absolve a bank from honouring its guarantee, this
    Court in the above case quoted with approval the
    observations of Sir John Donaldson, M.R. in Bolivinter
    Oil SA v. Chase Manhattan Bank NA (1984 [1] AER 351
    at 352): “The wholly exceptional case where an
    injunction may be granted is where it is proved that the
    bank knows that any demand for payment already
    made or which may thereafter be made will clearly be
    fraudulent. But the evidence must be clear both as to
    the fact of fraud and as to the bank’s knowledge. It
    would certainly not normally be sufficient that this rests
    on the uncorroborated statement of the customer, for
    irreparable damage can be done to a bank’s credit in
    the relatively brief time which must elapse between the
    granting of such an injunction and an application by the
    bank to have it charged”.

    7

    UKHC010110302026

    2026:UHC:6546-DB
    This Court set aside an injunction granted by the High
    Court to restrain the realisation of the bank guarantee.

    The same question came up for consideration
    before this Court in Svenska Handelsbanken v. M/s
    Indian Charge Chrome & Ors. (1994 [1] SCC 502). The
    Court once again reiterated that a confirmed bank
    guarantee/irrevocable letter of credit cannot be
    interfered with unless there is established fraud or
    irretrievable injustice involved in the case. Irretrievable
    injury has to be of the nature noticed in the case of Itek
    Corporation v. The First National Bank of Boston etc.
    (566 Fed Supp. 1210). On the question of fraud this
    Court confirmed the observations made in the case
    of U.P. Cooperative Federation Ltd. (supra) and stated
    that the fraud must be that of the beneficiary, and not
    the fraud of anyone else.

    Clearly, therefore, the existence of any dispute
    between the parties to the contract is not a ground for
    issuing an injunction to restrain the enforcement of
    bank guarantees. There must be a fraud in connection
    with the bank guarantee….”

    4) As regard the second prayer made by the

    appellants through application 22C it has been observed

    that the AAI in pursuance of notice dated 15.05.2025 had

    already terminated the agreement. The appellants were

    granted liberty by this Court by order dated 20.03.2026 in

    Writ Petition (M/B) Nos. 381 and 383 of 2025 to amend

    the reliefs in their applications pending before the

    Commercial Court under Section 9 of the Act. However,

    the appellants have failed to claim any relief in light of the

    8
    UKHC010110302026

    2026:UHC:6546-DB
    subsequent development, namely the termination of the

    license agreement. The Commercial Court has, therefore,

    held that the appellants have failed to establish any prima

    facie case in their favour, nor balance of convenience lies

    with them. It has also been observed that the present

    case is not a case where even if any loss or injury is

    suffered the same cannot be compensated in terms of

    money. Accordingly, the application has been rejected.

    5) Mr. Jitendra Chaudhary, learned counsel for the

    appellants submits that an order restraining a party to

    invoke the bank guarantee can also be passed if a case of

    irretrievable injustice or injury is made out and the court

    below has not considered the said aspect of the matter.

    In support of the said submission he also places reliance

    on the same judgment of the Supreme Court in case of

    M/s Sumac International Ltd. (supra). He further

    submits that the object of granting injunction under

    Section 9 of the Arbitration and Conciliation Act, 1996 is

    to preserve the lis. It is submitted that if injunction is not

    granted, the lis would be destroyed. He accordingly

    submits that the court below has erred in rejecting the

    application under Section 9 of the Act.

    9

    UKHC010110302026

    2026:UHC:6546-DB

    6) On the other hand, learned counsel for AAI, has

    supported the order passed by the Commercial Court and

    has further submitted that the license agreement was

    terminated on 31.05.2025 as the appellants had failed to

    comply with the conditions of the agreement and recoup

    the security deposit. He further submits that since after

    issuance of notice dated 15.05.2025 the agreement itself

    was terminated, therefore, Section 9 application itself was

    rendered infructuous.

    7) The Supreme Court in M/s Sumac International

    Ltd. (supra) has held that an order restraining a party

    from invoking bank guarantee should not be passed in a

    casual manner. Only two exceptions have been carved

    out. The first being in case of fraud and, the other one,

    where any irretrievable injustice would be caused.

    8. In the present case, the main dispute between

    the parties was whether AAI was entitled to realize license

    fees from the ‘access date’ of each location or from 60

    days from the date of issuance of LOI. The further

    dispute was whether the AAI was justified in raising

    demands on pro- rata basis in respect of the area of which

    possession was delivered to the appellants. Various other

    ancillary questions are also involved. The Commercial

    10
    UKHC010110302026

    2026:UHC:6546-DB
    Court has rightly observed that these issues are still to be

    examined by the Arbitral Tribunal.

    9) On query made from learned counsel for the

    appellants, it is admitted that till date the appellants have

    not taken any steps to even get the dispute referred to

    the arbitral tribunal.

    10) The alleged injury, as rightly observed by the

    Commercial Court, is capable of being computed in terms

    of money and, it is not a case where any irretrievable

    injury would be caused. The court below has rightly

    observed that no case is made out in favour of the

    appellants to grant any injunction.

    11) The notice dated 15.05.2025 in respect of which

    application 17C was filed has also exhausted itself as

    thereafter the contract has already been terminated. We

    are also of the considered opinion that the present case is

    not one of such case where any injunction against the

    invocation of bank guarantee, or upon its invocation, for

    its restitution, should be granted to the appellants.

    12) The appellants are still free to approach the

    Arbitral Tribunal to get the dispute between the parties

    resolved.

    11

    UKHC010110302026

    2026:UHC:6546-DB

    13) Accordingly, we find no good ground to interfere

    with the order of the Commercial Court. The appeal lacks

    merit and is, accordingly, dismissed.

    14) Pending application(s), if any, also stand

    disposed of.

    ______________________
    MANOJ KUMAR GUPTA, C.J.

    _________________
    SUBHASH UPADHYAY, J.

             TH
    Dt: 29        JULY, 2026
    Negi
    
                   Digitally signed by HIMANSHU NEGI
    
    
    
    HIMANS
                   DN: c=IN, o=HIGH COURT OF
                   UTTARAKHAND, ou=HIGH COURT OF
                   UTTARAKHAND,
    

    2.5.4.20=bb3b60774012c1ef1dae20d13aaf1
    16e73351fdaf6878326386908a7f90d5757,

    HU NEGI
    postalCode=263001, st=UTTARAKHAND,
    serialNumber=75BD9D0FB7F4A80990FC51A
    722A6BC552D470EB4FD2F88DDF7C18DB2A
    1524A4D, cn=HIMANSHU NEGI
    Date: 2026.07.30 11:53:37 +05’30’

    12



    Source link

    LEAVE A REPLY

    Please enter your comment!
    Please enter your name here